69778 v1 THAILAND — HIGHWAYS MANAGEMENT PROJECT P075173 LOAN NO.4721-TH Restructuring Paper 1. Proceeds for Thailand -- Highways Management Project, Loan No. 4721-TH, P075173 will be reallocated as follow: Category of Current Disbursed and Undisbursed Request Proposed Percentage Expenditure Allocation Documented Balance Increase/ Final of (in US$) (in US$) (in US$) Decrease Allocation Financing (in US$) Current (No change) Works 79,620,000 79,178,717 441,283 (441,283) 79,178,717 55% Consultants’ 4,670,000 4,668,651 1,350 441,283 5,111,283 92% Services Total 84,290,000 83,847,368 442,633 0 84,290,000 2. The project implementation progress for activities under Loan 4721-TH is near completion, the project is rated unsatisfactory due to slow procurement process for activities under the additional financing (Loan 7775-TH). All civil works have been completed with the remaining fund of US$441,283 under this category. All periodic maintenance works were completed by September 2011 and the International Procurement Consultant (IPC) has been hired since March 9, 2011. The only remaining activity is Consultancy for the Design of Performance-Based Contracts (PBC), estimated at US$350,000. 3. The proposed reallocation is necessary to complete the remaining consultants’ services per client’s request.