75481 Attachment: Updated Revised Procurement Plan for Consulting Services for Preparation of Phase 2 (CL-CS-4.3) Express- Basic Cost Duration of Code of Selection WB’s ion of Contract Detailed description of Contract Estimate Contract Comment Contract Method view Interest Award (USD) (month) EOI CL-CS- Surveying, detailed design - cost 199,500 CQS Post 03/2013 6/2013 8 4.3A estimate, preparing bidding document for items: LIA1, LIA2, LIA3, LIA5 and embankment of Kenh Cho Lake – Component 2 CL-CS- Surveying, detailed design - cost 195,000 CQS Post 04/2013 7/2013 8 4.3B estimate, preparing bidding document for items: LIA7, LIA10, LIA12, LIA13, LIA14, social infrastructure works and Ton Duc Thang street – Component 2. CL-CS- Surveying, detailed design - cost 479,000 QCBS Prior 05/2013 05/2014 12 4.3C estimate, preparing bidding document for the remaining items of Component 2 (Phase 2)