PROCUREMENT PLAN (Textual Part) Project information: Mauritania Social Safety Net Project II (P171125) Project Implementation agency: Delegation Générale Taazour Date of the Procurement Plan: March 17th, 2020 Period covered by this Procurement Plan: 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: “Not Applicable” Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Mauritania : Social Safety Net System Project II PLAN General Information Country: Mauritania Bank’s Approval Date of the Original Procurement Plan: 2020-03-18 2021-09-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171125 GPN Date: Project Name: Social Safety Net System Project II Loan / Credit No: IDA / D5680 Social Safety Net System Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-178803-GO-RFB / Acquisition 9 véhiculeS (4x4): Lot 1 (4 pour le RS, 1 pour le Component 1: Updating and Single Stage - One En attente PFSRC et 2 pour Tekavoul) Lot IDA / D5680 A posteriori Appel d'offres Open - National 0.00 2020-06-10 2020-06-15 2020-07-27 2020-08-26 2020-09-30 2021-03-29 enhancing the Social Registry Envelope d'exécution 2 (1 véhicule pour le RS) Lot 3 (1 véhicule pour Tekavoul) TEK/RS/PFSRC MR-SSNS-211604-GO-RFB / Component 1: Updating and Single Stage - One En attente Matériel Informatique IDA / D5680 A posteriori Appel d'offres Open - National 0.00 2020-12-31 2021-01-05 2021-02-16 2021-03-18 2021-04-22 2021-10-19 enhancing the Social Registry Envelope d'exécution (TEK,RS,PFSRC,Coord.) MR-SSNS-211605-GO-RFQ / Mobilier et équipements de Component 1: Updating and Single Stage - One En attente bureaux (bureaux, mobiliers, IDA / D5680 A posteriori Demande de prix Limited 0.00 2021-01-09 2021-03-06 2021-09-02 enhancing the Social Registry Envelope d'exécution téléphones, climatiseurs…) TEK,RS,PFSRC,Coord. MR-SSNS-211968-GO-RFQ / Consommable informatique & Component 1: Updating and Single Stage - One En attente IDA / D5680 A posteriori Demande de prix Limited 0.00 2021-01-25 2021-03-22 2021-09-18 fournitures de bureau enhancing the Social Registry Envelope d'exécution TEK,RS,PFSRC,Coord MR-SSNS-211973-GO-RFQ / Component 2: Enhancing the Equipement Promotion Sociale Single Stage - One En attente IDA / D5680 socio-economic inclusion of A posteriori Demande de prix Limited 0.00 2021-01-25 2021-03-22 2021-09-18 + Dialogue Familiale Envelope d'exécution poor households (formation) TEK MR-SSNS-212002-GO-RFQ / Component 1: Updating and Single Stage - One Kits équipes mobiles (nattes, IDA / D5680 A posteriori Demande de prix Limited 12,548.12 Signé 2021-01-25 2021-08-03 2021-03-22 2021-08-30 2021-09-18 enhancing the Social Registry Envelope torches, lits picots…) TEK,RS MR-SSNS-212017-GO-RFB / Production outils de communication (images, brochures, spots radio, vidéo Component 1: Updating and Single Stage - One En attente sur les réalisations du prog, IDA / D5680 A posteriori Appel d'offres Open - National 0.00 2021-02-10 2021-02-15 2021-03-29 2021-04-28 2021-06-02 2021-11-29 enhancing the Social Registry Envelope d'exécution postres, panneau, depliant rollup, banderol gadgets, casquette, gilet, foulard) TEK/RS MR-SSNS-212049-GO-RFQ / Component 4: Project Single Stage - One Matériels de protection Covid IDA / D5680 Coordination and A posteriori Demande de prix Limited 3,650.64 Signé 2021-01-25 2021-08-03 2021-03-22 2021-08-19 2021-09-18 Envelope 19 Coord Management MR-SSNS-212283-GO-RFB / Component 1: Updating and Single Stage - Two En attente Acquisition de 2 Véhicules IDA / D5680 A posteriori Appel d'offres Open - National 0.00 2021-02-22 2021-02-27 2021-04-10 2021-06-23 2021-07-28 2022-01-24 enhancing the Social Registry Envelope d'exécution 4X4 RS/ TK MR-SSNS-212037-GO-RFQ / Acquisition et installation Component 1: Updating and Single Stage - One En attente IDA / D5680 A posteriori Demande de prix Limited 0.00 2021-01-26 2021-03-23 2021-09-19 système de vidéoconférence enhancing the Social Registry Envelope d'exécution RS/TEK/PFSRC MR-SSNS-219273-GO-RFB / Acquisition 6 véhicules 4x4: Lot 1 ( (04) véhicules 4X4 Pick Component 1: Updating and Single Stage - One En attente up : 3 pour Tekavoul et 1 IDA / D5680 A posteriori Appel d'offres Open - International 0.00 2021-03-17 2021-03-22 2021-05-03 2021-06-02 2021-07-07 2022-01-03 enhancing the Social Registry Envelope d'exécution pour MAOUNA) Lot 2 ( (02) véhicules 4X4 1 pour la Coordination et 1 pour RS) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-165047-NC-RFB / SELECTION D’UN OU PLUSIEURS OPERATEURS DE PAIEMENT POUR LA Component 2: Enhancing the Single Stage - One En cours REALISATION DE TRANSFERTS IDA / D5680 socio-economic inclusion of A priori Appel d'offres Open - International 0.00 2020-03-20 2020-09-15 2020-03-25 2020-09-16 2020-05-06 2020-06-05 2020-07-10 2021-01-06 Envelope d'exécution MONETAIRES ELECTRONIQUES poor households AU PROFIT DES MENAGES PAUVRES (5 lots) - Accord Cadre 2 ans et demi -PNTS Page 1 MR-SSNS-196334-NC-RFB / Sélection d'un ou plusieurs opérateurs dans le cadre d'un Component 3: Strengthening deuxième passage de the shock response system Single Stage - One En cours distribution de cash transfer IDA / D5680 A posteriori Demande de prix Limited 0.00 2020-10-10 2020-12-05 2021-06-03 for households vulnerable to Envelope d'exécution au profit de 210 000 ménages climate-shocks bénéficiaires en réponse au COVID 19 (Financement: BAD, BM et Etat Mauritanien) MR-SSNS-211963-NC-RFB / Component 1: Updating and Single Stage - One En attente IMPRESSION cartes de IDA / D5680 A posteriori Appel d'offres Open - National 0.00 2021-02-08 2021-02-13 2021-03-27 2021-04-26 2021-05-31 2021-11-27 enhancing the Social Registry Envelope d'exécution ménages TEK/RS/PFSRC MR-SSNS-211978-NC-RFQ / Component 2: Enhancing the Maintenance matériels Single Stage - One En attente IDA / D5680 socio-economic inclusion of A posteriori Demande de prix Limited 0.00 2021-01-25 2021-03-22 2021-09-18 informatiques et de froid Envelope d'exécution poor households Coord/TEK MR-SSNS-211982-NC-RFQ / Component 1: Updating and Single Stage - One En attente Entretien et réparation des IDA / D5680 A posteriori Demande de prix Limited 0.00 2021-01-25 2021-03-22 2021-09-18 enhancing the Social Registry Envelope d'exécution véhicules TEK,RS,PFSRC,Coord MR-SSNS-211958-NC-RFB / Component 1: Updating and Single Stage - One En cours Location Véhicules IDA / D5680 A posteriori Appel d'offres Open - National 0.00 2021-01-05 2021-02-15 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-10-24 enhancing the Social Registry Envelope d'exécution TEK/RS/PFSRC MR-SSNS-212229-NC-RFQ / Component 2: Enhancing the Single Stage - One En attente Production des émissions IDA / D5680 socio-economic inclusion of A posteriori Demande de prix Limited 0.00 2021-01-25 2021-03-22 2021-09-18 Envelope d'exécution Radio TEK poor households MR-SSNS-212285-GO-RFQ / Component 1: Updating and Single Stage - One En attente Location de Véhicules (Contrat IDA / D5680 A posteriori Demande de prix Limited 0.00 2021-01-31 2021-03-28 2021-09-24 enhancing the Social Registry Envelope d'exécution de 3mois) TEK Coord RS MR-SSNS-218651-NC-DIR / Passation de Location de véhicules pour le Component 1: Updating and En cours IDA / D5680 A priori marché de gré à Direct 0.00 2021-02-10 2021-03-10 2021-02-15 2021-03-22 2021-09-18 PASyFIS (contrat de 3 mois enhancing the Social Registry d'exécution gré renouvelable 1 fois) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-196264-CS-LCS / Component 4: Project Auditeur Externe pour les Sélection au En cours IDA / D5680 Coordination and A priori Open - International 0.00 2020-09-28 2020-09-25 2020-10-19 2020-10-13 2020-12-02 2021-01-19 2020-12-30 2021-03-09 2021-01-29 2021-06-15 2021-03-05 2021-04-09 2021-10-06 exercices 2020, 2021 et 2022 moindre coût d'exécution Management - Unité de Coordination MR-SSNS-212022-CS-CQS / Sélection fondée Acquisition d’un système Component 1: Updating and sur les En attente d’archivage numérique et IDA / D5680 A posteriori Open - National 0.00 2021-02-08 2021-03-01 2021-04-14 2021-05-14 2021-06-18 2021-12-15 enhancing the Social Registry qualifications des d'exécution gestion elecronique des consultants documents RS MR-SSNS-212039-CS-CQS / Développement d’une API Sélection fondée d’accès externe et d’un Component 1: Updating and sur les En attente système de collecte des IDA / D5680 A posteriori Open - International 0.00 2021-02-15 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-12-22 enhancing the Social Registry qualifications des d'exécution retours et des activités des consultants utilisateurs des données du Registre social RS MR-SSNS-212041-CS-CQS / Création d'une plateforme web pour l'accès et la gestion Sélection fondée sécurisées de données Component 1: Updating and sur les En attente ménages inscrits IDA / D5680 A posteriori Open - National 0.00 2021-02-17 2021-03-10 2021-04-23 2021-05-23 2021-06-27 2021-12-24 enhancing the Social Registry qualifications des d'exécution (Développement d’une consultants interface et tableau de bord dynamique des données du registre social) RS MR-SSNS-212042-CS-CQS / Sélection fondée Analyse des profils ménages Component 1: Updating and sur les En attente IDA / D5680 A posteriori Open - National 0.00 2021-02-23 2021-03-16 2021-04-29 2021-05-29 2021-07-03 2021-12-30 enregistrés dans la base de enhancing the Social Registry qualifications des d'exécution données RS consultants MR-SSNS-212044-CS-CQS / Sélection fondée Création d'un système de Component 1: Updating and sur les En attente génération et de lecture IDA / D5680 A posteriori Open - National 0.00 2021-03-01 2021-03-22 2021-05-05 2021-06-04 2021-07-09 2022-01-05 enhancing the Social Registry qualifications des d'exécution automatique des cartes de consultants ménages RS Sélection fondée MR-SSNS-211981-CS-CQS / Component 4: Project sur les Traduction de documents du IDA / D5680 Coordination and A posteriori Open - National 0.00 Annulé 2021-01-20 2021-02-10 2021-03-26 2021-04-25 2021-05-30 2021-11-26 qualifications des PaSyFiS II Coord. Management consultants MR-SSNS-219081-CS-CQS / Sélection fondée Component 2: Enhancing the Bureau pour l'élaboration de sur les En attente IDA / D5680 socio-economic inclusion of A posteriori Open - National 0.00 2021-02-22 2021-03-15 2021-04-28 2021-05-28 2021-07-02 2021-12-29 l'enquête de suivi Spotcheck qualifications des d'exécution poor households du PASYFIS II consultants INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-199379-CS-CDS / Component 2: Enhancing the Sélection de Enquête d'Evaluation d'Impact IDA / D5680 socio-economic inclusion of A priori consultants par Direct 449,184.00 Signé 2020-10-13 2020-10-13 2020-10-23 2019-11-12 2020-12-27 2020-11-09 2021-06-25 (midline) poor households entente directe Component 4: Project MR-SSNS-212051-CS-INDV / En attente IDA / D5680 Coordination and A posteriori Individuel Open 0.00 2021-02-16 2021-04-06 2021-04-27 2021-06-01 2021-11-28 Secretaire Coord d'exécution Management Page 2 Component 4: Project MR-SSNS-212052-CS-INDV / En attente IDA / D5680 Coordination and A posteriori Individuel Open 0.00 2021-02-10 2021-03-31 2021-04-21 2021-05-26 2021-11-22 Assistant SE (02) Coord d'exécution Management MR-SSNS-212057-CS-INDV / Component 2: Enhancing the En attente 2 Facilitateurs/trices Dialogue IDA / D5680 socio-economic inclusion of A posteriori Individuel Open 0.00 2021-02-18 2021-04-08 2021-04-29 2021-06-03 2021-11-30 d'exécution Familiale TEK poor households MR-SSNS-212061-CS-INDV / 7 superviseurs pour les Component 2: Enhancing the Moughataas du Hodh Chargui En attente IDA / D5680 socio-economic inclusion of A posteriori Individuel Open 0.00 2021-02-02 2021-03-23 2021-04-13 2021-05-18 2021-11-14 ( Timbedra, Nema, Bassiknou, d'exécution poor households N'Beiket Lehwach, Oualata, Amourj, Djiguenni) TEK MR-SSNS-212064-CS-INDV / 13 animateurs (2 à Timbedra, Component 2: Enhancing the 2 à Nema, 1 à Bassiknou, 1 à En attente IDA / D5680 socio-economic inclusion of A posteriori Individuel Open 0.00 2021-03-09 2021-04-27 2021-05-18 2021-06-22 2021-12-19 N'Beiket Lehwach, 1 à Oulata, d'exécution poor households 3 à Amourj et 3 à Djiguenni) TEK MR-SSNS-212221-CS-INDV / Component 2: Enhancing the 12 Enquêteurs de suivi spot En cours IDA / D5680 socio-economic inclusion of A posteriori Individuel Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 check T4 2020, et T1/T2/T3 d'exécution poor households 2021 TEK MR-SSNS-212231-CS-INDV / Component 2: Enhancing the Traducteur pour l'unité En attente IDA / D5680 socio-economic inclusion of A posteriori Individuel Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 Dialogue et Ressources d'exécution poor households Familiales TEK MR-SSNS-212233-CS-INDV / Component 2: Enhancing the Prestation graphiste pour En attente IDA / D5680 socio-economic inclusion of A posteriori Individuel Limited 0.00 2021-03-30 2021-04-04 2021-04-25 2021-05-30 2021-11-26 adaptation du manuel (dessin; d'exécution poor households graphiques) TEK Component 4: Project MR-SSNS-212241-CS-INDV / En attente IDA / D5680 Coordination and A posteriori Individuel Open 0.00 2021-01-20 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Aide comptable Coord d'exécution Management MR-SSNS-212244-CS-INDV / Component 1: Updating and En attente IDA / D5680 A posteriori Individuel Open 0.00 2021-01-20 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Assistant Communication RS enhancing the Social Registry d'exécution MR-SSNS-212245-CS-INDV / Component 1: Updating and En attente IDA / D5680 A posteriori Individuel Open 0.00 2021-01-20 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Assistant archivage RS enhancing the Social Registry d'exécution Component 2: Enhancing the MR-SSNS-212284-CS-INDV / En attente IDA / D5680 socio-economic inclusion of A posteriori Individuel Open 0.00 2021-02-15 2021-04-05 2021-04-26 2021-05-31 2021-11-27 Animateur Teintan TK d'exécution poor households Component 2: Enhancing the Sélection de MR-SSNS-212308-CS-CDS / En attente IDA / D5680 socio-economic inclusion of A posteriori consultants par Direct 0.00 2021-02-15 2021-02-25 2021-05-01 2021-10-28 Chauffeurs (03) TK d'exécution poor households entente directe MR-SSNS-212004-CS-INDV / Component 4: Project Consultant chargé de la En attente IDA / D5680 Coordination and A posteriori Individuel Limited 0.00 2021-02-16 2021-02-21 2021-03-14 2021-04-18 2021-10-15 gestion de l'infrastructure d'exécution Management informatique Coord MR-SSNS-212005-CS-INDV / 20 chauffeurs (7 pour TEK, 10 Component 1: Updating and En attente pour le RS, 1 chauffeurs IDA / D5680 A posteriori Individuel Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 enhancing the Social Registry d'exécution Coord., 2 chauffeurs pour le PFSRC ) TEK,RS,PFSRC,Coord. MR-SSNS-212046-CS-INDV / Responsable Administratif et Component 1: Updating and En cours IDA / D5680 A priori Individuel Open 0.00 2021-02-08 2021-02-17 2021-03-29 2021-03-30 2021-04-19 2021-04-15 2021-05-24 2021-11-20 Moyens Généraux enhancing the Social Registry d'exécution Coordination MR-SSNS-212236-CS-INDV / Component 2: Enhancing the En attente Responsable Promotion IDA / D5680 socio-economic inclusion of A posteriori Individuel Open 0.00 2021-01-04 2021-02-22 2021-03-15 2021-04-19 2021-10-16 d'exécution Sociale TEK. poor households MR-SSNS-212237-CS-INDV / Component 2: Enhancing the En cours Responsable Développement IDA / D5680 socio-economic inclusion of A posteriori Individuel Open 0.00 2021-01-20 2021-06-02 2021-03-10 2021-03-31 2021-05-05 2021-11-01 d'exécution Plateforme TEK poor households MR-SSNS-212238-CS-INDV / Component 4: Project En cours Expert Point Focal Bassiknou IDA / D5680 Coordination and A priori Individuel Open 0.00 2021-01-20 2021-03-25 2021-03-10 2021-03-31 2021-05-05 2021-11-01 d'exécution Coord Management MR-SSNS-212287-CS-CDS / Sélection de Component 1: Updating and En attente Expert informatique et base IDA / D5680 A posteriori consultants par Direct 0.00 2021-01-13 2021-01-23 2021-03-29 2021-09-25 enhancing the Social Registry d'exécution de données RS entente directe Sélection de MR-SSNS-212288-CS-CDS / Component 1: Updating and En attente IDA / D5680 A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Expert mobilisation sociale RS enhancing the Social Registry d'exécution entente directe MR-SSNS-212228-CS-INDV / Component 2: Enhancing the En attente Production films IDA / D5680 socio-economic inclusion of A posteriori Individuel Direct 0.00 2021-01-20 2021-01-30 2021-02-20 2021-03-27 2021-09-23 d'exécution primoadoptants TEK poor households Sélection de MR-SSNS-212289-CS-CDS / Component 1: Updating and En attente IDA / D5680 A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Expert Collecte de Données RS enhancing the Social Registry d'exécution entente directe MR-SSNS-212290-CS-CDS / Sélection de Component 1: Updating and En attente Gestionnaire / médiateur IDA / D5680 A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 enhancing the Social Registry d'exécution réclamations RS entente directe Sélection de MR-SSNS-212291-CS-CDS / Component 1: Updating and En attente IDA / D5680 A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Assistant administratif RS enhancing the Social Registry d'exécution entente directe Page 3 MR-SSNS-212292-CS-CDS / Sélection de Component 1: Updating and En attente Assistant informatique et IDA / D5680 A posteriori consultants par 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 enhancing the Social Registry d'exécution base de données RS entente directe Sélection de MR-SSNS-212296-CS-CDS / Component 1: Updating and En attente IDA / D5680 A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Secrétaire (1) RS enhancing the Social Registry d'exécution entente directe MR-SSNS-212298-CS-CDS / Component 2: Enhancing the Sélection de En attente Coordinateur du programme IDA / D5680 socio-economic inclusion of A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 d'exécution transferts sociaux TK poor households entente directe MR-SSNS-212299-CS-CDS / Component 2: Enhancing the Sélection de En attente Responsable supervision IDA / D5680 socio-economic inclusion of A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 d'exécution paiements TK poor households entente directe MR-SSNS-212300-CS-CDS / Component 2: Enhancing the Sélection de En attente Responsable du système IDA / D5680 socio-economic inclusion of A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 d'exécution d'information TK poor households entente directe MR-SSNS-212302-CS-CDS / Component 2: Enhancing the Sélection de Responsable promotion En attente IDA / D5680 socio-economic inclusion of A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 dialogue et Ressource d'exécution poor households entente directe Familiale TK MR-SSNS-212306-CS-CDS / Component 2: Enhancing the Sélection de En attente Gestionnaire des réclamations IDA / D5680 socio-economic inclusion of A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 d'exécution TEK poor households entente directe Component 2: Enhancing the Sélection de MR-SSNS-212307-CS-CDS / En attente IDA / D5680 socio-economic inclusion of A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Secrétaire TK d'exécution poor households entente directe MR-SSNS-212309-CS-CDS / Component 4: Project Sélection de En attente Spécialiste en passation des IDA / D5680 Coordination and A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 d'exécution marchés Coord Management entente directe MR-SSNS-212235-CS-INDV / Component 4: Project En cours Responsable Communication IDA / D5680 Coordination and A priori Individuel Limited 0.00 2021-01-20 2021-03-05 2021-01-25 2021-03-11 2021-02-15 2021-03-25 2021-03-22 2021-09-18 d'exécution Coord. Management MR-SSNS-212303-CS-CDS / Component 2: Enhancing the Sélection de En attente Adjoint au RSI Developpement IDA / D5680 socio-economic inclusion of A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 d'exécution SI TK poor households entente directe Component 2: Enhancing the Sélection de MR-SSNS-212304-CS-CDS / En attente IDA / D5680 socio-economic inclusion of A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Adjoint au Resp PS TK d'exécution poor households entente directe Component 2: Enhancing the Sélection de MR-SSNS-212305-CS-CDS / En attente IDA / D5680 socio-economic inclusion of A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Assistante de DirectionTK d'exécution poor households entente directe Component 4: Project Sélection de MR-SSNS-212310-CS-CDS / En attente IDA / D5680 Coordination and A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Auditeur interne Coord d'exécution Management entente directe MR-SSNS-212311-CS-CDS / Component 4: Project Sélection de En attente Responsable Suivi Evaluation IDA / D5680 Coordination and A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 d'exécution Coor Management entente directe MR-SSNS-212312-CS-CDS / Component 4: Project Sélection de En attente Responsable de IDA / D5680 Coordination and A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 d'exécution communication Coor Management entente directe MR-SSNS-212313-CS-CDS / Component 4: Project Sélection de En attente Assistant Comptable et IDA / D5680 Coordination and A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 d'exécution Financier Coord Management entente directe MR-SSNS-212314-CS-CDS / Component 4: Project Sélection de En attente Assistant Moyens Généraux et IDA / D5680 Coordination and A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 d'exécution logistique Coord Management entente directe Component 4: Project Sélection de MR-SSNS-212315-CS-CDS / En attente IDA / D5680 Coordination and A posteriori consultants par Direct 0.00 2021-01-05 2021-01-15 2021-03-21 2021-09-17 Assistant RH Coord d'exécution Management entente directe Component 4: Project Sélection de MR-SSNS-212316-CS-CDS / En attente IDA / D5680 Coordination and A posteriori consultants par Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Consultant informatique Coor d'exécution Management entente directe MR-SSNS-219094-CS-INDV / Component 3: Strengthening Consultant international pour the shock response system En attente la mise en place de la IDA / D5680 A posteriori Individuel Open 0.00 2021-02-26 2021-04-16 2021-05-07 2021-06-11 2021-12-08 for households vulnerable to d'exécution stratégie de financement de la climate-shocks réponse MR-SSNS-219102-CS-INDV / Component 3: Strengthening Consultant National pour la the shock response system En attente IDA / D5680 A posteriori Individuel Open 0.00 2021-02-24 2021-04-14 2021-05-05 2021-06-09 2021-12-06 mise en place de la stratégie for households vulnerable to d'exécution de financement de la réponse climate-shocks MR-SSNS-219204-CS-INDV / Component 2: Enhancing the Illustrateur pour l'unité En attente IDA / D5680 socio-economic inclusion of A posteriori Individuel Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Dialogue et Ressources d'exécution poor households Familiales MR-SSNS-219206-CS-INDV / Component 1: Updating and En attente IDA / D5680 A posteriori Individuel Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Assistant SIG RS enhancing the Social Registry d'exécution MR-SSNS-219207-CS-INDV / Component 1: Updating and En attente 2 Superviseurs mobilisation IDA / D5680 A posteriori Individuel Open 0.00 2021-02-24 2021-04-14 2021-05-05 2021-06-09 2021-12-06 enhancing the Social Registry d'exécution sociale Page 4 Component 3: Strengthening MR-SSNS-219213-CS-INDV / the shock response system En attente IDA / D5680 A posteriori Individuel Open 0.00 2021-02-24 2021-04-14 2021-05-05 2021-06-09 2021-12-06 Expert en sécurité alimentaire for households vulnerable to d'exécution climate-shocks Component 3: Strengthening MR-SSNS-219215-CS-INDV / the shock response system En attente IDA / D5680 A posteriori Individuel Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Coordinateur de la Réponse for households vulnerable to d'exécution climate-shocks Component 3: Strengthening MR-SSNS-219216-CS-INDV / the shock response system En attente IDA / D5680 A posteriori Individuel Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Amélioration du site Web for households vulnerable to d'exécution climate-shocks MR-SSNS-219256-CS-INDV / Component 2: Enhancing the En attente Responsable appui à IDA / D5680 socio-economic inclusion of A posteriori Individuel Direct 0.00 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 d'exécution l’enrôlement à l'Etat civil poor households MR-SSNS-219258-CS-INDV / Component 2: Enhancing the En attente Responsable mesure inclusion IDA / D5680 socio-economic inclusion of A posteriori Individuel Direct 0.00 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 d'exécution économique poor households MR-SSNS-219261-CS-INDV / Component 2: Enhancing the En attente 1 adjoint au RSI Base de IDA / D5680 socio-economic inclusion of A posteriori Individuel Direct 0.00 2021-12-16 2021-12-26 2022-01-16 2022-02-20 2022-08-19 d'exécution données poor households Component 2: Enhancing the MR-SSNS-219264-CS-INDV / En attente IDA / D5680 socio-economic inclusion of A posteriori Individuel Direct 0.00 2021-12-13 2021-12-23 2022-01-13 2022-02-17 2022-08-16 Adjoint au Resp PS d'exécution poor households MR-SSNS-219266-CS-INDV / Component 2: Enhancing the En attente Adjoint au Resp paiement IDA / D5680 socio-economic inclusion of A posteriori Individuel Direct 0.00 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 d'exécution (02) poor households MR-SSNS-219268-CS-INDV / Component 2: Enhancing the En attente 6 Facilitateurs "promotion IDA / D5680 socio-economic inclusion of A posteriori Individuel Direct 0.00 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 d'exécution dialogue familial" poor households MR-SSNS-219269-CS-INDV / Component 4: Project En attente Responsable Financier et IDA / D5680 Coordination and A posteriori Individuel Direct 0.00 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 d'exécution Comptable Management Component 4: Project MR-SSNS-219270-CS-INDV / En attente IDA / D5680 Coordination and A posteriori Individuel Direct 0.00 2021-12-16 2021-12-26 2022-01-16 2022-02-20 2022-08-19 Responsable Social et genre d'exécution Management MR-SSNS-219271-CS-INDV / Component 4: Project En attente Assistant Passation des IDA / D5680 Coordination and A posteriori Individuel Direct 0.00 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 d'exécution Marchés Management Component 4: Project MR-SSNS-219272-CS-INDV / En attente IDA / D5680 Coordination and A posteriori Individuel Direct 0.00 2021-12-16 2021-12-26 2022-01-16 2022-02-20 2022-08-19 Assistant communication d'exécution Management MR-SSNS-254473-CS-CDS / Conception et la production Sélection de des cartes graphiques pour Component 1: Updating and En attente IDA / D5680 A posteriori consultants par Direct 0.00 2021-09-22 2021-10-02 2021-12-06 2022-06-04 les districts de recensement enhancing the Social Registry d'exécution entente directe des neuves communes de Nouakchott Component 2: Enhancing the MR-SSNS-254598-CS-INDV / En attente IDA / D5680 socio-economic inclusion of A posteriori Individuel Open 0.00 2021-09-22 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Animateur Tintane d'exécution poor households MR-SSNS-254603-CS-INDV / Component 1: Updating and En attente IDA / D5680 A posteriori Individuel Open 0.00 2021-09-22 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Deux 2 animateurs pour le RS enhancing the Social Registry d'exécution MR-SSNS-254606-CS-INDV / Component 1: Updating and En attente IDA / D5680 A posteriori Individuel Open 0.00 2021-09-22 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Assistant RSI enhancing the Social Registry d'exécution Component 2: Enhancing the MR-SSNS-254613-CS-INDV / En attente IDA / D5680 socio-economic inclusion of A posteriori Individuel Open 0.00 2021-09-27 2021-11-15 2021-12-06 2022-01-10 2022-07-09 Superviseur Koubeni d'exécution poor households Component 3: Strengthening MR-SSNS-219214-CS-INDV / the shock response system En attente Assistant technique du IDA / D5680 A posteriori Individuel Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 for households vulnerable to d'exécution programme ELMAOUNA climate-shocks MR-SSNS-219217-CS-INDV / Component 1: Updating and En attente IDA / D5680 A posteriori Individuel Open 0.00 2021-02-24 2021-04-14 2021-05-05 2021-06-09 2021-12-06 Assistant mise à jour du RS enhancing the Social Registry d'exécution MR-SSNS-219103-CS-INDV / Component 3: Strengthening Consultant International the shock response system En attente Appui à la mise en place d'un IDA / D5680 A posteriori Individuel Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 for households vulnerable to d'exécution cadre permanent de réponse climate-shocks aux chocs Component 3: Strengthening MR-SSNS-219193-CS-INDV / the shock response system En attente IDA / D5680 A posteriori Individuel Open 0.00 2021-02-24 2021-04-14 2021-05-05 2021-06-09 2021-12-06 Statisticien junior OSA for households vulnerable to d'exécution climate-shocks Page 5