PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo – ELECTRICITY ACCESS AND SERVICE EXPANSION (EASE) - P156208 Project Implementation agency: UCM Date of the Procurement Plan: January 2018 Period covered by this Procurement Plan: January 2018 – June 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC Electricity Access & Services Expansion (EASE) PLAN General Information Country: Congo, Democratic Republic of Bank’s Approval Date of the Original Procurement Plan: 2018-03-16 2021-03-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156208 GPN Date: Project Name: DRC Electricity Access & Services Expansion (EASE) Loan / Credit No: IDA / D1770, IDA / V0350, IDA / 60180 UNITE DE COORDINATION ET MANAGEMENT DES PROJETS DU MINISTERE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-UCM-41701-CW-RFB / Network Upgrades and Single Stage - One 14,800,000.0 2018-09- Travaux d'électrification de IDA / D1770 Access Expansion in Selected A priori Appel d'offres Open - International 0.00 Annulé 2018-01-16 2018-04-17 2018-01-21 2018-04-26 2018-02-20 2015-12-22 2018-02-25 2018-03-07 Envelope 0 03 kimbanseke phase 2 (Lot 6B) SNEL Service Areas ZR-UCM-42629-CW-DIR / M03-Réhabilitation des Network Upgrades and Passation de 2018-08- postes Liminga, Lingwala, IDA / D1770 Access Expansion in Selected A posteriori marché de gré à Direct 4,100,000.00 0.00 Annulé 2018-01-16 2018-03-30 2018-01-21 2018-02-25 24 Mitendi, autres travaux dans SNEL Service Areas gré les injecteurs ZR-UCM-42534-CW-RFB / Network Upgrades and Single Stage - One 10,700,000.0 2022-05- Travaux de réhabilitation de la IDA / D1770 Access Expansion in Selected A priori Appel d'offres Open - International 0.00 Annulé 2019-02-05 2019-02-10 2019-03-24 2019-04-23 2019-05-28 Envelope 0 12 centrale de Mobayi-Mbongo SNEL Service Areas ZR-UCM-42665-CW-RFB / Network Upgrades and Electrification des poches Single Stage - One 2021-03- IDA / D1770 Access Expansion in Selected A priori Appel d'offres Open - International 5,910,000.00 0.00 Annulé 2018-01-30 2018-02-04 2018-03-06 2018-03-11 2018-04-06 noires de Mpasa, Kinseso et Envelope 21 SNEL Service Areas Malweka (Lot 7) ZR-UCM-42667-CW-RFB / Travaux de réhabilitation de la Network Upgrades and ligne de transport HT132 kV Single Stage - One 2021-08- IDA / D1770 Access Expansion in Selected A priori Appel d'offres Open - International 9,371,000.00 0.00 Annulé 2018-05-17 2018-05-22 2018-07-03 2018-08-02 2018-09-06 ainsi que la réhabilitation et Envelope 21 SNEL Service Areas l'extension des réseaux de distribution de Gbadolite ZR-UCM-66587-CW-DIR / Network Upgrades and Passation de Lot 6B - Extension du réseau 14,800,000.0 14,778,603. En cours 2020-01- IDA / D1770 Access Expansion in Selected A priori marché de gré à Direct 2018-03-22 2018-10-11 2018-03-27 2019-05-02 2018-05-01 2018-04-23 20/0,4Kv de Kimbanseke 0 72 d'examen 21 SNEL Service Areas gré (Phase 2) ZR-UCM-66603-CW-DIR / Lot 7 - Travaux Network Upgrades and Passation de 4,953,701.9 2019-09- d'électrification des poches IDA / D1770 Access Expansion in Selected A priori marché de gré à Direct 4,950,000.00 Signé 2018-03-22 2018-02-05 2018-03-27 2018-02-15 2018-05-04 2018-06-25 4 26 noires à Malweka, Mpasa & SNEL Service Areas gré Kisenso ZR-UCM-66597-CW-DIR / Network Upgrades and Passation de 9,131,495.2 2019-11- M03 - Travaux aux postes et IDA / D1770 Access Expansion in Selected A priori marché de gré à Direct 9,500,000.00 Signé 2018-03-22 2018-10-11 2018-03-27 2019-05-02 2018-05-01 2018-06-25 9 22 sous-stations SNEL Service Areas gré ZR-UCM-72750-CW-RFB / Travaux d'urgence pour la Network Upgrades and fiabilisation du groupe 2 et Single Stage - One 2019-09- IDA / D1770 Access Expansion in Selected A posteriori Appel d'offres Open - International 1,631,000.00 0.00 Annulé 2018-08-31 2018-09-05 2018-10-20 2018-11-19 2018-12-24 des engins de levage de la Envelope 20 SNEL Service Areas centrale hydroélectrique de Mobayi Mbongo ZR-UCM-76401-CW-RFB / Travaux d'urgence de fiabilisation et remise en Network Upgrades and service du groupe 2 et de Single Stage - One 2019-07- IDA / D1770 Access Expansion in Selected A posteriori Appel d'offres Limited 2,500,000.00 0.00 Annulé 2018-10-10 2018-10-15 2018-11-26 2018-12-26 2019-01-30 réhabilitation des engins de Envelope 29 SNEL Service Areas levage et de manutention de la Centrale Hydroélectrique de Mobayi ZR-UCM-88512-CW-RFB / Travaux de réhabilitation de la ligne de transport HT 132 kV Network Upgrades and Single Stage - One En cours 2019-11- Mobayi - Gbadolite ainsi que IDA / D1770 Access Expansion in Selected A priori Appel d'offres Open - International 9,371,000.00 0.00 2018-11-01 2020-01-16 2018-12-01 2020-03-13 2019-01-30 2019-03-31 2019-05-21 Envelope d'examen 17 la réhabilitation et l'extension SNEL Service Areas des réseaux de distribution de Gbadolite ZR-UCM-88500-CW-RFB / Network Upgrades and Travaux de réhabilitation de la Single Stage - One 10,700,000.0 2020-04- IDA / D1770 Access Expansion in Selected A priori Appel d'offres Open - International 0.00 Annulé 2018-11-01 2018-11-16 2019-01-20 2019-03-21 2019-04-25 centrale de Mobayi-Mbongo Envelope 0 19 SNEL Service Areas et des auxiliaires ZR-UCM-142770-CW-RFB / Électrification des poches noires, assainissement, Network Upgrades and Single Stage - One 19,000,000.0 23,549,688. 2020-08- réhabilitation et mise en IDA / D1770 Access Expansion in Selected A priori Appel d'offres Open - International Signé 2019-11-04 2019-11-22 2019-11-09 2019-12-06 2019-12-21 2020-01-31 2020-01-20 2020-05-26 2020-02-24 2020-08-31 Envelope 0 28 22 conformité des réseaux de SNEL Service Areas distribution d’électricité des directions SNEL DKC & DKO ZR-UCM-142777-CW-RFB / Électrification par MALT des poches noires, assainissement, réhabilitation Network Upgrades and Single Stage - One 5,270,157.0 2021-08- et mise en conformité des IDA / D1770 Access Expansion in Selected A priori Appel d'offres Open - International 8,000,000.00 Signé 2019-11-15 2019-11-28 2019-11-30 2019-12-06 2020-01-29 2020-02-14 2020-02-08 2020-04-09 2020-02-22 2020-08-31 Envelope 2 15 réseaux de distribution SNEL Service Areas d’électricité des directions SNEL de Kinshasa Centre et Kinshasa Ouest ZR-UCM-160825-CW-RFB / Recrutement d'un Private Sector Based Access Single Stage - One En attente 2021-10- entrepreneur pour la IDA / D1770 A posteriori Appel d'offres Open - National 2,615,000.00 0.00 2020-06-29 2020-07-04 2020-08-15 2020-09-14 2020-10-19 Expansion Envelope d'exécution 14 construction du bâtiment pour UCM, ARE & ANSER Page 1 ZR-UCM-84199-CW-RFB / Travaux de construction de Network Upgrades and l'ouvrage de protection de la Single Stage - One 2020-11- IDA / D1770 Access Expansion in Selected A posteriori Appel d'offres Open - International 4,000,000.00 0.00 Annulé 2019-07-15 2019-07-20 2019-08-31 2019-09-30 2019-11-04 berge de l'Ubangi à Mobayi Envelope 03 SNEL Service Areas Mbongo au niveau des village Ziamba et Kumbu ZR-UCM-88614-CW-RFB / Network Upgrades and Travaux de réhabilitation de la Single Stage - One 10,700,000.0 En attente 2022-07- IDA / D1770 Access Expansion in Selected A priori Appel d'offres Open - International 0.00 2021-01-21 2021-02-15 2021-04-16 2021-05-16 2021-07-06 centrale hydroélectrique de Envelope 0 d'exécution 01 SNEL Service Areas Mobayi et des auxiliaires ZR-UCM-42668-CW-RFB / Network Upgrades and Single Stage - One 2018-09- Travaux de réhabilitation du IDA / D1770 Access Expansion in Selected A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 Envelope 08 centre d'appels de SNEL SNEL Service Areas ZR-UCM-88511-CW-RFB / Sélection d'entrepreneurs en charge des Travaux Network Upgrades and d'électrification des poches Single Stage - One 51,460,000.0 2021-03- IDA / D1770 Access Expansion in Selected A priori Appel d'offres Open - International 0.00 Annulé 2019-07-15 2019-11-28 2019-09-13 2019-11-12 2020-01-11 2020-03-26 noires, d'assainissement, de Envelope 0 21 SNEL Service Areas réhabilitation et de mise en conformité du réseau de distribution SNEL DKO & DKC GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCM-41705-GO-DIR / Passation de Sector Development and Acquisition et installation IDA / D1770 A posteriori marché de gré à Direct 60,000.00 31,130.66 Achevé 2016-12-01 2017-04-07 2016-12-06 2017-06-05 2017-01-10 2017-06-05 2017-07-09 2020-06-29 Implementation Support logiciel TOM2PRO gré ZR-UCM-42669-GO-RFQ / Sector Development and Single Stage - One Acquisition matériels IDA / V0350 A posteriori Demande de prix Limited 23,000.00 22,600.00 Achevé 2018-01-13 2017-12-04 2018-02-17 2018-01-19 2018-03-19 2020-06-29 Implementation Support Envelope informatiques pour UCM ZR-UCM-42670-GO-RFQ / Acquisition fournitures de Sector Development and Single Stage - One IDA / V0350 A posteriori Demande de prix Limited 38,000.00 23,339.29 Achevé 2018-02-10 2018-09-11 2018-04-07 2019-05-13 2021-03-22 2020-06-29 bureau, consommables Implementation Support Envelope informatiques et bureautiques ZR-UCM-42671-GO-RFQ / Sector Development and Single Stage - One En attente Complément matériels IDA / D1770 A posteriori Demande de prix Limited 80,000.00 0.00 2018-02-12 2018-04-09 2018-05-09 Implementation Support Envelope d'exécution informatiques pour UCM ZR-UCM-42544-GO-RFB / Sector Development and Single Stage - One Progiciel Intégré SNEL issu du IDA / D1770 A posteriori Appel d'offres Open - International 1,100,000.00 0.00 Annulé 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Implementation Support Envelope PMEDE ZR-UCM-67716-GO-DIR / PRONTO-Installation et mise Passation de en oeuvre de: (i) un cloud Sector Development and IDA / D1770 A posteriori marché de gré à Direct 1,102,756.00 0.00 Annulé 2018-06-22 2018-06-27 2018-08-01 2018-08-31 privé SNEL, (ii) la gestion Implementation Support gré intégrée et (iii) le système d'information clientèle intégré ZR-UCM-42673-GO-DIR / Passation de Network Upgrades and Acquisition de véhicule pour marchés auprès IDA / D1770 Access Expansion in Selected A posteriori Direct 425,000.00 499,177.00 Achevé 2018-10-01 2018-11-05 2018-10-06 2018-11-05 2018-11-10 2018-11-05 2019-05-09 2020-06-29 la mise en œuvre du Projet des agences de SNEL Service Areas (UCM, SNEL) l'ONU ZR-UCM-72755-GO-RFQ / Acquisition de quatre Network Upgrades and véhicules pour l'Unité de Single Stage - One IDA / D1770 Access Expansion in Selected A posteriori Demande de prix Limited 175,000.00 195,020.00 Achevé 2018-06-30 2018-07-03 2018-08-25 2018-09-14 2019-02-21 2020-06-29 coordination et de Envelope SNEL Service Areas Management des Projets du Ministère (UCM) ZR-UCM-76562-GO-DIR / Acquisition et installation de kits (systèmes automatisés) Passation de de collecte des données pour Sector Development and IDA / D1770 A posteriori marché de gré à Direct 480,000.00 348,162.00 Signé 2018-08-31 2019-01-18 2018-09-05 2019-01-21 2018-10-10 2019-05-31 2019-04-08 le monitoring de la qualité de Implementation Support gré la fourniture d'électricité dans le cadre du projet EASE auprès de la firme MCT Télécom SPRL ZR-UCM-142721-GO-RFQ / Acquisition de matériels informatiques pour le Sector Development and Single Stage - One En attente IDA / D1770 A posteriori Demande de prix Limited 20,000.00 0.00 2019-11-20 2020-01-15 2020-07-13 Secrétariat Général du Implementation Support Envelope d'exécution Ministère des Ressources hydrauliques et de l'Electricité ZR-UCM-142748-GO-RFQ / Acquisition de mobilier pour Sector Development and Single Stage - One En attente le Secrétariat Général du IDA / D1770 A posteriori Demande de prix Limited 14,000.00 0.00 2019-11-20 2020-01-15 2020-07-13 Implementation Support Envelope d'exécution ministère des Ressources hydrauliques et de l'Electricité ZR-UCM-142753-GO-RFQ / Acquisition et installation de climatiseurs pour les bureaux Sector Development and Single Stage - One En attente IDA / D1770 A posteriori Demande de prix Limited 10,500.00 0.00 2019-11-20 2020-01-15 2020-07-13 du Secrétariat Général du Implementation Support Envelope d'exécution ministère des Ressources hydrauliques et de l'Electricité ZR-UCM-142778-GO-RFB / Network Upgrades and Fourniture de compteurs à pré- Single Stage - One IDA / D1770 Access Expansion in Selected A priori Appel d'offres Open - International 3,000,000.00 1,475,951.60 Signé 2019-10-31 2019-11-20 2019-11-15 2019-12-06 2020-01-14 2020-01-21 2020-02-13 2020-04-07 2020-03-20 2020-09-25 2021-09-11 paiement pour les réseaux Envelope SNEL Service Areas DKO & DKC ZR-UCM-185985-GO-RFQ / Acquisition de fournitures de bureau, consommables Sector Development and Single Stage - One En attente IDA / D1770 A posteriori Demande de prix Limited 40,000.00 0.00 2020-10-05 2020-11-30 2022-07-18 informatiques et bureautiques Implementation Support Envelope d'exécution d'UCM pour l'année 2021 et 2020 Page 2 ZR-UCM-42630-GO-RFQ / Sector Development and Single Stage - One En attente Acquisition de mobilier pour IDA / D1770 A posteriori Demande de prix Limited 70,000.00 0.00 2018-01-31 2018-03-03 2018-04-02 Implementation Support Envelope d'exécution UCM, ARE et ANSER ZR-UCM-42675-GO-RFB / Logiciel (formation) et Sector Development and Single Stage - One IDA / D1770 A posteriori Appel d'offres Open - National 293,690.00 0.00 Annulé 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 installation des points de Implementation Support Envelope vente pour SNEL (DDK et DC) ZR-UCM-192288-GO-RFQ / Acquisition des matériels Sector Development and Single Stage - One En attente IDA / D1770 A posteriori Demande de prix Limited 55,000.00 0.00 2020-10-03 2020-10-30 2020-11-29 informatiques et bureautiques Implementation Support Envelope d'exécution pour ANSER et ARE ZR-UCM-192298-GO-RFQ / Sector Development and Single Stage - One En attente Acquisition des mobiliers de IDA / D1770 A posteriori Demande de prix Limited 60,000.00 0.00 2020-10-03 2020-10-30 2020-11-29 Implementation Support Envelope d'exécution bureau pour ANSER et ARE NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCM-160814-NC-RFP / Sélection de compagnies de distribution et d'installation Private Sector Based Access Demande de Single Stage - One IDA / 60180 A priori Open - National 3,200,000.00 2,401,440.00 Signé 2020-03-22 2020-06-19 2020-03-27 2020-06-19 2020-05-08 2019-11-19 2020-06-07 2020-08-27 2020-07-12 2020-09-11 2021-01-08 de kits solaires dans le cadre Expansion propositions Envelope de la subvention basée sur les résultats ZR-UCM-185988-NC-DIR / Distribution des systèmes solaires photovoltaïques individuels suivant le Passation de Private Sector Based Access mécanisme de financement IDA / D1770 A posteriori marché de gré à Direct 900,000.00 859,668.00 Signé 2020-09-20 2020-09-25 2020-09-25 2020-10-02 2020-10-30 2021-01-08 2021-04-28 Expansion basé sur les résultats (RBF) gré dans le cadre du fonds d'électrification objet de la composante 2 du projet EASE CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCM-42604-CS-CQS / ONG pour mise en œuvre PAR (i) travaux électrification Sélection fondée réseaux SNEL DKO & DKC (ii) Network Upgrades and sur les En cours travaux électrification IDA / D1770 Access Expansion in Selected A priori Open - National 200,000.00 0.00 2018-02-05 2018-06-11 2018-02-26 2018-10-11 2018-04-11 2018-05-11 2018-06-15 2018-10-13 qualifications des d'exécution Kimbanseke (iii) travaux SNEL Service Areas consultants électrifcationréseaux SNEL Gbadolite et travaux ligne HT 132 kV Mobayi-Gbadolite ZR-UCM-42627-CS-QCBS / Ingénieur conseil pour APD & justification économique et Network Upgrades and Sélection fondée financière, DAO & supervision En cours IDA / D1770 Access Expansion in Selected A priori sur la qualité et le Open - International 1,284,000.00 0.00 2018-01-22 2018-10-11 2018-02-05 2018-03-05 2018-10-15 2018-04-19 2018-11-07 2018-05-19 2019-09-16 2018-06-23 2020-01-14 2018-07-28 2021-07-12 travaux réhabilitation centrale d'exécution SNEL Service Areas coût de Mobayi. APD & justification économique et financière pour l'extension centrale de Mobayi ZR-UCM-41689-CS-CQS / Ingénieur conseil pour (i) contrôle et supervision Sélection fondée Network Upgrades and travaux issus de PMEDE, (ii) sur les IDA / D1770 Access Expansion in Selected A priori Open - International 2,500,000.00 0.00 Annulé 2018-01-16 2018-02-06 2018-03-06 2018-03-20 2018-04-08 2021-03-23 validation études du tracé qualifications des SNEL Service Areas Kimbanseke et (iii) audit consultants technique marchés issus de PMEDE Network Upgrades and ZR-UCM-42626-CS-LCS / Sélection au IDA / D1770 Access Expansion in Selected A posteriori Open - International 313,000.00 0.00 Annulé 2017-01-10 2017-01-24 2017-04-08 2017-06-07 2017-07-07 2017-08-16 2018-01-14 2018-08-22 Auditeur du contrat de service moindre coût SNEL Service Areas ZR-UCM-42543-CS-LCS / ONG pour (i) campagne de Network Upgrades and communication adaptée au Sélection au IDA / D1770 Access Expansion in Selected A posteriori Open - National 100,000.00 0.00 Annulé 2018-02-05 2018-02-26 2018-08-22 2018-04-11 2018-05-09 2018-06-08 2018-07-13 2018-08-17 2018-12-07 genre et (ii) prise en compte moindre coût SNEL Service Areas des aspects sociaux dans les travaux de Kinshasa ZR-UCM-41695-CS-LCS / ONG pour (i) campagne de Network Upgrades and communication adaptée au Sélection au IDA / D1770 Access Expansion in Selected A posteriori Open - National 200,000.00 0.00 Annulé 2018-02-05 2018-02-26 2018-08-22 2018-04-11 2018-05-09 2018-06-08 2018-07-13 2018-08-17 2018-12-07 genre et (ii) prise en compte moindre coût SNEL Service Areas des aspects sociaux dans les travaux de Gbadolite & Mobayi ZR-UCM-42621-CS-QCBS / Sélection fondée Recrutement consultant Private Sector Based Access IDA / D1770 A priori sur la qualité et le Open - International 500,000.00 0.00 Annulé 2018-06-19 2018-07-10 2018-08-23 2018-09-20 2018-10-20 2018-11-24 2018-12-29 2021-12-13 vérificateur indépendant Expansion coût (intermédiation financière) ZR-UCM-41665-CS-QCBS / Consultant pour (i) études Sélection fondée architecturales, (ii) élaboration Sector Development and En attente IDA / D1770 A posteriori sur la qualité et le Open - National 360,000.00 0.00 2018-03-20 2018-04-10 2018-05-24 2018-06-21 2018-07-21 2018-08-25 2018-09-29 2020-09-28 DAO (iii) supervision travaux Implementation Support d'exécution coût de rénovation bâtiment UCM, ARE & ANSER ZR-UCM-41654-CS-CQS / Consultant pour les études de Sélection fondée (i) préfaisabilité électrification Sector Development and sur les IDA / D1770 A priori Open - International 900,000.00 0.00 Annulé 2018-02-06 2018-02-27 2018-04-12 2018-05-12 2018-06-16 2018-12-13 12 chefs-lieux de province et Implementation Support qualifications des (ii) faisabilité et Dao pour 2 à consultants 3 chefs-lieux Page 3 ZR-UCM-41727-CS-CQS / Sélection fondée Consultant pour la Sector Development and sur les IDA / D1770 A priori Open - International 700,000.00 0.00 Annulé 2018-03-06 2018-03-27 2018-05-10 2018-06-09 2018-07-14 2018-11-11 préparation du projet de Implementation Support qualifications des financement additionnel à consultants EASE ZR-UCM-41713-CS-CQS / Consultant pour la coordination et la mise en cohérence (i) de l'étude Sélection fondée géospatiale, (ii) de la Sector Development and sur les IDA / D1770 A priori Open - International 700,000.00 0.00 Annulé 2018-03-20 2018-04-10 2018-05-24 2018-06-23 2018-07-28 2018-11-25 préparation projet Implementation Support qualifications des financement additionnel, (iii) consultants préfaisabilité d'électrification (iv) études développement midsize ZR-UCM-42623-CS-CQS / Préparation nouveau projet d'interconnexion (i) APS, (iià Sélection fondée APD, (iii) justification Sector Development and sur les IDA / D1770 A priori Open - International 600,000.00 0.00 Annulé 2018-02-06 2018-02-27 2018-04-12 2018-05-12 2018-06-16 2018-11-11 économique et financière, (iv) Implementation Support qualifications des DAO lignes de transport et consultants réseaux de distribution pour 8 localités en RDC et 9 en RCA ZR-UCM-42659-CS-QBS / Ingénieur conseil pour le contrôle et la surveillance des Network Upgrades and travaux d'électrification des Sélection fondée En cours IDA / D1770 Access Expansion in Selected A priori Open - International 821,000.00 0.00 2018-02-13 2018-12-14 2018-03-06 2019-01-21 2018-04-19 2019-11-04 2018-05-17 2019-12-13 2018-06-16 2020-09-15 2018-07-16 2018-08-20 2021-08-04 poches noires er réhabilitation sur la qualité d'exécution SNEL Service Areas et de conformisation réseaux SNEL Gbadolite ainsi que ligne HT 132 kV Mobayi-Gbadolite ZR-UCM-42818-CS-CQS / Sélection fondée Consultant chargé du Sector Development and sur les IDA / V0350 A posteriori Open - International 27,900.00 29,500.00 Achevé 2017-04-14 2017-04-14 2017-04-28 2019-06-03 2017-05-12 2017-05-23 2017-05-17 2017-06-13 2017-06-13 2017-06-13 2017-08-07 2020-06-29 recrutement du personnel Implementation Support qualifications des d'UCM consultants ZR-UCM-41687-CS-LCS / Audit financier et comptable Sector Development and Sélection au des comptes annuels ainsi IDA / D1770 A posteriori Open - International 100,000.00 38,407.00 Signé 2018-01-08 2017-05-30 2018-01-29 2019-06-01 2018-03-14 2017-12-15 2018-04-11 2018-01-30 2018-05-11 2018-03-06 2018-06-15 2018-04-11 2018-07-20 2018-04-26 2021-07-13 Implementation Support moindre coût que des procédures de passation des marchés ZR-UCM-42589-CS-QCBS / Ingénieur conseil pour le contrôle et la surveillance des Network Upgrades and Sélection fondée travaux d'élecrrification des IDA / D1770 Access Expansion in Selected A priori sur la qualité et le Open - International 3,286,000.00 1,636,139.03 Signé 2018-02-02 2018-10-11 2018-02-23 2018-11-21 2018-04-08 2019-10-21 2018-05-06 2019-11-14 2018-06-05 2020-02-13 2018-07-10 2020-04-15 2018-08-14 2020-05-05 2021-07-29 poches noires, SNEL Service Areas coût assainissement, conformisation réseaux SNEL DKO & DKC ZR-UCM-69858-CS-QCBS / Ingénieur conseil chargé du Network Upgrades and Sélection fondée contrôle et de la surveillance IDA / D1770 Access Expansion in Selected A priori sur la qualité et le Open - International 1,700,000.00 1,236,522.50 Signé 2018-08-09 2018-12-11 2018-08-30 2019-01-21 2018-10-13 2019-10-21 2018-11-10 2019-11-29 2018-12-10 2020-02-05 2019-01-14 2020-06-20 2019-02-18 2020-03-05 2020-07-12 de la phase 2 des travaux SNEL Service Areas coût transférés de PMEDE à EASE ZR-UCM-69859-CS-QCBS / Etudes de: (i) préfaisabilité pour électrification par système solaire de 9 chefs-lieux de Sélection fondée Sector Development and province et 66 autres IDA / D1770 A priori sur la qualité et le Open - International 900,000.00 830,961.08 Signé 2018-08-13 2018-10-11 2018-09-03 2018-11-21 2018-10-17 2019-08-09 2018-11-14 2019-10-07 2018-12-14 2019-11-22 2019-01-18 2019-12-18 2019-02-22 2020-04-06 2019-10-31 Implementation Support agglomérations non coût desservies ou insuffisamment alimentés en électricité (ii) faisabilité, APD et DAO pour 3 chefs-lieux ZR-UCM-42625-CS-CQS / Consultant pour études du plan national géospatiale Sélection fondée d'électrification au moindre Sector Development and sur les IDA / D1770 A priori Open - International 1,500,000.00 0.00 Annulé 2018-02-20 2018-03-06 2018-04-03 2018-05-03 2018-06-07 2018-12-04 coût à l'horizon 2040 assorti Implementation Support qualifications des d'une stratégie de mise en consultants œuvre et de prospectus d'investissement ZR-UCM-69885-CS-QCBS / Consultant pour les études du Plan National Géo-spatial d'électrification au moindre Sélection fondée coût (PNGS) à l'horizon 2040, Sector Development and IDA / D1770 A priori sur la qualité et le Open - International 1,500,000.00 1,210,765.00 En cours d'examen 2018-07-23 2018-09-27 2018-08-13 2018-10-11 2018-09-26 2019-10-03 2018-10-24 2019-11-14 2018-11-23 2020-02-05 2018-12-28 2020-04-14 2019-02-01 2020-04-29 2019-07-31 assorti d'une stratégie de Implementation Support coût mise en oeuvre et de prospectus d'investissement (analyse des réseaux dans les agglomérations) ZR-UCM-72677-CS-QCBS / Consultant pour les études Sélection fondée Sector Development and En attente environnementales et sociales IDA / D1770 A posteriori sur la qualité et le Open - International 250,000.00 0.00 2018-08-15 2018-09-05 2018-10-19 2018-11-16 2018-12-16 2019-01-20 2019-02-24 2019-06-04 Implementation Support d'exécution des travaux de construction coût de digue ZR-UCM-72727-CS-CQS / Sélection fondée Network Upgrades and Consultant pour l'audit sur les IDA / D1770 Access Expansion in Selected A posteriori Open - International 150,000.00 194,585.00 Signé 2018-08-08 2018-09-14 2018-08-24 2019-01-21 2018-10-08 2019-08-30 2018-11-07 2019-10-02 2018-12-12 2019-10-07 2019-02-10 technique marchés des qualifications des SNEL Service Areas travaux transférés de PMEDE consultants ZR-UCM-72749-CS-CQS / Consultant chargé de dresser Sélection fondée Network Upgrades and l'état des lieux du passif sur les IDA / D1770 Access Expansion in Selected A posteriori Open - International 200,000.00 0.00 Annulé 2018-08-06 2018-08-27 2018-10-10 2018-11-09 2018-12-14 2019-06-12 environnemental et social des qualifications des SNEL Service Areas travaux de construction de la consultants centrale de Mobayi Mbongo ZR-UCM-73112-CS-CQS / Consultant pour le Sélection fondée recrutement du personnel Sector Development and sur les IDA / D1770 A posteriori Open - International 50,000.00 0.00 Annulé 2018-09-03 2018-09-24 2018-11-07 2018-12-07 2019-01-11 2019-04-11 additionnel d'UCM en rapport Implementation Support qualifications des avec le Projet d'électrification consultants transfrontalière Page 4 ZR-UCM-84205-CS-QCBS / Ingénieur conseil pour les études des travaux de construction de l'ouvrage de Network Upgrades and Sélection fondée protection des berges de IDA / D1770 Access Expansion in Selected A priori sur la qualité et le Open - International 1,500,000.00 0.00 Annulé 2018-11-05 2018-11-26 2019-01-09 2019-02-06 2019-03-08 2019-04-12 2019-05-17 2020-05-16 l'Ubangi au niveau des villages SNEL Service Areas coût ZIAMBA et KUMBU ainsi que la supervision et surveillance des travaux ZR-UCM-78835-CS-CQS / Consultant (ONG) pour : (i) Sélection fondée campagne de communication Network Upgrades and sur les et de sensibilisation adaptée IDA / D1770 Access Expansion in Selected A posteriori Open - National 200,000.00 247,635.00 Signé 2018-02-05 2018-04-26 2018-02-26 2019-03-05 2018-04-11 2019-03-28 2018-05-11 2019-06-07 2018-06-15 2019-06-19 2018-12-12 2020-06-29 qualifications des au genre, (ii) prise en compte SNEL Service Areas consultants des aspects sociaux dans les travaux de GBADOLITE ZR-UCM-78834-CS-CQS / Consultant (ONG) pour : (i) Sélection fondée campagne de communication Network Upgrades and sur les et de sensibilisation adaptée IDA / D1770 Access Expansion in Selected A posteriori Open - National 100,000.00 289,150.69 Signé 2018-02-05 2018-04-26 2018-02-26 2019-03-04 2018-04-11 2019-03-28 2018-05-11 2019-06-07 2018-06-15 2019-06-19 2018-12-12 2020-06-29 qualifications des au genre, (ii) prise en compte SNEL Service Areas consultants des aspects sociaux dans les travaux de KINSHASA ZR-UCM-72639-CS-QCBS / Consultant pour (i) les études de la digue de protection des berges au large des villages Network Upgrades and Sélection fondée En cours Ziamba et Kumbu (Mobayi IDA / D1770 Access Expansion in Selected A priori sur la qualité et le Open - International 1,600,000.00 0.00 2019-01-10 2019-04-03 2019-01-31 2019-08-13 2019-03-23 2021-02-11 2019-04-20 2019-05-20 2019-07-01 2019-08-05 2021-03-27 d'exécution Mbongo), (ii) élaboration du SNEL Service Areas coût DAO et (iii) surveillance des travaux de construction de la digue de protection ZR-UCM-42601-CS-LCS / EIES , PGES & PAR pour le Sector Development and Sélection au IDA / D1770 A posteriori Open - International 250,000.00 0.00 Annulé 2018-03-13 2018-04-03 2018-05-17 2018-06-14 2018-07-14 2018-08-18 2018-09-22 2019-05-20 nouveau projet Implementation Support moindre coût d'interconnexion ZR-UCM-106938-CS-CQS / Consultant chargé de la mise en oeuvre des PAR pour les Sélection fondée Network Upgrades and travaux:(i) d'électrification des sur les IDA / D1770 Access Expansion in Selected A posteriori Open - National 200,000.00 248,165.00 Signé 2019-03-19 2018-04-18 2019-04-09 2019-05-23 2019-05-28 2019-06-22 2019-06-23 2019-07-27 2019-06-20 2019-11-24 poches noires DKC & DKO, (ii) qualifications des SNEL Service Areas de réhabilitation de la CHE de consultants Mobayi et (iii) d'extension du réseau de Kimbanseke ZR-UCM-122294-CS-CQS / ONG chargée de la mise en Sélection fondée Network Upgrades and œuvre des mesures de sur les En cours IDA / D1770 Access Expansion in Selected A posteriori Open - National 295,000.00 0.00 2019-07-22 2019-11-01 2019-08-12 2020-01-13 2019-09-14 2019-10-14 2019-11-18 2020-05-16 prévention et réponse aux qualifications des d'exécution SNEL Service Areas VBG dans le cadre des consultants activités du projet EASE à Kinshasa ZR-UCM-122295-CS-CQS / Sélection fondée Firme pour l’actualisation des Network Upgrades and sur les En cours cadres environnementaux IDA / D1770 Access Expansion in Selected A posteriori Open - National 250,000.00 0.00 2019-07-23 2019-12-19 2019-08-13 2019-10-03 2019-11-02 2019-12-07 2020-06-04 qualifications des d'exécution CGES, CPR, CPPA du projet SNEL Service Areas consultants EASE ZR-UCM-142799-CS-CQS / ONG chargée de la mise en Sélection fondée Network Upgrades and œuvre des mesures de sur les En cours IDA / D1770 Access Expansion in Selected A posteriori Open - National 350,000.00 0.00 2019-11-15 2019-11-14 2019-12-06 2020-01-13 2020-01-26 2020-02-25 2020-03-31 2020-09-27 prévention et réponse aux qualifications des d'exécution SNEL Service Areas VBG dans le cadre des consultants activités du projet EASE à Gbadolite ZR-UCM-150803-CS-CQS / Consultant (Firme) chargé d'assister UCM dans le contrôle des activités réalisées Sélection fondée par les opérateurs de réseaux Private Sector Based Access sur les En cours et les entreprises IDA / D1770 A posteriori Open - International 300,000.00 0.00 2020-01-31 2020-11-11 2020-02-21 2020-11-26 2020-04-05 2020-05-05 2020-06-09 2020-12-06 Expansion qualifications des d'exécution sélectionnées dans le cadre consultants du fonds d'électrification du Projet EASE pour la distribution et 'installation de kits solaires ZR-UCM-160788-CS-LCS / Recrutement d'un cabinet Sector Development and Sélection au En cours d'audit financier et comptable IDA / D1770 A posteriori Open - National 100,000.00 0.00 2020-03-20 2020-08-27 2020-04-10 2020-09-23 2020-05-24 2020-06-21 2020-07-21 2020-08-25 2020-09-29 2021-03-28 Implementation Support moindre coût d'exécution pour les audits externes annuels du projet ZR-UCM-167931-CS-QCBS / Sélection fondée Recrutement d'un cabinet Sector Development and En cours IDA / D1770 A priori sur la qualité et le Open - International 510,000.00 0.00 2020-04-07 2020-06-19 2020-04-28 2020-06-20 2020-06-11 2020-08-07 2020-07-09 2020-09-24 2020-08-08 2021-02-11 2020-09-12 2020-10-17 2021-10-17 pour l'Etude tarifaire et la Implementation Support d'exécution coût fiscalité du secteur de l'électricité ZR-UCM-154442-CS-CQS / Consultant pour (i) élaboration structure tarifaire Sélection fondée applicable au secteur de Sector Development and sur les l’électricité, (ii) proposition IDA / D1770 A posteriori Open - International 350,000.00 0.00 Annulé 2020-01-18 2020-02-08 2020-03-23 2020-04-22 2020-05-27 2020-11-23 Implementation Support qualifications des régime fiscal et parafiscal consultants incitatif spécifique au secteur (iii) élaboration d’une grille tarifaire propre au cas de la SNEL ZR-UCM-174906-CS-QCBS / Sélection fondée Recrutement d'un cabinet Sector Development and IDA / D1770 A posteriori sur la qualité et le Open - National 80,000.00 0.00 Annulé 2020-05-29 2020-11-17 2020-06-19 2020-08-02 2020-08-30 2020-09-29 2020-11-03 2020-12-08 2021-12-08 pour l'audit interne trimestriel Implementation Support coût du projet ZR-UCM-42661-CS-QCBS / Consultant pour l'étude de préfaisabilité et de faisabilité Sélection fondée Sector Development and de 3 sites hyroélectriques IDA / D1770 A priori sur la qualité et le Open - International 7,700,000.00 0.00 Annulé 2018-02-15 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2020-02-18 Implementation Support parmi les midsizes coût prometteurs identifiés par l'étude géospatiale Page 5 ZR-UCM-72753-CS-QCBS / Consultant pour l'élaboration des études de faisabilité et Sélection fondée élaboration de l'APD et DAO Sector Development and IDA / D1770 A priori sur la qualité et le Open - International 600,000.00 0.00 Annulé 2018-11-18 2018-12-09 2019-01-22 2019-02-19 2019-03-21 2019-04-25 2019-05-30 2019-11-26 pour l'électrification de la ville Implementation Support coût de Mbandaka à partir du réseau de la République du Congo Brazzaville (Imboulou) ZR-UCM-42660-CS-QCBS / Consultant chargé de l'analyse des dossiers techniques Sélection fondée Private Sector Based Access devant bénéficier des lignes IDA / D1770 A priori sur la qualité et le Open - International 500,000.00 0.00 Annulé 2018-06-19 2018-07-10 2018-08-23 2018-09-20 2018-10-20 2018-11-24 2018-12-29 2021-12-13 Expansion de crédit (EDC, ENK & coût VIRUNGA SARL)- Intermédiation financière ZR-UCM-88599-CS-QCBS / Consultant pour: (i) Etudes de faisabilité, (ii) APD, (iii) justification économique et Sélection fondée financière (iv) élaboration Sector Development and IDA / D1770 A priori sur la qualité et le Open - International 1,000,000.00 0.00 Annulé 2019-01-23 2019-02-13 2019-04-05 2019-06-04 2019-07-04 2019-08-08 2019-09-28 2020-09-27 DAO des lignes de transport à Implementation Support coût partir de la CHE de Mobayi et du site de l'ile des éléphants pour électrification 14 centres en RDC ZR-UCM-42887-CS-QCBS / Cabinet pour (i) l'assistance technique en vue de Sélection fondée renforcement des capacités Sector Development and IDA / D1770 A posteriori sur la qualité et le Open - International 194,000.00 0.00 Annulé 2019-02-01 2019-02-22 2019-04-07 2019-05-05 2019-06-04 2019-07-09 2019-08-13 2020-08-12 institutionnelles MERH, ARE, Implementation Support coût ANSER & CSPP, (ii) mise en œuvre plan de formation financé par le projet PAGASE ZR-UCM-69853-CS-QCBS / Etudes de préfaisabilité, faisabilité, APD et DAO pour l'électrification des localités en RDC partant de la CHE Sélection fondée Mobayi, et études de Sector Development and IDA / D1770 A priori sur la qualité et le Open - International 950,000.00 0.00 Annulé 2018-08-20 2018-09-10 2018-10-24 2018-11-21 2018-12-21 2019-01-25 2019-03-01 2019-07-20 planification du Implementation Support coût développement de sites hydroélectriques pour l'électrification des mêmes localités au Nord et Sud Ubangi ZR-UCM-69904-CS-QCBS / Consultant (Firme) chargé d'élaborer les cadres environnementaux et sociaux (cadre de gestion Sélection fondée environnementale, CGES, Sector Development and IDA / D1770 A posteriori sur la qualité et le Open - International 400,000.00 0.00 Annulé 2018-11-01 2018-11-22 2019-01-05 2019-02-02 2019-03-04 2019-04-08 2019-05-13 2019-08-11 cadre de politique de Implementation Support coût réinstallation, CPR, cadre de planification pour les populations autochtones, CPPA) pour les localités en RDC ZR-UCM-69901-CS-CQS / Consultant pour le recrutement du personnel des Sélection fondée unités de gestion de Projet Sector Development and sur les d'électrification IDA / D1770 A posteriori Open - International 200,000.00 0.00 Annulé 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-04-18 Implementation Support qualifications des transfrontalière: UCM, PEAC et consultants Unité de gestion ENERCA (Pour UCM-recrutement en 2 phases) ZR-UCM-69890-CS-QCBS / Consultant pour l'actualisation Sélection fondée des études APD et DAO Sector Development and sur les effectués par le PEAC pour IDA / D1770 A posteriori Open - International 200,000.00 0.00 Annulé 2018-11-30 2018-12-21 2019-02-03 2019-03-05 2019-04-09 2019-10-06 Implementation Support qualifications des l'électrification des localités consultants de Mobayi Banga, Alindao et Kembe en RCA ZR-UCM-88596-CS-CQS / Sélection fondée Consultant firme pour le Network Upgrades and sur les recrutement interne du IDA / D1770 Access Expansion in Selected A posteriori Open - International 100,000.00 0.00 Annulé 2019-01-14 2019-02-04 2019-04-05 2019-05-05 2019-06-09 2019-12-06 qualifications des personnel SNEL aux postes SNEL Service Areas consultants vacants laissés par MHI ZR-UCM-152794-CS-CQS / Consultant chargé de l'analyse Sélection fondée des dossiers techniques Private Sector Based Access sur les IDA / D1770 A posteriori Open - National 150,000.00 0.00 Annulé 2020-03-02 2020-03-23 2020-05-06 2020-06-05 2020-07-10 2020-07-13 devant bénéficier des lignes Expansion qualifications des de crédit (EDC, ENK & consultants VIRUNGA SARL) ZR-UCM-160466-CS-CQS / Sélection d'un cabinet de Sélection fondée vérification indépendante des Private Sector Based Access sur les IDA / D1770 A posteriori Open - International 200,000.00 0.00 Annulé 2020-03-01 2020-03-22 2020-05-05 2020-06-04 2020-07-09 2021-01-05 réalisation des opérateurs Expansion qualifications des réseaux et compagnies consultants solaires ZR-UCM-152815-CS-QCBS / Sélection fondée Sector Development and En attente Etude des axes de IDA / D1770 A priori sur la qualité et le Open - International 700,000.00 0.00 2020-10-01 2020-10-22 2020-12-21 2021-02-19 2021-03-21 2021-04-25 2021-05-30 2022-05-30 Implementation Support d'exécution restructuration de SNEL coût ZR-UCM-80600-CS-CQS / Sélection fondée Consultant chargé de Sector Development and sur les En attente IDA / D1770 A posteriori Open - National 195,000.00 0.00 2021-01-11 2021-02-01 2021-03-17 2021-04-16 2021-05-21 2021-11-17 l'élaboration du plan de Implementation Support qualifications des d'exécution communication d'UCM consultants ZR-UCM-88498-CS-LCS / Sélection des banques Private Sector Based Access Sélection au commerciales pour la gestion IDA / D1770 A priori Open - National 10,000,000.00 0.00 Annulé 2018-11-01 2018-11-22 2019-01-05 2019-02-02 2019-03-04 2019-04-08 2019-05-13 2019-11-09 Expansion moindre coût des fonds destinés à la ligne de crédit Page 6 ZR-UCM-72635-CS-CQS / Sélection fondée Consultant pour l'élaboration Sector Development and IDA / D1770 A posteriori sur la qualité et le Open - International 200,000.00 0.00 Annulé 2018-08-29 2018-09-19 2018-11-02 2018-11-30 2018-12-30 2019-02-03 2019-03-10 2019-07-08 du plan de communication Implementation Support coût d'UCM ZR-UCM-143154-CS-QCBS / Ingénieur conseil pour APD & justification économique et financière, DAO & supervision Network Upgrades and Sélection fondée des travaux de réhabilitation IDA / D1770 Access Expansion in Selected A priori sur la qualité et le Open - International 1,284,000.00 0.00 Annulé 2019-10-28 2019-11-04 2019-11-18 2019-11-07 2020-01-01 2019-11-11 2020-01-29 2018-11-07 2020-02-28 2019-11-13 2020-04-03 2020-05-08 2021-05-08 de la CHE de Mobayi. SNEL Service Areas coût Réalisation APD & justification économique et financière pour l'extension centrale de Mobayi ZR-UCM-69898-CS-QCBS / Sélection fondée Consultant pour la Sector Development and IDA / D1770 A priori sur la qualité et le Open - International 700,000.00 0.00 Annulé 2018-09-18 2018-10-09 2018-11-22 2018-12-20 2019-01-19 2019-02-23 2019-03-30 2019-07-28 préparation du projet de Implementation Support coût financement additionnel à EASE ZR-UCM-69884-CS-QCBS / Consultant pour la coordination et la mise en cohérence de: 1) l'étude géospatiale Sélection fondée 2) la préparation du projet de Sector Development and IDA / D1770 A priori sur la qualité et le Open - International 700,000.00 0.00 Annulé 2018-10-31 2018-11-21 2019-01-04 2019-02-01 2019-03-03 2019-04-07 2019-05-12 2020-05-11 financement additionnel Implementation Support coût 3) l'étude de préfaisabilité de l'électrification par énergie solaire 4) des études de développement des Midsizes ZR-UCM-187598-CS-CQS / Recrutement d'un Consultant Sélection fondée (firme) pour l'élaboration des Network Upgrades and sur les En attente cadres environnementaux IDA / D1770 Access Expansion in Selected A posteriori Open - National 250,000.00 0.00 2020-09-30 2020-10-21 2020-12-11 2021-01-10 2021-02-14 2021-08-13 qualifications des d'exécution CGES, CPR, CPPA du Projet SNEL Service Areas consultants d'Accélération de l'Accès à l'Electricité (nouveau projet) ZR-UCM-192414-CS-QCBS / Network Upgrades and Sélection fondée Consultant chargé de l'analyse En attente IDA / D1770 Access Expansion in Selected A posteriori sur la qualité et le Open - National 180,000.00 0.00 2021-01-25 2021-02-15 2021-03-31 2021-04-28 2021-05-28 2021-07-02 2021-08-06 2022-08-06 des indicateurs de l'objectif de d'exécution SNEL Service Areas coût développement du Projet ZR-UCM-192246-CS-CQS / Sélection fondée Cabinet chargé du Sector Development and sur les En cours IDA / V0350 A posteriori Open - National 45,000.00 0.00 2020-09-21 2020-10-06 2020-10-05 2021-01-19 2020-10-20 2020-10-30 2020-11-09 2021-01-08 recrutement du personnel Implementation Support qualifications des d'exécution complémentaire d'UCM consultants ZR-UCM-192256-CS-QCBS / Consultant firme chargé d'élaborer et mettre en œuvre Sélection fondée Sector Development and En attente une feuille de route visant à IDA / D1770 A priori sur la qualité et le Open - National 800,000.00 0.00 2020-10-19 2020-11-09 2020-12-23 2021-01-20 2021-02-19 2021-03-26 2021-04-30 2022-04-30 Implementation Support d'exécution doter ARE des capacités coût nécessaires pour assumer ses missions ZR-UCM-192257-CS-QCBS / Consultant (firme) en charge de la structuration technique, institutionnelle et financière en vue de la mise en Sélection fondée Sector Development and En attente concession en PPP des projets IDA / D1770 A priori sur la qualité et le Open - International 1,600,000.00 0.00 2020-10-26 2020-11-16 2020-12-30 2021-01-27 2021-02-26 2021-04-02 2021-05-07 2022-05-07 Implementation Support d'exécution d’électrification des coût agglomérations prioritaires retenues dans le Programme d’Investissements Prioritaires (PIP) ZR-UCM-192286-CS-QCBS / Consultant en charge de la structuration technique, Sélection fondée institutionnelle et financière Sector Development and En attente IDA / D1770 A priori sur la qualité et le Open - International 800,000.00 0.00 2020-10-30 2020-11-20 2021-01-03 2021-01-31 2021-03-02 2021-04-06 2021-05-11 2022-05-11 en vue de la mise en Implementation Support d'exécution coût concession en PPP des projets d'électrification des 8 chefs- lieux prioritaires retenus ZR-UCM-160802-CS-CQS / Consultant (Cabinet) pour la Sélection fondée vulgarisation de la loi n° Sector Development and sur les 14/011 du 17 juin 2014 IDA / D1770 A posteriori Open - National 150,000.00 0.00 Annulé 2020-06-29 2020-07-20 2020-09-02 2020-10-02 2020-11-06 2021-05-05 Implementation Support qualifications des relative au secteur de consultants l'électricité en RDC et des mesures d'application ZR-UCM-142660-CS-QCBS / Etude (i) d'une structure tarifaire et de la fiscalité Sélection fondée applicable au secteur de Network Upgrades and sur les l'électricité, (ii) de la IDA / D1770 Access Expansion in Selected A priori Open - International 510,000.00 0.00 Annulé 2019-11-15 2020-02-18 2019-12-06 2020-06-06 2020-01-19 2020-02-18 2020-03-24 2020-09-20 qualifications des structuration de la dette de SNEL Service Areas consultants SNEL vis-à-vis de sa clinetèle privée, (iii) de la restructuration de la SNEL ZR-UCM-219395-CS-QCBS / Consultant (firme) en qualité de gestionnaire de fonds dans Sélection fondée Sector Development and En attente le cadre de la mise en place IDA / D1770 A posteriori sur la qualité et le Open - International 450,000.00 0.00 2021-02-22 2021-03-15 2021-04-28 2021-05-26 2021-06-25 2021-07-30 2021-09-03 2022-09-03 Implementation Support d'exécution du Fonds de soutien à coût l’électrification hors réseau (Fonds Mwinda) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7 ZR-UCM-41709-CS-CDS / APD & DAO pour électrification poches noires, Network Upgrades and Sélection de assainissement, réhabilitation IDA / D1770 Access Expansion in Selected A priori consultants par Direct 563,500.00 488,849.00 Signé 2017-07-07 2018-04-17 2017-07-17 2017-07-20 2017-09-20 2017-10-10 2018-06-17 et conformité réseaux SNEL SNEL Service Areas entente directe DKO &DKC ainsi que Gbadolite et ligne HT 132 kV Gbadolite-Mobayi ZR-UCM-42540-CS-INDV / Etude d'une architecture de Network Upgrades and réseau MALT et triphasé avec IDA / D1770 Access Expansion in Selected A posteriori Individuel Limited 130,000.00 0.00 Annulé 2017-06-26 2017-06-26 2017-07-01 2018-01-17 2018-02-05 2018-04-09 transformateur sur poteau à SNEL Service Areas Kinshasa et Gbadolite ZR-UCM-41691-CS-CDS / Elaboration EIES & PAR pour électrification poches noires, assainissement, réhabilitation Network Upgrades and Sélection de et conformité réseaux SNEL IDA / D1770 Access Expansion in Selected A priori consultants par Direct 200,000.00 573,500.00 Signé 2018-01-08 2018-10-11 2018-01-18 2018-07-07 2018-03-08 2018-02-27 2018-05-24 DKO &DKC. Actualisation SNEL Service Areas entente directe PGES et PAR des travaux d'électrification de Kimbanseke phase 2 (Lot 6B du PMEDE) ZR-UCM-42537-CS-CDS / Elaboration du CPR pour Network Upgrades and Sélection de l'amélioration de l'accès à IDA / V0350 Access Expansion in Selected A posteriori consultants par Direct 37,500.00 37,500.00 Signé 2016-02-24 2016-08-15 2016-04-09 2016-10-16 2016-10-14 2016-10-14 2017-02-28 2020-06-29 l'électricité à travers SNELet SNEL Service Areas entente directe les promoteurs privés ZR-UCM-42539-CS-CDS / Elaboration des cadres de CGES, CPPA pour Network Upgrades and Sélection de l'accroissement et IDA / V0350 Access Expansion in Selected A posteriori consultants par Direct 89,000.00 84,150.00 Signé 2016-02-24 2016-08-09 2016-03-23 2016-10-11 2016-10-14 2016-10-14 2017-02-28 2020-06-29 l'amélioration de l'accès à SNEL Service Areas entente directe l'électricité à travers SNEL & les promoteurs privés ZR-UCM-41723-CS-CDS / Validation TDR et cadres Network Upgrades and Sélection de En cours (CGES, CPR & CPA) par IDA / V0350 Access Expansion in Selected A posteriori consultants par Direct 15,500.00 0.00 2016-08-05 2017-01-02 2017-03-08 2017-03-16 d'exécution l'Agence Congolaise de SNEL Service Areas entente directe l'Environnement (ACE) ZR-UCM-41712-CS-CDS / Network Upgrades and Sélection de En cours Validation TDR et cadres IDA / D1770 Access Expansion in Selected A posteriori consultants par Direct 104,500.00 0.00 2018-01-25 2018-02-04 2018-04-10 2021-03-25 d'exécution (CGES, CPR & CPA) par ACE SNEL Service Areas entente directe ZR-UCM-41725-CS-CDS / Network Upgrades and Sélection de En cours Contrat de service MANITOBA IDA / D1770 Access Expansion in Selected A priori consultants par Direct 4,200,000.00 0.00 2018-01-23 2018-10-11 2018-02-02 2018-02-17 2018-06-27 d'exécution HYDRO INTERNATIONAL SNEL Service Areas entente directe ZR-UCM-42547-CS-INDV / Sector Development and En cours IDA / D1770 A priori Individuel Open 270,000.00 0.00 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-09-29 2018-09-30 Spécialiste en production Implementation Support d'exécution ZR-UCM-42535-CS-INDV / Sector Development and En cours Spécialiste en énergies IDA / D1770 A priori Individuel Open 246,000.00 0.00 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-09-29 2018-09-30 Implementation Support d'exécution renouvelables ZR-UCM-41681-CS-INDV / Sector Development and IDA / D1770 A priori Individuel Open 180,000.00 0.00 Annulé 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-09-29 2018-09-30 Chargée de suivi évaluation Implementation Support ZR-UCM-41683-CS-INDV / Sector Development and En cours Spécialiste en question IDA / D1770 A priori Individuel Open 258,000.00 0.00 2017-02-13 2018-10-11 2017-04-03 2017-04-13 2017-05-02 2018-04-30 Implementation Support d'exécution environnementales ZR-UCM-42546-CS-INDV / Sector Development and En cours Spécialiste en développement IDA / D1770 A priori Individuel Open 276,000.00 0.00 2017-02-13 2018-10-11 2017-04-03 2017-04-24 2017-09-29 2018-12-14 Implementation Support d'exécution sociale ZR-UCM-42541-CS-INDV / Sector Development and En cours Responsable des questions IDA / D1770 A priori Individuel Open 336,000.00 0.00 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-09-29 2018-09-30 Implementation Support d'exécution juridiques et transactionnelles ZR-UCM-41696-CS-INDV / Sector Development and En cours Responsable de la passation IDA / D1770 A priori Individuel Open 258,000.00 0.00 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-09-29 2018-10-17 Implementation Support d'exécution de marchés ZR-UCM-41686-CS-INDV / Sector Development and IDA / D1770 A priori Individuel Open 180,000.00 0.00 Annulé 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-11-09 2018-11-08 Comptable Implementation Support ZR-UCM-42558-CS-INDV / Responsable de la Sector Development and En cours IDA / D1770 A priori Individuel Open 324,000.00 0.00 2018-01-05 2018-10-11 2018-02-23 2018-03-16 2018-03-31 2018-09-30 planification et gestion Implementation Support d'exécution technique ZR-UCM-42562-CS-INDV / Sector Development and En cours Responsable Administratif et IDA / D1770 A priori Individuel Open 258,000.00 0.00 2018-01-05 2018-10-11 2018-02-23 2018-03-16 2018-03-31 2018-09-30 Implementation Support d'exécution Financier ZR-UCM-42533-CS-CDS / Elaboration EIES, PGES & PAR Network Upgrades and Sélection de des travaux de réhabilitation IDA / D1770 Access Expansion in Selected A posteriori consultants par Direct 145,000.00 141,515.00 Signé 2018-01-08 2018-01-08 2018-01-18 2018-08-10 2018-03-08 2018-02-27 2018-05-17 2020-06-29 centrale de Mobayi, ligne HT SNEL Service Areas entente directe 132 kV Mobayi-Gbadolite et réseaux Gbadolite ZR-UCM-42862-CS-INDV / Assistant technique Sector Development and IDA / D1770 A posteriori Individuel Open 196,000.00 155,800.00 Signé 2018-01-10 2017-10-23 2018-02-28 2017-12-12 2018-03-21 2018-01-12 2018-04-25 2018-04-11 2018-12-21 2020-06-29 spécialiste de passation de Implementation Support marchés ZR-UCM-69854-CS-CDS / Ingénieur conseil chargé du contrôle et de la surveillance Network Upgrades and Sélection de de la phase 1 des travaux IDA / D1770 Access Expansion in Selected A priori consultants par Direct 1,068,000.00 1,525,930.00 Signé 2018-08-08 2018-08-29 2018-08-27 2018-09-07 2018-10-31 2018-11-09 2019-10-26 transférés de PMEDE à EASE et SNEL Service Areas entente directe de la validation des études du tracé Kimbanseke Page 8 ZR-UCM-75550-CS-INDV / Consultant individuel chargé de dresser l'état des lieux du Network Upgrades and passif environnemental et IDA / D1770 Access Expansion in Selected A posteriori Individuel Limited 95,000.00 79,300.00 Achevé 2018-08-25 2018-07-07 2018-08-30 2018-08-21 2018-09-09 2018-09-14 2018-10-07 2018-09-18 2018-11-08 2020-06-29 social des travaux de SNEL Service Areas construction de la Centrale hydroélectrique de Mobayi- Mbongo ZR-UCM-76476-CS-INDV / Network Upgrades and Audit environnemental et IDA / D1770 Access Expansion in Selected A posteriori Individuel Limited 190,000.00 145,000.00 Signé 2018-08-01 2018-12-12 2018-08-06 2019-01-22 2018-08-27 2019-05-27 2018-10-01 2019-05-27 2018-11-30 2020-06-29 social des travaux transférés SNEL Service Areas du projet PMEDE à EASE ZR-UCM-41653-CS-CDS / Sélection de Sector Development and Prestataire pour l'entretien IDA / D1770 A posteriori consultants par Direct 12,000.00 0.00 Annulé 2018-10-01 2018-10-11 2018-12-15 2021-11-29 Implementation Support des bureaux entente directe ZR-UCM-78836-CS-INDV / Remplacement du Spécialiste Sector Development and En cours IDA / D1770 A posteriori Individuel Limited 45,000.00 0.00 2018-06-01 2018-06-28 2018-06-06 2018-06-27 2018-08-01 2019-01-28 en questions Implementation Support d'exécution environnementales ZR-UCM-76561-CS-CDS / Institution supérieure technique (Institut Supérieur Sélection de de Techniques Appliquées- Sector Development and En cours IDA / D1770 A posteriori consultants par Direct 350,000.00 0.00 2018-08-31 2019-10-30 2018-09-10 2018-11-14 2020-05-07 ISTA) pour le monitoring de la Implementation Support d'exécution entente directe qualité de la fourniture d'électricité dans les zones d'intervention du projet EASE ZR-UCM-42557-CS-INDV / Sector Development and En cours Auditeur interne (Personnel IDA / D1770 A priori Individuel Open 276,000.00 0.00 2017-06-16 2019-06-18 2017-08-04 2017-08-25 2017-09-29 2018-11-30 Implementation Support d'exécution UCM) ZR-UCM-78824-CS-INDV / Sector Development and Recrutement d'un Spécialiste IDA / D1770 A priori Individuel Open 240,000.00 60,000.00 Signé 2018-10-01 2019-01-23 2018-11-19 2020-03-19 2018-12-10 2020-04-09 2019-01-14 2020-05-15 2020-01-09 Implementation Support en passation des marchés ZR-UCM-88767-CS-CDS / Recrutement du consultant Khaled HAMMOU pour l'étude Network Upgrades and Sélection de d'une architecture de réseau IDA / D1770 Access Expansion in Selected A posteriori consultants par Direct 135,000.00 131,050.00 Signé 2017-06-01 2018-06-25 2017-07-11 2018-02-23 2017-09-14 2018-03-08 2018-03-13 2020-06-29 MALT et triphasé avec SNEL Service Areas entente directe transformateur sur poteau à Kinshasa et Gbadolite ZR-UCM-89499-CS-CDS / Recrutement du consultant Khaled HAMMOU pour la Network Upgrades and Sélection de poursuite et l'achèvement de IDA / D1770 Access Expansion in Selected A posteriori consultants par Direct 70,000.00 49,900.00 Achevé 2018-12-09 2018-12-20 2019-02-17 2019-05-31 2019-04-23 2019-04-27 2019-10-20 2020-06-29 l'étude d'une architecture de SNEL Service Areas entente directe réseau MALT et triphasé avec transformateur sur poteau à Kinshasa et Gbadolite ZR-UCM-89561-CS-INDV / Sector Development and En cours IDA / D1770 A posteriori Individuel Limited 84,000.00 0.00 2019-01-14 2019-01-30 2019-01-29 2019-02-28 2019-04-20 2019-10-17 Recrutement d'un chauffeur Implementation Support d'exécution ZR-UCM-97545-CS-CDS / Sélection de Convention de subvention Private Sector Based Access En cours IDA / D1770 A priori consultants par Direct 14,469,262.00 0.00 2019-01-30 2019-03-07 2019-03-11 2018-06-25 2019-05-15 2019-11-11 d'investissement avec Expansion d'exécution entente directe VIRUNGA SARL ZR-UCM-97558-CS-CDS / Sélection de Private Sector Based Access En cours Convention de subvention IDA / D1770 A priori consultants par Direct 8,256,393.00 0.00 2019-01-30 2019-03-11 2019-05-15 2019-11-11 Expansion d'exécution d'investissement avec EDC entente directe ZR-UCM-97561-CS-CDS / Sélection de Private Sector Based Access Convention de subvention IDA / D1770 A priori consultants par Direct 7,967,008.00 0.00 En cours d'examen 2019-01-30 2019-03-11 2019-05-15 2019-11-11 Expansion avec ENK entente directe ZR-UCM-97562-CS-CDS / Network Upgrades and Sélection de Protocole d'accord de IDA / D1770 Access Expansion in Selected A posteriori consultants par Direct 103,670.00 92,950.00 Signé 2019-01-30 2019-01-29 2019-03-11 2019-02-19 2019-05-15 2019-03-26 2019-11-11 2020-06-29 collaboration entre UCM et SNEL Service Areas entente directe COPIREP ZR-UCM-104712-CS-INDV / Sector Development and En cours IDA / D1770 A posteriori Individuel Limited 84,000.00 0.00 2019-03-20 2019-01-30 2019-04-19 2019-03-21 2019-05-19 2019-07-09 2020-07-03 Deuxième chauffeur pour Implementation Support d'exécution UCM ZR-UCM-111601-CS-INDV / Sector Development and IDA / D1770 A posteriori Individuel Open 180,000.00 28,800.00 Signé 2019-04-23 2017-02-16 2019-06-11 2017-10-26 2019-07-02 2017-10-31 2019-08-06 2017-11-09 2020-02-02 Comptable Implementation Support ZR-UCM-111602-CS-INDV / Sector Development and En cours IDA / D1770 A priori Individuel Open 220,000.00 0.00 2019-04-23 2019-06-18 2019-06-11 2019-07-02 2019-08-06 2020-08-06 Chargé de suivi-évaluation Implementation Support d'exécution ZR-UCM-99465-CS-INDV / Sector Development and Assistant technique du IDA / D1770 A priori Individuel Limited 210,000.00 0.00 Annulé 2019-02-12 2019-06-19 2019-02-22 2019-05-03 2019-03-15 2019-04-19 2022-02-22 Implementation Support Coordonnateur ZR-UCM-88514-CS-INDV / Sector Development and Assistant technique du IDA / D1770 A priori Individuel Open 210,000.00 0.00 Annulé 2018-11-01 2019-02-02 2019-01-06 2019-02-05 2019-03-19 2020-03-13 Implementation Support Coordonnateur ZR-UCM-98164-CS-INDV / Sector Development and Assistant technique du IDA / D1770 A priori Individuel Limited 240,000.00 0.00 Annulé 2019-02-01 2019-03-07 2019-03-08 2019-02-07 2019-04-12 2019-05-17 2022-05-01 Implementation Support Coordonnateur ZR-UCM-122292-CS-INDV / Sector Development and En cours ASSISTANT TECHNIQUE DU IDA / D1770 A priori Individuel Limited 240,000.00 0.00 2019-07-10 2019-08-04 2019-07-15 2019-08-19 2019-08-05 2019-09-26 2019-09-09 2020-03-07 Implementation Support d'exécution COORDONNATEUR ZR-UCM-122296-CS-INDV / Consultant individuel pour la réalisation de l’audit Network Upgrades and environnemental et social de En attente IDA / D1770 Access Expansion in Selected A posteriori Individuel Limited 180,000.00 0.00 2019-07-29 2019-08-03 2019-08-24 2019-09-28 2020-03-26 la deuxième ligne Inga- d'exécution SNEL Service Areas Kinshasa sur le tronçon Kimwenza-poste de Kimbanseke Page 9 ZR-UCM-142694-CS-INDV / Consultant individuel à temps partiel chargé de la Sector Development and En cours géolocalisation des IDA / D1770 A posteriori Individuel Limited 36,000.00 0.00 2019-11-15 2019-11-30 2019-11-20 2019-12-11 2020-01-15 2022-12-30 Implementation Support d'exécution branchements/kits solaires et travaux/équipement du Projet EASE ZR-UCM-142763-CS-INDV / Consultant chargé de la ligne Private Sector Based Access En attente IDA / D1770 A posteriori Individuel Open 75,000.00 0.00 2019-11-15 2020-01-12 2020-02-02 2020-03-08 2022-02-26 de crédit et des subventions Expansion d'exécution réseaux/solaires ZR-UCM-142767-CS-INDV / Cabinet pour la mise à jour du Sector Development and En attente IDA / D1770 A posteriori Individuel Limited 30,000.00 0.00 2019-11-15 2019-11-29 2019-12-20 2020-01-24 2020-07-22 site Internet et la messagerie Implementation Support d'exécution d'UCM ZR-UCM-152802-CS-INDV / Consultant individuel à temps partiel chargé de la Private Sector Based Access En attente géolocalisation des IDA / D1770 A posteriori Individuel Direct 40,000.00 0.00 2020-01-15 2020-01-25 2020-02-15 2020-03-21 2020-11-16 Expansion d'exécution branchements/kits solaires et travaux/équipement du Projet EASE ZR-UCM-152806-CS-CDS / Sélection de Private Sector Based Access Intermédiation financière UCM- IDA / 60180 A priori consultants par Direct 10,000,000.00 10,000,000.00 Signé 2020-03-20 2020-12-01 2020-03-30 2020-03-13 2020-06-03 2020-05-22 2020-07-09 Expansion BCC entente directe ZR-UCM-154949-CS-INDV / Consultant individuel (M. Georges BAKALY) pour la coordination des études Sector Development and En attente IDA / D1770 A posteriori Individuel Direct 50,000.00 0.00 2020-01-22 2020-02-01 2020-02-22 2020-03-28 2020-05-03 visant le renforcement et Implementation Support d'exécution l'amélioration de la gouvernance du secteur de l'électricité ZR-UCM-41684-CS-INDV / Sector Development and IDA / D1770 A priori Individuel Open 552,000.00 0.00 Annulé 2017-02-13 2018-10-11 2017-02-28 2017-03-05 2017-03-11 2018-02-28 Coordonnateur UCM Implementation Support ZR-UCM-174915-CS-CDS / Groupement ARTELIA-SHER Consultant chargé de la revue de l'étude de pré faisabilité Sélection de Sector Development and En attente relative à l'aménagement IDA / D1770 A posteriori consultants par Direct 150,000.00 0.00 2020-05-24 2020-06-03 2020-08-07 2021-02-03 Implementation Support d'exécution hydroélectrique sur la rivière entente directe Ubangi dans le cadre de l'interconnexion électrique entre la RDC et la RCA ZR-UCM-178594-CS-INDV / Sector Development and En attente Renouvellement du contrat du IDA / D1770 A priori Individuel Direct 220,800.00 0.00 2020-06-15 2020-06-25 2020-07-16 2020-08-20 2021-02-16 Implementation Support d'exécution Coordonnateur d'UCM Network Upgrades and Sélection de ZR-UCM-67725-CS-CDS / IDA / D1770 Access Expansion in Selected A posteriori consultants par Direct 313,000.00 0.00 Annulé 2018-06-24 2018-07-04 2018-09-07 2019-03-06 Audit du Contrat de Service SNEL Service Areas entente directe ZR-UCM-143149-CS-CDS / Sélection de Consultant pour le Sector Development and IDA / D1770 A posteriori consultants par Direct 45,000.00 0.00 Annulé 2019-11-15 2019-12-05 2020-02-08 2020-08-06 développement du site Implementation Support entente directe Internet d'ARE ZR-UCM-69902-CS-INDV / Consultant individuel pour l'actualisation des études d'impacts environnementaux Sector Development and IDA / D1770 A priori Individuel Open 200,000.00 0.00 Annulé 2018-08-31 2018-10-19 2018-11-09 2018-12-14 2019-03-14 et sociaux (PGES) et plan Implementation Support d'action de relocalisation des populations pour les réseaux d'électrification en RCA ZR-UCM-142691-CS-INDV / Private Sector Based Access Deuxième Vérificateur des IDA / D1770 A posteriori Individuel Open 48,000.00 0.00 Annulé 2019-11-15 2020-01-03 2020-01-24 2020-02-28 2023-02-12 Expansion systèmes et kits solaires ZR-UCM-142685-CS-INDV / Vérificateur technique des Sector Development and raccordements réalisés par les IDA / D1770 A posteriori Individuel Limited 138,000.00 0.00 Annulé 2019-11-15 2019-11-20 2019-12-11 2020-01-15 2022-12-30 Implementation Support opérateurs privés des mini- réseaux électriques ZR-UCM-104711-CS-CQS / consultant chargé de l'analyse technique des dossiers des opérateurs privés Private Sector Based Access IDA / D1770 A priori Individuel Limited 250,000.00 0.00 Annulé 2019-07-10 2019-07-25 2019-08-29 2019-10-24 2022-10-08 avant octroi de prêts et Expansion subvention sur la ligne de crédit et le fonds d'électrification ZR-UCM-88607-CS-INDV / Consultant individuel chargé de l'analyse technique des dossiers des opérateurs privés Private Sector Based Access IDA / D1770 A priori Individuel Open 1,000,000.00 0.00 Annulé 2019-01-27 2019-04-03 2019-04-24 2019-05-29 2019-11-25 avant octroi de prêts et Expansion subvention sur la ligne de crédit et le fonds d'électrification ZR-UCM-97541-CS-INDV / Vérificateur technique (agent Sector Development and UCM) de la mise en oeuvre IDA / D1770 A priori Individuel Open 216,000.00 0.00 Annulé 2019-01-30 2019-04-10 2019-05-01 2019-06-05 2019-12-02 Implementation Support des activités de la composante 2 du Projet EASE ZR-UCM-142688-CS-INDV / Premier Vérificateur des Private Sector Based Access IDA / D1770 A posteriori Individuel Open 138,000.00 0.00 Annulé 2019-11-15 2020-01-03 2020-01-24 2020-02-28 2023-02-12 systèmes et kits solaires Expansion individuels Page 10 ZR-UCM-88515-CS-INDV / Consultant individuel pour apprécier et examiner (i) la Network Upgrades and pertinence de la poursuite de IDA / D1770 Access Expansion in Selected A priori Individuel Limited 210,000.00 0.00 Annulé 2018-11-01 2018-11-22 2019-01-06 2019-02-21 2019-08-20 la mission d'assistance SNEL Service Areas technique à SNEL ainsi que (ii) les conditions et dispositions y relatives ZR-UCM-186446-CS-INDV / Élaboration du manuel Sector Development and En attente IDA / D1770 A posteriori Individuel Direct 60,000.00 0.00 2020-08-30 2020-09-09 2020-09-30 2020-11-04 2021-05-03 d'exécution et du manuel de Implementation Support d'exécution procédures du projet EASE ZR-UCM-186490-CS-INDV / Consultant staff assumant la Sector Development and En attente IDA / D1770 A posteriori Individuel Direct 138,000.00 0.00 2020-08-24 2020-09-03 2020-09-24 2020-10-29 2021-04-27 fonction de Contrôleur Implementation Support d'exécution financier pour UCM ZR-UCM-142674-CS-CDS / Consultant staff assumant la Sector Development and IDA / D1770 A posteriori Individuel Limited 138,000.00 0.00 Annulé 2019-11-15 2019-11-19 2019-11-20 2019-12-11 2020-01-15 2022-12-30 fonction de Contrôleur Implementation Support financier pour UCM ZR-UCM-104716-CS-CDS / Protocole d'Accord de Network Upgrades and Sélection de collaboration entre UCM et En attente IDA / D1770 Access Expansion in Selected A posteriori consultants par Direct 180,000.00 0.00 2021-01-10 2021-03-11 2021-05-15 2021-11-11 COPIREP pour les prestations d'exécution SNEL Service Areas entente directe de COPIREP dans la nouvelle assistance technique ZR-UCM-145369-CS-CDS / Consultant (Groupement ARTELIA SHER) chargé de la revue de l’étude de pré Sélection de faisabilité relative à Sector Development and IDA / D1770 A posteriori consultants par Direct 200,000.00 0.00 Annulé 2019-11-20 2019-11-30 2020-02-03 2020-08-01 l’aménagement Implementation Support entente directe hydroélectrique sur la rivière Ubangi dans le cadre de l’interconnexion électrique entre la RDC et la RCA ZR-UCM-142676-CS-INDV / Consultant pour (i) la Vulgarisation de la loi n° Sector Development and 14/011 et des mesures IDA / D1770 A posteriori Individuel Limited 160,000.00 0.00 Annulé 2019-11-15 2019-11-20 2019-12-11 2020-01-15 2020-07-13 Implementation Support d'application ainsi que (ii) l'élaboration des procédures et mesures d'application ZR-UCM-142584-CS-INDV / Consultant individuel à temps Sector Development and IDA / D1770 A posteriori Individuel Open 138,000.00 0.00 Annulé 2019-11-15 2020-01-13 2020-02-03 2020-03-09 2023-02-22 partiel assumant la fonction Implementation Support d'auditeur Interne ZR-UCM-186539-CS-INDV / Consultant chargé de l'élaboration des EIES et PAR Sector Development and En attente IDA / D1770 A posteriori Individuel Open 25,000.00 0.00 2021-03-29 2021-05-17 2021-05-22 2021-06-01 2021-07-16 pour les travaux de Implementation Support d'exécution construction du bâtiment UCM, ARE & ANSER ZR-UCM-104709-CS-CDS / consultant individuel chargé d'élaborer le Plan de Réparation des dommages et Network Upgrades and Sélection de de Réinstallation Sociale dans IDA / D1770 Access Expansion in Selected A posteriori consultants par Direct 100,000.00 0.00 Annulé 2019-03-15 2019-04-08 2019-04-24 2019-06-28 2019-12-25 le cadre du règlement du SNEL Service Areas entente directe passif environnemental et social des travaux de construction de la Centrale hydroélectrique de Mobayi ZR-UCM-41693-CS-CDS / Sélection de Elaboration du manuel Sector Development and IDA / D1770 A posteriori consultants par Direct 60,000.00 0.00 Annulé 2017-07-14 2017-06-16 2017-07-23 2017-08-02 2018-03-30 d'exécution du projet et du Implementation Support entente directe manuel de procédures ZR-UCM-192218-CS-INDV / Consultant individuel chargé de l'élaboration des procédures de Gestion de la Sector Development and En cours IDA / D1770 A posteriori Individuel Direct 40,000.00 0.00 2020-09-28 2020-10-05 2020-10-08 2020-10-13 2020-10-23 2020-12-22 Main d’œuvre dans le cadre Implementation Support d'exécution du Projet de Gouvernance et d’Accès à l’Électricité et à l’Eau en RDC (nouveau projet) ZR-UCM-192248-CS-INDV / Sector Development and En cours Responsable de la Gestion IDA / D1770 A posteriori Individuel Open 60,000.00 0.00 2020-09-21 2020-10-27 2020-11-09 2020-11-19 2020-11-25 2021-11-25 Implementation Support d'exécution Technique au sein d'UCM ZR-UCM-192249-CS-INDV / Consultant chargé de la Sector Development and En attente gestion des activités de la IDA / D1770 A posteriori Individuel Open 36,000.00 0.00 2020-09-21 2020-10-24 2020-11-03 2020-11-09 2021-11-09 Implementation Support d'exécution composante 2 du projet EASE à UCM ZR-UCM-192250-CS-INDV / Consultant, spécialiste en Sector Development and En cours IDA / D1770 A posteriori Individuel Open 36,000.00 0.00 2020-09-21 2020-10-27 2020-10-24 2020-11-03 2020-11-09 2021-11-09 développement social au sein Implementation Support d'exécution d'UCM ZR-UCM-192251-CS-INDV / Sector Development and En attente Consultant, assistant en suivi IDA / D1770 A posteriori Individuel Open 12,000.00 0.00 2020-09-21 2020-10-24 2020-10-29 2020-11-04 2021-11-05 Implementation Support d'exécution & évaluation pour UCM ZR-UCM-192252-CS-INDV / Deux (2) Consultants, Sector Development and En cours ingénieur en électricité, IDA / D1770 A posteriori Individuel Open 96,000.00 0.00 2020-09-21 2020-10-27 2020-10-24 2020-11-03 2020-11-09 2021-11-09 Implementation Support d'exécution spécialiste en distribution au sein d'UCM ZR-UCM-192254-CS-INDV / Sector Development and En attente Trois (3) consultants pour IDA / D1770 A posteriori Individuel Limited 150,000.00 0.00 2020-10-19 2020-10-24 2020-11-03 2020-11-18 2021-11-18 Implementation Support d'exécution appuyer ARE Page 11 ZR-UCM-192284-CS-INDV / Consultant individuel chargé Sector Development and En attente IDA / D1770 A posteriori Individuel Open 20,000.00 0.00 2020-09-28 2020-10-31 2020-11-10 2020-11-20 2021-01-19 de la mise en place des sites Implementation Support d'exécution internet de ARE et ANSER ZR-UCM-192302-CS-CDS / Consultant (firme) chargé de la traduction des codes de Network Upgrades and Sélection de bonne conduite et des clauses En attente IDA / D1770 Access Expansion in Selected A posteriori consultants par Direct 40,000.00 0.00 2020-09-28 2020-10-08 2020-11-07 2020-12-22 environnementales et sociales d'exécution SNEL Service Areas entente directe de Français en langues nationales (Lingala, Tshiluba, Swahilite Kokongo) ZR-UCM-193104-CS-INDV / Consultant individuel chargé de l'élaboration du Cadre de Network Upgrades and gestion environnementale et En cours IDA / D1770 Access Expansion in Selected A posteriori Individuel Limited 100,000.00 0.00 2020-09-21 2020-10-05 2020-09-26 2020-11-13 2020-10-06 2020-10-16 2020-12-15 sociale (CGES) du Projet de d'exécution SNEL Service Areas Gouvernance et d’Accès à l’Électricité et à l’Eau en RDC (nouveau projet) ZR-UCM-193108-CS-INDV / Consultant individuel chargé de l'élaboration du cadre de Network Upgrades and politique de réinstallation En cours IDA / D1770 Access Expansion in Selected A posteriori Individuel Limited 50,000.00 0.00 2020-09-14 2020-10-06 2020-09-19 2020-09-29 2020-10-09 2020-12-08 (CPR) du Projet de d'exécution SNEL Service Areas Gouvernance et d’Accès à l’Électricité et à l’Eau en RDC (nouveau projet) ZR-UCM-193114-CS-INDV / Consultant individuel chargé de l'actualisation des EIES et PAR pour la réhabilitation Network Upgrades and et/ou l’extension des parties En cours IDA / D1770 Access Expansion in Selected A posteriori Individuel Limited 180,000.00 0.00 2020-09-21 2021-03-12 2020-09-26 2020-10-06 2020-10-16 2020-12-15 du réseau de Kinshasa dans le d'exécution SNEL Service Areas cadre du Projet de Gouvernance et d’Accès à l’Électricité et à l’Eau en RDC (nouveau projet) ZR-UCM-194171-CS-CDS / Consultant firme chargé des Network Upgrades and Sélection de études de pré-faisabilité pour En attente IDA / D1770 Access Expansion in Selected A posteriori consultants par Direct 300,000.00 0.00 2020-10-26 2020-11-05 2021-01-09 2021-07-08 l'électrification de dix (10) d'exécution SNEL Service Areas entente directe agglomérations autres que les chefs-lieux de province ZR-UCM-211818-CS-INDV / Consultant individuel chargé d’élaborer la stratégie de passation des marchés pour le Sector Development and En cours développement (PPSD en sigle IDA / D1770 A posteriori Individuel Direct 40,000.00 0.00 2021-01-11 2021-02-15 2021-01-23 2021-01-30 2021-02-11 2021-05-12 Implementation Support d'exécution en anglais) dans le cadre de la préparation du Projet de Gouvernance et d’Accès à l’Electricité et à l’Eau ZR-UCM-211819-CS-INDV / Consultant individuel chargé d’assumer la fonction Sector Development and En attente IDA / D1770 A posteriori Individuel Limited 100,000.00 0.00 2021-01-11 2021-01-16 2021-01-26 2021-02-05 2022-10-31 d’ingénieur spécialiste en Implementation Support d'exécution production hydroélectrique du projet EASE au sein d'UCM ZR-UCM-211820-CS-INDV / Consultant individuel chargé Sector Development and En attente d’assumer la fonction de IDA / D1770 A posteriori Individuel Limited 70,000.00 0.00 2021-01-11 2021-01-16 2021-01-26 2021-02-05 2022-10-31 Implementation Support d'exécution Comptable du projet EASE au sein d’UCM ZR-UCM-192255-CS-INDV / Consultant international en Sector Development and En attente charge de l'appui à IDA / D1770 A posteriori Individuel Limited 100,000.00 0.00 2021-02-22 2021-02-27 2021-03-09 2021-03-24 2022-03-24 Implementation Support d'exécution l'opérationnalisation du Fonds Mwinda au sein d'ANSER ZR-UCM-219628-CS-INDV / Consultant national en charge de l’appui à l’opérationnalisation du fonds d’électrification hors réseau, « Sector Development and En attente IDA / D1770 A posteriori Individuel Limited 50,000.00 0.00 2021-02-22 2021-02-27 2021-03-20 2021-04-24 2021-10-21 Fonds MWINDA », au sein des Implementation Support d'exécution structures internes d’ANSER et du développement de partenariats stratégiques avec ANSER Page 12