PROCUREMENT PLAN Poverty Reduction Fund Project, Phase III (Project ID: P157963) Revised as of 11 May 2017 I. GENERAL 1. Project information - Country: Lao PDR - Borrower/Recipient: Lao PDR - Project Name: Poverty Reduction Fund Project, Phase III - Project ID No: P157963 - Project Implementing Agency: Poverty Reduction Fund, 2. Bank’s approval Date of the procurement Plan: - Original Plan: 28 April 2016 - First revised: 11 May 2017 3. Date of General Procurement Notice: - UNDB online: 19 April 2017 4. Period covered by this procurement plan:18 months II. GOODS AND WORKS AND NON-CONSULTING SERVICES 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Contract Value Prior Review No. Procurement Method Comments Threshold USD Threshold USD 1 ICB (Goods) >=600,000 All contracts above 1.5 million 2 NCB (Goods) 100,000 - None <600,000 3 Shopping (Goods) <100,000 None 4 Direct Contracting (Goods, - All contracts Subject to Works, and Non-consulting above 1.5 the Bank Services) million and 5 approval. million for goods and works respectively 5 ICB (Works) >= 2,000,000 All contracts above 5 million 6 NCB (Works) 200,000 - None <2,000,000 7 Shopping (Works) <200,000 None 8 Procurement from UN <600,000 None Use World agencies (Goods) Bank-UN contract template 1 2. Prequalification: Not expected for the works/goods packages 3. Reference to Project Operational Manual: PRF III 4. Any Other Special Procurement Arrangements: N/A 5. Procurement Packages for Works & Goods (prior & post reviews) with Methods and Time Schedule: The following table lists goods, furniture, works contracts for which procurement activities are expected to commence during the project cycle. A. Goods Domesti Review Expecte Estimat PQ c Contract Proc. by Bank d Bid/ No. ed Cost (yes Preferen Comment (Description) Method (Prior / Openin USD /no) ce Post) g Date (yes/no) G00 Procurement of 3 99,000 Shoppi No No Post Dec- Completed 1 Pick-ups 4x4 WD ng 2016 Keo Auto Co. Double Cab (1,078,000 ,000 LAK) G00 Procurement of 40 52,000 Shoppi No No Post Dec- 3 Motorcycles 100-125 ng 2017 cc G00 Procurement of IT 144,900 Shoppi No No Post Dec- 4 equipment ng 2017 G00 Procurement of 2,500 Shoppi No No Post Dec- 5 Furniture for PRF ng 2017 Central Office G00 Procurement of 15,600 Shoppi No No Post Oct- Multiple 6 Furniture for ng 2017 packages or framework Provinces and contract districts (600 USD per Office) G00 Procurement of 3 99,000 Shoppi No No Post Dec- 7 Pick-ups 4x4 WD ng 2018 Double Cab G00 Procurement of 58 75,400 Shoppi No No Post Dec- 8 Motorcycles 100-125 ng 2018 cc G00 Procurement of IT 90,000 Shoppi No No Post Dec- 9 equipment ng 2018 G01 Procurement of 15,600 Shoppi No No Post Dec- Multiple 0 Furniture for ng 2018 packages or framework provinces and contract districts (600 USD per Office) Total (Goods): 594,000 B. WORKS Contract Estimat Proc. PQ Domesti Review Expecte No. Comment (Description) ed Cost Method (yes c by d Bid/ 2 USD /no) Preferen Bank Openin ce (Prior / g Date (yes/no) Post) W001 PRF Central Off. 19,600 Shoppi No No Post Dec- repair ng 2018 W002 PRF Province Off. 7,500 Shoppi No No Post Dec- Multiple repair (1,500 USD ng 2017 packages each office) W003 PRF District Off. 25,200 Shoppi No No Post Dec- Multiple repair (1,200 USD ng 2017 packages each office) W004 PRF Province Off. 7,500 Shoppi No No Post Dec- Multiple repair (1,500 USD ng 2018 packages each office) W005 PRF District Off. 25,200 Shoppi No No Post Dec- Multiple Repair (1,200 USD ng 2018 packages each office) Total (Works): 85,000 C. IEC Materials Revie Expecte Domesti PQ w by d Bid/ Estimat c Proc. (ye Bank Quotati No. Contract (Description) ed Cost Preferen Comment Method s/n (Prior on USD ce o) / Openin (yes/no) Post) g Date IEC01 Produce PRF Calendar, 45,000 Shoppi No No Post Dec- Diary, logo, sticker, ng 2017 brochure, T-shirt etc…. IEC02 Printing manual, 50,000 Shoppi No No Post Sep- guideline, report, etc… ng 2017 IEC03 Produce PRF story video 45,000 Shoppi No No Post Sep- and etc… ng 2017 IEC04 Printing Livelihoods and 17,500 Shoppi No No Post Jan- Nutrition IEC materials ng 2018 Total (IEC): 157,500 Total (Goods + Works + IEC) = 836,500 III. SELECTION OF CONSULTANTS 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Contract Value Prior Review No. Selection Method Comments Threshold Threshold (USD) (USD) 1 Competitive Methods (Firms) – >=300,000 All contracts above Quality & Cost Based Selection 500,000 (QCBS) and Quality Based Selection (QBS) 3 Contract Value Prior Review No. Selection Method Comments Threshold Threshold (USD) (USD) 2 Competitive Methods (Firms) – <300,000 None Least-Cost Selection (LCS) and Selection Based on Consultant Qualifications (CQS) 3 Single Source All contracts above Subject to the 500,000 and 200,000 Bank approval. for firm and individual consultant respectively 4 Individual Consultants All contract above Project staff may 200,000 for entire be employed over project duration. All entire duration of ToRs require World project or as Bank clearance requirement subject to annual performance review. Contract extension shall be subject to post review. 2. Short list comprising entirely of national consultants: No short lists of consultants for services are expected to comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. However, if a need arises during the project implementation and if it is warranted, short lists of consultants for services estimated to cost less than $200,000 equivalent per contract may be composed entirely of national consultants 3. Any Other Special Selection Arrangements: Advance contracting may be applied for some items as specified in the Procurement Plan. All existing project staff will be single source subject to satisfactory performance review by the Project and Bank. 4. Consultancy Assignments with Selection Methods (prior & post reviews) and Time Schedule 5. For all individual contract amendments /extensions/ follow-on contracts, etc., the following guidelines shall apply: i) gross salary increases shall be limited to CPI plus a performance-based increase not to exceed 2% of the current contract per annum; ii) there shall be no increase in living allowances or similar expenses unless explicitly authorized by MOF Decree. Estimat Selectio Bank Expecte Description of Consultant Sr. e Cost n Revie d EOI Comments Services (USD) Method w Date C00 PRF: 197 Local Staff (Central 3,133,1 SSS Post Dec- Completed 1 Provincial and District staff ) 71 2016 Continuation contracts C00 LN: 52 Local Staff 375,500 SSS Post Jan- Completed 2 2017 Continuation contracts C00 International Institutional 19,840 SSS Post Jun- Continuation. 3 Development Consultant 2017 Dr. Gamini Premaratna Batuwitage 4 Estimat Selectio Bank Expecte Description of Consultant Sr. e Cost n Revie d EOI Comments Services (USD) Method w Date C00 International TA 17,000 SSS Post Jun- Continuation. 4 2017 Garvan O’Keeffe C00 International M&E 12,000 SSS Post Jun- Continuation. 5 2017 George Norman Collet C00 International Internal Audit 5,661 SSS Post Jul-2017 Continuation. 6 Advisor Competitive selection under PRF II. Bishwakanta Gautam C00 Senior Technical Advisor 93,636 SSS Post Jan- Completed 7 2017 Julien Rossard C00 Technical, Cost Effectiveness, 70,000 CQS Post Feb- 8 Cost Benefits Assessment 2018 C00 ACCPAC Accounting System 10,000 CQS Post Feb- 9 Software Upgrading 2018 C01 Providing capacity building 5,000 IC Post Jun- 0 and assistance on website 2017 improvement, update and maintenance C01 External Audit FY 2016-2017 25,000 CQS Post Jun- 1 2017 C01 PRF Process Evaluation 50,000 CQS Post Nov- 2 Assessment 2018 C01 Organization Assessment 50,000 CQS Post Dec- 3 2017 C01 HH Survey (Impact Evaluation) 50,000 CQS Post Mar- 4 2019 C01 International Road 25,000 SSS Post May- Continuation. 5 Maintenance and Management 2017 Competitive selection under PRF II (SDC Fund). Mr. Serge Cartier van Dissel C01 International Disaster Risk 25,000 IC Post Jun- Under SDC Fund 6 Management (DRM) 2017 Grand Total : 3,966,8 08 5 PROCUREMENT Lao People's Democratic Republic : Poverty Reduction Fund III PLAN General Information Country: Lao People's Democratic Republic Bank’s Approval Date of the Original Procurement Plan: 2017-08-24 2021-03-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157963 GPN Date: 2017-04-18 Project Name: Poverty Reduction Fund III Loan / Credit No: IDA / 58270 Poverty Reduction Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G003 / 40 Motorcycles 100- Component 3 ? Project Request for Single Stage - One IDA / 58270 Post Limited 52,000.00 0.00 Canceled 2017-12-31 2017-12-31 2017-12-31 125 cc Management Quotations Envelope G001 / 3 Pick-up Trucks 4x4 Component 3 ? Project Request for Single Stage - One IDA / 58270 Post Limited 99,000.00 126,446.15 Completed 2016-10-14 2016-11-15 2016-11-15 2017-03-10 2017-03-10 WD Double Cab Management Quotations Envelope Component 4 ? Nutrition IEC04 / Printing Livelihoods Request for Single Stage - One IDA / 58270 Enhancing Livelihood Post Limited 17,500.00 0.00 Canceled 2018-02-05 2018-04-02 2018-09-29 and Nutrition IEC Material Quotations Envelope Development Component 2 ? Local and IEC03 / Produce PRF Story Request for Single Stage - One IDA / 58270 Community Development Post Limited 36,000.00 12,317.55 Completed 2018-04-30 2018-04-30 2018-04-24 2018-04-30 2018-11-21 Video and etc… Quotations Envelope Capacity Building Component 2 ? Local and IEC02 / Printing Manuals, Request for Single Stage - One IDA / 58270 Community Development Post Limited 50,000.00 89,222.04 Signed 2017-09-30 2017-09-30 2018-06-29 2017-09-30 Guidelines, Reports, etc... Quotations Envelope Capacity Building IEC01 / Produce PRF Component 2 ? Local and Request for Single Stage - One Calendar, Diary, Logo, Sticker, IDA / 58270 Community Development Post Limited 45,000.00 38,640.74 Completed 2018-01-31 2018-01-31 2018-02-21 2018-01-31 2018-06-19 Quotations Envelope Brochure, T-shirt etc…. Capacity Building G011 / TA survey tools including 12 Schmidt Component 3 ? Project Request for Single Stage - One hammers, 5 Dynamic Cone IDA / 58270 Post Limited 55,000.00 35,340.20 Completed 2018-03-05 2018-03-15 2018-04-30 2018-04-25 2018-10-27 2018-05-16 Management Quotations Envelope Spectrometers, 45 Abney levels G007 / 3 Pick-up Trucks 4x4 Component 3 ? Project Request for Single Stage - One IDA / 58270 Post Limited 99,000.00 128,689.57 Completed 2018-12-31 2018-12-31 2019-06-12 2018-12-31 2019-08-13 WD Double Cab Management Quotations Envelope IEC06 / Printing field construction record book and Component 2 ? Local and Request for Single Stage - One quality control book (compare IDA / 58270 Community Development Post Limited 17,900.00 16,616.37 Completed 2018-04-07 2018-03-30 2018-06-02 2018-04-26 2018-11-29 2018-06-08 Quotations Envelope equipment for construction Capacity Building good and bad pictograph) G004 / Procurement of equipment support to IEC Component 3 ? Project Request for Single Stage - One IDA / 58270 Post Limited 13,000.00 12,714.15 Completed 2018-10-05 2018-09-19 2018-11-30 2018-10-19 2019-05-29 2018-11-20 (Camera Lens, Battery and Management Quotations Envelope ect....) G008 / 58 Motorcycles 100- Component 3 ? Project Request for Single Stage - One IDA / 58270 Post Limited 75,400.00 0.00 Canceled 2018-12-31 2018-12-31 2018-12-31 125 cc Management Quotations Envelope G009 / IT Equipment Component 3 ? Project Request for Single Stage - One IDA / 58270 Post Limited 90,000.00 0.00 Canceled 2018-12-31 2018-12-31 2018-12-31 (Computer, Printer, etc...) Management Quotations Envelope Component 2 ? Local and Pending AF-G-001 / Sub-project IEC Request for Single Stage - One IDA / 58270 Community Development Post Limited 36,000.00 0.00 Implementati 2020-04-05 2020-05-31 2020-11-27 Materials Quotations Envelope Capacity Building on Component 2 ? Local and AF-G-002 / Environmental Request for Single Stage - One IDA / 58270 Community Development Post Limited 2,400.00 1,975.43 Completed 2020-02-05 2020-03-10 2020-04-01 2020-04-02 2020-09-28 2020-05-04 and Social Safeguards Quotations Envelope Capacity Building AF-G-003 / Office IT Component 3 ? Project Request for Single Stage - One IDA / 58270 Post Open - National 66,000.00 43,655.55 Completed 2020-03-04 2020-04-29 2020-07-09 2020-10-26 2020-09-08 Equipment Management Quotations Envelope Pending Component 3 ? Project Single Stage - One AF-G-004 / Motorbikes IDA / 58270 Post Request for Bids Open - National 252,000.00 0.00 Implementati 2020-01-31 2020-02-05 2020-03-18 2020-04-17 2020-05-22 2020-11-18 Management Envelope on Component 4 ? Nutrition Request for Single Stage - One AF-G-005 / Record Books IDA / 58270 Enhancing Livelihood Post Limited 43,525.00 41,495.23 Completed 2020-02-05 2020-05-18 2020-04-01 2020-06-12 2020-09-28 2020-08-17 Quotations Envelope Development Component 4 ? Nutrition Pending AF-G-006 / Floor Mats, Request for Single Stage - One IDA / 58270 Enhancing Livelihood Post Limited 52,255.00 0.00 Implementati 2020-04-05 2020-05-31 2020-11-27 Boxes Quotations Envelope Development on Component 4 ? Nutrition AF-G-007 / Produce Posters, Request for Single Stage - One IDA / 58270 Enhancing Livelihood Post Open - National 23,088.00 15,131.05 Completed 2020-04-05 2020-05-31 2020-07-12 2020-11-27 2020-08-17 Leaflets, etc... Quotations Envelope Development AF-G-008 / Mills, Plastic Component 4 ? Nutrition Request for Single Stage - One Boxes, Extension Cords and IDA / 58270 Enhancing Livelihood Post Limited 23,850.00 23,208.77 Completed 2020-04-05 2020-07-30 2020-05-31 2020-08-25 2020-11-27 2020-09-10 Quotations Envelope Adapter Development Page 1 Component 4 ? Nutrition Request for Single Stage - One AF-G-009 / Cooking Sets IDA / 58270 Enhancing Livelihood Post Limited 52,470.00 47,630.15 Completed 2020-05-05 2020-08-06 2020-06-30 2020-08-27 2020-12-27 2020-10-02 Quotations Envelope Development Component 4 ? Nutrition Pending AF-G-010 / Stoves IDA / 58270 Enhancing Livelihood Post Direct Selection Direct 5,000.00 0.00 Implementati 2020-03-31 2020-04-05 2020-05-10 2020-11-06 Development on Component 4 ? Nutrition Pending AF-G-011 / Pellet Machines IDA / 58270 Enhancing Livelihood Post Direct Selection Direct 20,000.00 0.00 Implementati 2020-03-31 2020-04-05 2020-05-10 2020-11-06 and Driers Development on Component 4 ? Nutrition Pending AF-G-012 / Pellets IDA / 58270 Enhancing Livelihood Post Direct Selection Direct 5,824.00 0.00 Implementati 2020-03-31 2020-04-05 2020-05-10 2020-11-06 Development on Component 4 ? Nutrition Pending AF-G-013 / Stove Top up IDA / 58270 Enhancing Livelihood Post Direct Selection Direct 500.00 0.00 Implementati 2020-03-31 2020-04-05 2020-05-10 2020-11-06 Development on Component 4 ? Nutrition Pending Request for Single Stage - One AF-G-014 / Cooking Book IDA / 58270 Enhancing Livelihood Post Limited 24,310.00 0.00 Implementati 2020-05-05 2020-06-30 2020-12-27 Quotations Envelope Development on AF-G-015 / Agricultural Component 4 ? Nutrition Request for Single Stage - One Seasonal Calendar and Crop IDA / 58270 Enhancing Livelihood Post Limited 4,770.00 5,108.86 Completed 2020-09-05 2020-07-30 2020-10-31 2020-08-26 2021-04-29 2020-09-22 Quotations Envelope Sheets Development AF-G-016 / Microphones, Component 4 ? Nutrition Request for Single Stage - One Phone Projectors, Speakers, IDA / 58270 Enhancing Livelihood Post Limited 95,400.00 148,247.04 Signed 2020-02-05 2020-07-22 2020-04-01 2020-08-27 2020-09-28 Quotations Envelope and Phone Credit Development Component 4 ? Nutrition Pending AF-G-017 / Shade house Single Stage - One IDA / 58270 Enhancing Livelihood Post Request for Bids Open - National 108,750.00 0.00 Implementati 2020-03-31 2020-04-05 2020-05-17 2020-06-16 2020-07-21 2021-01-17 Materials Envelope Development on Component 4 ? Nutrition Request for Single Stage - One AF-G-018 / Seeds IDA / 58270 Enhancing Livelihood Post Limited 87,000.00 0.00 Canceled 2020-03-04 2020-04-29 2020-10-26 Quotations Envelope Development NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4 ? Nutrition Under AF-C.033 / Multi-media Peer IDA / 58270 Enhancing Livelihood Post Direct Selection Direct 160,000.00 0.00 Implementati 2020-06-01 2021-03-09 2020-06-06 2020-07-11 2021-01-07 Learning Development on Component 4 ? Nutrition Pending FA-NC.001 / Buffalo Dairy IDA / 58270 Enhancing Livelihood Post Direct Selection Direct 55,000.00 0.00 Implementati 2020-06-01 2020-06-06 2020-07-11 2021-01-07 Development on Component 4 ? Nutrition Under AF-NC.002 / Home Nutrition IDA / 58270 Enhancing Livelihood Post Direct Selection Direct 186,000.00 0.00 Implementati 2020-06-01 2021-03-09 2020-06-06 2020-07-11 2021-01-07 Garden Development on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Consultant C011 / External Audit of PRF Component 3 ? Project IDA / 58270 Post Qualification Open - National 38,000.00 37,953.00 Signed 2017-06-30 2018-04-10 2017-06-30 2017-06-30 2017-04-28 2017-06-30 2017-07-27 2017-06-30 2017-09-13 2017-06-30 III for fiscal year 2016-2020 Management Selection Component 2 ? Local and Consultant C009 / ACCPAC Accounting IDA / 58270 Community Development Post Qualification Open - National 10,000.00 0.00 Canceled 2018-02-28 2018-02-28 2018-02-28 2018-02-28 2018-02-28 2018-02-28 System Software Upgrading Capacity Building Selection Component 2 ? Local and Consultant C013 / Organization IDA / 58270 Community Development Post Qualification Open - National 50,000.00 0.00 Canceled 2017-12-31 2017-12-31 2017-12-31 2017-12-31 2017-12-31 2017-12-31 Assessment Capacity Building Selection Component 2 ? Local and Consultant C012 / PRF Process IDA / 58270 Community Development Post Qualification Open - National 50,000.00 0.00 Canceled 2018-11-30 2018-11-30 2018-11-30 2018-11-30 2018-11-30 2018-11-30 Evaluation Assessment Capacity Building Selection C008 / Technical, Cost Component 2 ? Local and Consultant Effectiveness, Cost Benefits IDA / 58270 Community Development Post Qualification Open - National 70,000.00 91,041.00 Completed 2019-04-30 2017-12-04 2019-04-30 2019-04-30 2018-02-06 2019-04-30 2018-02-28 2019-04-30 2018-03-12 2019-04-30 2018-05-18 Assessment Capacity Building Selection Component 4 ? Nutrition Consultant C016 / Micro-finance IDA / 58270 Enhancing Livelihood Post Qualification Open - National 20,000.00 21,850.00 Completed 2018-10-31 2018-11-01 2018-11-21 2018-11-21 2019-01-04 2019-01-10 2019-02-03 2019-02-20 2019-03-10 2019-03-13 2019-09-06 2020-01-28 Services Development Selection Component 2 ? Local and Consultant C014 / HH Survey (Impact IDA / 58270 Community Development Post Qualification Open - National 50,000.00 0.00 Canceled 2019-11-15 2019-11-30 2019-11-30 2019-11-30 2019-11-30 2019-11-30 Evaluation) Capacity Building Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C003 / International Component 2 ? Local and Institutional Development IDA / 58270 Community Development Post Direct Selection Direct 19,840.00 0.00 Canceled 2017-06-30 2017-06-30 2017-07-21 2018-01-17 Consultant Capacity Building Page 2 Component 2 ? Local and C004 / International TA IDA / 58270 Community Development Post Direct Selection Direct 17,000.00 0.00 Canceled 2017-06-30 2017-06-30 2017-07-21 2018-01-17 Specialist Capacity Building Component 2 ? Local and C005 / International M&E IDA / 58270 Community Development Post Direct Selection Direct 12,000.00 18,395.00 Terminated 2018-03-31 2018-01-08 2018-03-31 2018-01-08 2018-04-21 2018-03-19 2018-10-18 Consultant Capacity Building C015 / International Component 2 ? Local and Community Force Account IDA / 58270 Community Development Post Direct Selection Direct 30,000.00 61,887.00 Signed 2018-03-30 2017-12-04 2018-04-09 2018-01-08 2018-06-13 2018-03-19 2018-12-10 (CFA) Specialist Capacity Building C010 / PRF III website Component 2 ? Local and Individual improvement, update and IDA / 58270 Community Development Post Consultant Limited 5,000.00 7,342.00 Completed 2018-03-31 2017-12-04 2018-03-31 2018-03-31 2018-03-06 2018-03-31 2018-03-14 2018-03-31 2018-09-19 maintenance Capacity Building Selection Component 2 ? Local and C007 / Senior Technical IDA / 58270 Community Development Post Direct Selection Direct 93,636.00 96,468.00 Completed 2017-01-31 2017-01-31 2017-02-21 2018-01-05 2017-08-20 2018-09-15 Advisor Capacity Building Component 2 ? Local and C006 / International Internal IDA / 58270 Community Development Post Direct Selection Direct 5,661.00 6,235.00 Completed 2017-07-31 2017-06-13 2017-07-31 2017-08-21 2017-07-18 2018-02-17 2018-02-01 Audit Advisor Capacity Building Individual C017 / National Senior Component 3 ? Project IDA / 58270 Post Consultant Limited 21,000.00 20,766.27 Completed 2018-10-31 2018-08-14 2018-11-05 2018-09-06 2018-11-26 2018-10-15 2018-12-31 2018-10-16 2019-06-29 2019-12-31 Capacity Building Officer Management Selection Individual C018 / National Technical Component 3 ? Project IDA / 58270 Post Consultant Limited 23,000.00 22,745.01 Completed 2018-10-31 2018-08-14 2018-11-05 2018-09-06 2018-11-26 2018-10-15 2018-12-31 2018-10-16 2019-06-29 2019-12-31 Internal Audit Officer Management Selection C019 / Training on Home Nutrition Garden and Component 4 ? Nutrition Community Video IDA / 58270 Enhancing Livelihood Post Direct Selection Direct 12,167.00 11,683.32 Completed 2019-08-21 2019-07-21 2019-08-31 2019-08-23 2019-11-04 2019-09-30 2020-05-02 2020-05-29 Development of 2 Buffalo Development Dairy Product and 1 Home Nutrition Garden Construction Component 4 ? Nutrition C020 / Training on technical IDA / 58270 Enhancing Livelihood Post Direct Selection Direct 13,500.00 12,176.39 Signed 2019-08-21 2019-07-21 2019-08-31 2019-08-23 2019-11-04 2019-11-18 2020-05-02 skill for raising dairy buffaloes Development AF-C.031 / External Financial Component 3 ? Project Pending IDA / 58270 Post Direct Selection Direct 42,500.00 0.00 2020-09-01 2020-09-11 2020-11-15 2021-05-14 Audit Management Implementation AF-C.001 / Executive Component 3 ? Project IDA / 58270 Post Direct Selection Direct 58,834.00 58,834.00 Signed 2020-01-31 2019-12-18 2020-02-10 2019-12-24 2020-04-15 2019-12-30 2020-10-12 Director Management Individual AF-C.002 / Deputy Executive Component 3 ? Project IDA / 58270 Post Consultant Open 41,565.00 38,104.00 Signed 2020-01-31 2019-12-18 2020-03-20 2020-01-23 2020-04-10 2020-01-27 2020-05-15 2020-02-01 2020-11-11 Director Management Selection AF-C.003 / TA Specialist Component 3 ? Project IDA / 58270 Post Direct Selection Direct 41,526.00 85,134.00 Signed 2020-01-31 2019-12-18 2020-02-10 2019-12-24 2020-04-15 2019-12-30 2020-10-12 (Head) Management Individual Component 3 ? Project AF-C.004 / TA Assistant IDA / 58270 Post Consultant Open 23,057.00 42,940.00 Signed 2020-01-31 2019-12-18 2020-03-20 2020-01-24 2020-04-10 2020-01-27 2020-05-15 2020-03-01 2020-11-11 Management Selection AF-C.005 / Monitoring Component 3 ? Project IDA / 58270 Post Direct Selection Direct 35,700.00 73,188.00 Signed 2020-01-31 2019-12-18 2020-02-10 2019-12-24 2020-04-15 2019-12-30 2020-10-12 &Evaluation Specialist (Head) Management Individual Component 3 ? Project AF-C.006 / MIS Officer IDA / 58270 Post Consultant Open 15,610.00 17,006.00 Signed 2020-01-31 2019-12-18 2020-03-20 2020-01-24 2020-04-10 2020-01-27 2020-05-15 2020-02-01 2020-11-11 Management Selection Individual AF-C.007 / Reporting and Component 3 ? Project IDA / 58270 Post Consultant Open 15,609.00 12,000.00 Terminated 2020-01-31 2019-12-18 2020-03-20 2020-01-24 2020-04-10 2020-01-27 2020-05-15 2020-03-01 2020-11-11 Evaluation Officer Management Selection AF-C.008 / Finance and Component 3 ? Project Administration Specialist IDA / 58270 Post Direct Selection Direct 41,526.00 85,134.00 Signed 2020-01-31 2019-12-18 2020-02-10 2019-12-24 2020-04-15 2019-12-30 2020-10-12 Management (Head) AF-C.009 / FM Supervision Component 3 ? Project IDA / 58270 Post Direct Selection Direct 28,223.00 57,863.00 Signed 2020-01-31 2019-12-18 2020-02-10 2019-12-24 2020-04-15 2019-12-30 2020-10-12 Officer Management AF-C.010 / Accountant Component 3 ? Project IDA / 58270 Post Direct Selection Direct 28,224.00 57,864.00 Signed 2020-01-31 2019-12-18 2020-02-10 2019-12-24 2020-04-15 2019-12-30 2020-10-12 Officer Management AF-C.011 / Accounting Component 3 ? Project IDA / 58270 Post Direct Selection Direct 19,092.00 39,144.00 Signed 2020-01-31 2019-12-18 2020-02-10 2019-12-24 2020-04-15 2019-12-30 2020-10-12 Package Officer Management Component 3 ? Project AF-C.012 / Cashier IDA / 58270 Post Direct Selection Direct 10,391.00 21,299.00 Signed 2020-01-31 2019-12-18 2020-02-10 2019-12-24 2020-04-15 2019-12-30 2020-10-12 Management AF-C.013 / Procurement Component 3 ? Project IDA / 58270 Post Direct Selection Direct 30,812.00 63,164.00 Signed 2020-01-31 2019-12-18 2020-02-10 2019-12-24 2020-04-15 2019-12-30 2020-10-12 Officer Management Individual AF-C.014 / Procurement Component 3 ? Project IDA / 58270 Post Consultant Open 13,031.00 22,780.00 Signed 2020-01-31 2019-12-18 2020-03-20 2020-04-30 2020-04-10 2020-04-30 2020-05-15 2020-05-01 2020-11-11 Assistant Management Selection Component 3 ? Project AF-C.015 / IT Officer IDA / 58270 Post Direct Selection Direct 19,092.00 39,144.00 Signed 2020-01-31 2019-12-18 2020-02-10 2019-12-24 2020-04-15 2019-12-30 2020-10-12 Management Individual AF-C.016 / Administration Component 3 ? Project IDA / 58270 Post Consultant Open 8,967.00 13,130.00 Signed 2020-01-31 2019-12-18 2020-03-20 2020-01-24 2020-04-10 2020-01-27 2020-05-15 2020-02-01 2020-11-11 Assistant Management Selection AF-C.017 / Nutrition & Individual Component 3 ? Project Community Development IDA / 58270 Post Consultant Open 35,700.00 37,800.00 Signed 2020-01-31 2019-12-18 2020-03-20 2020-01-24 2020-04-10 2020-01-27 2020-05-15 2020-02-01 2020-11-11 Management Specialist (Head) Selection Page 3 Individual AF-C.018 / Capacity Component 3 ? Project IDA / 58270 Post Consultant Open 21,951.00 21,000.00 Signed 2020-01-31 2019-12-18 2020-03-20 2020-01-24 2020-04-10 2020-01-27 2020-05-15 2020-02-01 2020-11-11 Development Officer Management Selection Component 4 ? Nutrition AF-C.019 / Agriculture & IDA / 58270 Enhancing Livelihood Post Direct Selection Direct 33,305.00 68,273.00 Signed 2020-01-31 2019-12-18 2020-02-10 2019-12-24 2020-04-15 2019-12-30 2020-10-12 Livelihood Specialist (Head) Development Component 4 ? Nutrition Individual AF-C.020 / Micro-Finance IDA / 58270 Enhancing Livelihood Post Consultant Open 23,058.00 15,400.00 Terminated 2020-01-31 2019-12-18 2020-03-20 2020-01-24 2020-04-10 2020-01-27 2020-05-15 2020-02-01 2020-11-11 Officer Development Selection Component 4 ? Nutrition Individual AF-C.021 / Micro-Finance IDA / 58270 Enhancing Livelihood Post Consultant Open 15,372.00 10,000.00 Terminated 2020-01-31 2019-12-18 2020-03-20 2020-01-24 2020-04-10 2020-01-27 2020-05-15 2020-02-01 2020-11-11 Assistant Development Selection Component 4 ? Nutrition Individual AF-C.022 / Agricultural & IDA / 58270 Enhancing Livelihood Post Consultant Open 25,620.00 40,940.00 Signed 2020-01-31 2019-12-18 2020-03-20 2020-01-24 2020-04-10 2020-01-27 2020-05-15 2020-02-01 2020-11-11 Livestock Officer Development Selection Component 4 ? Nutrition Individual AF-C.023 / Senior Nutrition IDA / 58270 Enhancing Livelihood Post Consultant Open 29,392.00 15,730.00 Terminated 2020-01-31 2019-12-18 2020-03-20 2020-01-24 2020-04-10 2020-01-27 2020-05-15 2020-02-01 2020-11-11 Officer Development Selection Component 4 ? Nutrition Individual AF-C.021-1 / Micro-finance IDA / 58270 Enhancing Livelihood Post Consultant Open 12,372.00 21,761.00 Signed 2020-07-11 2019-12-18 2020-07-22 2020-05-29 2020-08-12 2020-06-02 2020-09-16 2020-07-21 2021-03-15 Assistant Development Selection Individual AF-C.007-1 / Reporting and Component 3 ? Project IDA / 58270 Post Consultant Open 10,809.00 24,180.00 Signed 2020-07-11 2019-12-18 2020-08-29 2020-06-22 2020-09-19 2020-06-24 2020-10-24 2020-07-01 2021-04-22 Evaluation Officer Management Selection Component 4 ? Nutrition Individual AF-C.023-1 / Senior IDA / 58270 Enhancing Livelihood Post Consultant Open 22,238.00 36,000.00 Signed 2020-07-11 2019-12-18 2020-08-29 2020-06-21 2020-09-19 2020-06-25 2020-10-24 2020-07-01 2021-04-22 Nutrition Officer Development Selection Component 4 ? Nutrition Individual AF-C.020-1 / Microfinance Pending IDA / 58270 Enhancing Livelihood Post Consultant Open 21,600.00 0.00 2021-03-04 2021-04-22 2021-05-13 2021-06-17 2021-12-14 Officer Implementation Development Selection Page 4