Procurement Plan (Textual Part) I. General 1. Project Information Country: Zambia Project Name: Zambia Integrated Forest Landscape Project (ZIFLP) Project Id: P161490 2. Project Implementation Agency: Ministry of National Development Planning 3. Date of the Procurement Plan: 4. Period Covered by this procurement plan: March 2018 to June 30, 2019 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement Act, 2011, The Public Procurement (Amendment) Act, 2016 and the Regulations, 2013, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1 There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification: Not applicable VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable VII. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not applicable VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each. (a) Goods: Not applicable (b) Works: Not applicable Domestic preference is not applicable for National Open Competitive Procurement IX. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable: Not applicable X. Other Relevant Procurement Information Not applicable XI. Procurement Prior Review Thresholds (US$ millions) 2 Type of Procurement High Substantial Moderate Low Risk Risk Risk Risk Works (including turnkey, supply 15 & installation of plant and equipment, and PPP) Goods, information technology 2 and non-consulting services Consultants: firms 0.5 Consultants: Individuals 0.3 Post Review: All contacts not subject to prior review shall be subject to post review. XII. Thresholds for Procurement Approaches and Method (US$ millions) Works Goods, IT and Non-consulting Shortlist of National Services Consultants Open Open Request Open Open Request Consulti Engineeri Internatio Nationa for Internatio Nation for ng ng & nal l Quotati nal al Quotati Services Construct on on ion ≥ < ≥ < Supervisi ≤ ≤ on 15 15 0.2 2 2 0.1 0.3 0.3 XIII. Summary of the procurement packages: (Planned for the first 18 months after project effectiveness): Category: Sr. Contract Descrip-tion Estima Revi Market Selectio Evalua Procure- Prequa Domesti Expect Expecte No ted ew Approa n -tion ment li- c ed d date Cost by ch Method Option Process fication Preferen date of of (US$) Bank (Open- (RFP, s (Single (Yes/ ce bid/ Contrac (Prio Nation RFB, (BAFO, stage- No) (Yes/No) propos t r/ al/ QCBS Rated single al Signatur Post) Limite etc.) Criteria envelope openin e d etc.) etc.) etc.) g 1 Construction/drilling of 10,000 Post Limite RFB BAFO Single NO NO Sept Oct 2 borehole d 2018 2018 2 Rehabilitation of the 6,000 Post Limite RFB BAFO Single NO NO Aug 18 Sept boreholes (2) d 2018 3 Boundary beaconing- 41,000 Prior Limite FCA BAFO Single NO NO May 18 June Lukusuzi d 2018 4 Boundary beaconing- 32,000 Prior Limite FCA BAFO Single NO NO May 18 June Luambe d 2018 3 5 Rehabilitation of NPIU 40,000 Post Limite RFB BAFO Single NO NO April May Offices d 18 2018 6 Rehabilitation of PPIU 40,000 Post Limite RFB BAFO Single NO NO Dec 18 Jan Offices d 2019 7 Motorbikes x 9-District 49,600 Post Limite RFB BAFO Single NO NO April Oct Planning d 18 2018 8 59,800 Post Limite RFB BAFO Single NO NO April April Procurement of Field d 18 2018 Desk Equipment Computers and GIS Software-District Planning 9 17,600 Post Limite RFB BAFO Single NO NO April April Computers-Desktops d 18 2018 and Laptop-District Planning 10 Hand Held and 38,000 Post Limite RFB BAFO Single NO NO April April Differential GPS d 18 2018 11 20,000 Post Limite RFB BAFO Single NO NO May 18 Dec Information, Education d 2018 and Communication activities (i.e Radio programs, production of documentaries, phamphlets, brochures, newsletter) 12 Procure Inputs –seeds, 47,800 Post Limite RFB BAFO Single NO NO May 18 June fertilizers d 2018 13 Soil Doc Kit for FTC and 21,000 Post Limite RFB BAFO Single NO NO May 18 June ZARI d 2018 14 Field soil samples, lab 29,000 Post Limite RFB BAFO Single NO NO May 18 June tests and soil fertility d 2018 mapping 15 Procure Vehicle – 50,000 Post Direct UNOPS BAFO Single NO NO April May Provincial 18 2018 16 3 laptops, Plotter ,3 24,975 Post Limite RFB BAFO Single NO NO May 18 June hand held GPS 1 x d 2018 differential GPS (GNSS?GPS) 17 Post Harvest handling 38,240 Post Limite RFB BAFO Single NO NO May 18 June (Metal Silos for demo) d 2018 18 Set of Laboratory 431,60 Post Nation RFB BAFO Single NO NO May 18 June equipment for ZARI 0 al 2018 219 Vehicles x 2- Forest 100,00 Post Direct UNOPS BAFO Single NO NO April May Management 0 18 2018 20 Procure materials for 25,000 Post Limite RFB BAFO Single NO NO May 18 June nurseries and tree d 2018 planting (procurement of nursery requisites, etc)- 30 ha Annually 21 Equipment-office 25,000 Post Limite RFB BAFO Single NO NO May 18 May equipment, furniture & d 2018 computers for 9 districts 22 Printing of guidelines 3,000 Post Limite RFB BAFO Single NO NO June Dec (Community forest d 18 2018 management guidelines) 23 1 x Quad bikes- 3,200 Post Limite RFB BAFO Single NO NO June July Lukusuzi NP d 18 2018 24 1 x Motorcycle - 5,000 Post Limite RFB BAFO Single NO NO June July Lukusuzi NP d 18 2018 25 50,000 Post Direct UNOPS BAFO Single NO NO April May 1 Vehicle - Lukusuzi NP 18 2018 4 26 Field equipment (rain 15,000 Post Limite RFB BAFO Single NO NO June July coats, boots, tents, d 18 2018 GPS, camp beds etc.) for 30 WFOs 27 1 x Quad bikes- 3,200 Post Limite RFB BAFO Single NO NO May Sept Luambe NP d 2018 2018 28 1 Vehicle - Luambe NP 50,000 Post Direct UNOPS BAFO Single NO NO May 18 Sept 2018 29 Field equip (Rain Coats, 15,000 Post Limite RFB BAFO Single NO NO May 18 July Boots, Tnts, GPS d 2018 30 1 Vehicle 50,000 Post Direct UNOPS BAFO Single NO NO April May 18 2018 31 Equip (fire craker, 3,000 Post Limite RFB BAFO Single NO NO May 18 Sept Blastig)- Lukusuzi d 2018 NPEquipment for HWC 32 1 Vehicle 50,000 Post Direct UNOPS BAFO Single NO NO April May 18 2018 33 Equipment-server-2 18,000 Post Limite RFB BAFO Single NO NO June July Laptops, 2 Desktops d 18 2018 and1 x Projector 34 450,00 Post Direct UNOPS BAFO Single NO NO April May 9x Vehicles NPUI-4? 0 18 2018 PPUI 5 35 8,200 Post Limite RFB BAFO Single NO NO March April 2 x Video /still Camera d 18 2018 & 1 audio recorder NPUI/PPUI 36 12200 Post Limite RFB BAFO Single NO NO March April Furniture and 0 d 18 2018 Equipment (Computers, Printers, Scanners)- NPUI/PPUI 37 2,200 Post Limite RFB BAFO Single NO NO March April TV SET and Audio d 18 2018 recorder-NPUI/PPUI 38 20,000 Post Limite RFB BAFO Single NO NO May 18 June Procure and Install d 2018 Payroll Management System-NPUI 39 20,000 Post Limite RFB BAFO Single NO NO May 18 June Procurement of d 2018 Accounting Package – NPUI/PPUI 40 10,000 Post Limite RFB BAFO Single NO NO May 18 June Procure and Install d 2018 Internet Services 41 ToT for district 50,000 Post Nation INDV BAFO Single NO NO May 18 July multisectoral teams in al 2018 landuse and community action planning, landscape/community action planning with specila attention to ESS Desk officers 42 Develop the gender 35,000 Post Nation INDV BAFO Single NO NO May July strategy al 2018 2018 43 Support updating of 210,00 Post Nation RFP BAFO single NO NO May 18 July District Situation 0 al ENV 2018 Analysis reports in Katete, Petauke, Chipata, Nyimba and Chadiza and completion of DSAs in Sinda and Vubwi (Physical Planning) Support for land use planning (harmonizing the data 5 on land use from all sources)/ Participatory landuse planning, problem analysis, action planning, priority setting and zoning 44 Conduct the GHG 430,00 Prior Interna RFP BAFO Single NO NO May 18 Aug Emission Baseline 0 tional ENV 2018 Study 45 Carbon benefit sharing 100,00 Post Nation INDV BAFO Single NO NO May 18 July, and Stakeholder 0 al ENV 2018 consultation on REDD+ at multiple scales of action in Eastern Province 46 Develop of a SESA, 200,00 Post Nation RFP BAFO Single NO NO May 18 Aug updating ESMF and 0 al ENV 2018 other social safeguards 47 500,00 Prior Interna RFP BAFO Single NO NO May 18 Aug ERPD 0 tional ENV 2018 48 Develop systems to 365,00 Prior Interna RFP BAFO Single NO NO June Sep manage data on land tional ENV 18 2018 rights 49 Clarification of 150,00 Post Nation RFP BAFO Single NO NO June Aug ownership Rights 0 al ENV 18 2018 50 Digitization of all 250,00 Post Nation RFP BAFO Single NO NO April June201 cadastral maps 0 al ENV 18 8 51 Mapping of informal 200,00 Post Nation RFP BAFO Single NO NO May 18 Aug agricultural properties 0 al ENV 2018 52 Completion of 50,000 Post Nation INDV BAFO Single NO NO June Aug customary rights al ENV 18 2018 recording USAID - supported pilot 53 Land component 70,000 Post Nation INDV BAFO Single NO NO June Aug coordinator 0 al ENV 18 2018 54 Assistant Land 50,000 Post Nation INDV BAFO Single NO NO June Aug Component Coordinator al ENV 18 2018 55 Planning, Monitoring 53,460 Post Nation INDV BAFO Single NO NO Feb March and Evaluation Officer al ENV 2018 2018 56 National Project 123,93 Post Nation INDV BAFO Single NO NO Feb March Manager 0 al ENV 2018 2018 57 Procurement Officer 56,700 Post Nation INDV BAFO Single NO NO Feb March al ENV 2018 2018 58 Project Accountant 58,320 Post Nation INDV BAFO Single NO NO Feb March al ENV 2018 2018 59 Internal Auditor 51,840 Post Nation INDV BAFO Single NO NO Feb March al ENV 2018 2018 60 Administrative 27,540 Post Nation INDV BAFO Single NO NO Feb March Assistant al ENV 2018 2018 61 Environmental and 55,080 Post Nation INDV BAFO Single NO NO Feb March Social Inclusion Officer al ENV 2018 2018 62 Communications Officer 48,600 Post Nation INDV BAFO Single NO NO Feb March al ENV 2018 2018 63 Driver X2 27,540 Post Nation INDV BAFO Single NO NO Feb March al ENV 2018 2018 64 Planning, Monitoring 53,460 Post Nation INDV BAFO Single NO NO Feb March and Evaluation Officer al ENV 2018 2018 65 Provincial Project 90,882 Post Nation INDV BAFO Single NO NO Feb March Manager al ENV 2018 2018 66 Procurement Officer 56,700 Post Nation INDV BAFO Single NO NO Feb March al ENV 2018 2018 67 Project Accountant 58,320 Post Nation INDV BAFO Single NO NO Feb March al ENV 2018 2018 68 Internal Auditor 51,840 Post Nation INDV BAFO Single NO NO Feb March al ENV 2018 2018 69 Administrative 27,540 Post Nation INDV BAFO Single NO NO Feb March Assistant al ENV 2018 2018 70 Environmental and 55,080 Post Nation NDV BAFO Single EN NO NO Feb March Social Inclusion Officer al 2018 2018 6 71 Communications Officer 48,600 Post Nation NDV BAFO Single EN NO NO Feb March al 2018 2018 72 Driver x 2 27,540 Post Nation NDV BAFO Single EN NO NO Feb March al 2018 2018 7 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 8 contract, financially or in any other manner;2 (ii) to be a nominated3 sub- contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 9 the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 10 PROCUREMENT Zambia : Zambia Integrated Forest Landscape Project (GEF) PLAN General Information Country: Zambia Bank’s Approval Date of the Original Procurement Plan: 2018-05-25 2021-08-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161490 GPN Date: Project Name: Zambia Integrated Forest Landscape Project (GEF) Loan / Credit No: IDA / 60380, TF / A4646, TF / A4645, TF / A3169 Ministry of National Development Planning Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MNDP/ZIFLP/CW/002/2018 / Boundary beaconing-Lukusuzi 2. Livelihood and low-carbon 2018-05- Ganme Park/-Luambe Game IDA / 60380 Prior Force Account Direct 73,000.00 0.00 Canceled 2018-05-01 2018-05-01 2018-05-01 investments 01 Park AWPB REF:2.2.3.1.5/2.2.3.2.5 MNDP/ZIFLP/CW/003/2018 / Rehabilation of NPIU Offices Single Stage - One 2019-01- IDA / 60380 3. Project management Post Request for Bids Limited 80,000.00 0.00 Canceled 2018-04-01 2018-04-06 2018-05-18 2018-06-17 2018-07-22 and PPIU Offices AWPB Envelope 18 REF:3.1.2/3.2.2 MNDP/ZIFLP/CW/003/2019 / Construction of Under 2. Livelihood and low-carbon Single Stage - One 2020-03- houses/Offices AWPB IDA / 60380 Post Request for Bids Open - National 610,000.00 0.00 Implementat 2019-06-01 2019-07-08 2019-06-06 2021-02-09 2019-07-18 2019-08-17 2019-09-21 investments Envelope 19 REF:2.1b.1.2.9,2.2.3.1.2,2.2.3 ion .2.3 MNDP/ZIFLP/CW/008/2019 / 2. Livelihood and low-carbon Request for Single Stage - One 2019-11- Construction of Gates AWWPB IDA / 60380 Post Limited 20,000.00 0.00 Canceled 2019-04-06 2019-06-01 investments Quotations Envelope 28 REF: 2.2.3.2.2 MNDP/ZIFLP/CW/008/2018 / Procurement of Post Harvest 2018-05- IDA / 60380 1. Enabling environment Prior Force Account Direct 38,240.00 0.00 Canceled 2018-05-30 2018-05-30 2018-05-30 handling (Metal silos for 30 demo) under CSA REF;2.1a 4.2 MNDP/ZIFLP/CW/001/2019 / construction of a soil 2. Livelihood and low-carbon Single Stage - One 2020-04- IDA / 60380 Post Request for Bids Open - National 350,000.00 0.00 Canceled 2019-06-30 2019-07-05 2019-08-16 2019-09-15 2019-10-20 laboratory (720M) at Msekera investments Envelope 17 AWPB REF No:2.1a.2.9 MNDP/ZIFLP/CW/021/2019 / Under Construction and set up of in 2. Livelihood and low-carbon Single Stage - One 2021-01- IDA / 60380 Post Request for Bids Open - National 578,740.00 473,015.17 Implementat 2020-04-01 2020-07-12 2020-04-06 2021-02-10 2020-05-18 2020-08-20 2020-06-17 2020-09-23 2020-07-22 field Drip lines networkAWPB investments Envelope 18 ion REF;2.1a.1.5.2 MNDP/ZIFLP/CW/023/2019 / Provision of Signages at 2. Livelihood and low-carbon Request for Single Stage - One 2020-11- IDA / 60380 Post Limited 5,000.00 0.00 Canceled 2020-04-06 2020-06-01 Various Irrigation Sites AWPB investments Quotations Envelope 28 REF;2.1a.1.5.2 MNDP/ZIFLP/CW/022/2019 / Fencing of Irrigation Schemes 2. Livelihood and low-carbon Request for Single Stage - One 2021-01- IDA / 60380 Post Limited 132,283.00 0.00 Canceled 2020-06-06 2020-08-01 at various SitesAWPB investments Quotations Envelope 28 REF;2.1a.1.5.2 MNDP/ZIFLP/CW/020/2019 / Site, Drill Boreholes for Under Irrigation Schemes,Equipping 2. Livelihood and low-carbon Single Stage - One 2021-01- IDA / 60380 Post Request for Bids Open - National 372,757.34 0.00 Implementat 2020-04-01 2020-07-13 2020-04-06 2021-02-10 2020-05-18 2020-08-21 2020-06-17 2020-09-15 2020-07-22 with Solar Powered investments Envelope 18 ion Submersible Pumps,AWPB REF;2.1a.1.5.2 MNDP/ZIFLP/CW/006/2020 / 2. Livelihood and low-carbon Single Stage - One 2021-02- Construction of Msekera Lab IDA / 60380 Post Request for Bids Open - National 650,000.00 532,706.92 Signed 2020-04-30 2020-05-20 2020-05-05 2020-06-16 2020-06-24 2020-07-16 2020-07-03 2020-08-20 2020-09-08 investments Envelope 16 in Chipata MNDP/ZIFLP/CW/007/2020 / Construction of nursery shelter with pit latrine for 2. Livelihood and low-carbon Request for Single Stage - One 2021-03- IDA / 60380 Post Limited 19,800.00 20,728.16 Signed 2020-08-04 2020-04-24 2020-09-29 2020-07-21 Forest Department at Masupe investments Quotations Envelope 28 Forestry Station: AWPB 2.1b 1.2.15 MNDP/ZIFLP/CW/008A/2020 Under / Creation of loop roads for 2. Livelihood and low-carbon 2021-03- IDA / 60380 Prior Force Account Direct 78,700.00 0.00 Implementat 2020-08-14 2021-04-26 2020-08-19 2020-09-23 Lukusuzi & Luambe National investments 22 ion Parks MNDP/ZIFLP/CW/009/2020 / 2. Livelihood and low-carbon Request for Single Stage - One 2021-04- Refurbshment of Offices at IDA / 60380 Post Limited 16,350.00 0.00 Canceled 2020-08-12 2020-10-07 investments Quotations Envelope 05 Department of Survey MNDP/ZIFLP/CW/007/2019 / Under 2. Livelihood and low-carbon Request for Single Stage - One 2021-05- Watering holes AWPB IDA / 60380 Post Limited 55,000.00 0.00 Implementat 2020-10-05 2020-11-30 investments Quotations Envelope 29 REF:2.2.3.1.6,2.2.3.2.8 ion MNDP/ZIFLP/CW/005/2019 / 2. Livelihood and low-carbon Request for Single Stage - One 2021-05- Upgrading of existing tracks, IDA / 60380 Post Limited 62,700.00 0.00 Canceled 2020-10-05 2020-11-30 investments Quotations Envelope 29 AWPB REF:2.2.3.1.3,,2.2.3.2.6, MNDP/ZIFLP/CW/002/2019 / 2. Livelihood and low-carbon Request for Single Stage - One 2021-05- Borehole & Water Reticulation IDA / 60380 Post Limited 50,000.00 260,235.26 Signed 2020-10-05 2021-04-23 2020-11-30 2021-05-19 investments Quotations Envelope 29 AWPB REF:2.1b1.2.8 MNDP/ZIFLP/CW/002/2020 / Procure Civil Works - 2. Livelihood and low-carbon Request for Single Stage - One 2021-05- Rehabilitate/construct 20 IDA / 60380 Post Limited 160,000.00 0.00 Canceled 2020-10-05 2020-11-30 investments Quotations Envelope 29 water harvesting structures- AWPB 2.1a.3.1.3- Page 1 MNDP/ZIFLP/CW/003/2020 / Procure Civil Works rehabilitation and 2. Livelihood and low-carbon Request for Single Stage - One 2021-05- IDA / 60380 Post Limited 30,000.00 0.00 Canceled 2020-10-05 2020-11-30 maintenance services- investments Quotations Envelope 29 Breeding Centres- AWPB'2.1a.3.1.5 MNDP/ZIFLP/CW/010/2020 / Procurement ofcontruction of Under 2. Livelihood and low-carbon Single Stage - One 2021-07- medium houses for DNPW & IDA / 60380 Post Request for Bids Open - National 500,000.00 0.00 Implementat 2020-09-30 2020-10-02 2020-10-05 2021-02-10 2020-11-16 2020-11-09 2020-12-16 2020-12-31 2021-01-20 investments Envelope 19 houses and Office blocks for ion FD MNDP/ZIFLP/CW/004/2020 / Construct Halal standard meat 2. Livelihood and low-carbon Request for Single Stage - One 2021-08- IDA / 60380 Post Limited 150,000.00 0.00 Canceled 2021-01-01 2021-02-26 processing plant -AWPB investments Quotations Envelope 25 2.1a.3.5.2.2- MNDP/ZIFLP/CW/001/2018 / Construction of infrastructure Pending 2. Livelihood and low-carbon Request for Single Stage - One 2021-08- ( 2boreholes)/Rehabilation of IDA / 60380 Post Limited 16,000.00 0.00 Implementat 2020-12-25 2021-02-19 investments Quotations Envelope 18 Infrstructure ( 2boreholes) - ion AWPB REF: 2.1b.2.9/2.1b.2.10 MNDP/ZIFLP/CW/001/2020 / Support towards structural 2. Livelihood and low-carbon Request for Single Stage - One 2021-08- improvements of 11 storage IDA / 60380 Post Limited 61,068.97 0.00 Canceled 2020-12-25 2021-02-19 investments Quotations Envelope 18 structures AWPB REF;2.1a.1.5.2 MNDP/ZIFLP/CW/012/2020 / 2. Livelihood and low-carbon Single Stage - One 2021-08- Construction of a fertilizer IDA / 60380 Post Request for Bids Open - National 3,313,182.96 0.00 Canceled 2020-11-09 2020-11-14 2020-12-26 2021-01-25 2021-03-01 investments Envelope 28 Blending Plant in Sinda MNDP/ZIFLP/CW/002/2021 / Rehabilitation of offices at Request for Pending Mindola and Msipazi Forestry 2. Livelihood and low-carbon Request for Single Stage - One 2022-06- IDA / 60380 Post Limited Quotations (Non 66,000.00 0.00 Implementat 2021-11-04 2021-12-30 Camps and camp house at investments Quotations Envelope 28 Bank-SPD) ion Masupe, Mindola and Msipazi for FD MNDP/ZIFLP/CW/004/2021 / Request for Pending 2. Livelihood and low-carbon Request for Single Stage - One 2022-06- Construction of store room at IDA / 60380 Post Limited Quotations (Non 18,700.00 0.00 Implementat 2021-11-04 2021-12-30 investments Quotations Envelope 28 Provincial Office for FD Bank-SPD) ion MNDP/ZIFLP/CW/007/2021 / Request for Pending Procurement of sheds for 2. Livelihood and low-carbon Request for Single Stage - One 2022-04- IDA / 60380 Post Limited Quotations (Non 66,000.00 0.00 Implementat 2021-08-25 2021-10-20 nuseries at Masupe, Mindola investments Quotations Envelope 18 Bank-SPD) ion ,Msipazi & Sinda for FD MNDP/ZIFLP/CW/006/2021 / Construction of 9 staff house Request for Bids - Pending at Kalindi (3) & Nchenche (6) 2. Livelihood and low-carbon Single Stage - One Small Works SPD 2022-07- IDA / 60380 Post Request for Bids Open - National 840,500.00 0.00 Implementat 2021-09-13 2021-09-18 2021-10-30 2021-11-29 2022-01-03 and 3 entry gates at investments Envelope (1 envelope 02 ion Chikomeni, Chakolwa & process) Changachanga GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MNDP/ZIFLP/GO/007/2018 / Motor Vehilcle(16)-CSA (1), Forestry(2) GMA(1), DNPW(2), UN Agencies Lands(1), NPU(4)/PPIU (5) IDA / 60380 1. Enabling environment Post Direct 800,000.00 570,832.96 Completed 2018-04-30 2018-04-30 2018-07-18 2018-04-30 2018-09-17 2018-04-30 2019-01-21 (Direct) REF:2.1a.1.5.1/2.1b.1.6/2.2.3 .1.16/2.2.3.2.14/2.2.3.3.3/2. 1c.4.3/3.1.5/3.2.5 MNDP/ZIFLP/GO/017/2018 / Procurement of Set of Soil 2. Livelihood and low-carbon Single Stage - One Laboratory equipment for IDA / 60380 Post Request for Bids Open - National 431,600.00 431,580.70 Signed 2018-06-30 2018-08-13 2018-07-05 2018-08-16 2018-10-12 2018-09-15 2019-02-18 2018-10-20 2019-05-02 2019-04-18 investments Envelope ZARI AWPB REF:(2.1a.2.8 to 2.1a.2.15) MNDP/ZIFLP/GO/004/2018 / Procurement of Agriculuture 2. Livelihood and low-carbon Request for Single Stage - One inputs(Seeds, Fertilizers)- IDA / 60380 Post Limited 47,800.00 20,401.13 Completed 2018-07-04 2018-09-05 2018-08-29 2018-11-18 2019-02-25 2018-12-04 investments Quotations Envelope Climate Smart Agriculture AWPB REF NOS;2.1a.1.3.1 MNDP/ZIFLP/GO/009/2018 / Procurement of materials for nurseries and tree planting - 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 25,000.00 7,073.72 Signed 2018-07-14 2018-08-26 2018-09-08 2018-11-23 2019-03-07 procure nurseries requisites investments Quotations Envelope etc, 30ha annually AWPB REF:2.1b.2.12 MNDP/ZIFLP/GO/011/2018 / Procurement of Quad bikes-2 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 6,400.00 0.00 Canceled 2018-07-21 2018-09-15 2019-03-14 Lukusuzi/Luambe AWPB investments Quotations Envelope REF:2.2.3.1.14/2.2.3.2.12 MNDP/ZIFLP/GO/012/2018 / Procurement of Field Equipment(rain coats,tents, 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 25,000.00 3,510.00 Completed 2018-07-07 2018-10-30 2018-09-01 2019-01-31 2019-02-28 2019-04-23 GPS, Camp beds for 30 WFOs)- investments Quotations Envelope Lukusuzi/LuambeAWPB REF:2.2.3.1.23/2.2.3.2.20 MNDP/ZIFLP/GO/013/2018 / Procurement 1 x Equipment 2. Livelihood and low-carbon Request for Single Stage - One for Human Wildlife Conflict IDA / 60380 Post Limited 3,000.00 0.00 Canceled 2018-07-28 2018-09-22 2019-03-21 investments Quotations Envelope (fire crackers,blasting for Lukusuzi AWPB REF:2.2.2.2.2 Page 2 MNDP/ZIFLP/GO/014/2018 / Procurement of Equipment- 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 18,000.00 13,143.21 Completed 2018-07-14 2018-08-28 2018-09-08 2018-10-02 2019-03-07 2019-03-07 Server, 2 Laptops, 2 Desktops, investments Quotations Envelope 1 Projector AWPB REF:2.1c.4.4 MNDP/ZIFLP/GO/015/2018 / Procurement of 4 x Video/Still Camera and 2 x Audio Request for Single Stage - One IDA / 60380 3. Project management Post Limited 10,200.00 4,337.80 Signed 2018-07-07 2018-08-28 2018-09-01 2018-06-26 2019-02-28 recorder 2 x TVs for Quotations Envelope NPIU/PPIU AWPB REF:3.1.6/3.1.7/3.2.6/3.2.7 MNDP/ZIFLP/GO/001/2018 / Procurement of 9 x Motor bikes for Field Officers- Request for Single Stage - One IDA / 60380 1. Enabling environment Post Limited 54,600.00 0.00 Canceled 2018-07-07 2018-09-01 2019-02-28 District and Local Planning & Quotations Envelope 1 Lukusuzi N Park AWPB REF:1.1.4.1/2.2.3.1.15 MNDP/ZIFLP/GO/005/2018 / Under Procurement of Soil Doc kit 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 21,000.00 0.00 Implementati 2018-07-04 2019-02-18 2018-08-29 2019-02-25 for FTC and ZARI under CSA investments Quotations Envelope on AWPB REF No:2.1a.2.2 MNDP/ZIFLP/GO/016/2018 / Procurement of various equipment(Computers, Single Stage - One IDA / 60380 3. Project management Post Request for Bids Limited 122,000.00 0.00 Canceled 2018-04-30 2018-05-05 2018-06-16 2018-07-16 2018-08-20 2019-02-16 Printers and scanners for the Envelope NPIU/PPIU AWPB REF:3.1.4/3.2.4 MNDP/ZIFLP/PPG/G/001/201 Request for Single Stage - One 7 / Computers , Printers and IDA / 60380 3. Project management Post Limited 5,000.00 0.00 Canceled 2017-09-05 2017-10-31 2018-04-29 Quotations Envelope furniture MNDP/ZIFLP/GO/0016/2018 / Procurement of various equipment(Computers, Request for Single Stage - One IDA / 60380 3. Project management Post Limited 98,000.00 54,892.01 Signed 2018-05-05 2018-08-28 2018-06-30 2019-01-14 2018-12-27 2019-03-07 Printers and scanners for the Quotations Envelope NPIU/PPIU AWPB REF:3.1.4/3.2.4 MNDP/ZIFLP/GO/002/2018 / Procurement of various IT Equipment (Computers and GIS Software -District &Local Planning/ 3 x Single Stage - One Laptops,Plotter3x Handheld IDA / 60380 1. Enabling environment Post Request for Bids Limited 165,375.00 144,579.52 Signed 2018-04-30 2018-11-30 2018-05-05 2018-12-05 2018-06-16 2019-01-25 2018-07-16 2019-05-03 2018-08-20 2019-07-17 2019-02-16 2020-07-03 Envelope GPS and 1 1x Differential GPS/ CSA/furniture and computers for 9 districts - Frst)2.1b.2.12/2.1a.2.3- 2.6/2.1b.2.12 MNDP/ZIFLP/GOA/007/2018 Request for Single Stage - One / Motor Vehilcle (2)-NPU and IDA / 60380 3. Project management Post Limited 110,000.00 78,904.17 Completed 2018-04-06 2018-04-20 2018-06-01 2018-06-08 2018-11-28 2018-12-10 Quotations Envelope PPIU (REF: /3.1.5/3.2.5 MNDP/ZIFLP/GO/011A/2018 / Procurement of motor cycles- 2. Livelihood and low-carbon Request for Single Stage - One 2 Lukusuzi/Luambe AWPB IDA / 60380 Post Limited 11,400.00 9,992.81 Completed 2019-02-06 2018-10-30 2019-04-03 2019-01-30 2019-09-30 2019-03-21 investments Quotations Envelope REF:2.2.3.1.14/2.2.3.2.12/2.2 .3.1.15 MNDP/ZIFLP/GO/001A/2018 UN Agencies / procurement of 1 motor TF / A4645 1. Enabling environment Prior Direct 49,600.00 0.00 Canceled 2019-03-01 2019-03-01 2019-03-01 2019-03-01 (Direct) vehicle AWPB REF:1.1.4.1 MNDP/ZIFLP/GO/016/2019 / 2. Livelihood and low-carbon Request for Single Stage - One Procurement of Soil Doc kit IDA / 60380 Post Limited 9,000.00 28,700.00 Completed 2019-05-05 2019-02-18 2019-06-30 2019-05-14 2019-12-27 2019-08-21 investments Quotations Envelope for FTC AWPB REF No:2.1a.21 MNDP/ZIFLP/GO/001/2019 / UN Agencies Procurement of 5 motor TF / A4645 1. Enabling environment Prior Direct 275,000.00 217,572.88 Completed 2019-08-01 2019-06-06 2019-08-01 2019-09-30 2019-08-01 2019-08-29 2019-08-01 2020-01-06 (Direct) vehicles AWPB REF NO:1.1.3.1 MNDP/ZIFLP/GO/002/2019 / Request for Single Stage - One Procurement of A1 Plotter, TF / A4645 1. Enabling environment Post Limited 16,500.00 24,361.55 Terminated 2019-04-06 2019-07-02 2019-06-01 2019-08-29 2019-11-28 Quotations Envelope AWPB REF:1.1.3.2 MNDP/ZIFLP/GO/022/2019 / Procure Inventory Forest 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 30,000.00 24,080.98 Completed 2019-12-05 2019-08-21 2020-01-30 2019-10-21 2020-07-28 2020-02-12 Equipment AWPB investments Quotations Envelope REF:2.1b.1.2.1 MNDP/ZIFLP/GO/028/2019 / Procure Nursery shelter, Crop 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 38,600.00 10,872.68 Terminated 2019-05-06 2019-10-09 2019-07-01 2019-11-06 2019-12-28 protector AWPB 2.1b.1.2.1.5, investments Quotations Envelope 2.1b.1.2.1.6 MNDP/ZIFLP/GO/036/2019 / Procure Office Equipment & 2. Livelihood and low-carbon Request for Single Stage - One Furnishings AWPB IDA / 60380 Post Limited 42,900.00 7,587.52 Completed 2019-04-06 2019-06-03 2019-06-01 2019-07-10 2019-11-28 2019-07-20 investments Quotations Envelope REF:2.2.3.1.7,2.2.3.1.1.1,2.2. 3.2.1.1,2.2.3.5.1.0,2.2.2.2.2 MNDP/ZIFLP/GO/035/2019 / Procure Field Equipment and 2. Livelihood and low-carbon Single Stage - One Protective wear (rain coats, IDA / 60380 Post Request for Bids Open - National 220,000.00 62,375.46 Signed 2019-06-01 2019-06-12 2019-06-06 2019-07-18 2019-07-31 2019-08-17 2019-09-03 2019-09-21 2019-12-30 2020-03-19 investments Envelope camp beds etc) AWPB REF:2.2.3.1.1.0,2.2.3.2.1.1 MNDP/ZIFLP/GO/041/2019 / 2. Livelihood and low-carbon Request for Single Stage - One Equipment for HWC AWPB IDA / 60380 Post Limited 7,700.00 4,156.00 Completed 2019-04-06 2019-07-11 2019-06-01 2019-10-10 2019-11-28 2019-12-06 investments Quotations Envelope REF:2.2.2.2.2 MNDP/ZIFLP/GO/040/2019 / 2. Livelihood and low-carbon Request for Single Stage - One Office Equipment (Computers IDA / 60380 Post Limited 5,500.00 0.00 Canceled 2019-04-06 2019-06-01 2019-11-28 investments Quotations Envelope etc) AWPB REF: 2.2.3.3.5 Page 3 MNDP/ZIFLP/GO/012A/2019 / Procurement of 62 motor 2. Livelihood and low-carbon Single Stage - One IDA / 60380 Post Request for Bids Open - National 306,900.00 0.00 Canceled 2019-05-30 2019-06-04 2019-07-16 2019-08-15 2019-09-19 2020-03-17 cycles AWPB REF investments Envelope NO:2.1a.1.5.1 MNDP/ZIFLP/GO/033/2019 / 2. Livelihood and low-carbon Single Stage - One Grader and Trailor AWPB IDA / 60380 Post Request for Bids Open - National 119,000.00 0.00 Canceled 2019-05-01 2019-05-06 2019-06-17 2019-07-17 2019-08-21 2020-02-17 investments Envelope REF2.2.3.1.8, 2.2.3.1.9 MNDP/ZIFLP/GO/030/2019 / Procure Tractor and Plough 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 60,400.00 0.00 Canceled 2019-05-06 2019-07-01 2019-12-28 discs AWPB REF: 2.1b.1.2.1.7, investments Quotations Envelope 2.1b.1.2.1.8, MNDP/ZIFLP/GO/023/2019 / Procurement of Assorted seeds, D 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 20,525.00 0.00 Canceled 2019-05-05 2019-06-30 2019-12-27 Compound,polythene investments Quotations Envelope pots,chemicals,Sprayers AWPB REF:2.1b.1.2.10,2.1b.1.2.11,2 .1b.1.2.13,2.1b.1.2.14 MNDP/ZIFLP/GO/014/2019 / Procure Equipment 2 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 3,270.00 0.00 Canceled 2019-05-06 2019-07-01 2019-12-28 Desktops and Projector AWPB investments Quotations Envelope REF:2.1c.4.5 and 2.Ia.1.5.4 MNDP/ZIFLP/GO/011/2019 / 2. Livelihood and low-carbon Request for Single Stage - One Procurement of Protective IDA / 60380 Post Limited 30,000.00 0.00 Canceled 2019-04-04 2019-05-30 2019-11-26 investments Quotations Envelope clothing-AWPB REF: 2.1a.1.3.5 MNDP/ZIFLP/GO/010/2019 / 2. Livelihood and low-carbon Request for Single Stage - One Herbicides, chakas hoes and IDA / 60380 Post Limited 20,000.00 0.00 Canceled 2019-07-06 2019-08-31 2020-02-27 investments Quotations Envelope rippers, AWPB REF: 2.1a 1.3.4 MNDP/ZIFLP/GO/009/2019 / Agro forestry trees seed- 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 15,048.00 0.00 Canceled 2019-07-06 2019-08-31 2020-02-27 FFS/LF/FF-AWPB REF: 2.1a investments Quotations Envelope 1.3.3 MNDP/ZIFLP/GO/007/2019 / Inputs-FFS seeds, fertlizer, 2. Livelihood and low-carbon Single Stage - One lead farmers seeds and IDA / 60380 Post Request for Bids Open - National 449,540.00 0.00 Canceled 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-21 2020-04-18 investments Envelope fertilizer -AWPB REF: 2.1a 1.3.1-1.3.2 MNDP/ZIFLP/GO/014A/2019 / Procure Equipment 2 Desktops (lands) Projector 2. Livelihood and low-carbon Request for Single Stage - One (CSA),Office Equipment IDA / 60380 Post Limited 8,770.00 9,378.62 Completed 2019-06-04 2019-06-13 2019-07-30 2019-11-06 2020-01-26 2019-11-08 investments Quotations Envelope (Computers) DNPW AWPB REF:2.1c.4.5 and 2.Ia.1.5.4,2.2.3.3.5 MNDP/ZIFLP/GO/012B/2019 / Procurement of 62 motor cycles,Procure Tractor and Plough disc,Grader and Trailor 2. Livelihood and low-carbon Single Stage - One IDA / 60380 Post Request for Bids Open - National 487,200.00 285,778.58 Signed 2019-05-30 2019-06-12 2019-06-04 2019-07-16 2019-07-19 2019-08-15 2019-08-16 2019-09-19 2020-02-13 2020-03-17 2020-10-13 AWPB REF investments Envelope NO:2.1a.1.5.1,2.1b.1.2.1.7, 2.1b.1.2.1.8,2.2.3.1.8, 2.2.3.1.9 MNDP/ZIFLP/GO/007A/2019 / Inputs-FFS seeds, fertlizer, lead farmers seeds and fertilizer-CSA (Assorted 2. Livelihood and low-carbon Single Stage - One seeds, D IDA / 60380 Post Request for Bids Open - National 470,065.00 165,132.34 Signed 2019-07-01 2019-10-01 2019-07-06 2019-08-17 2019-08-14 2019-09-16 2019-09-01 2019-10-21 2019-10-31 2020-04-18 2019-11-22 investments Envelope Compound,polythene pots,chemicals,Sprayers-FD) - AWPB REF: 2.1a 1.3.1- 1.3.2,2.1b.1.2.10,2.1b.1.2.11, 2.1b.1.2.13,2.1b.1.2.14 MNDP/ZIFLP/GO/009A/2019 / Agro forestry trees seed,Procurement of 2. Livelihood and low-carbon Request for Single Stage - One Protective clothing,Herbicides, IDA / 60380 Post Limited 65,048.00 2,917.68 Completed 2019-07-06 2019-09-20 2019-08-31 2019-09-20 2020-02-27 2019-09-20 investments Quotations Envelope chakas hoes and rippers- FFS/LF/FF-AWPB REF: 2.1a 1.3.3,2.1a.1.3.5,2.1a 1.3.4 MNDP/ZIFLP/GO/050/2019 / Equipment (soil mapping 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 8,128.00 7,330.87 Signed 2019-06-04 2019-04-16 2019-07-30 2019-04-30 2020-01-26 2019-05-08 preparatory) -AWPB REF: 2.1a investments Quotations Envelope 2.2 & 2.1a.2.10 MNDP/ZIFLP/GO/051/2019 / 2. Livelihood and low-carbon Single Stage - One Chemicals (soil sample IDA / 60380 Post Request for Bids Open - National 110,300.00 71,693.05 Signed 2019-05-30 2019-06-14 2019-06-04 2019-07-16 2019-07-19 2019-08-15 2019-08-12 2019-09-19 2019-12-30 2020-03-17 investments Envelope analysis) -AWPB REF: 2.1a 2.5 MNDP/ZIFLP/GO/043/2019 / Procure Equipment of 2 multi Request for Single Stage - One IDA / 60380 3. Project management Post Limited 1,540.00 763.84 Completed 2019-06-04 2019-06-19 2019-07-30 2019-06-26 2020-01-26 2019-06-26 functional color printers- Quotations Envelope AWPB REF:3.1.3 and 3.2.4 MNDP/ZIFLP/GO/046/2019 / Request for Single Stage - One 2 TV sets-AWPB REF: 3.1.5 IDA / 60380 3. Project management Post Limited 2,200.00 1,888.25 Signed 2019-07-05 2019-06-20 2019-08-30 2019-06-24 2020-02-26 Quotations Envelope and 3.2.7 MNDP/ZIFLP/GO/049/2019 / Request for Single Stage - One IDA / 60380 3. Project management Post Limited 1,000.00 0.00 Canceled 2019-06-04 2019-07-30 2020-01-26 2 cameras-AWPB REF: 3.2.6 Quotations Envelope MNDP/ZIFLP/GO/047/2019 / Request for Single Stage - One Procure Microsoft Visio for IDA / 60380 3. Project management Post Limited 1,000.00 368.06 Signed 2019-06-04 2019-07-31 2019-07-30 2019-07-31 2020-01-26 Quotations Envelope M&E-AWPB REF: 3.2.15 MNDP/ZIFLP/GO/053/2019 / Equipment for Digitization 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 25,000.00 75,786.52 Completed 2019-08-05 2019-06-27 2019-09-30 2019-08-01 2020-03-28 2019-10-07 Program (scanners, computers investments Quotations Envelope & Printers)-AWPB REF:2.1c.2.1 Page 4 MNDP/ZIFLP/GO/054/2019 / Revenue Improvement 2. Livelihood and low-carbon Request for Single Stage - One Equipment (Solar kits,laptops, IDA / 60380 Post Limited 10,000.00 16,292.48 Completed 2019-08-05 2019-07-02 2019-09-30 2019-08-01 2020-03-28 2019-12-16 investments Quotations Envelope routers & printers)-AWPB REF: 2.2.1.1 MNDP/ZIFLP/GO/056/2019 / Arc GIS Pro Desk Software for TF / A4645 1. Enabling environment Prior Direct Selection Direct 59,800.00 0.00 Canceled 2019-08-19 2019-09-29 2019-11-03 2020-05-01 Physical Planning for 5 users- AWPB REF: 1.1.3.5 MNDP/ZIFLP/GO/044/2019 / 2 Macrobook laptops-AWPB IDA / 60380 3. Project management Post Direct Selection Direct 6,000.00 0.00 Canceled 2019-05-30 2019-09-29 2019-11-03 2020-05-01 REF: 3.1.4 and 3.2.5 MNDP/ZIFLP/GO/044A/2019 Request for Single Stage - One / 2 Macrobook laptops-AWPB IDA / 60380 3. Project management Post Limited 6,000.00 5,751.11 Completed 2019-10-19 2019-10-28 2019-12-14 2019-11-06 2020-06-11 2020-12-24 Quotations Envelope REF: 3.1.4 and 3.2.5 MNDP/ZIFLP/GO/059/2019 / Procure Equipment of 3 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 98,500.00 97,666.00 Completed 2020-01-03 2020-03-10 2020-02-28 2020-05-12 2020-08-26 2020-05-29 tractors-AWPB REF:2.1b1.2.17 investments Quotations Envelope and 2.2.3.1.8 MNDP/ZIFLP/GO/057/2019 / 2. Livelihood and low-carbon Request for Single Stage - One Procurement of gases for ZARI- IDA / 60380 Post Limited 20,000.00 20,811.68 Signed 2019-12-05 2020-01-02 2020-01-30 2020-02-03 2020-07-28 investments Quotations Envelope AWPB REF: 2.1a 2.5 MNDP/ZIFLP/GO/058/2019 / Procurement of 1,400 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 15,000.00 28,796.71 Completed 2019-12-05 2019-12-16 2020-01-30 2020-02-03 2020-07-28 2020-08-05 improved cook stove AWPB investments Quotations Envelope 2.1b.2.3 MNDP/ZIFLP/GO/061/2019 / Procurement of Starter up Under 2. Livelihood and low-carbon Request for Single Stage - One packs (Agriculture Inputs) for IDA / 60380 Post Limited 52,000.00 0.00 Implementati 2020-04-06 2020-06-01 2020-11-28 investments Quotations Envelope the powered Irrigation on Schemes AWPB REF;2.1a.1.5.2 MNDP/ZIFLP/GO/001/2020 / Procurement of Smart Request for Single Stage - One TF / A4645 1. Enabling environment Post Limited 28,100.00 98,235.00 Completed 2020-04-06 2020-04-13 2020-06-01 2020-05-12 2020-11-28 2020-11-27 Inspectorate Kits (50 tablets) Quotations Envelope AWPB REF; 1.2.1.8 MNDP/ZIFLP/GO/008/2020 / Procure 2000 breeding stock for Nyanje fish farm and 2. Livelihood and low-carbon Request for Single Stage - One Chipata fish & fish feed ration IDA / 60380 Post Limited 26,000.00 0.00 Canceled 2020-05-15 2020-07-10 2021-01-06 investments Quotations Envelope formulations to 1500 fish farmers -AWBP 2.1a.3.3.5 & 2.1a.3.3.7- MNDP/ZIFLP/GO/009/2020 / Procure 15000 trees and 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 7,500.00 0.00 Canceled 2020-11-15 2021-01-10 2021-07-09 shrubs around ponds and investments Quotations Envelope rivers-AWPB 2.1a.3.3.6- MNDP/ZIFLP/GO/010/2020 / Procure internet and mobile based disease reporting systems (purchase of 75 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 52,000.00 0.00 Canceled 2020-04-06 2020-06-01 2020-11-28 smart phones, data server investments Quotations Envelope ,desk top computers & Procure backup power system AWPB2.1a.3.4.1- MNDP/ZIFLP/GO/011/2020 / Procure laboratory reagents, e coli isolation reagents & Vaccines for livestock (800 000 village chickens per year) 2. Livelihood and low-carbon Single Stage - One IDA / 60380 Post Request for Bids Open - National 150,000.00 68,845.96 Signed 2020-04-10 2020-05-15 2020-04-15 2020-05-27 2020-06-18 2020-06-26 2020-09-02 2020-07-31 2020-11-12 2021-01-27 & Screening services for investments Envelope livestock and fish diseasesAWPB 2.1a.3.4.3,2.1a.3.4.4 &2.1a.3.4.5- MNDP/ZIFLP/GO/013/2020 / Procure Packaging and 2. Livelihood and low-carbon Request for Single Stage - One refridgeration equipment IDA / 60380 Post Limited 18,000.00 0.00 Canceled 2021-04-15 2021-06-10 2021-12-07 investments Quotations Envelope 18000 for Poultry and Goat meat-AWPB 2.1a.3.5.2.3- MNDP/ZIFLP/GO/016/2020 / 2. Livelihood and low-carbon Request for Single Stage - One Office furniture for forestry IDA / 60380 Post Limited 9,147.00 6,839.75 Completed 2020-05-05 2020-04-23 2020-06-30 2020-05-29 2020-12-27 2020-09-07 investments Quotations Envelope AWPB REF;2.1b.1.2.4 MNDP/ZIFLP/GO/015/2020 / Procurement of Video Request for Single Stage - One IDA / 60380 3. Project management Post Limited 13,000.00 13,922.13 Completed 2020-04-11 2020-04-01 2020-06-06 2020-04-28 2020-12-03 2020-06-16 Conference Equipment for Quotations Envelope Lusaka & Chipata Offices MNDP/ZIFLP/GO/021/2020 / 2. Livelihood and low-carbon Request for Single Stage - One Procurement of fertilizers for IDA / 60380 Post Limited 12,200.00 0.00 Canceled 2020-08-08 2020-10-03 2021-04-01 investments Quotations Envelope field trials MNDP/ZIFLP/GO/017/2020 / Procurement of Agriculture Inputs -for lead farmers seeds 2. Livelihood and low-carbon IDA / 60380 Post Request for Bids Open - National 279,247.12 142,162.27 Completed 2020-04-30 2020-05-08 2020-04-30 2021-02-09 2020-04-30 2020-06-12 2020-04-30 2020-06-19 2020-04-30 2020-09-03 2020-04-30 2020-09-16 & schools for 2020/21 investments season AWPB REF; 2.1a.1.3.1- 2.1a.1.3.2 & 2.1a.1.3.4 MNDP/ZIFLP/GO/020/2020 / Procurement of vehicles (3 2. Livelihood and low-carbon UN Agencies 4x4 station wagon and pick IDA / 60380 Prior Direct 371,000.00 443,610.31 Signed 2020-06-30 2020-05-03 2020-07-05 2020-05-04 2020-08-09 2020-07-08 2021-02-05 investments (Direct) up, 1x15 ton Light truck, 1x truck & trailer) & 1x folk lift Page 5 MNDP/ZIFLP/GO/022/2020 / Procurement of Agroforestry 2. Livelihood and low-carbon Single Stage - One seedlings (Fidebia Albida and IDA / 60380 Post Request for Bids Limited 560,200.22 0.00 Canceled 2020-07-30 2020-08-04 2020-09-15 2020-10-15 2020-11-19 2021-05-18 investments Envelope Of Gliricidia Sepium) AWPB REF: MNDP/ZIFLP/GO/024/2020 / Procurement of crop protector 2. Livelihood and low-carbon Request for Single Stage - One Forest Department for IDA / 60380 Post Limited 18,800.00 18,600.21 Signed 2020-08-04 2020-04-20 2020-09-29 2020-06-29 2021-03-28 investments Quotations Envelope Chimutengu & Kaluwe forest reseves AWPB: 2.1b1.2.16 MNDP/ZIFLP/GO/023/2020 / Procurement of GPS for 2. Livelihood and low-carbon Request for Single Stage - One Department of National Parks IDA / 60380 Post Limited 5,000.00 4,408.78 Completed 2020-08-04 2020-04-19 2020-09-29 2020-05-27 2021-03-28 2020-08-06 investments Quotations Envelope & Wildlife (7) AWPB REF;2.1b.1.2.4 MNDP/ZIFLP/GO/025/2020 / Procurement of solar back Request for Single Stage - One IDA / 60380 3. Project management Post Limited 33,000.00 14,501.00 Completed 2020-05-16 2020-05-22 2020-07-11 2020-09-01 2021-01-07 2020-11-20 equipment for PPIU OFFICE Quotations Envelope AWPB REF; 3.2.18 MNDP/ZIFLP/GO/014/2020 / Procure Referegerated truck 2. Livelihood and low-carbon Request for Single Stage - One for poultry and goats , 4x4 IDA / 60380 Post Limited 110,000.00 0.00 Canceled 2021-04-15 2021-06-10 2021-12-07 investments Quotations Envelope motor vehicle- AWPB- 2.1a.3.5.2.3 & AWPB 2.1a.3.6.5 MNDP/ZIFLP/GO/006/2020 / Procure stock and materials to 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 15,000.00 0.00 Canceled 2020-05-15 2020-07-10 2021-01-06 support Creation of 1500 investments Quotations Envelope new ponds-AWPB2.1a.3.3.3- MNDP/ZIFLP/GO/007/2020 / Procure crops and/or poultry (Integration of fish culture 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 10,000.00 0.00 Canceled 2020-05-15 2020-07-10 2021-01-06 1000 hectares of crops investments Quotations Envelope amongst the 1500 farmers)- AWPB2.1a.3.3.4- MNDP/ZIFLP/GO/026/2020 / Procurement of office 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 7,300.00 7,538.75 Completed 2020-08-12 2020-04-23 2020-10-07 2020-05-29 2021-04-05 2020-11-04 furniture for Survey investments Quotations Envelope Department MNDP/ZIFLP/GO/037/2019 / 2. Livelihood and low-carbon Request for Single Stage - One Procure Patrol rations AWPB IDA / 60380 Post Limited 40,000.00 4,650.90 Completed 2020-10-02 2021-03-01 2020-11-27 2021-03-16 2021-05-26 2021-04-13 investments Quotations Envelope REF:2.2.3.1.1.2,2.2.3.2.1.2 MNDP/ZIFLP/GO/012/2020 / Procure Inputs for the 14 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 32,500.00 0.00 Canceled 2020-09-02 2020-10-28 2021-04-26 farmer field schools-AWPB investments Quotations Envelope 2.1a.3.5.3.1- MNDP/ZIFLP/GO/005/2020 / Procure different drought 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 92,000.00 0.00 Canceled 2020-09-02 2020-10-28 2021-04-26 tolerant perennials (restore 4 investments Quotations Envelope 500 ha)-AWPB2.1a.3.2.1- MNDP/ZIFLP/GO/002/2020 / Supply and installation of 21 2. Livelihood and low-carbon Single Stage - One IDA / 60380 Post Request for Bids Open - National 449,400.00 0.00 Canceled 2020-08-31 2020-10-02 2020-09-05 2020-10-17 2020-11-16 2020-11-16 2020-12-21 2021-06-19 Solar powered cold storage investments Envelope facilities AWPB REF;2.1a.1.5.2 MNDP/ZIFLP/GO/028/2020 / 2. Livelihood and low-carbon IDA / 60380 Post Direct Selection Direct 4,500.00 0.00 Canceled 2020-09-30 2020-09-22 2020-10-05 2020-11-09 2021-05-08 Software for Livestock investments MNDP/ZIFLP/GO/027/2020 / Procurement of GPS and 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 6,800.00 10,927.20 Completed 2020-10-20 2021-03-24 2020-12-15 2021-05-17 2021-06-13 2021-06-22 Digital cameras for Forestry investments Quotations Envelope Department MNDP/ZIFLP/GO/030/2020 / Supply ,deliver, installation & commissioning of fetrilizer 2. Livelihood and low-carbon Single Stage - One blending equipmnet ( IDA / 60380 Post Request for Bids Open - National 495,000.00 0.00 Canceled 2020-11-09 2020-11-14 2020-12-26 2021-01-25 2021-03-01 2021-08-28 investments Envelope Complete list is in the comments and attached document) MNDP/ZIFLP/GO/031/2020 / Procurement of Raw Materials (Urea-1320 tons, Phosphate 2. Livelihood and low-carbon Single Stage - One IDA / 60380 Prior Request for Bids Open - International 2,586,240.00 0.00 Canceled 2020-12-30 2021-01-04 2021-02-15 2021-03-17 2021-04-21 2021-10-18 4050 tons, MOP 1260 tons, investments Envelope Boron 142 tons & Zinx 71 tons.) MNDP/ZIFLP/GO/032/2020 / Procurement of materials for 2. Livelihood and low-carbon Request for Single Stage - One bee keeping training for IDA / 60380 Post Limited 32,000.00 14,111.37 Signed 2021-01-15 2021-01-25 2021-03-12 2021-04-23 2021-09-08 investments Quotations Envelope Forestry Department AWPB 2.1b1.3.3 MNDP/ZIFLP/GO/035/2020 / Procurement of materials for 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 2,400.00 2,934.06 Completed 2021-01-15 2020-12-21 2021-03-12 2021-01-14 2021-09-08 2021-02-08 Office renovations at DNPW investments Quotations Envelope AWPB 2.2.3.16 & 2.2.3.2.9 MNDP/ZIFLP/GO/033/2020 / 2. Livelihood and low-carbon Request for Single Stage - One Procurement of inputs for IDA / 60380 Post Limited 9,100.00 6,586.05 Signed 2021-01-15 2020-12-21 2021-03-12 2021-01-14 2021-09-08 investments Quotations Envelope resttlement in Lundazi MNDP/ZIFLP/GO/034/2020 / Procurement of Smart Tablets Request for Single Stage - One TF / A4645 1. Enabling environment Post Limited 31,000.00 2,900.00 Signed 2021-02-04 2021-02-15 2021-04-01 2021-04-23 2021-09-28 for ZIFLP for Data Collection & Quotations Envelope Internert MIFIs MNDP/ZIFLP/GO/039/2020 / Procurement of materials for 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 17,500.00 19,482.05 Completed 2021-02-04 2021-03-14 2021-04-01 2021-04-21 2021-09-28 2021-05-20 Forest Reserve Management investments Quotations Envelope AWPB 2.1b1.5.2 Page 6 MNDP/ZIFLP/GO/040/2020 / Procurement of Patrol 2. Livelihood and low-carbon Request for Single Stage - One Equipment(camera lenses, IDA / 60380 Post Limited 1,255.00 1,633.70 Completed 2021-02-04 2020-12-23 2021-04-01 2021-01-14 2021-09-28 2021-02-02 investments Quotations Envelope bags and memory cards) AWPB 2.2.3.2.10 and 11 MNDP/ZIFLP/GO/041/2020 / 2. Livelihood and low-carbon Request for Single Stage - One Procurement of 2 laptops for IDA / 60380 Post Limited 2,400.00 2,311.46 Completed 2021-02-04 2020-12-23 2021-04-01 2021-01-12 2021-09-28 2021-03-03 investments Quotations Envelope Energy Department AWPB MNDP/ZIFLP/GO/004B/2021 / Procure inputs for setting up sustainable livestock pastures, 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 52,278.00 57,099.10 Signed 2021-03-05 2021-03-18 2021-04-30 2021-05-17 2021-10-27 fodder banks, rangeland and investments Quotations Envelope water harvesting systems- AWPB 2.1a.3.1.2 MNDP/ZIFLP/GO/003/2020 / Procure 807 LUs of breeds 2. Livelihood and low-carbon Single Stage - One IDA / 60380 Post Request for Bids Open - National 242,450.00 0.00 Canceled 2020-05-17 2020-05-08 2020-05-22 2020-07-03 2020-08-02 2020-09-06 2021-03-05 resilient to climate change- investments Envelope AWPB 2.1a.3.1.1 - MNDP/ZIFLP/GO/004/2020 / Procure inputs for setting up sustainable livestock pastures, 2. Livelihood and low-carbon Single Stage - One IDA / 60380 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2020-04-15 2020-05-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-02-01 fodder banks, rangeland and investments Envelope water harvesting systems- AWPB 2.1a.3.1.2 MNDP/ZIFLP/GO/003B/2021 / Procure 807 LUs of breeds 2. Livelihood and low-carbon Single Stage - One IDA / 60380 Post Request for Bids Limited 187,974.29 152,428.19 Signed 2021-02-28 2021-03-17 2021-03-05 2021-03-18 2021-04-16 2021-04-19 2021-05-16 2021-06-20 2021-07-28 2021-12-17 resilient to climate change- investments Envelope AWPB 2.1a.3.1.1 - MNDP/ZIFLP/GO/001/2021 / Under 2. Livelihood and low-carbon Request for Single Stage - One Procurement of materials for IDA / 60380 Post Limited 24,650.00 0.00 Implementati 2021-08-05 2021-09-30 2022-03-29 investments Quotations Envelope nurseries establishment on MNDP/ZIFLP/GO/005/2021 / Procurement, licensing and Pending operation of a Drone for land Request for Single Stage - One TF / A4645 1. Enabling environment Post Limited 70,000.00 0.00 Implementati 2021-08-25 2021-10-20 2022-04-18 use planning and natural Quotations Envelope on resource management for Physical Planning MNDP/ZIFLP/GO/006/2021 / Pending Procurement of safety 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 27,566.00 0.00 Implementati 2021-09-18 2021-11-13 2022-05-12 equipment & camping investments Quotations Envelope on equipment for FD MNDP/ZIFLP/GO/008/2021 / Pending Procureemnt of disc harrows, 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 11,770.00 0.00 Implementati 2021-09-04 2021-10-30 2022-04-28 disc ploughs & pruning saw investments Quotations Envelope on for FD MNDP/ZIFLP/GO/009/2021 / Pending Procureemnt of 19 motor 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 67,925.00 0.00 Implementati 2021-08-25 2021-10-20 2022-04-18 cycles for community reach investments Quotations Envelope on out for FD MNDP/ZIFLP/GO/013/2021 / Pending 2. Livelihood and low-carbon Request for Single Stage - One Equipment for weather station TF / A4646 Post Limited 50,000.00 0.00 Implementati 2021-09-04 2021-10-30 2022-04-28 investments Quotations Envelope for DNPW on MNDP/ZIFLP/GO/014/2021 / Pending Uniforms for Officers at 2. Livelihood and low-carbon Request for Single Stage - One TF / A4646 Post Limited 76,765.00 0.00 Implementati 2021-09-04 2021-10-30 2022-04-28 Luambe & Lukusuzi National investments Quotations Envelope on Parks MNDP/ZIFLP/GO/015/2021 / Pending Equipment & Furnishing for 2. Livelihood and low-carbon Request for Single Stage - One TF / A4646 Post Limited 30,000.00 0.00 Implementati 2021-09-04 2021-10-30 2022-04-28 DNPW for Lukusuzi & Luambe investments Quotations Envelope on National Parks MNDP/ZIFLP/GO/017/2021 / Pending 2. Livelihood and low-carbon Request for Single Stage - One Equipment for implimentation TF / A4646 Post Limited 4,200.00 0.00 Implementati 2021-09-04 2021-10-30 2022-04-28 investments Quotations Envelope of fire management plan on MNDP/ZIFLP/GO/018/2021 / Pending Procurement and distribution 2. Livelihood and low-carbon Single Stage - One IDA / 60380 Post Request for Bids Limited 209,881.00 0.00 Implementati 2021-08-20 2021-08-25 2021-10-06 2021-11-05 2021-12-10 2022-06-08 of inputs -FFS & LFS (Province) investments Envelope on for Agric MNDP/ZIFLP/GO/002/2021 / Procurement of office equipment for DMT, GIS Work Pending Request for Single Stage - One Station for 9 districts, ICT for IDA / 60380 1. Enabling environment Post Limited 70,340.00 0.00 Implementati 2021-08-25 2021-10-20 2022-04-18 Quotations Envelope DNPW for network & Control on Room and smart phones & rechargeable torches for HWC) MNDP/ZIFLP/GO/003/2021 / Pending 2. Livelihood and low-carbon Request for Single Stage - One Procument of 300 Tablets (14 TF / A4645 Post Limited 90,000.00 0.00 Implementati 2021-07-24 2021-09-18 2022-03-17 investments Quotations Envelope Districts, 239 camps etc) on MNDP/ZIFLP/GO/011/2021 / Pending PPE (safety boots, work suits 2. Livelihood and low-carbon Request for Single Stage - One TF / A4646 Post Limited 10,340.00 0.00 Implementati 2021-09-18 2021-11-13 2022-05-12 and rain coats) & fire crackers investments Quotations Envelope on for HWC -DNPW NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7 MNDP/ZIFLP/NC/003/2018 / Information, Communication Single Stage - One and Education Activities - TF / A4646 1. Enabling environment Post Request for Bids Limited 20,000.00 0.00 Canceled 2018-04-30 2018-05-05 2018-06-16 2018-07-16 2018-08-20 2019-02-16 Envelope Radio programs etc AWPB REF:1.2.2.4 MNDP/ZIFLP/NC/018/2018 / Single Stage - One Payroll Package AWPB IDA / 60380 3. Project management Post Request for Bids Limited 20,000.00 0.00 Canceled 2018-05-01 2018-05-06 2018-06-17 2018-07-17 2018-08-21 2019-02-17 Envelope REF:3.1.10 MNDP/ZIFLP/NC/006/2018 / Procurement of Field Soil 2. Livelihood and low-carbon Request for Single Stage - One samples, lab tests and soil IDA / 60380 Post Limited 29,000.00 0.00 Canceled 2018-07-14 2018-09-08 2019-03-07 investments Quotations Envelope fertility mapping under CSA AWPB REF NO:2.1a.2.1 MNDP/ZIFLP/GO/010/2018 / Printing of guidelines Request for Single Stage - One (Community forest TF / A4645 1. Enabling environment Post Limited 3,000.00 2,973.42 Signed 2018-07-07 2018-11-04 2018-09-01 2018-12-18 2019-02-28 Quotations Envelope Management guidelines) AWPB REF:2.1b.1.3 MNDP/ZIFLP/NC/020/2018 / Supply and installation of Request for Single Stage - One IDA / 60380 3. Project management Post Limited 10,000.00 0.00 Canceled 2018-07-07 2018-09-01 2019-02-28 internet services for PPIU Quotations Envelope Offices AWPB REF:3.2.11 MNDP/ZIFLP/NC/019/2018 / Request for Single Stage - One Accounting Package AWPB IDA / 60380 3. Project management Post Limited 20,000.00 16,534.73 Signed 2018-08-28 2018-08-27 2018-10-23 2018-10-02 2019-04-21 Quotations Envelope REF:3.1.11/3.2.10 MNDP/ZIFLP/NC/0020/2018 / Supply and installation of Request for Single Stage - One IDA / 60380 3. Project management Post Limited 20,000.00 3,632.67 Signed 2018-08-06 2018-08-21 2018-10-01 2019-02-06 2019-03-30 internet services for NPIU & Quotations Envelope PPIU Offices AWPB REF:3.2.11 MNDP/ZILFP/NC/011/2018 / Mapping of informal 2. Livelihood and low-carbon Single Stage - One IDA / 60380 Prior Request for Bids Open - National 325,000.00 0.00 Canceled 2018-07-16 2018-07-21 2018-09-01 2018-10-01 2018-11-05 2019-05-04 agricultural propertiesAWPB investments Envelope REF;2.1c.2.2 MNDP/ZIFLP/NC/018A/2018 Request for Single Stage - One / Payroll Package AWPB IDA / 60380 3. Project management Post Limited 20,000.00 1,717.36 Signed 2018-05-06 2018-08-28 2018-07-01 2018-10-01 2018-12-28 Quotations Envelope REF:3.1.10 MNDP/ZIFLP/NC/003A/2018 / Information, Communication and Education Activities - Request for Single Stage - One TF / A4645 1. Enabling environment Post Limited 40,000.00 37,357.43 Signed 2018-09-04 2018-08-13 2018-10-30 2019-02-08 2019-04-28 Radio programs etc AWPB Quotations Envelope REF:1.2.2.4, 2.1B.6.6, 2.2.3.5.3, 2.2.3.4.4 MNDP/ZIFLP/NC/003/2019 / 2. Livelihood and low-carbon Request for Single Stage - One TV and Radio programs-AWPB IDA / 60380 Post Limited 10,450.00 1,986.58 Completed 2019-05-05 2019-10-26 2019-06-30 2018-11-05 2019-12-27 2018-12-07 investments Quotations Envelope REF: 2.1a.1.4.1-2.1a 1.4.2 MNDP/ZIFLP/NC/004/2019 / Printing of visibility and 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 4,400.00 215.34 Completed 2019-05-05 2019-12-09 2019-06-30 2019-12-17 2019-12-27 2020-03-02 promotional materials AWPB investments Quotations Envelope REF:2.1a 1.4.3 MNDP/ZIFLP/NCS/010 / 2. Livelihood and low-carbon Single Stage - One Digitization of all cadastral IDA / 60380 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2018-11-28 2018-12-03 2018-12-26 2019-01-14 2019-01-18 2019-02-13 2019-03-20 2019-09-16 investments Envelope maps AWPB REF;2.1c.2.1 MNDP/ZIFLP/NC/001/2019 / Printing of Final IDPs, Request for Single Stage - One Safeguards instruments and IDA / 60380 1. Enabling environment Post Limited 30,000.00 8,101.87 Signed 2019-12-05 2019-07-19 2020-01-30 2019-08-29 2020-07-28 Quotations Envelope DNPW Policy REF:1.1.2.5,1.1.3.8, 2.2.1.2 MNDP/ZIFLP/NC/008A/2018 Under / Procurement of Post Harvest 2. Livelihood and low-carbon IDA / 60380 Post Force Account Direct 80,480.00 0.00 Implementati 2019-04-30 2020-04-21 2019-04-30 2019-04-30 2019-04-30 handling (Metal silos for investments on demo) REF;2.1a 4.1 MNDP/ZIFLP/NC/011/2019 / Training of staff in Land Under 2. Livelihood and low-carbon Degradation Surveillance IDA / 60380 Prior Direct Selection Direct 25,520.00 0.00 Implementati 2019-11-01 2020-01-14 2019-11-06 2020-02-04 2019-12-11 2020-06-08 investments Framework ( ICRAF model) on AWPB REF No:2.1a.2.10 MNDP/ZIFLP/NC/015/2019 / Preparation of Environmental 2. Livelihood and low-carbon Project Brief for ZEMA IDA / 60380 Prior Force Account Direct 4,000.00 0.00 Canceled 2020-01-15 2020-01-20 2020-02-24 2020-08-22 investments approval of Project/sAWPB REF;2.1a.1.5.2 MNDP/ZIFLP/NC/006/2019 / 2. Livelihood and low-carbon Request for Single Stage - One Creation of loop roads AWPB IDA / 60380 Post Limited 78,700.00 0.00 Canceled 2020-07-05 2020-08-30 2021-02-26 investments Quotations Envelope REF2.2.3.1.5,2.2.3.2.7 MNDP/ZIFLP/NC/008/2019 / Procure Aerial Survey services 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 51,000.00 0.00 Canceled 2020-10-02 2020-11-27 2021-05-26 AWPB REF:2.2.3.1.1.4, investments Quotations Envelope 2.2.3.2.1.3 MNDP/ZIFLP/NC/002B/2020 / Provision of transportation( 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 36,000.00 15,468.34 Completed 2020-10-05 2020-11-22 2020-11-30 2021-01-05 2021-05-29 2021-03-01 loading & offloading inclusive) investments Quotations Envelope of seedlings-Lot 1 MNDP/ZIFLP/NC/009/2019 / Printing of handbooks, 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 2,920.00 0.00 Canceled 2020-09-02 2020-10-28 2021-04-26 brochures & reports AWPB investments Quotations Envelope REF: 2.1a 2.7 MNDP/ZIFLP/NC/001/2020 / Procure Advertisement 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 2,000.00 0.00 Canceled 2020-09-25 2020-11-20 2021-05-19 Services for poultry and goat investments Quotations Envelope Market-AWPB 2.1a.3.5.2.3- Page 8 Under MNDP/ZIFLP/NC/010/2020 / Request for Single Stage - One TF / A4645 1. Enabling environment Post Limited 13,750.00 0.00 Implementati 2021-02-04 2021-04-01 2021-09-28 Printing of the final IDPs Quotations Envelope on MNDP/ZIFLP/NC/008/2020 / Hire of air craft for provision 2. Livelihood and low-carbon Request for Single Stage - One of services for Aerial Survey: IDA / 60380 Post Limited 27,700.00 0.00 Canceled 2020-09-04 2020-08-24 2020-10-30 2021-04-28 investments Quotations Envelope AWPB 2.2.3.2.13 and 2.2.3.1.14 MNDP/ZIFLP/NC/006/2020 / Provision of transportation( 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 6,000.00 0.00 Canceled 2020-10-05 2020-11-30 2021-05-29 loading & offloading inclusive) investments Quotations Envelope of seedlings-Lot 5 MNDP/ZIFLP/NC/004/2020 / Provision of transportation( 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 6,000.00 0.00 Canceled 2020-10-05 2020-11-30 2021-05-29 loading & offloading inclusive) investments Quotations Envelope of seedlings-Lot 3 MNDP/ZIFLP/NC/007/2020 / Provision of transportation( 2. Livelihood and low-carbon Request for Single Stage - One TF / A3169 Post Limited 6,000.00 0.00 Canceled 2020-10-05 2020-11-30 2021-05-29 loading & offloading inclusive) investments Quotations Envelope of seedlings-Lot 6 MNDP/ZIFLP/NC/003/2020 / Provision of transportation( 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 6,000.00 0.00 Canceled 2020-10-05 2020-11-30 2021-05-29 loading & offloading inclusive) investments Quotations Envelope of seedlings-Lot 2 MNDP/ZIFLP/NC/005/2020 / Provision of transportation( 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 6,000.00 0.00 Canceled 2020-10-05 2020-11-30 2021-05-29 loading & offloading inclusive) investments Quotations Envelope of seedlings-Lot 4 MNDP/ZIFLP/NC/007/2021 / Pending Conducting of aerial survey in 2. Livelihood and low-carbon Request for Single Stage - One TF / A4646 Post Limited 40,000.00 0.00 Implementati 2021-11-04 2021-12-30 2022-06-28 Luambe & Lukusuzi National investments Quotations Envelope on Parks for DNPW MNDP/ZIFLP/NC/002/2021 / Project visibility materials Pending (signage posters FFS & 2. Livelihood and low-carbon Request for Single Stage - One IDA / 60380 Post Limited 86,000.00 0.00 Implementati 2021-11-04 2021-12-30 2022-06-28 Tshirts for LF) & Printing of investments Quotations Envelope on Manuals & other IEC materials for 10755 LF for Agric MNDP/ZIFLP/NC/001/2021 / Printing of safeguards Pending Request for Single Stage - One instruments under Emission IDA / 60380 1. Enabling environment Post Limited 27,050.00 0.00 Implementati 2021-11-04 2021-12-30 2022-06-28 Quotations Envelope Reduction & policy briefs for on Land Component MNDP/ZIFLP/NC/005/2021 / Printing of visibility materials ( brochures, posters, stickers Pending 2. Livelihood and low-carbon Request for Single Stage - One and calendars) for FD & IDA / 60380 Post Limited 40,000.00 0.00 Implementati 2021-09-18 2021-11-13 2022-05-12 investments Quotations Envelope visibility materials (GMP, on brochures, posters, stickers and calendars) for DNPW CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MNDP/ZIFLP/CS/008/2018 / Develop systems to manage 2. Livelihood and low-carbon Quality And Cost- IDA / 60380 Prior Open - International 365,000.00 0.00 Canceled 2018-06-01 2018-12-11 2018-06-22 2018-12-19 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 data on land rights AWPB investments Based Selection REF;2.1c.1 MNDP/ZIFLP/CS/003/2018 / Support updating of District situation anazlysis reports in Katete,Petauke,Chipata,Nyimb Consultant a nad Cadiza and completion TF / A4645 1. Enabling environment Post Qualification Open - National 210,000.00 0.00 Canceled 2018-07-09 2018-07-30 2018-09-12 2018-10-12 2018-11-16 2019-05-15 of DSA in Sinda and Vubwi Selection and support landuse planning(harmonizing the data on land use from all sources)AWPB REF;1.1.2.4 MNDP/ZIFLP/CS/004/2018 / Conduct the GHG Emission Quality And Cost- TF / A4645 1. Enabling environment Prior Open - International 430,000.00 0.00 Canceled 2018-05-01 2018-05-22 2018-07-05 2018-08-02 2018-09-01 2018-10-06 2018-11-10 2019-11-10 Baseline Study AWPB Based Selection REF;1.2.1.1 MNDP/ZIFLP/CS/006/2018 / Development of a SESA, Quality And Cost- TF / A4645 1. Enabling environment Post Open - National 200,000.00 200,000.00 Signed 2018-04-30 2018-02-07 2018-05-21 2018-07-04 2018-08-28 2018-08-01 2018-10-05 2018-08-31 2018-10-11 2018-10-05 2019-04-23 2018-11-09 2019-07-16 2019-11-09 updatingESMF and other Based Selection social safeguards AWPB REF;1.2.2.5 MNDP/ZIFLP/CS/007/2018 / Quality And Cost- Develop ERPD AWPB TF / A4645 1. Enabling environment Prior Open - International 500,000.00 0.00 Canceled 2018-06-01 2018-06-22 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 Based Selection REF;1.2.2.8 MNDP/ZIFLP/CS/009/201818 Consultant 2. Livelihood and low-carbon / Clarification of ownership IDA / 60380 Post Qualification Open - National 150,000.00 0.00 Canceled 2018-07-09 2018-07-30 2018-09-12 2018-10-12 2018-11-16 2019-05-15 investments Rights AWPB REF;2.1c.2 Selection MNDP/ZIFLP/PPG/CS/002/20 Least Cost IDA / 60380 3. Project management Post Open - National 5,000.00 0.00 Canceled 2017-12-31 2018-01-21 2018-03-06 2018-04-03 2018-05-03 2018-06-07 2018-07-12 2019-01-08 18 / Audit services Selection MNDP/ZIFLP/CS/033/2018 / Consultant Conduct the ZIFLP ( socia- TF / A4645 1. Enabling environment Post Qualification Open - National 150,000.00 0.00 Canceled 2018-06-11 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-04-17 economic) baseline study Selection AWPB REF:1.2.1.2 Page 9 MNDP/ZIFLP/CS/033A/2018 / Completion of customary Consultant 2. Livelihood and low-carbon rights recording USAID - IDA / 60380 Post Qualification Open - National 150,000.00 0.00 Canceled 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 investments supported pilot -AWPB REF Selection ;2.1c.3.5(CHIPATA) MNDP/ZIFLP/CS/034B/2018 / Completion of customary Consultant 2. Livelihood and low-carbon rights recording USAID - IDA / 60380 Post Qualification Open - National 100,000.00 0.00 Canceled 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 investments supported pilot Selection (PETAUKE)AWPB REF ;2.1c.3.5 MNDP/ZIFLP/CS/004A/2018 / Conduct the GHG Emission 2. Livelihood and low-carbon Quality And Cost- TF / A4645 Post Open - International 430,000.00 112,040.00 Signed 2019-04-01 2019-03-18 2019-04-22 2019-04-23 2019-06-05 2019-08-02 2019-07-03 2019-09-09 2019-08-02 2019-10-03 2019-09-06 2019-11-04 2019-10-11 2019-12-26 2020-10-10 Baseline Study AWPB investments Based Selection REF;1.2.1.1 MNDP/ZIFLP/CS/007A/2018 2. Livelihood and low-carbon Quality And Cost- / Develop ERPD AWPB TF / A4645 Post Open - International 500,000.00 0.00 Canceled 2019-04-01 2019-03-15 2019-04-22 2019-04-23 2019-06-05 2019-08-02 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 investments Based Selection REF;1.2.2.8 MNDP/ZIFLP/CS/008A/2018 / Develop systems to manage 2. Livelihood and low-carbon Quality And Cost- IDA / 60380 Post Open - International 365,000.00 396,939.00 Completed 2019-02-01 2018-08-02 2019-02-22 2019-04-07 2019-03-19 2019-05-05 2019-05-24 2019-06-04 2019-06-18 2019-07-09 2019-08-29 2019-08-13 2019-11-06 2020-08-12 2020-06-03 data on land rights AWPB investments Based Selection REF;2.1c.1 MNDP/ZIFLP/CS/003A/2018 / Support updating of District situation anazlysis reports in Katete,Petauke,Chipata,Nyimb Consultant a nad Cadiza and completion 2. Livelihood and low-carbon TF / A4645 Post Qualification Open - National 210,000.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2020-02-05 of DSA in Sinda and Vubwi investments Selection and support landuse planning(harmonizing the data on land use from all sources)AWPB REF;1.1.2.4 MNDP/ZIFLP/CS/004A/2019 Consultant Under / Development of an IDA / 60380 3. Project management Post Qualification Open - National 80,000.00 0.00 2019-06-30 2019-11-07 2019-07-21 2019-09-03 2020-01-08 2019-10-03 2019-11-07 2020-05-05 Implementation electronic MIS for ZIFLP Selection MNDP/ZIFLP/CS/007A/2019 / Consultancy services for Quality And Cost- IDA / 60380 1. Enabling environment Post Open - National 500,000.00 171,398.00 Signed 2019-12-15 2019-11-06 2020-01-05 2020-02-18 2019-11-06 2020-03-17 2019-12-10 2020-04-16 2019-12-13 2020-05-21 2019-12-13 2020-06-25 2020-01-03 2021-06-25 ERPD Develop AWPB Based Selection REF;1.2.2.8- MNDP/ZIFLP/CS/008/2019 / Consultancy services Consultant Engaging technical service TF / A4645 1. Enabling environment Post Qualification Open - National 260,000.00 0.00 Canceled 2019-11-29 2019-12-03 2019-12-20 2020-02-02 2020-03-03 2020-04-07 2020-10-04 providers to implement the Selection private sector and marketfor AWPB REF;1.1.1.14 MNDP/ZIFLP/CS/012/2019 / Consultant Consultancy services for 2. Livelihood and low-carbon IDA / 60380 Post Qualification Open - National 267,900.00 281,501.92 Signed 2019-12-18 2019-12-18 2020-01-08 2020-02-21 2020-05-05 2020-03-22 2020-09-22 2020-04-26 2020-10-08 2020-10-23 Agriculture Value Chain investments Selection AWPB REF;2.1a6.2 MNDP/ZIFLP/CS/011/2019 / Consultant Consultancy services for TF / A4645 1. Enabling environment Post Qualification Open - National 230,400.00 0.00 Canceled 2019-12-18 2019-12-18 2020-01-08 2020-02-21 2020-03-22 2020-04-26 2020-10-23 Integrated Land Management Selection AWPB REF;1.1.1.14 MNDP/ZIFLP/CS/013/2019 / Consultant Consultancy services for 2. Livelihood and low-carbon IDA / 60380 Post Qualification Open - National 255,900.00 213,614.05 Signed 2019-12-18 2019-12-18 2020-01-08 2020-02-21 2020-05-05 2020-03-22 2020-09-14 2020-04-26 2021-01-28 2020-10-23 Forestry Value Chain AWPB investments Selection REF;2.1b.1.4.1 MNDP/ZIFLP/CS/014/2019 / Consultant Consultancy services for 2. Livelihood and low-carbon IDA / 60380 Post Qualification Open - National 213,400.00 213,898.60 Signed 2019-12-18 2019-12-18 2020-01-08 2020-02-21 2020-05-05 2020-03-22 2020-09-14 2020-04-26 2020-11-12 2020-10-23 Wildlife Value Chain AWPB investments Selection REF;2.2.3.5.1 MNDP/ZIFLP/CS/001/2019 / Consultant 2. Livelihood and low-carbon Clarification of ownership IDA / 60380 Post Qualification Open - National 150,000.00 0.00 Canceled 2020-02-23 2020-03-15 2020-04-28 2020-05-28 2020-07-02 2020-12-29 investments Rights AWPB REF;2.1c.2 Selection MNDP/ZIFLP/CS/003/2020 / Consultant Consultancy services for TF / A4645 1. Enabling environment Post Qualification Open - National 230,400.00 189,832.06 Signed 2020-05-29 2020-06-28 2020-06-19 2020-08-02 2020-08-26 2020-09-01 2020-12-09 2020-10-06 2021-02-07 2021-04-04 Integrated Land Management Selection AWPB REF;1.1.1.14 MNDP/ZIFLP/CS/002/2021 / Consultant Consultancy services to Pending TF / A4645 1. Enabling environment Post Qualification Open - National 151,916.00 0.00 2021-10-30 2021-11-20 2022-01-03 2022-02-02 2022-03-09 2022-09-05 conduct end of project Implementation Selection evaluation MNDP/ZIFLP/CS/003/2021 / Consultancy services to create Consultant a Climate Change Portal for TF / A4645 1. Enabling environment Post Qualification Open - National 274,700.00 0.00 Under Review 2021-08-30 2021-08-18 2021-09-20 2021-11-03 2021-12-03 2022-01-07 2022-07-06 ZEMA- AWPB REF; 1.2.1.8.1- Selection 1.2.1.8.3 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual MNDP/ZIFLP/CS/002/2018 / TF / A4646 1. Enabling environment Post Consultant Open 36,000.00 0.00 Canceled 2018-05-01 2018-06-19 2018-07-10 2018-08-14 2019-02-10 Develop the gender strategy Selection MNDP/ZIFLP/CS/012/2018 / Completion of customary Individual 2. Livelihood and low-carbon rights recording USAID - IDA / 60380 Post Consultant Open 50,000.00 0.00 Canceled 2018-05-01 2018-06-19 2018-07-10 2018-08-14 2019-02-10 investments supported pilot AWPB REF Selection ;2.1c.3.5 Page 10 MNDP/ZIFLP/CS/013/2018 / Individual 2. Livelihood and low-carbon Land component coordinator IDA / 60380 Post Consultant Open 70,000.00 173,600.00 Completed 2018-06-01 2018-12-07 2018-07-20 2019-02-18 2018-08-10 2019-05-27 2018-09-14 2019-06-26 2019-03-13 2020-11-30 investments AWPB REF;2.1c.4.1 Selection MNDP/ZIFLP/CS/022/2018 / Individual Communications Officer- IDA / 60380 3. Project management Post Consultant Open 48,600.00 60,100.16 Completed 2018-02-01 2018-03-22 2018-01-05 2018-04-12 2019-02-13 2018-05-17 2019-02-15 2018-11-13 2019-08-04 AWBP REF; 3.1.1 Selection MNDP/ZIFLP/CS/024/2018 / Individual Project Manager-PPIU-AWBP IDA / 60380 3. Project management Post Consultant Open 90,882.00 112,387.31 Completed 2018-02-01 2018-03-22 2017-12-07 2018-04-12 2017-12-11 2018-05-17 2017-12-11 2018-11-13 2020-02-25 REF; 3.2.1 Selection MNDP/ZIFLP/CS/025/2018 / Individual Enviromental & Social IDA / 60380 3. Project management Post Consultant Open 55,080.00 68,113.52 Signed 2018-02-01 2018-03-22 2018-01-05 2018-04-12 2018-01-28 2018-05-17 2018-01-28 2018-11-13 Inclusion Officer-AWBP REF; Selection 3.2.1 MNDP/ZIFLP/CS/027/2018 / Individual Procurement Officer-AWBP IDA / 60380 3. Project management Post Consultant Open 56,700.00 70,116.86 Completed 2018-02-01 2018-03-22 2018-01-18 2018-04-12 2019-02-13 2018-05-17 2018-01-29 2018-11-13 2020-04-24 REF; 3.2.1 Selection MNDP/ZIFLP/CS/28/2018 / Individual Communications Officer- IDA / 60380 3. Project management Post Consultant Open 48,600.00 60,100.16 Completed 2018-02-01 2018-03-22 2018-01-05 2018-04-12 2018-01-13 2018-05-17 2018-01-18 2018-11-13 2019-08-04 AWBP REF; 3.2.1 Selection MNDP/ZIFLP/CS/029/2018 / Individual Planning Monitoring & IDA / 60380 3. Project management Post Consultant Open 53,460.00 115,149.00 Signed 2018-02-01 2018-03-22 2018-01-05 2018-04-12 2019-02-12 2018-05-17 2018-01-22 2018-11-13 Evaluation Officer- PPIU-AWBP Selection REF; 3.2.1 MNDP/ZIFLP/CS/030/2018 / Individual Project Accountant -AWBP IDA / 60380 3. Project management Post Consultant Open 58,320.00 125,617.32 Signed 2018-02-01 2018-03-22 2018-01-05 2018-04-12 2019-01-24 2018-05-17 2018-01-24 2018-11-13 REF; 3.2.1 Selection MNDP/ZIFLP/CS/001/2018 / ToT for district multisectoral teams in landuse and community action planning, Individual landscape/community action TF / A4645 1. Enabling environment Post Consultant Open 50,000.00 0.00 Canceled 2018-05-01 2018-06-19 2018-07-10 2018-08-14 2019-02-10 planning with specila Selection attention to ESS Desk officers- District and Local Planning AWPB REF;1.1.1.7 MNDP/ZIFLP/CS/005/2018 / Carbon benefit sharing and Individual stakeholder consultation on TF / A4645 1. Enabling environment Post Consultant Open 100,000.00 0.00 Canceled 2018-06-01 2018-07-20 2018-08-10 2018-09-14 2019-03-13 REDD+at multiplescales of Selection action in Eastern Province AWPB REF; 1.2.1.2 MNDP/ZIFLP/CS/014/2018 / Individual Assistant Land Component 2. Livelihood and low-carbon IDA / 60380 Prior Consultant Open 50,000.00 0.00 Canceled 2018-06-01 2018-07-20 2018-08-10 2018-09-14 2019-03-13 Coordinator AWBP REF investments Selection ;2.1c.4.2 MNDP/ZIFLP/CS/015/2018 / Individual Planning Monitoring & IDA / 60380 3. Project management Post Consultant Open 53,460.00 66,110.18 Completed 2018-02-01 2018-03-22 2018-01-05 2018-04-12 2019-02-13 2018-05-17 2019-02-15 2018-11-13 2020-05-31 Evaluation Officer- NPIU AWBP Selection REF; 3.1.1 MNDP/ZIFLP/CS/016/2018 / Individual National Project Manager- IDA / 60380 3. Project management Prior Consultant Open 123,930.00 0.00 Canceled 2018-02-01 2018-03-22 2017-12-07 2018-04-12 2018-05-17 2018-11-13 AWBP REF; 3.1.1 Selection MNDP/ZIFLP/CS/017/2018 / Individual Procurement Officer-AWBP IDA / 60380 3. Project management Post Consultant Open 56,700.00 122,672.43 Signed 2018-02-01 2018-03-22 2018-01-18 2018-04-12 2019-02-13 2018-05-17 2019-02-15 2018-11-13 REF; 3.1.1 Selection MNDP/ZIFLP/CS/018/2018 / Individual Project Accountant --AWBP IDA / 60380 3. Project management Post Consultant Open 58,320.00 72,120.20 Completed 2018-02-01 2018-03-22 2018-01-05 2018-04-12 2019-02-13 2018-05-17 2018-01-22 2018-11-13 2020-01-21 REF; 3.1.1 Selection MNDP/ZIFLP/CS/019/2018 / Individual Internal Auditor--AWBP REF; IDA / 60380 3. Project management Post Consultant Open 51,840.00 64,106.84 Completed 2018-02-01 2018-03-22 2018-01-05 2018-04-12 2019-02-13 2018-05-17 2019-02-15 2018-11-13 2019-05-10 3.1.1 Selection MNDP/ZIFLP/CS/021/2018 / Individual Enviromental & Social IDA / 60380 3. Project management Post Consultant Open 55,080.00 68,113.52 Completed 2018-02-01 2018-03-22 2018-01-05 2018-04-12 2018-01-22 2018-05-17 2019-02-15 2018-11-13 2019-08-04 Inclusion Officer-AWBP REF; Selection 3.1.1 MNDP/ZIFLP/PPG/CS/001/20 Individual 18 / Public Private IDA / 60380 1. Enabling environment Post Consultant Open 51,782.00 51,782.00 Completed 2017-08-31 2017-08-26 2017-10-19 2017-12-05 2017-11-09 2018-07-10 2017-12-14 2018-07-10 2018-06-12 2018-10-31 Partnerships models for BioCF Selection component MNDP/ZIFLP/CS/035/2018 / Leveraging the Geospatial 2. Livelihood and low-carbon IDA / 60380 Prior Direct Selection Direct 100,000.00 100,000.00 Signed 2018-12-12 2018-12-27 2018-12-13 2019-03-02 2019-02-18 2019-08-29 Capability of the Agriculture investments Observatory into the ZIFLP MNDP/ZIFLP/CS/014B/2018 Individual / Assistant Land Component 2. Livelihood and low-carbon IDA / 60380 Prior Consultant Direct 50,000.00 0.00 Canceled 2018-11-26 2018-12-06 2018-12-27 2019-01-31 2019-07-30 Coordinator (AWPB Ref:2.1c. investments Selection 4.2) MNDP/ZIFLP/CS/014A/2018 Individual / Assistant Land Component 2. Livelihood and low-carbon IDA / 60380 Prior Consultant Direct 50,000.00 50,400.00 Signed 2018-12-01 2018-12-11 2018-12-17 2019-01-01 2019-02-12 2019-02-05 2019-06-14 2019-08-04 Coordinator AWBP REF investments Selection ;2.1c.4.2 Individual MNDP/ZIFLP/CS/002A/2018 TF / A4646 1. Enabling environment Post Consultant Limited 36,000.00 28,500.00 Completed 2018-05-01 2019-02-18 2018-05-06 2018-10-09 2018-05-27 2019-05-02 2018-07-01 2019-06-05 2018-12-28 2020-06-30 / Develop the gender strategy Selection MNDP/ZIFLP/CS/020/2018 / Individual Administrative Assistant- IDA / 60380 3. Project management Post Consultant Open 27,540.00 0.00 Canceled 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-11-13 AWBP REF; 3.1.1 Selection Page 11 MNDP/ZIFLP/CS/31/2018 / Individual Administrative Assistant- IDA / 60380 3. Project management Post Consultant Open 27,540.00 0.00 Canceled 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-11-13 AWBP REF; 3.2.1 Selection Individual MNDP/ZIFLP/CS/023/2018 / IDA / 60380 3. Project management Post Consultant Open 38,880.00 0.00 Canceled 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-11-13 Driver *2-AWBP REF; 3.1.1 Selection Individual MNDP/ZIFLP/CS/032/2018 / IDA / 60380 3. Project management Post Consultant Open 38,880.00 0.00 Canceled 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-11-13 Driver *2-AWBP REF; 3.2.1 Selection MNDP/ZIFLP/CS/001A/2018 / ToT for district multisectoral teams in landuse and community action planning, Individual 2. Livelihood and low-carbon landscape/community action TF / A4645 Post Consultant Limited 50,000.00 0.00 Canceled 2019-04-01 2019-06-06 2019-04-06 2019-04-27 2019-06-01 2019-11-28 investments planning with specila Selection attention to ESS Desk officers- District and Local Planning AWPB REF;1.1.1.7 MNDP/ZIFLP/CS/005A/2018 / Carbon benefit sharing and Individual stakeholder consultation on 2. Livelihood and low-carbon TF / A4645 Post Consultant Open 100,000.00 116,970.00 Signed 2019-04-01 2019-03-18 2019-05-20 2019-08-02 2019-06-10 2019-09-01 2019-07-15 2019-10-08 2020-01-11 REDD+at multiplescales of investments Selection action in Eastern Province AWPB REF; 1.2.1.2 MNDP/ZIFLP/CS/002/2019 / Preparation livelihood Individual 2. Livelihood and low-carbon restoration plans IDA / 60380 Post Consultant Open 60,000.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-20 2019-08-10 2019-09-14 2020-03-12 investments (Lukusuzi/Luambe) AWPB Selection REF:2.2.3.4.2 MNDP/ZIFLP/CS/026/2018 / Individual Internal Auditor-AWBP REF; IDA / 60380 3. Project management Post Consultant Open 51,840.00 0.00 Canceled 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-11-13 3.2.1 Selection MNDP/ZIFLP/GO/016B/2018 Individual / National Project Manager - IDA / 60380 3. Project management Post Consultant Open 123,930.00 253,672.55 Signed 2019-06-30 2017-12-07 2019-08-18 2017-12-07 2019-09-08 2018-01-08 2019-10-13 2018-01-08 2020-04-10 AWPB REF: 3.1.1 Selection MNDP/ZIFLP/CS/003/2019 / Consultancy for training of 2. Livelihood and low-carbon IDA / 60380 Prior Direct Selection Direct 25,520.00 0.00 Canceled 2019-09-22 2019-10-02 2019-12-06 2020-06-03 staff in LDSF( ICRAF investments model)AWPB REF No:2.1a.2.10 MNDP/ZIFLP/CS/010/2019 / Individual Consultancy services IDA / 60380 3. Project management Post Consultant Open 30,000.00 0.00 Canceled 2019-11-29 2020-01-17 2020-02-07 2020-03-13 2020-09-09 Stakeholder Engagement Selection Specilasist AWPB REF;3.2.1 MNDP/ZIFLP/CS/010A/2019 Individual / Consultancy services IDA / 60380 3. Project management Prior Consultant Direct 30,000.00 0.00 Canceled 2019-11-29 2019-11-28 2019-12-09 2019-12-30 2020-02-03 2020-08-01 Stakeholder Engagement Selection Specilasist AWPB REF;3.2.1 MNDP/ZIFLP/CS/010B/2019 Individual / Consultancy services IDA / 60380 3. Project management Post Consultant Limited 30,000.00 0.00 Canceled 2019-11-29 2019-12-18 2019-12-04 2019-12-24 2019-12-25 2020-01-29 2020-07-27 Stakeholder Engagement Selection Specilasist AWPB REF;3.2.1 MNDP/ZIFLP/CS/001/2020 / Individual Consultancy Services 2. Livelihood and low-carbon IDA / 60380 Prior Consultant Direct 155,600.00 115,795.00 Signed 2020-03-02 2020-02-21 2020-03-12 2020-04-25 2020-04-02 2020-07-08 2020-05-07 2020-07-09 2020-11-03 Technical Advisor-Community investments Selection Forestry AWPB REF;2.1b1.3.10 MNDP/ZIFLP/CS/002/2020 / Individual Individual Consultancy 2. Livelihood and low-carbon IDA / 60380 Post Consultant Limited 26,000.00 0.00 Canceled 2020-04-30 2020-05-05 2020-05-26 2020-06-30 2020-12-27 Services for EIA-for fertilzer investments Selection blending plant AWPB REF: MNDP/ZIFLP/CS/006/2020 / Individual Under Technical Officer- AWPB REF; IDA / 60380 3. Project management Post Consultant Open 157,950.00 0.00 2020-08-21 2020-08-17 2020-10-09 2020-11-13 2020-10-30 2020-12-04 2021-06-02 Implementation 3.2.1.10 Selection MNDP/ZIFLP/CS/005/2020 / Individual Under Assistant Accountant- AWPB IDA / 60380 3. Project management Post Consultant Open 85,750.00 0.00 2020-08-21 2020-08-17 2020-10-09 2020-10-30 2020-12-04 2021-06-02 Implementation REF; 3.2.1.11 Selection MNDP/ZIFLP/CS/001/2021 / Individual Consultancy Services 2. Livelihood and low-carbon Under IDA / 60380 Post Consultant Direct 113,600.00 0.00 2021-06-07 2021-08-17 2021-06-17 2021-07-08 2021-08-12 2022-02-08 Technical Advisor-Community investments Implementation Selection Forestry MNDP/ZIFLP/CS/005/2021 / Individual Consultancy Services to Under TF / A4645 1. Enabling environment Post Consultant Direct 36,000.00 0.00 2021-06-07 2021-06-30 2021-06-17 2021-07-08 2021-08-12 2022-02-08 develop a Carbon Benefit Implementation Selection Sharing Plan Page 12