Page 1 September 23, 1997 His Excellency Jérémie Bonnelame Minister for Foreign Affairs and Economic Planning P.O. Box 656 Mont Fleuri Republic of Seychelles Excellency: Loan No. 3551 SEY (Environment and Transport Project) Amendment to Loan Agreement and Project Agreement We refer to the Loan Agreement (the Agreement), dated January 15, 1993, for the Environment and Transport Project (the Project) between the Republic of Seychelles (the Borrower) and the International Bank for Reconstruction and Development (the Bank) and to the Project Agreement between the Bank and Public Utilities Corporation of even date therewith (the Project Agreement). We also refer to your letter dated January 9, 1997 to the Bank requesting the Bank to agree to finance a water supply scheme in Baie Lazare as an additional component under the Project. We are pleased to confirm, therefore, our consent to amend the Agreement as follows: 1. Schedule 1 is amended to read as set forth in the Attachment to this letter. 2. Paragraph 1. of Part A of the Schedule 2 to the Agreement will be changed to: "1. Praslin Water Supply Phase II and Baie Lazare Water Works construction of two additional intakes near existing intakes at Fonds B’offay and Nouvelle Découverte in Praslin, and, construction of treatment works, including a pumping station, to abstract water from Baie Lazare in Mahé. Furthermore, we confirm our consent to amend Part B of Section I in Schedule 1 to the Project Agreement as follows: "2. Civil works under Part A.1 of the Project, up to an aggregate amount equivalent to $600,000, may be carried out by force account. 3. Civil works under Parts A.1of the Project, up to an aggregate amount equivalent to $500,000, may be carried out by national competitive bidding." Please indicate your agreement with the foregoing amendment by signing and dating the confirmation form on the attached copy of this letter and returning it to us, while keeping the original for your records. This amendment will become effective as of the date of confirmation of this letter. Sincerely, Michael N. Sarris Country Director for the Republic of Seychelles Africa Region Attachments Page 2 AGREED: REPUBLIC OF SEYCHELLES By: Jérémine Bonnelame Authorized Representative Date: October 6, 1997 SCHEDULE 1 Withdrawal of the Proceeds of the Loan 1. The table below sets forth the Categories of items to be financed out of the proceeds of the Loan, the allocation of the amounts of the Loan to each Category and the percentage of expenditures for items so to be financed in each Category: Amount of the Loan Allocated % of (Expressed in Expenditures Category Dollar Equivalent) to be Financed (1) Civil works: 100% of foreign expenditures and (a) under Part A.1 75% of local of the Project 730,000 expenditures (b) under Part C.1 of the Project 2,100,000 (c) under Part C.2 of the Project 30,000 (d) other 420,000 (2) Equipment, materials 100% of foreign and supplies: expenditures and 75% of local (a) under Part A.1 expenditures of the Project 700,000 (b) under Part A.3 of the Project 20,000 (c) under Part C.1 of the Project 30,000 (d) other 130,000 (3) Training 75,000 100% of foreign expenditures and 50% of local expenditures (4) Technical assistance: 50% of local expenditures for services of (a) under Part A.3 consultants of the Project -0- domiciled within the territory of (b) other 40,000 the Borrower and 100% of foreign expenditures for Page 3 services of other consultants (5) Consultants' 50% of local services: expenditures for services of (a) under Part A.3 consultants of the Project -0- domiciled within the territory of (b) other 25,000 the Borrower and 100% of foreign expenditures for services of other consultants (6) Artisan compensation -0- 100% of foreign and reinstallation expenditures and 50% of local expenditures (7) Unallocated 200,000 ________ TOTAL 4,500,000