Page 1 1 2 3 4 6 7 8 9 10 11 Ref. No. Description Type Contract No. No. of packages Proc. Method Review by Bank Prior/Post Preperation BD/RFP date Expected Bid- Open. Date/Proposal Submission Date Conctract signed date Contract completion date WORKS (INCLUDING SUPPLY & INSTALLATION) 1 Construction of Water Network and Reservoir(s) and Renovation of Customer Connections Works KUT-W1 1 NCB POST June 2007 August 2007 October 2007 October 2008 Works Sub-Total GOODS 1 Renovation of the Water Pumps, Procurement of Chlorination Equipment and Software and Hardware under Institutional Strengthening G KUT-G1 multiple Shopping POST February 2008 October 2008 Goods Sub-Total CONSULTANT'S SERVICES AND TRAINING 1 Preparation of Environmental Management Plan C KUT-C1 1 LPM February 2007 June 2007 2 CANCELLED C KUT-C2 multiple Individual POST 3 Preparation of Bidding Documents and Construction Supervision C KUT-C3 1 QCBS PRIOR June 2006 August 2006 February 2007 October 2008 4 Training C KUT-C4 multiple Other POST September 2007 September 2008 Consultant Sub-Total PHYSICAL AND PRICE CONTINGENCY TOTAL a) All ICB contracts for works and goods and all direct contracting will be subject to prior review by the Bank. b) The works contracts to cost less than Euro 7,5 million each may be procured through NCB. Bank’s sample NCB documents for ECA Region for Works will be used. The conditions for using NCB are listed in Schedule 4 to the Loan Agreement. c) Consultancy services by firms estimated to cost Euro 200,000 or more per contract, individual consultant contracts estimated to cost Euro 50,000 or more and single source selection of consultants will be subject to prior review by the Bank. d) entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. LPM: Local Procurement Method Short lists composed entirely of national consultants: Short lists of consultants for services estimated to cost less than Euro 200,000 equivalent per contract may be composed MUNICIPAL SERVICES PROJECT - KUTAHYA MUNICIPALITY PROCUREMENT PLAN (Fifth Revision / 27 December, 2007 )