AR Forest and Communities (P132846) Procurement Plan Country: Argentina Region: LATIN AMERICA AND CARIBBEAN Approval Date: 07-Apr-2015 July 9, 2010 PROCUREMENT Argentina : Forests and Community PLAN General Information Country: Argentina Banks Approval Date of the Original Procurement Plan: 2017-02-11 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-09-18 Project ID: P132846 GPN Date: Project Name: Forests and Community Loan / Credit No: IBRD / 84930 Executing Agency(ies): Ministry of Environment and Sustainable Development WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sustainable Livelihoods AR-NA-193-O-CP / Realización Project Management and Impact de mejoras en las instalaciones Monitoring Request for Pending de una Radio Comunitaria en Forest Monitoring Post Limited - National 4,000.00 0.00 2016-11-01 2016-11-23 2016-12-21 Quotations Implementation Monte Quemado, Pcia. de Skills and Technology Transfer Santiago del Estero Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-192-O-CP / Realización Project Management and Impact de mejoras en las instalaciones Monitoring Request for Pending de una Radio Comunitaria en Forest Monitoring Post Limited - National 4,000.00 0.00 2016-11-01 2016-11-23 2016-12-21 Quotations Implementation Boqueron, Pcia. de Santiago del Skills and Technology Transfer Estero Natural Forest Management and Civil Society AR-NA-212-O-CP / Obras para realización de Techos de Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Limited - National 90,000.00 0.00 2017-05-08 2017-05-17 2017-06-26 Captación de Agua de Lluvia, Quotations Envelope Implementation Pcia. de Salta AR-MADS-16038-CW-RFQ / Obras para la realización de Request for Single Stage - One Pending Techos para la captación de IBRD / 84930 Sustainable Livelihoods Post Limited - National 90,000.00 0.00 2017-06-13 2017-07-17 2017-08-31 Quotations Envelope Implementation agua de lluvia en la provincia de Santiago del Estero AR-MADS-24325-CW-RFQ / Obras para la realización de tres Techos para la captación de Request for Single Stage - One Pending agua de lluvia, en la provincia del IBRD / 84930 Sustainable Livelihoods Post Limited 85,000.00 0.00 2017-08-28 2017-08-28 2017-12-19 Quotations Envelope Implementation Chaco, en el marco de la ejecución de los Planes Integrales Comunitarios. GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sustainable Livelihoods Project Management and Impact AR-NA-23-B-CP / Adquisición Monitoring Request for Pending de Mobiliario para la UEL de Forest Monitoring Post Limited - National 20,000.00 0.00 2016-06-16 2016-07-27 2016-08-29 Quotations Implementation Chaco Skills and Technology Transfer Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-171-B-CP / Adquisición Monitoring de 3 equipos de Airea Request for Pending Forest Monitoring Post Limited - National 1,700.00 0.00 2016-09-01 2016-09-23 2016-10-07 Acondicionados para la UEL de Quotations Implementation Skills and Technology Transfer Pcia. de Chaco Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-24-B-NA / Adquisición Monitoring Request for Pending de Mobiliario para la UEL de Forest Monitoring Post Limited 10,000.00 0.00 Quotations Implementation Salta Skills and Technology Transfer Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-211-B-CP / Adquisición Monitoring de Paneles Solares y Bombas Request for Pending Forest Monitoring Post Limited - National 50,000.00 0.00 2016-10-26 2016-11-15 2016-11-30 para Plan de Corto Plazo Quotations Implementation Skills and Technology Transfer PBNyC., Pcia. de Salta Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-22-B-#TIT_LPN# / Project Management and Impact Adquisición de 6(seis) Vehículos Monitoring Pending 4x4 Pick Up para el Forest Monitoring Post Request for Bids Open - National 255,000.00 0.00 2016-07-25 2016-07-27 2016-08-29 2016-09-07 2016-09-21 2016-11-21 Implementation funcionamiento de las UEL del Skills and Technology Transfer Proyecto Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-202-B-CP / Adquisición Project Management and Impact de 5 Acoplados Cisterna de Monitoring Request for Pending Agua para consumo humano, en Forest Monitoring Post Limited - National 40,000.00 0.00 2016-09-22 2016-10-19 2016-11-23 Quotations Implementation el marco de los Planes Integrales Skills and Technology Transfer Comunitarios (PIC) Natural Forest Management and Civil Society Page 1 Sustainable Livelihoods Project Management and Impact AR-NA-149-B-CP / Adquisición Monitoring Request for Pending de mobiliario para las oficinas de Forest Monitoring Post Limited - National 5,000.00 0.00 2016-08-11 2016-08-23 2016-09-14 Quotations Implementation la UEN del PBNyC Skills and Technology Transfer Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-35-B-#TIT_LPN# / Monitoring Adquisición de Equipamiento Pending Forest Monitoring Post Request for Bids Open - National 140,000.00 0.00 2016-04-28 2016-05-12 2016-05-27 2016-06-15 2016-07-19 2016-09-27 Informático para la UEN y las Implementation Skills and Technology Transfer UEL del Proyecto Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-150-B-CP / Adquisición Monitoring Request for Pending de una Caja Fuerte para la Forest Monitoring Post Limited - National 500.00 0.00 2016-08-22 2016-09-07 2016-09-23 Quotations Implementation Unidad Ejecutora del Proyecto Skills and Technology Transfer Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-12-B-CP / Provisión e Monitoring Instalación de Equipos de Aires Request for Pending Forest Monitoring Post Limited - National 35,200.00 0.00 2016-04-27 2016-06-07 2016-07-07 Acondicionados para la Unidad Quotations Implementation Skills and Technology Transfer Ejecutora Nacional del Proyecto Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-214-B-CP / Adquisición Monitoring Request for Pending de Equipos de Informática para el Forest Monitoring Post Limited - National 10,000.00 0.00 2016-11-07 2016-11-28 2016-12-20 Quotations Implementation PBNyC Skills and Technology Transfer Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-148-B-CP / Adquisición Monitoring de 10 Cubiertas para los Request for Pending Forest Monitoring Post Limited - National 2,300.00 0.00 2016-08-19 2016-08-30 2016-09-05 vehículos afectados a la UEL de Quotations Implementation Skills and Technology Transfer Santiago del Estero Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-25-B-CP / Adquisición Monitoring Request for Pending de Mobiliario para la UEL de Forest Monitoring Post Limited - National 10,000.00 0.00 2016-06-14 2016-07-19 2016-08-30 Quotations Implementation Santiago del Estero Skills and Technology Transfer Natural Forest Management and Civil Society AR-NA-194-B-CP / Adquisición Sustainable Livelihoods de equipamiento informatico para Project Management and Impact las radios comunitarias, Monitoring Request for Pending ubicadas Monte Quemado y Forest Monitoring Post Limited - National 4,000.00 0.00 2016-10-20 2016-11-15 2016-12-09 Quotations Implementation Boqueron, departamento de Skills and Technology Transfer Copo, Pcia. de Santiago del Natural Forest Management and Estero Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-1-B-#TIT_LPN# / Monitoring Adquisición de Tractores y Forest Monitoring Prior Request for Bids Open - National 233,732.00 248,025.44 Signed 2015-06-03 2015-06-25 2015-08-05 2015-09-09 2015-10-23 2016-02-23 Maquinaria Agrícola Skills and Technology Transfer Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-2-B-#TIT_LPN# / Monitoring Adquisición de Casillas Forest Monitoring Prior Request for Bids Open - National 183,100.00 143,612.27 Signed 2015-08-18 2015-09-04 2015-10-26 2015-11-19 2016-03-10 2016-05-16 Rodantes Rurales, Talleres Skills and Technology Transfer Rodantes y Acoplados Cisterna Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-185-B-CP / Adquisición Project Management and Impact de Equipos de Monitoring Request for Pending Telecomunicaciones (software y Forest Monitoring Post Limited - National 15,000.00 0.00 2016-10-17 2016-10-31 2016-11-10 Quotations Implementation hardware) - Sistema de Alerta Skills and Technology Transfer Temprana de deforestación Natural Forest Management and Civil Society AR-SADS-9060-GO-RFQ / Adquisición e Instalación de 2 Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Prior Open - National 1,500.00 0.00 2017-03-19 2017-05-14 2017-06-13 Aires Acondicionados para la Quotations Envelope Implementation UEL de Salta AR-SADS-9272-GO-RFQ / Adquisición de 10 cubiertas para Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 2,100.00 0.00 2017-03-26 2017-05-21 2017-06-20 el vehículo oficial de la UEL de Quotations Envelope Implementation Chaco AR-SADS-9277-GO-RFQ / Adquisición de cubiertas para los Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 2,400.00 0.00 2017-03-25 2017-05-20 2017-06-19 vehículos oficiales de la UEL de Quotations Envelope Implementation Salta AR-SADS-9295-GO-RFQ / Request for Single Stage - One Pending Adquisición de insumos de IBRD / 84930 Sustainable Livelihoods Post Open - National 2,000.00 0.00 2017-04-08 2017-06-03 2017-08-02 Quotations Envelope Implementation librería para la UEL de Salta AR-SADS-9299-GO-RFQ / Adquisición de insumos de Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 2,000.00 0.00 2017-04-09 2017-06-04 2017-08-03 librería para la UEL de Santiago Quotations Envelope Implementation del Estero AR-SADS-9301-GO-RFQ / Request for Single Stage - One Pending Adquisición de insumos de IBRD / 84930 Sustainable Livelihoods Post Open - National 2,000.00 0.00 2017-04-15 2017-06-10 2017-08-09 Quotations Envelope Implementation liberia para la UEL de Chaco Page 2 AR-SADS-9304-GO-RFQ / Project Management and Impact Request for Single Stage - One Pending Adquisición de insumos de IBRD / 84930 Post Open - National 5,000.00 0.00 2017-04-15 2017-06-10 2017-08-09 Monitoring Quotations Envelope Implementation librería para la UEN AR-MADS-11175-GO-RFQ / Request for Single Stage - One Pending Adquisicion de GPS portátiles de IBRD / 84930 Sustainable Livelihoods Post Open - National 2,250.00 0.00 2017-04-03 2017-04-20 2017-04-25 Quotations Envelope Implementation mano para las UEL del PBNyC. AR-MADS-14611-GO-RFQ / Adquisición de uniformes y Request for Single Stage - One Pending elementos de trabajo para IBRD / 84930 Forest Monitoring Post Limited 40,000.00 0.00 2017-05-10 2017-06-08 2017-06-19 Quotations Envelope Implementation técnicos de Inventario Forestal en el marco del Componente IV. AR-MADS-14601-GO-RFQ / Adquisición de neumáticos para Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 6,500.00 0.00 2017-05-15 2017-06-01 2017-06-12 los vehículos OKM oficiales de la Quotations Envelope Implementation UEL de Salta AR-MADS-14604-GO-RFQ / Adquisición de neumáticos para Request for Single Stage - One Pending los vehículos oficiales 0km de la IBRD / 84930 Sustainable Livelihoods Post Limited 6,500.00 0.00 2017-05-11 2017-05-26 2017-06-06 Quotations Envelope Implementation UEL de la UEL Santiago del Estero AR-MADS-14605-GO-RFQ / Adquisición de neumáticos para Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Limited 6,500.00 0.00 2017-05-11 2017-05-26 2017-06-09 los vehículos oficiales 0km de la Quotations Envelope Implementation UEL de la UEL Chaco. AR-MADS-14720-GO-RFQ / Adquisición de buzones Natural Forest Management and Request for Single Stage - One Pending impresos para recomendaciones IBRD / 84930 Post Limited 2,000.00 0.00 2017-06-08 2017-07-06 2017-07-31 Civil Society Quotations Envelope Implementation y denuncias de las comunidades de las 3 provincias. AR-NA-203-B-CP / Provisión y colocación de cercos de acero, Request for Single Stage - One Pending en el marco de los Planes IBRD / 84930 Sustainable Livelihoods Post Limited - National 95,000.00 0.00 2017-05-11 2017-05-24 2017-06-07 Quotations Envelope Implementation Integrales Comunitarios (PIC), para la Provincia de Chaco AR-MADS-14595-GO-RFQ / Adquisición de Bombas y Request for Single Stage - One Pending paneles en el marco de los IBRD / 84930 Sustainable Livelihoods Post Open - National 90,000.00 0.00 2017-05-12 2017-06-07 2017-06-21 Quotations Envelope Implementation Planes Integrales Comunitarios (PIC), para la provincia de Salta. AR-MADS-14609-GO-RFQ / Adquisición de bebederos, Request for Single Stage - One Pending corrales, etc en el marco de los IBRD / 84930 Sustainable Livelihoods Post Limited 40,000.00 0.00 2017-10-17 2017-10-30 2017-12-14 Quotations Envelope Implementation Planes Integrales Comunitarios (PIC) AR-MADS-16290-GO-RFQ / Impresión de productos graficos institucionales (banners, lonas, Request for Single Stage - One Pending IBRD / 84930 Skills and Technology Transfer Post Open - National 19,000.00 0.00 2017-06-15 2017-07-09 2017-09-15 etc.) para las Capacitaciones Quotations Envelope Implementation que se efectuen en el marco del PBNyC AR-MADS-16291-GO-RFQ / Adquisicion de cartuchos para Project Management and Impact Request for Single Stage - One Pending IBRD / 84930 Post Open - National 7,000.00 0.00 2017-06-19 2017-07-14 2017-08-28 las impresoras de la UEN, Monitoring Quotations Envelope Implementation PBNyC AR-MADS-16292-GO-RFQ / Adquisicion de cartuchos de Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 2,600.00 0.00 2017-06-07 2017-06-26 2017-07-26 impresoras para la UEL de la Quotations Envelope Implementation Pcia de Chaco AR-NA-218-B-CP / Adquisición de 6 Detectores de Metales en el Request for Single Stage - One Pending IBRD / 84930 Forest Monitoring Post Limited - National 7,500.00 0.00 2017-05-31 2017-07-31 2017-08-23 marco de los Inventarios Quotations Envelope Implementation Forestales AR-NA-205-B-CP / Provisión y colocación de cercos de acero, en el marco de los Planes Request for Single Stage - One IBRD / 84930 Sustainable Livelihoods Post Limited - National 95,000.00 0.00 Canceled 2017-05-08 2017-05-24 2017-06-06 Integrales Comunitarios (PIC), Quotations Envelope para la Provincia de Santaigo del Estero AR-NA-204-B-CP / Provisión y colocación de cercos de acero, Request for Single Stage - One en el marco de los Planes IBRD / 84930 Sustainable Livelihoods Post Limited - National 95,000.00 0.00 Canceled 2017-05-08 2017-05-24 2017-07-01 Quotations Envelope Integrales Comunitarios (PIC), para la Provincia de Salta AR-MADS-16423-GO-RFQ / Adquisición de equipos Project Management and Impact Request for Single Stage - One Pending IBRD / 84930 Post Open - National 5,000.00 0.00 2017-08-08 2017-09-05 2017-11-04 informaticos para la UEN del Monitoring Quotations Envelope Implementation PBNyC AR-NA-195-B-CP / Adquisición de equipamiento tecnico para las radios comunitarias, ubicadas Natural Forest Management and Request for Single Stage - One Pending IBRD / 84930 Post Limited - National 33,000.00 0.00 2017-07-10 2017-09-04 2017-10-30 Monte Quemado y Boqueron, Civil Society Quotations Envelope Implementation departamento de Copo, Pcia. de Santiago del Estero AR-MADS-24335-GO-RFQ / Adquisición de 8 hornos metálicos para carbonización, y capacitaciones en manejo, uso y Request for Single Stage - One Pending mantenimiento de los mismos, IBRD / 84930 Sustainable Livelihoods Post Open - National 40,000.00 0.00 2017-08-23 2017-09-20 2017-12-20 Quotations Envelope Implementation en el marco de la ejecución de los Planes Integrales Comunitarios, provincias de Santiago del Estero y Chaco. Page 3 AR-MADS-24835-GO-RFQ / Provisión de cercos, en el marco Request for Single Stage - One Pending de los Planes Integrales IBRD / 84930 Sustainable Livelihoods Post Open - National 80,000.00 0.00 2017-08-28 2017-10-03 2017-11-17 Quotations Envelope Implementation Comunitarios (PIC), para la Provincia del Santiago del Estero AR-MADS-24317-GO-RFQ / Adquisición de Paneles Solares para generación de electricidad, en el marco de la Ejecución de Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Limited 85,000.00 0.00 2017-08-28 2017-08-28 2017-12-18 los Planes Integrales Quotations Envelope Implementation Comunitarios (PIC´s) para las provincias de Chaco, Salta y Santiago del Estero. AR-MADS-24332-GO-RFQ / Adquisición de cocinas mejoradas para las provincias de Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Limited 40,000.00 0.00 2017-08-28 2017-08-28 2017-12-22 Salta, Chaco y Santiago del Quotations Envelope Implementation Estero, en el marco de los Planes Integrales Comunitarios. AR-MADS-24342-GO-RFQ / Adquisición seis de básculas mecánicas de 1500kg para Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Limited 60,000.00 0.00 2017-08-28 2017-08-28 2017-12-18 pesaje de ganado, con Quotations Envelope Implementation instalación, en el marco de los Planes Integrales Comunitarios. AR-MADS-26514-GO-RFQ / Adquisición de carritos Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 30,000.00 0.00 2017-10-05 2017-10-22 2017-12-06 multiproposito en el marco de los Quotations Envelope Implementation PIC´s AR-MADS-26519-GO-RFQ / Adquisición de sticker/calcos Request for Single Stage - One Pending con logos del MAyDS para ser IBRD / 84930 Sustainable Livelihoods Post Open - National 2,000.00 0.00 2017-09-26 2017-10-12 2017-11-11 Quotations Envelope Implementation colocados en los carritos multipropositos NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sustainable Livelihoods AR-NA-178-S-CP / Realización Project Management and Impact del Taller de Capacitación para Monitoring Request for Pending Asistencia Técnica en Planes Forest Monitoring Post Limited - National 3,500.00 0.00 2016-10-24 2016-11-09 2016-11-18 Quotations Implementation Integrales Comunitarios (Modulo Skills and Technology Transfer 3), Pcia. de Chaco Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-173-S-CP / Realización Project Management and Impact del Taller de Capacitación para Monitoring Request for Pending Asistencia Técnica en Planes Forest Monitoring Post Limited - National 3,000.00 0.00 2016-08-30 2016-09-12 2016-09-16 Quotations Implementation Integrales Comunitarios (Modulo Skills and Technology Transfer 1), Pcia. de Chaco Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-175-S-CP / Realización Project Management and Impact del Taller de Capacitación para Monitoring Request for Pending Asistencia Técnica en Planes Forest Monitoring Post Limited - National 1,500.00 0.00 2016-09-20 2016-09-29 2016-10-07 Quotations Implementation Integrales Comunitarios (Modulo Skills and Technology Transfer 2), Pcia. de Chaco Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-18-S-CD / Instalación de Monitoring parcelas remedibles para el Forest Monitoring Prior Direct Selection 183,000.00 172,437.08 Signed 2016-09-05 2017-09-06 Inventario Forestal de la Provincia Skills and Technology Transfer del Chaco Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-176-S-CP / Realización Project Management and Impact del Taller de Capacitación para Monitoring Request for Pending Asistencia Técnica en Planes Forest Monitoring Post Limited - National 2,000.00 0.00 2016-09-23 2016-10-07 2016-10-14 Quotations Implementation Integrales Comunitarios (Modulo Skills and Technology Transfer 2), Pcia. de Salta Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-179-S-CP / Realización Project Management and Impact del Taller de Capacitación para Monitoring Request for Pending Asistencia Técnica en Planes Forest Monitoring Post Limited - National 4,000.00 0.00 2016-11-08 2016-11-21 2016-11-25 Quotations Implementation Integrales Comunitarios (Modulo Skills and Technology Transfer 3), Pcia. de Salta Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-159-S-CP / Realización Monitoring del taller de consenso y Request for Pending Forest Monitoring Post Limited - National 700.00 0.00 2016-09-06 2016-09-19 2016-09-23 planificación para la estrategia de Quotations Implementation Skills and Technology Transfer implementación de SACVeFor Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-221-S-CP / Reunion de Monitoring la UEN en el marco de la Request for Pending Forest Monitoring Post Limited - National 1,000.00 0.00 2016-11-15 2016-11-24 2016-12-16 evaluación de cierre del 1er. año Quotations Implementation Skills and Technology Transfer de PBNyC Natural Forest Management and Civil Society Page 4 Sustainable Livelihoods Project Management and Impact AR-NA-207-S-CP / Realización Monitoring de varios Spots publicitarios para Request for Pending Forest Monitoring Post Limited - National 30,000.00 0.00 2016-10-25 2016-11-07 2016-12-07 difusión del Proyecto Bosques Quotations Implementation Skills and Technology Transfer Nativos y Comunidad _x000D_ Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-50-S-CP / Readecuación Project Management and Impact de la instalacion electrica de las Monitoring Request for Pending oficinas de la UEN para el Forest Monitoring Post Limited - National 7,000.00 0.00 2016-05-23 2016-06-14 2016-07-18 Quotations Implementation correcto funcionamiento de los Skills and Technology Transfer aires acondicionados Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-182-S-CP / Provisión e Monitoring Impresión de gorras Request for Pending Forest Monitoring Post Limited - National 1,800.00 0.00 2016-09-07 2016-09-23 2016-10-06 institucionales para la UEN y las Quotations Implementation Skills and Technology Transfer UEL PBNyC Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-147-S-CP / Publicación Monitoring Request for Pending de Avisos de Licitación (LPN N° Forest Monitoring Post Limited - National 6,600.00 0.00 2016-08-04 2016-08-11 2016-08-12 Quotations Implementation 01/2016 y LPN N° 02/2016) Skills and Technology Transfer Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-94-S-CP / Impresión de Monitoring Cartillas para Formulación de Request for Pending Forest Monitoring Post Limited - National 6,500.00 0.00 2016-06-10 2016-06-27 2016-07-06 Planes Integrales Comunitarios Quotations Implementation Skills and Technology Transfer (PIC´s) Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-184-S-CP / Impresión de Project Management and Impact Cuadernillos para Monitoring Request for Pending Jornadas/Talleres y Forest Monitoring Post Limited - National 32,000.00 0.00 2016-09-22 2016-10-11 2016-10-18 Quotations Implementation capacitaciones a realizarse en el Skills and Technology Transfer marco del PBNyC Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-142-S-CP / Realización Monitoring de un Documental sobre el Request for Pending Forest Monitoring Post Limited - National 60,000.00 0.00 2016-07-07 2016-08-03 2016-12-21 Registro del avance del Proyecto Quotations Implementation Skills and Technology Transfer PBNyC Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-146-S-CP / Servicio de Monitoring Impresión de Dípticos y Lonas Request for Pending Forest Monitoring Post Limited - National 2,400.00 0.00 2016-08-05 2016-08-16 2016-08-23 Vinílicas Institucionales para la Quotations Implementation Skills and Technology Transfer UEN del PBNyC Natural Forest Management and Civil Society AR-NA-143-S-CP / Sustainable Livelihoods Publicaciones para el pedido de Project Management and Impact Manifestaciones de Interés para Monitoring Request for Pending el 'Proceso Lógico de Forest Monitoring Post Limited - National 18,000.00 0.00 2016-07-26 2016-08-15 2016-08-15 Quotations Implementation Identificación de Necesidades de Skills and Technology Transfer Asistencia Técnica para la Natural Forest Management and Formulación de PIC' Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-180-S-CP / Producción Monitoring de 2(dos) piezas radiales o Request for Pending Forest Monitoring Post Limited - National 6,000.00 0.00 2016-11-07 2016-11-18 2016-12-01 audiovisuales en el marco del Quotations Implementation Skills and Technology Transfer Componente 2 PBNyC Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-155-S-CP / Organización Project Management and Impact para la realización del Curso de Monitoring Capacitación en Sistema de Request for Pending Forest Monitoring Post Limited - National 2,000.00 0.00 2016-10-18 2016-10-31 2016-11-04 Alerta Temprana de Quotations Implementation Skills and Technology Transfer Deforestacion para Agentes Natural Forest Management and Provinciales Civil Society AR-NA-153-S-CP / Organización Sustainable Livelihoods de 6 Talleres (incluye catering y Project Management and Impact materiales didácticos) para Monitoring Request for Pending capacitación de Docentes de Forest Monitoring Post Limited - National 4,700.00 0.00 2016-10-10 2016-10-25 2016-11-16 Quotations Implementation Escuelas Secundarias en Monte Skills and Technology Transfer Quemado, Pcia. de Santiago del Natural Forest Management and Estero Civil Society Sustainable Livelihoods AR-NA-190-S-CP / Realización Project Management and Impact de la Capacitación para Monitoring productores en temas de Request for Pending Forest Monitoring Post Limited - National 10,000.00 0.00 2016-08-31 2016-09-12 2016-09-23 Comunicación, San José de Quotations Implementation Skills and Technology Transfer Boqueron, Pcia. de Santiago del Natural Forest Management and Estero Civil Society AR-NA-152-S-CP / Organización Sustainable Livelihoods de la Capacitación (incluye Project Management and Impact traslado, materiales didácticos y Monitoring Request for Pending catering) en Manejo Forestal y Forest Monitoring Post Limited - National 5,200.00 0.00 2016-09-07 2016-09-21 2016-10-07 Quotations Implementation Legislación Laboral en Monte Skills and Technology Transfer Quemado, Pcia. de Santiago del Natural Forest Management and Estero Civil Society Page 5 AR-NA-151-S-CP / Organización Sustainable Livelihoods de 3 Capacitaciones (incluye Project Management and Impact traslado, materiales didacticos y Monitoring Request for Pending catering) en Legislación Forestal Forest Monitoring Post Limited - National 5,000.00 0.00 2016-08-25 2016-09-07 2016-09-16 Quotations Implementation para Productores, en Monte Skills and Technology Transfer Quemado, Pcia. de Santiago del Natural Forest Management and Estero Civil Society Sustainable Livelihoods AR-NA-172-S-CP / Realización Project Management and Impact del Taller de Capacitación para Monitoring Request for Pending Asistencia Tecnica en Planes Forest Monitoring Post Limited - National 3,000.00 0.00 2016-08-24 2016-09-02 2016-09-06 Quotations Implementation Integrales Comunitarios (Modulo Skills and Technology Transfer 1), Pcia. de Santiago del Estero Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-188-S-CP / Realización Monitoring del Taller de Lideres de Opinión Request for Pending Forest Monitoring Post Limited - National 3,000.00 0.00 2016-11-21 2016-12-05 2016-12-16 Publica en temas forestales - Quotations Implementation Skills and Technology Transfer UEL Santiago del Estero Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-177-S-CP / Realización Project Management and Impact del Taller de Capacitación para Monitoring Request for Pending Asistencia Técnica en Planes Forest Monitoring Post Limited - National 3,500.00 0.00 2016-10-17 2016-10-31 2016-11-04 Quotations Implementation Integrales Comunitarios (Modulo Skills and Technology Transfer 3), Pcia. de Santiago del Estero Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-28-S-CD / Instalación de Monitoring la red de parcelas remedibles Forest Monitoring Prior Direct Selection 196,000.00 186,074.16 Signed 2016-09-28 2017-09-27 para el Inventario Forestal de la Skills and Technology Transfer Provincia de Santiago del Estero Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-156-S-CP / Organización Project Management and Impact para la realización del Curso de Monitoring Capacitación en Sistema de Request for Pending Forest Monitoring Post Limited - National 2,000.00 0.00 2016-11-01 2016-11-11 2016-11-16 Alerta Temprana de Quotations Implementation Skills and Technology Transfer Deforestacion para Agentes Natural Forest Management and Provinciales Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-183-S-CP / Impresión del Monitoring Request for Pending Cuadernillo Protocolo de Forest Monitoring Post Limited - National 32,000.00 0.00 2016-08-23 2016-09-01 2016-09-12 Quotations Implementation participación del PIC Skills and Technology Transfer Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-189-S-CP / Realización Monitoring del Taller de Lideres de Opinión Request for Pending Forest Monitoring Post Limited - National 3,000.00 0.00 2016-08-26 2016-09-12 2016-09-16 Publica en temas forestales - Quotations Implementation Skills and Technology Transfer UEN Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-174-S-CP / Realización Project Management and Impact del Taller de Capacitación para Monitoring Request for Pending Asistencia Técnica en Planes Forest Monitoring Post Limited - National 1,500.00 0.00 2016-09-12 2016-09-26 2016-09-30 Quotations Implementation Integrales Comunitarios (Modulo Skills and Technology Transfer 2), Pcia. de Santiago del Estero Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-220-S-CP / Publicación Project Management and Impact Aviso para la Manifestación de Monitoring Interés para Alquiler de Inmueble Request for Pending Forest Monitoring Post Limited - National 350.00 0.00 2016-10-31 2016-11-04 2016-11-10 para el funcionamiento de la UEL Quotations Implementation Skills and Technology Transfer del PBNyC, de Santiago del Natural Forest Management and Estero Civil Society Sustainable Livelihoods AR-NA-191-S-CP / Realización Project Management and Impact de la Capacitación para Monitoring Request for Pending productores en temas de Forest Monitoring Post Limited - National 10,000.00 0.00 2016-11-24 2016-12-07 2016-12-14 Quotations Implementation Comunicación, Monte Quemado, Skills and Technology Transfer Pcia. de Santiago del Estero Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-217-S-CP / Servicios de Monitoring conectividad y comunicación Request for Pending Forest Monitoring Post Limited - National 15,000.00 0.00 2016-11-03 2016-11-21 2017-04-28 para agencias provinciales, Quotations Implementation Skills and Technology Transfer Santiago del Estero Natural Forest Management and Civil Society AR-SADS-9053-NC-RFB / LPN 01/2017 - Servicio para la Instalación de parcelas remedibles de Inventario en las Single Stage - One Pending IBRD / 84930 Forest Monitoring Post Request for Bids Open - National 677,250.00 0.00 2017-03-10 2017-03-26 2017-05-07 2017-06-06 2017-07-11 2018-08-10 Provincias de: Salta, Jujuy, Envelope Implementation Tucumán, Formosa, Neuquén, Rio Negro, Chubut, Santa Cruz, Tierra del Fuego. AR-SADS-9058-NC-RFQ / Publicación del Aviso para la Request for Single Stage - One Pending Manifestacion de Interés de IBRD / 84930 Forest Monitoring Prior Open - National 15,000.00 0.00 2017-03-19 2017-05-05 2017-06-04 Quotations Envelope Implementation PIC´s en diarios nacionales y diarios locales AR-SADS-9283-NC-RFQ / Contratación del Servicio para la Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 90,000.00 0.00 2017-04-01 2017-05-27 2017-12-23 realización de un registro Quotations Envelope Implementation Audiovisual del Proyecto BNyC Page 6 AR-SADS-9310-NC-RFQ / Contratación del servicio para la Request for Single Stage - One Pending realización de micros radiales IBRD / 84930 Sustainable Livelihoods Post Open - National 5,000.00 0.00 2017-05-20 2017-07-15 2017-10-13 Quotations Envelope Implementation para las emisoras comunitarias de la Pcia. de Salta AR-SADS-9311-NC-RFQ / Contratación del servicio para la Request for Single Stage - One Pending elaboración de micros radiales IBRD / 84930 Sustainable Livelihoods Post Open - National 5,000.00 0.00 2017-05-20 2017-07-15 2017-10-13 Quotations Envelope Implementation para las emisoras de la Pcia. de Chaco AR-SADS-9312-NC-RFQ / Contratación del servicio para la Request for Single Stage - One Pending elaboración de micros radiales IBRD / 84930 Sustainable Livelihoods Post Open - National 5,000.00 0.00 2017-05-20 2017-07-15 2017-10-13 Quotations Envelope Implementation para las emisoras de la Pcia, de Santiago del Estero AR-MADS-11173-NC-RFQ / Request for Single Stage - One Pending Adquisicion de Libros de Acta en IBRD / 84930 Sustainable Livelihoods Post Open - National 5,000.00 0.00 2017-04-03 2017-04-21 2017-04-25 Quotations Envelope Implementation el marco de los PIC´s. AR-MADS-11210-NC-RFQ / Contratación de los servicios de Project Management and Impact Request for Single Stage - One Pending un escribano para el IBRD / 84930 Post Open - National 1,000.00 0.00 2017-04-03 2017-05-11 2017-05-26 Monitoring Quotations Envelope Implementation patentamiento de las 6 Pick Up OKM AR-MADS-11211-NC-RFQ / Servicio para el ploteo de las 6 Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 3,500.00 0.00 2017-04-03 2017-04-27 2017-05-12 Pick Up OKM con el logo del Quotations Envelope Implementation Ministerio de Ambiente AR-MADS-11212-NC-RFQ / Servicios para la instalacion de Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 600.00 0.00 2017-04-03 2017-04-30 2017-05-10 Aires Acondicionados en la UEL Quotations Envelope Implementation de la Provincia de Chaco AR-MADS-12244-NC-RFQ / Servicios para la realización de los Inventario Forestales y Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 25,000.00 0.00 2017-05-06 2017-07-01 2017-12-28 Estudios de Biodiversidad para Quotations Envelope Implementation los 2 PIC desarrollados por la UEL de Salta AR-MADS-12248-NC-RFQ / Publicación del Aviso para la Request for Single Stage - One Pending Manifestación de Interés de IBRD / 84930 Sustainable Livelihoods Post Open - National 23,000.00 0.00 2017-09-18 2017-10-11 2017-10-12 Quotations Envelope Implementation PIC´s en diarios nacionales y diarios locales, 2do. semestre AR-MADS-12251-NC-RFQ / Publicación Aviso para la Manifestación de Interés para el Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 950.00 0.00 2017-04-17 2017-05-25 2017-05-26 Alquiler de un Inmueble para el Quotations Envelope Implementation funcionamiento de la UEL Salta PBNyC AR-MADS-14813-NC-RFQ / Contratacion de los servicios para la realización del Taller de prensa para la difusión y Natural Forest Management and Request for Single Stage - One Pending IBRD / 84930 Post Limited 80,000.00 0.00 2017-07-18 2017-07-30 2017-09-28 concientización de la Ley de Civil Society Quotations Envelope Implementation Bosques, con las Provincias de Salta, Chaco y Santiago del Estero PBNyC AR-MADS-10847-NC-RFQ / Contratación de los servicios para la Realización de las Capacitaciones en: Enfoque de Request for Single Stage - One Pending genero, Panificación de Obras y IBRD / 84930 Skills and Technology Transfer Post Open - National 18,000.00 0.00 2017-05-29 2017-06-22 2017-10-31 Quotations Envelope Implementation Salvaguardas, Comercialización para Planificación de Cuenca, y Comercialización Certicación, Pcia. de Chaco AR-SADS-9056-NC-RFQ / Publicación del Aviso de Request for Single Stage - One Pending IBRD / 84930 Forest Monitoring Post Open - National 20,000.00 0.00 2017-03-15 2017-03-24 2017-03-29 Licitación (LPN 01/2017) Diarios Quotations Envelope Implementation Nacionales y Diarios Locales AR-MADS-16287-NC-RFQ / Contratación de los Servicios para la organización del Taller Request for Single Stage - One Pending IBRD / 84930 Forest Monitoring Post Open - National 20,000.00 0.00 2017-07-10 2017-07-29 2017-08-31 Regional para la difusion y Quotations Envelope Implementation Acuerdos de Implementacion del SACVeFor AR-MADS-16288-NC-RFQ / Contratación de los Servicios para la organización del Taller Request for Single Stage - One Pending IBRD / 84930 Forest Monitoring Post Open - National 20,000.00 0.00 2017-05-29 2017-06-17 2017-06-30 Regional para la difusión y Quotations Envelope Implementation Acuerdos de Implementación del SACVeFor AR-MADS-16289-NC-RFQ / Contratación de los Servicios para la organización del Taller Request for Single Stage - One Pending IBRD / 84930 Forest Monitoring Post Open - National 20,000.00 0.00 2017-05-26 2017-06-13 2017-07-13 Regional para la difusión y Quotations Envelope Implementation Acuerdos de Implementación del SACVeFor AR-MADS-16402-NC-RFQ / Adquisición del catering para la realización de los Talleres con Comunidades (PIC´s), en el Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 21,000.00 0.00 2017-05-31 2017-06-25 2017-09-29 marco del Componente I del Quotations Envelope Implementation Proyecto Bosques Nativos y Comunidad-Provincia de Salta año 2017 Page 7 Sustainable Livelihoods AR-NA-53-S-CP / Encuentro Project Management and Impact sobre conceptos de Economía Monitoring Request for Social, cadenas de Valor, Forest Monitoring Post Limited - National 625.00 0.00 Canceled 2016-08-16 2016-08-30 2016-09-14 Quotations Comercialización, etc. en la Pcia Skills and Technology Transfer de Santiago del Estero Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-56-S-CP / Taller de Monitoring Diagnostico Participativo y Request for Forest Monitoring Post Limited - National 625.00 0.00 Canceled 2016-10-06 2016-10-17 2016-10-31 Estrategia de Comercialización Quotations Skills and Technology Transfer en la Pcia. de Salta Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-59-S-CP / Taller de Monitoring Diagnostico Participativo y Request for Forest Monitoring Post Limited - National 625.00 0.00 Canceled 2016-11-07 2016-11-16 2016-11-30 Estrategia de Comercialización Quotations Skills and Technology Transfer en la Pcia de Salta Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-57-S-CP / Taller de Project Management and Impact Diagnostico Participativo y Monitoring Request for Estrategia de Comercializacion Forest Monitoring Post Limited - National 625.00 0.00 Canceled 2016-11-07 2016-11-16 2016-11-30 Quotations en la Pcia de Santiago del Skills and Technology Transfer Estero Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-55-S-CP / Taller de Monitoring Diagnostico Participativo y Request for Forest Monitoring Post Limited - National 625.00 0.00 Canceled 2016-10-06 2016-10-17 2016-10-31 Estrategia de Comercializacion Quotations Skills and Technology Transfer en la Pcia de Chaco Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-60-S-CP / Taller de Monitoring Diagnostico Participativo y Request for Forest Monitoring Post Limited - National 625.00 0.00 Canceled 2016-12-05 2016-12-12 2016-12-21 Estrategia de Comercialización Quotations Skills and Technology Transfer en la Pcia de Salta Natural Forest Management and Civil Society Sustainable Livelihoods Project Management and Impact AR-NA-61-S-CP / Taller de Monitoring Diagnostico Participativo y Request for Forest Monitoring Post Limited - National 625.00 0.00 Canceled 2016-12-05 2016-12-12 2016-12-21 Estrategia de Comercialización Quotations Skills and Technology Transfer en la Pcia de Chaco Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-62-S-CP / Taller de Project Management and Impact Diagnostico Participativo y Monitoring Request for Estrategia de Comercialización Forest Monitoring Post Limited - National 625.00 0.00 Canceled 2016-12-05 2016-12-12 2016-12-21 Quotations en la Pcia de Santiago del Skills and Technology Transfer Estero Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-52-S-CP / Encuentro Project Management and Impact sobre conceptos de Economía Monitoring Request for Social, cadenas de Valor, Forest Monitoring Post Limited - National 625.00 0.00 Canceled 2016-07-21 2016-08-04 2016-08-18 Quotations Comercialización, etc. en la Pcia Skills and Technology Transfer de Chaco Natural Forest Management and Civil Society Sustainable Livelihoods AR-NA-51-S-CP / Encuentro Project Management and Impact sobre conceptos de Economía Monitoring Request for Social, cadenas de Valor, Forest Monitoring Post Limited - National 625.00 0.00 Canceled 2016-07-12 2016-07-26 2016-07-28 Quotations Comercialización, etc. en la Pcia Skills and Technology Transfer de Salta Natural Forest Management and Civil Society AR-SADS-9309-NC-RFQ / Project Management and Impact Contratación de seguros para Request for Single Stage - One Pending IBRD / 84930 Monitoring Post Open - National 25,000.00 0.00 2017-03-18 2017-05-13 2017-06-12 Pick Up y Bienes de oficina del Quotations Envelope Implementation Sustainable Livelihoods PBNyC AR-MADS-16422-NC-RFQ / Contratación de los servicios para la realización de los Talleres de Capacitación en Request for Single Stage - One Pending Recuperación de practicas IBRD / 84930 Skills and Technology Transfer Post Open - National 30,000.00 0.00 2017-06-06 2017-06-29 2017-12-22 Quotations Envelope Implementation tradicionales en: diagnostico situación Tierras, Carpinteria y Telar, cia. de Santiago del Estero AR-NA-58-S-CP / Contratación de los servicios para la Request for Single Stage - One Pending realización del Taller de IBRD / 84930 Sustainable Livelihoods Post Limited - National 625.00 0.00 2016-11-07 2016-11-16 2016-11-30 Quotations Envelope Implementation Diagnostico Participativo en la Pcia de Santiago del Estero AR-NA-160-S-CP / Contratación de los servicios para la Request for Single Stage - One Pending realización del taller de consenso IBRD / 84930 Forest Monitoring Post Limited - National 700.00 0.00 2016-10-20 2016-11-09 2016-11-09 Quotations Envelope Implementation y planificación para la estrategia de implementación de SACVeFor AR-MADS-10856-NC-RFQ / Contratación de los servicios para la Realización del Taller de Request for Single Stage - One Pending Capacitación de iniciación para IBRD / 84930 Skills and Technology Transfer Post Open - National 500.00 0.00 2017-04-05 2017-05-02 2017-05-12 Quotations Envelope Implementation el uso de GPS y del SIG libre QGIS, en Boquerón, en la Pcia. de Santiago del Estero Page 8 AR-MADS-10851-NC-RFQ / Contratación de los servicios para la Realización de las Capacitaciones en: Enfoque de Genero, Request for Single Stage - One Pending IBRD / 84930 Skills and Technology Transfer Post Open - National 10,000.00 0.00 2017-05-29 2017-06-14 2017-10-30 Planificacion de Obras y Quotations Envelope Implementation Salvaguardas, Comercializacion I Planificacion, Comercializacion II Certificacion, en la Pcia. de Santiago del Estero AR-MADS-11250-NC-RFQ / Contratacion de los servicios para la realizacion de Capacitaciones en: Manejo Forestal para estudiantes, Request for Single Stage - One Pending IBRD / 84930 Skills and Technology Transfer Post Open - National 34,000.00 0.00 2017-05-31 2017-06-19 2017-10-02 Ganaderia Menor, Apicultura Quotations Envelope Implementation Tradicional y Apicultura con Meliponas en el marco de los PIC´s, en la Pcia. de Santiago del Estero AR-MADS-10850-NC-RFQ / Contratación de los servicios para la Realización de las Capacitaciones en: Enfoque de Request for Single Stage - One Pending Genero, Planificacion de Obras y IBRD / 84930 Skills and Technology Transfer Post Open - National 25,000.00 0.00 2017-05-29 2017-06-25 2017-10-31 Quotations Envelope Implementation Salvaguardas, Comercializacion I Planificacion de Cuenca, y Comercialización II Certificacion, en la Pcia. de Salta AR-MADS-11247-NC-RFQ / Contratación de los Servicios para la realización del Taller Request for Single Stage - One Pending Nacional para el intercambio de IBRD / 84930 Skills and Technology Transfer Post Open - National 18,000.00 0.00 2017-10-10 2017-11-11 2017-12-01 Quotations Envelope Implementation Experiencias Piloto de Formulación y Ejecución de PIC´s, UEN y UEL´s AR-MADS-11162-NC-RFQ / Contratación de los servicios para la "Realización de la Project Management and Impact Request for Single Stage - One Pending IBRD / 84930 Post Open - National 7,000.00 0.00 2017-04-02 2017-04-26 2017-04-27 Reunión Plenaria de la UEN y de Monitoring Quotations Envelope Implementation las UEL´s del Proyecto, en la Cuidad de Buenos Aires". AR-MADS-11163-NC-RFQ / Contratación de los servicios Request for Single Stage - One Pending para la "Realización del Taller de IBRD / 84930 Skills and Technology Transfer Post Open - National 1,000.00 0.00 2017-03-29 2017-04-17 2017-04-20 Quotations Envelope Implementation Inventario, Proyecto BNyC, en la Provincia de Salta". AR-MADS-11164-NC-RFQ / Contratación de un "Servicio de Catering para el Taller de Capacitación en Inventario y Request for Single Stage - One Pending IBRD / 84930 Skills and Technology Transfer Post Open - National 1,500.00 0.00 2017-03-29 2017-04-24 2017-04-26 Fichas Familiares para técnicos Quotations Envelope Implementation formuladores del Proyecto BNyC en la Provincia de Santiago del Estero". AR-MADS-11166-NC-RFQ / Contratación de los Servicios Request for Single Stage - One Pending para la realización del Taller del IBRD / 84930 Sustainable Livelihoods Post Open - National 1,000.00 0.00 2017-04-10 2017-05-10 2017-05-15 Quotations Envelope Implementation Consejo Consultivo, en la Provincia del Chaco. AR-MADS-11167-NC-RFQ / Contratación de los servicios Request for Single Stage - One Pending para la realización del Taller del IBRD / 84930 Sustainable Livelihoods Post Open - National 1,000.00 0.00 2017-06-07 2017-07-10 2017-07-17 Quotations Envelope Implementation Consejo Consultivo en la Pcia. De Salta. AR-MADS-11170-NC-RFQ / Servicio de Catering para el Taller de Fortalecimiento de Request for Single Stage - One Pending IBRD / 84930 Sustainable Livelihoods Post Open - National 1,000.00 0.00 2017-04-03 2017-04-24 2017-04-28 Capacidades para el Monitoreo y Quotations Envelope Implementation Seguimiento de los Componentes del PBNyC - UEN AR-NA-145-S-CP / Contratación de los servicios para la realización del Taller destinado a Request for Single Stage - One Pending las Agencias (ADR y ONG´s) de IBRD / 84930 Sustainable Livelihoods Post Limited - National 6,500.00 0.00 2016-08-10 2016-09-11 2016-09-21 Quotations Envelope Implementation Asistencia Técnica para la Formulación de PIC´s (Modulo 1), Pcia. de Salta AR-MADS-11216-NC-RFQ / Contratación de los servicios para la realización de la Request for Single Stage - One Pending IBRD / 84930 Skills and Technology Transfer Post Open - National 20,000.00 0.00 2017-05-29 2017-06-27 2017-07-27 Capacitación en Manejo Forestal Quotations Envelope Implementation Sostenible y Capacitacion en MBGI, UEL Pcia. Salta AR-MADS-11217-NC-RFQ / Contratación de los servicios para la realización de la Request for Single Stage - One Pending Capacitación en Manejo IBRD / 84930 Skills and Technology Transfer Post Open - National 1,500.00 0.00 2017-09-18 2017-10-17 2017-11-16 Quotations Envelope Implementation (ganadería, forestal, y otros) UEL de Santiago del Estero CP Nº 26/2017 AR-MADS-11218-NC-RFQ / Contratación de los Servicios para la realización de la Request for Single Stage - One Pending IBRD / 84930 Skills and Technology Transfer Post Open - National 10,000.00 0.00 2017-05-01 2017-06-01 2017-07-01 Capacitación en Manejo Forestal Quotations Envelope Implementation UEL de Chaco CP Nº 27/2017 AR-NA-200-S-CP / Contratación de un servicio para el revelamiento de información Natural Forest Management and Request for Single Stage - One Pending IBRD / 84930 Post Limited - National 39,000.00 0.00 2017-06-13 2017-08-07 2017-11-30 sobre conocimientos del Bosque Civil Society Quotations Envelope Implementation Nativo, en la Pcia. de Santiago del Estero Page 9 AR-NA-199-S-CP / Contratación de un servicio para el Request for Single Stage - One Pending revelamiento de información IBRD / 84930 Sustainable Livelihoods Post Limited - National 45,000.00 0.00 2017-08-28 2017-08-28 2017-11-30 Quotations Envelope Implementation sobre conocimientos del Bosque Nativo, en la Pcia. de Salta AR-NA-198-S-CP / Contratación de un servicio para el Natural Forest Management and Request for Single Stage - One Pending revelamiento de información IBRD / 84930 Post Limited - National 45,000.00 0.00 2017-08-28 2017-08-28 2017-12-19 Civil Society Quotations Envelope Implementation sobre conocimientos del Bosque Nativo, en la Pcia. de Chaco CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-SADS-9292-CS-CQS / Consultant Contratación del Servicio para la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 90,000.00 0.00 2017-04-17 2017-05-08 2017-06-21 2017-07-21 2017-08-25 2018-02-21 realización de la Evaluación de Implementation Selection Impacto del PBNyC AR-NA-186-CF-SCC / Asistencia Técnica para la Consultant Formulación de Planes Integrales Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-12 2017-06-21 2017-07-16 2017-07-23 2017-08-01 2018-01-15 Comunitarios(PIC), Pcia. de Sgo. Implementation Selection del Estero SCC-CF-09 AR-NA-167-CF-SCC / Asistencia Técnica para la Consultant Formulación de Planes Integrales Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2016-08-25 2016-10-17 2016-12-30 Comunitarios(PIC), Pcia. de Sgo. Implementation Selection del Estero SCC-CF-10 AR-NA-169-CF-SCC / Asistencia Técnica para la Consultant Formulación de Planes Integrales Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-14 2017-06-14 2017-07-09 2017-07-19 2017-08-14 2018-02-16 Comunitarios(PIC), Pcia. de Implementation Selection Sago. del Estero SCC-CF-11 AR-NA-168-CF-SCC / Asistencia Técnica para la Consultant Formulación de Planes Integrales Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-12 2017-06-12 2017-07-07 2017-07-17 2017-08-14 2018-03-05 Comunitarios(PIC), Pcia. de Sgo. Implementation Selection del Estero SCC-CF-12 AR-NA-162-CF-SCC / Asistencia Técnica para la Consultant Formulación de Planes Integrales Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-12 2017-06-12 2017-07-07 2017-07-17 2017-08-14 2018-02-26 Comunitarios(PIC), Pcia. de Implementation Selection Chaco SCC-CF-01 AR-NA-161-CF-SCC / Asistencia Técnica para la Consultant Formulación de Planes Integrales Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-12 2017-06-12 2017-07-07 2017-07-17 2017-08-14 2018-02-19 Comunitarios(PIC), Pcia. de Implementation Selection Chaco SCC-CF-02 AR-NA-163-CF-SCC / Asistencia Técnica para la Consultant Formulación de Planes Integrales Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-12 2017-06-12 2017-07-07 2017-07-17 2017-08-07 2018-02-05 Comunitarios(PIC), Pcia. de Implementation Selection Chaco SCC-CF-03 AR-MADS-17796-CS-CQS / Asistencia Tecnica para la Consultant Pending Formulacion de PIC , Pcia. del IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-12 2017-06-15 2017-07-10 2017-07-20 2017-08-10 2018-02-06 Implementation Chaco Selection SCC-CF-04 AR-MADS-17883-CS-CQS / Asistencia Tecnica para la Consultant Pending Formulación del PIC, Pcia. del IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-14 2017-07-09 2017-07-19 2017-08-02 2018-01-29 Implementation Chaco Selection SCC-CF-05 AR-MADS-17884-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. del IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-14 2017-07-09 2017-07-19 2017-08-02 2018-01-29 Implementation Chaco Selection SCC-CF-06 AR-MADS-17885-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. del IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-15 2017-07-10 2017-07-20 2017-08-03 2018-01-30 Implementation Chaco Selection SCC-CF-07 AR-MADS-17887-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. del IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-15 2017-07-10 2017-07-20 2017-08-03 2018-01-30 Implementation Chaco Selection SCC-CF-08 AR-MADS-17888-CS-CQS / Consultant Asistencia Técnica para la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-09-18 2017-09-20 2017-10-15 2017-10-25 2017-11-08 2018-05-07 Formulación del PIC, Pcia. del Implementation Selection Chaco AR-MADS-17889-CS-CQS / Consultant Asistencia Técnica para la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-09-25 2017-09-27 2017-10-21 2017-10-31 2017-11-14 2018-05-13 Formulación del PIC, Pcia. del Implementation Selection Chaco Page 10 AR-MADS-17890-CS-CQS / Consultant Asistencia Técnica para la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-10-02 2017-10-04 2017-10-19 2017-10-29 2017-11-12 2018-05-11 Formulación del PIC, Pcia. del Implementation Selection Chaco AR-MADS-17893-CS-CQS / Consultant Asistencia Técnica para la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-10-02 2017-10-04 2017-10-28 2017-11-07 2017-11-21 2018-05-20 Formulación del PIC, Pcia. del Implementation Selection Chaco AR-MADS-17894-CS-CQS / Consultant Asistencia Técnica para la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-10-02 2017-10-04 2017-10-28 2017-11-07 2017-11-21 2018-05-20 Formulación del PIC, Pcia. del Implementation Selection Chaco AR-MADS-17895-CS-CQS / Consultant Asistencia Técnica para la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-10-02 2017-10-04 2017-10-28 2017-11-07 2017-11-21 2018-05-20 Formulación del PIC, Pcia. del Implementation Selection Chaco AR-MADS-17896-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. de IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-15 2017-06-30 2017-07-10 2017-07-24 2018-01-20 Implementation Santiago del Estero Selection SCC-CF-13 AR-MADS-17897-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. de IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-15 2017-07-09 2017-07-19 2017-08-02 2018-01-29 Implementation Santiago del Estero Selection SCC-CF-14 AR-MADS-17898-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. de IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-15 2017-07-09 2017-07-19 2017-08-02 2018-01-29 Implementation Santiago del Estero Selection SCC-CF-15 AR-MADS-17899-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. de IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-15 2017-07-09 2017-07-19 2017-08-02 2018-01-29 Implementation Santiago del Estero Selection SCC-CF-23 AR-MADS-17900-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. de IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-15 2017-07-09 2017-07-19 2017-08-02 2018-01-29 Implementation Santiago del Estero Selection SCC-CF-24 AR-MADS-17901-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. de IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-15 2017-07-09 2017-07-19 2017-08-02 2018-01-29 Implementation Santiago del Estero Selection SCC-CF-25 AR-MADS-17903-CS-CQS / Consultant Asistencia Técnica para la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-10-09 2017-10-11 2017-11-04 2017-11-14 2017-11-28 2018-05-27 Formulación del PIC, Pcia. de Implementation Selection Santiago del Estero AR-MADS-17905-CS-CQS / Consultant Asistencia Técnica para la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-10-09 2017-10-11 2017-11-04 2017-11-14 2017-11-28 2018-05-27 Formulación del PIC, Pcia. de Implementation Selection Santiago del Estero AR-MADS-17906-CS-CQS / Consultant Asistencia Técnica para la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-10-09 2017-10-11 2017-11-04 2017-11-14 2017-11-28 2018-05-27 Formulación del PIC, Pcia. de Implementation Selection Santiago del Estero AR-MADS-17910-CS-CQS / Consultant Asistencia Técnica para la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-10-16 2017-10-18 2017-11-11 2017-11-21 2017-12-05 2018-06-03 Formulación del PIC, Pcia. de Implementation Selection Santiago del Estero AR-MADS-17911-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. del IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-15 2017-07-09 2017-07-19 2017-08-02 2018-01-29 Implementation Chaco Selection SCC-CF-16 AR-MADS-17912-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. del IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-15 2017-07-09 2017-07-19 2017-08-02 2018-01-29 Implementation Chaco Selection SCC-CF-18 AR-MADS-17913-CS-CQS / Asistencia Técnica para la Consultant Pending Formulación del PIC, Pcia. del IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-06-13 2017-06-15 2017-07-09 2017-07-19 2017-08-02 2018-01-29 Implementation Chaco Selection SCC-CF-19 AR-NA-164-CF-SCC / Asistencia Técnica para la Consultant Formulación de Planes Integrales Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-08-14 2017-08-14 2017-09-08 2017-09-18 2017-10-16 2018-04-16 Comunitarios(PIC), Pcia. de Implementation Selection Salta SCC-CF-20 AR-MADS-17908-CS-CQS / Asistencia Técnica para la Consultant Formulación del PIC, a la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-10-16 2017-10-18 2017-11-11 2017-11-21 2017-12-05 2018-06-03 comunidad Retiro, Buen Lugar Implementation Selection (SE016) de la Provincia de Santiago del Estero - SCC-CF-37 Page 11 AR-MADS-17904-CS-CQS / Asistencia Técnica para la Consultant Formulación del PIC, a la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-10-09 2017-10-11 2017-11-04 2017-11-14 2017-11-28 2018-05-27 comunidad Saladillo (SE015) de Implementation Selection la Provincia de Santiago del Estero - SCC-CF-36 AR-MADS-17909-CS-CQS / Asistencia Técnica para la Consultant Formulación del PIC, a la Pending IBRD / 84930 Sustainable Livelihoods Post Qualification Open - National 30,000.00 0.00 2017-10-16 2017-10-18 2017-11-11 2017-11-21 2017-12-05 2018-06-03 comunidad El Moradito (SE014) Implementation Selection de la Provincia de Santiago del Estero - SCC-CF-35 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sustainable Livelihoods Project Management and Impact Monitoring AR-NA-187-CI-3CV / Experto en Individual Consultant Pending Forest Monitoring Post Limited 5,400.00 0.00 2016-09-01 2016-12-31 Energías Renovables UEN Selection Implementation Skills and Technology Transfer Natural Forest Management and Civil Society AR-NA-201-CI-3CV / Experto en Sustainable Livelihoods cuestiones legales vinculadas al Project Management and Impact Fortalecimiento de Tenencia de Monitoring Individual Consultant Pending la Tierra para Comunidades Forest Monitoring Post Limited 2,000.00 0.00 2016-10-01 2016-12-31 Selection Implementation Indígenas y Campesinas UEL Skills and Technology Transfer Santiago del Estero - Contrato de Natural Forest Management and Obra Civil Society Sustainable Livelihoods AR-NA-196-CI-3CV / Experto en Project Management and Impact cuestiones legales vinculadas al Monitoring Fortalecimiento de Tenencia de Individual Consultant Pending Forest Monitoring Post Limited 6,800.00 0.00 2016-09-01 2016-12-31 la Tierra para Comunidades Selection Implementation Skills and Technology Transfer Indígenas y Campesinas UEN - Natural Forest Management and Contrato de Obra Civil Society Sustainable Livelihoods Project Management and Impact Monitoring AR-NA-197-CI-3CV / Individual Consultant Pending Forest Monitoring Post Limited 1,800.00 0.00 2016-09-01 2016-12-31 Cadete/Asistente para la UEN Selection Implementation Skills and Technology Transfer Natural Forest Management and Civil Society AR-SADS-9293-CS-INDV / Contratación de un consultor individual Contrato de Obra - Individual Consultant Pending IBRD / 84930 Sustainable Livelihoods Post Open 8,000.00 0.00 2017-03-27 2017-05-15 2017-06-05 2017-07-10 2017-10-08 Puesto: Fotógrafo Institucional Selection Implementation para registrar imagenes del PBNyC AR-MADS-16514-CS-NPO / Capacitación en Formación Agroecologica en el Chaco Salteño, en temas de: Pending Producción hortícola, clima, IBRD / 84930 Skills and Technology Transfer Post Direct Selection Direct 11,000.00 0.00 2017-06-08 2017-06-24 2017-07-02 2017-10-30 Implementation suelos, cultivos, abonos verdes, sistemas de riego, semillas, Biodiversidad. Cercos, siembra, vivero, plan productivo AR-MADS-14606-CS-INDV / Consultor para relevamiento de Individual Consultant Pending información de potenciales IBRD / 84930 Sustainable Livelihoods Post Limited 15,000.00 0.00 2017-05-08 2017-05-10 2017-05-15 2017-06-01 2017-08-31 Selection Implementation proveedores de bienes y servicios. AR-MADS-14598-CS-INDV / Asesor para el diseño de Natural Forest Management and Individual Consultant Pending estrategia de comunicación, IBRD / 84930 Post Limited 9,000.00 0.00 2017-05-09 2017-05-14 2017-05-17 2017-06-12 2017-12-09 Civil Society Selection Implementation articulación y fortalecimiento radios comunitarias. AR-MADS-22683-CS-INDV / Individual Consultant Pending Asesor Legal UEL Santiago del IBRD / 84930 Sustainable Livelihoods Post Open 2,500.00 0.00 2017-08-28 2017-08-28 2017-08-28 2017-08-28 2017-12-31 Selection Implementation Estero AR-MADS-24833-CS-INDV / Consultor individual para la realizacion de los Proyectos y Individual Consultant Pending Espacificaciones Tecnicas de IBRD / 84930 Sustainable Livelihoods Post Open 10,000.00 0.00 2017-10-01 2017-10-01 2017-10-01 2017-10-01 2018-03-30 Selection Implementation represas, conexiones de agua, etc. de Agua en el marco de los PIC´s Page 12