Textual Procurement Plan (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2015]: Revision of decentralized PP by provinces, starting from Jan.2016 until now] 2. Date of General Procurement Notice: July 2016 3. Period covered by this procurement plan: The procurement period of project covered the first 12 months from July 2016 to June 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Risk Rating - High Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 3 million All 2. NCB (Goods) Above US$ 1.5 million All above threshold 3. ICB (Works) Above US$ 20 million All 4. NCB (Works) Above US$ 5 million All above threshold 5. Shopping for Works (below US$ None 200,000) 6. Shopping for Goods (below US$ None 100,000) 7. Non-consulting services Above US$ 1.5 million 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan issued by the CPMU for VN-DRaSIP 5. 6. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 02 NCB works packages may be subject to advance procurement 7. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 0 0 No N/A Works the ICB contracts (Works) above US$ 5 million Summary of 0 0 No N/A the ICB (Goods) Summary of 11 No Prior First the NCB NCB (Works) contracts in each of the 11 Phase-1 provinces Summary of 0 0 No N/A the NCB (Goods) Summary of 0 0 No N/A the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 0.5 million QCBS, FBS, LCS packages above US$ 500,000 2. Single Source (Firms) Above US$ 0.5 million SSS 3. Individual Above US$ 200,000 IC 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable]: 06 QCBS packages may be subject to advance procurement and retroactive financing. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 8.000 4 Prior Prior review number of of QCBS contracts that contracts will be let above 0.5 under QCBS million per each Summary of 0.715 3 Post CQS number of contracts that will be let under other methods for firms Summary of 1.732 9 Prior/Po Prior review number of st of IC contracts contracts with above 0.2 Individual million per Consultants each PROCUREMENT Vietnam : Vietnam Dam Rehabilitation and Safety Improvement Project PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2016-11-28 2018-08-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152309 GPN Date: Project Name: Vietnam Dam Rehabilitation and Safety Improvement Project Loan / Credit No: IDA / 57490 Executing Agency(ies):Central Project Management Unit for DRSIP, Quang Ngai Province Project Management Unit for DRSIP, Khanh Hoa Province Project Management Unit for DRSIP, Binh Thuan Province Project Management Unit for DRSIP, Binh Dinh Province Project Management Unit of Construction Investment Works for Agriculture and Rural Development, Da WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1-QN-DL-W1 / The first NCB Works contract for Single Stage - One Dap Lang Reservoir IDA / 57490 Prior Request for Bids Open - National 778,841.23 Signed 2017-01-16 2017-01-23 2017-02-28 2017-04-27 2017-05-18 2018-11-09 Envelope Rehabilitation and Safety Improvement C1-BT-SQ-W-01 / This CW package comprises 03 lots, including: Lot 1: Spillway 2, estimated at USD 3,843,875; Lot 2: Main dam, Under Single Stage - One auxiliary dam, construction IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2017-07-31 2017-08-14 2017-09-25 2017-11-24 2017-12-29 2019-12-29 Envelope road, management house, on estimated at USD 2,937,848; Lot 3: Dan Sach Dam headworks; estimated at USD 986,456. C1-BT-SQ-W-03 / Dan Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Canceled 2017-07-24 2017-08-07 2017-09-18 2017-11-17 2017-12-22 2019-12-22 Sach dam headworks Envelope C1-BD-TB-W1 / Thach Ban Single Stage - One reservoir rehabilitation and IDA / 57490 Prior Request for Bids Open - National 871,955.05 Signed 2017-05-24 2017-06-03 2017-07-18 2017-09-06 2017-10-11 2019-10-01 Envelope safety improvement. C1-LD-DT-W1 / Da Teh Dam Rehabilition and Under Single Stage - One Safety improverment (The IDA / 57490 Prior Request for Bids Open - National 3,027,071.09 Implementati 2017-05-22 2017-06-07 2017-07-16 2017-09-14 2017-10-05 2019-10-05 Envelope first NCB package in Lam on Dong - the first-year province) C1-TQ-NL2-W1 / Ngoi La Single Stage - One 2 reservoir Rehabilitation IDA / 57490 Prior Request for Bids Open - National 1,518,551.66 Signed 2017-03-15 2017-03-28 2017-05-05 2017-06-23 2017-07-14 2019-01-05 Envelope and Safety improvement C1-HB-DT-W1 / Dai Thang Reservoir Rehabilitation and Under Single Stage - One Safety Improvement (This is IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2017-02-13 2017-02-20 2017-03-22 2017-05-04 2017-05-25 2019-05-25 Envelope first NCB of the year-1 on subproject) C1-QB-PV-W1 / Rehabilitation and Safely Single Stage - One Improvement of Phu Vinh IDA / 57490 Prior Request for Bids Open - National 0.00 Canceled 2017-02-05 2017-02-10 2017-03-24 2017-05-03 2017-06-07 2019-05-28 Envelope (This is first NCB of the year-1 subproject) C1-QB-GD1-W1 / Rehabilitation and Safely Improvement of Phu Vinh (Include: Build, insurance Single Stage - One IDA / 57490 Prior Request for Bids Open - National 2,876,323.72 Signed 2017-04-20 2017-05-10 2017-06-21 2017-07-31 2017-09-04 2019-08-25 works and Supply and Envelope installation of SCADA) - This is first NCB of the year-1 subproject Page 1 C1-QB-GD2-W2 / Rehabilitation and Safely Pending Single Stage - One Improvement of Thanh Son IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-08-10 2018-08-25 2018-10-06 2018-11-15 2018-12-20 2020-12-09 Envelope and Vung Mo and Dap on Lang (Phase 2) C1-QB-GD2-W3 / Pending Rehabilitation and Safely Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-08-10 2018-08-25 2018-10-06 2018-11-15 2018-12-20 2020-12-09 Improvement of Long Dai Envelope on and Dong Suon (Phase 2) C1-QB-GD2-W4 / Rehabilitation and Safely Pending Improvement of Thach Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-08-10 2018-08-25 2018-10-06 2018-11-15 2018-12-20 2020-12-09 Truong and Dong Vat and Envelope on Cay Bom and Buoi Roi (Phase 2) C2-MONRE-CW1 / Construction of water Pending resources, hydro and Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-04-01 2018-04-11 2018-05-11 2018-07-08 2018-07-22 2019-06-30 meteorology monitoring Envelope on stations in the Ca and Vu Gia - Thu Bon river basin C1-DAKNONG-W2 / Civil works: Repair 9 lakes, inclu ding 2 lots: Lot 1: 2 lakes Pending in Đắk R'lấp and Tuy Đức Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-04-30 2018-05-15 2018-06-25 2018-08-20 2018-09-10 2020-03-03 districts, estimated amount Envelope on US$ 1,089,000. Lot 2: 7 lak es in Đắk Glong district, es timated amount US$ 3,267, 000. C1-QN-KC-W1 / Khe Che Pending Single Stage - One reservoir rehabilitation and IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-02-27 2018-03-16 2018-04-20 2018-06-22 2018-07-13 2019-05-09 Envelope safety improvement on C1-TH-DB-W1 / The first ncb work contract for Reha Single Stage - One IDA / 57490 Post Request for Bids Open - National 1,456,677.47 Signed 2017-09-25 2017-09-30 2017-10-30 2017-11-19 2017-12-15 2019-06-08 bilitation and Safety Improv Envelope ement of Đồng Bể Dam. C1-PT-B-W1 / Repairs and safety upgrades reservoirs Ban and Insurance of Single Stage - One IDA / 57490 Prior Request for Bids Open - National 483,496.90 Signed 2017-06-08 2017-06-18 2017-08-17 2017-10-26 2017-11-23 2019-05-02 works. (The first NCB Envelope package in Phu Tho - the first-year province). C1-DAKNONG-W1 / Civil works: Repair 9 lakes, Inclu ding 2 plots: Lot 1: 6 lakes in Đắk Mil district, estimat Pending ed amount US$ 2,719,200, Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-04-27 2018-05-11 2018-06-15 2018-08-14 2018-09-04 2020-02-26 Lot 2: 3 lakes in Đắk Song Envelope on district, estimated amount US$ 1,812,800 (the first NC B contract of first-year subp roject) C1-GL-W2 / Repair 3 reser voirs, including 03 lots: Lot 1: Buôn Lưới Reservoir, esti mated cost US$ 493,000, Lo Pending Single Stage - One t 2: Plei Tô Kôn Reservoir IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-03-01 2019-03-31 2019-05-05 2019-07-04 2019-07-25 2020-07-19 Envelope , estimated cost US$ 309,00 on 0, Lot 3: Ia Năng and Làn g Me Reservoir, estimated c ost US$ 635,000 C1-GL-W1 / Repair 4 reser voirs, including 04 lots:Lot 1:Iaring,estimated cost US$1 ,370,000,Lot 2:Ayun Hạ,esti Pending mated cost US$ 850,000,Lot Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-03-01 2019-03-31 2019-05-05 2019-07-04 2019-07-25 2020-07-19 3:Ea Dreh,estimated cost U Envelope on S$ 210,000,Lot 4:Hà Tam, e stimated cost US$ 449,000 ( The first NCB contract of fi rst-year subproject) Page 2 C1-NA-KG-W1 / The package includes 02 lots: Lot 1: Rehabilitation and upgrading Khe Gang Under Reservoir. Lot 2: Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2017-12-26 2017-12-30 2018-01-30 2018-03-01 2018-03-22 2019-09-13 Rehabilitation and Envelope on upgrading Khe San Reservoir. The lots include work, equipment, insurance and general items. C1-LANGSON-W2 / Construction of 5 reservoirs: Pending Single Stage - One Bo Chuong, Tham Sinh, IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2020-03-18 2020-03-30 2020-05-04 2020-07-03 2020-08-06 2022-01-28 Envelope Khau Pieu, Khuoi Man, Coc on Lung C1-LANGSON-W1 / Pending Construction of 5 reservoirs: Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-03-22 2019-04-03 2019-05-08 2019-07-10 2019-08-15 2021-02-05 Ban Cuom, Ba Son, Ky Na, Envelope on Khuon Pinh, Phai Luong C1-SONLA-W1 / Civil wor k package - Rehabilitation Under and safety improvement of Single Stage - One IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2018-09-25 2018-10-10 2018-11-14 2019-01-03 2019-02-07 2020-06-01 Bản Ỏ, Noong Chạy, Huổi Envelope on Nhả - Khơ Mú, Xa Căn, X um Lo, Bản Củ, Nà Bó Re servoirs C1-LAMDONG-W1 / Constr uction of 8 reservoirs: inte Pending r-reservoir Suối Đỉa - Cây Single Stage - One IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2019-08-20 2019-09-03 2019-10-08 2019-12-10 2020-01-15 2022-01-14 Xoài, Đạ Sa, R'Lôm, Ma Po Envelope on h, Thanh Bạch, Hồ Số 4, Lộc Thắng, Đạ Bo B C1-DL-TDAI-W2 / Rehabilit ation and safety improveme nt of 07 reservoirs in sub-p roject 1 including lot1: 725 Pending Single Stage - One ,C19 reservoir - Lot 2: Ea IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-05-31 2019-06-10 2019-07-15 2019-09-09 2019-10-14 2021-04-06 Envelope Blong Thượng, Ea Kmiên 3 on reservoir -Lot 3: Ea Nao D ar, Ea Ngách, Ea Brơ 2 re servoir C1-QN-GD1-W3 / Repair and improve the safety of Pending 04 water reservoirs. Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-01-20 2019-01-25 2019-02-24 2019-03-21 2019-04-02 2020-09-23 Including 02 lots: Lot 1: Envelope on Hoc Khe, Ho Hieu. Lot 2: An Phong, Hoc Co C1-QN-GD1-W2 / Repair Pending and improve the safety of Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-11-12 2018-11-17 2018-12-17 2019-01-11 2019-01-23 2020-07-16 02 water reservoirs: Liet Envelope on Son, Cay Khe C1-QN-GD1-W1 / Repair and improve the safety of Pending 04 water reservoirs. Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-09 2018-10-14 2018-11-13 2018-12-08 2018-12-20 2020-06-12 Including 02 lots: Lot 1: Go Envelope on Lang, Hoc Bua. Lot 2: Lien Tri, Ho Da C1-QN-W1 / Rehabilitation and safety improvement of 06 reservoirs, divided into 0 Pending 3 lots, including: Lot 1: Đậ Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-01 2018-10-05 2018-11-05 2018-12-17 2018-12-28 2020-12-27 p Đá and Hố Lau reservoir Envelope on s, Lot 2: Hóc Két and Hóc Bầu reservoirs, Lot 3: Đồng Nhơn and Hố Mây reservoi rs. C1-QUANGTRI-W1 / Pending Rehabilitation and Safely Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-01-14 2019-01-29 2019-03-11 2019-05-10 2019-05-31 2020-11-21 Improvement of Kinh Mon Envelope on and Dap Hoi Reservoirs Page 3 C1-QUANGTRI-W3 / Rehabilitation and Safely Pending Improvement of Khe Muong Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-11-11 2019-11-26 2019-12-31 2020-02-24 2020-03-16 2021-09-07 and Km6 and Da Cua and Envelope on Khom 7 and Tan Vinh Reservoirs C1-QUANGTRI-W2 / Rehabilitation and Safely Pending Improvement of Duc Duc Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-05-14 2019-05-23 2019-06-27 2019-08-21 2019-09-11 2021-03-04 and Khe Na and Khom 2 Envelope on and Co Kieng 2 and Tram Reservoirs C1-BT-TDA2-W-01 / Rehabi litation and Safety Improve ment for 06 reservoirs, incl Pending uding 03 lots: Lot 1: Đá B Single Stage - One IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2020-03-05 2020-03-10 2020-04-16 2020-06-12 2020-07-17 2021-07-17 ạc, Cẩm Hang and Hộc T Envelope on ám Reservoirs, Lot 2: Tà M on and Tân Lập Reservoirs, Lot 3: Trà Tân Reservoir C1-KHANH HOA-W1 / Re habilitation and Safety Impr ovement for 04 reservoirs, d Pending Single Stage - One ivided into 02 lots, icluding: IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-12-14 2018-12-19 2019-01-23 2019-03-20 2019-04-03 2020-09-24 Envelope Lot 1: Láng Nhớt and Cây on sung reservoirs, Lot 2: Đồn g Bò and Đá Mài reservoirs C1-HB-GD2-W1 / Rehabilit ation and safety improveme nt of 5 reservoirs, divided Pending Single Stage - One into 2 lots, including: Lot 1 IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-26 2018-10-29 2018-11-28 2018-12-12 2018-12-18 2020-08-19 Envelope : Đồng Bến, Rả and Rộc K on háo reservoirs, Lot 2: Mền 1, Mền 2 reservoirs. C1-VINHPHUC-W1 / Reha bilitation and safety improv ement of 8 reservoirs, divid ed into 3 lot, including: Lot Pending Single Stage - One 1: Bò Lạc reservoir, Lot 2: IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-07-13 2018-07-16 2018-08-20 2018-09-19 2018-10-10 2020-04-10 Envelope Suối Sải, Đá Ngang and K on huôn reservoirs, Lot 3: Rừn g Vàu, Đá Bạc 2, Đồng Mồ and Đa Mang reservoirs. C1-VINHPHUC-W2 / Reha bilitation and safety improv ement of 3 reservoirs, divid ed into 3 lots, including: Lo Pending Single Stage - One t 1: Vĩnh Thành reservoir, IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-07-13 2018-07-16 2018-08-20 2018-09-19 2018-10-10 2020-04-10 Envelope Lot 2: Tân Bình and Trại on Trâu reservoirs, Lot 3: Trea tment of termite for reservo irs under subproject. C1-DL-TDAI-W1 / Rehabilit ation and safety improveme nt of 03 reservoirs in sub-p Pending Single Stage - One roject 1 including Lot 1: Ea IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-05-14 2019-05-24 2019-07-02 2019-08-27 2019-09-30 2021-03-23 Envelope Uy thượng reservoir- Lô 2: on Đội 11, Buôn Dung II reser voir. C1-TTH-W1 / Rehabilitation and safety Pending improvement of 03 Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-11-14 2018-11-21 2018-12-21 2019-01-28 2019-02-18 2020-08-11 reservoirs Including 02 lots: Envelope on Lot 1: Phu Bai 2 reservoir- Lot 2: Phu Nu and Cay Coi reservoir C1-TTH-W2 / Rehabilitation and safety improvement of 06 Pending reservoirs Including 03 lots: Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-05-15 2019-05-27 2019-07-01 2019-08-19 2019-09-09 2021-03-02 Lot 1: Cua and Khe Rung Envelope on reservoir-Lot 2: Ka Tu and Ta Rinh reservoir-Lot 3: Nam Lang and Ba Cua reservoir Page 4 C1-YB-W1 / Construction 5 of reservoirs, divided into 2 Pending lots, including: Lot 01: Tu Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-23 2018-10-26 2018-11-26 2018-12-21 2018-12-27 2020-06-27 Do, Chop Du reservoirs - Envelope on Lot 02: Goc Nhoi, Khe Hoai, Hang Luon reservoirs C1-YB-W2 / Construction 5 of reservoirs, divided into 2 lots, including: Lot 01: Pending Single Stage - One Nong truong nghia lo, thon IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-01-04 2019-01-22 2019-02-22 2019-03-29 2019-04-04 2020-10-03 Envelope 26-3 reservoirs - Lot 02: on Lang At, Khe Hop, Khe Ngang reservoirs C1-YB-W3 / Construction 6 of reservoirs, divided into 3 lots, including: Lot 01: Pending Khe Dua, Khe Vai Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-02-22 2019-03-11 2019-04-11 2019-05-21 2019-05-31 2020-11-29 reservoirs -Lot 02: Khe Envelope on Chinh, Phu Nham reservoir - Lot 03: Tang An, Roong Đen reservoirs C1-BD-GD2-W1 / Pending Construction of 03 Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-01 2018-10-21 2018-12-10 2019-02-08 2019-03-15 2021-03-04 reservoirs Cu Le, Lo Mon Envelope on and Ho Cung C1-BD-GD2-W2 / Construction of 05 Pending reservoirs (Including 2 lot: Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-01-03 2019-01-23 2019-03-14 2019-05-13 2019-06-17 2021-06-06 Lot 01: Hoc Tranh, Kim Envelope on Son and My Duc, lot 02: Da Ban, Giao Hoi) C1-BD-GD2-W3 / Construction of 05 reservoirs (Including 2 lot: Pending Lot 01: An Tuong, Nui Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-09-27 2019-10-17 2019-12-06 2020-02-04 2020-03-10 2022-02-28 Mieu and monitoring Envelope on equipment, lot 02: Trinh Van, Suoi Run and Hung Long) C1-LC-W1 / Rehabilitation and safety improvement of 6 reservoirs, divided into 2 Pending lots, including: Lot 1: Ta Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-18 2018-10-23 2018-11-22 2018-12-06 2018-12-14 2019-12-09 Xin, Phong Niên and Pho Envelope on rang reservoirs, Lot 2: Phu Nhuan, Sung Lang and Tan An reservoirs. C1-KONTUM-W1 / Rehabil itation and safety improvem Pending ent of 04 reservoirs includin Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-03-29 2019-04-08 2019-05-13 2019-07-02 2019-07-23 2021-12-29 g Lot 1: Đăk Hơ Niêng, Đă Envelope on k Tin reservoir- Lot 2: Kon Tu Zốp, Thôn 9 reservoir. C1-KONTUM-W2 / Rehabil itation and safety improvem ent of 04 reservoirs and co nstruction of new 04 manag Pending Single Stage - One ement house including Lot IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-04-29 2019-05-13 2019-06-17 2019-08-12 2019-09-16 2021-09-15 Envelope 1: Ya Xăng, Đăk Ngót rese on rvoir- Lot 2: Đội 5, Cà Sâ m reservoir- Lot 3: 04 Man agement house C1-KHANH HOA-W2 / Re habilitation and Safety Impr ovement for 04 reservoirs, d Pending ivided into 02 lots, icluding: Single Stage - One IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2019-02-21 2019-02-26 2019-04-02 2019-05-28 2019-06-11 2020-12-02 Lot 1: Suối Trầu and Bến Envelope on Ghe reservoirs, Lot 2: Suối Luồng and Suối Lớn reserv oirs Page 5 C1-KONTUM-W3 / Rehabil itation and safety improvem ent of 06 reservoirs includin Pending Single Stage - One g Lot 1: C2, A1 đội 4 rese IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-05-20 2019-06-03 2019-07-08 2019-09-06 2019-10-11 2021-10-15 Envelope rvoir- Lot 2: C3, C4 reservo on ir- Lot 3: C3 (704), Ia Ban g Thượng reservoir. GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1-QB-PV-G2 / Supply and Request for Single Stage - One IDA / 57490 Post Open - National 0.00 Canceled 2018-05-20 2018-07-15 2019-07-10 Installation of SCADA Quotations Envelope C2-MONRE-GO2 / Procurement of equipments Pending Single Stage - One for monitoring rainfall in IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-01 2018-10-11 2018-11-10 2018-12-31 2019-01-14 2019-12-31 Envelope the Ca and Vu Gia - Thu on Bon river basin C2-MONRE-GO1 / Procurement of equipments Pending for monitoring water level, Open - Single Stage - One IDA / 57490 Prior Request for Bids 0.00 Implementati 2018-10-01 2018-10-11 2018-11-25 2019-01-15 2019-01-29 2020-01-15 water discharge and water International Envelope on quality in the Ca and Vu Gia - Thu Bon river basin NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Consultant C2-MARD-CS1 / Support Pending IDA / 57490 Post Qualification Open - National 0.00 2017-03-01 2017-03-22 2017-05-18 2017-08-03 2017-08-24 2018-06-24 for database development Implementation Selection C2-MARD-CS2 / Improving Consultant Pending the legal framework for IDA / 57490 Post Qualification Open - National 0.00 2017-03-01 2017-03-22 2017-05-18 2017-08-03 2017-08-24 2018-06-24 Implementation dam safety management Selection C3-CPMU-CS1 / Project Quality And Cost- Open - Under Implementation Consultant IDA / 57490 Prior 0.00 2016-10-30 2016-11-13 2016-12-11 2017-01-08 2017-02-14 2017-03-23 2017-04-13 2022-06-30 Based Selection International Implementation (PIC) C1-QN-DL-CS1 / Consultant construction supervision IDA / 57490 Post Qualification Open - National 13,838.40 Signed 2016-12-27 2017-01-16 2017-03-16 2017-04-27 2017-05-18 2018-11-09 consultants Selection C1-KHANH HOA-CS1 / Consultant Environmental and Social IDA / 57490 Prior Qualification Open - National 96,113.19 Signed 2016-12-14 2016-12-29 2017-04-04 2017-06-01 2017-06-16 2017-08-30 Safeguard Reports Preparing Selection Consutant. C1-BT-SQ-CS-01 / Consulting services for Consultant Under investigations, construction IDA / 57490 Post Qualification Open - National 0.00 2016-12-14 2016-12-28 2017-03-16 2017-05-05 2017-05-26 2017-08-14 Implementation drawing design and cost Selection estimate Page 6 C3-CPMU-CS3 / Audit of Consultant Under financial statements for the IDA / 57490 Post Qualification Open - National 0.00 2017-02-20 2017-03-13 2017-05-29 2017-07-25 2017-08-15 2022-06-30 Implementation first 3 years Selection C1-CPMU-CS1 / International Monitoring Quality And Cost- Open - IDA / 57490 Prior 1,313,712.92 Signed 2016-12-30 2017-01-13 2017-02-10 2017-04-07 2017-05-29 2017-07-05 2017-07-26 2022-06-30 and Evaluation (M&E) Based Selection International consultant C3-CPMU-CS2 / Third party Independent Quality And Cost- Open - IDA / 57490 Prior 1,366,673.00 Signed 2016-12-23 2017-01-06 2017-02-03 2017-03-03 2017-04-17 2017-05-24 2017-06-14 2022-06-30 Supervision and Internal Based Selection International audit Consultant (ISC) C1-DL-TDA1-CS1 / Consultant Environmental and Social IDA / 57490 Post Qualification Open - National 0.00 Canceled 2016-12-19 2017-01-03 2017-03-22 2017-05-09 2017-05-30 2017-11-26 Safeguard Reports Preparing Selection Consultant C1-BD-GD2-CS1 / Consultant feasibility study report and dam safety Quality And Cost- report year - 2 of Binh IDA / 57490 Post Open - National 289,509.05 Completed 2017-01-16 2017-03-07 2017-05-16 2017-06-20 2017-07-25 2017-09-06 2017-10-26 2018-04-24 Based Selection Dinh province Dam rehabilitation and safety improvement project C1-LD-DT-CS1 / Construction Supervision Consultant Under and Preparation of IDA / 57490 Post Qualification Open - National 0.00 2017-04-28 2017-05-12 2017-08-10 2017-09-11 2017-10-02 2019-10-05 Implementation Emergency Preparedness Selection Plan (EPP) C1-QN-GD1-CS1 / Consultancy service for Consultant preparation of feasibility IDA / 57490 Post Qualification Open - National 263,745.09 Signed 2017-02-15 2017-03-08 2017-05-05 2017-06-16 2017-07-07 2018-01-03 study and dam safety Selection report C1-QN-GD1-CS3 / Report on environmental Iimpact Consultant assessment, environmental IDA / 57490 Post Qualification Open - National 111,443.87 Signed 2017-02-15 2017-03-08 2017-05-03 2017-06-02 2017-06-23 2017-11-20 and social impact Selection assessment, resettlement action plan C1-GL-CS1 / Consultant Consultant for developing feasibility Under IDA / 57490 Post Qualification Open - National 0.00 2017-07-13 2017-07-27 2017-10-25 2017-11-24 2017-12-22 2018-03-22 study and dam safety Implementation Selection report C1-GL-CS2 / Consultant Consultant for developing social and Under IDA / 57490 Post Qualification Open - National 0.00 2017-07-13 2017-07-27 2017-10-25 2017-11-24 2017-12-22 2018-03-22 environmental safeguards Implementation Selection reports C1-QN-CS1 / Consultant Consultant for developing feasibility Under IDA / 57490 Post Qualification Open - National 0.00 2017-02-28 2017-03-14 2017-06-12 2017-07-14 2017-08-04 2017-12-02 study and dam safety Implementation Selection report C1-QN-CS2 / Consultant Consultant Under for developing social and IDA / 57490 Post Qualification Open - National 0.00 2017-02-28 2017-03-14 2017-06-12 2017-07-14 2017-08-04 2017-12-02 Implementation environmental safeguards Selection C1-LC-CS1 / Consultant Consultant for developing feasibility IDA / 57490 Post Qualification Open - National 112,895.02 Signed 2017-02-21 2017-03-01 2017-05-29 2017-06-30 2017-07-21 2017-09-20 study and dam safety Selection report C1-LC-CS2 / Consultant Consultant for developing safeguards IDA / 57490 Post Qualification Open - National 51,513.93 Signed 2017-02-21 2017-03-01 2017-05-29 2017-06-30 2017-07-21 2017-09-20 reports Selection C1-KONTUM-CS1 / Consultant Feasibility Study and Dam IDA / 57490 Post Qualification Open - National 228,754.84 Signed 2017-02-14 2017-02-28 2017-05-19 2017-06-19 2017-07-10 2017-11-07 Safety Report Preparing Selection Consultant Page 7 C1-HB-GD2-CS1 / Consultant Consultant for developing Under IDA / 57490 Post Qualification Open - National 0.00 2017-05-18 2017-06-02 2017-09-08 2017-10-13 2017-11-03 2018-04-05 feasibility Study and Dam Implementation Selection Safety Reports - Phase 2 C1-HB-GD2-CS2 / Consultant for developing Consultant Pending environmental and Social IDA / 57490 Post Qualification Open - National 0.00 2017-05-18 2017-06-02 2017-09-08 2017-10-13 2017-11-03 2018-04-05 Implementation Safeguard Report - Phase Selection 2 C1-BG-CS1 / Consultant Consultant for developing feasibility Pending IDA / 57490 Post Qualification Open - National 0.00 2017-11-30 2017-12-30 2018-03-15 2018-04-16 2018-05-09 2018-08-07 study and dam safety Implementation Selection report C1-BG-CS2 / Consultant Consultant for developing social and Pending IDA / 57490 Post Qualification Open - National 0.00 2017-11-30 2017-12-30 2018-03-15 2018-04-16 2018-05-09 2018-08-07 environmental safeguards Implementation Selection reports C1-QB-PV-CS4 / Consultant for developing feasibility study and dam Consultant safety report of subproject: IDA / 57490 Post Qualification Open - National 0.00 Canceled 2017-02-27 2017-03-20 2017-05-03 2017-06-02 2017-07-07 2017-10-05 Improvement of Dam safety Selection in Quang Binh Province (Phase 2) C1-QB-PV-CS03 / Consultant Consultant for Emergency IDA / 57490 Post Qualification Open - National 0.00 Canceled 2017-04-15 2017-05-06 2017-06-19 2017-07-19 2017-08-23 2018-02-19 Preparedness Plan of Phu Selection Vinh (EPP) C1-QB-GD2-CS1 / Consultant services for Feasible Study report Consultant establishment on Dam IDA / 57490 Post Qualification Open - National 224,988.94 Signed 2017-05-10 2017-05-31 2017-07-14 2017-08-13 2017-09-17 2017-12-16 safety of subproject: Selection Improvement of Dam safety in Quang Binh province (Phase 2) C1-QB-GD2-CS2 / Environmental and Social Safeguard Reports Preparing Consultant Consultant of subproject: IDA / 57490 Post Qualification Open - National 96,508.20 Signed 2017-05-10 2017-05-31 2017-07-14 2017-08-13 2017-09-17 2017-12-16 Improvement of Dam safety Selection in Quang Binh province (Phase 2) C2-MONRE-CS4 / Development of real-time Consultant Pending multi-reservoir operation IDA / 57490 Post Qualification Open - National 0.00 2018-07-01 2018-07-29 2018-09-02 2018-09-09 2018-09-23 2020-12-31 Implementation scenarios in the Ca and Vu Selection Gia - Thu Bon river basin Consultant C2-MONRE-CS1 / Survey Under IDA / 57490 Post Qualification Open - National 0.00 2017-05-25 2017-06-08 2017-07-13 2017-08-03 2017-08-17 2018-03-31 and design for construction Implementation Selection C2-MONRE-CS3 / Development of database, hydrology and hydraulic models to serve for the Quality And Cost- Pending IDA / 57490 Post Open - National 0.00 2018-10-01 2018-10-15 2018-11-26 2018-12-03 2018-12-17 2019-01-07 2019-01-21 2020-12-31 management of the multi- Based Selection Implementation reservoir operation in the Ca and Vu Gia- Thu Bon river basin C2-MONRE-CS2 / Development of maps on Quality And Cost- Pending river bed topography in the IDA / 57490 Prior Open - National 0.00 2017-06-15 2017-06-29 2017-08-10 2017-08-17 2017-08-31 2017-09-21 2017-10-05 2020-12-31 Based Selection Implementation Ca and Vu Gia - Thu Bon river basin Page 8 C1-PT-CS3 / Consultant services for Feasible Study report establishment on Consultant Under Dam safety of subproject: IDA / 57490 Post Qualification Open - National 0.00 2017-05-25 2017-06-08 2017-09-26 2017-10-26 2017-11-23 2018-02-21 Implementation Improvement of Dam safety Selection in Phu Tho Province (Phase 2) C1-PT-CS2 / Consultant services on report establishment on social Consultant environmental safety IDA / 57490 Post Qualification Open - National 0.00 Canceled 2017-02-20 2017-03-06 2017-06-24 2017-07-24 2017-08-21 2017-11-19 policies of subproject: Selection Improvement of Dam safety in Phu Tho Province (Phase 2) C1-QUANGTRI-CS2 / Consultant Preparation of IDA / 57490 Post Qualification Open - National 168,701.91 Completed 2017-04-10 2017-06-06 2017-08-23 2017-10-03 2017-10-17 2018-01-25 environmental and social Selection safeguards instruments. C1-QB-CS3 / Consultant engineering design (phase 2) and Planning for Emergency Quality And Cost- Pending Preparedness (EPP) of the IDA / 57490 Post Open - National 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-28 2018-05-28 2018-07-02 2018-08-06 2018-11-04 Based Selection Implementation subproject: Improving Dam Safety in Quang Binh Province C1-DAKNONG-CS1 / Consultant Environmental and Social IDA / 57490 Post Qualification Open - National 85,726.96 Signed 2017-05-31 2017-06-14 2017-09-13 2017-10-13 2017-11-10 2018-02-08 Safeguard Reports Preparing Selection Consutant C1-DAKNONG-CS2 / Consultant Consulting services for Under IDA / 57490 Post Qualification Open - National 0.00 2017-05-30 2017-06-13 2017-09-15 2017-10-17 2017-11-14 2018-02-12 survey, construction drawing Implementation Selection design and cost estimate C1-TTH-CS1 / Consultant Consultant for developing feasibility IDA / 57490 Post Qualification Open - National 158,736.46 Signed 2017-05-04 2017-05-18 2017-08-17 2017-09-18 2017-10-23 2018-01-31 study and dam safety Selection report C1-TTH-CS2 / Consultant Consultant for developing social and IDA / 57490 Post Qualification Open - National 69,889.60 Signed 2017-05-30 2017-06-13 2017-09-12 2017-10-13 2017-11-17 2018-02-15 environmental safeguards Selection C1-PHUYEN-CS1 / Consultant Feasibility Study and Dam Under IDA / 57490 Post Qualification Open - National 0.00 2017-04-28 2017-05-25 2017-07-31 2017-08-28 2017-09-12 2017-12-13 Safety Reports Preparing Implementation Selection Consultant C1-QUANGTRI-CS1 / Consultant Preparation of feasibility IDA / 57490 Post Qualification Open - National 224,309.78 Completed 2017-05-08 2017-06-02 2017-08-19 2017-09-29 2017-10-13 2018-01-21 study and dam safety Selection reports for phase-2 dams. Consultant C1-BD-GD2-CS2 / Tu van IDA / 57490 Post Qualification Open - National 122,666.86 Signed 2017-06-12 2017-07-03 2017-08-16 2017-09-15 2017-10-20 2018-03-19 cac chinh sach an toan Selection C1-PT-B-CS1 / Consulting Consultant supervision for construction IDA / 57490 Post Qualification Open - National 12,785.44 Signed 2017-06-02 2017-06-16 2017-09-29 2017-10-29 2017-11-19 2019-04-15 works and installation of Selection equiment C1-DAKNONG-CS3 / Consultant Pending Construction supervision IDA / 57490 Post Qualification Open - National 0.00 2018-03-22 2018-04-05 2018-07-06 2018-08-06 2018-09-03 2020-03-03 Implementation consultant Selection C1-TQ-NL2-CS1 / Construction supervision Consultant and Preparation of IDA / 57490 Post Qualification Open - National 0.00 Canceled 2017-02-22 2017-03-07 2017-06-05 2017-07-07 2017-07-28 2019-01-19 Emergency Preparedness Selection Plan (EPP) Page 9 C1-TQ-CS3 / Preparation of Emergency Preparedness Plan for 2 Projects (Subproject 1: Ngoi La 2 reservoir, Subproject 2: Consultant Under Trung Long, Hai Mo, Khe IDA / 57490 Post Qualification Open - National 0.00 2017-11-30 2017-12-15 2018-03-15 2018-04-16 2018-05-10 2021-03-09 Implementation Thuyen, Cay Gao, Minh Selection Cam, Na Vang, Ao Buc, Khuoi Thung, Hoang Khai, Na Heng, O Ro, Cay Dau and Noong Mo reservoir) VN-DRSIP MOIT-16496-CS- Consultant LCS / Project audit Pending IDA / 57490 Post Qualification Open - National 0.00 2017-11-01 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2018-11-09 annually (2017, 2018, 2019, Implementation Selection 2020, 2021) C1-THAINGUYEN-CS1 / Consultant Feasibility Study and Dam Under IDA / 57490 Post Qualification Open - National 0.00 2017-09-19 2017-10-03 2018-01-02 2018-02-06 2018-02-27 2018-04-28 Safety Reports preparing Implementation Selection consultant. C2-THAINGUYEN-CS2 / Consultant Environmental and social Under IDA / 57490 Post Qualification Open - National 0.00 2017-09-19 2017-10-03 2018-01-02 2018-02-06 2018-02-27 2018-04-28 safeguard reports preparing Implementation Selection consultant. VN-DRSIP MOIT-12374-CS- CQS / Consultant service for assessment apply of Consultant standards and regulations IDA / 57490 Post Qualification Open - National 0.00 Canceled 2018-07-02 2018-07-23 2018-09-05 2018-10-05 2018-11-09 2019-05-08 system in design, Selection construction, operation and management of hydropower projects C1-GL-CS3 / Consultant to survey, prepare construction Consultant drawing design and cost Pending IDA / 57490 Post Qualification Open - National 0.00 2018-05-01 2018-05-25 2018-08-25 2018-09-24 2018-10-22 2019-01-20 estimates and Consultant to Implementation Selection prepare Emergency Preparedness Plan (EPP) VN-DRSIP MOIT-18007-CS- QCBS / Improve standards and regulations system for Quality And Cost- Pending IDA / 57490 Prior Open - National 0.00 2018-06-01 2018-06-22 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 hydropower dams in periods Based Selection Implementation of design, construction, operation and management C1-PHUYEN-CS2 / Consultant Environmental and Social Under IDA / 57490 Post Qualification Open - National 0.00 2017-09-21 2017-10-05 2017-12-23 2018-01-29 2018-02-05 2018-05-06 Safeguard Reports Preparing Implementation Selection Consultant C1-TQ-NL2-CS2 / Consultant Supervision consultant for IDA / 57490 Post Qualification Open - National 30,561.12 Signed 2017-09-20 2017-10-05 2017-11-20 2017-11-30 2017-12-11 2019-06-11 Ngoi La 2 reservoir sub- Selection project C1-DL-TDAII-CS2 / Feasibility Study and Dam Consultant Under Safety Reports preparing IDA / 57490 Post Qualification Open - National 0.00 2017-11-15 2017-12-06 2018-01-19 2018-02-19 2018-03-26 2018-09-24 Implementation consultant, subproject phase Selection II VN-DRSIP MOIT-16468-CS- Consultant CQS / Consulting Company Pending IDA / 57490 Post Qualification Open - National 0.00 2018-04-01 2018-04-22 2018-06-05 2018-07-05 2018-08-09 2019-02-05 for Project Monitoring and Implementation Selection Evaluation (M&E) C1-VINHPHUC-CS1 / Consultant Environmental and Social Pending IDA / 57490 Post Qualification Open - National 0.00 2017-11-15 2017-12-29 2018-02-26 2018-03-29 2018-04-19 2018-06-29 Safeguard Reports Preparing Implementation Selection Consutant C1-VINHPHUC-CS2 / Consultant Survey, design construction Pending IDA / 57490 Post Qualification Open - National 0.00 2018-01-08 2018-01-22 2018-04-20 2018-05-20 2018-06-10 2018-08-29 drawing, cost estimates Implementation Selection consultant Page 10 C1-HB-GD3-CS1 / Consultant Consultant for developing Pending IDA / 57490 Post Qualification Open - National 0.00 2018-04-20 2018-05-04 2018-07-06 2018-08-10 2018-08-24 2018-11-22 feasibility Study and Dam Implementation Selection Safety Reports - Phase 3 C1-HB-GD3-CS2 / Consultant Environmental and Social Pending IDA / 57490 Post Qualification Open - National 0.00 2018-04-20 2018-05-04 2018-07-06 2018-08-10 2018-08-24 2018-11-22 Safeguard Reports Preparing Implementation Selection Consultant-Phase 3 C1-TQ-GD2-CS1 / Feasibility study and dam safety reports preparing consultant (Subproject 2: Consultant Trung Long, Hai Mo, Khe IDA / 57490 Post Qualification Open - National 218,883.23 Signed 2017-11-10 2017-11-24 2018-02-19 2018-03-23 2018-04-20 2018-08-20 Thuyen, Cay Gao, Minh Selection Cam, Na Vang, Ao Buc, Khuoi Thung, Hoang Khai, Na Heng, O Ro, Cay Dau and Noong Mo reservoir) C1-TQ-GD2-CS2 / Environmental and Social Safeguard Reports Preparing Consultant (Subproject 2: Consultant Trung Long, Hai Mo, Khe IDA / 57490 Post Qualification Open - National 114,953.61 Signed 2017-10-31 2017-11-24 2018-02-22 2018-03-26 2018-04-16 2018-06-16 Thuyen, Cay Gao, Minh Selection Cam, Na Vang, Ao Buc, Khuoi Thung, Hoang Khai, Na Heng, O Ro, Cay Dau and Noong Mo reservoir) C1-BK-CS1 / Consulting Consultant Under package of Feasibility Study IDA / 57490 Post Qualification Open - National 0.00 2017-11-06 2017-11-28 2018-02-26 2018-03-30 2018-05-04 2018-08-03 Implementation and Dam Safety Report Selection C1-BK-CS2 / Consulting Consultant package of Social and Social Pending IDA / 57490 Post Qualification Open - National 0.00 2017-11-06 2017-11-28 2018-02-26 2018-03-30 2018-05-04 2018-08-03 Environmental Safety Implementation Selection Reports C1-NT-CS04 / Consultant Environmental and social Pending IDA / 57490 Post Qualification Open - National 0.00 2017-11-16 2017-12-15 2018-03-16 2018-04-20 2018-05-11 2018-09-08 safeguard reports preparing Implementation Selection consultant C1-NT-CS05 / Construction Consultant Pending supervision consultancy IDA / 57490 Post Qualification Open - National 0.00 2018-08-01 2018-09-15 2018-11-30 2018-12-30 2019-01-20 2019-07-19 Implementation package Selection C1-LANGSON-CS1 / Consultation on preparation of safety policy reports including: Environmental Impact Assessment Report, Consultant Under Social Environment Impact IDA / 57490 Post Qualification Open - National 0.00 2018-02-02 2018-02-27 2018-05-29 2018-07-03 2018-07-25 2018-09-24 Implementation Assessment Report, Selection Resettlement Action Plan Report, Social Impact Assessment Report , ethnic minority development plan C1-LANGSON-CS2 / Consultant Consultancy of construction Pending IDA / 57490 Post Qualification Open - National 0.00 2018-06-11 2018-06-26 2018-09-27 2018-11-01 2018-11-23 2019-01-22 drawing design - total cost Implementation Selection estimate C1-LANGSON-CS3 / Consultant Pending Construction supervision IDA / 57490 Post Qualification Open - National 0.00 2019-08-15 2019-08-29 2019-12-18 2020-01-19 2020-02-13 2022-02-28 Implementation consultant Selection C1-SONLA-CS1 / Consultant Construction supervision, Pending IDA / 57490 Post Qualification Open - National 0.00 2018-09-03 2018-09-17 2018-12-17 2019-01-17 2019-02-07 2020-06-01 Emergency Preparedness Implementation Selection Plan (EPP) Page 11 C1-KONTUM-CS2 / Consultant Environmental and Social IDA / 57490 Post Qualification Open - National 72,649.43 Signed 2018-01-18 2018-02-01 2018-04-23 2018-05-24 2018-06-28 2018-09-26 Safeguard Documents Selection Preparing Consutant C1-PT-CS2-2 / Consultant services on report establishment on social Consultant Pending environmental safety policies IDA / 57490 Post Qualification Open - National 0.00 2028-01-19 2028-02-28 2028-04-19 2028-05-24 2028-06-28 2028-09-26 Implementation of subproject: Improvement Selection of Dam safety in Phu Tho Province (Phase 2) C1-LAMDONG-CS1 / Consultant Environmental and Social Pending IDA / 57490 Post Qualification Open - National 0.00 2018-01-30 2018-02-13 2018-05-15 2018-06-19 2018-07-11 2019-01-07 Safeguard Reports Preparing Implementation Selection Consultant C1-LAMDONG-CS2 / Consultancy of construction Consultant drawing design - total cost Pending IDA / 57490 Post Qualification Open - National 0.00 2018-08-09 2018-08-23 2018-11-22 2018-12-27 2019-01-18 2019-07-17 estimate + Emergency Implementation Selection Preparedness Plan Preparation Consultant C1-LAMDONG-CS3 / Consultant Pending Construction supervision IDA / 57490 Post Qualification Open - National 0.00 2019-08-05 2019-08-19 2019-11-20 2019-12-25 2020-01-15 2022-01-14 Implementation consultant Selection C1-NB-CS1 / Consulting Consultant services for Feasibility Pending IDA / 57490 Post Qualification Open - National 0.00 2018-03-16 2018-03-30 2018-06-29 2018-08-03 2018-08-24 2018-10-23 Study and Dam Safety Implementation Selection report C1-NB-CS2 / Consultant Environmental and Social Pending IDA / 57490 Post Qualification Open - National 0.00 2018-04-26 2018-05-15 2018-08-15 2018-09-19 2018-10-10 2018-12-09 Safeguard Reports Preparing Implementation Selection Consultant C1-NB-CS3 / Consultancy Consultant Pending of construction drawing IDA / 57490 Post Qualification Open - National 0.00 2018-08-03 2018-08-17 2018-11-15 2018-12-20 2019-01-10 2019-03-11 Implementation design - total cost estimate Selection C1-DL-TDAI-CS4 / Consultant Pending construction supervision for IDA / 57490 Post Qualification Open - National 0.00 2019-03-29 2019-04-12 2019-07-12 2019-08-12 2019-09-02 2021-02-23 Implementation sub-project 1 Selection C1-KHANH HOA-CS2 / Consultant to survey, Consultant Pending prepare construction IDA / 57490 Post Qualification Open - National 0.00 2018-05-05 2018-05-19 2018-07-18 2018-08-02 2018-08-16 2018-12-14 Implementation drawing design and cost Selection estimates C1-KHANH HOA-CS3 / Consultant Consultant to prepare Pending IDA / 57490 Post Qualification Open - National 0.00 2018-08-15 2018-08-29 2018-11-27 2018-12-29 2019-01-19 2019-07-18 Emergency Preparedness Implementation Selection Plan (EPP) C1-BT-TDA2-CS-01 / Consultant for developing Consultant Pending feasibility study and dam IDA / 57490 Post Qualification Open - National 0.00 2018-04-27 2018-05-11 2018-08-09 2018-09-10 2018-10-01 2019-01-29 Implementation safety report for subproject Selection 2 C1-BT-TDA2-CS-02 / Consultant for developing Consultant Pending social and environmental IDA / 57490 Post Qualification Open - National 0.00 2018-05-21 2018-06-04 2018-09-02 2018-10-04 2018-10-25 2019-02-22 Implementation safeguards reports for Selection subproject 2 C1-BT-TDA2-CS-03 / Consultant to survey, Consultant Pending prepare construction IDA / 57490 Post Qualification Open - National 0.00 2019-04-29 2019-05-13 2019-08-09 2019-09-10 2019-10-01 2019-12-30 Implementation drawing design and cost Selection estimates for subproject 2 Page 12 C1-BT-TDA2-CS-04 / Consultant Pending Consultant to construction IDA / 57490 Post Qualification Open - National 0.00 2020-03-02 2020-03-16 2020-06-14 2020-07-16 2020-08-07 2021-08-07 Implementation supervision for subproject 2 Selection C1-QN-GD1-CS4 / Survey, Consultant design construction drawing Under IDA / 57490 Post Qualification Open - National 0.00 2018-05-15 2018-05-20 2018-07-14 2018-07-24 2018-08-05 2019-02-01 and emergency response Implementation Selection planning consultant C1-QN-GD1-CS5 / Consultant Construction, environment Pending IDA / 57490 Post Qualification Open - National 0.00 2018-09-01 2018-09-11 2018-11-10 2018-11-20 2018-12-02 2020-05-25 and society supervision Implementation Selection consultant C1-QUANGTRI-CS3 / Consultancy on construction Consultant drawing design, Operational IDA / 57490 Post Qualification Open - National 237,866.21 Signed 2018-06-01 2018-06-15 2018-09-14 2018-10-19 2018-11-09 2019-11-04 and Maintenance Plan Selection (O&M), Emergency Preparedness Plan (EPP) C1-QN-CS3 / Consultancy f or survey, construction draw ing design and cost estimat Consultant Pending es for 06 reservoirs, includi IDA / 57490 Post Qualification Open - National 0.00 2018-07-16 2018-07-30 2018-09-03 2018-09-10 2018-09-21 2018-12-20 Implementation ng: Đập Đá, Hố Lau, Hóc Selection Két, Hóc Bầu, Đồng Nhơn and Hố Mây Reservoirs. C1-QUANGTRI-CS4 / Consultant Consultancy service for Under IDA / 57490 Post Qualification Open - National 0.00 2018-05-21 2018-06-04 2018-09-03 2018-10-08 2018-10-29 2021-06-25 construction supervision and Implementation Selection environmental monitoring C1-QN-CS4 / Consultancy f or prepare Emergency Prep aredness Plan (EPP) for 06 Consultant Pending reservoirs, including: Đập Đ IDA / 57490 Post Qualification Open - National 0.00 2018-12-26 2019-01-09 2019-03-20 2019-04-03 2019-04-17 2019-08-15 Implementation á, Hố Lau, Hóc Két, Hóc B Selection ầu, Đồng Nhơn, Hố Mây r eservoirs C1-KONTUM-CS5 / Constr uction supervision consultan t of 14 reservoirs C3, C4, Đội 5, Cà Sâm, Ia Bang T Consultant Pending hượng,Đăk Hơ Niêng,Kon T IDA / 57490 Post Qualification Open - National 0.00 2019-03-29 2019-04-12 2019-05-31 2019-07-01 2019-07-23 2021-12-29 Implementation u Zốp,Đăk Tin, C2, A1 đội Selection 4, Thôn 9, Ya Xăng, C3(704 ), Đăk Ngót and 04 manage ment house C1-VINHPHUC-CS3 / Consultant Pending Consultant to construction IDA / 57490 Post Qualification Open - National 0.00 2018-07-16 2018-07-30 2018-08-30 2018-10-01 2018-10-22 2020-04-22 Implementation supervision Selection C1-VINHPHUC-CS4 / Consultant Consultant to prepare Pending IDA / 57490 Post Qualification Open - National 0.00 2018-07-16 2018-07-30 2018-08-30 2018-10-01 2018-10-22 2019-04-22 Emergency Preparedness Implementation Selection Plan. C1-TTH-CS4 / Consulting service for investigation, Consultant Pending design of construction IDA / 57490 Post Qualification Open - National 0.00 2018-07-02 2018-07-16 2018-08-14 2018-09-04 2018-09-14 2018-11-13 Implementation drawings, termite Selection investigation and EPP Consultant C1-TTH-CS5 / Supervision Pending IDA / 57490 Post Qualification Open - National 0.00 2018-11-29 2018-12-13 2019-01-14 2019-02-04 2019-02-18 2021-03-02 consultant Implementation Selection C1-YB-CS6 / Survey, Consultant Preparation of termite Pending IDA / 57490 Post Qualification Open - National 0.00 2018-07-10 2018-07-26 2018-08-14 2018-09-03 2018-09-08 2019-01-06 treatment documents for all Implementation Selection dams under Subproject C1-YB-CS7 / Construction Consultant Pending Supervision Consultant for IDA / 57490 Post Qualification Open - National 0.00 2018-10-24 2018-11-09 2018-12-07 2018-12-21 2018-12-27 2020-11-28 Implementation all dams under Subproject Selection Page 13 C1-BD-GD2-CS3 / Consultant for surveying, construction drawing design and cost estimation for 10 reservoirs (Kim Son, My Quality And Cost- Duc, Hoc Tranh, Hung IDA / 57490 Post Open - National 0.00 Canceled 2018-07-20 2018-09-08 2018-11-17 2018-12-22 2019-01-26 2019-03-10 2019-04-09 2019-12-05 Based Selection Long, Giao Hoi, Da Ban, Suoi Run, Trinh Van, An Tuong, Nui Mieu) and Emergency preparedness plan for 4 large reservoirs C1-BD-GD2-CS4 / Consultant Consultant for construction Pending IDA / 57490 Post Qualification Open - National 0.00 2018-07-30 2018-08-20 2018-10-19 2018-11-18 2018-12-23 2021-12-22 supervision and equipment Implementation Selection of 13 reservoirs C1-LC-CS3 / Consultancy of construction drawing Consultant design - total cost estimate: Pending IDA / 57490 Post Qualification Open - National 0.00 2018-07-20 2018-07-27 2018-08-17 2018-09-07 2018-09-14 2018-10-29 Sung Lang, Phu Nhuan, Implementation Selection Tan An, Pho Rang, Phong Nien, Ta Xin reservoirs. C1-YB-CS5 / Consultancy f or survey, construction draw ing design, cost estimates of 16 reservoirs: Tặng An, Ro ong Đen, Làng Át, Gốc Nh Consultant Pending ội, Khe Hoài, Hang Luồn, IDA / 57490 Post Qualification Open - National 0.00 2018-07-10 2018-07-26 2018-08-14 2018-09-03 2018-09-08 2019-01-06 Implementation Khe Vải, Khe dứa, Khe Hó Selection p, Khe Ngang, Khe Chinh, Tự Do, Chóp Dù, Phù Nha m, Nông trường Nghĩa Lộ, Thôn 26 C1-KONTUM-CS3 / Consul ting services for design of c onstruction drawings of 14 reservoirs C3, C4, Đội 5, C Consultant Pending à Sâm, Ia Bang Thượng,Đă IDA / 57490 Post Qualification Open - National 0.00 2018-08-24 2018-09-07 2018-11-01 2018-11-30 2018-12-21 2019-03-21 Implementation k Hơ Niêng,Kon Tu Zốp,Đă Selection k Tin, C2, A1 đội 4, Thôn 9, Ya Xăng, C3(704), Đăk Ngót and 04 management h ouse C1-KONTUM-CS4 / Consulting services for Consultant Pending Preparing of Emergency IDA / 57490 Post Qualification Open - National 0.00 2018-10-01 2018-10-15 2018-12-14 2019-01-09 2019-01-30 2019-04-01 Implementation Preparedness Plan (EPP) of Selection Ya Xăng reservoirs C1-DL-CS1 / Consultant Environmental and Social Pending IDA / 57490 Post Qualification Open - National 0.00 2018-10-15 2018-10-29 2018-12-28 2019-01-28 2019-02-27 2019-08-26 Safeguard Reports Preparing Implementation Selection Consultant C1-DL-TDAI-CS3 / Consulting services for Consultant Pending Construction Drawing IDA / 57490 Post Qualification Open - National 0.00 2018-08-24 2018-09-17 2018-12-17 2019-01-17 2019-02-07 2019-06-07 Implementation Designs and Cost Estimates Selection for sub-project 1 C1-BD-GD2- CS3 / Consultant for surveying, construction drawing design and cost estimation for 10 reservoirs (Kim Son, My Consultant Under Duc, Hoc Tranh, Hung IDA / 57490 Post Qualification Open - National 0.00 2018-08-21 2018-09-11 2018-10-05 2018-11-04 2018-12-05 2019-11-30 Implementation Long, Giao Hoi, Da Ban, Selection Suoi Run, Trinh Van, An Tuong, Nui Mieu) and Emergency preparedness plan for 4 large reservoirs INDIVIDUAL CONSULTANTS Page 14