Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan: April, 06, 2017 3. Date of General Procurement Notice: None 4. Period covered by this procurement plan: April 2017 to June 2017 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 5 High installation of plant and equipment and PPP) 2. (Goods; Information Technology & Non- 1.5 High Consulting Services) 3. Consultant Services (Firms) 0.5 High 4. Consultant Services (Individual Consultants) 0.2 High 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. 9. Renewal or extension of individual consultants contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. March 17, 2017 PROCUREMENT Uganda : Agriculture Cluster Development Project PLAN General Information Country: Uganda Banks Approval Date of the Original Procurement Plan: 2017-03-01 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-01-29 Project ID: P145037 GPN Date: Project Name: Agriculture Cluster Development Project Loan / Credit No: IDA / 56110 Executing Agency(ies): Ministry of Agriculture, Animal Industry and Fisheries WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MAAIF-30688-CW-RFB / Component 2: Preparation for Establishment of small holder Single Stage - One Pending IDA / 56110 Agricultural Water Management Prior Request for Bids Open - International 555,556.00 0.00 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 irrigation demos for Coffee (5 and Envelope Implementation Investment 15 acre models) Component 4: Project UG-MAAIF-30718-CW-RFQ / Management, Policy, Request for Single Stage - One Pending Procurement of green houses for IDA / 56110 Post Limited 38,889.00 0.00 2018-02-25 2018-04-22 2018-10-19 Regulatory, and ICT functions of Quotations Envelope Implementation Quarantine facilities MAAIF GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MAAIF-7479-GO-RFQ / Component 4: Project Procurement of Heavy Duty Management, Policy, Request for Single Stage - One Pending IDA / 56110 Post Open - National 16,667.00 0.00 2017-03-22 2017-05-17 2017-11-13 Photocopier for PCU (1) Desk Regulatory, and ICT functions of Quotations Envelope Implementation Printers (2) Colored Printer (1) MAAIF Component 4: Project UG-MAAIF-7485-GO-RFQ / Management, Policy, Request for Single Stage - One Pending Assorted Office Consumables & IDA / 56110 Post Open - National 48,000.00 0.00 2017-03-28 2017-05-23 2017-11-19 Regulatory, and ICT functions of Quotations Envelope Implementation Computer Supplies MAAIF Component 4: Project UG-MAAIF-7486-GO-RFQ / Management, Policy, Request for Single Stage - One Pending General Supplies of Goods and IDA / 56110 Post Open - National 27,778.00 0.00 2017-04-04 2017-05-30 2017-11-26 Regulatory, and ICT functions of Quotations Envelope Implementation Services MAAIF UG-MAAIF-7453-GO-RFB / Component 4: Project Procurement of Motor Vehicles Management, Policy, Single Stage - One Under Lot 1 Double Cabins (25) Lot 2 IDA / 56110 Prior Request for Bids Open - International 2,244,988.00 0.00 2017-03-15 2017-12-01 2017-03-20 2017-12-04 2017-05-01 2017-05-31 2017-07-05 2018-01-01 Regulatory, and ICT functions of Envelope Implementation Station wagons (3) Lot 3 Motor MAAIF Cycles (27) Lot 4 Saloon Cars (2) Component 4: Project UG-MAAIF-7465-GO-RFB / Management, Policy, Single Stage - One Pending Furniture and Fixtures Lot1 IDA / 56110 Post Request for Bids Open - National 490,000.00 0.00 2017-04-21 2017-04-26 2017-06-07 2017-07-07 2017-08-11 2018-02-07 Regulatory, and ICT functions of Envelope Implementation Tables Lot2 Chairs Lot 3 shelves MAAIF UG-MAAIF-30675-GO-RFB / Component 1: Support for Single Stage - One Pending Procurement and supply of farm IDA / 56110 Intensification of On-Farm Post Request for Bids Open - National 400,000.00 0.00 2018-03-28 2018-04-02 2018-05-14 2018-06-13 2018-07-18 2019-01-14 Envelope Implementation inputs for subsidy beneficiaries Production UG-MAAIF-30681-GO-RFB / Procure basic inputs (seed, Component 1: Support for fertilizers, agro-chemicals and Single Stage - One Pending IDA / 56110 Intensification of On-Farm Prior Request for Bids Open - International 3,500,000.00 0.00 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 small tools, rice tillers and Envelope Implementation Production weeders) demonstrations for 5 commodities UG-MAAIF-30693-GO-RFB / Component 2: Preparation for Single Stage - One Pending Procurement of GIS Survey IDA / 56110 Agricultural Water Management Post Request for Bids Open - National 83,333.00 0.00 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2018-12-04 Envelope Implementation equipment Investment Component 3: Market Linkages, UG-MAAIF-30700-GO-RFQ / Request for Single Stage - One Pending IDA / 56110 Post-Harvest Handling, Storage Post Limited 6,111.00 0.00 2018-01-22 2018-03-19 2018-09-15 Procurement of laptops Quotations Envelope Implementation and Value-Addition Component 4: Project UG-MAAIF-30720-GO-RFQ / Management, Policy, Request for Single Stage - One Pending Procurement of equipment for the IDA / 56110 Post Limited 13,889.00 0.00 2018-02-25 2018-04-22 2018-10-19 Regulatory, and ICT functions of Quotations Envelope Implementation mini-labs for the five pilot districts MAAIF UG-MAAIF-30721-GO-RFQ / Component 4: Project laying of an irrigation drip line for Management, Policy, Request for Single Stage - One Pending IDA / 56110 Post Limited 33,333.00 0.00 2018-02-20 2018-04-17 2018-10-14 the testing of candidate seed Regulatory, and ICT functions of Quotations Envelope Implementation varieties for release MAAIF UG-MAAIF-30773-GO-RFB / Installation and maintenance of Component 4: Project access controls, including Management, Policy, Single Stage - One Pending IDA / 56110 Post Request for Bids Open - National 208,333.00 0.00 2018-02-27 2018-03-04 2018-04-15 2018-05-15 2018-06-19 2018-12-16 survellience systems, Intrusion Regulatory, and ICT functions of Envelope Implementation detection systems as well as MAAIF firewall systems for the server UG-MAAIF-30775-GO-RFQ / Component 4: Project Procurement of GIS infrastructure Management, Policy, Request for Single Stage - One Pending including GIS software, network IDA / 56110 Post Limited 41,667.00 0.00 2018-03-04 2018-04-29 2018-10-26 Regulatory, and ICT functions of Quotations Envelope Implementation storage system and Large format MAAIF laminating NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Component 4: Project UG-MAAIF-7477-NC-DIR / Management, Policy, Pending IDA / 56110 Post Direct Selection Direct 27,778.00 0.00 2017-03-10 2017-03-15 2017-04-19 2017-10-16 Advertising in the Print Media Regulatory, and ICT functions of Implementation MAAIF Component 4: Project UG-MAAIF-7483-NC-RFQ / Management, Policy, Request for Single Stage - One Pending Repair and Maintenance of Motor IDA / 56110 Post Open - National 55,556.00 0.00 2017-03-20 2017-05-15 2017-11-11 Regulatory, and ICT functions of Quotations Envelope Implementation Vehicles/Cycles MAAIF Component 4: Project UG-MAAIF-7487-NC-RFQ / Management, Policy, Request for Single Stage - One Pending IDA / 56110 Post Open - National 20,000.00 0.00 2017-04-02 2017-05-28 2017-11-24 Insurance and Licenses Regulatory, and ICT functions of Quotations Envelope Implementation MAAIF Component 4: Project UG-MAAIF-7488-NC-RFQ / Management, Policy, Request for Single Stage - One Pending IDA / 56110 Post Open - National 5,000.00 0.00 2017-06-25 2017-08-20 2018-02-16 Engraving of Projects Assets Regulatory, and ICT functions of Quotations Envelope Implementation MAAIF Component 4: Project UG-MAAIF-12100-NC-RFQ / Management, Policy, Request for Single Stage - One Pending Provision of Printing and Binding IDA / 56110 Post Limited 102,500.00 0.00 2017-04-26 2017-06-21 2017-12-18 Regulatory, and ICT functions of Quotations Envelope Implementation services MAAIF UG-MAAIF-30672-NC-RFQ / Component 1: Support for Request for Single Stage - One Pending Printing of 100 copies for each of IDA / 56110 Intensification of On-Farm Post Limited 2,778.00 0.00 2018-06-04 2018-07-30 2019-01-26 Quotations Envelope Implementation the translated manual Production Component 1: Support for UG-MAAIF-30678-NC-RFQ / Request for Single Stage - One Pending IDA / 56110 Intensification of On-Farm Post Limited 22,222.00 0.00 2018-01-02 2018-02-27 2018-08-26 Print of training manuals (4 sets) Quotations Envelope Implementation Production UG-MAAIF-30682-NC-RFQ / Component 1: Support for Request for Single Stage - One Pending Printing of training materials for IDA / 56110 Intensification of On-Farm Post Limited 19,444.00 0.00 2018-02-25 2018-04-22 2018-10-19 Quotations Envelope Implementation agro-input dealers Production UG-MAAIF-30704-NC-RFQ / Develop, print and disseminate Component 3: Market Linkages, Request for Single Stage - One Pending guidelines on post harvest IDA / 56110 Post-Harvest Handling, Storage Post Limited 111,111.00 0.00 2018-02-20 2018-04-17 2018-10-14 Quotations Envelope Implementation handling and storage for each and Value-Addition commodity Component 4: Project UG-MAAIF-30712-NC-RFQ / Management, Policy, Request for Single Stage - One Pending Printing of ACDP publicity and IDA / 56110 Post Limited 11,111.00 0.00 2017-11-27 2018-01-22 2018-07-21 Regulatory, and ICT functions of Quotations Envelope Implementation awareness Promotional Materials MAAIF UG-MAAIF-30713-NC-RFQ / Component 4: Project Publications and media adverts Management, Policy, Request for Single Stage - One Pending IDA / 56110 Post Limited 22,222.00 0.00 2017-12-03 2018-01-28 2018-07-27 and talk shows for ACDP Regulatory, and ICT functions of Quotations Envelope Implementation awareness MAAIF UG-MAAIF-30716-NC-RFQ / Component 4: Project Printing and Dissemination of Management, Policy, Request for Single Stage - One Pending IDA / 56110 Post Limited 3,333.00 0.00 2017-11-25 2018-01-20 2018-07-19 pests information bulletins and Regulatory, and ICT functions of Quotations Envelope Implementation maps MAAIF Component 4: Project UG-MAAIF-30731-NC-RFQ / Management, Policy, Request for Single Stage - One Pending Repairs of heavy duty generators IDA / 56110 Post Limited 5,556.00 0.00 2018-02-28 2018-04-25 2018-10-22 Regulatory, and ICT functions of Quotations Envelope Implementation (seed lab and Agrchemical lab) MAAIF Component 4: Project UG-MAAIF-30739-NC-RFQ / Management, Policy, Request for Single Stage - One Pending Design and Development of the IDA / 56110 Post Limited 75,000.00 0.00 2018-02-25 2018-04-22 2018-10-19 Regulatory, and ICT functions of Quotations Envelope Implementation Agriculture Geo Portal platform MAAIF UG-MAAIF-30740-NC-RFQ / ICT systems supplies & service, Component 4: Project maintenance and licenses 1 Ms Management, Policy, Request for Single Stage - One Pending IDA / 56110 Post Limited 22,278.00 0.00 2018-03-05 2018-04-30 2018-10-27 Exchange Licence for the Regulatory, and ICT functions of Quotations Envelope Implementation exchange server and 200 user MAAIF cals UG-MAAIF-30741-NC-RFQ / Component 4: Project Supply and Installation of a Management, Policy, Request for Single Stage - One Pending IDA / 56110 Post Limited 55,556.00 0.00 2018-02-20 2018-04-17 2018-10-14 Hybrid power backup system for Regulatory, and ICT functions of Quotations Envelope Implementation MAAIF Server room MAAIF UG-MAAIF-30859-NC-RFQ / Maintenance of the various Component 4: Project functional servers Mail server, Management, Policy, Request for Single Stage - One Pending IDA / 56110 Post Limited 41,667.00 0.00 2018-03-28 2018-05-23 2018-11-19 Antivirus Server, Voice and DC Regulatory, and ICT functions of Quotations Envelope Implementation including regular upgrades of HW MAAIF & SW requirements UG-MAAIF-30860-NC-RFQ / Broadband connectivity and voice Component 4: Project subscription (1) Backup service Management, Policy, Request for Single Stage - One Pending IDA / 56110 Post Limited 13,889.00 0.00 2018-03-20 2018-05-15 2018-11-11 for the Mail server and campuses Regulatory, and ICT functions of Quotations Envelope Implementation outside the NBI infrastructure, (2) MAAIF Toll free line CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Project UG-MAAIF-8086-CS-CQS / Consultant Management, Policy, Under Consultancy to undertake ACDP IDA / 56110 Prior Qualification Open - National 179,306.00 0.00 2017-03-13 2017-04-03 2017-05-17 2017-06-16 2017-07-21 2018-01-17 Regulatory, and ICT functions of Implementation Baseline Survey Selection MAAIF Page 2 UG-MAAIF-30691-CS-CQS / Consultancy services to Component 2: Preparation for Consultant Pending establish a GIS based IDA / 56110 Agricultural Water Management Post Qualification Open - National 116,667.00 0.00 2018-02-27 2018-03-20 2018-05-03 2018-06-02 2018-07-07 2019-01-03 Implementation Agricultural Water Management Investment Selection Information System (AWMIS) UG-MAAIF-30708-CS-CQS / Component 4: Project Consultant Consultancy services to develop Management, Policy, Pending IDA / 56110 Post Qualification Open - National 166,667.00 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-04 2018-12-01 ESMPs for all project sites Regulatory, and ICT functions of Implementation Selection within the 12, 2nd phase districts MAAIF INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MAAIF-8071-CS-INDV / Component 3: Market Linkages, Consultancy to undertake Individual Consultant Under IDA / 56110 Post-Harvest Handling, Storage Post Open 41,667.00 0.00 2017-03-17 2017-04-22 2017-05-05 2017-05-26 2017-06-30 2017-12-27 Commodity Production, marktet Selection Implementation and Value-Addition & Marketing UG-MAAIF-8081-CS-INDV / Component 4: Project Process consultancy contract Management, Policy, Individual Consultant Under IDA / 56110 Post Open 23,750.00 0.00 2017-03-15 2017-04-22 2017-05-03 2017-05-24 2017-06-28 2017-12-25 management (Project Monitoring Regulatory, and ICT functions of Selection Implementation Plan) MAAIF UG-MAAIF-8158-CS-INDV / Component 1: Support for Consultant to Develop guidelines Individual Consultant Under IDA / 56110 Intensification of On-Farm Post Open 27,778.00 0.00 2017-03-15 2017-04-22 2017-05-03 2017-05-24 2017-06-28 2017-12-25 for fertilizer handling, use and Selection Implementation Production control UG-MAAIF-8160-CS-INDV / Consultancy to Assess Pesticide Component 1: Support for Individual Consultant Under Residue Analytical Lab IDA / 56110 Intensification of On-Farm Post Open 19,444.00 0.00 2017-03-24 2017-04-27 2017-05-12 2017-06-02 2017-07-07 2018-01-03 Selection Implementation (Namalere) and develop strategy Production to accredit it UG-MAAIF-8167-CS-INDV / Component 2: Preparation for Individual Consultant Under Consultancy to Develop Coffee IDA / 56110 Agricultural Water Management Post Open 55,556.00 0.00 2017-03-20 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-12-30 Selection Implementation small scale irrigation models Investment Component 4: Project UG-MAAIF-15646-CS-INDV / Management, Policy, Individual Consultant Under Recruitment of Farmer IDA / 56110 Post Open 40,000.00 0.00 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2018-03-12 Regulatory, and ICT functions of Selection Implementation Organisation Specialist MAAIF Component 4: Project UG-MAAIF-15647-CS-INDV / Management, Policy, Individual Consultant Under IDA / 56110 Post Open 40,000.00 0.00 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2018-03-12 Recruitment of Agronomist Regulatory, and ICT functions of Selection Implementation MAAIF Component 4: Project UG-MAAIF-15648-CS-INDV / Management, Policy, Individual Consultant Under IDA / 56110 Post Open 40,000.00 0.00 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2018-03-12 Recruitment of Road Engineer Regulatory, and ICT functions of Selection Implementation MAAIF Component 4: Project UG-MAAIF-15649-CS-INDV / Management, Policy, Individual Consultant Pending IDA / 56110 Post Open 40,000.00 0.00 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2018-03-12 Recruitment of Water Engineer Regulatory, and ICT functions of Selection Implementation MAAIF Component 4: Project UG-MAAIF-15650-CS-INDV / Management, Policy, Individual Consultant Under IDA / 56110 Post Open 40,000.00 0.00 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2018-03-12 Recruitment for Social Scientist Regulatory, and ICT functions of Selection Implementation MAAIF Component 4: Project UG-MAAIF-15654-CS-INDV / Management, Policy, Individual Consultant Under Recruitment of Procurement IDA / 56110 Post Open 26,667.00 0.00 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2018-03-12 Regulatory, and ICT functions of Selection Implementation Assistant MAAIF Component 4: Project UG-MAAIF-15658-CS-INDV / Management, Policy, Individual Consultant Under Recruitment of Monitoring & IDA / 56110 Post Open 26,667.00 0.00 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2018-03-12 Regulatory, and ICT functions of Selection Implementation Evaluation Assistant MAAIF Component 4: Project UG-MAAIF-15659-CS-INDV / Management, Policy, Individual Consultant Under Recruitment of Financial IDA / 56110 Post Open 26,667.00 0.00 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2018-03-12 Regulatory, and ICT functions of Selection Implementation Management Assistant MAAIF UG-MAAIF-30671-CS-INDV / Component 1: Support for Procure consultants to translate Individual Consultant Pending IDA / 56110 Intensification of On-Farm Post Open 41,667.00 0.00 2017-12-20 2018-02-07 2018-02-28 2018-04-04 2018-10-01 the E-voucher manual into six (6) Selection Implementation Production local languages UG-MAAIF-30684-CS-INDV / Consultancy services to Component 2: Preparation for Individual Consultant Pending undertake studies to determine IDA / 56110 Agricultural Water Management Post Open 55,555.00 0.00 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2018-10-10 Selection Implementation appropriate coffee irrigation Investment business models UG-MAAIF-30686-CS-INDV / Develop Business model for Component 2: Preparation for Individual Consultant Pending small holder irrigation IDA / 56110 Agricultural Water Management Post Open 27,778.00 0.00 2017-12-15 2018-02-02 2018-02-23 2018-03-30 2018-09-26 Selection Implementation interventions for the Coffee Investment production UG-MAAIF-30687-CS-INDV / Component 2: Preparation for Consultancy to design Individual Consultant Pending IDA / 56110 Agricultural Water Management Post Open 55,555.00 0.00 2017-12-22 2018-02-09 2018-03-02 2018-04-06 2018-10-03 smallholder irrigation schemes Selection Implementation Investment (coffee) UG-MAAIF-30689-CS-INDV / Component 2: Preparation for Consultancy to develop a Individual Consultant Pending IDA / 56110 Agricultural Water Management Post Open 55,555.00 0.00 2018-01-25 2018-03-15 2018-04-05 2018-05-10 2018-11-06 legal/policy framework for water Selection Implementation Investment users' groups/associations Page 3 UG-MAAIF-30690-CS-INDV / Component 2: Preparation for Consultancy to develop Individual Consultant Pending IDA / 56110 Agricultural Water Management Post Open 55,555.00 0.00 2018-03-15 2018-05-03 2018-05-24 2018-06-28 2018-12-25 performance and management Selection Implementation Investment frameworks for WUG/As UG-MAAIF-30695-CS-INDV / Component 3: Market Linkages, Consultancy to conduct Individual Consultant Pending IDA / 56110 Post-Harvest Handling, Storage Post Open 41,667.00 0.00 2018-02-16 2018-04-06 2018-04-27 2018-06-01 2018-11-28 production, Market and Selection Implementation and Value-Addition marketing surveys UG-MAAIF-30709-CS-INDV / Component 4: Project Consultancy to develop PMPs for Management, Policy, Individual Consultant Pending IDA / 56110 Post Open 69,444.00 0.00 2018-01-22 2018-03-12 2018-04-02 2018-05-07 2018-11-03 the 5 different priority Regulatory, and ICT functions of Selection Implementation commodities MAAIF UG-MAAIF-30732-CS-INDV / Component 4: Project Procure service of a consultant to Management, Policy, Individual Consultant Pending develop a detailed fertilizer IDA / 56110 Post Open 27,778.00 0.00 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2018-12-08 Regulatory, and ICT functions of Selection Implementation handling guidelines along the MAAIF value chains UG-MAAIF-44867-CS-INDV / Component 2: Preparation for Provision of Consultancy Individual Consultant Pending IDA / 56110 Agricultural Water Management Post Open 16,667.00 0.00 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 Services to Develop Agricultural Selection Implementation Investment Mechanization Strategy UG-MAAIF-44870-CS-CDS / Provision of Consultancy Component 4: Project Services to support Gender Management, Policy, Individual Consultant Pending IDA / 56110 Post Limited 12,500.00 0.00 2018-02-15 2018-02-20 2018-03-13 2018-04-17 2018-10-14 consultant for East Central Africa Regulatory, and ICT functions of Selection Implementation Agricultural Transformation MAAIF Project preparation UG-MAAIF-44894-CS-CDS / Provision of Consultancy Component 4: Project Services to develop the ECAAT Management, Policy, Individual Consultant Pending Project Environment and social IDA / 56110 Post Limited 30,000.00 0.00 2018-02-15 2018-02-20 2018-03-13 2018-04-17 2018-10-14 Regulatory, and ICT functions of Selection Implementation management Framework (ESMF) MAAIF and Pest Management Plan (PMP) UG-MAAIF-45341-CS-CDS / Component 4: Project Provision of Consultancy services Management, Policy, Individual Consultant Pending to Develop ECAAT Project IDA / 56110 Post Limited 15,000.00 0.00 2018-02-15 2018-02-20 2018-03-13 2018-04-17 2018-10-14 Regulatory, and ICT functions of Selection Implementation Resettlement Policy Framework MAAIF (RPF) UG-MAAIF-45342-CS-CDS / Component 4: Project Provision of Consultancy services Management, Policy, Individual Consultant Pending to Develop ECAAT Project IDA / 56110 Post Limited 12,500.00 0.00 2018-02-15 2018-02-20 2018-03-13 2018-04-17 2018-10-14 Regulatory, and ICT functions of Selection Implementation Vulnerable and Marginalised MAAIF Groups Framework (VMGP) Page 4