FEDERAL REPUBLIC OF NIGERIA Nigeria Erosion and Watershed Management Project (NEWMAP) PROCUREMENT PLAN I. GENERAL 1. Project information: Country: Nigeria Borrower: Federal Government of Nigeria Project Name: Nigeria Erosion and Watershed Management Project-(NEWMAP) Loan / Credit No.: PIA: National NEWMAP Coordinating Unit. 2. Bank’s approval Date of the procurement Plan: March, 2012 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments (US$ equivalent) 1. ICB and LIB (Goods and services other > 750,000.00 ALL than consultancy services) 2. NCB 50,000.00 ≤ 750,000.00 NONE 3. ICB (Works) > 5,000,000.00 ALL 4. NCB (Works) 200,000 ≤ 5,000,000.00 NONE 5 Shopping-Goods < 50,000.00 NONE 6 Shopping-Works < 100,000.00 NONE 7 Training, Workshops, Study Tours All Values Based on Annual Work Plans & Budgets 2. Prequalification. Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Shall apply 4. Reference to (if any) Project Operational/Procurement Manual: shall apply 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages with Methods and Time Schedule Procurement of Goods : 1 2 3 4 5 6 7 8 9 Re Contract Estimate Procure Prequalificati Domestic Review Expected Comments f. (Description) d ment on (yes/no) Preference by Bank Bid- No Cost Method (yes/no) (Prior / Post) Opening . US$’000 Date 1 Computer Systems, Office, software and Accessories Computers and 684 NCB NO NO POST June 7, Procureme Accessories, software (see 2012 nt by each remark of the 7 packages, Photo- Colum) SPMU & copiers, UPS, Printers FPMU is and Scanners, Fax estimated Machines, Laptops, at ( USD Stationeries, 85.5) Consumables, LAN, Telephony,Lasers Software Licenses and Application,. 2 Office Furniture’s and Equipment Computer workstations 680 NCB NO NO PRIOR June 7, Procureme and Office Furniture (see 2012 nt by each remark of the 7 Water Dispenser, Colum) SPMU & Refrigerators, FPMU is Airconditioners, estimated Tables, Chairs, etc at ( USD 85) 3 Operational Vehicles 4-WD Vehicles (32 1440 NCB NO NO PRIOR June 7, Procureme units) (see 2012 nt by each remark of the 7 Colum) SPMU & FPMU is estimated at (180USD 4 Generator 40KVA Sound-Proof 240 NS NO NO PRIOR June 7, Procureme Electricity Generating (see 2012 nt by each Set-Purchase and remark of the 7 Installation (8 units) Colum) SPMU & FPMU is estimated at (30 USD 5 Training Communication, Presentation, Media Equipment and materials, etc Multimedia 364 NS NO NO PRIOR June 7, Procureme Projectors, (see 2012 nt by each remark of the 7 Flip Chart Stands, Colum) SPMU & Boards, GSM FPMU is TV/Video/Radio/Reco estimated rders and Digital at (45.5 Cameras, Internet USD Facilities, GPS, Raincoats and Enumerators bags, Program information kit, Program posters Community oriented Implementation manual 6 Field Equipment Purchase of Weather 2,400 NCB NO NO PRIOR June 7, Procureme Monitoring Stations, (see 2012 nt by each GPSs, Laser Measures, remark of the 7 Measuring Wheels, 1- Colum) SPMU & 2km Range Radios and FPMU is other survey equipment estimated and tools to gauge and at (300 trace watershed, USD terrestrial carbon and water flow 7 Geographic Information System Purchase of GIS 3520 NCB NO NO PRIOR June 7, Procureme data/Satellite Imagery,, (see 2012 nt by each Overhead photography, remark of the 7 etc Colum) SPMU & FPMU is estimated at (440 USD Sub Total 9,328.00 Procurement of Civil Works 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procure Prequalificati Domestic Review Expected Comments No. (Description) Cost ment on (yes/no) Preference by Bank Bid- US$’000 Method (yes/no) (Prior / Post) Opening Date 1 Civil works, and 252,000.00 ICB NO YES PRIOR October Procureme maintenance of flood 12, 2012 nt by ICB and gully erosion sites for all 7 SPMU 2 Office accommodation 240,000 NS NO NO PRIOR July, 2012 for 7 SPMU & FPCU SUB TOTAL 252,240.00 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1 Consultant Services-QCBS- All Values ALL International 2 Consultant Services-QCBS-National > 200,000.00 ALL 3 Consultant Services-CQS < 200,000.00 NONE 4 Consultant Services-lC > 50,000.00 ALL 5 Consultant Services-lC < 50,000.00 ToR only but ALL 6 Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref. Description of Assignment Estimated Selection Review Expected Comments No. Method by Bank Proposals Cost. (Prior / Submission US$’000 Post) Date 1 Consultancy for the detailed 3,395.24 QCBS Prior On-going Consultancy for Engineering designs and data (see remark Priority sites collation for 35 sites Colum by each of the 7 SPMU (see each State Proc. Plan). 2 Consultancy for the supervision 6,824.47 QCBS Prior September Consultancy for of Civil Works for 35sites (see remark 2012 Priority sites Colum by each of the 7 SPMU (see each State Proc. Plan). 3 Consultancy for the RAP study 875.00 IC Prior On-going Consultancy for for 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at (25 USD. 4 Consultancy for the ESIA study 875.00 IC Prior On-going Consultancy for for 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at (25 USD. 5 Consultancy for the Socio- 875.00 IC Prior On-going Consultancy for Economic study 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at 25 USD per site 6 Consultancy for GIS data 875.00 IC Prior On-going Consultancy for collection and Mapping for 35 (see remark Priority sites sites Colum by each of the 7 SPMU is estimated at 75 USD per site 7 Consultancy for the detailed 3500.00 QCBS Prior August, 2012 Consultancy for Engineering designs and data (see remark 5 additional collation for additional 35sites Colum sites by each of the 7 SPMU is estimated at 100 USD per site 8 Consultancy for the detailed 2625.00 QCBS Prior June, 2013 Consultancy for ESIA, RAP and Socio (see remark 5 additional Economic Studies for Colum sites by each of additional 35 sites the 7 SPMU is estimated at 75 USD per site 9 Environmental engineering and 800 QCBS 9 design consultancy, 10 Procurement consultancy for 800 QCBS 10 June 1012 support of FPMU and SPMUs 11 M&E consultancy 400 QCBS 11 12 Consultancy for the support of 800.00 QCBS 12 Sept., 2012 Consultancy by SPMUs and FPMU (see remark each of the 7 Colum SPMU & FPMU is estimated at (100 USD 13 Consultancy for Legal Services 800.00 IC 13 Sept., 2012 Consultancy by each of the 7 (see remark SPMU & Colum FPMU is estimated at (100 USD 14 Consultancy for valuation and 3500.00 14 Sept., 2012 Consultancy by resettlement implementation (see remark each of the 7 Colum SPMU, to cover all sites is estimated at (500 USD per SPMU 15 Consultancy for Training and 1600.00 QCBS Prior August, 2012 Consultancy by Capacity Building (see remark each of the 7 Colum SPMU & FPMU is estimated at (200 USD 16 Consultancy-External Auditor 400.00 QCBS Prior March, 2013 Consultancy by (see remark FPMU to cover Colum each SPMU 17 Consultancy on Community 800.00 IC Prior Sept., 2012 Consultancy by consultation, Public Education (see remark each of the 7 and Erosion Management and Colum SPMU & awareness Techniques, FPMU is estimated at (100 USD Sub Total 27,744.71 IV. Implementing Agency Capacity Building Activities with Time Schedule 1. In this section the agreed Capacity Building Activities are listed with time schedule below; No. Expected outcome / Estimated Estimated Start Date Com Activity Description Cost US$ Duration m ‘000 e n t s A. TRAINING 1 3. Nos. Training courses for August 2012 Capacity Building PMU staff; Project activities for each Coordinator, Procurement of the 7 SPMU & Specialist, and financial mgt, FPMU is estimated at (90 USD M&E, Environmental specialists, Communication, Livelihood, Engineering 720.00(see 2WKS, specialists remark Colum each 2 Training of project finance August 2012 Capacity Building staff(FMS, APA, FO, IA) on 160.00(see activities for each flexible accounting software remark Colum 1wk of the 7 SPMU & FPMU is estimated at (20 USD B. WORKSHOP 3 September Capacity Building 2012 activities for each of the 7 SPMU & Capacity Building for key 240.00(see FPMU is estimated stakeholders remark Colum 3 days at (30 USD 4 September, Capacity Building 2012 activities for each of the 7 SPMU & 160(see FPMU is estimated ICT Training remark Colum 1 wk at (20 USD 5 Various Capacity Building activities for each Professional of the 7 SPMU & Seminars/Workshops/ 120.00(see FPMU is estimated subscriptions remark Colum Various at (15 USD 6 September Capacity Building 2 Days Sensitization/ activities for each 2012 Workshop for State and Local of the 7 SPMU & Govt. Officials on erosion and 200.00(see FPMU is estimated watershed management remark Colum 2 days at (25 USD 7 October Capacity Building 3 Day workshop for Line activities for each 2012 Ministries and MDAs on of the 7 SPMU & addressing and prevention of 240.00(see FPMU is estimated Land Degradation remark Colum 3- days at (30 USD 8 3 Day workshop for local October Capacity Building Govt. Focal Persons and 2012 activities for each Community Erosion watch of the 7 SPMU & Dogs on prevention of erosion FPMU is estimated 240.00(see at (30 USD and land degradation remark Colum 3-days 9 2013 Capacity Building activities for each Capacity Building on use of of the 7 SPMU & Metrological and GPS 200.00(see FPMU is estimated Equipment remark Colum 5-days at (25 USD C. STUDY/TOURS 10 240.00(see Various October Capacity Building remark Colum times 2012 activities for each Baseline survey/ Community of the 7 SPMU & needs assessment and capacity FPMU is estimated building at (30 USD 11 240.00(see Various August, Capacity Building remark Colum times 2012 activities for each Sensitization/ Awareness of the 7 SPMU & creation of NEWMAP in the FPMU is estimated 18 LGA at (30 USD 12 160.00(see WB and Capacity Building remark Colum FAO to activities for each Participation in watershed of the 7 SPMU & determine studies organized by the world FPMU is estimated bank and FAO at (20 USD 13 240.00(see Various December, Capacity Building remark Colum 2012 activities for each of the 7 SPMU & Launching of ESIA and RAP FPMU is estimated for priority sites at (30 USD 14 160.00(see Various Oct., 2012 Capacity Building remark Colum activities for each of the 7 SPMU & FPMU is estimated livelihood studies at (20 USD 15 160.00(see Various World Bank Capacity Building Participation in remark Colum activities for each determined Biodiversity/forest carbon of the 7 SPMU & study organized by the World FPMU is estimated Bank at (20 USD 16 120.00(see 4-days each July 2012 Capacity Building remark Colum activities for each Recognizance survey of of the 7 SPMU & Project sites (Erosion and FPMU is estimated Watershed) at (15 USD 17 2480.00(see 4-wks February., Capacity Building remark Colum 2013 activities for each of the 7 SPMU & International Training and FPMU is estimated study tours at (310 USD 18 Various World Bank Capacity Building determined activities for each Attendance of World Bank of the 7 SPMU & Organized training, meetings, 800.00(see FPMU is estimated seminar and workshops remark Colum at (100 USD Sub Total 6,880.00 PROCUREMENT Nigeria : Nigeria Erosion and Watershed Management Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2017-07-14 2019-03-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P124905 GPN Date: Project Name: Nigeria Erosion and Watershed Management Project Loan / Credit No: IDA / 51050, IDA / 62770 Executing Agency(ies): NEWMAP - Federal Projects Management Unit WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NEWMAP-FPMU-78533- CW-RFB / Rehabilitation and Pending Single Stage - One development of underground IDA / 51050 Post Request for Bids Open - National 0.00 Implementati 2019-03-12 2019-03-17 2019-04-28 2019-05-28 2019-07-02 2019-12-29 Envelope water monitoring systems on (including instrumentation) NG-NEWMAP-FPMU-102206- Pending Request for Single Stage - One CW-RFQ / Renovation of IDA / 51050 Post Limited 0.00 Implementati 2019-04-02 2019-05-28 2019-11-24 Quotations Envelope New and Old Offices on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NEWMAP-FPMU-19535- Pending GO-RFB / Procurement of Single Stage - One IDA / 51050 Post Request for Bids Open - National 0.00 Implementati 2017-07-19 2017-07-24 2017-09-04 2017-10-04 2017-11-08 2018-05-07 ICT Equipments and Envelope on Internet Provision. NG-NEWMAP-FPMU-19584- GO-RFQ / Production of Pending IEC Materials & Newsletters Request for Single Stage - One IDA / 51050 Post Open - National 0.00 Implementati 2017-07-30 2017-09-24 2018-03-23 on Activities of NEWMAP Quotations Envelope on (for Awareness Raising and Advocacy purposes) NG-NEWMAP-FPMU-19572- GO-RFB / Procurement of Pending Single Stage - One statistical and analytical IDA / 51050 Post Request for Bids Open - National 0.00 Implementati 2017-08-07 2017-08-12 2017-09-23 2017-10-23 2017-11-27 2018-05-26 Envelope software tools and equipment on for DPRS of the FMEnv NG-NEWMAP-FPMU-19537- Single Stage - One GO-RFB / Upscaling of IDA / 51050 Post Request for Bids Open - National 0.00 Canceled 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 Envelope National EA Portal NG-NEWMAP-FPMU-19516- GO-RFB / Operationalisation Single Stage - One of National Climate Change IDA / 51050 Post Request for Bids Open - National 0.00 Canceled 2017-08-16 2017-08-21 2017-10-02 2017-11-01 2017-12-06 2018-06-04 Envelope GHG Data Management System- Page 1 NG-NEWMAP-FPMU-19527- Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / 51050 Post Open - National 0.00 Implementati 2017-07-22 2017-09-16 2018-03-15 ICT equipment for GEF Quotations Envelope on desk office NG-NEWMAP-FPMU-83102- GO-RFQ / Stationaries, File Pending Request for Single Stage - One Jackets, Folders & Branded IDA / 51050 Post Limited 0.00 Implementati 2019-01-28 2019-03-25 2019-09-21 Quotations Envelope Notepads,Green Bond on Secretariat. NG-NEWMAP-FPMU-83087- Pending GO-RFQ / Support to Request for Single Stage - One IDA / 51050 Post Limited 0.00 Implementati 2019-02-15 2019-04-12 2019-10-09 Steering committee (FMenv), Quotations Envelope on Procurement of 2No. SUVs NG-NEWMAP-FPMU-83059- Pending Request for Single Stage - One GO-RFQ / Nigeria's Green IDA / 62770 Post Limited 0.00 Implementati 2019-02-17 2019-04-14 2019-10-11 Quotations Envelope Bond Story on NG-NEWMAP-FPMU-83090- Pending Request for Single Stage - One GO-RFQ / Prospectus Green IDA / 51050 Post Limited 0.00 Implementati 2019-01-26 2019-03-23 2019-09-19 Quotations Envelope Bond Second Issuance. on NG-NEWMAP-FPMU-83085- GO-RFQ / Procurement of 1 Pending Request for Single Stage - One No. 16 Seater Bus for Green IDA / 51050 Post Limited 0.00 Implementati 2019-02-02 2019-03-30 2019-09-26 Quotations Envelope Bond Monitoring & on verification of Projects. NG-NEWMAP-FPMU-83091- Pending GO-RFQ / Green Bond Request for Single Stage - One IDA / 51050 Post Limited 0.00 Implementati 2019-02-23 2019-04-20 2019-10-17 Manual Green Bond Second Quotations Envelope on Issuance. NG-NEWMAP-FPMU-83060- Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / 51050 Post Limited 0.00 Implementati 2019-02-02 2019-03-30 2019-09-26 2No. 4x4wd Pick Up Van Quotations Envelope on for FPMU NG-NEWMAP-FPMU-83113- Pending GO-RFQ / Facts behind the Request for Single Stage - One IDA / 51050 Post Limited 0.00 Implementati 2019-04-24 2019-06-19 2019-12-16 figures Green Bond Second Quotations Envelope on Issuance. NG-NEWMAP-FPMU-83066- GO-RFQ / Procurement of 3 Pending Request for Single Stage - One No. professional Still IDA / 51050 Post Limited 0.00 Implementati 2019-03-04 2019-04-29 2019-10-26 Quotations Envelope cameras with high resolution on for Green Bond Secretariat. NG-NEWMAP-FPMU-102202- GO-RFQ / Production of Pending Request for Single Stage - One guidance manual  for IDA / 51050 Post Limited 0.00 Implementati 2019-04-14 2019-06-09 2019-12-06 Quotations Envelope Climate Change response  on Agenda NG-NEWMAP-FPMU-102207- Pending Request for Single Stage - One GO-RFQ / Office Equipment IDA / 51050 Post Limited 0.00 Implementati 2019-03-05 2019-04-30 2019-10-27 Quotations Envelope and Furniture on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 NG-NEWMAP-FPMU-19582- NC-RFB / Consultancy Single Stage - One IDA / 51050 Post Request for Bids Open - National 304,222.46 Signed 2017-07-03 2017-07-08 2017-08-19 2017-09-18 2017-10-23 2018-04-21 Services for EA Archiival Envelope Digital cataloguing NG-NEWMAP-FPMU-19575- NC-RFB / Bathymetry & Pending Open - Single Stage - One Geomorphological Study of IDA / 51050 Prior Request for Bids 0.00 Implementati 2017-07-03 2017-07-08 2017-08-19 2017-09-18 2017-10-23 2018-04-21 International Envelope the River Benue System & on Kiridam NG-NEWMAP-FPMU-102204- NC-RFQ / Engagement of a Pending Request for Single Stage - One service provider for the IDA / 51050 Post Limited 0.00 Implementati 2019-04-03 2019-05-29 2019-11-25 Quotations Envelope maintenance of Project on Vehicles CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NEWMAP-FPMU-19512- CS-QCBS / Extension of Quality And Cost- Open - Pending IDA / 51050 Prior 0.00 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 Procurement Consultancy Based Selection International Implementation Firm NG-NEWMAP-FPMU-19539- CS-QCBS / Federal Quality Control and Engineering Design Firm (FQCEDF)- EXTENSION- for additional Quality And Cost- Open - Pending IDA / 51050 Prior 0.00 2017-07-03 2017-07-24 2017-09-06 2017-10-04 2017-11-03 2017-12-08 2018-01-12 2019-01-12 area for the aerial Based Selection International Implementation photography/survey of erosion sites Including capacity building and GIS software, archiving system. NG-NEWMAP-FPMU-19567- CS-QCBS / Consulting services for the development of framework for the Quality And Cost- Open - adoption of LPG as Low IDA / 51050 Prior 3,011,027.28 Under Review 2017-02-06 2017-02-27 2017-04-12 2017-05-10 2017-06-09 2017-07-14 2017-08-18 2018-08-18 Based Selection International Carbon Alternative to Firewood and Kerosene and Supervision of the Implementation. NG-NEWMAP-FPMU-19578- CS-QCBS / Federal quality control and engineering Quality And Cost- Open - IDA / 51050 Prior 0.00 Under Review 2017-07-17 2017-08-07 2017-09-20 2017-10-18 2017-11-17 2017-12-22 2018-01-26 2019-01-26 design firm of erosion Based Selection International control sites Old and New States. NG-NEWMAP-FPMU-19589- CS-QCBS / Procurement of Quality And Cost- Open - IDA / 51050 Prior 0.00 Under Review 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 Procurement firm in Old Based Selection International and New States. NG-NEWMAP-FPMU-19580- CS-QCBS / Spatial Baseline Modelling of Electricity Infrastructure for Remote Quality And Cost- Open - IDA / 51050 Prior 0.00 Canceled 2017-07-26 2017-08-16 2017-09-29 2017-10-27 2017-11-26 2017-12-31 2018-02-04 2019-02-04 and Off-Grid Power Supply Based Selection International and Demonstration Projects on Low Carbon Off-Grid/mini- grid options Page 3 NG-NEWMAP-FPMU-19586- CS-CQS / Technology Needs Consultant Assessment for Climate IDA / 51050 Post Qualification Open - National 0.00 Canceled 2017-07-22 2017-08-12 2017-09-25 2017-10-25 2017-11-29 2018-05-28 Change in Nigeria Towards Selection low Carbon Development NG-NEWMAP-FPMU-19533- Consultant CS-CQS / Development of IDA / 51050 Post Qualification Open - National 0.00 Canceled 2017-07-22 2017-08-12 2017-09-25 2017-10-25 2017-11-29 2018-05-28 Climate Smart Agriculture. Selection NG-NEWMAP-FPMU-19585- CS-CQS / Procurement of Consultant Consultant for the Spatial IDA / 51050 Post Qualification Open - National 0.00 Canceled 2017-08-21 2017-09-11 2017-10-25 2017-11-24 2017-12-29 2018-06-27 Knowledge Information Selection System on Erosion and Watershed NG-NEWMAP-FPMU-19561- Quality And Cost- Open - CS-QCBS / Engagement of IDA / 51050 Prior 0.00 Canceled 2017-03-20 2017-04-10 2017-05-24 2017-06-21 2017-07-21 2017-08-25 2017-09-29 2018-09-29 Based Selection International IUCN NG-NEWMAP-FPMU-19530- CS-QCBS / Vulnerability Quality And Cost- Open - IDA / 51050 Prior 0.00 Canceled 2017-09-04 2017-09-25 2017-11-08 2017-12-06 2018-01-05 2018-02-09 2018-03-16 2019-03-16 Mapping and Action Plan for Based Selection International Nigeria. NG-NEWMAP-FPMU-83088- CS-QCBS / Strategy Development for the Quality And Cost- Open - Pending Commercialization of 50 Nos. IDA / 51050 Prior 0.00 2019-03-20 2019-04-10 2019-05-24 2019-06-21 2019-07-21 2019-08-25 2019-09-29 2020-09-28 Based Selection International Implementation Flared Associated Gas Sites in Crude Oil Exploration in Nigeria NG-NEWMAP-FPMU-83063- CS-QCBS / Project Management Consultancy provide technical and administrative support to the FPMU NEWMAP in the Quality And Cost- Open - Pending IDA / 51050 Prior 0.00 2019-02-27 2019-03-20 2019-05-03 2019-05-31 2019-06-30 2019-08-04 2019-09-08 2020-09-07 areas of Erosion and Based Selection International Implementation Watershed Management Investments, Erosion and Watershed Management Institution and Information Services, NG-NEWMAP-FPMU-100131- CS-QCBS / Procurement of Quality And Cost- Open - Pending an Umbrella NGO for the IDA / 51050 Prior 0.00 2019-02-14 2019-03-07 2019-04-20 2019-05-18 2019-06-17 2019-07-22 2019-08-26 2020-08-25 Based Selection International Implementation Old and New States of NEWMAP NG-NEWMAP-FPMU-95582- Consultant CS-CDS / Engagement of Pending IDA / 51050 Post Qualification Open - National 0.00 2019-02-15 2019-03-08 2019-04-21 2019-05-21 2019-06-25 2019-12-22 Financial Adviser Green Implementation Selection Bond Second Issuance. NG-NEWMAP-FPMU-98274- Consultant Pending CS-CDS / Legal Adviser IDA / 51050 Prior Qualification Open - National 0.00 2019-02-15 2019-03-08 2019-04-21 2019-05-21 2019-06-25 2019-12-22 Implementation Green Bond Second Issuance. Selection NG-NEWMAP-FPMU-102200- Consultant CS-CQS / Inventorisation of Pending IDA / 51050 Post Qualification Open - National 0.00 2019-03-21 2019-04-11 2019-05-25 2019-06-24 2019-07-29 2020-01-25 GHG emissions of NEWMAP Implementation Selection intervention sites . Page 4 NG-NEWMAP-FPMU-102203- CS-QCBS / Engagement of Quality And Cost- Pending IDA / 51050 Prior Open - National 0.00 2019-04-15 2019-05-06 2019-06-19 2019-07-17 2019-08-16 2019-09-20 2019-10-25 2020-10-24 Firm for Green Bond Third Based Selection Implementation Issuance NG-NEWMAP-FPMU-102209- CS-QCBS / Consultancy services for the Study of the Quality And Cost- Open - Pending adoption of gas based (CNG IDA / 51050 Prior 0.00 2019-05-29 2019-06-19 2019-08-02 2019-08-30 2019-09-29 2019-11-03 2019-12-08 2020-12-07 Based Selection International Implementation and LPG) fuels in road transportation and carbon capture sequenstration. NG-NEWMAP-FPMU-19531- CS-QCBS / Engagement of Quality And Cost- Open - IDA / 51050 Prior 0.00 Canceled 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 an Umbrella NGO in Old Based Selection International and New States. INDIVIDUAL CONSULTANTS Page 5