RP1645 V2 THE UNITED REPUBLIC OF TANZANIA Report prepared for The Dar es Salaam Water and Sanitation Authority (DAWASA) . Volume 3: RESETTLEMENT ACTION PLAN KIMBIJI AND MPERA WATER PROJECTS [This report: The Resettlement Action Plan (RAP) details the mitigation measures of the effects of resettlement that might be caused by the implementation of the Kimbiji and Mpera Water projects. The RAP was developed through a process of public consultation with all interested and affected parties. This was particularly important as proper consultation with affected parties can increase the effectiveness and reduce the costs of RAP implementation. As part of Disclosure requirement, this document on the Resettlement Action Plan must be widely disclosed to people affected by the project (PAP), to areas where the PAP will be settled to, local and central government and financiers.] EXECUTIVE SUMMARY Introduction This Resettlement Action Plan has been developed to address displacement impacts that will be caused by the deep well projects consisting of the Kisarawe II (20 deep wells, water mains pipe network to the water storage facilities) and a similar composition for 10 wells, water mains pipe network to the water storage facilities for the Mpera well field. Project Rationale The project will exploit suitable groundwater aquifers to improve water supply security for the city of Dar es Salaam and some areas of the Coast region e.g. Mkuranga district. Dar es Salaam for example currently experiences a deficit of 135,634 m3/d, which would reach 687,982 m3/day by year 2032. The RAP has been prepared through a process of public consultation with all interested and affected parties. This was particularly important as proper consultation with affected parties can increase the effectiveness and reduce the costs of RAP implementation. Limitations of this Resettlement Action Plan To fast track development of the water wells, it was decided to break the RAP into two components that will be phased. This Phase I RAP covers the Kimbiji (Kisarawe II) and Mpera well field, areas covered by the transmission lines to water storage facilities and areas required for the construction of water tanks/storage facilities. The protection of the remaining area required to protect the complete water catchment areas will be addressed in the Phase II RAP II. This RAP has been prepared in accordance with the existing Resettlement Policy Framework and The World Bank policy, World Bank policy on involuntary resettlement (OP 4.12). The objective being to avoid or minimize resettlement; if unavoidable, to enable affected people to share project benefits through meaningful consultation and participation in planning; and to assist people restore or improve their livelihoods Categories and Estimates of Project Affected People ii The survey was conducted by a team involving the municipal valuer, land owner, land surveyor, village chairman, ward chairman or a witness for the land owner. When the survey was completed, a survey form was signed by the team. The survey data included identified the number of people, their assets (buildings of whatever nature, economic activities, land, crops, etc.). The total number of Project Affected People (PAP) in the project components involved in this Phase I RAP I are 143 (67 persons in the Kimbiji (Kisarawe II) well field; 63 persons for the Mpera well field; and 14 persons for the water storage facility areas at Pugu Kajiungeni and Buyuni. The compensation entitlement was The Land Act No.4 and Village Land Act No. 5 of 1999 have set clear procedures for full, fair and prompt compensation while acquiring land from citizens. These procedures were adhered to, especially the Land (assessment of the value of compensation) Regulations - made under S.179 of Land Act No.4 of 1999. Appropriate corrections to meet the World Bank Involuntary Resettlement Policy (OP 4.12) were also applied. The compensation covers replacement of loss of structures, shelter/accommodation (for tenants), inconvenience/disturbance allowance, land, crop, transport allowance for luggage and loss of profit if the area is of business nature. Other principal Land Laws and Policies relating to land acquisition and resettlement such as Land Act, 1999, Cap. 113 R.E. 2002; Village Land Act, 1999, Cap. 114 R.E. 2002; Land Acquisition Act, Cap. 118 R.E. 2002; Urban Planning Act, 2007; Land Use Planning Act, 2007; Graves (Removal) Act, Cap. 73; Local Government (District Authorities) Act, Cap. 287; and Local Government (Urban Authorities) Act, Cap. 288 were also considered. Consultation and Participation Various stakeholders were identified and involved in the development of the RAP public consultation and participation are essential because they afford potential displaced persons the opportunity to contribute to both the design and implementation of project activities. The socio-economic situation prevailing in Tanzania as discussed earlier, makes public consultation with the communities, indispensable. Furthermore, it is the local communities iii who are to claim ownership of this project for it to be successful and their wealth of knowledge of local conditions are invaluable assets to the project. In recognition of this, particular attention was paid to public consultation with potentially affected individuals/households when resettlement and compensation concerns are involved. The following stakeholders were actively consulted: Government ministries (Lands, Housing and Human Settlement Development; Water and Irrigation; Health and Social Welfare; Education; and Natural Resources and Tourism), local government (Dar es Salaam City Council, Temeke Municipal Council, Mkuranga District Council, Ward and Village Councils (Kisarawe II and Mpera). Other stakeholders included TANROADS, TANESCO, and Tanzania Petroleum Development Cooperation. Individual stakeholders referred to those owning, living or working within the immediate impact area that will experience the highest level of impacts resulting from project implementation were also consulted. They included PAPs, unaffected household within the project area, water users, Dar es Salaam Zoo owner and Local inhabitants (Farmers) Funding Arrangements The PAP preferred mode of compensation was by way of cash payment. The compensations have not yet been made. The Ministry Water through the Dar es Salaam Water and Sanitation Authority (DAWASA) will coordinate the overall project and il be responsible for making the payments. DAWASA and the ministry have implemented other projects in the past that required resettlement and are unlikely to face difficulties in successfully implementing this project. The payments will be made by government cheque and PAP will be counselled by DAWASA through municipal councils to ensure that the money paid is used for the intended purpose. The implementation of this RAP will take established rational steps: establishing roles and responsibilities of stakeholders, awareness creation, Impacts identification and development of mitigation measures (done through the environmental and social impact assessment), mobilization of relevant authority e.g. Municipal, district and village/mtaa) on the pending RAP process, discussing of resettlement options including identification of land for iv resettlement, physical valuation of assets, approval of valuation, set-up of grievance redress mechanism, council on management of compensation funds (before and after payments are made), payment of compensation and monitoring of the RAP implementation to ascertain if the mitigation measure that were prescribed are adequate or not and improving/upgrading mitigation measures as appropriate. v Compensation Entitlements for Mpera The compensation entitlement for Mpera sub-project is influenced by for the typical characteristics of assets (structures size and type of construction, land, crops including trees). It covers a total of 63 PAPs and is estimated to be 1,228,531,392 TShs (adjusted by a headline inflation index of 13.1%). Compensation Entitlements for Kisarawe II (Kimbiji) The compensation entitlement for Kisarawe II (Kimbiji) sub-project is influenced by for the typical characteristics of assets (structures size and type of construction, land, crops including trees). It covers a total of 63 PAPs and is estimated to be 457,080,680 TShs (adjusted by a headline inflation index of 13.1%). Compensation Entitlements for Water Storage Facilities Land was acquired land for water storage facilities at Pugu Kajiungeni and Buyuni. This procurement was done before the completion of the RAP and based on the principles of the existing Resettlement Policy Framework (RPF) to allow for strategic design of water transmission lines from the well fields to the storage facilities. During the development of this RAP, a review of the procedure and the resulting compensation was done to ensure that it was done in accordance with the existing RPF. After this review we can acknowledge that the procedures used were in line with the existing RPF. The total number of the PAPs for the water storage was 13 with 13 houses. In this sub project, the total compensation amounted to 795,585,090. The compensation that has already been paid is TShs. 703,435,093 TShs. Thus a balance of TShs. 92,149,997 has yet to be paid. Resettlement Implementation Schedule The resettlement costs of the whole project areas have yet to be determined. This RAP covers Phase I only. It is however important to note that the process is governed by law and the procedures are at times very slow. The frequent changes in the design while understandable are none the less compromising the progress. vi It is important to complete the valuation exercise so that resettlement costs are not underestimated. The costs of resettlement planning and implementation must additionally be factored in. The project proponent indicates that the source of funding for the RAP budget will be the government. It is important that adequate notice and preparation are made to factor in the so common difficulties to overcome unpredictable cash flows from government coffers. Monitoring The RAP set out a monitoring regime (by both internal external evaluation) to check if affected people have been paid in full and before implementation of the project; and if the people who are affected by the project have been affected in such a way that they are now living at a higher standard than before, living at the same standard as before, or they are poorer than before. vii Conclusion This RAP has noted that the proposed project will meet the requirements for increasing the water supply Dar es Salaam and nearby communities and will have little to moderate negative impacts on environment and people. The more serious concerns revolve around social impacts, to which mitigation measures, including compensations have been proposed. The valuation of properties, land, crops and other assets was carried out by municipal Valuers in the presence of the owner of the property/asset and the survey team. Grievance or complaint procedures have been established to make sure that all PAP are properly compensated and have a possibility to appeal if they are dissatisfied with the awarded compensation amount. Project, grievances are handled by a Grievance Redress Committee formed at project level that will administratively be formed as part of the Project Field Payments Teams. This arrangement was made known to PAP during the negotiations process. The Disputes Resolution Group normally included experts that were not on the team that carried out the valuation. The Disputes Resolution Group will include a team of experts including an independent valuer, lawyer and a sociologist involving the local leadership i.e. Village Chairman or Village Executive Officer. In the case where the affected person is not satisfied with the decision of the Disputes Resolution Group, the matter will be referred to the Commissioner for Lands. This procedure however does not limit any PAP to seek redress in a any Court of law. The social impacts due to displacement (physical and economical) caused by the project have been addressed by the RAP and the corresponding Environmental and Social Impact Assessment to which mitigation measures, including compensations have been proposed. The RAP sets up a fair and prompt compensation calling all project affected people to receive their preferred mode of compensation: cash compensation based on national and international standards (World Bank OP 4.12) so that the compensation renders them at least as well off and possibly better off than before the commissioning of the project. The compensation budget for the project (that is World Bank compliant) is 2,389,047,167 TShs. (or 2,702,012,346 TShs if adjusted for 13.1% headline inflation). viii ix TABLE OF CONTENTS EXECUTIVE SUMMARY .......................................................................................................ii 1. INTRODUCTION ........................................................................................................... 13 1.1 Project Background .....................................................................................................13 1.2 Project Rationale .........................................................................................................19 1.3 Disclosure of the Resettlement Action Plan .................................................................19 1.4 Limitations of this Resettlement Action Plan ...............................................................20 1.5 Structure of the Resettlement Plan ...............................................................................21 2. OBJECTIVES AND GUIDING PRINCIPLES ............................................................... 22 3. RAP PREPARATION PROCESS ................................................................................... 24 4. CATEGORIES AND ESTIMATES OF AFFECTED PEOPLE ..................................... 26 5. ELIGIBILITY CRITERIA FOR COMPENSATION ..................................................... 28 6. LEGAL FRAMEWORK FOR RESETTLEMENT AND FIT WITH BANK POLICIES 28 6.1 National Land Policy, 1995 ........................................................................................... 34 6.2 National Environmental Policy (1997) .......................................................................... 35 6.3 National Forest Policy, 1996 ......................................................................................... 36 6.4 Local Government Acts .................................................................................................. 36 6.5 Land Tenure and Ownership ................................................................................... 37 6.6 The Land Act No. 4 (Cap 3) ..................................................................................... 38 6.7 The Village Land Act Cap 4 of 1999.............................................................................. 39 6.8 The Land Acquisition Act, 1967 ..................................................................................... 40 6.9 Water Utilization and Regulation Act, (No. 42) 1974 ................................................... 40 6.10 The Forest Act, (No. 14), 2002 .................................................................................... 40 6.11 The National Land Use Planning Commission Act, (No. 3), 1984 .............................. 41 6.12 Contractors Registration Board Act No. 17 of 1997 ................................................... 42 7. VALUATION METHODS.............................................................................................. 42 7.1 Compensation Payments ................................................................................................ 43 7.2 Forms of Compensation ................................................................................................. 43 7.3 Compensation for Assets ................................................................................................ 44 7.3.1 Compensation for land ............................................................................................ 44 7.3.2 Compensation for crops .......................................................................................... 45 7.3.3 Compensation for buildings and structures............................................................. 46 7.3.4 Compensation for sacred sites ................................................................................ 47 7.3.5 Compensation for vegetable gardens and beehives ................................................ 47 7.3.6 Compensation for Horticultural, Floricultural and Fruit Trees ............................... 47 7.3.7 Compensation for other domestic cash crops and fruit trees .................................. 49 8. INSTITUTIONAL ARRANGEMENTS FOR IMPLEMENTATION OF THE RAP .... 51 8.1 Implementation of the RAP ............................................................................................ 51 x 9. GRIEVANCE MECHANISM ......................................................................................... 53 9.1 Formal Process Through Courts ................................................................................... 53 9.2 Informal Process through Dispute Resolution Groups .................................................. 54 Chapter 10 ................................................................................................................................ 55 10. FUNDING ARRANGEMENTS...................................................................................... 55 10.1 Compensation Entitlements for Mpera .................................................................... 55 10.2 Compensation Entitlements for Kisarawe II (Kimbiji) ............................................ 56 10.1 Compensation Entitlements for Water Storage Facilities ....................................... 59 11. CONSULTATION AND PARTICIPATION .................................................................. 62 11.1 Consultative Strategy ............................................................................................... 62 11.2 The Consultative Process ......................................................................................... 62 11.2.1 Stakeholder identification and methods of participation ................................. 62 11.2.2 Methods of stakeholder participation............................................................... 65 11.2.3 Notification to stakeholders ............................................................................. 65 11.2.4 Household interviews....................................................................................... 65 11.2.5 Official meetings with village leaders ............................................................. 66 11.2.6 Meetings with districts officials ....................................................................... 66 11.2.7 Consultations with other relevant stakeholders ............................................... 66 11.3 Summary of Stakeholder Issues and Concerns ........................................................ 66 12. RESETTLEMENT IMPLEMENTATION SCHEDULE ................................................ 68 12.1 Resettlement Implementation Schedule.................................................................... 68 12.1 Conclusion ............................................................................................................... 69 13. MONITORING ................................................................................................................ 71 12.2 General Objectives and Evaluation Monitoring ...................................................... 71 12.3 Evaluation Objectives .............................................................................................. 73 14. CONCLUSION ................................................................................................................ 75 15. BIBLIOGRAPHY ............................................................................................................ 76 APPENDIX .............................................................................................................................. 79 Appendix I: Crop Compensation Rates for Period Commencing on 01/01/2010 ................ 79 Appendix 2: Upgrading Compensation for Various Sub Projects ...................................... 85 A2.1 Compensation for Mpera Sub project .................................................................. 85 A2.2 Compensation for Kisarawe II Sub project .......................................................... 85 A2.3 Compensation for Storage Facilities Sub project................................................. 85 A2.4 Supplementary Compensation Budgets ............................................................. 101 A2.5 Compensation entitlements for Mpera ............................................................... 102 A2.6 Compensation entitlements for Kisarawe II (Kimbiji) ...................................... 102 A2.7 Compensation entitlements for water storage facilities ..................................... 103 A2.8 Adjusting Compensation for Inflation ............................................................... 103 xi LIST OF FIGURES Figure 1: Kimbiji and Mpera Water Projects ........................................................................... 16 Figure 2: Kimbiji water project................................................................................................ 17 Figure 3: Mpera water project.................................................................................................. 18 xii LIST OF TABLES Table 1: Value of Some of common crops .............................................................................. 27 Table 2: Comparison of Tanzanian Law and World Bank OP 4.12 Regarding Compensation33 Table 3: Proposed Schedule for Mango and Coconut Trees Cut Down .................................. 49 Table 4: Entitlement Matrix for Mpera Well Fields ................................................................ 57 Table 5: Entitlement Matrix for Kimbiji well Field................................................................. 58 Table 6: Entitlement Matrix for Water Storage Facilities ....................................................... 60 Table 7: Summary of Compensation for RAP Phase I ............................................................ 61 Table 8: Resettlement action plan schedule ............................................................................. 69 A1- 1: Perennial Crops............................................................................................................. 79 A1- 2: Value of mixed crops per stem/cluster ......................................................................... 82 A1- 3: Value of seasonal Crops per hectare............................................................................. 83 A2- 1: Compensation Characteristics for the Mpera Sub Project ............................................ 86 A2- 2: Compensation Characteristics for the Kisarawe II (Kimbiji) Sub Project ................... 89 A2- 3: Characteristics of compensation of the Water Storage Facilities Areas ....................... 92 A2- 4: Mpera Compensation Entitlement Matrix .................................................................... 93 A2- 5: Kisarawe II (Kimbiji) Compensation Entitlement Matrix ............................................ 96 A2- 6: Water Storage Facilities (Pugu Kajiungeni & Buyuni) Compensation Entitlement Matrix ..................................................................................................................................... 100 A2- 7: Guiding Compensation Rate per Unit of Asset .......................................................... 101 A2- 8: World Bank Policy Compliant Compensation for Mpera .......................................... 104 A2- 9: Supplementary Compensation Budget for Mpera ...................................................... 107 A2- 10: World Bank Policy Compliant Compensation for Kisarawe II (Kimbiji) ................ 110 A2- 11: World Supplementary Compensation Budget for Kisarawe II (Kimbiji)................. 113 A2- 12: World Bank Policy Compliant Compensation for Water Storage Facility Areas .... 115 A2- 13: World Supplementary Compensation Budget for Water storage facilities at Pugu Kajiungeni and Buyuni .............................................................................................. 116 A2- 14: Summary of Compensation for RAP Phase I ........................................................... 117 A2- 15: Summary of Supplementary Compensation Budget for RAP Phase I ..................... 117 Chapter 1 1. INTRODUCTION 1.1 Project Background The water balance assessment of Dar es Salaam indicates that the city has a deficit of 135,634 m3/d (AAW Consulting Engineers, WSSP Framework Report, and June, 2007). Total demand by year 2032 will be around 963,983 Ml/d. This means that there will be a shortage xiii of 687,982 m3/d. Due to the above situations and the need to ensure water supply security DAWASA is implementing a project to exploit suitable groundwater aquifers covering Kimbiji and Mpera. There are five main sites related to the Kimbiji well-field and associated facilities project. They are the well-field site at Kisarawe II village, and several storage reservoirs in Temeke, the rising main route between the well-field and storage facilities, the transmission pipeline route between storage facilities and main storage facilities (to be located within the well field) and the distribution pipeline route in Kigamboni. The project is located at two different locations: Kimbiji and Mpera. The project area is shown below in Figure 1. For the Mpera project component, there are four main sites related to the Mpera well-field and associated facilities project. They are the well-field site at Kisemvule village, the Pugu storage tanks site at Pugu Kajiungeni, the Buyuni storage tank site at Buyuni (Ukonga) and the transmission pipeline route between well-field and storage facilities (Figure 1 and 3). The land for both the well fields and the corresponding storage facilities will have to be acquired and become restricted for this project purpose only, i.e. other human activities will not be allowed. Luckily most of the land in question is rural with minor development except for the zoo development at Kisarawe II. The zoo is well established with several support structures (houses, a mosque, etc.). The zoo already attracts a lot of visitors form Dar es Salaam and beyond. While it is not impossible to relocate the zoo, its resettlement could be prohibitively expensive. For this reason it is proposed that the zoo be left at its current premises, but with additional tenancy conditions/restrictions. These could include prohibition to expand the size of the zoo, prohibition to set up bulk storage facilities for petroleum products, etc. The Minister responsible for environment shall prescribe, as provided by law, all the necessary restrictions for the purpose of safeguarding the water supply. 14 15 Figure 1: Kimbiji and Mpera Water Projects 16 Figure 2: Kimbiji water project 17 Figure 3: Mpera water project 18 1.2 Project Rationale The project intends to exploit suitable groundwater aquifers covering Kimbiji and Mpera in order to improve water supply security for the city of Dar es Salaam and some areas of the Coast region e.g. Mkuranga district. The Kimbiji and Mpera well fields would supplement the present public water supply for Dar es Salaam from the unregulated Ruvu River (Upper Ruvu and Lower Ruvu intakes). These two intakes currently have an installed capacity of 276,000 m3/day which is insufficient and becomes worse during droughts. The water balance assessment indicates that the City has currently a deficit of 135,634 m3/d, which would reach 687,982 m3/day by year 2032. 1.3 Disclosure of the Resettlement Action Plan The RAP has been prepared through a process of public consultation with all interested and affected parties. This was particularly important as proper consultation with affected parties can increase the effectiveness and reduce the costs of RAP implementation. As part of Disclosure requirement, this document on the Resettlement Action Plan must be widely disclosed. Methods that can be used to disclose the document include (but not limited to): (a) Distribution of as many copies as possible to different institutions and community levels for comments and suggestions; (b) Distribution to Persons Affected by the Project (PAP); (c) Distribution to individuals and representative persons like Members of Parliament (MPs) House of Representative, District Commissioners (DCs), Village Councillors; (d) Conducting meetings and workshops for discussion of the plan. The meeting and workshops will be conducted at various places including the place where the resettlement will take place; and (e) Through inter-net for the internal and external disclosure of the plan. 19 1.4 Limitations of this Resettlement Action Plan This project consists of two major components: The Kisarawe II component consisting of 20 deep wells, water mains pipe network and its associated distribution network and a similar composition for 10 wells, water mains pipe network and its associated distribution network for the Mpera well field. In view of the fact the estimated cost of resettlement (assets, land, crops, loss of profit from business, disruption of livelihood, etc.) for the whole project is estimated to be over 40 Billion Tanzanian Shillings. This is a huge sum that is presently unavailable. This RAP therefore has been forced to be broken into two phases. These are: Phase I: RAP for the Kimbiji (Kisarawe II) and Mpera well field including areas required for the construction of water tanks/storage facilities. This RAP also covers the transmission lines to the storage tanks. However it does not cover the distribution lines to the consumers; and Phase II: RAP for the water mains distribution lines to the storage tanks. It is important to point out here that the valuation of the required land for transmission ideally ought to have been done in this Phase I study. Unfortunately, the actual survey and eventual design has yet to be done. The ESIA process reviewed the proposed routes and where necessary alternative routes were identified and their impacts discussed. A good example is the transmission of water from Mpera to Mbagala which was planned to pass along the main road to Mbagala and branch to Chamazi and Chanika on the way to the storage facilities at Buyuni and Pugu was proposed to be moved to the way leave of natural gas (Songas) pipeline. Phase I RAP i.e. for the Kimbiji (Kisarawe II) and Mpera well field including areas required for the construction of water tanks/storage facilities. 20 1.5 Structure of the Resettlement Plan This RAP is organized into fifteen Chapters, these include: (a) The Introduction of the Project; (b) Resettlement Principles and Objectives; (c) RAP Preparation Process; (d) Categories and estimates of affected people; (e) Eligibility Criteria for compensation; (f) Legal Framework for Resettlement and Fit with Bank Policies; (g) Valuation Methods; (h) Organizational Responsibilities; (i) Implementation Procedures; (j) Grievance Mechanisms; (k) Funding Arrangements; (l) Mechanisms for Consultation and Participation; (m) Monitoring Arrangements; (n) Conclusion; and (o) Bibliography 21 Chapter 2 2. OBJECTIVES AND GUIDING PRINCIPLES The objectives of the RAP are to comply with both National laws and World Bank policy on involuntary resettlement. The World Bank policy, OP 4.12, in particular has a succinct statement of policy objectives that bears quoting directly, rather than paraphrasing, these are: (a) Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs; (b) Where it is not feasible to avoid resettlement, resettlement activities should be conceived and executed as sustainable development programs, providing sufficient investment resources to enable the persons displaced by the project to share in project benefits. Displaced persons should be meaningfully consulted and should have opportunities to participate in planning and implementing resettlement programs; and (c) Displaced persons should be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre- displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher (Para 2, OP.4.12, 3/2007). The critical terms are to avoid or minimize resettlement; if unavoidable, to enable affected people to share project benefits through meaningful consultation and participation in planning; and to assist people restore or improve their livelihoods. Adequate measures to minimize requirement for displacing people physically or economically were taken. This involved review of design and location of facilities. For example the original route of the water mains from Mpera was relocated to pass along the natural gas pipeline so as to avoid displacing residents along a 15metre corridor over nearly 7 km road from Mbagala to Chamazi. The guiding principle used in preparation of this RAP (in addition to minimizing impacts) was transparency, equity, fairness, and active participation of the PAP. Some of the key factors considered were: 22 (a) Displaced persons/parties receive benefits from the project that is displacing them (b) Social disruption is minimized; (c) Resettlement activities are executed as a sustainable development programme; (d) Affected persons are consulted through the planning and implementation stages of the compensation and resettlement process; (e) Income restoration is integral to the compensation and resettlement process; (f) There is a net improvement in livelihood activities and standards of living of affected persons as compared with their situation prior to displacement or implementation of the project; (g) Fair and prompt compensation (in cash or in kind, as preferred by the PAP) is paid before project activities (development of well field) begin; (h) Resettlement timetables are well-coordinated with project activities; (i) An adequate budget is provided for the compensation and resettlement process. DAWASA as the developer was fully engaged to ensure that the above these principles are applied in the implementation of RAP. 23 Chapter 3 3. RAP PREPARATION PROCESS The RAP was prepared through several stages. These were: Stage 1: Determination of land acquisition/resettlement: This was the initial stage, a screening process to determine whether or not land acquisition/resettlement will occur. This was done a part of the Environmental and Social Impact Assessment. It was established that well fields including the 60m buffer area prescribed by law will need to be protected by acquiring the relevant areas; Stage 2: Public Sensitization and Consultation: The identified PAP were made aware of the project and its implications through house to house consultation and public meeting. Only PAP were involved in the meeting if there was no community/public land to minimize anxiety and unnecessary opposition to the project; Stage 3: Preparation of a Census of affected persons: Through local government and the municipal valuer a survey was conducted to establish baseline data in order to determine the number, economic status, livelihoods and standard of living of PAP and to identify vulnerable people who have special needs; Stage 4: Establishment of a cut-off date for eligibility for compensation Stage 5: Inventory and Valuation of affected assets: Through negotiations based on government approved procedures and rates, the so called methods and standards (see Appendix 1, and asset market values), PAPs were involved in discussing and valuation agreeing on the rates; Stage 6: Socio-economic analysis of impacts. This involved the assessment of impacts on the households and communities, including impacts on common property and community assets; Stage 7: The municipal valuer, subject to agreements agreement directed or negotiated above, prepared a draft valuation for verification by PAP. This is then used in the preparation of the draft RAP; Stage 8: Public disclosure and discussion of draft RAP; 24 Stage 9: Submission of RAP for government review and funding; and Stage 10: Submission to Project/World Bank for review. Most of the survey and assessment were conducted last year and the valuation was firmed up in January 2010. 25 Chapter 4 4. CATEGORIES AND ESTIMATES OF AFFECTED PEOPLE The survey was conducted by a team involving the municipal valuer, land owner, land surveyor, village chairman, ward chairman or a witness for the land owner. When the survey was completed, a survey form was signed by the team. The survey data included identified the number of people, their assets (buildings of whatever nature, economic activities, land, crops, etc.). The total number of PAP in the project components involved in this Phase I Rap is: (a) 67 persons in the Kimbiji (Kisarawe II) well field; (b) 63 persons for the Mpera well field; and (c) 14 persons for the water storage facility areas at Pugu Kajiungeni and Buyuni. According to the provisions of Section 3(1) of Land Act No. 4 of 1999, the compensation covers: (a) Inconvenience/disturbance allowance of 5% of the value of building, land or crop; (b) Shelter/accommodation allowance of 36 months based on average monthly rental fee for a fully completed house with the own living in; (c) Transport allowance for 12 tons of luggage covering 20km; and (d) Profit loss allowance if the area is of business nature. The study showed that between 2009 and 2010, the market price for land in the area of Mpera, Kibamba, Kisemvule and Kisarawe II had been growing driven for growing needs for farming lands and that at the time of the survey an acre of land ranged from 2.0 and 2.5 million Tanzanian shillings. After a series of consultations with land valuation experts and the communities involved, it was agreed that the price of land/farm per acre should be 2.5 million Tanzanian shillings and 26 that land sizes would be measured by the land surveyor using GPS. The going rate/market value at the time of evaluation was 2 million Tanzanian shillings per acre. The land value was worked out by assessing the size of the land (land value), the amount and type of crops. The agreed value for different crops is shown in Appendix 1. The value of the common crops identified is shown in Table 1. Table 1: Value of Some of common crops Rate Crops Crop Rate [TShs/tree] [TShs/tree] Ashock 7,500 Kivuli 7,500 Avocado 16,900 Mango 20,800 Banana 14,300 Mifenesi 15,600 Cashew nut 18,980 Mikenge 30,000 Cassava 617,000 Mistafeli 5,200 Christmas tree 7,500 Mjohoro 7,500 Coconut 28,600 Mkungu 5,200 Mtikivuli 7,500 Pawpaw 5,200 Neem 7,500 Pineapple 780 Mtikivuli 7,500 Oil palm 15,600 Topetope 5,200 Orange 18,200 Values of structures depended on size, type of construction materials used, age of the building and whether it was complete or not. Where the value of compensation of the building was based on actual replacement value, no depreciation was indicated. The valuation rates for buildings are set by the Ministry of Lands, Housing and Human Settlement Development. These sates are reviewed annually, and although rates for other regions have not been reviewed since 2008, the rates for Dar es Salaam are up to date. 27 Chapter 5 5. ELIGIBILITY CRITERIA FOR COMPENSATION One of the main objectives of a Resettlement Action Plan should be to minimize social disruption, thus limiting the number of people who will be eligible for compensation and resettlement. Compensation is given only to those who are eligible to be paid. Compensation is paid to an owner, occupier or a person who has a legal right or interest on a piece of land that is being acquired or affected. Criteria for compensation are provided for in the Land Act and its Regulations. While the Land Act provides that any holder of a granted right of occupancy or customary land title is eligible to compensation. In this evaluation, all land and asset holders were considered eligible for compensation. This is in line with the Land Act and the Village Act recognizes that land in itself, even where it is bare or undeveloped, has value. The necessity of having tangible improvements before compensation is paid has been abandoned in Tanzania. This valuation is also in compliance with the Land (Compensation Claims) Regulations, 2001 that provides for any person occupying land to be eligible to apply for claim for compensation. This is in recognition that when making a decision as to who is eligible to get compensation it must be borne in mind that there are people who may not have the title to a piece of land but have acquired interest and rights over that piece of land. Chapter 6 6. LEGAL FRAMEWORK FOR RESETTLEMENT AND FIT WITH BANK POLICIES The impacts due to involuntary resettlement from development projects, may give rise to economic, social and environmental risks resulting in production systems being dismantled, 28 people facing impoverishment when their productive assets or income sources are lost, people being relocated to environments where their productive skills may be less applicable and the competition for resources increases; community institutions and social networks being weakened; kin groups being dispersed; and cultural identity, traditional authority, and the potential for mutual help being diminished or lost. This RAP has been triggered because the project activities will cause land acquisition, e.g. physical piece of land will be acquired for the development of well fields at Kimbiji and Mpera and for construction of water storage facilities. People will be affected because they are cultivating that land, some have buildings on the land, or they will lose access to the land economically, spiritually or in any other way which may not be possible during and after the project is implemented. It is for this reasons that PAP must appropriately be compensated for their loss (of land, property or access). The compensation worked out in this RAP is in cash, this was the PAPs’ preferred option. The Land Act No.4 and Village Land Act No. 5 of 1999 have set clear procedures for full, fair and prompt compensation while acquiring land from citizens. These procedures were adhered to, especially the Land (assessment of the value of compensation) Regulations - made under S.179 of Land Act No.4 of 1999. GN 78 published on 4/5/2001. Therefore, the objectives of this RAP are the following:  Adopted design alternatives have been adopted to avoided where feasible, or minimize the level of Involuntary resettlement;  Where it was not possible to avoid involuntary resettlement and land acquisition the affected persons were adequately consulted and participated in planning, valuation and implementing resettlement; and  The Proponent – DAWASA and the Local government has set up procedures to educate, communicate and assist the Displaced and Compensated persons in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher. These efforts include making 29 payments through banks and offering counsel on sound utilization of the compensation finances. Here, the affected people, according to both the Land Act No.4 and Village Land Act No. 5 of 1999 and the World Bank policy, for this project refer to people who are directly affected socially and economically by the Bank assisted investment projects, caused by: The involuntary taking of land and other assets resulting in: (a) relocation or loss of shelter; (b) loss of assets or access to assets; and (c) loss of income sources or means of livelihood, whether or not the affected persons must move to another location; or  The involuntary restriction of access to legally designated parks and protected areas results in adverse impacts on the livelihood of the displaced persons. The RAP will apply to all components of the sub-project (well field development, water storage facilities, water distribution network, and other associated infrastructure e.g. access road, maintenance and support services infrastructure). This requirement is not influenced by the funding body. The resettlement policy which determines the formulation of this RAP applied to all displaced persons regardless of the total number affected, the severity of impact and whether or not they have legal title to land. Additional attention was taken on the needs of vulnerable groups among those displaced; especially the elderly, women. In the survey and valuation exercise, the elderly were given support by the survey team to fully address their issues of concern. This RAP is developed for both Kimbiji (Kisarawe II) and Mpera water projects. However as stated earlier this RAP is limited to the development of the well fields and the water storage facilities. The valuation was done separately for each sub-project that requires land acquisition. These include: 30 (a) The Kimbiji well filed including the 60m radius(i.e. 2.8acres) around each well; (b) The Mpera field including the 60m radius (i.e. 2.8acres) around each well; (c) Areas where storage facilities (tanks) will constructed; (d) Areas where the water distribution lines will be laid. Implementation of the sub-projects requiring resettlement plans cannot commence before necessary measures for resettlement and compensation are in place according to steps identified in the resettlement plan. These measures included provision for compensation and other assistance required for relocation, prior to displacement, and preparation and provision of resettlement sites with adequate facilities (where appropriate/required). In particular, the acquired land and related assets shall take place only after compensation has been paid and, where applicable, resettlement sites, new homes, related infrastructure, public services and moving allowances have been provided to the displaced persons. The policy aims to have the affected persons perceive the process and any compensation to be full, fair and prompt. And in practice, the PAP were actively involved e.g. in choosing their preferred compensation option. The principal Land Laws and Policies relating to land acquisition and resettlement are: (a) Land Act, 1999, Cap. 113 R.E. 2002; (b) Village Land Act, 1999, Cap. 114 R.E. 2002; (c) Land Acquisition Act, Cap. 118 R.E. 2002; (d) Urban Planning Act, 2007; (e) Land Use Planning Act, 2007; (f) Graves (Removal) Act, Cap. 73; (g) Local Government (District Authorities) Act, Cap. 287; and (h) Local Government (Urban Authorities) Act, Cap. 288. These are informed by the National Land Policy (1996) which is a policy statement, rather than legislation. The Land Act and Regulations are perhaps the most critical legislation that set the standards for compensation, which is fair and adequate compensation, based on the 31 market value of the land and above ground assets. Market value is a combination of different factors: (a) Value of land; (b) Value of houses/buildings including site works; (c) Value of crops or plants in the plot/land; (d) Value of services and other infrastructure; (e) Disturbance allowance; (f) Transport allowance; (g) Loss of profit, where applicable; and (h) Other costs, such as grave removal, utilities and others. Experiences from other projects indicate that it is common to experience delays in payment. These delays often result in decrease of the actual value of compensation. The valuation for the sub projects in question were done in January this year. The valuations are, as provided for by law, valid for a maximum of six months. As these payments have not yet been effected, this RAP document provides a projection of value of compensation, using the Bank of Tanzania annual inflation index to determine the approximate compensation value in June of the year 2011 (which is considered as a realistic payment date). There are also other laws that are relevant, these are: (a) Town and Country Planning Ordinance, Cap. 378; (b) Highway Ordinance, Cap. 167; (c) National Environmental Policy, 1997; (d) Local Government Acts, 1982, 1984; (e) Water Utilization and Regulation Act, 1974; (f) National Land Use Planning Commission Act, 1984; and There are gaps between Tanzanian Laws and the World Bank OP 4.12. The principle differences between OP 4.12 and Tanzanian laws relate to compensation for land, valuation and entitlements. OP 4.12 advocates land-for-land compensation for people engaged in agriculture, whereas Tanzanian law gives priority to cash compensation, with land-for-land as an option at the choice of the affected person (see Table 2). OP 4.12 insists on full 32 replacement cost for valuation, whereas depreciation may be applied in some instances in Tanzania. The difference in entitlements concerns primarily those without occupancy rights - squatters and encroachers -who are included under OP 4.12 and may be excluded under Tanzanian law. Table 2: Comparison of Tanzanian Law and World Bank OP 4.12 Regarding Compensation Category of PAPs and Tanzanian Law World Bank OP 4.12 Types of Loss of Assets Cash compensation based upon market value under statute or Land-for -Land, disturbance and transport allowances, loss of profits or accommodation, cost of Recommends Land-for-Land Land Owners acquiring or obtaining the said land, any other immediate compensation. Other compensation costs or capital expenditure on the development of the is at replacement cost said land. Compensation must be prompt with delays incurring interest at market rates Tenants would be entitled to full, fair and prompt compensation and other Entitled to compensation based on the amount of rights relocation assistance. PAPs are Land Tenants they hold upon land under relevant laws. Illegal tenants entitled to some form of not entitled to compensation. compensation regardless of the nature of their occupancy (legal/illegal)  In some cases land users have some form of secured tenure extended to them under new laws. In other WB OP 4.12 includes displaced cases land users are not entitled to compensation for persons who have no recognizable Land Users land. legal right or claim to the land they  Entitled to compensation for crops and any other are occupying economic assets.  Land-for-Land Under the WB OP 4.12 permanent and non-permanent buildings need to be compensated. Where however, the displaced persons have no recognizable legal Users of Cash compensation based on valuation, disturbance rights they are to be provided with Temporary allowance or entitled to new equivalent structure based on resettlement assistance in lieu of Buildings market value. compensation for the land they occupy, as well as other assistance. Cash compensation levels should be sufficient to replace the lost land and other assets at full replacement cost in local markets. Under the WB OP 4.12 permanent Owners of Cash compensation is based on market value or cost of and non-permanent buildings need to Permanent putting up equivalent structure at the time of valuation. be compensated. Buildings Disturbance allowance. Where however, the displaced 33 Category of PAPs and Tanzanian Law World Bank OP 4.12 Types of Loss of Assets persons have no recognizable legal rights they are to be provided with resettlement assistance in lieu of compensation for the land they occupy, as well as other assistance. Cash compensation levels should be sufficient to replace the lost land and other assets at full replacement cost in local markets Cash compensation at market value based upon historical Perennial records. Rates for each crop established by the Valuation Crops Division in Ministry of Lands and Human Settlements Source: United Republic of Tanzania, Ministry of lands, Housing and Human Settlements Development, Private Sector Competitiveness Project, Land Reform Sub-component, Resettlement Policy Framework, October, 2008, page 5. The RAP has been developed based on the resettlement policy framework draws its strength from legal instruments that exist in Tanzania specifically the Land Policy 1995 and the Land Act 1994. These and other legislative instruments provide the basis and the legal platform for the conduct of land acquisition, compensation and resettlement of persons that have to be moved to pave way for this water projects. The principal Land Laws and Policies relating to land acquisition and resettlement that are directly relevant follow: 6.1 National Land Policy, 1995 The National Land Policy, 1995, advocates the protection of land resources from degradation for sustainable development. The policy addresses several environmental and social issues relevant to water resources development projects such as land use planning. (Hazardous lands (5.7 Land Act) There are three categories of land namely General land, reserved land and Village land. General land is vested under the President of the United Republic of Tanzania, administered by Land Commissioner. The Reserved Land is mainly under authorized institution such National parks and Game reserves and Water shades. The village Land is demarcated for an established village and administered by the respective Village Government. There are procedures to shift the title from one category to another. 34 Policy Statement: Individuals should be allowed to obtain titles within an area not designated for communal uses, land conservation, and other specified village or communal projects. These areas need to be protected against encroachment by outsiders and individual villagers. Villagers through their village assemblies will therefore be allowed to survey such lands and get separate Certificates of Village Land. The Policy is enforced by law. Land use planning takes into consideration the land uses, ensures proper management of coastal/urban/rural land resources, promote resource sharing and multiple land use techniques in land use, and lastly advocates the involvement of community in resource management, land use and conflict resolution. It is therefore imperative that the projects operations should be aware of the National Land Use Plans requirements for protection of land resources and displaced indigenous people. 6.2 National Environmental Policy (1997) The National Environmental Policy (NEP) seeks to provide the framework for making fundamental changes necessary to bring environmental considerations to mainstream decision making. It seeks to provide policy guidelines, plans and give guidance to the determination of priority actions, and provides for monitoring and regular reviews of policies, plans and programs. It further provides for sectoral and cross sectoral policy analysis in order to achieve compatibility among sectors. As stated in the NEP, the environmental objective of the Water, Sewerage and Sanitation sector is to support the overall national objective of providing clean and safe water to within easy reach, satisfy other needs, protect water sources and prevent environmental pollution. In order to achieve maximum utilization, the policy has provided to the following which is relevant to the program: (a) Planning and implementation of water resources and other development programs in an integrated manner and in ways that protect water catchment areas and their vegetative cover; (b) Improved management and conservation of wetlands; (c) Promotion of technology for efficient and safe water use, particularly for water and wastewater treatment and recycling; and 35 (d) Institution of appropriate user-charges that reflect the full value of water resources. 6.3 National Forest Policy, 1996 The National Forest Policy, 1996, identifies four main policy areas (forest land management, forest based industries and products, ecosystem conservation and management, institutions and human resources) and present policy statements and instruments/directives to be applied to each of these. The policy requires, Environmental Impact Assessment (EIA) to be considered for all investments, which convert forestland uses or may cause damage to the forest environment. Some of the policy strategy statements that are relevant for water projects include the following:  To enable sustainable management of forest on public lands, clear ownership for all forests and trees on these lands will be defined and management responsibility promoted.  Biodiversity conservation and management as well as watershed management and soil conservation will be included in the management plans for all protection forests. Involvement of forestry management authority, local communities and other stakeholders in conservation will be consulted while establishing water sources and project sites. 6.4 Local Government Acts The Local Government system in Tanzania is based in the decentralization policy and is enshrined in the 1977 Constitution, which was amended through Act No. 15 of 1984 with the effect of making the existence of local government authorities constitutionally sanctioned. The decentralization policy is implemented through the Regional Administration Act (1997), which effectively initiated the decentralization process by scaling down the roles, functions and staffing at the regional level. The Local Government Act No.8 of 1982 and Local Government (Urban Authorities) Act No.9 of 1982 provide for the system of local governments. Administratively, Tanzania is 36 divided into three levels of Local Governments whereby each level has statutory functions with respect to development planning. The three levels are as follows: Local Government Unit Level District / Municipal / city councils 3 Town Councils and Ward 2 Village/"Mtaa" Councils 1 Districts are LGAs that are in rural or semi-rural settings. Each district is subdivided into Wards that in turn are divided into villages and these consist of Hamlets ("Vitongoji"). Municipal Councils are subdivided into Municipal Wards followed by 'Mtaa" (Sub-Ward). There are five city councils; Dar es Salaam City Council, which is sub-divided into three Municipal Councils and Mwanza City Council, Mbeya, Arusha and Tanga. The District councils, City Councils, Municipal Councils, and Village Councils are body Corporate. 6.5 Land Tenure and Ownership The Land Act (Cap 113) and Village Land Act (Cap 114) have set clear procedures for full, fair and prompt compensation while acquiring land. These procedures should be adhered to, especially the Land (Assessment of the Value of Compensation) Regulations made under section 179 of Land Act Cap 112.and advertisement in GN 78 published on 4/5/2001. Land tenure and ownership in Tanzania is governed by statutes such as Land Act Cap 13 of 1999, and Village Land Act Cap 14 of 1999, Land Acquisition Act 1967, and Land Ordinance, 1923 Cap. 113. Land in Tanzania is owned by the public and vested to the President as a custodian. For the purpose of management of land under the land Act Cap 114 of 1999 and all other laws applicable to land, there are three categories of Lands:  General land;  Village land; and  Reserved land. Socio-economic activities are permitted on land in the first two categories of general/public land and not permitted or restricted in land reserved for national parks, protected areas and wildlife/forest reserves except under special conditions stipulated by the Law. 37 In respect of public land, Tanzania has a dual system of land tenure. The system recognizes both customary and statutory rights of occupancy. Tenure rights to land can be held by individuals and communities. Holdings of individuals can be (i) by leasehold right of occupancy for varying periods e.g. 33, 66 or 99 years; (ii) by customary rights of occupancy that have no term limit. 6.6 The Land Act No. 4 (Cap 3) The basic principles of the Land Act are adopted from Land Policy 1995. The fundamental principles of the land policy are stipulated as follows:  All land in Tanzania is public land vested in the president as trustee on behalf of all citizens.  Land has value.  The rights and interest of citizen in land shall not be taken without due process of law.  Full, fair and prompt compensation shall be paid when land is acquired to any person whose right of occupancy or recognized long-standing occupation or customary use of land is revoked or otherwise interfered with to their detriment by anybody or acquired under the Land Acquisition Act. The main objective is to protect the majority of citizens of Tanzania who have acquired land from either inheritance or village council allocation, compensated, purchased from others. As such they should not easily lose their land without full and fair compensation. The full and fair compensation is only assessed by including all components of land quality. Another important principle of the Land Act related to compensation is to facilitate the operation of a market in land and regulate the operation of a market in land to ensure that rural and urban smallholders and pastoralists are not disadvantaged. To protect small holders and pastoralists, the approach should not be to avoid consideration of land allocations to this group. Any disadvantage group should get compensation just like any other person of true land values of the land being held by any other group. Regarding resettlement, this should be in accordance with provisions of the Land Act (and 38 Acquisition Act of 1967). A process for preparing and approving resettlement plans should be based on PLUM (Participatory Land Use Planning and Management) which is explicitly recognized in the Land Policy 1995. The village government should therefore be able to:  Review the proposal to prepare a resettlement plan;  Discuss the proposal in its village; prepare and agree on the resettlement plan; and  Approve the resettlement plan subject to national legislation esp. Land Act No 4 of 1999 and Land Acquisition Act of 1967. 6.7 The Village Land Act Cap 4 of 1999 The Village Land Act defines village land as consisting of:  land falling in boundaries of a registered village under Section 22 of the District Authorities Act no. 7 of 1982;  land designated as village land under the Land Tenure (Village Settlement) Act no. 27 of 1965;  land having boundaries demarcated as village land under any law or administrative procedure in force at any time before the Land Act No. 4;  land with its boundaries have been agreed upon between the village councils having jurisdiction over that land; or land other than reserved land which the villagers have, during the 12 years preceding the enactment of the Land Act of 1999 been regularly occupying and using as village land in whatever manner. The majority of people in Tanzania get land freely within their village land from inheritance, allocation from the village council, or by clearing land, purchase or special program. The Village Land Act Cap 14 empowers the village Assembly to manage village land as trustee managing property on behalf of the villagers and other persons resident in the village and the village assembly is empowered to divide the village land, occupied, used, available for occupation, community used and/or public used land, then to be known as communal 39 village land. It can also identify land being occupied or used by an individual, family, or group of persons under customary law. Finally, the village council can identify land, which may be made available for communal or individual occupation and use, through allocation by the village council. The same Act provides a mandate to the village assembly to further plan the land uses to be designated to the communal village land. 6.8 The Land Acquisition Act, 1967 The Land Acquisition Act gives powers to the President to take land for public purposes when in the public interest it is necessary to do so. 6.9 Water Utilization and Regulation Act, (No. 42) 1974 The Water Utilization (Control and Regulation) Act, (No. 42), 1974, is the principal legislation dealing with the protection of water resources and control of water extraction for different uses. This act has gone through three amendments, amendment through Act No. 10 of 1981, Written Laws (miscellaneous amendment) Act No. 17 of 1989 and the Water Utilization (miscellaneous amendment) Act No 8 of 1997. The extraction of water for different users is controlled through a "water right permit". Under this law, applications for water rights are required to be submitted to the River Basin Water Office for water sources falling under the River Basin. The applicant is required to undertake EIA as classified in the EMA (2004) and (the OP 4.37 safety of Dams) and submit the environmental clearance certificate from NEMC to the Basin Water Office. The provisions for the water rights under this act contain the following: The Water projects needs to understand the procedures for acquiring and managing water rights, discharges to open environment and maintenance of water quality, which are provided by this act. The proposed Water Legislation in Part XII provides for dam safety and flood management. 6.10 The Forest Act, (No. 14), 2002 40 The Forest Act, (No. 14), 2002, provides for the management of forests and its main objectives are to promote and enhance the contribution of the forest sector to the Sustainable development of Tanzania and the conservation and management of natural resources for the benefit of the present and future generations. In addition, the legislation aims to ensure ecosystem stability through conservation of forest biodiversity, water catchments and soil fertility. According to section 18 of this Act, an EIA is required for certain developments in accordance with the modalities and substance as set out in the guidelines by authorities responsible for the protection of the environment. Among others are (a) road construction or the laying of pipelines; (b) construction of dams, power stations, electrical or telecommunication installations; (c) construction of buildings. This Act is mentioned here in recognition of the Kazimzumbwi forest which will be impacted in Phase II of the project which will involve construction of the water pipe network some of which will cross this forest. 6.11 The National Land Use Planning Commission Act, (No. 3), 19 The national land Use Planning Commission Act, (No. 3), 1984, established the National Land Use Planning Commission. The Commission is the principal advisory organ of the Government on all matters, related to land use. In this RAP, the PAP preferred option was cash compensation, and as such, there is no aspect of physical relocation of PAP. Thus it is unlikely that PAP may find themselves in land conflicts that may be a result of lack of land use planning. 41 6.12 Contractors Registration Board Act No. 17 of 1997 According to this act, all construction contracts are required to be executed by registered companies and entitled class in respect to the costs of the project. The procedures for appointing a construction firm for the development of the well fields and the water storage tanks must comply with the requirement of this law. Chapter 7 7. VALUATION METHODS The valuation of affected assets was carried out by estimation of the market value, when it is known, and/or by estimation of the replacement cost. Graves are valued separately under the Graveyard Removal Act of 1968. However in this project, the old graves within the Mpera sub project component could be left undisturbed Valuation methods for affected land and assets would depend on the type of asset. The land asset types identified under Tanzanian law in this policy framework are:  Public land not within the jurisdiction of a village; and  Village land, including customary rights of villagers. Public owned land would be allocated according to laid down procedures which include the paying of surveying and registration fees. The project would be expected to pay to acquire land in this category in cases. This is because, although public owned, individuals and/or community may use the land. The guiding principle is that whoever was using the land to be acquired by the project would be provided other land of equal size and quality. In both the Kisarawe II and Mpera project sub component there is no public land (or land on customary rights on public owned land) that was identified as a target for acquisition. In valuing assets and investments, the land on which the assets were located was also valued for compensation. Thus, a customary landowner or land user on state-owned land will be 42 compensated for land, assets, investments, loss of access etc, at market rates at the time of the loss. If payment is delayed by more than six months, an inflation premium of 1% plus interest at the official rate of inflation (using consumer price index, CPI), will be added to the agreed upon sum. 7.1 Compensation Payments Compensation of the affected will be done according to the governing Laws and Regulations of Tanzania and WB/Relevant Development Partner Regulations. Available options for compensation to individual and household was in cash, in-kind, and/or through assistance. The types of compensation is an individual choice although every effort will be made to instil the preference of accepting in-kind compensation if the loss amounts to more than 20 percent of the total loss of subsistence assets. Through meeting with the project affected person, the cash compensation method was unanimously proffered. 7.2 Forms of Compensation Compensation can be made in three different forms:  Cash Payments - Compensation calculated and paid in Tanzanian shillings. Rates will be adjusted for inflation at the time of payment.  In-kind Compensation - Compensation may include items such as land, houses other buildings, building materials, seedlings, agricultural inputs and financial credits for equipment.  Assistance - Assistance may include moving allowance, transportation and labour. Making compensation payments raises some issues regarding inflation, security and timing that must be considered. One purpose of providing in-kind compensation is to reduce inflationary pressures on the costs of goods and services. Local inflation may still occur. Market prices can be monitored within the time period that compensation is being made to allow for adjustment in compensation values. The general approach in most projects has been to adjust the agreed upon sum by an inflation premium of 1% plus interest at the official rate of inflation (using consumer price index, CPI). The final cost of compensation reported in 43 this RAP has been adjusted for inflation based on the assumption that the payment date is likely to be in the first half of next year. The method of payment of the compensation money will be by government cheque payable at a local bank for purpose of security. DAWASA shall counsel the PAP on responsible use of the compensation money to ensure that the money paid is used for the intended purpose. In recognizing that the local regulations requires the money be paid through the local government, DAWASA shall institute contractual and auditable mechanism with the local government to ensure that actions set out by DAWASA to educate, inform and counsel the PAP before payment are done. 7.3 Compensation for Assets 7.3.1 Compensation for land Compensation is intended to provide a farmer whose land is acquired and used for project purposes with compensation for the land, labour and crop loss. For this reason, and for transparency, "land" is defined as an area:  In cultivation;  Being prepared for cultivation; or  Cultivated during the last agricultural season. This definition recognizes that the biggest investment a farmer makes in producing a crop is his or her labour. A farmer works on his/her land most of the months of the year. The major input for producing a crop is not seed or fertilizer, but the labour put into the land each year by the farmer. As a result, compensation relating to land will cover the market price of labour invested times the amount of time spent preparing a plot equivalent to that taken. The market price of the crop lost is considered separately, below. The labour cost for preparing replacement land is calculated on what it would cost a farmer to clear and create replacement land. This value is found by adding together the average costs of clearing, ploughing, sowing, weeding twice, and harvesting the crop. Labour costs will be 44 paid in Tanzanian shillings, at the prevailing market rates. In this RAP compensation for crops was developed based on the type/specie of crop, the level of development (as a percentage, a fully grown crop was considered to be 100% developed) and the number or acreage of the crop. This approach was used to account for agricultural labour activities. So that, for need for transparency, all land labour are thus compensated for at the same rate. The land compensation in this format therefore covers all investments that a farmer made. The crop value is based on the market value of the annual produce that type of crop is likely to produce. For the purposes of measuring land, the unit of measurement was agreed to be acre which is used by and understood by PAPs. To ensure that fairness and transparency is maintained all measurement were made by the land surveyor in the presence of the owner of the land witnessed by the survey teams. This was particularly important to avoid subsequent accusations of wrong measurements or miscalculation of areas. 7.3.2 Compensation for crops The prices for cash crops will be determined as the average value of the cash crop during the previous year, corrected for inflation. The prices for subsistence crops will be determined as the highest value over the previous year, corrected for inflation. Crop values will be based on: (a) Type of crop/species. Typical vales of crops is shown in Appendix I; (b) The size/area or number of crops (whichever is appropriate); (c) The level of development of a crop to distinguish crops that are already a source of income to the PAP. A crop that is already producing crops is considered to be 100% developed; (d) The estimated level/amount of crop particular specie is likely to produce per year and the market value of that crop. These values determine the value of a crop as shown in Appendix I. 45 7.3.3 Compensation for buildings and structures In principle, and as required by law and by the World Bank policy, replacing structures such as huts, houses, farm outbuildings, latrines and fences requires payment of compensation. It is normal to assume that any homes lost in will be rebuilt on acquired replacement land; however cash compensation (as was preferred in this case) would be available as a preferred option for lost structures (including extra buildings) that are not the main house or house in which someone is living. In determining the values of the structure the current market prices of construction materials and labour are be used. Alternatively, in-kind compensation is worked out and paid for the replacement cost without depreciation of the structure. This is the full replacement cost. Compensation will be made for structures that are abandoned because of relocation or resentment of an individual or household; or are directly damaged by construction activities. Replacement values will be used on:  Drawings of individual's household and all its related structure and support services;  Average replacement costs of different types of household buildings and structure based on collection of information on the numbers and types of materials used to construct different types of structures (e.g. bricks, rafters, bundles of straw, doors etc.) For vulnerable groups, replacement values will be based on actual replacement costs;  Prices of these items collected in different local markets; costs for transportation and delivery of these items to acquire/ replacement land or building site; and  Estimates of construction of new buildings including labour required. The compensation for building was based on the following: (a) Floor area of the building; (b) Type of building materials used (roofing materials, bricks, window type, etc.); (c) Number of bedrooms; 46 (d) Number and size of adjoining facilities (veranda, sheds, etc.); (e) Wells (number and type of build of well); (f) Status of the building (whether complete, type of finishing, age, etc.); (g) Etc. The municipal valuer was responsible of establish the value of the building using the rates set by the Ministry of Lands, Housing and Human Settlement Development. These rates are supposed to be reviewed annually. The rates for Dar es Salaam are which were used are update (rates for other regions were last reviewed in 2008). As the owner of the asset was present during the valuation, reasonable discussion was allowed to arrive and a consensus. 7.3.4 Compensation for sacred sites Sacred sites include but are not restricted to altars, initiation centres, ritual sites, tombs, and cemeteries. They include other such sites, places or features that are accepted by practice, tradition and culture as sacred. To avoid any possible conflicts between individual and / or communities, the use of sacred sites for any project activity is not permitted under this project. In these projects no sacred sites is affected. 7.3.5 Compensation for vegetable gardens and beehives Until a replacement garden starts to produce, the displaced family will need to purchase vegetables in the market. Compensation for loss of vegetable gardens was calculated based on the average amount that an average town dweller spends on buying vegetables over one year per adult in the local market. The cost for vegetable is also included in Appendix I. 7.3.6 Compensation for Horticultural, Floricultural and Fruit Trees Large fruit trees (e.g. mangoes and coconut) are important as sources of:  Subsistence food for families;  Petty market income in some areas; and 47  Shade. Given their significance to the local subsistence economy, which this project intends to enhance, such trees as mangoes and coconuts will be compensated using a combined replacement/market value. Mango and coconut trees used for commercial purposes will be compensated at market value based on historical production records. If households choose to resettle, they will be compensated for the labour invested in the trees they leave behind. The compensation rate is based on information obtained from the socio-economic study. From this, a compensation schedule for trees is developed incorporating the following objectives:  To replace subsistence trees (e.g. mango, coconut, etc.) production losses as quickly as possible;  To provide subsistence farmers with trees to extend the number of months of the year during which fruit is produced and can be harvested as a supplemental source of food for their families during their "hungry season"1;  To provide farmers with the opportunity to derive additional production income from trees bearing more valuable fruits at off-season periods; and  To provide cash payment to farmers to replace pre-project income derived from the sale of excess production until replacement trees produce the equivalent (or more) in projected cash income. It should be pointed out the Valuation Division in the Ministry of Lands and Human Settlements Development has developed crop compensation rates. These rates reviewed every year. The Chief Government Valuer must approve compensation assessments. Displaced people have to be issued Landforms 59 and 70, which allow them to indicate what they expect to be compensated. The compensation schedule is based on providing a combination of new grafted and local trees to farmers, as well as cash payments to offset lost yearly income. Table 3 gives an example for mango trees. When the mango trees are affected and must be cut down, the farmer has two options: To take cash compensation or take an in kind 1 The season when trees are not bearing fruits is considered as a “hungry season� 48 replacement. In kind replacement, the farmer would be given mango trees to plant to replace the ones that have been cut down. Depending on the age of the mango tree cut down, the farmer may opt for replacement Table 3: Proposed Schedule for Mango and Coconut Trees Cut Down Estimated Type/Age of Tree In Kind Replacement for Local Mangos Years Sapling trees planted after project cut off date in area will not be eligible for 0-1  Not eligible compensation Sapling/young tree in first minor Deliver to farmer production of 12-50 fruits occurs about 1-6  Choice of two mango trees (local and/or age 4-5 years improved grafted) per each tree lost; Mango Trees—Fruit producing 6-30  Supplies: fencing to protect tree, a bucket for Mango Trees—Low or non-fruit 30+ watering and a spade producing No compensation will be paid for minor pruning of trees. Compensation for removal of limbs will be prorated on the basis of the number of square meters of surface area removed. The total surface area of the tree will be calculated using the following formula" (1/2 diameter of canopy) 2 x 3.14. As the preferred compensation was in monetary terms, in kind replacement of trees was not used in this RAP. Values of various types of trees are included in Appendix I. 7.3.7 Compensation for other domestic cash crops and fruit trees These trees have recognized local market values, depending on their species and age. Individual compensation will be paid for wild trees “owned� by individuals, who are located in lands as defined in this policy. Note that wild, productive trees belong to the community when they occur in the true bush, as opposed to fallow land. These trees will be compensated under the umbrella of the village or community compensation. Examples include avocado, bananas, lemon and guava. This type of compensation is paid to the local government e.g. the mtaa council, Kitongoji council whichever is appropriate. As the preferred compensation was in monetary terms, in kind replacement of trees was not used in this RAP. Values of various types of trees are included in Appendix I. 49 50 Chapter 8 8. INSTITUTIONAL ARRANGEMENTS FOR IMPLEMENTATION OF THE RAP The Ministry Water and Irrigation through the Dar es Salaam Water and Sanitation Authority (DAWASA) will coordinate the overall project. DAWASA and the ministry have implemented other projects in the past that required resettlement and are unlikely to face difficulties in successfully implementing this project. Some of the required teams are already in place. The survey/evaluation team for example was constituted by the government valuer, the municipal land surveyor, the village/mtaa chairperson and the PAPs (individual PAP when his/her farm/land/property is being evaluated). The evaluations of the compensations reported in this RAP have gone through the required approval mechanism: Through the municipals, district levels and up to the Chief Government Valuer on the way up for verification and approval. After assessment verification and approval they have been submitted back through the same root for eventual payment of the compensation once the money is made available, 8.1 Implementation of the RAP Implementation of RAP follows certain logical steps. In the preliminary stage there are a number of activities that need to undertaken before the RAP IS actually implemented. These include: (a) Establishing the roles and responsibilities of all the stakeholders involved in the implementation of the compensation and resettlement process, so that each party is clearly aware of its obligations and deliverables. In this project the formal established procedure used invariably by all government/public projects requiring land acquisition was used. This entailed the formation of RAP team consisting of Municipal, District, Ward and Village Executive Officers, District Community Development Officers, District Lands Officer. The field survey team consisted of the land surveyor, municipal valuer, the village/mtaa chairperson and 51 representative of the PAP (respective individual when his/her assets are being evaluated); (b) Awareness creation activities were carried out and were through focused meeting with the PAP. These were used to provide information about the project and impacts (positive and adverse) of the project. The meetings also discussed various compensation options that were available. In this Phase I, there was no public land that was acquired and therefore there were no complimentary general public meetings on the project; (c) Impacts of the projects to the public were addressed in the process of carrying out the Environmental and Social Impact Assessment. Such issues like impacts of HIV and Aids, impacts on water supply, resettlement requirement, water supply services and security were carried out; (d) The ESIA exercise also allowed for the notification/mobilisation of the relevant organisations (Municipal, district and village/mtaa) on the pending RAP process; and (e) The compensation rates for land and structures were negotiated and upon approval, through disclosure the PAP get to see the document so that they can confirm not only the compensation rates but also the sizes of land and structure. This is important to ensure that the values are correct. This exercise also addresses the timing of payment so that delays in payment do not lead to depreciation of the initial valuation (as there may be a significant lapse between the times the asset valuation survey was undertaken and when compensation is to be paid). 52 Chapter 9 9. GRIEVANCE MECHANISM In normal circumstances, grievances are dealt with either statutorily through courts and tribunals, or administratively using the Government or traditional institutions. Using the courts in determining grievances related to compensation and resettlement is not the best option as it is tedious, costly and lengthy. To ease this burden, an alternative method (that does not limit ones right to seek redress in a court of law) is set up: a grievance and conflict resolution mechanism. Grievance and conflict resolution processes must be affordable and timely. Timely redress is vital for the satisfactory implementation of resettlement and indeed for the completion of a road project on schedule. As there is no universal model on how to provide for grievance redress and conflict resolution related to compensation and resettlement, in some instances resolution may be achieved through the project management team, local civil administration and other acceptable of mediation or traditional institutions of dispute resolution. 9.1 Formal Process Through Courts The Village Land Act, Cap. 114 establish the Village Land Council while the Land Act, Cap. 113 establish the Land Division of the High Court. In addition, the Courts (Land Disputes Settlement) Act, 2002, elaborates on land disputes settlement in Mainland Tanzania. Section 3 of the Act lists the following to be judicial organs for land dispute resolution:  The Village Land Council  The Ward Tribunal  The District Land and Housing Tribunal  The High Court (Land Division)  The Court of Appeal of Tanzania. The Village Land Council is empowered under Section 7 of the Act to: 53  Receive complaints from parties in respect of land;  Convene meetings for hearing of disputes from parties;  Mediate between and assist parties to arrive at a mutually acceptable settlement of disputes on any matter concerning land within its area of jurisdiction. The Ward Tribunal receives appeals and references from the Village Land Council. Under Section 13 (3) of the Act, when carrying out mediation, it is required to take consideration of:  Any customary principles of mediation;  Natural justice in so far as any customary principles of mediation do not apply;  Any principles and practices of mediation in which members have received training. 9.2 Informal Process through Dispute Resolution Groups However the nature of grievances that arise in complaints or claims with regard to compensation require a mechanism that is affordable and timely, and one which is not encumbered with technicalities. Although an official framework of grievances and conflict resolution in matters of compensation and resettlement is not explicitly legislated in Tanzania, practice and experience does exist. Project, grievances are handled by a Grievance Redress Committee formed at project level that will administratively be formed as part of the Project Field Payments Teams. This arrangement was made known to PAP during the negotiations process. The Disputes Resolution Group normally included experts that were not on the team that carried out the valuation. The Disputes Resolution Group will include a team of experts including an independent valuer, lawyer and a sociologist involving the local leadership i.e. Village Chairman or Village Executive Officer. In the case where the affected person is not satisfied with the decision of the Disputes Resolution Group, the matter will be referred to the Commissioner for Lands 54 Chapter 10 10. FUNDING ARRANGEMENTS The arrangements include the preparation and review of costs estimates, the flow of funds, and contingency arrangements. The base compensation will be met by DAWASA through funds to be provided by the government through the Ministry of Water and Irrigation. The total number of people who will be affected by this project is 143 (63 in Mpera, 67 in Kimbiji and 13 in water storage facilities areas of Pugu Kajiungeni and Buyuni). The 12 – month average annual headline inflation increased to 12.1 percent in December 2009 from 10.3 percent recorded in the corresponding period (January 2008 to December 2008) (Bank of Tanzania monthly economic review, January 2010). For the purpose of this evaluation an inflation rate of 12.1% + 1% i.e. 13.1% will be used to compound the entitlements. 10.1 Compensation Entitlements for Mpera The compensation entitlement for Mpera sub-project is influenced by for the typical characteristics of assets (structures size and type of construction, land, crops including trees). The Mpera characteristics are shown in Table A2-1 in Appendix 2. The levels of compensation for Mpera well field sub project was evaluated to amount to a total of 1,228,531,394 TShs. Compensation for land was 64,276,000TShs., compensation for loss of structures/buildings was 162,060,291 TShs.; compensation for crops was 963,279,345 TShs., relocation/transport allowance was 14,175,000 TShs. Other Assistance (i.e. disturbance and accommodation amounted to 24,740,758 TShs. The detail breakdown is given in Table A2-2 in Appendix 2. The valuations were completed in January 2010 but no payments have been done. It is likely that the payments might be delayed to next year that is over six months cut off time. 55 Using a headline inflation index of 13.1%, the inflation adjusted compensation entitlements will thus be 1,228,531,392 TShs. The budget for upgrading the valuation to meet the requirement of the World Bank Involuntary Resettlement Policy is in this report called the supplementary budget. This supplementary budget2 for Mpera well field sub project was evaluated to amount to a total of 905,653,893 TShs. Compensation for loss of structures/buildings was 162,060,291 TShs. compensation for crops was 963,279,343 TShs. Accommodation; relocation/transport allowance was 38,915,758,000 TShs. The Entitlement Matrix for Mpera is given in Table 4. 10.2 Compensation Entitlements for Kisarawe II (Kimbiji) The compensation entitlement for Kisarawe II (Kimbiji) sub-project is influenced by for the typical characteristics of assets (structures size and type of construction, land, crops including trees). The Kisarawe II characteristics are shown in Table A2-3 in Appendix 2. The total compensation for this component is 457,080,680 TShs. Compounded from 31,016,750 TShs for compensation for structures/buildings, 225,021,560 TShs. for compensation for land. Compensation for crops was 160,189,084 TShs. Compensation for accommodation, transport and disturbance was 40,853,286 TShs. The supplementary budget for compensation for Kimbiji (Kisarawe II) well field sub project was evaluated to amount to a total of 163,565,890 TShs. Compensation for crops was 143,946,189TShs, relocation/transport allowance was 15,075,000 TShs. Other Assistance (i.e. disturbance and accommodation amounted to 4,544,701 TShs. Likewise, the inflation adjusted compensation entitlements will be 184,993,022 TShs. The Entitlement Matrix for Kisarawe II (Kimbiji) is given in Table 5. 2 “Supplementary budget� is the budget which is above the budget which would be for the compensation based strictly on the Tanzanian laws. It covers differences in value of structures (covering actual replacement values, values of trees, loss of profit from business, compensation for investment cost in farms/agriculture, etc.) 56 Table 4: Entitlement Matrix for Mpera Well Fields Number of Value Value as a % of Affected Categories Affected (Compensation Compensation Entitlement People Budget) [TShs] Budget Cash compensation calculated based on the legal Houses 15 162,060,291 13.2 procedures to replacement value for land similar to the one lost Land (other than of Full compensation of the replacement cost in a similar/ 63 64,276,000 5.2 house) comparable area Crops 63 913,072,269 74.3 Cash compensation to cover loss of equivalent earning Non Perennial Crops 63 50,207,074 4.1 Cash compensation to cover loss of equivalent earning Cash compensation to cover loss of equivalent earning for Business (loss of profit) - - - the duration in which a new business is not yet established (3 years) Relocation & Additional compensation paid in lieu of moving and Disturbance 63 38,915,758 3.2 transition allowance Allowance Totals 1,228,531,392 100.0 Vulnerable households Given support during evaluation. Their assets were given 3 40,643,737 3.3 (the elderly) priority in assessing. The same to be done during payment 57 Table 5: Entitlement Matrix for Kimbiji well Field Value Affected Number of Value as a % of (Compensation Entitlement Categories Affected People Compensation Budget Budget) [TShs] Cash compensation calculated based on the legal Houses 14 31,016,750 6.8 procedures to replacement value for land similar to the one lost Land (other than Full compensation of the replacement cost in a similar/ 52 225,021,560 49.2 of house) comparable area Crops 40 158,785,357 34.7 Cash compensation to cover loss of equivalent earning Non Perennial 60 1,403,727 0.3 Cash compensation to cover loss of equivalent earning Crops Cash compensation to cover loss of equivalent earning Business (loss of - - - for the duration in which a new business is not yet profit) established (3 years) Relocation & Ensure that their monthly assistance from the charity Disturbance 67 40,853,286 8.9 organizations is not cut. In addition, a onetime cash Allowance payment up to an amount of USD 1000 Additional compensation paid in lieu of moving and Totals 457,080,680 100.0 transition allowance Given support during evaluation. Their assets were given The Vulnerable 7 45,766,250 10.0 priority in assessing. The same to be done during (the Elderly) payment 58 10.1 Compensation Entitlements for Water Storage Facilities Land was acquired land for water storage facilities at Pugu Kajiungeni and Buyuni. This procurement was done before the completion of the RAP and based on the principles of the existing Resettlement Policy Framework (RPF) to allow for strategic design of water transmission lines from the well fields to the storage facilities. During the development of this RAP, a review of the procedure and the resulting compensation was done to ensure that it was done in accordance with the existing Resettlement Policy Framework (RPF). After this review we can acknowledge that the procedures used were in line with the existing RPF. The total number of the PAPs for the water storage was 13 with 13 houses. The characteristic of the PAP for this component is presented in Table A2-3 in Appendix 2. In this sub project, the total compensation amounted to 703,435,093 TShs. covering 309,163,450 TShs. for structures/buildings, 101,763,125 TShs. for land, 221,314,865 TShs. for crops. Compensation for loss of profit from business was 10,800,000 TShs. Allowances for relocation/transport would amount to 2,925,000TShs. While other Assistance (i.e. disturbance and accommodation amounted to 57,468,653 TShs. As stated earlier, the compensation entitlement for the water storage facilities have already been paid. The inflation adjusted compensation would amount to 795,585,090 TShs. The Entitlement water storage facilities) is given in Table 6. 59 Table 6: Entitlement Matrix for Water Storage Facilities Value as a % of Number of Value (Compensation Affected Categories Compensation Entitlement Affected People Budget) [TShs] Budget Cash compensation calculated based on Houses 11 44.0 the legal procedures to replacement 309,163,450 value for land similar to the one lost Full compensation of the replacement cost Land (other than of house) 13 14.5 101,763,125 in a similar/ comparable area Cash compensation to cover loss of Crops 13 30.9 217,633,305 equivalent earning Cash compensation to cover loss of Non Perennial Crops 8 0.5 3,681,560 equivalent earning Cash compensation to cover loss of equivalent earning for the duration in Business (loss of profit) 1 1.5 10,800,000 which a new business is not yet established (3 years) Relocation & Disturbance Additional compensation paid in lieu of 13 8.6 Allowance 60,393,653 moving and transition allowance Totals 100 703,435,093 Given support during evaluation. Their Vulnerable households (the 0 0 assets were given priority in assessing. The elderly) - same to be done during payment 60 The Summary of Compensation for RAP Phase I is shown in Table 7. Table 7: Summary of Compensation for RAP Phase I Compensation in Million Tanzanian Shillings Loss of Component Structures Land Crops Transport Disturbance Total Profit Mpera 1,621 643 9,633 0 142 247 12,285 Kisarawe II 310 2,250 1,602 0 151 258 4,571 (Kimbiji) Water storage 3,092 1,018 2,213 108 29 575 7,034 facilities 5,022 3,911 13,448 108 322 1,080 Grand Total 23,890 61 Chapter 11 11. CONSULTATION AND PARTICIPATION Public consultation and participation are essential because they afford potential displaced persons the opportunity to contribute to both the design and implementation of project activities. The socio-economic situation prevailing in Tanzania as discussed earlier, makes public consultation with the communities, indispensable. Furthermore, it is the local communities who are to claim ownership of this project for it to be successful and their wealth of knowledge of local conditions are invaluable assets to the project. In recognition of this, particular attention was paid to public consultation with potentially affected individuals/households when resettlement and compensation concerns are involved. 11.1 Consultative Strategy Stakeholder consultations are an important element of Resettlement Action Plan (RAP) since it ensures that all the interested and affected stakeholders are involved in the project. It also enhances collaboration between the developers and stakeholders throughout all the phases of a project. Therefore it is important to involve all key stakeholders and capture adequate information. In order to make sure that all key stakeholders are consulted and adequate information are captured different strategies were applied. These include literature review, site visit in order to verify the project area and project boundaries. 11.2 The Consultative Process Consultative process involved identification of relevant stakeholders, notification and involvement. This section provides a description of the stakeholder involvement process conducted for the RAP for the proposed Kimbiji and Mpera well-field projects. 11.2.1 Stakeholder identification and methods of participation 62 The preliminary site visits were carried out in gathering adequate information on the site issues related to the Resettlement Action Plan, identification of spatial boundaries and pre identification of all stakeholders who will be affected by the definition of the spatial and institutional boundaries for the proposed development in Dar es Salaam and Coat Regions provide the dimensions of defining stakeholders who involved in the RAP. The following stakeholders were identified: (a) Institutional stakeholders: Institutional stakeholders were defined as decisions that might affect the proposed development project. These are: (i) Ministries  Lands, Housing and Human Settlement Development;  Water and Irrigation;  Health and Social Welfare;  Education; and  Natural Resources and Tourism. 63 (ii) Local governments  Dar es Salaam City Council (DCC);  Temeke Municipal Council (TMC);  Mkuranga District Council;  Ward (Kisarawe II); and  Village Councils (Kisarawe II and Mpera). (iii) Others  TANROADS;  DAWASA/DAWASCO;  TANESCO;  NBS;  DDCA;  WRBWO; and  TPDC. (b) Individual stakeholders: Individual stakeholders referred to those owning, living or working within the immediate impact area that will experience the highest level of impacts resulting from project implementation. They include:  Affected Households within the project area  Unaffected Household within the project area  Water users  Dar es Salaam Zoo owner  Local inhabitants (Farmers) 64 11.2.2 Methods of stakeholder participation Stakeholder’s interviews and consultations were the main methods followed during Resettlement Action Plan. The team involved the key identified stakeholders in order to generate issues of concern in relation to project implementation. In respect of the intended project activities, the stakeholders that were consulted raised concerns on a number of issues that need attention. Concerns raised vary from one type of stakeholders to another (from Ministerial and district officials to villages concerns). The issues raised were:  Land acquisition  Land and property compensation  Employment 11.2.3 Notification to stakeholders Stakeholders were notified prior meeting with them. Notifications were through use of letter and telephone communication. 11.2.4 Household interviews Household interviews were conducted to the affected population only. Household Questionnaires were used in both Mpiji and Mpera well field area 65 11.2.5 Official meetings with village leaders Village public meetings were conducted using checklist. Village officials including Chairman, Village executive Officer and committee members were invited and participated infectively. 11.2.6 Meetings with districts officials Two districts were relevant to the project; namely Temeke in Dar es Salaam region and Mkuranga in Coast region. District officials were notified and consulted. Checklist and open discussion were applied during meeting with district officials. 11.2.7 Consultations with other relevant stakeholders Other relevant stakeholders include developer (DAWASA), DAWASCO, World Bank, relevant ministries such as ministry of water and Irrigation, Ministry of Lands, Housing and Human Settlement Development. The RAP team visited these stakeholders and undertook open discussion guided by checklist in order to capture adequate information. 11.3 Summary of Stakeholder Issues and Concerns In respect of the intended project activities, the stakeholders that were consulted raised concerns on a number of issues listed below: (a) Land: This has been one of their major concerned especially on exactly what size of the land to be acquired for the well-field. To the local farmers and land owners. DAWASA being unclear at this stage, has decided to conduct the RAP in two 66 phases due to budget constraints: i) areas within 60 m around individual wells or ii) the whole demarcated well-field area which need to be gazetted for protection of the well fields. Now that two phase RAP has been adapted, this one for the 60 m around the individual wells and one for the whole demarcated well field. The PAPs have been informed by the minister for water through public meeting and letter to the local government. Accordingly the PAPs can plan the use of the remaining land accordingly as the valuated initial compensation for the whole well-field (the 27 km2 at Kimbiji) was suspended. The binding compensation is the current Phase I RAP (the 60 m perimeter around individual wells) implemented to fast-track the drilling of wells is. The well-field areas have, however, been demarcated and the PAPs were consulted in the process of preparing the valuation of the area are aware of the pending development. (b) Property compensation Another concern raised by the PAPs during the initial consultation was the compensation rates given for different types of perennial crops from on-going evaluation of the well-field land to be acquired. Some have indicated, for example, an annual economic return from a mango tree of up to TShs. 100,000 or more while it is compensated at TShs. 25,000. To them, this is unacceptably low compensation rate that is not attractive for selling their land. The entitlement matrix in this RAP uses better rates e.g. TShs. 375,000/year/tree (See Table “A2 - 1: Guiding Compensation Rate per Unit of Asset�). (c) Employment This was raised from the need of local inhabitants for securing temporary unskilled labour jobs particularly during construction and also during operation of the facilities. They indicated such jobs as casual labourers during construction activities and watchmen/ security guards during operation of the facilities. Affected communities expect to lose farmlands and crops would like to be given priority for temporary unskilled jobs to recompense from loss of their properties even if they are expected to be compensated from loss of their properties. 67 Chapter 12 12. RESETTLEMENT IMPLEMENTATION SCHEDULE 12.1 Resettlement Implementation Schedule The actual resettlement costs of the project have yet to be determined. It is important to note that the process is governed by law and the procedures are at times very slow. The frequent changes in the design while understandable are none the less compromising the progress. It is important to complete the valuation exercise so that resettlement costs are not underestimated. The costs of resettlement planning and implementation must additionally be factored in. The project proponent indicates that the source of funding for the RAP budget will be the government. It is important that adequate notice and preparation are made to factor in the so common difficulties to overcome unpredictable cash flows from government coffers. The RAP budget should be linked with a detailed implementation schedule for all key resettlement and rehabilitation activities. A tentative schedule is shown below. 68 Table 8: Resettlement action plan schedule 2010 2011 2012 Task Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Completion of draft RAP Approval of Draft RAP Community consultation Negotiation or resettlement sites Confirmation or relocation sites Notification of entitlements Agreement of entitlements Establish linkages with other government programmes Notice of demolition Grievance mechanisms & procedures Preparation of site plans Demolition of old structures Drilling of wells Construction f tanks Layout of pipes Performance monitoring External evaluation 12.1 Conclusion This RAP has noted that the proposed project will meet the requirements for increasing the water supply Dar es Salaam and nearby communities and will have little to moderate negative impacts on environment and people. The more serious concerns revolve around social impacts, to which mitigation measures, including compensations have been proposed. Therefore, the proposed development qualifies for consideration alongside the implementation of the proposed mitigation measures. For the loss of land, crops and structures, this RAP recommends alternative routings as a measure to reduce the effect of the proposed project on such structures. The proposed alternatives do not completely remove impacts, but simply reduces the severity of the impacts. For example, some alternatives may reduce the number of affected houses and structures in some specific areas or will affect houses whose value is relatively low, and hence manageable through compensation. In addition, this RAP recommends fair and prompt compensation where alternative routes are untenable. All project affected people must receive cash compensation based on national and international standards applicable in such cases so that the compensation renders them at least as well off and possibly better off than before the commissioning of the project. 69 A valuation of properties will be carried out by government Valuers to identify all affected households and to determine the value of houses, fixed assets, crops and trees that will be lost because of the transmission line. A grievance or complaint procedure will be established to make sure that all PAP are properly compensated and have a possibility to appeal if they are dissatisfied with the awarded compensation amount. Considerable notification must be given to all PAP to participate in person in meetings deliberating on compensation issues, as detailed in this RAP. 70 Chapter 13 13. MONITORING The arrangements for monitoring will fit into the overall monitoring plan of the entire project. This will institute a reporting system that: (a) Alerts project authorities to the necessity for land acquisition in a project; (b) Provides timely information about the valuation and negotiation process; (c) Reports any grievances that require resolution; and (d) Documents timely completion of project resettlement obligations (i.e. payment of the agreed-upon sums, construction of new structures, etc) for all permanent and temporary losses, as well as unanticipated, additional construction damage. 12.2 General Objectives and Evaluation Monitoring The objective will be to make a final evaluation in order to determine:  if affected people have been paid in full and before implementation of the project; and  if the people who are affected by the project have been affected in such a way that they are now living at a higher standard than before, living at the same standard as before, or they are poorer than before. To assess whether these goals are met, the resettlement and compensation plans will indicate parameters to be monitored, milestones to be met and provide the resources necessary to carry out the monitoring activities. Local Governments will maintain information on all individuals impacted by the projects' land use requirements including relocation/ resettlement and compensation, land impacts or damages. Each individual will have a compensation dossier recording his or her initial situation, all subsequent project uses of assets/ improvements, and compensation agreed upon and received. 71 A watch will be kept over process indicators and regularly reported through DAWASA, local government to the Permanent Secretary of the Ministry of Water and Irrigation. These will include: (a) Number of grievances and time and quality of resolution; (b) Relations between the project and the local communities; (c) Percentages of individuals selecting cash or a combination of cash and in-kind; (d) Compensation; (e) Outstanding village compensation contracts; (f) Outstanding individual compensation or resettlement contracts; (g) Seasonal or inter- annual fluctuation of key foodstuffs; (h) Number of impacted locals employed by the civil works contractors; (i) Training of affected; (j) Use of payments; and (k) Number of contentious cases out of the total. The following indicators will be used in assessing the overall effectiveness of implementation of resettlement and compensation plans: (a) Pre-project production versus present production (crop for crop, land for land); (b) Ability of individual and families to -re establish their pre-displacement activities, standard of living, and land and crops or other alternative incomes; (c) Outstanding compensation or resettlement contracts not completed before next agricultural season; (d) Grievances recognized as legitimate out of all complaints lodged. (e) Communities unable to settle at village-level grievances/compensation after two years; and (f) All legitimate grievances rectified and time frame. DAWASA and the Ministry of Water and Irrigation will maintain financial records to permit calculation of the final cost of resettlement and compensation per individual or household. Each individual receiving will have a dossier containing:  individual bio-data information; 72  number of people s/ he claims as household dependents; and  amount of land available to the individual or household when the dossier is opened. Additional information will be acquired for individuals eligible for resettlement /compensation:  level of income and of production;  inventory of material assets and improvement in land; and debts. Each time land is used by the project; the dossier will be updated to determine if the individual or household is being affected to the point of financial non-viability and eligibility for compensation/ resettlement or its alternative. These dossiers will provide the foundation for monitoring and evaluation, as well as documentation of compensation agreed to, received, and signed for. It is normal that some compensation procedure and rates may require revision at some time during the project cycle. The Local Government will implement changes, which will require feedback from:  indicators monitored by the local governments to determine whether goals are being met; and  a grievance procedure for the local community to express dissatisfaction about implementation of compensation and resettlement. 12.3 Evaluation Objectives These are two categories of these objectives, i.e. the internal and external objectives as discussed hereunder. 13.2.1 Internal evaluation The internal evaluation has the specific objectives of general assessment of the compliance of the implementation of the RAP with objectives and methods defined in this document; 73 assessment of the compliance of the implementation of the RAP with laws regulations and safeguard policies as stated above; and assessment of the consultation procedures that took place at individual and community levels, as well as with relevant district, municipal and national authorities. The other objectives are to assess the fairness, adequacy and prompt compensation and resettlement procedures as they have been implemented; to evaluate the impact of the compensation/resettlement program on incomes and/or standards of living, with focus on the "no worse-off" requirement; and to identify actions to be taken as part of the on-going monitoring to improve the positive impacts of the program and mitigate against possible negative impacts. 13.2.2 External evaluation External evaluations may be conducted for instance either by WB missions and/or by missions of representatives of other interested institutions. The external monitoring evaluations may cover aspects such as the implementation progress, the compensation and resettlement policies, the status of the delivery of entitlements, the progress and changes in living conditions of relocated people and consultation with affected people (PAP) and other stakeholders. Independent evaluation of the RAP implementation should be conducted in at least two successive stages. The first of these evaluations should take place within 6 months after completion of the implementation, while the second may take place within two years after completion of the implementation. For comparative purposes, both evaluations should be carried out using a similar methodology and using the same indicators. 74 Chapter 14 14. CONCLUSION This RAP has noted that the proposed project will meet the requirements for increasing the water supply Dar es Salaam and nearby communities and will have little to moderate negative impacts on environment and people. The more serious concerns revolve around social impacts, to which mitigation measures, including compensations have been proposed. The proposed development thus qualifies for consideration alongside the implementation of the proposed mitigation measures. The recommended offered during the Environment and Social Impact assessment stage, particularly in the selection of water mains pipe significantly reduced the size of land to be acquired and thus minimized loss of land, crops and structures. In addition, this RAP recommends fair and prompt compensation where alternative routes are untenable. All project affected people must receive cash compensation based on national and international standards applicable in such cases so that the compensation renders them at least as well off and possibly better off than before the commissioning of the project. The valuation of properties, land, crops and other assets was carried out by municipal Valuers in the presence of the owner of the property/asset and the survey team. Grievance or complaint procedures have been established to make sure that all PAP are properly compensated and have a possibility to appeal if they are dissatisfied with the awarded compensation amount. The compensation budget for the project (that is World Bank compliant) is 2,389,047,167 TShs. (or 2,702,012,346 TShs. if adjusted for 13.1% headline inflation). 75 Chapter 15 15. BIBLIOGRAPHY FC Handbook for Preparing a Resettlement Action Plan; 2121 Pennsylvania Avenue, NW Washington, DC 20433 USA; OP 4.12 - Involuntary Resettlement, The World Bank, December, 2001; AAW, DCL and Norplan (2008). Development of a Strategic Water Supply Plan for Dar es Salaam: Water Supply Improvement Plan Report. DEH (2006). Water efficiency guide: Office and public buildings, 59p. Fagotti, C. and Poggi, A., (1995). Traffic Noise Abatment Strategies. The Analysis of Real Case not Really Effective. In: Proc. of 18th International Congress for Noise Abatment, Bologna (Italy), 223-233. Josse, R. (1972). Notions d’acoustique Paris. France: Ed. Eyrolles. NBS (2003). Population and Housing Census. Norconsult (2008). Environmental Impacts Statement for the Kidunda Dam: Main Report and Appendices, 247p + 150p. Norconsult, WRA and NIVA (2005). Development of a Future Water Source for Dar es Salaam: Water Source Options Review Draft, 235p. Norconsult, WRA and NIVA (2007). Development of a Future Water Source for Dar es Salaam: Pre-Design and Environmental Report: Part 1: Water Source Medium Term Works Pre-Design. 76 Norconsult, WRA and NIVA (2007). Development of a Future Water Source for Dar es Salaam: Pre-Design and Environmental Report: Part 2: Review of Social and Environmental Factors. Norconsult, WRA and NIVA (2007). Development of a Future Water Source for Dar es Salaam: Water Source Development Master Plan. Torell, E. and Mmochi, A., (2006), Mkuranga Governance Baseline, Coastal Resources Center, University of Rhode Island, 18p. URT (1995). National Land Policy. URT (1997a). National Environmental Policy. URT (1997b) National Employment Policy. National Wildlife Policy. URT (1999a). National Tourism Policy. URT (2001). National Policy on HIV/AIDS. URT (2002a). National Water Policy. URT (2003a). National Energy Policy. URT (2003b). National Transport Policy. URT (2005). Environmental Impact Assessment Regulations. WBG (1998). World Bank Pollution Prevention Handbook WHO (1999). Community noise guidelines, 161p. 77 WHO (2000). Air quality guidelines for Europe, 2nd Edition, 288p. WHO (2005). Air quality guidelines: Global updates, 496p. WHO (2007). Night noise guidelines for Europe: Final implementation 78 APPENDIX Appendix I: Crop Compensation Rates for Period Commencing on 01/01/2010 A1- 1: Perennial Crops Market Value in TShs. Per Hectare Per stem or cluster Crops Plant Average between Population Cared Mature Average seedlings to Per Hectare Crop Cared Mature first harvest Aged Crop Seedlings (say Crop A (say 50% of A) (say 25% of A) 25% of A) A Cash Crops 1 Coconut (Minazi) 125 7,150,000 57,200 28,600 14,300 5,720 2 Cashewnuts (Mikorosho) 100 3,796,000 37,960 18,980 9,490 3,796 3 Sugar cane(Miwa) 12,500 26,000,000 2,080 1,040 520 208 4 Oil palm (Michikichi) 150 4,680,000 31,200 15,600 7,800 3,120 5 Cloves (Mikarafuu) 200 14,560,000 72,800 36,400 18,200 7,280 6 Msufi 200 2,600,000 13,000 6,500 3,250 1,300 7 Tobacco 13,000 10,400,000 800 400 200 80 8 Sisal 5,000 20,000,000 4,000 2,000 1,000 400 9 Cocoa 1,000 20,000,000 20,000 10,000 5,000 2,000 10 Cotton 40,000 32,000,000 800 400 200 80 11 Coffee 2,000 40,000,000 20,000 10,000 5,000 2,000 B Fruits 1 Ovacado (Mparachlohl) 100 3,380,000 33,800 16,900 8,450 3,380 2 Ovacado (Improved) 150 9,000,000 60,000 30,000 15,000 6,000 79 Market Value in TShs. Per Hectare Per stem or cluster Crops Plant Average between Population Cared Mature Average seedlings to Per Hectare Crop Cared Mature first harvest Aged Crop Seedlings (say Crop A (say 50% of A) (say 25% of A) 25% of A) 3 l^angarine (Mchenza) 250 8,450,000 33,800 16,900 8,450 3,380 4 Oranges (Machungwa) 250 9,100,000 36,400 18,200 9,100 3,640 5 Lemon (Ndimu) 250 3,250,000 13,000 6,500 3,250 1,300 6 Mlimau (Lemon improved) 250 3,250,000 13,000 6,500 3,250 1,300 7 Mango (mwembe) 75 3,120,000 41,600 20,800 10,400 4,160 8 Mango(Mwembe) improved 150 12,480,000 83,200 j 41,600 20,800 8,300 9 Guava (Mpera) 150 2,340,000 15,600 7,800 3,900 1,560 10 Jackfruit (Mifenesi) 75 2,340,000 31,200 15,600 7,800 3,120 11 Bananas(Migomba 6) 750 21,450,000 28,600 14,300 7,150 2,860 12 Pinaples (Minanasi) 10,000 15,600,000 1560 780 390 156 13 Pawpaw (Mipapai) 800 8,000,000 10,000 5,000 2,500 1,000 14 Mikweme (Oyster nuts) 150 4,680,000 31,200 15,600 7,800 3,120 15 Kongamanga 250 1,300,000 5,200 2,600 1,300 520 16 Mistafeli (Custard apple) 350 3,640,000 10,400 5,200 2,600 1,040 17 Mitende (Date palm) 125 650,000 5,200 2,600 1,300 520 18 Passion fruits 1,111 4,444,000 4,000 2,000 1,000 400 19 Pears 156 6,489,600 41,600 20,800 10,400 4,160 20 Apples 156 6,489,600 41,600 20,800 10,400 4,160 21 Plums/Peaches 156 6,489,600 41,600 20,800 10,400 4,160 22 Mlozi (Almond) 150 3,120,000 20,800 10,400 5,200 2,080 23 Walnuts 150 5,694,000 37,960 18,980 9,490 3,796 24 Chestnuts 150 5,694,000 37,960 18,980 9,490 3,796 Note: For improved varieties like mango, citrus, guava etc. compensation will base on costs provided by the farmer upon approval 80 Market Value in TShs. Per Hectare Per stem or cluster Crops Plant Average between Population Cared Mature Average seedlings to Per Hectare Crop Cared Mature first harvest Aged Crop Seedlings (say Crop A (say 50% of A) (say 25% of A) 25% of A) by professional horticulturist C SPICES 1 Cardamon (lliki) 800 3,200,000 4,000 2,000 1,000 400 2 Cinamomum (Mdalasini) 1,500 6,240,000 4,160 2,080 1,040 416 3 Black pepper (Pilipili Manga) 1,500 7,800,000 5,200 2,600 1,300 520 4 Tangawizi (Ginger) 5,000 19,000,000 3,800 1,900 950 380 5 Macademia nuts 100 3,796,000 37,960 18,980 9,490 3,796 6 Vanilla . 1,000 10,000,000 10,000 5,000 2,500 1,000 7 Flowers 2,500 10,000,000 4,000 2,000 1,000 400 8 Rossela 2,500 10,000,000 4,000 2,000 1,000 400 9 Alovera 2,500 10,000,000 4,000 2,000 1,000 400 10 Litch (Shokishoki) 100 20,000,000 200,000 100,000 50,000 20,000 11 Mashelisheli 100 20,000,000 200,000 100,000 50,000 20,000 D MENGINEYO 1 Mchikichi (Palm) 2 Mianzi (Bambo) 100 20,000,000 200,000 100,000 50,000 20,000 3 Mzabibu (Grape) 2,857 11,428,000 4,000 2,000 1,000 400 4 Msufi (Kapok) 200 2,600,000 13,000 6,500 3,250 1,300 5 Mlozi (Indian Almondi) 250 3,250,000 13,000 6,500 3,250 1,300 6 Mzeituni 400 33,280,000 83,200 41,600 20,800 8,320 7 Mkungumanga (Nutmeg) 400 5,200,000 13,000 6,500 3,250 1,300 81 A1- 2: Value of mixed crops per stem/cluster Market Value per Type of Crop Stem/Cluster 1 Shade trees 13,100.00 2 Katani 1,872.00 3 Miti ya mbao Ngumu i.e Mninga, Mpingo etc. 65,000.00 4 Mbilimbi 3,900.00 5 Nyanya chungu 1,300.00 6 Spinachi 1,300.00 7 Cassava ( Tshs 617,500/- per acre) 780 8 Mianzi(bamboo) 15,600.00 9 Nyasi za Ng'ombe( Elephant grass) 1,040.00 10 Mkulabi 5,200.00 11 Mkungu 13,000.00 12 Mbuyu 39,000.00 13 Mtopetope 10,400.00 14 Mzartlbarau 13,000.00 15 Mkwaju 20,800.00 16 Matikiti maji 6,500.00 17 Mikaratus 13,000.00 18 Mfuru 2,600.00 19 Maboga 5,200.00 20 Kunde 780 21 Mwarobaini 13,000.00 22 Mng'ong'o 26,000.00 23 Mlonge 26,000.00 24 Mpira(rubber) 13,000.00 25 Mgundi(Gum) 13,000.00 26 Mpilipili 2,080.00 27 Mkrismasi 13,000.00 28 Mzabibu 10,400.00 29 Bamia 1,300.00 30 Lucina trees 13,000.00 31 Mitufaa(apple) 13,000.00 32 Ashok trees 13,000.00 33 Mihogo(shlna) 780 34 Mbaazi(shina) 780 35 Michongoma 650 36 Misonobari 13,000.00 37 Gravelia 13,000,00 38 Rossella 4,000.00 39 Flowers 40,000.00 40 Mashokishoki 200,000.00 41 Macademia nuts( karariga miti) 37,960.00 42 Peaches 41,600.00 82 A1- 3: Value of seasonal Crops per hectare Maturity of Crop Crop Sowing to Knee high to Mature Crops Knee 10% tussling 50% A CEREALS Maize ( Mahindi Ukanda wa 1 28,600.00 143,000.00 286,000.00 chini) Maize ( Mahindi Ukanda wa 2 28,600.00 143,000.00 286,000.00 Kati) Maize ( Mahindi Ukanda wa 3 28,600.00 143,000.00 286,000.00 Juu) Paddy (Mpunga) wa 4 39,000.00 195,000.00 390,000.00 mabondeni 5 Paddy (Mpunga) wa Mwinuko. 39,000.00 195,000.00 390,000.00 6 Sorghum (Mtama) 20,800.00 104,000.00 208,000.00 7 Ulezi 62,400.00 312,000.00 624,000.00 8 Uwele 62,400.00 312,000.00 624,000.00 9 Ngano 114,400.00 572,000.00 1,144,000.00 B OIL SEEDS 1 Sunflower (Alizeti) 44,200.00 221,000.00 442,000.00 2 Ground Nuts (Karanga) 54,600.00 273,000.00 546,000.00 3 Ufuta (simsim) 80,830.60 404,153.00 808,306.00 4 Castor Nyonyo 13,000.00 65,000.00 130,000.00 5 Jatropher 2,000.00 10,000.00 20,000.00 6 Soybean 169,000.00 845,000.00 1,690,000.00 7 MIonge 2,120.00 10,600.00 21,200.00 8 Kweme 3,796.00 18,980.00 37,960.00 9 Walnuts 3,780.00 18,900.00 37,800.00 C BEANS 1 Choroko - - 2 Beans (Maharage) 22,620.00 113,100.00 226,200.00 3 Mbaazi 20,280.00 101,400.00 202,800.00 4 Kunde 22,620.00 113,100.00 226,200.00 5 Njegere 169,000.00 845,000.00 1,690,000.00 6 Bambara nuts (Njugumawe) 169,000.00 845,000.00 1,690,000.00 7 Fiwi nuts 169,000.00 845,000.00 1,690,000.00 8 Dengu 169,000.00 845,000.00 1,690,000.00 D MIZIZI 1 Cocoyams (Magimbi) 75,400.00 377,000.00 754,000.00 2 Cassava(Mihogo) 123,500.00 617,500.00 1,235,000.00 3 Sweet potatoes (Viazi vitamu) 54,600.00 273,000.00 546,600.00 4 Irish Potatoes (Viazi mviringo) 180,700.00 903,500.00 1,807,000.00 5 Viazi vikuu (yams) 75,400.00 377,000.00 754,000.00 E VEGETABLES 1 Bamia 49,400.00 247,000.00 494,000.00 2 Bilinganya 74,360.00 371,800.00 743,600.00 83 Maturity of Crop Crop Sowing to Knee high to Mature Crops Knee 10% tussling 50% 3 Kabichi 156,000.00 780,000.00 1,560,000.00 4 Karoti 254,800.00 1,274,000.00 2,548,000.00 5 Koliflawa 71,500.00 357,500.00 715,000.00 6 Maboga 78,000.00 390,000.00 780,000.00 7 Matango 35,000.00 175,000.00 350,000.00 8 Matikiti maji 152,100.00 760,500.00 1,521,000.00 9 Mchicha 57,200.00 286,000.00 572,000.00 10 Nyanya 23,600.00 118,000.00 236,000.00 11 Pilipili hoho 57,980.00 289,900.00 579,800.00 12 Pilpili kali 180,700,00 903,500.00 1,807,000.00 13 Saladi/Lectuce/Chinese 79,300.00 396,500.00 793,000.00 14 Vitungu maji/Onion 308,100.00 1,540,500.00 3,081,000.00 15 Vitungu saumu/Garlic 332,800.00 1,664,000.00 3,328,000.00 16 Mnafu 57,200.00 286,000.00 572,000.00 17 Matemt>ele 57,200.00 286,000.00 572,000.00 18 Nyanya chungu 74,360.00 371,800.00 743,600.00 19 Spinachi 57,200.00 286,000.00 572,000.00 20 Mishelisheli 20,000.00 100,000.00 200,000.00 21 Beetrot; 254,800.00 1,274,000.00 2,548,000.00 22 Radishes 254,800.00 1,274,000.00 2,548,000.00 84 Appendix 2: Upgrading Compensation for Various Sub Projects A2.1 Compensation for Mpera Sub project The valuation characteristics of the Mpera, Kisarawe II and Storage facilities are shown in Tables A2-1 to A2-3. The corresponding base valuations of the assets (structures, farm land, crops, loss of profit from business, etc.) are presented in Tables A2-4 to A2-6. The base valuation puts the compensation for Mpera well field sub project (Table A2-4) at a total of 322,877,501 TShs. Compensation for land was 64,276,000 TShs., compensation for loss of structures/buildings was 137,524,900 TShs.; compensation for crops was 97,674,853 TShs., relocation/transport allowance was 3,240,000 TShs. Other Assistance (i.e. disturbance and accommodation amounted to 20,161,748 TShs. The base valuation is the valuation done based on or current local (Tanzanian) laws which unfortunately in some cases does not meet the minimum requirement of the funding agency- The World Bank Involuntary Resettlement Policy (OP. 4.12). This policy for example requires compensation to be based in the full replacement value of structures, cost of investment made on land or crop production, etc. To meet these requirements, the base valuation has to be upgraded. A2.2 Compensation for Kisarawe II Sub project The corresponding base compensation valuation for the Kisarawe II (Kimbiji) sub project is 293,514,790 TShs. Compounded from 31,016,750 TShs for compensation for structures/buildings, 225,021,560 TShs for compensation for land. Compensation for crops was 16,242,895 TShs. Other Assistance (i.e. disturbance and accommodation amounted to 21,233,585 TShs. The breakdown for the Kisarawe II compensation is given in Table A2-5. A2.3 Compensation for Storage Facilities Sub project Land for water storage facilities had to be acquired. This land in fact was acquired before this RAP was developed. As discussed under section 10.1 the resulting compensation was reviewed (and found to have done so) during the development of this RAP to ensure that it was done in accordance with the involuntary resettlement policy. The compensation for land for storage facilities at Pugu Kajiungeni and Buyuni (Table A2-6) totalled 503,718,274 TShs. covering 309,163,450 TShs. for structures/buildings, 101,763,125 TShs. for land, 10,800,000 TShs. for crops, 22,440,943 TShs. to cover loss of profit from businesses, 640,000 TShs as relocation/transport allowance. Other Assistance (i.e. disturbance and accommodation amounted to 58,910,756. 85 A2- 2: Compensation Characteristics for the Mpera Sub Project Total No Type of No of Non Perennial Farm Project Affected Person (PAP) Property Area of Rooms Property Trees Trees Area 1 Abdul Ally Mpande 595 12 2 Mateo Ovide Doto 36 3 Jumanne Selemani Mvuma 81 4 Masudi Bakari Mtitu 50 5 Salama Mbaraka Kiumbo 59 6 Kilio Shari Omari 1 7 Omary Masudi Mwinymbuga 104 8 Bakari Yusuf Upya 134 12 9 Ally Hamisi Hussein 95 144 10 Bakari Zuberi Chondogoro 99 1152 11 Jafari Hassan Mbwela 162 160 + 0.4 acres 12 Hamisi Abdalal Mahege 31 5 13 Mohamed Ramadhani Abdalah 10 10 14 Hamisi Omari Kilongola 141 250 15 Fatuma Mohamed Shombe 55 102 16 Halifa Ibrahim 152 1.25 acres 17 Omari Masudi Mwenyembuga 43 24 18 Abdalah Nassoro Kipazi 50 61 19 Mohamed Hamisi Hussein 53 250 20 Nusura Hamisi Hussein 163 201 21 Isaack Hubert Kilato 26 22 Iddi Hamisi Mgalukaa 5 7 23 Dr. Kunge Mnymura Kunge 30 3 24 Juma Selemani Mtambo 45 48 25 Mohamedi Masudi Selungwi 36 10 26 Ally Sadi Ngebe 47 86 Total No Type of No of Non Perennial Farm Project Affected Person (PAP) Property Area of Rooms Property Trees Trees Area 27 Ibrahim Omari Mkuu 13 236 28 Mohamed Salehe 6 546 29 Mohamed Salehe L 625 30 Zainabu Zitta Semgalawe 29 31 Juma Mohamedi Nyumba 7 45 32 Juma Mohamedi Nyumba 34 17 33 Shabani Saidi Kihambwe 6 8 34 Shemu Simon Malila 136 12 35 Saidi Ramadhani Kigangwa 128 0.25 acres 36 Sulemani Rajabu Goza 22 41 37 Twaha Musa Jafari 16 25 38 Sulemani Rajabu Goza (administrator) 14 33 39 Mwanaharusi Abdala Mshamu 5 21 40 Nassoro 6 41 Zuhura Yamba Juma 174 39 42 Ally Mohamed Limbita 48 28 43 Hamisi Said Ulaya 177 2500 44 Salum Abdalah Awadhi 17 45 Moshi Ally Iddi 155 46 Zahara Rashidi Mtebene 155 0.125 acres 47 Charles Kabaja Semgalawe 4 48 Rashidi Hassan Koyo 222 0.5 acres 49 Hamisi Hussen Hassan 57.76 3 2 98 81 50 Rukia Selemani Goza 32.24 3 2 48 784 51 Hamisi Mohamed Lusambi 24 2 3 13 20 52 Mwajabu Irenus Mbawala 38.7 4 1 17 1 53 Fatuma Abdalah Mgalusi 24.88 2 1 70 47 87 Total No Type of No of Non Perennial Farm Project Affected Person (PAP) Property Area of Rooms Property Trees Trees Area 54 Jihadhari Halfani Goza 37.98 2 1 23 41 55 Mwajabu Saidi Malage 47.66 5 2 38 144 56 Amina Abdlah Mtanga 49.3 3 3 1 46 57 Abdalah Selemani Mahamdu 45.77 3 2 31 200 58 Pili Swalehe Kilonda 40 3 1 25 163 59 Shomari Seif Kwesa 114.27 10 3 18 120 60 Hassan Musa Mnewani 44 3 1 1 28 61 Ali Selemani Kimbunga 62.9 7 3 18 438 62 Sief Rajabu Kigwanga 50.82 3 3 260 300+0.5 acres 63 Witness David Mjema 36.6 2 1 145 96 + 0.157 acres Key: Property Type 1: Grass thatched mud house with mud floor 2: Mud house with mud floor but roofed with corrugated iron sheets 3: Cement block house with cement floor and roofed with corrugated iron sheets 4: Single or more Storey building but not complete 5: Single or more Storey building Non perennial trees include such plants like cassava and pineapples 88 A2- 3: Compensation Characteristics for the Kisarawe II (Kimbiji) Sub Project Non Property Total No of Type of No of Perennial Farm/Land Project Affected Person (PAP) Area Rooms Property Trees Trees Area 1 Mazomba 0 0 0 9 7,406 2 Hussein Shamte Mbonde 14 0 0 810 3 Juma Kibwana Mazengoi 14 2 1 4 Said Kondo Ngota 0 0 0 10 5,761 5 Jumanne Ramadhnai Waziri 14 3 1 6 M