Sample Procurement Plan I. General 1. Bank’s approval Date of the Procurement Plan: Original, October 2015. 2. Date of General Procurement Notice: June 26, 2017 3. Period covered by this procurement plan: From September 2017 to September 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB (Works) All All 2. ICB (Goods and Non- All All Consulting Services) 3. NCB (Works) From US$ 15 million All 4. NCB (Goods and Non- From US$ 4 million All Consulting Services) 5. Shopping (Works) None None 6. Shopping (Goods and Non- None None Consulting Services) 7. Direct Contracting (Works) From US$ 15 million All Direct Contracting (Goods From US$ 4 million All and Non-Consulting Services) 2. Prequalification. Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: Not applicable. 4. Reference to (if any) Project Operational/Procurement Manual: The Operations Manual issued by the SEPLAN (Project Implementation Unit) describes the methods and procedures applicable to all procurement of goods, works, non-consulting services and consulting services financed by the Loan Agreement # 8575-BR. July 9, 2010 5. Any Other Special Procurement Arrangements: Eligible expenditures under Part 1 of the Project are not subject to the Procurement and Consultant Guidelines. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior/Pos US$ rence t) million (yes/ no) 1 Summary 0.24 1 No Prior of the ICBs (Goods) 2 Summary 3.1 16 No Post of the NCBs (Goods) 3 Summary 0.96 11 No Post of the NCBs (Non- Consulting Services) 4 Summary 0.23 5 No Post of the Shoppings (Goods) 5 Summary 0.37 10 No Post of the Shoppings (Non- Consulting Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) From US$ 1 million All 2. Single Source Selection (Firms) From US$ 1 million All 3. Individual Consultant From US$ 300,000 All July 9, 2010 4 Single Source Selection From US$ 300,000 All (Individuals) 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 1,500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million 1 Summary 5.8 19 Prior of number of contracts that will be let under QCBS method 2 Summary 2.2 25 Post SCQ of number of contracts that will be let under methods other than QCBS 3 Summary 2.7 22 Post IC of number of contracts that will be let under Individual Consultant method July 9, 2010 July 9, 2010 PROCUREMENT Brazil : Piaui: Pillars of Growth and Social Inclusion Project PLAN General Information Country: Brazil Bank’s Approval Date of the Original Procurement Plan: 2017-11-24 2021-10-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P129342 GPN Date: 2017-06-26 Project Name: Piaui: Pillars of Growth and Social Inclusion Project Loan / Credit No: IBRD / 85750 I Executing Agency(ies): nstitute of Piaui Lands WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-INTERPI-PI-48237-GO- Component 2: Provision of RFQ / Aquisição de mobiliário technical assistance to Solicitação de Single Stage - One para nova sede e abrigo de IBRD / 85750 Posterior Open - National 64,725.00 39,288.85 Assinado 2018-05-05 2018-06-30 2018-08-24 2018-12-27 strengthen the Borrower’s Cotações Envelope novos setores do INTERPI - public management. Fase 2 BR-INTERPI-PI-48252-GO- RFB / Aquisição de 02 Component 2: Provision of unidades móveis de technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 280,000.00 130,589.91 Assinado 2018-02-19 2018-04-13 2018-02-24 2018-04-07 2018-04-16 2018-05-07 2018-07-09 2018-06-11 2018-08-24 2018-12-08 regularização fundiária para strengthen the Borrower’s Ofertas Envelope aumento da efetividade das public management. ações do INTERPI BR-INTERPI-PI-48245-GO- RFQ / Aquisição de rádios Component 2: Provision of comunicadores para uso em technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 24,272.00 14,702.97 Assinado 2018-05-05 2018-06-30 2018-08-24 2018-12-27 atividades de campo de strengthen the Borrower’s Cotações Envelope competência do INTERPI (6 public management. kits) BR-INTERPI-PI-48369-GO- RFQ / Aquisição de Component 2: Provision of Eletrodomésticos para technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 38,700.00 0.00 Cancelado 2018-02-24 2018-04-21 2018-10-18 escritórios em Teresina e no strengthen the Borrower’s Cotações Envelope Sul do Estado (GERCOG, public management. Ministério Público) BR-INTERPI-PI-21-GO-RFQ / Component 2: Provision of Aquisição de Mobiliário para technical assistance to Solicitação de Single Stage - One escritórios em Teresina e no IBRD / 85750 Posterior Open - National 51,300.00 0.00 Cancelado 2018-02-24 2018-04-21 2018-10-18 strengthen the Borrower’s Cotações Envelope Sul do Estado (GERCOG, public management. Ministério Público) BR-INTERPI-PI-3-GO-RFQ / Component 2: Provision of Equipamentos de informática technical assistance to Solicitação de Single Stage - One (Computadores, Scanner, IBRD / 85750 Posterior Open - National 80,906.00 50,634.41 Assinado 2018-04-30 2018-06-21 2018-05-05 2018-06-16 2018-06-29 2018-07-16 2018-06-29 2018-08-20 2018-08-24 2019-02-16 strengthen the Borrower’s Ofertas Envelope impressora, notebook, public management. estabilizador) - Fase 2 BR-INTERPI-PI-2-GO-RFQ / Component 2: Provision of Aquisição de plataformas para technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Limited 17,949.00 0.00 Cancelado 2017-06-06 2017-08-01 2018-01-28 deficientes visuais nos strengthen the Borrower’s Cotações Envelope assentamentos (10) public management. Component 2: Provision of BR-INTERPI-PI-57772-GO- technical assistance to Solicitação de Single Stage - One RFQ / Aquisição de aparelhos IBRD / 85750 Posterior Open - National 19,417.00 10,506.88 Assinado 2018-06-04 2018-07-30 2018-08-24 2019-01-26 strengthen the Borrower’s Cotações Envelope de ar condicionado public management. BR-INTERPI-PI-149932-GO- RFQ / Aquisição de mobiliário Component 2: Provision of para os novos setores do technical assistance to Solicitação de Single Stage - One INTERPI (cadeiras, mesas e IBRD / 85750 Posterior Open - National 37,500.00 27,596.91 Assinado 2019-12-20 2020-02-14 2020-08-21 2020-08-12 strengthen the Borrower’s Cotações Envelope estações de trabalho) para public management. fortalecer os trabalhos de regularização fundiária. BR-INTERPI-PI-149934-GO- RFQ / Aquisição de MARCOS E PLAQUETAS para atender as Component 2: Provision of Em fase de necessidades do Instituto de technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 25,000.00 0.00 Implementaçã 2019-12-20 2020-02-14 2020-08-12 Terras do Piauí – INTERPI, a strengthen the Borrower’s Cotações Envelope o regularização fundiária e o public management. fortalecimento da gestão institucional. BR-INTERPI-PI-126290-GO- RFQ / AQUISIÇÃO DE EQUIPAMENTOS VANTS (VEÍCULOS AÉREOS NÃO Component 2: Provision of TRIPULADOS) E GPS technical assistance to Solicitação de GEODÉSICOS DUPLA IBRD / 85750 Posterior Open - National Multi Stage 226,776.00 0.00 Cancelado 2019-09-30 2019-10-05 2019-12-14 2020-03-27 2020-05-01 2021-10-23 strengthen the Borrower’s Propostas FREQUÊNCIA L1/L2 PARA public management. UTILIZAÇÃO NA REGULARIZAÇÃO FUNDIÁRIA DAS TERRAS ESTADUAIS E DOS ASSENTAMENTOS RURAIS BR-INTERPI-CGJ-PI-68151- GO-RFQ / Aquisição de Component 2: Provision of equipamento de inteligencia e technical assistance to Solicitação de Single Stage - One tecnologia da informação IBRD / 85750 Posterior Open - National 216,216.00 0.00 Cancelado 2018-07-24 2018-09-18 2019-03-17 strengthen the Borrower’s Cotações Envelope (incluindo licencia, instalação, public management. e trainamento dos operadores) - GERCOG Page 1 BR-INTERPI-PI-126313-GO- RFQ / CONTRATAÇÃO DE UMA EMPRESA ESPECIALIZADA EM FORNECIMENTO DE EQUIPAMENTOS E MATERIAL Component 2: Provision of DE INFORMÁTICA, PELO technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 350,000.00 289,518.40 Assinado 2020-01-26 2020-01-31 2020-01-31 2020-03-13 2020-05-13 2020-04-12 2020-06-11 2020-05-17 2020-07-16 2020-11-13 INTERPI, PARA strengthen the Borrower’s Ofertas Envelope PROCURADORIA DO public management. PATRIMÔNIO E DO MEIO- AMBIENTE DA PROCURADORIA GERAL DO ESTADO DO PIAUÍ- PGE/PI E PARA O INTERPI BR-INTERPI-PI-149933-GO- Component 2: Provision of RFP / Aquisição de Pares de technical assistance to Solicitação de Single Stage - One GPS Geodésico para ajudar as IBRD / 85750 Posterior Open - National 175,000.00 156,541.04 Assinado 2020-01-26 2020-01-31 2020-01-31 2021-05-31 2020-03-13 2020-03-30 2020-04-12 2020-04-08 2020-05-17 2020-07-01 2020-11-13 strengthen the Borrower’s Ofertas Envelope equipes no campo e fazer as public management. marcações com mais precisão BR-INTERPI-PI-149732-GO- RFB / Aquisição de 10 camionetes tipo pick ups para facilitar o deslocamento das Component 2: Provision of equipes de campo formadas technical assistance to Solicitação de Single Stage - One por técnicos para a realização IBRD / 85750 Posterior Open - National 325,000.00 0.00 Cancelado 2019-12-15 2020-01-31 2019-12-20 2020-01-31 2020-03-01 2020-04-05 2020-10-02 strengthen the Borrower’s Ofertas Envelope de vistorias nas áreas a serem public management. regularizadas. Características: veículos automotores, com tração 4x4, movida a óleo diesel. BR-INTERPI-PI-149732-GO- RFB-2 / Locação 5 (cinco) camionetes tipo pick ups, c/ cabine dupla, automotores, c/ Component 2: Provision of tração 4X4, movida a óleo technical assistance to Solicitação de Single Stage - One diesel, p/ auxiliar as equipes IBRD / 85750 Posterior Open - National 80,000.00 56,891.99 Assinado 2020-09-20 2020-11-15 2020-10-13 2021-05-14 strengthen the Borrower’s Cotações Envelope de campo formadas por public management. técnicos p/ a realização de vistorias, implementação do subcomponente de Regularização Fundiária. BR-INTERPI-PI-237642-GO- RFQ / AQUISIÇÃO DE Component 2: Provision of VEÍCULOS AÉREOS NÃO technical assistance to Solicitação de Single Stage - One Implementaçã TRIPULADOS TIPO IBRD / 85750 Posterior Open - National 100,000.00 0.00 2021-07-05 2021-08-30 2022-02-26 strengthen the Borrower’s Cotações Envelope o Pendente MULTIROTOR, COM public management. EQUIPAMENTOS E ACESSÓRIOS PARA APOIAR O INTERPI BR-INTERPI-PI-237645-GO- Component 2: Provision of RFQ / AQUISIÇÃO DE technical assistance to Solicitação de Single Stage - One Implementaçã IBRD / 85750 Posterior Open - National 50,000.00 0.00 2021-07-05 2021-08-30 2022-02-26 EQUIPAMENTO DE PROTEÇÃO strengthen the Borrower’s Cotações Envelope o Pendente INDIVIDUAL - EPI'S public management. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-INTERPI-PI-13-NC-RFQ / Component 2: Provision of Organização de conferências technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 12,821.00 13,509.04 Assinado 2018-08-06 2018-10-01 2019-11-05 2019-03-30 (encontro de institutos de strengthen the Borrower’s Cotações Envelope terra) public management. BR-INTERPI-PI-14-NC-RFQ / Component 2: Provision of Organização de conferências technical assistance to Solicitação de Single Stage - One Implementaçã IBRD / 85750 Posterior Open - National 12,821.00 0.00 2019-08-06 2019-10-01 2020-03-29 (encontro de institutos de strengthen the Borrower’s Cotações Envelope o Pendente terra) public management. BR-INTERPI-PI-15-NC-RFQ / Component 2: Provision of Organização de conferências technical assistance to Solicitação de Single Stage - One Implementaçã IBRD / 85750 Posterior Open - National 12,821.00 0.00 2020-01-08 2020-03-04 2020-08-31 (conferência de encerramento strengthen the Borrower’s Cotações Envelope o Pendente do projeto) public management. BR-INTERPI-PI-7-NC-RFQ / Aquisição de passagens e Component 2: Provision of infraestrutura para visita de technical assistance to Solicitação de Single Stage - One estudo no institutos de terras IBRD / 85750 Posterior Limited 17,949.00 0.00 Cancelado 2018-03-12 2018-05-07 2018-11-03 strengthen the Borrower’s Cotações Envelope do Ceara, secretaria do public management. patrimônio da União e instituto de terras do Pará. BR-INTERPI-PI-16-NC-RFQ / Serviço de realização de Component 2: Provision of eventos para mobilização e technical assistance to Solicitação de Single Stage - One divulgação das ações do IBRD / 85750 Posterior Limited 51,282.00 0.00 Cancelado 2016-05-06 2016-07-01 2016-12-28 strengthen the Borrower’s Cotações Envelope INTERPI nas regiões a serem public management. regularizadas quanto a sua situação fundiária. BR-INTERPI-PI-12-NC-RFQ / Component 2: Provision of Organização de conferências technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Limited 12,821.00 0.00 Cancelado 2017-08-06 2017-10-01 2018-03-30 (encontro de institutos de strengthen the Borrower’s Cotações Envelope terra) public management. BR-INTERPI-PI-105720-NC- DIR / Taxa de inscrição de 04 (quatro) participantes na Conferência Anual do Banco Mundial sobre Terra e Component 2: Provision of Pobreza, dia 25 a 29 de março technical assistance to Implementaçã IBRD / 85750 Posterior Aquisição Direta Direct 4,000.00 0.00 2019-03-13 2019-03-18 2019-03-28 2019-09-24 de 2019, em Washington DC. strengthen the Borrower’s o Pendente 02 (dois) representantes do public management. Instituto de Terras do Piauí - INTERPI 02 (dois) representantes da CGJ Page 2 BR-INTERPI-PI-57167-NC- RFB / Contratação de empresa Component 2: Provision of especializada na prestação de technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 161,812.00 0.00 Cancelado 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 serviços de digitalização e strengthen the Borrower’s Ofertas Envelope customização de Documentos public management. do INTERPI. BR-INTERPI-PI-68114-NC- RFQ / Contratação de Component 2: Provision of empresa para prestar serviços technical assistance to Solicitação de Single Stage - One de cadastramentos e IBRD / 85750 Posterior Open - National 1,000,000.00 0.00 Cancelado 2018-07-21 2018-09-15 2019-08-01 strengthen the Borrower’s Cotações Envelope georefrenciamentos do public management. imoves por varredura em um município piloto do Cerrado BR-INTERPI-PI-126432-NC- RFQ / CONTRATAÇÃO DE EMPRESA PARA GERENCIAR A Component 2: Provision of REALIZAÇÃO DE SEIS EVENTOS technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 120,115.00 0.00 Cancelado 2019-09-30 2019-10-05 2019-11-16 2019-12-16 2020-01-20 2020-07-18 REGIONAIS DE strengthen the Borrower’s Propostas Envelope “CONFERÊNCIAS SOBRE public management. REGULARIZAÇÃO FUNDIÁRIA E AGRICULTURA FAMILIAR” BR-INTERPI-PI-258732-NC- RFP / CONTRATAÇÃO DE EMPRESA PARA GERENCIAR A Component 2: Provision of REALIZAÇÃO DO “ENCONTRO technical assistance to Solicitação de Single Stage - One Implementaçã IBRD / 85750 Posterior Open - National 100,000.00 0.00 2021-10-20 2021-10-25 2021-12-06 2022-01-05 2022-02-09 2022-08-08 DE FORMAÇÃO DE strengthen the Borrower’s Ofertas Envelope o Pendente MULTIPLICADORES public management. LIDERANÇAS QUILOMBOLAS” PARA O INTERPI CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-INTERPI-PI-5-CS-QCBS / Component 2: Provision of Seleção Baseada Contratação de consultoria technical assistance to IBRD / 85750 Posterior nas Qualificações Open - National 51,282.00 0.00 Cancelado 2018-04-01 2018-04-22 2018-06-05 2018-07-05 2018-08-09 2019-02-05 para elaborar uma estratégia strengthen the Borrower’s dos Consultores de digitalização de arquivo public management. BR-INTERPI-PI-57802-CS- INDV / Contratação de Component 2: Provision of Seleção Baseada consultoria para desenvolver technical assistance to Implementação IBRD / 85750 Posterior na Qualidade e Open - National 32,362.00 0.00 2018-08-30 2018-09-20 2018-11-03 2018-12-01 2018-12-31 2019-02-04 2019-03-11 2020-03-10 um module "intergracao strengthen the Borrower’s Pendente Custo SEMAR-INTERPI" no sistema public management. de monitoramento da SEMAR BR-INTERPI-PI-59664-CS- INDV / Contratação de Component 2: Provision of Seleção Baseada consultoria para realização de technical assistance to IBRD / 85750 Posterior nas Qualificações Open - National 113,268.61 0.00 Em Análise 2019-02-04 2019-12-27 2019-02-25 2019-04-10 2019-05-10 2019-06-14 2019-12-11 estudo Exploratório do strengthen the Borrower’s dos Consultores potencial das terras devolutas public management. do Estado do Piauí BR-INTERPI-PI-59649-CS- Component 2: Provision of INDV / Consultoria para Seleção Baseada technical assistance to elaborar e implantar um plano IBRD / 85750 Posterior nas Qualificações Open - National 97,087.38 0.00 Em Análise 2019-01-31 2021-01-13 2019-02-21 2019-04-06 2019-05-06 2019-06-10 2019-12-07 strengthen the Borrower’s de desenvolvimento dos Consultores public management. institucional do INTERPI BR-INTERPI-PI-111526-CS- Component 2: Provision of CQS / Consultoria para Seleção Baseada technical assistance to Implementação estruturar a Câmara de IBRD / 85750 Posterior nas Qualificações Open - National 11,480.00 0.00 2019-04-22 2019-05-13 2019-06-26 2019-07-26 2019-08-30 2020-02-26 strengthen the Borrower’s Pendente Resolução Consensual de dos Consultores public management. Conflitos Fundiários - CGJ/PI. BR-INTERPI-PI-126316-CS- QBS / CONTRATAÇÃO DE Component 2: Provision of CONSULTORIA PARA technical assistance to Seleção Baseada DESENVOLVIMENTO E IBRD / 85750 Posterior Open 125,000.00 0.00 Em Análise 2019-10-31 2019-10-11 2019-11-21 2020-01-04 2020-02-01 2020-03-02 2020-04-01 2020-05-06 2021-05-06 strengthen the Borrower’s na Qualidade IMPLEMENTAÇÃO DE UM public management. SISTEMA DE REGISTRO ELETRÔNICO DE TÍTULOS BR-INTERPI-PI-59667-CS- INDV / Contratação de consultoria para realizar Component 2: Provision of Seleção Baseada estudo de identificação e technical assistance to IBRD / 85750 Posterior nas Qualificações Open - National 97,087.38 0.00 Em Análise 2019-09-30 2020-04-16 2019-10-21 2019-12-04 2020-01-03 2020-02-07 2020-08-05 caracterização das strengthen the Borrower’s dos Consultores comunidades tradicionais nos public management. municípios piauienses da região do MATOPIBA BR-INTERPI-PI-155584-CS- QBS / CONTRATAÇÃO DE Component 2: Provision of CONSULTORIA PARA Seleção Baseada technical assistance to ELABORAÇÃO E CONFECÇÃO IBRD / 85750 Posterior nas Qualificações Open - National 110,000.00 0.00 Em Análise 2020-01-28 2020-04-29 2020-02-18 2020-04-02 2020-05-02 2020-06-06 2020-12-03 strengthen the Borrower’s DE MATERIAL DE dos Consultores public management. DIVULGAÇÃO DA NOVA LEI DE REGULARIZAÇÃO FUNDIÁRIA INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-INTERPI-PI-1-CS-INDV / Consultor para assessorar tecnicamente o INTERPI. Coordenar a execução da Assistência Técnica. Component 2: Provision of Aconselhar o INTERPI e os technical assistance to IBRD / 85750 Posterior Individual Open 107,692.00 0.00 Em Análise 2017-01-03 2016-11-01 2017-02-21 2017-03-14 2017-04-18 2019-10-31 Órgãos Parceiros para a strengthen the Borrower’s realização das metas do public management. Projeto. Atuar como ponto focal entre o INTERPI, o Órgãos Parceiros e o Banco Mundial Page 3 BR-INTERPI-PI-4-CS-INDV / Component 2: Provision of Contratação de consultoria technical assistance to para apoiar a criação de um IBRD / 85750 Posterior Individual Open 26,923.00 0.00 Cancelado 2017-06-01 2017-07-20 2017-08-10 2017-09-14 2018-03-13 strengthen the Borrower’s sistema de protocolo public management. eletrônico do INTERPI BR-INTERPI-PI-48376-CS- INDV / Engenheiro Agrônomo Component 2: Provision of para atividades de technical assistance to IBRD / 85750 Posterior Individual Open 55,000.00 0.00 Em Análise 2018-02-19 2017-08-03 2018-04-04 2018-04-16 2018-05-01 2019-10-30 demarcação, diagnóstico de strengthen the Borrower’s propriedades e delimitação de public management. áreas BR-INTERPI-PI-48388-CS- INDV / Cartógrafo para atividades de planejamento, orientação, coleta de dados, Component 2: Provision of representação e reprodução technical assistance to IBRD / 85750 Posterior Individual Open 55,000.00 0.00 Em Análise 2018-02-19 2017-08-03 2018-03-31 2018-04-16 2018-05-14 2019-11-11 gráfica dos imóveis rurais do strengthen the Borrower’s Estado do Piauí e análise de public management. informações para apoio ao processo de tomada de decisões BR-INTERPI-PI-48389-CS- INDV / Antropólogo para pesquisas, elaboração e Component 2: Provision of apresentação de Relatórios technical assistance to Antropológicos. Para a IBRD / 85750 Posterior Individual Open 35,780.00 0.00 Em Análise 2018-02-19 2017-08-03 2018-04-01 2018-04-22 2018-05-10 2019-11-07 strengthen the Borrower’s caracterização da identidade public management. étnica e da territorialidade das comunidades remanescentes de quilombo BR-INTERPI-PI-19-CS-INDV / Component 2: Provision of Estudo de impacto do technical assistance to IBRD / 85750 Posterior Individual Open 38,462.00 0.00 Cancelado 2020-01-03 2020-02-21 2020-03-13 2020-04-17 2020-10-14 Programa de Regularização strengthen the Borrower’s Fundiária do INTERPI (ex- public management. post) BR-INTERPI-PI-18-CS-INDV / Component 2: Provision of Estudo de impacto do technical assistance to IBRD / 85750 Posterior Individual Open 38,462.00 0.00 Cancelado 2018-03-25 2018-05-13 2018-06-03 2018-07-08 2019-01-04 Programa de Regularização strengthen the Borrower’s Fundiária do INTERPI (ex-ante) public management. BR-INTERPI-PI-20-CS-INDV / Engenheiro Agrimensor para Component 2: Provision of atividades de demarcação, technical assistance to reavivamento e reocupação de IBRD / 85750 Posterior Individual Open 55,000.00 0.00 Cancelado 2018-02-19 2018-03-24 2018-04-02 2018-05-02 2019-11-05 strengthen the Borrower’s marcos, medição e sinalização public management. de limites de porções territoriais BR-INTERPI-PI-110-CS-INDV / Contratação de consultoria Component 2: Provision of para estudo de viabilidade de technical assistance to um projeto de assentamento IBRD / 85750 Posterior Individual Open 20,513.00 0.00 Cancelado 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 strengthen the Borrower’s de agricultura familiar de alta public management. produtividade no cerrado piauiense. BR-INTERPI-PI-11-CS-INDV / Component 2: Provision of Contratação de consultoria technical assistance to para estabelecimento de uma IBRD / 85750 Posterior Individual Open 20,513.00 0.00 Cancelado 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 strengthen the Borrower’s metodologia de avaliação das public management. terras publicas no Piaui. BR-INTERPI-PI-17-CS-INDV / Component 2: Provision of Contratação de um consultor technical assistance to para estudo de proposição de IBRD / 85750 Posterior Individual Open 15,385.00 0.00 Cancelado 2016-05-01 2016-06-19 2016-07-10 2016-08-14 2017-02-10 strengthen the Borrower’s uma política de public management. reassentamento no Estado BR-INTERPI-PI-9-CS-INDV / Component 2: Provision of Consultoria para elaboração technical assistance to de estratégia organizacional IBRD / 85750 Posterior Individual Open 20,513.00 0.00 Cancelado 2017-07-01 2017-08-19 2017-09-09 2017-10-14 2018-04-12 strengthen the Borrower’s de médio e longo prazos para public management. o INTERPI. BR-INTERPI-PI-59665-CS- INDV / Contração de Component 2: Provision of consultoria para levantamento technical assistance to Em fase de da demanda potencial e IBRD / 85750 Posterior Individual Open 32,362.46 0.00 2018-11-22 2019-08-26 2019-01-10 2019-01-31 2019-03-07 2019-09-03 strengthen the Borrower’s Implementação efetiva para criação de novos public management. assentamentos rurais de pequenos produtores no Piauí BR-INTERPI-CGJ-PI-68149- Component 2: Provision of CS-INDV / Contratação de technical assistance to Implementação técnico para apoio as ações IBRD / 85750 Posterior Individual Open 77,838.00 0.00 2018-07-19 2018-09-06 2018-09-27 2018-11-01 2019-11-01 strengthen the Borrower’s Pendente de regularização (advogado) - public management. CGJ BR-INTERPI-PI-68120-CS- Component 2: Provision of INDV / Contratação de um technical assistance to Em fase de assessor técnico especializado IBRD / 85750 Posterior Individual Open 83,715.00 0.00 2018-10-29 2019-08-20 2018-12-17 2019-01-07 2019-02-11 2020-02-11 strengthen the Borrower’s Implementação - área de governaças de public management. terras (INTERPI) BR-INTERPI-CGJ-PI-68145- Component 2: Provision of CS-INDV / Contratação de technical assistance to técnico para apoio as ações IBRD / 85750 Posterior Individual Open 77,383.00 0.00 Em Análise 2018-07-19 2019-07-16 2018-09-06 2018-09-27 2018-11-01 2019-11-01 strengthen the Borrower’s de regularização (agrônomo public management. #2) - CGJ BR-INTERPI-CGJ-PI-68146- Component 2: Provision of CS-INDV / Contratação de technical assistance to IBRD / 85750 Posterior Individual Open 77,383.00 0.00 Em Análise 2018-07-19 2019-07-16 2018-09-06 2018-09-27 2018-11-01 2019-11-01 técnico para apoio as ações strengthen the Borrower’s de regularização (agrimensor public management. #1) BR-INTERPI-CGJ-PI-68147- Component 2: Provision of CS-INDV / Contratação de technical assistance to IBRD / 85750 Posterior Individual Open 77,383.00 0.00 Em Análise 2018-07-19 2019-07-16 2018-09-06 2018-09-27 2018-11-01 2019-11-01 técnico para apoio as ações strengthen the Borrower’s de regularização (agrimensor public management. #2) Page 4 BR-INTERPI-CGJ-PI-68148- Component 2: Provision of CS-INDV / Contratação de technical assistance to técnico para apoio as ações IBRD / 85750 Posterior Individual Open 51,892.00 0.00 Em Análise 2018-07-19 2019-07-16 2018-09-06 2018-09-27 2018-11-01 2019-11-01 strengthen the Borrower’s de regularização (especialista public management. geoprocessamento) - CGJ BR-INTERPI-PI-68137-CS- INDV / Contratação de Component 2: Provision of consultoria individual para technical assistance to IBRD / 85750 Posterior Individual Open 58,378.00 0.00 Cancelado 2018-11-05 2018-12-24 2019-01-14 2019-02-18 2020-02-13 área de planejamento e strengthen the Borrower’s monitoramento das atividades public management. do INTERPI BR-INTERPI-CGJ-PI-68142- Component 2: Provision of CS-INDV / Contratação de technical assistance to técnico para apoio as ações IBRD / 85750 Posterior Individual Open 77,838.00 0.00 Em Análise 2018-07-19 2019-07-16 2018-09-06 2018-09-27 2018-11-01 2019-11-01 strengthen the Borrower’s de regularização (agrônomo public management. #1) - CGJ BR-INTERPI-PI-149495-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to Em fase de IBRD / 85750 Posterior Individual Open 15,000.00 0.00 2019-12-18 2020-02-06 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s Implementação (ENGENHEIRO AGRIMENSOR public management. #1) - INTERPI BR-INTERPI-PI-149496-CS- Component 2: Provision of INDV / CONTRATAÇÃO DE technical assistance to TÉCNICO PARA APOIO ÀS IBRD / 85750 Posterior Individual Open 10,500.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s AÇÕES DE REGULARIZAÇÃO public management. (GEOMENSOR #01) - INTERPI BR-INTERPI-PI-150588-CS- INDV / CONTRATAÇÃO DE CONSULTOR INDIVIDUAL NA Component 2: Provision of ÁREA DE PROCESSAMENTO DE technical assistance to DADOS E SISTEMA DE IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s INFORMAÇÃO PARA public management. ASSESSORAMENTO TÉCNICO AO INSTITUTO DE TERRAS DO PIAUÍ (#01) BR-INTERPI-PI-150627-CS- INDV / CONTRATAÇÃO DE CONSULTOR INDIVIDUAL NA Component 2: Provision of ÁREA DE PROCESSAMENTO DE technical assistance to DADOS E SISTEMA DE IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s INFORMAÇÃO PARA public management. ASSESSORAMENTO TÉCNICO AO INSTITUTO DE TERRAS DO PIAUÍ (#02) BR-INTERPI-PI-150630-CS- INDV / CONTRATAÇÃO DE CONSULTOR INDIVIDUAL NA Component 2: Provision of ÁREA DE PROCESSAMENTO DE technical assistance to DADOS E SISTEMA DE IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s INFORMAÇÃO PARA public management. ASSESSORAMENTO TÉCNICO AO INSTITUTO DE TERRAS DO PIAUÍ (#03) BR-INTERPI-PI-150632-CS- INDV / CONTRATAÇÃO DE CONSULTOR INDIVIDUAL NA Component 2: Provision of ÁREA DE PROCESSAMENTO DE technical assistance to DADOS E SISTEMA DE IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s INFORMAÇÃO PARA public management. ASSESSORAMENTO TÉCNICO AO INSTITUTO DE TERRAS DO PIAUÍ (#04) BR-INTERPI-PI-150633-CS- INDV / CONTRATAÇÃO DE CONSULTOR INDIVIDUAL NA Component 2: Provision of ÁREA DE PROCESSAMENTO DE technical assistance to DADOS E SISTEMA DE IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s INFORMAÇÃO PARA public management. ASSESSORAMENTO TÉCNICO AO INSTITUTO DE TERRAS DO PIAUÍ (#05) BR-INTERPI-PI-150634-CS- INDV / CONTRATAÇÃO DE CONSULTOR INDIVIDUAL NA Component 2: Provision of ÁREA DE PROCESSAMENTO DE technical assistance to DADOS E SISTEMA DE IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s INFORMAÇÃO PARA public management. ASSESSORAMENTO TÉCNICO AO INSTITUTO DE TERRAS DO PIAUÍ (#06) BR-INTERPI-PI-150636-CS- INDV / CONTRATAÇÃO DE CONSULTOR INDIVIDUAL NA Component 2: Provision of ÁREA DE PROCESSAMENTO DE technical assistance to DADOS E SISTEMA DE IBRD / 85750 Posterior Individual Open 15,000.00 11,451.58 Assinado 2019-12-16 2020-02-13 2020-02-03 2020-06-24 2020-02-24 2020-07-21 2020-03-30 2020-07-21 2021-03-30 strengthen the Borrower’s INFORMAÇÃO PARA public management. ASSESSORAMENTO TÉCNICO AO INSTITUTO DE TERRAS DO PIAUÍ (#07) BR-INTERPI-PI-150637-CS- INDV / CONTRATAÇÃO DE CONSULTOR INDIVIDUAL NA Component 2: Provision of ÁREA DE PROCESSAMENTO DE technical assistance to DADOS E SISTEMA DE IBRD / 85750 Posterior Individual Open 15,000.00 11,482.92 Assinado 2019-12-16 2020-02-13 2020-02-03 2020-07-24 2020-02-24 2020-07-21 2020-03-30 2020-07-21 2021-03-30 strengthen the Borrower’s INFORMAÇÃO PARA public management. ASSESSORAMENTO TÉCNICO AO INSTITUTO DE TERRAS DO PIAUÍ (#08) Page 5 BR-INTERPI-PI-150638-CS- INDV / CONTRATAÇÃO DE CONSULTOR INDIVIDUAL NA Component 2: Provision of ÁREA DE PROCESSAMENTO DE technical assistance to DADOS E SISTEMA DE IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s INFORMAÇÃO PARA public management. ASSESSORAMENTO TÉCNICO AO INSTITUTO DE TERRAS DO PIAUÍ (#09) BR-INTERPI-PI-150641-CS- INDV / CONTRATAÇÃO DE CONSULTOR INDIVIDUAL NA Component 2: Provision of ÁREA DE PROCESSAMENTO DE technical assistance to Em fase de DADOS E SISTEMA DE IBRD / 85750 Posterior Individual Open 15,000.00 0.00 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s Implementação INFORMAÇÃO PARA public management. ASSESSORAMENTO TÉCNICO AO INSTITUTO DE TERRAS DO PIAUÍ (#10) BR-INTERPI-PI-150651-CS- Component 2: Provision of INDV / CONTRATAÇÃO DE technical assistance to TÉCNICO PARA APOIO ÀS IBRD / 85750 Posterior Individual Open 10,500.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s AÇÕES DE REGULARIZAÇÃO public management. (GEOMENSOR #02) - INTERPI BR-INTERPI-PI-150652-CS- Component 2: Provision of INDV / CONTRATAÇÃO DE technical assistance to TÉCNICO PARA APOIO ÀS IBRD / 85750 Posterior Individual Open 10,500.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s AÇÕES DE REGULARIZAÇÃO public management. (GEOMENSOR #03) - INTERPI BR-INTERPI-PI-150654-CS- Component 2: Provision of INDV / CONTRATAÇÃO DE technical assistance to TÉCNICO PARA APOIO ÀS IBRD / 85750 Posterior Individual Open 10,500.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s AÇÕES DE REGULARIZAÇÃO public management. (GEOMENSOR #04) - INTERPI BR-INTERPI-PI-150655-CS- Component 2: Provision of INDV / CONTRATAÇÃO DE technical assistance to TÉCNICO PARA APOIO ÀS IBRD / 85750 Posterior Individual Open 10,500.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s AÇÕES DE REGULARIZAÇÃO public management. (GEOMENSOR #05) - INTERPI BR-INTERPI-PI-150656-CS- Component 2: Provision of INDV / CONTRATAÇÃO DE technical assistance to Em fase de TÉCNICO PARA APOIO ÀS IBRD / 85750 Posterior Individual Open 10,500.00 0.00 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s Implementação AÇÕES DE REGULARIZAÇÃO public management. (GEOMENSOR #06) - INTERPI BR-INTERPI-PI-150657-CS- Component 2: Provision of INDV / CONTRATAÇÃO DE technical assistance to TÉCNICO PARA APOIO ÀS IBRD / 85750 Posterior Individual Open 10,500.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s AÇÕES DE REGULARIZAÇÃO public management. (GEOMENSOR #07) - INTERPI BR-INTERPI-PI-150658-CS- Component 2: Provision of INDV / CONTRATAÇÃO DE technical assistance to TÉCNICO PARA APOIO ÀS IBRD / 85750 Posterior Individual Open 10,500.00 0.00 Em Análise 2019-12-16 2020-02-13 2020-02-03 2020-02-24 2020-03-30 2021-03-30 strengthen the Borrower’s AÇÕES DE REGULARIZAÇÃO public management. (GEOMENSOR #08) - INTERPI BR-INTERPI-PI-150829-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 10,500.00 0.00 Em Análise 2019-12-17 2020-02-13 2020-02-04 2020-02-25 2020-03-31 2021-03-31 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (assistente social #1) - public management. INTERPI BR-INTERPI-PI-150830-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 10,500.00 0.00 Em Análise 2019-12-17 2020-02-13 2020-02-04 2020-02-25 2020-03-31 2021-03-31 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (assistente social #2) - public management. INTERPI BR-INTERPI-PI-150831-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 10,500.00 0.00 Em Análise 2019-12-17 2020-02-13 2020-02-04 2020-02-25 2020-03-31 2020-09-27 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (assistente social #3) - public management. INTERPI BR-INTERPI-PI-150832-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to Em fase de IBRD / 85750 Posterior Individual Open 10,500.00 0.00 2019-12-17 2020-02-13 2020-02-04 2020-02-25 2020-03-31 2021-03-31 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s Implementação (assistente social #4) - public management. INTERPI BR-INTERPI-PI-150833-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 10,500.00 0.00 Em Análise 2019-12-17 2020-02-13 2020-02-04 2020-02-25 2020-03-31 2021-03-31 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (assistente social #5) - public management. INTERPI BR-INTERPI-PI-151033-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to Em fase de IBRD / 85750 Posterior Individual Open 15,000.00 0.00 2019-12-18 2020-02-06 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s Implementação (ENGENHEIRO AGRIMENSOR public management. #2) - INTERPI BR-INTERPI-PI-151034-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to Em fase de IBRD / 85750 Posterior Individual Open 15,000.00 0.00 2019-12-18 2020-02-06 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s Implementação (ENGENHEIRO AGRIMENSOR public management. #3) - INTERPI Page 6 BR-INTERPI-PI-151035-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-06 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #4) - INTERPI BR-INTERPI-PI-151036-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #5) - INTERPI BR-INTERPI-PI-151039-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #6) - INTERPI BR-INTERPI-PI-151040-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #7) - INTERPI BR-INTERPI-PI-151041-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #8) - INTERPI BR-INTERPI-PI-151042-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #9) - INTERPI BR-INTERPI-PI-151043-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #10) - INTERPI BR-INTERPI-PI-151044-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #11) - INTERPI BR-INTERPI-PI-151045-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #12) - INTERPI BR-INTERPI-PI-151048-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #13) - INTERPI BR-INTERPI-PI-151049-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #14) - INTERPI BR-INTERPI-PI-151050-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #15) - INTERPI BR-INTERPI-PI-151051-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #16) - INTERPI BR-INTERPI-PI-151052-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #17) - INTERPI BR-INTERPI-PI-151053-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #18) - INTERPI BR-INTERPI-PI-151055-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #19) - INTERPI Page 7 BR-INTERPI-PI-151056-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2019-12-18 2020-02-13 2020-02-05 2020-02-26 2020-04-01 2021-04-01 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO AGRIMENSOR public management. #20) - INTERPI BR-INTERPI-PI-155459-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to AÇÕES DE REGULARIZAÇÃO IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2020-01-26 2020-02-13 2020-03-15 2020-04-05 2020-05-10 2021-05-10 strengthen the Borrower’s (ENGENHEIRO public management. AGRÔNOMO/CIVIL/ARQUITET O #1) - INTERPI BR-INTERPI-PI-155468-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to AÇÕES DE REGULARIZAÇÃO IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2020-01-26 2020-02-13 2020-03-15 2020-04-05 2020-05-10 2021-05-10 strengthen the Borrower’s (ENGENHEIRO public management. AGRÔNOMO/CIVIL/ARQUITET O #2) - INTERPI BR-INTERPI-PI-155469-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to AÇÕES DE REGULARIZAÇÃO IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2020-01-26 2020-02-13 2020-03-15 2020-04-05 2020-05-10 2021-05-10 strengthen the Borrower’s (ENGENHEIRO public management. AGRÔNOMO/CIVIL/ARQUITET O #3) - INTERPI BR-INTERPI-PI-155474-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to AÇÕES DE REGULARIZAÇÃO IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2020-01-26 2020-02-13 2020-03-15 2020-04-05 2020-05-10 2021-05-10 strengthen the Borrower’s (ENGENHEIRO public management. AGRÔNOMO/CIVIL/ARQUITET O #4) - INTERPI BR-INTERPI-PI-155478-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to AÇÕES DE REGULARIZAÇÃO IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2020-01-26 2020-02-13 2020-03-15 2020-04-05 2020-05-10 2021-05-10 strengthen the Borrower’s (ENGENHEIRO public management. AGRÔNOMO/CIVIL/ARQUITET O #5) - INTERPI BR-INTERPI-PI-155479-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to AÇÕES DE REGULARIZAÇÃO IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2020-01-26 2020-02-13 2020-03-15 2020-04-05 2020-05-10 2021-05-10 strengthen the Borrower’s (ENGENHEIRO public management. AGRÔNOMO/CIVIL/ARQUITET O #6) - INTERPI BR-INTERPI-PI-155480-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to AÇÕES DE REGULARIZAÇÃO IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2020-01-26 2020-02-13 2020-03-15 2020-04-05 2020-05-10 2021-05-10 strengthen the Borrower’s (ENGENHEIRO public management. AGRÔNOMO/CIVIL/ARQUITET O #7) - INTERPI BR-INTERPI-PI-155482-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to AÇÕES DE REGULARIZAÇÃO IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2020-01-26 2020-02-13 2020-03-15 2020-04-05 2020-05-10 2021-05-10 strengthen the Borrower’s (ENGENHEIRO public management. AGRÔNOMO/CIVIL/ARQUITET O #8) - INTERPI BR-INTERPI-PI-155483-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to AÇÕES DE REGULARIZAÇÃO IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2020-01-26 2020-02-13 2020-03-15 2020-04-05 2020-05-10 2021-05-10 strengthen the Borrower’s (ENGENHEIRO public management. AGRÔNOMO/CIVIL/ARQUITET O #9) - INTERPI BR-INTERPI-PI-155485-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to AÇÕES DE REGULARIZAÇÃO IBRD / 85750 Posterior Individual Open 15,000.00 0.00 Em Análise 2020-01-26 2020-02-13 2020-03-15 2020-04-05 2020-05-10 2021-05-10 strengthen the Borrower’s (ENGENHEIRO public management. AGRÔNOMO/CIVIL/ARQUITET O #10) - INTERPI BR-INTERPI-PI-210087-CS- CDS / Contratação Direta de Consultoria Individual em Component 2: Provision of Antropologia para a technical assistance to Seleção Direta de caracterização da identidade IBRD / 85750 Posterior Direct 36,000.00 0.00 Em Análise 2020-12-21 2021-01-14 2020-12-31 2021-03-06 2021-09-02 strengthen the Borrower’s Consultores étnica e da territorialidade das public management. comunidades remanescentes de quilombo, indígenas e comunidades tradicionais BR-INTERPI-PI-210577-CS- INDV / Consultoria individual especializada na área de Component 2: Provision of Direito Agrário e technical assistance to IBRD / 85750 Posterior Individual Open 25,000.00 0.00 Em Análise 2020-12-21 2021-01-19 2021-02-08 2021-03-01 2021-04-05 2022-04-05 Regularização Fundiária de strengthen the Borrower’s comunidades tradicionais, public management. indígenas e quilombolas para o INTERPI BR-INTERPI-PI-219320-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 37,300.00 0.00 Em Análise 2021-02-15 2020-02-13 2021-04-05 2021-04-26 2021-05-31 2022-05-31 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO CIVIL #11) - public management. INTERPI Page 8 BR-INTERPI-PI-219321-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 37,300.00 0.00 Em Análise 2021-02-15 2020-02-13 2021-04-05 2021-04-26 2021-05-31 2022-05-31 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO CIVIL #12) - public management. INTERPI BR-INTERPI-PI-219322-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 37,300.00 0.00 Em Análise 2021-02-15 2020-02-13 2021-04-05 2021-04-26 2021-05-31 2022-05-31 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO CIVIL #13) - public management. INTERPI BR-INTERPI-PI-219323-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of TÉCNICO PARA APOIO ÀS technical assistance to IBRD / 85750 Posterior Individual Open 37,300.00 0.00 Em Análise 2021-02-15 2020-02-13 2021-04-05 2021-04-26 2021-05-31 2022-05-31 AÇÕES DE REGULARIZAÇÃO strengthen the Borrower’s (ENGENHEIRO CIVIL #14) - public management. INTERPI BR-INTERPI-PI-248020-CS- INDV / Contratação de Consultor Individual Component 2: Provision of Antropólogo para realizar technical assistance to Implementação estudo Etnografia dos Grupos IBRD / 85750 Posterior Individual Open 13,000.00 0.00 2021-08-15 2021-10-03 2021-10-24 2021-11-28 2022-05-27 strengthen the Borrower’s Pendente Sociais e Comunidades public management. Autoidentificados Indígenas no Estado do Piauí para o INTERPI Page 9