Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 10, 2017 (Original procurement plan). 2. Date of General Procurement Notice: NA 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. Goods Above US$ 4 million All 2. Works Above US$ 15 million All 3. Non-Consultant Services Above US$ 4 million All 2. Prequalification. NA. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: The Project Implementation Manual (PIM) makes reference to all applicable procurement guidelines and manuals including the Commune/Sangkat Fund PIM for small-scale infrastructure activities carried out by the sub-national levels (Commune/Sangkat), has been developed for this project. 4. Any Other Special Procurement Arrangements: 5 packages (goods) would be financed under retroactive financing 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness. 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Community 5.48 60 No Post procured by infrastructur Communes/Sa es ngkats individually for the whole life of the project June 12, 2017 Procureme 0.92 8 No Post will be nt of procured vehicles, centrally at the office beginning of project equipment, implementation office (shopping furniture, method) motorcycle s, etc. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Selection of Consulting firms Above US$ 2 million All 2. Selection of Individual Consultant Above US$ 400,000 All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 11 individual consultants would be financed through retroactive financing. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 6 7 Ref. Description Estimated Pack Review Comments No. Cost ages by Bank US$ million (Prior / Post) Producer Group 0.34 1 Post QCBS method Mobilization for Siem Reap (NGO package) Self-help Group 0.27 1 Post QCBS method Mobilization for SRP (NGO) Human Resources 0.92 2 Post QBS method Development Services Provider (HRDSP) for Siem Reap (NGO/Firm) Consulting firms for 0.175 1 Post CQS method baseline survey, impact survey, and final impact June 12, 2017 survey, and External financial auditing Individual consultants 2.93 126 Post Selection of for supporting the individual national level and sub- consultant. national level project entities (finance, procurement, infrastructure, community development, micro- finance experts, livelihood specialists, etc.) June 12, 2017 PROCUREMENT Cambodia : KH - Livelihood Enhancement and Association of the Poor Project (LEAP) PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2017-06-12 2019-07-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153591 GPN Date: Project Name: KH - Livelihood Enhancement and Association of the Poor Project (LEAP) Loan / Credit No: IDA / 59600 Executing Agency(ies): Ministry of Interior WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-99874-CW-RFQ / Pending Request for Single Stage - One Office Renovation at PCO- IDA / 59600 Post Open - National 0.00 Implementati 2019-03-06 2019-04-17 2019-05-17 Quotations Envelope MOI on KH-MOI-99875-CW-CDD / The rehabilitation laterite road (Length 2400m, Width Community Pending 4.00m, 0.15m thick) and IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Single Pipe Culvert Ø 1.0m Development on (2 units) for Anlong Samnar, Chi Kraeng. KH-MOI-99886-CW-CDD / The rehabilitation laterite road ( Length 1500m, Width Community Pending 4.00m, 0.15m Thick) and IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-03-01 2019-03-08 2019-04-30 2019-05-07 2019-05-21 2019-08-19 Construction of Box Culver Development on heigth 2m with Stop Log (1 unit) for Doun Kaev, Puok. KH-MOI-99878-CW-CDD / The rehabilitation laterite Community Pending road (Length 2419m, Width IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 2019-07-11 3.50m, 0.15m thick) for Chi Development on Kraeng, Chi Kraeng. KH-MOI-99880-CW-CDD / The rehabilitation laterite road (Length 2090m, Width 4.00m, 0.15m thick) and Community Pending Construction of Single Pipe IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 2019-07-11 Culvert Ø 0.6m (1 unit), Development on Single Pipe Culvert Ø 0.8m (1 unit) and Single Pipe Culvert Ø 1.0m (1unit) for Dan Run, Soutr Nikom. KH-MOI-99881-CW-CDD / The rehabilitation laterite road (Length 1550m, Width 4.00m, 0.15m thick), Single Community Pending Pipe Culvert Ø 1.0m (1unit) IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2019-09-19 and Construction of Double Development on Pipe Culvert Ø 0.8m (5units), for Ballangk, Prasat Bakong. Page 1 KH-MOI-99887-CW-CDD / Construction of Box Culvert heigth 2m with stop Log (1unit), Box Culvert heigth Community Pending 1.5m with stop Log (1unit) IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Pipe Culver Ø 0.8m with Development on Stop Log (1unit) and Single Pipe Culvert Ø 0.8m (4 unit) for Sasar Sdam, Puok. KH-MOI-99888-CW-CDD / Construction of Reinforced Community Pending Concrete Road (Lengh 260m, IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 width 5.00m, 0.15m thick) Development on for Kampong Thkov, Kralanh. Total: 0.260 km KH-MOI-99890-CW-CDD / The rehabilitation ponds size (60mx30mx5m), Community Pending (30mx25mx5m), IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 2019-07-11 (40mx20mx5m), Development on (50mx50mx5m) for Slaeng Spean, Srei Snam. Total:4 Places KH-MOI-99891-CW-CDD / The rehabilitation laterite Community Pending road (1.450km) and Single IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Pipe Culvert Ø 1.0m (3 Development on units) for Svay Chek, Angkor Thum. KH-MOI-99892-CW-CDD / The rehabilitation laterite road ( Length 2520m, Width Community Pending 4.00m, 0.15 Thick) and IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Construction of Single Pipe Development on Culvert Ø 1.0m (2 unit) for Leang Dai, Angkor Thum. KH-MOI-99893-CW-CDD / The rehabilitation laterite road (Length 1080m, Width 4.00m, 0.15m thick) and Community Pending Construction of Single Pipe IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-05-07 2019-08-05 Culvert Ø 0.8m (1 unit) and Development on Triple Pipe Culvert, Ø 1.0m (3 unit) for Ta Siem, Svay Leu. KH-MOI-99894-CW-CDD / Construction of Reinforced Community Pending Concrete Road (Length IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 445m, Width 3.50m, 0.15m Development on thick) for khnang Phnum, Svay Leu. KH-MOI-99889-CW-CDD / The rehabilitation laterite Community Pending road (Length 2600m, Width IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 5.00m, 0.15m thick) for Development on Klang Hay, Srei Snam. Total: 2.600 km Page 2 KH-MOI-110144-CW-CDD / Construction: 1-Reinforcement concrete road:(L262m, w 2.6m, T 0.12m) ,Drainage system:(262m,0.6m), 2- Community Pending Installation:(18 Sola street IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 lighting and poles for 262m) Development on and 3-Concrete bridge: (L206m, width1.50m, T0.07m) in Sangkat Srah Chak, Khan Daun Penh KH-MOI-110147-CW-CDD / Construction:1-Reinforcement concrete road, Drainage (L171m),Installation of Sola street lighting and Community Pending poles(171m), 2-Reinforcement IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 concrete Development on road(147m),drainage(48m), Installation of Sola street lighting and poles (147m) in Sangkat Khmuonh, Khan Saen Sokh KH-MOI-110151-CW-CDD / Construction: 1-Reinforcement concrete road (340m) and drainage system:(448m), 2- Road (L130m) and drainage Community Pending system (130m), 3-Road IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 (120m) and drainage Development on system:(250m), 4- Road (238m) and drainage system (238m) in Sangkat Trapeang Krasang, Khan Por Sen Chey KH-MOI-110153-CW-CDD / Construction:1- Reinforcement concrete road:(L353m, W 4m, T0.15m) and drainage Community Pending system (L353m, 0.6m ) and IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 2-Reinforcement concrete Development on road (L357m, W 4m, T 0.15m) in Sangkat Dangkao, Khan Dangkao KH-MOI-110154-CW-CDD / Construction of Reinforcement concrete road and Drainage System: 1- Community Pending Road (100m) , 2-Road IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 2019-09-24 (171m ), 3-Road (52m), 4- Development on Road(88m) ,5- Road (90m), 6- Road (93m) and 7-Road (L128m) in Sangkat Prey Veaeng, Khan Dangkao KH-MOI-110155-CW-CDD / Construction of reinforcement concrete: 1- Road (99m) ,1- Road(101m), 2-Road(60m), 3- Drainage system:(9m), 4- Community Pending Installation of Sola street IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 2019-09-24 lighting and poles Development on (120m),(439m),(439m) and (98m) in Sangkat Chrang Chamreas Ti Muoy,Khan Russey Keo Page 3 KH-MOI-110159-CW-CDD / Construction of reinforcement concrete road:(466m, width 5m, thickness 0.15m ), 2- Community Pending Road:(312m, width 4m, IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 2019-09-24 thickness 0.15m ) and Development on drainage system:(312m,cross section 0.6m) in Sangkat Kork Roka, Khan Preak Pnov KH-MOI-110162-CW-CDD / Construction of reinforcement concrete:1- road:(L102m, width 2.5m, thickness 0.12m) Community Pending and drainage IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 2019-09-24 system:(114m).2- road:(169m, Development on width 3.5m, thickness 0.15m) and drainage system:(169m) in Sangkat Boeng Kak 1, Khan Tuol Kork KH-MOI-110165-CW-CDD / Construction of reinforcement concrete road and and drainage system in Prey Community Pending Spueu & Prey Sandaek, IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 2019-10-09 Sangkat Chaom Chau 2, Development on Khan Por Sen Chey (663m) and drainage system (523m) in Sangkat Chaom Chau 2, Khan Por Sen Chey KH-MOI-110168-CW-CDD / Construction of reinforcement concrete:1- road(158m) and drainage (138m), 2-Road and drainage system (77m),3- Community Pending road(261m) and drainage IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 2019-10-09 (207m),4-Installation of Sola Development on street lighting and poles(158m), (77m)and (261m) in Sangkat Chak Angrae Leu, Khan Mean Chey KH-MOI-110173-CW-CDD / Construction of reinforcement concrete: 1- Road(110m, width 4m, thickness 0.15m), Community Pending 2- Road(100m),2-Installation IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 2019-10-09 of Sola street lighting and Development on poles (250m) in Khtor,Sangkat Preak Leap, Khan Chroy Changvar KH-MOI-110174-CW-CDD / Construction of reinforcement concrete: 1- Road(124m), 2- Road (137m). 3- Road (117m Community Pending ). 4-Installation of Sola IDA / 59600 Post Driven Open - National 0.00 Implementati 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 2019-10-09 street lighting and poles Development on (117m), and (139m ) in Sangkat Chbar Ampov Ti Pir, Khan Chbar Ampov GOODS Page 4 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-14029-GO-RFQ / Pending Office Furniture for National Request for Single Stage - One IDA / 59600 Post Open - National 0.00 Implementati 2017-07-14 2017-09-03 2017-10-18 Level and Sub National Quotations Envelope on Level KH-MOI-14017-GO-RFQ / Pending Request for Single Stage - One Softwares ( Accounting) for IDA / 59600 Post Open - National 0.00 Implementati 2017-07-31 2017-09-20 2017-11-19 Quotations Envelope PCO-MOI 1 unit on KH-MOI-26199-GO-RFB / Pending Motorcycles plus helmets for Single Stage - One IDA / 59600 Post Request for Bids Open - National 0.00 Implementati 2017-10-02 2017-10-16 2017-11-15 2017-12-06 2018-01-03 2018-03-04 National level and Sub- Envelope on National (Total 133 Units) KH-MOI-26827-GO-RFB / Lot1: Develop Management Information System (MIS) Pending System Lot2: Single Stage - One IDA / 59600 Post Request for Bids Open - National 0.00 Implementati 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 Server, Network, Tablet, Envelope on website, etc.) Lot 3:MIS webside maintenance for PCO-MOI KH-MOI-33988-GO-RFQ / 4 Pending Request for Single Stage - One Laptop Computers for IDA / 59600 Post Open - National 0.00 Implementati 2017-11-05 2017-12-05 2017-12-20 Quotations Envelope Management on KH-MOI-34259-GO-RFB / Pending Office Equipment for Single Stage - One IDA / 59600 Post Request for Bids Open - National 0.00 Implementati 2017-11-08 2017-11-13 2017-12-15 2018-01-14 2018-02-18 2018-04-19 National and Sub National Envelope on Leve KH-MOI-36613-GO-UN / Lot1:Vehicles (Station Wagon) 3 units for -PCO- MOI and 1 units for MEF, Pending UN Agencies Lot2:Vehicles (Pick up Cars) IDA / 59600 Post Direct 0.00 Implementati 2017-11-17 2017-11-22 2017-12-25 2018-02-23 (Direct) for 1units for GDA-MAFF, 3 on units for Siem Reap and 2 units for PPM. The total Vehicles: 10 Units KH-MOI-34266-GO-UN / Vehicles (Station Wagon) 3 UN Agencies units for -PCO-MOI and 1 IDA / 59600 Post Direct 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-02-23 (Direct) units for MEF, Total Vehicles: 4 Units KH-MOI-11051-GO-RFB / Vehicles (Pick up Cars) for 1units for GDA-MAFF, 3 Single Stage - One IDA / 59600 Post Request for Bids Open - National 0.00 Canceled 2017-10-02 2017-10-16 2017-11-15 2017-12-15 2018-01-07 2018-05-07 units for Siem Reap and 2 Envelope units for PPM. Total Vehicles: 6 Units KH-MOI-99858-GO-RFQ / Pending Request for Single Stage - One Total 7 Air Conditioners for IDA / 59600 Post Open - National 0.00 Implementati 2019-03-06 2019-04-03 2019-04-17 Quotations Envelope PCO and MAFF on KH-MOI-99860-GO-RFQ / Pending Request for Single Stage - One Office Furniture for MOI- IDA / 59600 Post Open - National 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 Quotations Envelope PCO on Page 5 KH-MOI-99861-GO-RFQ / Printing Material and Pending Thumbprint pad for Request for Single Stage - One IDA / 59600 Post Open - National 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 SHG/producer Quotations Envelope on group/commune federation for 2019 KH-MOI-99863-GO-RFQ / Material for SHG/producer Pending Request for Single Stage - One group/commune federation IDA / 59600 Post Open - National 0.00 Implementati 2019-03-06 2019-04-24 2019-05-24 Quotations Envelope (Boxes for keeping on documents and cash) KH-MOI-99865-GO-RFQ / Equipment for Pending Request for Single Stage - One Commune/Sangkat IDA / 59600 Post Open - National 0.00 Implementati 2019-03-06 2019-04-03 2019-04-18 Quotations Envelope Investment Projects (SRP on and PPCH) KH-MOI-99868-GO-RFQ / 72 Tablets for MIS (3 MoI, Pending Request for Single Stage - One 3 GDA, 3 PPCH, 3 Pro. IDA / 59600 Post Open - National 0.00 Implementati 2019-04-06 2019-05-04 2019-06-03 Quotations Envelope S_Reap, 47 commune, 13 on Sangkat) KH-MOI-99869-GO-RFQ / Printing Materials (Logos, Pending Request for Single Stage - One Printed Folder, Factsheets, IDA / 59600 Post Open - National 0.00 Implementati 2019-05-06 2019-06-03 2019-06-24 Quotations Envelope Newsletters, Brochures, on Posters and Standing Poster) KH-MOI-99871-GO-RFQ / Printing Materials for Pending Request for Single Stage - One SHG/producer IDA / 59600 Post Open - National 0.00 Implementati 2019-12-06 2020-01-04 2020-02-03 Quotations Envelope group/commune federation for on 2020 KH-MOI-26829-GO-RFB / Material for SHG/Poducer group/commune federation(books keeping, Single Stage - One IDA / 59600 Post Request for Bids Open - National 0.00 Canceled 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 cash book, pay and loan Envelope record book, SHG box for keeping docs. And Thumprint pad) for SRP KH-MOI-121052-GO-RFQ / Pending Procurement of supply Request for Single Stage - One IDA / 59600 Post Open - National 0.00 Implementati 2019-07-10 2019-08-04 2019-09-03 Server and network for Quotations Envelope on LEAP Project NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-99864-NC-RFQ / Pending Request for Single Stage - One Develop Website for LEAP IDA / 59600 Post Open - National 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 Quotations Envelope Projec on Pending KH-MOI-99870-NC-RFQ / Request for Single Stage - One IDA / 59600 Post Open - National 0.00 Implementati 2019-07-06 2019-08-17 2019-10-16 Four (4) Video Spots Quotations Envelope on CONSULTING FIRMS Page 6 Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-39863-CS-CQS / Consultant Impact Survey (3nd year of Pending IDA / 59600 Post Qualification Open - National 0.00 2020-01-02 2020-01-23 2020-03-07 2020-04-06 2020-05-11 2020-11-07 the project/Mid-term review) Implementation Selection (Local Firm) at PCO-MOI KH-MOI-39867-CS-CQS / Final Impact Survey ( (5th Consultant Pending year of Project evaluation IDA / 59600 Post Qualification Open - National 0.00 2022-01-03 2022-01-24 2022-03-09 2022-04-08 2022-05-13 2022-11-09 Implementation and completion report) (Local Selection Firm) at PCO-MOI KH-MOI-82848-CS-CQS / Development of Community Consultant Institutions of the Poor for Pending IDA / 59600 Post Qualification Open - National 0.00 2018-10-22 2018-11-12 2019-01-11 2019-02-10 2019-03-17 2022-11-30 4 Districts​​  (Angkor Thum, Implementation Selection Kralanh, Pouk and Srei Snam District) KH-MOI-82083-CS-CQS / Development of Community Institutions of the Poor for Consultant Pending 5 Districts ( Chi Kraeng, IDA / 59600 Post Qualification Open - National 0.00 2018-10-22 2018-11-12 2019-01-11 2019-02-10 2019-03-17 2022-12-05 Implementation Prasat Bakong, Siem Reap, Selection Soutr Nikom and Svay Leu District) KH-MOI-70310-CS-QCBS / Human Resource Quality And Cost- Open - Under Development Service IDA / 59600 Prior 0.00 2018-12-14 2019-01-13 2019-02-26 2019-04-12 2019-05-12 2019-06-16 2019-07-21 2023-06-30 Based Selection International Implementation Provider (HRDSP) for SRP and PPCH KH-MOI-39858-CS-QCBS / Human Resources Quality And Cost- Open - Development Services IDA / 59600 Post 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 Based Selection International Provider(HRDSP) for PPM (NGO/Firm) KH-MOI-39860-CS-CQS / Consultant Baseline Survey (1st IDA / 59600 Post Qualification Open - National 0.00 Canceled 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-11-21 year)(Local Firm) at PCO- Selection MOI KH-MOI-39857-CS-QCBS / Human Resources Quality And Cost- Open - Development Services IDA / 59600 Post 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 Based Selection International Provider(HRDSP) for SRP (NGO/Firm) INDIVIDUAL CONSULTANTS Page 7