Procurement Plan I. General 1. Project Information: Nigeria: Ibadan Urban Flood Management Project 2. Bank’s approval Date of the Procurement Plan: May 2014 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement Procurement Method Method Prior Review Threshold Threshold USD 1. ICB (Goods and Non- Equal to and All consulting services) above 5,000,000 2. NCB (Goods and Non- Below 5,000,000 Equal to or Consulting Services) above USD700,000 3. Shopping (Goods) Below 100,000 None Shopping (Vehicles) - Below 500,000 None Quotations shall be from 1st line vehicle distributors 4. ICB (Works) Above 20,000,000 All 5. NCB (Works) Below 20,000,000 Equal to or above USD5,000,000 6. Shopping (Works) Below 200,000 None 2. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 3. Procurement Packages with Methods and Time Schedule 1 2 3 4 5 6 7 Re Description Estimat Procure Domes Revie Comme f. ed ment tic w nts No Cost Method Prefer by . US$ ence Bank million (yes/n (Prior o) / Post) 00 Urban 17.4 ICB No Prior 1 Drainage Infrastructure Improvement at priority sites 00 Eleyele Dam 3.5 NCB No Prior This will 2 Safety Works be prior reviewed because of the sensitive nature of the package. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Method Prior Review Threshold (USD) Threshold (USD) 1. Competitive Methods Equal to or above All (Firms); QCBS, QBS, LCS, 300,000 FCS 2. Consultant Qualification Below 300,000 None 3. Single Source Selection N/A All (Firms & Individual) 4. Individual N/A Above 100,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimat Selecti Review Comments No. Assignment ed on by Bank Cost Metho (Prior / US$ d Post) 001 Engineering designs 2.0 QCBS Prior and construction supervision for works at priority sites 002 Engineering design 0.5 SSS Prior Due to the and construction unsafe supervision for condition of Eleyele dam safety the dam, works single source selection will be used to fast track the design and the bidding process for the works. 003 Ibadan integrated 3.5 QCBS Prior flood risk management master plan 004 Ibadan integrated 1.5 QCBS Prior physical master plan 005 Ibadan solid waste 1.5 QCBS Prior management master plan 006 Project management 4.0 QCBS Prior consultancy in support of PIU in areas of fiduciary, safeguards and technical 007 Preparation of ESIA 0.15 CQS Post 008 Preparation of RAP 0.15 CQS Post PROCUREMENT Nigeria : Ibadan Urban Flood Management Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2017-04-07 2021-08-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P130840 GPN Date: Project Name: Ibadan Urban Flood Management Project Loan / Credit No: IDA / 55100 IBADAN FLOOD MANAGEMENT PROJECT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-IUFMP-11114-CW-RFB / Component 2: Flood Risk Single Stage - One 12,000,000.0 10,811,401. 2018-01- IDA / 55100 Prior Request for Bids Open - International Signed 2017-01-31 2017-04-09 2017-04-09 2017-04-11 2017-05-21 2017-06-06 2017-06-20 2018-02-20 2017-07-25 2018-03-20 Eleyele Dam Safety Works Reduction Envelope 0 17 21 NG-IUFMP-11148-CW-RFB / Component 3: Project Pending Single Stage - One 2018-06- Renovation of Project Office IDA / 55100 Administration and Post Request for Bids Open - National 620,000.00 0.00 Implementat 2017-02-02 2017-02-07 2017-04-06 2017-05-06 2017-06-10 Envelope 10 Accomodation Management ion NG-IUFMP-11154-CW-RFB / Construction Works at Ten Component 2: Flood Risk Single Stage - One 21,000,000.0 17,794,267. 2018-02- IDA / 55100 Prior Request for Bids Open - International Signed 2017-04-28 2017-06-27 2017-05-03 2017-07-14 2017-06-14 2017-07-14 2018-04-23 2017-08-18 2018-05-31 (10) + Two (2) + One (1) Reduction Envelope 0 50 14 Priority Sites NG-IUFMP-11125-CW-RFB / Component 1: Flood Risk Pending Construction Works for Single Stage - One 2018-05- IDA / 55100 Identification, Prevention and Post Request for Bids Open - National 5,600,000.00 0.00 Implementat 2017-08-08 2017-08-13 2017-09-24 2017-10-24 2017-11-28 Extended Roads at 4 Priority Envelope 27 Preparedness ion Sites NG-IUFMP-11110-CW-RFQ / Component 1: Flood Risk Pending Request for Single Stage - One 2017-10- Dredging of Rivers and IDA / 55100 Identification, Prevention and Post Open - National 1,000,000.00 0.00 Implementat 2017-03-06 2017-05-01 Quotations Envelope 28 Streams Preparedness ion NG-IUFMP-11153-CW-RFB / Construction Works at Second Pending Component 2: Flood Risk Single Stage - One 30,000,000.0 2018-07- pool of Priority Sites as IDA / 55100 Prior Request for Bids Open - International 0.00 Implementat 2017-10-04 2017-10-09 2017-11-20 2017-12-20 2018-01-24 Reduction Envelope 0 23 Identified by Drainage ion Management NG-IUFMP-11155-CW-RFB / Component 1: Flood Risk Pending Urban Drainage Infrastructure Single Stage - One 2017-07- IDA / 55100 Identification, Prevention and Post Request for Bids Open - National 4,900,000.00 0.00 Implementat 2015-04-20 2015-04-25 2015-06-06 2015-07-06 2015-08-10 Improvements at four (4) Envelope 31 Preparedness ion Priority Sites NG-IUFMP-64349-CW-RFB / Construction Works at First Component 2: Flood Risk Single Stage - One 40,000,000.0 29,744,501. 2019-02- pool of Priority Sites as IDA / 55100 Prior Request for Bids Open - International Signed 2018-05-05 2018-12-18 2018-05-10 2019-01-23 2018-06-21 2019-03-20 2018-07-21 2020-04-01 2018-08-25 2020-05-29 Reduction Envelope 0 34 21 Identified by Drainage Master Plan NG-IUFMP-70359-CW-RFQ / Pending Dredging of Rivers/Streams Component 2: Flood Risk Request for Single Stage - One 2018-11- IDA / 55100 Post Open - National 1,700,000.00 0.00 Implementat 2018-04-04 2018-05-30 and Clearing of Blocked Reduction Quotations Envelope 26 ion Drains NG-IUFMP-70333-CW-RFQ / Pending Component 2: Flood Risk Request for Single Stage - One 2018-10- Rehabilitation of Consultant's IDA / 55100 Post Open - National 30,000.00 0.00 Implementat 2018-03-06 2018-05-01 Reduction Quotations Envelope 28 Office at Eleyele Dam Site ion NG-IUFMP-100563-CW-RFB Pending / 2019 Dredging of Component 2: Flood Risk Single Stage - One 2020-01- IDA / 55100 Post Request for Bids Open - National 1,000,000.00 0.00 Implementat 2019-03-30 2019-04-04 2019-05-16 2019-06-15 2019-07-20 Rivers/Streams and Clearing Reduction Envelope 16 ion of Blocked Drains NG-IUFMP-100565-CW-RFQ Component 3: Project Pending / Rehabilitation of BPP&DC Request for Single Stage - One 2019-10- IDA / 55100 Administration and Post Open - National 140,000.00 0.00 Implementat 2019-02-20 2019-04-17 Office Complex (Master Plan Quotations Envelope 14 Management ion Implementation) NG-IUFMP-100294-CW-RFQ Component 3: Project Pending Request for Single Stage - One 2019-09- / Additional Works at IUFMP IDA / 55100 Administration and Post Open - National 50,000.00 0.00 Implementat 2019-02-02 2019-03-30 Quotations Envelope 26 Project Office Management ion NG-IUFMP-156339-CW-RFB / Construction Works at Third Under & Fourth Pool of Long Term Component 2: Flood Risk Single Stage - One 83,000,000.0 15,671,465. 2021-01- IDA / 55100 Prior Request for Bids Open - International Implementat 2020-04-01 2020-08-01 2020-04-06 2020-08-06 2020-05-18 2020-10-02 2020-06-17 2021-06-11 2020-07-22 Investment as Identified by Reduction Envelope 0 03 18 ion Drainage Master Plan (Lots 3a&b, 4a&b) NG-IUFMP-156363-CW-RFB Pending / 2020 Dredging of Component 2: Flood Risk Single Stage - One 2020-11- IDA / 55100 Post Request for Bids Open - National 1,500,000.00 0.00 Implementat 2020-02-01 2020-02-06 2020-03-19 2020-04-18 2020-05-23 Rivers/Streams and Clearing Reduction Envelope 19 ion of Blocked Drains NG-IUFMP-156358-CW-RFB Pending / Rehabilitation & Component 2: Flood Risk Single Stage - One 2021-01- IDA / 55100 Post Request for Bids Open - National 5,000,000.00 0.00 Implementat 2020-03-15 2020-03-20 2020-05-01 2020-05-31 2020-07-05 Construction of Appurtenant Reduction Envelope 01 ion Structures of Agodi Lake NG-IUFMP-230356-CW-RFQ Request for / Rehabilitation of Office Component 1: Flood Risk Quotations - Small Pending Request for Single Stage - One 2021-12- Accommodation for EWS at IDA / 55100 Identification, Prevention and Post Open - National Works 120,000.00 0.00 Implementat 2021-04-25 2021-06-20 Quotations Envelope 17 Ministry of Environment & Preparedness (Emergency) SPD - ion Natural Resources Competitive NG-IUFMP-230353-CW-RFB Request for Bids - Pending / 2021 Dredging of Component 2: Flood Risk Single Stage - One Works (without 2022-02- IDA / 55100 Post Request for Bids Open - National 1,000,000.00 0.00 Implementat 2021-04-27 2021-05-02 2021-06-13 2021-07-13 2021-08-17 Rivers/Streams and Clearing Reduction Envelope prequalification) 13 ion of Blocked Drains SPD GOODS Page 1 Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-IUFMP-11105-GO-RFQ / Component 1: Flood Risk Pending Request for Single Stage - One Computers and Office IDA / 55100 Identification, Prevention and Post Open - National 16,000.00 0.00 Implementati 2017-03-12 2017-05-07 2017-11-03 Quotations Envelope Equipment Preparedness on NG-IUFMP-11160-GO-RFQ / Component 3: Project Pending Electronic Contract Request for Single Stage - One IDA / 55100 Administration and Post Open - National 10,000.00 0.00 Implementati 2017-04-17 2017-06-12 2017-12-09 Management Software Quotations Envelope Management on (Supply, Installation and Training) Component 3: Project Pending NG-IUFMP-11151-GO-RFQ / Request for Single Stage - One IDA / 55100 Administration and Post Open - National 16,000.00 0.00 Implementati 2017-03-19 2017-05-14 2017-11-10 Office Furniture Quotations Envelope Management on NG-IUFMP-11116-GO-RFQ / Component 1: Flood Risk Pending Fabrication of Complaint Request for Single Stage - One IDA / 55100 Identification, Prevention and Post Open - National 2,000.00 0.00 Implementati 2017-05-22 2017-07-17 2018-01-13 Boxes (40 No.) for Grievance Quotations Envelope Preparedness on Redress Mechanism (GRM) NG-IUFMP-11129-GO-RFQ / Component 3: Project Pending Printing of Project Documents Request for Single Stage - One IDA / 55100 Administration and Post Open - National 2,000.00 0.00 Implementati 2017-03-06 2017-05-01 2017-10-28 - (Accounting/Procurement Quotations Envelope Management on Documents) NG-IUFMP-22114-GO-RFQ / Component 3: Project Pending Procurement of 4x4WD Pick- Request for Single Stage - One IDA / 55100 Administration and Post Limited 60,000.00 0.00 Implementati 2017-08-27 2017-10-22 2018-04-20 Up Van for State Mediation Quotations Envelope Management on Centre NG-IUFMP-22118-GO-RFQ / Component 3: Project Pending Procurement of Office Request for Single Stage - One IDA / 55100 Administration and Post Limited 5,000.00 0.00 Implementati 2017-08-28 2017-10-23 2018-04-21 Equipment in Support of State Quotations Envelope Management on Mediation Centre NG-IUFMP-22123-GO-RFQ / Pending Component 2: Flood Risk Request for Single Stage - One Procurement of Material for IDA / 55100 Post Limited 3,800.00 0.00 Implementati 2017-09-05 2017-10-31 2018-04-29 Reduction Quotations Envelope Flood Emergency Response on NG-IUFMP-22126-GO-RFQ / Component 1: Flood Risk Pending Request for Single Stage - One Printing of Notepad with IDA / 55100 Identification, Prevention and Post Limited 12,000.00 0.00 Implementati 2017-08-14 2017-10-09 2018-04-07 Quotations Envelope Behavioral Change Messages Preparedness on NG-IUFMP-22128-GO-RFQ / Procurement of Award and Component 1: Flood Risk Pending Request for Single Stage - One Sanitation Material for IDA / 55100 Identification, Prevention and Post Limited 1,600.00 0.00 Implementati 2017-08-28 2017-10-23 2018-04-21 Quotations Envelope Operation Keep Ibadan Clean Preparedness on and Flood Free (OKIC&FF) NG-IUFMP-70341-GO-RFQ / Procurement of 3 Nos 4x4WD Pick-Up, one (2) Cars and one Pending Component 2: Flood Risk Request for Single Stage - One (1) Mini Jeep for supervision IDA / 55100 Post Open - National 200,000.00 0.00 Implementati 2018-02-25 2018-04-22 2018-10-19 Reduction Quotations Envelope of construction works at on Thirteen (13) Priority Sites and Eleyele Dam Rehabilitation NG-IUFMP-70348-GO-RFQ / Supply and Installation of Component 3: Project Pending Request for Single Stage - One slotted Angle Racks for IDA / 55100 Administration and Post Open - National 16,500.00 0.00 Implementati 2018-06-20 2018-08-15 2019-02-11 Quotations Envelope Archiving Procurement Management on Documents NG-IUFMP-91416-GO-RFQ / Component 3: Project Pending Request for Single Stage - One Procurement of Office IDA / 55100 Administration and Post Open - National 92,000.00 0.00 Implementati 2018-12-18 2019-02-12 2019-08-11 Quotations Envelope Furniture & Fittings Management on NG-IUFMP-100562-GO-RFQ / Design and Production of Component 1: Flood Risk Pending Request for Single Stage - One IUFMP Calendars and Branded IDA / 55100 Identification, Prevention and Post Open - National 50,000.00 0.00 Implementati 2019-10-06 2019-12-01 2020-05-29 Quotations Envelope Souvenirs for Project Preparedness on Stakeholders NG-IUFMP-100567-GO-RFQ / Procurement of additional Component 3: Project Pending Office Furniture and Fittings Request for Single Stage - One IDA / 55100 Administration and Post Limited 50,000.00 0.00 Implementati 2019-02-15 2019-04-12 2019-10-09 for IUFMP Project Office Quotations Envelope Management on (Cabinets, Tables & Chairs, Reading Lamps, etc) NG-IUFMP-100692-GO-RFQ / Procurement of Laptops and Component 3: Project Pending Desktop Computers, Request for Single Stage - One IDA / 55100 Administration and Post Open - National 75,000.00 0.00 Implementati 2019-02-16 2019-04-13 2019-10-10 Photocopiers Machine, Quotations Envelope Management on Multipurpose Printers (A0, A1 & A3) UPS, etc NG-IUFMP-104691-GO-RFQ / Design and Printing of Component 1: Flood Risk Pending IUFMP Quarterly Newsletter, Request for Single Stage - One IDA / 55100 Identification, Prevention and Post Open - National 22,500.00 0.00 Implementati 2019-03-30 2019-05-25 2019-11-21 Community GRM Operations Quotations Envelope Preparedness on Manual and other Awareness Materials. NG-IUFMP-121992-GO-RFQ Component 3: Project Pending / Procurement of Geographic Request for Single Stage - One IDA / 55100 Administration and Post Open - National 250,000.00 0.00 Implementati 2019-07-15 2019-09-09 2020-03-07 Information System (GIS) Quotations Envelope Management on Equipment NG-IUFMP-156369-GO-RFQ / Procurement & Installation of 10KVA Hybrid (Solar/Grid) Power Backup to cover IUFMP Component 3: Project Pending Request for Single Stage - One Office Complex, Internet/Data IDA / 55100 Administration and Post Open - National 30,000.00 0.00 Implementati 2020-02-15 2020-04-11 2020-10-08 Quotations Envelope Security Hardware & Software Management on and Provision of 4G LTE Internet Connectivity at 11 Zonal UREMEC Offices Page 2 NG-IUFMP-156362-GO-RFQ / Procurement of one (1) Component 3: Project Pending Request for Single Stage - One Multipurpose Network Printer IDA / 55100 Administration and Post Open - National 15,000.00 0.00 Implementati 2020-02-15 2020-04-11 2020-10-08 Quotations Envelope and two (2) other Network Management on Printers/Copier NG-IUFMP-121987-GO-RFQ / Provision of Internet and Component 3: Project Under Request for Single Stage - One Information Technology IDA / 55100 Administration and Post Open - National 125,000.00 0.00 Implementati 2019-07-14 2019-09-08 2020-03-06 Quotations Envelope Infrastructure in IUFMP Project Management on Office NG-IUFMP-199032-GO-RFB / Procurement and Installation Under of Flood Early Warning and Component 2: Flood Risk Single Stage - One IDA / 55100 Prior Request for Bids Open - International 2,000,000.00 0.00 Implementati 2020-10-09 2021-02-10 2020-10-14 2021-04-07 2020-11-25 2020-12-25 2021-01-29 2021-07-28 Response System Equipment Reduction Envelope on in Strategic locations in Ibadan NG-IUFMP-230434-GO-RFQ / Procurement and Installation Component 3: Project Pending Request for Single Stage - One of Flood Warning Post in the IDA / 55100 Administration and Post Open - National 50,000.00 0.00 Implementati 2021-05-08 2021-07-03 2021-12-30 Quotations Envelope Flood Plain Areas in Ibadan Management on City NG-IUFMP-230454-GO-RFQ / Supply and Installation of Component 3: Project Pending fifteen (15) Laptop Computers Request for Single Stage - One IDA / 55100 Administration and Post Open - National 15,000.00 0.00 Implementati 2021-07-23 2021-09-17 2022-03-16 for PIU Staff and one (1) Quotations Envelope Management on Multipurpose Photocopying Machine NG-IUFMP-156485-GO-RFB / Procurement of 6 Nos. 4X4WD Pick-up Monitoring Component 3: Project Pending Single Stage - One Vehicles for Contract IDA / 55100 Administration and Post Request for Bids Open - National 250,000.00 0.00 Implementati 2020-02-16 2020-02-21 2020-04-03 2020-05-03 2020-06-07 2020-12-04 Envelope Supervision of Pool of Works Management on on LTI as identified by Drainage Master Plan NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-IUFMP-22132-NC-RFQ / Component 1: Flood Risk Pending Radio Drama Production and Request for Single Stage - One IDA / 55100 Identification, Prevention and Post Limited 12,000.00 0.00 Implementati 2017-08-13 2017-10-08 2018-04-06 Broadcast (Season/Quarter- Quotations Envelope Preparedness on 13 Episodes) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-IUFMP-11115-CS-QCBS / Component 2: Flood Risk Quality And Cost- Pending IDA / 55100 Post Open - International 1,500,000.00 0.00 2014-04-28 2014-05-19 2014-07-02 2014-07-30 2014-08-29 2014-10-03 2014-11-07 2017-07-14 Ibadan City Urban Master Plan Reduction Based Selection Implementation NG-IUFMP-11118-CS-QCBS / Component 2: Flood Risk Quality And Cost- Ibadan Solid Waste IDA / 55100 Prior Open - International 1,500,000.00 0.00 Canceled 2014-05-05 2014-05-26 2014-07-09 2014-08-06 2014-09-05 2014-10-10 2017-05-04 2017-04-20 2018-04-20 Reduction Based Selection Management Master Plan NG-IUFMP-11126-CS-QCBS / Ibadan Integrated Flood Risk Component 2: Flood Risk Quality And Cost- Under IDA / 55100 Prior Open - International 3,500,000.00 0.00 2014-04-21 2014-05-12 2014-06-25 2017-04-07 2014-07-23 2016-03-29 2014-08-22 2017-04-07 2014-09-26 2017-04-07 2017-04-20 2021-04-20 Management and Drainage Reduction Based Selection Implementation Master Plan NG-IUFMP-11156-CS-QBS / Preparation and Supervision of Implementation of Component 2: Flood Risk Quality Based Pending IDA / 55100 Post Open - International 2,500,000.00 0.00 2017-02-27 2017-04-28 2017-06-11 2017-07-09 2017-08-08 2017-09-07 2017-10-12 2018-10-12 Safeguard Instrument for Pool Reduction Selection Implementation of Priority Sites as Identified in the Drainage Masterplan NG-IUFMP-11161-CS-QCBS / Engineering design and Component 2: Flood Risk Quality And Cost- IDA / 55100 Prior Open - International 1,876,000.00 0.00 Canceled 2015-04-01 2015-04-22 2015-06-05 2015-07-03 2015-08-02 2015-09-06 2015-10-11 2020-04-01 construction supervision for Reduction Based Selection works at 10 +2 priority sites NG-IUFMP-11147-CS-QCBS / Component 2: Flood Risk Quality And Cost- Development of Flood Early IDA / 55100 Prior Open - International 7,000,000.00 0.00 Canceled 2016-08-12 2016-09-02 2017-05-12 2017-12-19 2017-06-09 2018-03-05 2017-07-09 2017-08-13 2017-09-17 2018-09-17 Reduction Based Selection Warning and Response System Component 1: Flood Risk NG-IUFMP-11145-CS-QCBS / Quality And Cost- Pending IDA / 55100 Identification, Prevention and Post Open - International 250,000.00 0.00 2016-03-11 2016-04-01 2017-04-25 2017-05-23 2017-06-22 2017-07-27 2017-08-31 2018-08-31 Project Baseline Survey Based Selection Implementation Preparedness NG-IUFMP-11149-CS-CQS / Component 1: Flood Risk Consultant Pending Creation and Hosting of GIS IDA / 55100 Identification, Prevention and Post Qualification Open - National 45,000.00 0.00 2015-02-08 2015-02-08 2015-02-08 2015-02-08 2017-03-15 2017-09-11 Implementation Enabled Portal Preparedness Selection NG-IUFMP-11137-CS-CQS / Consultant Component 2: Flood Risk Pending ESIA for Eleyele Dam IDA / 55100 Post Qualification Open - International 100,000.00 0.00 2015-03-23 2015-04-13 2015-05-27 2015-06-26 2015-07-31 2017-02-27 Reduction Implementation Rehabilitation Selection NG-IUFMP-11106-CS-CQS / Consultant Preparation of ESIAs, ESMP's Component 2: Flood Risk Pending IDA / 55100 Post Qualification Open - International 280,000.00 0.00 2015-03-26 2015-04-16 2015-05-30 2015-06-29 2015-08-03 2017-04-28 and RAP for ten (10) priority Reduction Implementation Selection sites NG-IUFMP-11159-CS-QCBS / Component 1: Flood Risk Project Monitoring and Quality And Cost- Pending IDA / 55100 Identification, Prevention and Post Open - International 250,000.00 0.00 2016-03-14 2016-04-04 2016-05-18 2016-06-15 2016-07-15 2016-08-19 2017-05-16 2018-05-16 Evaluation (M&E) Management Based Selection Implementation Preparedness Information System (MIS) Page 3 NG-IUFMP-11123-CS-CQS / Component 1: Flood Risk Consultant Design and Construction Pending IDA / 55100 Identification, Prevention and Post Qualification Open - National 50,000.00 0.00 2015-12-04 2015-12-25 2016-02-07 2016-03-08 2016-04-12 2017-05-30 Supervision of New Project Implementation Preparedness Selection Office NG-IUFMP-11146-CS-CQS / Engineering design and Component 1: Flood Risk Consultant Pending construction supervision for IDA / 55100 Identification, Prevention and Post Qualification Open - National 120,000.00 0.00 2017-02-14 2017-03-07 2017-04-20 2017-05-20 2017-06-24 2017-12-21 Implementation Extended Roads at 4 Priority Preparedness Selection Sites NG-IUFMP-70346-CS-CQS / Component 3: Project Consultant Pending Engagement of External IDA / 55100 Administration and Post Qualification Open - National 9,000.00 0.00 2018-02-10 2018-03-03 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Implementation Auditor (PFMU) Management Selection NG-IUFMP-70327-CS-CQS / Component 3: Project Consultant Development and deployment Pending IDA / 55100 Administration and Post Qualification Open - National 100,000.00 0.00 2018-02-01 2018-02-22 2018-04-07 2018-05-07 2018-06-11 2018-12-08 of Data Digitization and Implementation Management Selection Archive Management NG-IUFMP-70361-CS-QCBS / Component 1: Flood Risk Quality And Cost- Development of Early Warning IDA / 55100 Identification, Prevention and Prior Open - International 7,000,000.00 2,281,408.75 Signed 2018-05-25 2018-06-15 2018-07-29 2018-08-26 2018-09-25 2018-10-30 2018-11-21 2018-12-04 2019-01-02 2019-12-04 Based Selection and Response Systems Preparedness NG-IUFMP-91443-CS-CQS / Component 3: Project Consultant Consultancy Service to Under IDA / 55100 Administration and Post Qualification Open - National 200,000.00 0.00 2018-12-24 2019-02-27 2019-01-14 2019-02-27 2019-03-29 2019-05-03 2019-10-30 Undertake Mid-Term Review Implementation Management Selection Assessment NG-IUFMP-100558-CS-CQS / Engagement of Consultant for the Preparation of Component 1: Flood Risk Consultant Safeguards Instruments Pending IDA / 55100 Identification, Prevention and Post Qualification Open - National 492,000.00 0.00 2019-02-04 2019-02-25 2019-04-10 2019-05-10 2019-06-14 2019-12-11 (ESMP, ESIA & RAP) for the Implementation Preparedness Selection Second Pool of Long Term Investment as identified by Drainage Master Plan NG-IUFMP-100555-CS-CQS / Engagement of Consultant for the Conduct of 3rd Party Consultant Environmental and Social Component 2: Flood Risk Under IDA / 55100 Post Qualification Open - National 150,000.00 0.00 2019-01-28 2019-05-16 2019-02-18 2019-04-03 2019-05-03 2019-06-07 2019-12-04 Monitoring for ongoing Reduction Implementation Selection Projects (Construction Works at 13 Sites, 4 Priority Sites and Eleyele Dam) NG-IUFMP-100564-CS-CQS / Consultancy Services for Component 1: Flood Risk Consultant Strategic Communication Pending IDA / 55100 Identification, Prevention and Post Qualification Open - National 250,000.00 0.00 2019-02-05 2019-02-26 2019-04-11 2019-05-11 2019-06-15 2019-12-12 Activities (Essay Competition, Implementation Preparedness Selection Documentary, Jingles, Drama, Advertisments etc) NG-IUFMP-100699-CS-CQS Component 3: Project Consultant / Selection of Witness Non- Pending IDA / 55100 Administration and Post Qualification Open - National 50,000.00 0.00 2019-02-28 2019-03-21 2019-05-04 2019-06-03 2019-07-08 2020-01-04 Governmental Organization Implementation Management Selection (NGO) for RAP Implementation NG-IUFMP-100702-CS-CQS / Selection of Consultant to Component 3: Project Consultant Pending Conduct Beneficiary Impact IDA / 55100 Administration and Post Qualification Open - National 120,000.00 0.00 2019-09-09 2019-09-30 2019-11-13 2019-12-13 2020-01-17 2020-07-15 Implementation Assessment and Satisfaction Management Selection Survey NG-IUFMP-100718-CS-CQS / 2019 Retreat on Visioning Component 3: Project Consultant Pending and Acculturation for PIU IDA / 55100 Administration and Post Qualification Open - National 45,000.00 0.00 2019-02-25 2019-03-18 2019-05-01 2019-05-31 2019-07-05 2020-01-01 Implementation members and Other Management Selection Stakeholders NG-IUFMP-104668-CS-CQS / Consultancy Service for the Consultant Supervision of 2019 Dredging Component 2: Flood Risk Pending IDA / 55100 Post Qualification Open - National 26,000.00 0.00 2019-03-18 2019-04-08 2019-05-22 2019-06-21 2019-07-26 2020-01-22 of Selected River/Streams and Reduction Implementation Selection Desilting of Drains in Ibadan City. NG-IUFMP-104678-CS-QCBS / Consultancy Service for Component 2: Flood Risk Quality And Cost- Pending Construction Supervision of IDA / 55100 Post Open - National 750,000.00 0.00 2019-03-18 2019-04-08 2019-05-22 2019-06-19 2019-07-19 2019-08-23 2019-09-27 2020-09-26 Reduction Based Selection Implementation Works at Second Pool of Long Term Investment. NG-IUFMP-104667-CS-CQS Consultant / Consultancy Service for Dam Component 2: Flood Risk IDA / 55100 Post Qualification Open - National 100,000.00 0.00 Canceled 2019-03-15 2019-04-05 2019-05-19 2019-06-18 2019-07-23 2020-01-19 Safety Assessment of Awba Reduction Selection and IITA Dams. NG-IUFMP-156356-CS-CQS / Consultancy Services for the Consultant Supervision of 2020 Dredging Component 2: Flood Risk Pending IDA / 55100 Post Qualification Open - National 50,000.00 0.00 2020-02-18 2020-03-10 2020-04-23 2020-05-23 2020-06-27 2020-12-24 of Selected Rivers/Streams Reduction Implementation Selection and Desilting of Drains in Ibadan City NG-IUFMP-156424-CS-CQS / Consultancy Service for Design and Implementation of Consultant Integrated Standard Operating Component 2: Flood Risk Pending IDA / 55100 Post Qualification Open - National 25,000.00 0.00 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-04-21 Procedures (SOP) including Reduction Implementation Selection Training and Drilling during rainy season for Early Warning Systems for MDAs NG-IUFMP-156364-CS-CQS / Consultancy Service for Preparation of Safeguards Component 1: Flood Risk Consultant Pending Instruments IDA / 55100 Identification, Prevention and Post Qualification Open - National 150,000.00 0.00 2020-01-20 2020-02-10 2020-03-25 2020-04-24 2020-05-29 2020-11-25 Implementation (ESIAs/ESMPs/RAPs) for Preparedness Selection Priority Solid Waste Management Assests Page 4 NG-IUFMP-156425-CS-QCBS / Support for Economic Activities with Public Private Component 2: Flood Risk Quality And Cost- Partnership (PPP) Initiative IDA / 55100 Prior Open - International 5,000,000.00 0.00 Under Review 2020-03-05 2020-03-26 2020-05-09 2020-06-06 2020-07-06 2020-08-10 2020-09-14 2021-09-14 Reduction Based Selection around Pool of Investments including Assest Management Inventory/Plan NG-IUFMP-156430-CS-CQS Consultant Component 2: Flood Risk Pending / Bathymetry Survey & Design IDA / 55100 Post Qualification Open - National 80,000.00 0.00 2020-02-10 2020-03-02 2020-04-15 2020-05-15 2020-06-19 2020-12-16 Reduction Implementation of Agodi Lake Rehabilitation Selection NG-IUFMP-156368-CS-CQS / Preparation of Safeguards Instruments (ESMPs, ESIAs & Component 1: Flood Risk RAP) for the Construction Least Cost Under IDA / 55100 Identification, Prevention and Post Open - National 400,000.00 0.00 2020-02-04 2020-03-17 2020-02-25 2020-04-09 2020-04-28 2020-05-07 2020-06-06 2020-07-11 2020-08-15 2021-02-11 Works at Second and Third Selection Implementation Preparedness pool of Priority Sites as Identified by Drainage Management (Lot 3 & 4) NG-IUFMP-104666-CS-CQS / Consultancy Service for Consultant Component 2: Flood Risk Under Bathymetric Survey and Dam IDA / 55100 Post Qualification Open - National 230,000.00 0.00 2019-03-15 2019-06-11 2019-04-05 2019-05-19 2019-06-18 2019-07-23 2020-01-19 Reduction Implementation Safety Assessment for Eleyele Selection Dam, Awba Dam and IITA Dam NG-IUFMP-162546-CS-QCBS / Preparation of Solid Waste Component 1: Flood Risk Quality And Cost- Master Plan including detailed IDA / 55100 Identification, Prevention and Prior Open - International 1,000,000.00 0.00 Under Review 2020-03-11 2020-03-06 2020-04-01 2020-04-03 2020-05-15 2021-08-17 2020-06-12 2021-06-04 2020-07-12 2020-08-16 2020-09-20 2021-09-20 Based Selection Engineering Design of Preparedness recommended Infrastructure NG-IUFMP-100287-CS-INDV / Engagement of Consultant Component 3: Project Consultant for the Mapping Services for Pending IDA / 55100 Administration and Post Qualification Open - National 120,000.00 0.00 2020-06-12 2020-07-03 2020-08-16 2020-09-15 2020-10-20 2021-04-18 Gender-Based Violence and Implementation Management Selection Development of Referral Directory & Protocol NG-IUFMP-104674-CS-QCBS / Consultancy Service for Component 2: Flood Risk Quality And Cost- Construction Supervision of IDA / 55100 Prior 4,050,467.18 3,663,165.21 Signed 2019-03-08 2020-08-27 2019-03-29 2019-05-12 2019-06-09 2019-07-09 2019-08-13 2020-09-25 2019-09-17 2020-10-09 2020-09-16 Reduction Based Selection Works at First Pool of Long Term Investment. NG-IUFMP-211438-CS-CQS / Consultancy Services for Unmanned Aerial Vehicle Component 1: Flood Risk Consultant Pending (UAV) Based Monitoring & IDA / 55100 Identification, Prevention and Post Qualification Open - National 100,000.00 0.00 2020-12-24 2021-01-14 2021-02-27 2021-03-29 2021-05-03 2021-10-30 Implementation Evaluation, Training and Flood Preparedness Selection Damage Assessment Mapping of Areas in Ibadan City NG-IUFMP-230367-CS-LCS / Consultancy Service for the Component 2: Flood Risk Least Cost IDA / 55100 Post Open - National 165,000.00 0.00 Under Review 2021-04-27 2021-04-21 2021-05-18 2021-07-01 2021-07-29 2021-08-28 2021-10-02 2021-11-06 2022-05-05 Supervision of Agodi Lake Reduction Selection Rehabilitation NG-IUFMP-230368-CS-CQS Component 1: Flood Risk Consultant / Consultancy Service for the Pending IDA / 55100 Identification, Prevention and Post Qualification Open - National 10,000.00 0.00 2021-04-26 2021-05-17 2021-06-30 2021-07-30 2021-09-03 2022-03-02 Preparation of ESIA for Agodi Implementation Preparedness Selection Lake Rehabilitation NG-IUFMP-230390-CS-CQS / Consultancy Service for the Component 1: Flood Risk Consultant Preparation of Safeguards Pending IDA / 55100 Identification, Prevention and Post Qualification Open - National 100,000.00 0.00 2021-04-27 2021-05-18 2021-07-01 2021-07-31 2021-09-04 2022-03-03 Instruments for the Extension Implementation Preparedness Selection Works at thirteen (13) Priority Sites NG-IUFMP-230429-CS-CQS / Consultancy Service for the Component 1: Flood Risk Consultant Pending Preparation of Emergency IDA / 55100 Identification, Prevention and Post Qualification Open - National 15,000.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 Implementation Preparedness Plan (EPP) for Preparedness Selection Eleyele Dam Safety NG-IUFMP-230402-CS-CQS Component 3: Project Consultant / Consultancy Service for Pending IDA / 55100 Administration and Post Qualification Open - National 75,000.00 0.00 2021-04-26 2021-05-17 2021-06-30 2021-07-30 2021-09-03 2022-03-02 Development of Asset Implementation Management Selection Management Plan INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-IUFMP-11108-CS-CDS / Engineering design and Component 2: Flood Risk Pending IDA / 55100 Post Direct Selection Direct 500,000.00 0.00 2014-09-29 2014-09-29 2014-10-20 2017-08-31 construction supervision for Reduction Implementation Eleyele Dam Safety Works NG-IUFMP-11124-CS-INDV / Component 1: Flood Risk Individual Pending Stakeholders Engagement IDA / 55100 Identification, Prevention and Post Consultant Open 75,000.00 0.00 2015-04-22 2015-04-22 2015-04-22 2016-07-22 2017-01-18 Implementation Plan for Fourteen (14) Priority Preparedness Selection Sites NG-IUFMP-11157-CS-INDV / Preparation of Safeguard Component 1: Flood Risk Individual Pending Instrument (ESMP) for the IDA / 55100 Identification, Prevention and Post Consultant Open 32,000.00 0.00 2017-03-14 2017-05-02 2017-05-23 2017-06-27 2017-12-24 Implementation Extended Roads at 4 Priority Preparedness Selection Sites NG-IUFMP-11112-CS-INDV / Component 1: Flood Risk Individual Pending Baseline Survey for IDA / 55100 Identification, Prevention and Post Consultant Open 75,000.00 0.00 2017-03-06 2017-04-24 2017-05-15 2017-06-19 2017-12-16 Implementation Cummunication Strategy Preparedness Selection NG-IUFMP-70352-CS-INDV / Component 1: Flood Risk Individual Preparation of ESMP & RAP for Pending IDA / 55100 Identification, Prevention and Post Consultant Open 65,000.00 0.00 2018-02-10 2018-03-31 2018-04-21 2018-05-26 2018-11-22 Extended Roads at Four (4) Implementation Preparedness Selection Priority Sites Page 5 NG-IUFMP-91421-CS-INDV / Component 3: Project Individual Under Engagement of Monitoring IDA / 55100 Administration and Post Consultant Open 75,000.00 0.00 2018-12-13 2019-01-29 2019-01-31 2019-02-21 2019-03-28 2019-09-24 Implementation and Evaluation Consultant Management Selection NG-IUFMP-91434-CS-INDV / Component 3: Project Individual Under Engagement of Procurement IDA / 55100 Administration and Post Consultant Open 75,000.00 0.00 2018-12-13 2019-01-29 2019-01-31 2019-02-21 2019-03-28 2019-09-24 Implementation Consultant Management Selection NG-IUFMP-91435-CS-INDV / Component 3: Project Individual Under Engagement of Hydraulic IDA / 55100 Administration and Post Consultant Open 75,000.00 0.00 2018-12-13 2019-01-29 2019-01-31 2019-02-21 2019-03-28 2019-09-24 Implementation Consultant Management Selection NG-IUFMP-91436-CS-INDV / Component 3: Project Individual Under Engagement of Information IDA / 55100 Administration and Post Consultant Open 75,000.00 0.00 2018-12-13 2019-01-29 2019-01-31 2019-02-21 2019-03-28 2019-09-24 Implementation Technology (IT) Consultant Management Selection NG-IUFMP-91440-CS-INDV / Component 3: Project Individual Engagement of Geographic Under IDA / 55100 Administration and Post Consultant Open 75,000.00 0.00 2018-12-13 2019-01-29 2019-01-31 2019-02-21 2019-03-28 2019-09-24 Information System (GIS) Implementation Management Selection Consultant NG-IUFMP-100552-CS-INDV Individual / Re-Engagement of Dam Component 2: Flood Risk Pending IDA / 55100 Post Consultant Open 83,000.00 0.00 2019-02-15 2019-04-05 2019-04-26 2019-05-31 2019-11-27 Panel of Experts for Eleyele Reduction Implementation Selection Dam Supervision NG-IUFMP-100550-CS-INDV / Engagement of Consultant for the Preparation of Individual Component 2: Flood Risk Pending Safeguards Instruments for IDA / 55100 Post Consultant Open 65,500.00 0.00 2019-02-11 2019-04-01 2019-04-22 2019-05-27 2019-11-23 Reduction Implementation 2019 Dredging of Selection Rivers/Streams and Clearing of Blocked Drains NG-IUFMP-100297-CS-INDV / Engagement of Consultant Component 3: Project Individual Pending to conduct RAP Completion IDA / 55100 Administration and Post Consultant Open 30,000.00 0.00 2019-09-01 2019-10-20 2019-11-10 2019-12-15 2020-06-12 Implementation Audit and RAP Endline M&E Management Selection study for 13 Priority Sites NG-IUFMP-100289-CS-INDV Component 1: Flood Risk Individual / Engagement of Consultant Pending IDA / 55100 Identification, Prevention and Post Consultant Open 50,000.00 0.00 2019-02-14 2019-04-04 2019-04-25 2019-05-30 2019-11-26 for the Update of Stakeholders Implementation Preparedness Selection Engagement Plan NG-IUFMP-100547-CS-INDV / Engagement of Consultant Component 3: Project Individual for the Deployment of Multi- Pending IDA / 55100 Administration and Post Consultant Open 82,000.00 0.00 2019-03-11 2019-04-29 2019-05-20 2019-06-24 2019-12-21 Channel Grievance Implementation Management Selection Management Suite (MCGMS) including toll-free hotline NG-IUFMP-100566-CS-INDV / Procurement and Setting Up of Licensed Microsoft Project Component 3: Project Individual Pending (Professional) Software, IDA / 55100 Administration and Post Consultant Open 20,000.00 0.00 2019-03-25 2019-05-13 2019-06-03 2019-07-08 2020-01-04 Implementation Primavera 6 Project Management Selection Management Softaware and Training of PIU members. NG-IUFMP-103399-CS-INDV / Engagement of 3 Nos Individual Consultants (2 Nos Component 3: Project Individual Pending Civil Engineers + 1 No IDA / 55100 Administration and Post Consultant Direct 5,000.00 0.00 2019-03-04 2019-03-14 2019-04-04 2019-05-09 2019-11-05 Implementation Safeguard) for Evaluation of Management Selection 1st Pool of Long Term Investment NG-IUFMP-154208-CS-CDS / Component 3: Project Under Engagement of Engr. S.A. IDA / 55100 Administration and Post Direct Selection Direct 35,000.00 0.00 2020-01-21 2020-02-05 2020-01-31 2020-04-05 2020-10-02 Implementation Adeniji (Hydraulic Expert) Management NG-IUFMP-156354-CS-INDV / Engagement of Urban Component 3: Project Individual Under Environment and Solid Waste IDA / 55100 Administration and Post Consultant Open 61,000.00 0.00 2020-02-10 2020-02-27 2020-03-30 2020-04-20 2020-05-25 2020-11-21 Implementation Management Expert Management Selection (supporting MoE&NR) NG-IUFMP-156360-CS-INDV Component 3: Project Individual / Engagement of Pending IDA / 55100 Administration and Post Consultant Open 61,000.00 0.00 2020-02-10 2020-03-30 2020-04-20 2020-05-25 2020-11-21 Environmental Councellor Implementation Management Selection (supporting MoE&NR) NG-IUFMP-156367-CS-INDV Component 3: Project Individual / Engagement of Pending IDA / 55100 Administration and Post Consultant Open 61,000.00 0.00 2020-02-10 2020-03-30 2020-04-20 2020-05-25 2020-11-21 Environmental Legal Adviser Implementation Management Selection (supporting MoE&NR) NG-IUFMP-179866-CS-CDS / Construction Supervision of Component 2: Flood Risk IDA / 55100 Prior Direct Selection Direct 190,434.74 728,505.31 Signed 2020-06-12 2020-06-22 2020-08-26 2020-09-01 2021-02-22 Eleyele Rehabilitation and Reduction Intake Works: NG-IUFMP-199036-CS-CDS / Short Term Consultancy on Valuation of Building and Component 3: Project Individual Pending Affected Structures in IDA / 55100 Administration and Post Consultant Direct 12,000.00 0.00 2020-11-25 2020-12-05 2020-12-26 2021-01-30 2021-04-30 Implementation Targeted Sites on LTIs on Management Selection Drainage MasterPlan for Ibadan City NG-IUFMP-206339-CS-CDS / Consultancy Service for the Component 2: Flood Risk Under Design and Construction IDA / 55100 Prior Direct Selection Direct 24,630.00 0.00 2021-01-17 2021-01-27 2021-04-02 2021-09-29 Reduction Implementation Supervision of Thirteen (13) Priority Sites NG-IUFMP-230397-CS-INDV / Consultancy Service for the Individual Supervision of 2021 Dredging Component 2: Flood Risk Pending IDA / 55100 Post Consultant Open 26,500.00 0.00 2021-04-27 2021-06-15 2021-07-06 2021-08-10 2022-02-06 of Rivers.Streams and Reduction Implementation Selection Desilting of Drains in Ibadan City Page 6 NG-IUFMP-243640-CS-INDV Component 3: Project Individual / Engagement of Individual Pending IDA / 55100 Administration and Post Consultant Open 350.00 0.00 2021-07-16 2021-09-03 2021-09-24 2021-10-29 2022-04-27 Consultant (Environmental Implementation Management Selection Safeguards Expert) NG-IUFMP-100277-CS-INDV / Engagement of Consultant Individual Component 2: Flood Risk to undertake the Supply, IDA / 55100 Post Consultant Open 22,000.00 0.00 Canceled 2019-01-31 2019-03-21 2019-04-11 2019-05-16 2019-11-12 Reduction Installation, Licensing and Selection Training on ODK Software NG-IUFMP-230374-CS-INDV Component 3: Project Individual / Engagement of Individual Pending IDA / 55100 Administration and Post Consultant Open 35,000.00 0.00 2021-04-26 2021-06-14 2021-07-05 2021-08-09 2022-02-05 Consultant (Social Safeguards Implementation Management Selection Expert) NG-IUFMP-230388-CS-INDV Component 3: Project Individual / Engagement of Project Pending IDA / 55100 Administration and Post Consultant Open 65,000.00 0.00 2021-04-26 2021-06-14 2021-07-05 2021-08-09 2022-02-05 Coordinator (Consultant) for Implementation Management Selection IUFMP Page 7