Prior Review Thresholds I. Goods and Works and non-consulting services. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Procurement Prior Review Remarks Method Thresholds (Estimated Cost of the Contract/Package) Works (including ICB, NCB, Direct >=US$ 10,000,000 turnkey, supply & Contract installation of plant RFQ None and equipment, and PPP) Goods, information ICB, NCB, Direct >=US$ 2,000,000 technology and non- Contract consulting services RFQ None II. Selection of Consultants Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of Procurement Procurement Prior Review Remarks Method Thresholds (Estimated Cost of the Contract/Package) Consultants: firms QCBS, QBS, FBS, >=US$ 1,000,000 CQS, Single Source Selection Consultants: IC (Open, 3CV, or >=US$ 300,000 Individual SSS) III. Short list comprising entirely of national consultants Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT Bangladesh : Bangladesh Urban Resilience Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2017-02-23 2020-09-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149493 GPN Date: Project Name: Bangladesh Urban Resilience Project Loan / Credit No: IDA / 55990 Executing Agency(ies): Rajdhani Unnayan Kartripakhha WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned URP/RAJUK/W-1 / Construction of 10 Storied plus 2 Basements Office Component B: Vulnerability Under Building with Research, Open - Single Stage - One IDA / 55990 Assessment of Critical and Prior Request for Bids 14,260,000.00 0.00 Implementat 2019-08-18 2019-11-04 2019-08-29 2019-11-06 2019-10-10 2019-12-30 2019-12-04 2020-03-22 2020-01-08 2021-10-29 Training and Testing International Envelope Essential Facilities ion Laboratory Facilities for Urban Resilience Unit, RAJUK URP/RAJUK/W-1A / Construction of Shed Component B: Vulnerability ,Partition and supportive Request for Single Stage - One IDA / 55990 Assessment of Critical and Post Open - National 12,987.00 0.00 Canceled 2018-03-15 2018-05-06 2018-06-05 Accessories for Quotations Envelope Essential Facilities Accommodation of PIU Office Security URP/RAJUK/W-1B / Component B: Vulnerability Request for Single Stage - One Renovation of office utility IDA / 55990 Assessment of Critical and Post Open - National 12,990.00 0.00 Canceled 2018-04-16 2018-06-11 2019-06-11 Quotations Envelope Space at Level 9 Essential Facilities URP/RAJUK/G-W1C / Component B: Vulnerability Request for Single Stage - One Renovation of Wash room IDA / 55990 Assessment of Critical and Post Open - National 12,990.00 0.00 Canceled 2018-05-18 2018-07-13 2019-07-13 Quotations Envelope and others Space at Level 9 Essential Facilities URP/RAJUK/W-2A / Component B: Vulnerability Request for Single Stage - One Renovation of Wash Rooms IDA / 55990 Assessment of Critical and Post Limited 23,400.00 23,409.41 Signed 2020-06-18 2020-06-15 2020-07-19 2020-07-01 2020-08-18 Quotations Envelope for PIU Office Essential Facilities URP/RAJUK/W-2 / Component B: Vulnerability Pending Refurbishment of PIU Office Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 88,500.00 0.00 Implementat 2020-08-30 2020-09-04 2020-09-18 2020-10-09 2020-11-13 2021-02-11 and Renovation of Utility Envelope Essential Facilities ion Spaces GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual URP/RAJUK/G-9 / Procurement of Earthquake Component B: Vulnerability & Seismic Equipment for Open - Single Stage - One IDA / 55990 Assessment of Critical and Prior Request for Bids 3,545,450.00 0.00 Canceled 2018-01-31 2018-02-25 2018-02-07 2018-04-26 2018-03-21 2018-04-26 2018-05-02 2018-10-27 2018-06-06 2018-08-08 Vulnerability Assessment of International Envelope Essential Facilities Critical Assets and etc. for URU Page 1 URP/RAJUK/G-10 / Procurement of Earthquake Component B: Vulnerability & Seismic Equipment for Open - Single Stage - One IDA / 55990 Assessment of Critical and Prior Request for Bids 3,389,610.00 0.00 Canceled 2018-01-31 2018-02-07 2018-02-07 2018-04-26 2018-03-21 2018-04-26 2018-05-02 2018-10-27 2018-06-06 2018-07-18 Developing Risk Sensitive International Envelope Essential Facilities Land Use Planning and etc for URU. URP/RAJUK/G-11 / Procurement of Earthquake Component B: Vulnerability Open - Single Stage - One & Seismic Equipment for IDA / 55990 Assessment of Critical and Prior Request for Bids 3,255,840.00 0.00 Canceled 2018-01-31 2018-02-25 2018-02-07 2018-04-26 2018-03-21 2018-05-08 2018-05-02 2018-06-30 2018-06-06 2018-12-03 International Envelope Laboratory and field testing Essential Facilities and etc. for URU Component B: Vulnerability URP/RAJUK/G-4 / Supply Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 389,610.00 109,645.38 Signed 2018-03-01 2018-05-21 2018-03-01 2018-03-31 2018-06-06 2018-04-30 2018-07-19 2018-06-04 2018-07-29 2019-06-04 of Furniture for PIU office Envelope Essential Facilities URP/RAJUK/G-1A / Mail Component B: Vulnerability domain and its accessories Request for Single Stage - One IDA / 55990 Assessment of Critical and Post Open - National 6,490.00 0.00 Canceled 2017-09-21 2017-09-21 2017-09-21 purhase & installation for Quotations Envelope Essential Facilities Emergecy Office use of PIU, URP/RAJUK/G-14 / Variable Refregerant Flow (VRF) Air Component B: Vulnerability Conditioning system supply Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 128,310.00 108,698.29 Signed 2018-04-01 2018-10-22 2018-04-06 2018-10-23 2018-05-06 2018-11-08 2018-06-05 2018-11-25 2018-07-10 2018-12-10 2019-07-10 and installation for the Envelope Essential Facilities renovation work of URP, RAJUK URP/RAJUK/G-1-1 / Supply Component B: Vulnerability of Computer and Related Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 194,810.00 173,285.54 Signed 2018-05-01 2018-04-01 2018-05-06 2018-06-05 2018-04-19 2018-07-05 2018-06-05 2018-08-09 2018-06-20 2019-08-09 Equipment for PIU Envelope Essential Facilities ,URP:RAJUK URP/RAJUK/G-3-1 / Procurement of Motor Vehicle for PIU of Component B: Vulnerability URPRAJUK-Phase1 : Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 448,050.00 391,465.99 Signed 2018-03-11 2018-03-06 2018-03-14 2018-04-15 2018-04-09 2018-05-22 2018-04-25 2018-06-26 2018-06-06 2019-06-26 i) 1no 4WD Sports Utility Envelope Essential Facilities Vehicle ii) 4 nos Double Cabin 4WD Pick-up and iii) 1 no Microbus URP/RAJUK/G-3-2 / Procurement of Motor Vehicle for PIU of Component B: Vulnerability URPRAJUK-Phase2 : Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 629,870.00 576,293.15 Signed 2018-04-08 2018-03-23 2018-04-08 2018-05-08 2018-04-16 2018-06-12 2018-04-25 2018-07-17 2018-06-06 2019-07-17 i) 1no 4WD Sports Utility Envelope Essential Facilities Vehicle ii) 5 nos Double Cabin 4WD Pick-up and iii) 3 no Microbus URP/RAJUK/G-2B / Supply Component B: Vulnerability Request for Single Stage - One of Stationery for Emergency IDA / 55990 Assessment of Critical and Post Open - National 6,250.00 5,902.19 Signed 2018-11-25 2018-12-10 2018-12-26 2018-12-24 2019-01-25 Quotations Envelope Office Use of PIU Essential Facilities URP/RAJUK/G-2C / Supply Component B: Vulnerability of Office Goods for Request for Single Stage - One IDA / 55990 Assessment of Critical and Post Open - National 6,250.00 5,878.21 Signed 2019-01-06 2018-12-10 2019-02-06 2018-12-24 2019-03-08 Emergency Office Use of Quotations Envelope Essential Facilities PIU URP/RAJUK/G-15 / Procurement of Field Component B: Vulnerability Open - Single Stage - One Equipment for Vulnerability IDA / 55990 Assessment of Critical and Post Request for Bids 1,613,725.00 1,188,000.00 Signed 2018-12-26 2018-12-23 2018-12-31 2019-01-03 2019-02-11 2019-02-25 2019-03-13 2019-03-31 2019-04-17 2019-05-06 2019-10-14 International Envelope Assessment Aspect of Essential Facilities Structures & Geo-physics URP/RAJUK/G-12 / Component B: Vulnerability Open - Single Stage - One Procurement of Seismic Lab IDA / 55990 Assessment of Critical and Prior Request for Bids 2,544,204.00 1,726,315.19 Signed 2018-12-26 2019-01-01 2018-12-31 2019-01-03 2019-02-11 2019-02-20 2019-03-13 2019-04-16 2019-04-17 2019-05-16 2019-10-14 International Envelope Equipment for URU Essential Facilities Page 2 URP/RAJUK/G-13 / Component B: Vulnerability Open - Single Stage - One Procurement of Seismic Field IDA / 55990 Assessment of Critical and Prior Request for Bids 2,623,370.00 2,035,000.00 Signed 2018-12-26 2019-01-01 2018-12-31 2019-01-15 2019-02-11 2019-03-04 2019-03-13 2019-04-29 2019-04-17 2019-07-07 2019-10-14 International Envelope Equipment for URU Essential Facilities URP/RAJUK/G-16 / Procurement of Equipment Component B: Vulnerability Open - Single Stage - One for Exploration of RSLUP IDA / 55990 Assessment of Critical and Post Request for Bids 1,593,350.00 0.00 Canceled 2018-12-26 2018-12-23 2018-12-31 2019-01-03 2019-02-11 2019-02-25 2019-03-13 2019-06-17 2019-04-17 2019-10-14 International Envelope Profile: 200 kN Truck Essential Facilities Mounted CPT Equipment URP/RAJUK/G-17 / Procurement of Equipment Component B: Vulnerability Open - Single Stage - One Under for Exploration of RSLUP IDA / 55990 Assessment of Critical and Prior Request for Bids 1,593,350.00 1,000,000.00 2019-08-20 2019-08-29 2019-08-25 2019-09-02 2019-10-06 2019-10-21 2019-11-05 2019-12-17 2019-12-10 2020-01-26 2020-06-07 International Envelope Review Profile: 200 kN Truck Essential Facilities Mounted CPT Equipment URP/RAJUK/G-18 / Supply & Installation of PA System, Component B: Vulnerability Telecommunication, Access Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 80,500.00 0.00 Canceled 2019-10-20 2019-11-05 2019-10-25 2019-11-06 2019-11-08 2019-11-25 2019-11-22 2019-12-03 2019-12-27 2020-03-26 Control & Security and Envelope Essential Facilities General Electrical Equipment for PIU Office URP/RAJUK/G-19 / Component B: Vulnerability Procurement of Motorcycle Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 29,500.00 0.00 Canceled 2019-11-03 2019-12-04 2019-11-08 2019-12-04 2019-11-22 2019-12-26 2019-12-13 2020-01-13 2020-01-17 2020-04-16 for PIU of Urban Resilience Envelope Essential Facilities Project: RAJUK Part URP/RAJUK/G-2D / Supply Component B: Vulnerability of Office Goods-1 for Request for Single Stage - One IDA / 55990 Assessment of Critical and Post Limited 5,925.00 5,771.18 Signed 2019-10-23 2019-11-11 2019-11-23 2019-11-24 2019-12-23 Emergency Office Use of Quotations Envelope Essential Facilities PIU URP/RAJUK/G-2E / Supply Component B: Vulnerability of Stationery-1 for Request for Single Stage - One IDA / 55990 Assessment of Critical and Post Limited 5,925.00 5,850.73 Signed 2019-10-30 2020-02-27 2019-11-30 2020-03-09 2019-12-30 Emergency Office Use of Quotations Envelope Essential Facilities PIU URP/RAJUK/G-18-1 / Supply & Installation of PA Component B: Vulnerability System, Telecommunication, Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 81,000.00 76,361.24 Signed 2019-12-19 2020-02-24 2019-12-22 2020-02-25 2020-01-12 2020-03-16 2020-01-26 2020-05-03 2020-03-01 2020-06-03 2020-05-30 Access Control & Security Envelope Essential Facilities and General Electrical Equipment for PIU Office URP/RAJUK/G-19-1 / Component B: Vulnerability Procurement of Motorcycle Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 29,500.00 28,303.56 Signed 2020-03-16 2020-06-28 2020-03-23 2020-06-28 2020-04-06 2020-07-16 2020-04-27 2020-07-26 2020-06-01 2020-08-18 2020-08-30 for PIU of Urban Resilience Envelope Essential Facilities Project: RAJUK Part URP/RAJUK/G-23 / Procurement of Equipment: Component B: Vulnerability Under Open - Single Stage - One Cutter Crane with 10 inch IDA / 55990 Assessment of Critical and Post Request for Bids 350,000.00 0.00 Implementati 2020-06-15 2020-06-16 2020-06-20 2020-06-17 2020-08-01 2020-08-06 2020-08-31 2020-08-31 2020-10-05 2021-04-03 International Envelope RCC Slab Cutting Capacity Essential Facilities on & 3.65 Ton Lifting Capacity URP/RAJUK/G-20 / Procurement of ICT Component B: Vulnerability Equipment for Deploying Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 813,000.00 0.00 Canceled 2020-03-08 2020-03-09 2020-03-12 2020-03-10 2020-04-09 2020-04-29 2020-04-30 2020-05-24 2020-06-04 2020-10-02 Electronic Construction Envelope Essential Facilities Permitting (ECP) System in RAJUK URP/RAJUK/G-20-1 / Procurement of ICT Component B: Vulnerability Equipment for Deploying Single Stage - One IDA / 55990 Assessment of Critical and Post Request for Bids Open - National 810,000.00 688,141.73 Signed 2020-06-28 2020-06-28 2020-07-01 2020-06-28 2020-07-22 2020-07-23 2020-08-12 2020-08-12 2020-09-16 2020-08-19 2021-01-14 Electronic Construction Envelope Essential Facilities Permitting (ECP) System in RAJUK Page 3 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual URP/RAJUK/NCS-1 / Hiring of Leased Lines for the Component B: Vulnerability Project Pilot Sites to Request for Single Stage - One IDA / 55990 Assessment of Critical and Post Limited 10,700.00 1,950.72 Signed 2019-11-24 2019-12-02 2019-12-25 2019-12-22 2020-06-22 facilitate the Networking Quotations Envelope Essential Facilities Infrastructure Supporting of the ECP System URP/RAJUK/NCS-2 / Hiring of Leased Lines for the Component B: Vulnerability Under RAJUK Zonal Offices to IDA / 55990 Assessment of Critical and Post Direct Selection Direct 25,300.00 25,295.43 Implementati 2020-07-30 2020-08-06 2020-08-04 2020-08-09 2020-08-28 2022-04-30 Facilitate the Networking Essential Facilities on Infrastructure Supporting of the ECP System CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual URP/RAJUK/S-6 / Component C: Improved Consultancy Services for Quality And Cost- Open - IDA / 55990 Construction, Urban Prior 3,522,730.00 5,110,247.81 Signed 2017-05-15 2017-06-05 2017-07-20 2017-08-25 2018-02-09 2017-10-20 2018-04-15 2017-12-01 2018-05-22 2018-02-16 2018-06-30 2018-03-23 2018-10-03 2020-06-30 Operationalizing the URU in Based Selection International Planning, and Development RAJUK URP/RAJUK/S-7 / Assessing the Current State and Deploying a Web-based Component C: Improved Quality And Cost- Open - Integrated Information IDA / 55990 Construction, Urban Prior 1,998,260.00 5,788,100.94 Signed 2017-05-15 2017-06-05 2017-07-20 2017-08-25 2018-02-09 2017-10-20 2017-12-01 2018-05-19 2018-02-16 2018-06-30 2018-03-23 2018-10-03 2020-06-30 Based Selection International Management System for the Planning, and Development Construction Permit System of RAJUK URP/RAJUK/S-4 / Consultancy Services for Component B: Vulnerability Vulnerability Assessment and Quality And Cost- Open - IDA / 55990 Assessment of Critical and Prior 6,781,520.00 8,210,272.05 Signed 2017-09-21 2017-09-21 2017-10-05 2017-11-02 2017-11-09 2018-01-31 2018-06-10 2018-03-14 2018-09-16 2018-04-18 2018-10-31 2020-06-30 Prioritized Investment Plan Based Selection International Essential Facilities for Critical Assets in Dhaka for URU URP/RAJUK/S-5 / Consultancy Services for Component B: Vulnerability Quality And Cost- Open - Development of a Risk- IDA / 55990 Assessment of Critical and Prior 6,296,550.00 7,184,152.72 Signed 2017-10-04 2017-10-04 2017-10-18 2017-11-15 2017-11-07 2018-02-13 2018-04-12 2018-03-27 2018-09-17 2018-05-01 2018-10-31 2020-06-30 Based Selection International sensitive Land Use Planning Essential Facilities Practice for URU URP/RAJUK/S-11 / Consultancy Services for Design and Supervision of Urban Resilience Unit (URU) Component B: Vulnerability Quality And Cost- Open - Building including Research, IDA / 55990 Assessment of Critical and Prior 2,425,950.00 3,010,367.57 Signed 2017-10-04 2017-10-04 2018-02-11 2018-03-11 2018-06-09 2018-04-03 2018-07-21 2018-07-23 2018-08-25 2018-08-16 2020-10-24 Based Selection International Training, and Testing Essential Facilities Laboratory facilities under RAJUK in Dhaka, Bangladesh URP/RAJUK/S-9 / Component C: Improved Quality And Cost- Open - Consultancy Services for IDA / 55990 Construction, Urban Prior 3,240,260.00 4,805,526.56 Signed 2017-09-21 2017-09-21 2018-03-11 2018-02-09 2018-04-22 2018-07-21 2018-05-21 2018-09-08 2018-07-23 2018-10-13 2018-10-30 2020-10-30 Based Selection International Building Code Enforcement Planning, and Development Page 4 URP/RAJUK/S-14 / Consultancy Services for the Component C: Improved Consultant Designing Website & IDA / 55990 Construction, Urban Post Qualification Open - National 37,500.00 33,977.01 Signed 2018-11-15 2018-11-26 2018-12-06 2018-12-03 2019-01-19 2019-01-31 2019-02-18 2019-03-21 2019-03-25 2019-04-04 2019-09-21 Archiving Project Documents Planning, and Development Selection for URU, RAJUK URP/RAJUK/S-8 / Component C: Improved Consultancy Services for Quality And Cost- Open - IDA / 55990 Construction, Urban Prior 3,542,210.00 0.00 Canceled 2017-05-15 2017-06-05 2017-07-20 2017-08-25 2018-02-09 2017-10-20 2017-11-19 2018-05-21 2018-03-04 2018-04-08 2020-06-30 Professional Accreditation Based Selection International Planning, and Development Program in RAJUK URP/RAJUK/S-8-1 / Component C: Improved Consultancy Services for Quality And Cost- Open - IDA / 55990 Construction, Urban Prior 3,542,210.00 0.00 Canceled 2018-10-15 2018-10-15 2018-10-15 2018-11-06 2018-10-28 2018-10-28 2018-11-27 2018-12-27 2019-01-31 2020-06-30 Professional Accreditation Based Selection International Planning, and Development Program in RAJUK URP/RAJUK/S-8A / Component C: Improved Consultant Consultancy Services for Open - IDA / 55990 Construction, Urban Post Qualification 995,000.00 0.00 Under Review 2020-05-25 2020-05-31 2020-06-15 2020-07-29 2020-08-28 2020-10-02 2022-03-26 Professional Accreditation International Planning, and Development Selection Program in RAJUK INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Reinforcing Individual the Country’s Emergency S1 / Procurement Specialist IDA / 55990 Prior Consultant Open 0.00 285,867.35 Signed 2016-04-28 2016-05-05 Management Response Selection Capacity Component A: Reinforcing S2 / Senior Financial Individual the Country’s Emergency Management & Planning IDA / 55990 Prior Consultant Open 0.00 285,867.35 Signed 2016-04-28 2016-05-05 Management Response Specialist Selection Capacity Component B: Vulnerability Individual URP/RAJUK/S-3 / IDA / 55990 Assessment of Critical and Post Consultant Limited 162,337.66 110,481.66 Signed 2018-06-03 2018-05-31 2018-06-08 2018-05-31 2018-06-29 2018-06-04 2018-08-03 2018-07-01 2019-01-30 Procurement Specialist Essential Facilities Selection URP/RAJUK/S-15 / Environmental Impact Component B: Vulnerability Assessment for Proposed 30 IDA / 55990 Assessment of Critical and Post Direct Selection Direct 95,000.00 88,776.10 Signed 2019-04-28 2019-05-02 2019-05-04 2019-05-08 2019-07-01 2019-05-30 2019-09-29 Storied Building of Urban Essential Facilities Resilience Unit URP/RAJUK/S-13 / Environmental Impact Component B: Vulnerability Individual Assessment of Proposed 30 IDA / 55990 Assessment of Critical and Post Consultant Limited 15,580.00 0.00 Canceled 2018-04-30 2018-05-05 2018-05-26 2018-06-30 2018-12-27 storied Urban Resilience Essential Facilities Selection Unit Building Page 5