Detailed Annual Procurement Plan From November 2017 to Year 2018 Mekong Integrated Water Resource Management Project: Additional Financing Revised as of 02 March 2018 I. General 1. Project information: • Country: Lao PDR • Project Implementing Agency: 1. Department of Planning and Cooperation, Ministry of Natural Resources and Environment (MoNRE) 2. Department of Irrigation-DIMU/PAFO in KHM. and SVK. 3. Department of Livestock and Fisheries-FCMU (CPS. ATP. and SEK.) 2. Bank’s approval Date of the procurement Plan • Original Plan: February, 3, 2017 • First Revision: January, 18, 2018 • Second Revision: February 12, 2018 • Third Revision: March 02, 2018 3. Date of General Procurement Notice: • To be advertised by ___ 2017 (UNDB online) 4. Period covered by this procurement plan: • Until the year 2018 implementation of the project. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Contract Value No. Procurement Method Prior Review Threshold US$ Comments Threshold US$ 1 ICB and LIB (Goods) >=600,000 All contracts above 1.5 million 2 NCB (Goods) 100,000 - <600,000 None 3 Shopping (Goods) <100,000 None 4 Direct Contracting (Goods, - All contracts above 1.5 million Works, and Non-consulting and 5 million for goods and Services) works respectively 5 ICB (Works) >= 2,000,000 All contracts above 5 million 6 NCB (Works) 200,000 - <2,000,000 None 7 Shopping (Works) <200,000 None 8 Community Participation None None 2. Prequalification. Not expected for the works/goods packages. 3. Reference to Project Operational Manual: Operation Manual dated 27 March 2017. 4. Any Other Special Procurement Arrangements: National procurement procedures as specified under paragraph 3.3 and 3.4 of the Procurement Guidelines and the conditions specified in Annex 1 to this Procurement Plan. 5. Procurement Packages for Works & Goods (prior & post reviews) with Methods and Time Schedule 1 2 3 4 5 6 7 8 9 Review by Expected Procurem PQ Domestic Estimated Bank Bid/Quotatio No. Contract (Description) ent (yes/n Preferenc Comment Cost USD (Prior / n Opening Method o) e (yes/no) Post) Date Component 2.1 : Support for Refining a Legal Framework Enabling integrated Water Resources Management C2.1-G- Office Equipment: Lot 1 10,000 Shopping No No Post May 2018 001 Component 2.2 : Support for Water Quality and Eco-System Health Completed Sonexay C2.2-W- Fence, parking lodge and 199,000 Shopping No No Post Jan 2018 Construction 001 warehouse Sole Company, Ltd C2.2-G- Laboratory Furniture 002 (Customized and 220,000 NCB No No Post May 2018 Specialized) C2.2-G- Office furniture and IT 99,000 Shopping No No Post May 2018 003 equipment C2.2-G- Vehicle 60,000 Shopping No No Post May 2018 004 Component 2.3 : Support for Water Resources Modelling and Assessment C2.3-G-001 Office Furniture and 40,000 Shopping No No Post Apr 2018 Equipment for modeller C2.3-G-002 Data on Geography, River network, Hydro-met, Socio- 20,000 SS No No Post Mar 2018 economic C2.3-G-003 Data on Geography, River network, Hydro-met, Socio- 20,000 SS No No Post Apr 2018 economic C2.3-G-004 Data on Geography, River network, Hydro-met, Socio- 10,000 SS No No Post Jul 2018 economic Component 2.4 : Support for Hydrological and Meteorological (Hydro-Met) Network Upgrading ADCP equipment supply C2.4-G-001 200,000 NCB No No Post May 2018 and training Hydro-Met Equipment and C2.4-G-002 Software and Automatic 740,000 ICB No No Post Jun 2018 Rain Gauges Rehabilitation of 2 C2.4-W-003 provincial and local offices in 150,000 Shopping No No Post Jun 2018 5 river basins Component 2.5 : National Project Management Unit (NMPU) Completed Isuzu Lao C2.5-G-001 Vehicles for NPMU: Lot 1 45,000 Shopping No No Post Jan 2018 Service Company C2.5-G-002 Office Equipment: Lot 1 15,000 Shopping No No Post Feb 2018 Office Renovation of new May 2018 C2.5-W-003 20,000 Shopping No No Post NPMU Feb 2018 Completed Kayasit C2.5-G-004 Office Furniture: Lot 1 7,000 Shopping No No Post Furniture Trading Component 3.1.1: River Basin Management Office Renovation of C3.1.1-W- Component Management, 180,000 NCB No No Post Apr 2018 001 PONRE, DONRE Coordination Office C3.1.1-G- Office equipment for 002 Component Management, 42,000 Shopping No No Post Apr 2018 PONRE, DONRE Offices (e.g. camera, laptop, printer) C3.1.1-G- Three (3) Vehicles for 120,000 NCB No No Post May 2018 003 PONRE offices C3.1.1-G- Motorbikes 30,000 Shopping No No Post May 2018 004 2 Payables under Retention contract 10% of Orginal C3.1.1-W- total contract for O Financing with 28,000 Shopping No Post Apr 2018 005 Construction building of o Contract PONRE-KHM Number: C3.1.1- W-01 Component 3.1.2:Sustainable Irrigation and Drainage Rehabilitation of Floodgates C3.1.2-W- in Houay Nonglom, Nongbok 100,000 Shopping No No Post Dec 2018 001 District, KHammouane Province: Lot 1 C3.1.2-W- Rehabilitation of Floodgates 002 in Houay Deuth 1, Nongbok 100,000 Shopping No No Post Dec 2018 District, KHammouane Province: Lot 2 C3.1.2-W- Rehabilitation of Floodgates 003 in Houay Deuth 2, Nongbok 100,000 Shopping No No Post Dec 2018 District, KHammouane Province:: Lot 3 C3.1.2-W- Rehabilitation of Floodgates 004 in Houay Boungsan, Nongbok District, 100,000 Shopping No No Post Dec 2018 KHammouane Province:: Lot 4 C3.1.2-W- Rehabilitation of Floodgates 005 in Xaibouly District, 100,000 Shopping No No Post Dec 2018 Savannakhet Province: Lot 5 Steel Pontoons for Irrigation Completed Pumping Stations in the Phouvieng C3.1.2-G- Catchment of Xebangfai: Lot Building and 90,000 Shopping No No Post Sep 2017 006 1 (Nongbok and Xebangfai Irrigation Districts, Khammouane Construction Province Company C3.1.2-G- Steel Pontoons for Irrigation Completed 007 Pumping Stations in the Phouvieng Catchment of Xebangfai: Lot Building and 2 (Nongbok District in 90,000 Shopping No No Post Sep 2017 Irrigation Khammouane Province and Construction Xaybouly District, Company Savanakhet Province) C3.1.2-G- Pontoon Mounted Electric Completed 008 Centrifugal Pump (75KW) for Noukham Irrigation Pumping Stations Irrigation Road in the Catchment of 99,000 Shopping No No Post Oct 2017 and Bridge Xebangfai, Nongbok District, Construction Co., Khammouane Province: Lot LTD 1 C3.1.2-G- Pontoon Mounted Electric Completed 009 Centrifugal Pump (75KW) for Noukham Irrigation Pumping Stations Irrigation Road in the Catchment of 99,000 Shopping No No Post Oct 2017 and Bridge Xebangfai, Nongbok District, Construction Co., Khammouane Province: Lot LTD 2 C3.1.2-G- Pontoon Mounted Electric 010 Centrifugal Pump (75KW) for Completed Irrigation Pumping Stations Noukham in the Catchment of Irrigation Road 99,000 Shopping No No Post Oct 2017 Xebangfai, Nongbok District, and Bridge Khammouane Province and Construction Co., Xaibouly District LTD Savannakhet Province: Lot 3 C3.1.2-G- Pontoon Mounted Electric 011 Centrifugal Pump (75KW) for Completed Irrigation Pumping Stations Noukham in the Catchment of Irrigation Road 99,000 Shopping No No Post Oct 2017 Xebangfai, Nongbok District, and Bridge Khammouane Province and Construction Co., Xaibouly District LTD Savannakhet Province Lot 4 C3.1.2-G- Pontoon Mounted Electric 012 Centrifugal Pump (75KW) for Irrigation Pumping Stations 99,000 Shopping No No Post Aug 2018 in the Catchment of Xebangfai, Nongbok District, Khammouane Province: Lot 3 5 C3.1.2-G- Electric Cables for Pumps 013 and Motors in the Catchment Completed of Xebangfai, Nongbok Bay Electric District, Khammouane 90,000 Shopping No No Post Dec 2017 Company, Ltd. Province and Xaibouly District Savannakhet Province Lot 4 C3.1.2-G- Supply of High Density 014 Polyethylene Pipes (HDPE) Completed and Flange Adapters for Xaignavong Group Irrigation Pumping Stations 90,000 Shopping No No Post Feb 2018 Sole Company. in the Catchment of Ltd Xebangfai (Nongbok District, Khammouane Province): Lot 1 C3.1.2-G- Supply of High Density 015 Polyethylene Pipes (HDPE) and Flange Adapters for Completed Irrigation Pumping Stations Xaignavong Group in the Catchment of 90,000 Shopping No No Post Feb 2018 Sole Company. Xebangfai (Nongbok District, Ltd Khammouane Province and Xaibouly District, Savannakhet Province): Lot 2 C3.1.2-G- Completed 016 Supply of Flexible Pipes for Noukham Irrigation Pumping Stations Irrigation Road 90,000 Shopping No No Post Oct 2017 in the Catchment of and Bridge Xebangfai : Lot 1 Construction Co., LTD C3.1.2-G- Supply of Flexible Pipes for 017 Irrigation Pumping Stations Completed in the Catchment of Noukham Xebangfai (Nongbok District, Irrigation Road 90,000 Shopping No No Post Oct 2017 Khammouane Province and and Bridge Xaibouly District, Construction Co., Savannakhet Province):: Lot LTD 2 C3.1.2-G- Construction Materials for Completed 018 Canal Improvement at Phouvieng Navang Noi; Navang Thong; Building and Navang Thay Scheme, 99,000 Shopping No No Post Oct 2017 Irrigation Nongbok District, Construction Khammouane Province: Lot Company 1 C3.1.2-G- Construction Materials for Completed 019 Canal Improvement at Sadu Phouvieng Tay; Phonesao-A; Building and Thamouang Scheme, 99,000 Shopping No No Post Oct 2017 Irrigation Nongbok District, Construction Khammouane Province: Lot Company 2 C3.1.2-G- Construction Materials for Completed 020 Canal Improvement at Phouvieng Dongphakpheua 1; Natai; Building and 99,000 Shopping No No Post Oct 2017 Sorbo Scheme, Nongbok Irrigation District, Khammouane Construction Province: Lot 3 Company C3.1.2-G- Construction Materials for Completed 021 Canal Improvement at Noukham Somsaat 1; Nongheuathong Irrigation Road 99,000 Shopping No No Post Oct 2017 2; Thakham Scheme, and Bridge Xaybouly District, Construction Co., Savannakhet Province: Lot 4 LTD C3.1.2-G- Construction Materials for 022 Canal Improvement (Nongbok District, Khammouane Province and 99,000 Shopping No No Post Oct 2018 Xaibouly District, Savannakhet Province): Lot 5 C3.1.2-G- Supply of High Density 023 Polyethylene Pipes (HDPE) Completed and Flange Adapters for Xaignavong Group 80,000 Shopping No No Post Feb 2018 Irrigation Pumping Stations Sole Company. in the Catchment of Ltd Xebangfai 4 C3.1.2-G- Tools and Accessories for 024 Pumps (Nongbok District, Khammouane Province and 80,000 Shopping No No Post May 2018 Xaibouly District, Savannakhet Province): C3.1.2-G- Demonstration Materials for 025 Agriculture Inputs (Nongbok District, Khammouane 30,000 Shopping No No Post June 2018 Province and Xaibouly District , Savannakhet Province): Lot 1 C3.1.2-G- Vehicle 45,000 Shopping No No Post Dec 2018 026 C3.1.2-G- Office Equipment 30,000 No No Post Sept 2018 027 Shopping Component 3.2 : Fisheries Management C3.2-W-001 New Hatchery Construction in Attapeu Province: Package 1 (Site Grading 194,000 Shopping No No Post Apr 2018 and Reservoir, Broodstock and Recycling Pond C3.2-W-002 New Hatchery Construction in Attapeu Province: 170,000 Shopping No No Post May 2018 Package 2 (Water Supply and Drainage System), C3.2-W-003 New Hatchery Construction in Attapeu Province: Package 3 (Two (2) 171,300 Shopping No No Post June 2018 broodstock and 8 nursery ponds), C3.2-W-004 New Hatchery Construction in Attapeu Province: 184,000 Shopping No No Post June 2018 Package 4 (Buildings) C3.2-G-005 Community support for Multiple Demarkation (8 Khum Bans 21,000 Shopping No No Post May 2018 Contracts x $3,000 per Khum Ban C3.2-G-006 Fisheries Management Plan Multiple Investments (8 Khum x 15,000 Shopping No No Post Jun 2018 Contracts $4,000 per Khum Ban C3.2-G-007 Motor Boat and engine for Champasack , Sekong and 30,000 Shopping No No Post May 2018 Attapeu C3.2-G-008 Equipment for MCS Office May 2018 Support (binoculars, life 15,000 Shopping No No Post jackets, cameras, first aid kits, etc.) C3.2-G-009 Logistic cost for FCZ (Sanctuary) Management (Construction Materials for 12,000 Shopping No No Post Oct 2018 construction of guard house or posts) C3.2-G-010 Truck for Attapeu Hatchery 28,000 Shopping No No Post Oct 2018 C3.2-G-11 Office Equipment for 5,000 Shopping No No Post Oct 2018 Champassak C3.2-G-12 Office Equipment for Sekong 5,000 Shopping No No Post Oct 2018 C3.2-G-13 Office Equipment for 5,000 Shopping No No Post Oct 2018 Attapeu C3.2-G-14 Equipment and furniture for Champassak and Sekong 20,000 Shopping No No Post Mar 2018 hatcheries Hengphouvanh Construction Company Signed Contract during Original Financing and Hatchery Renovation KM8, C3.2-G-15 14,800.00 Shopping No No Post Mar 2018 remaining cost CPS of the contract will be funded using AF. Remaining 10% payment for defects liability Hatchery renovation, Banna Thavysub C3.2-G-16 58,300.00 Shopping No No Post Dec 2018 CPS Construction 5 Company Signed Contract during Original Financing and remaining cost of the contract will be funded using AF. Remaining 30% final payment and 10% payment for defects liability Souvanh Construction Company Signed Contract during Original Financing and C3.2-G-17 Hatchery Renovation SEK 14,900.00 Shopping No No Post Mar 2018 remaining cost of the contract will be funded using AF. Remaining 10% payment for defects liability III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: No. Selection Method Contract Value Prior Review Threshold (US$) Comments Threshold (US$) 1 Competitive Methods (Firms) – Quality & >=300,000 All contracts above 500,000 Cost Based Selection (QCBS) and Quality Based Selection (QBS) 2 Competitive Methods (Firms) – Least- <300,000 None Cost Selection (LCS) and Selection Based on Consultant Qualifications (CQS) 3 Single Source (Firms) All contracts above 0.5 million 4 Individual Consultants All contracts above 200,000 for Contract extension will entire project duration. All ToRs be subject to post will require World Bank review. clearance. 2. Short list comprising entirely of national consultants: No short lists of consultants for services are expected to comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. However, if a need arises during the project implementation and if it is warranted, short lists of consultants for services estimated to cost less than $200,000 equivalent per contract may be composed entirely of national consultants. 3. Any Other Special Selection Arrangements: Advance Contracting Advance contracting may be applied for some items as specified in the Procurement Plan. 4. Consultancy Assignments with Selection Methods (prior & post reviews) and Time Schedule. 5. For all contract amendments/extensions/ follow-on contracts, etc. the following guidelines shall apply: i) gross salary increases shall be limited to CPI plus a performance-based increase not to exceed 2%; ii) there shall be no increase in living allowances or similar expenses unless explicitly authorized by MOF Decree. Expected Name Selectio Proposals Estimated Review Date of Contract n Department Submissio Cost for First by Bank Signing Ref. No. Description of Assignment Method responsible for n Contract (Prior / Review Method for First procurement Date for US$ Post) (Contract Contract First Sequence) Contract Component 2.1: Support for Refining a Legal Framework Enabling integrated Water Resources Management Cost for 1st year of C2.1-ICS-001 National IWRM Specialist 14,000 ICS NPMU/DWR Post Mar 2018 Contract (Part-time) 6 Cost for 1st year of C2.1-ICS-002 National Legal Specialist 14,000 ICS NPMU/DWR Post Mar 2018 Contract (Par-time) Component 2.2 : Support for Water Quality and Eco-System Health Regional expert on lab equipment evaluation and assessment: the expert will support NEL to identify, NPMU/ C2.2-ICS-001 20,000 SSS Post Mar 2018 . assess and select the most NREI suitable equipment (economic viable, technical liability..) Regional expert for validating of laboratory performance according NPMU/ C2.2-ICS-002 to the ISO/IEC17025, conducting 20,000 SSS Post Apr 2018 NREI internal auditing under the scope of ISO/IEC17025 Accreditation. Regional expert on lab equipment maintenance, technical supports NPMU/ C2.2-ICS-003 and conducting internal training 20,000 ICS Post May 2018 NREI on water quality analysis technique and in field monitoring NPMU/ C2.2-ICS-004 National expert on Bio-monitoring 20,000 SSS Post Apr 2018 NREI Component 2.3 : Support for Water Resources Modelling and Assessment NPMU/ C2.3-ICS-001 90,000 IC Post Apr 2018 Modeling & DSS Advisor NREI Topographic and river cross- NPMU/ C2.3-ICS-002 section survey : Package 1 (XBF 60,000 CQS Prior Apr 2018 NREI and XBH) Topographic and river cross- NPMU/ C2.3-ICS-003 section survey: Package 2 (Sedon 60,000 CQS Prior Jun 2018 NREI and Sekong) Detailed Design and Construction NPMU/ C2.3.0-ICS-004 64,000 CQS Post Apr 2018 Supervision for the NWRIC Bldg NREI eWater Consultant Signed Contract on July 2016 during Firm Service for Basin simulation NPMU/ Phase 1 with C2.3.0-ICS-005 300,000 SS Prior May 2016 model and Tools development. NREI Procurement Number: C2.3-ICS- 006. Cost to be charged to AF funds National Modelling and Database NPMU/ C2.3.0-ICS-006 32,500 IC Post Apr 2018 Specialist NREI Component 2.4 : Support for Hydrological and Meteorological (Hydro-Met) Network Upgrading Site Survey and Engineering for C2.4-ICS-001 Hydro-Met and Rain Stations 150,000 CQS NPMU/DMH Post May 2018 (Safeguards and UXO) Russel Boals Signed Contract Extension on April 2017 during Phase 1 C2.4-ICS-002 International Hydromet Advisor 112,000 SSS NPMU/DMH Post Feb 2018 with Procurement Number: C2.3-ICS- 002 to be charged to AF funds C2.4-ICS-003 National Hydromet Consultant 10,000 ICS NPMU/DMH Post Mar 2018 Component 2.5 : National Project Management Unit 7 Completed C2.5-CS-001 National Financial Manager 25,000 IC DPC-NPMU Post Jan 2018 Mrs. Khemmala Haraixay Completed C2.5-CS-002 National Project Account 18,000 ICS DPC-NPMU Post Jan 2018 Mrs. Sengchanh Phanthalangsy Completed Vic Macasaquit Signed Contract from Original Financing Implementation Support C2.5-CS-003 60,000 SSS DPC-NPMU Post Jan 2018 and Balance Consultant Contract Cost to be carried over to AF to be Shared with other Components International Procurement C2.5-CS-004 80,000 ICS DPC-NPMU Post Apr 2018 Part-time Specialist C2.5-CS-005 Completed Project Audit (Year 2017 and Year 28,930 SSS DPC-NPMU Post Jan 2018 KPMG Audit 2018) Company C2.5-CQS-006 Project Audit for Year 2019 15,000 CQS DPC-NPMU Post Dec 2018 C2.5-CQS-007 Detailed Design and Supervision for the Office Renovation of new 6,000 ICS DPC-NPMU Post Mar 2018 NPMU C2.5-CS-008 Continue from Accounting Software Developer Original Financing 9,600 ICS DPC-NPMU Post Jan 2018 Consultant (Part-time) Completed Bounmy Khounlath C2.5-CS-009 National Procurement Assistant 15,000 ICS DPC-NPMU Post Apr 2018 Vic Macasaquit Contract Extension Implementation Support C2.5-CS-010 165,000 SSS DPC-NPMU Post June 2018 and cost to be to be Consultant Shared with other Components Component 3.1.1 : River Basin Management Manida Unkulvasapaul Signed Contract from Original C3.1.1-CS-001 International IWRM Specialist 31,869 SSS NPMU/DWR Post Mar 2018 Financing and Balance Contract Cost to be carried over to AF National IWRM Specialist Mr. Vipaka Halsacda C3.1.1-CS-002 28,000 SSS NPMU/DWR Post Mar 2018 Continue from Original Financing C3.1.1-CS-003 Cashier 11,600 SSS NPMU/DWR Post May 2018 C3.1.1-CS-004 Project Administration Support 7,000 SSS NPMU/DWR Post May 2018 River Basin Planning and C3.1.1-CS-005 900,000 QCBS NPMU/DWR PostPrior June 2018 Management firm consultancy Local and Green Infrastructure and Water Conservance for Rural C3.1.1-CS-006 280,000 CQS NPMU/DWR Post May 2018 Water Services and Livelihood Improvement Savannakhet Groundwater C3.1.1-CS-007 Management Plan firm 200,000 CQS NPMU/DWR Post May 2018 consultancy Consultant for Development of a C3.1.1-CS-008 30,000 IC NPMU/DWR Post May 2018 Groundwater User Register Manida C3.1.1-CS-009 International IWRM Specialist 50,000 SSS NPMU/DWR Post Apr 2018 Unkulvasapaul Contract Extension Component 3.1.2 : Sustainable Irrigation and Drainage Completed Soksay Chaluersap C3.1.2-CS- Survey and Design for the Flood 20,000 CQS DIMU/ PAFO Post Feb 2018 Consulting Sole Co., 001 protection and drainage system LTD C3.1.2-CS- Community Development Specialist 8,246.75 SSS DIMU/ PAFO Post Apr 2018 Manane 002 Vongnalaysane 8 Signed Contract from Original Financing and Balance Contract Cost to be carried over to AF C3.1.2-CS- Senior Irrigation Management 42,000 ICS DIMU/ PAFO Post May 2018 003 Specialist Vivarath Sihabouj Signed Contract from C3.1.2-CS- Original Financing and Irrigation Engineer 7,890.72 SSS DIMU/ PAFO Post Jan 2018 004 Balance Contract Cost to be carried over to AF Somchith Phonephachanh C3.1.2-CS- Signed Contract from Pump Engineer 5,464.81 SSS DIMU/ PAFO Post Jan 2018 Original Financing and 005 Balance Contract Cost to be carried over to AF Completed C3.1.2-CS- Agriculture Extension and M&E 36,000 IC DIMU/ PAFO Post Jan 2018 Mr. Boun Ome 006 Specialist Soulideth Completed C3.1.2-CS- Accountant 18,000 SSS DIMU/ PAFO Post Nov 2017 Ms. Khouanta 007 Latthachack Completed C3.1.2-CS-08 Secretary-Cashier 9,700 SSS DIMU/ PAFO Post Nov 2017 Ms. Lathdaphone Atphanya C3.1.2-CS-09 Contract Extension Manane Community Development Specialist 36,000 SSS DIMU/ PAFO Post Apr 2018 Vongnalaysane C3.1.2-CS-10 Vivarath Sihabouj Irrigation Engineer 36,000 SSS DIMU/ PAFO Post Apr 2018 Contract Extension C3.1.2-CS-11 Somchith Pump Engineer 36,000 SSS DIMU/ PAFO Post Apr 2018 Phonephachanh Contract Extension Component 3.2: Fisheries Management Continue from Original Financing C3.2-CS- Completed Fishery Management Consultant 81,720 SSS CMU. CPS. Post Dec 2017 001 Mr. Sinthavong Viravong (12 months contract) C3.2-CS- Continue from 002 Original Financing National Technical Consultant for Completed 6,570 SSS CMU. CPS. Post Jan 2018 Rural Infrastructure 1 Mr. Khaykeo Xaymounvong (3 months contract) C3.2-CS- Continue from 003 Original Financing National Technical Consultant for Completed 2,520 SSS CMU. CPS. Post Jan 2018 Rural Infrastructure 2 Mr. Khampheui Phothisane (3 months contract) C3.2-CS- Kaviphone 004 National GIS 50,000 SSS CMU. CPS. Post Jan 2018 Phouthavong Contract Extension C3.2-CS- Vilayphone Inthilath 007 Signed Contract from Original Senior Accountant 1,329.79 SSS CMU. CPS. Post Jan 2018 Financing and Balance Contract Cost be carried over to AF 9 C3.2-CS- Vilayphone Inthilath Senior Accountant 17,287 SSS CMU. CPS. Post Feb 2018 008 Contract Extension C3.2-CS- Lamephone 009 Cashier 658.62 SSS CMU. CPS. Post Jan 2018 Onesengphet Signed Contract from Original Financing and Balance Contract Cost be carried over to AF C3.2-CS- Lamephone 010 Cashier 4,200 SSS CMU. CPS. Post Mar 2018 Onesengphet Contract Extension C3.2-CS- Completed 011 Vilaysuck Phonechalern Signed Contract Finance Management Consultant 5,424 SSS CMU. CPS. Post Jan 2018 from Original Financing and Balance Contract Cost to be carried over to AF C3.2-CS- Vilaysuck 012 Finance Management Consultant 23,209 SSS CMU. CPS. Post Mar 2018 Phonechalern Contract Extension C3.2-CS- Completed 013 Soulivanthong Kingkeo (6 months contract) Continue from Original Financing National Technical Advisor 11,905 SSS CMU. CPS. Post Dec 2017 Signed Contract from Original Financing and Balance Contract Cost to be carried over to AF C3.2-CS- Continue from 016 Original Financing National Livelihood Consultant 7,100 SSS CMU. CPS. Post Jan 2018 Completed Mr. Vilath Keovichith (3 months contract) C3.2-CS- Simon Diffey 017 Signed Contract from Original International Chief Technical Advisor 112,500 SSS CMU. CPS. Post Dec 2017 Financing and Balance Contract Cost to be carried over to AF C3.2-CS- GECI Consultant 018 Detailed Engineering Design and Signed Contract Construction Supervision for the from Original Improvement and Construction of 24,918 SSS CMU. CPS. Post Jan 2018 Financing and Hatcheries in the provinces of Balance Contract Champasack, Sekong and Attapeu Cost to be carried over to AF C3.2-CS- Sutthichai Rittitum 019 Signed Contract from Original Regional Part-Time Fish Hatchery 25,000 SSS CMU. CPS. Post Jan 2018 Financing and Operations and Management Expert Balance Contract Cost to be carried over to AF Annex 1 - Additional National Procurement Provisions. Procurement under National Procurement Procedures will be carried out in accordance with national regulations including the Procurement Decree #03, dated January 9, 2004 and Implementation Rule and Regulations (IRR) #0063 issued by MOF on March 12, 2004 and #0861/MOF, dated May 5, 2009 (amended version); Procurement Manual dated May 2009 and harmonized bidding documents for national competitive bidding and request for quotations agreed between Government of Lao PDR, 10 World Bank and Asia Development Bank. In addition to the provisions stipulated in the above documents, Government and Implementing agencies for Bank financed projects shall implement the following additional provisions: i. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; ii. Information related to award of contract including reasons for rejection of unsuccessful bidders shall be published on the implementing agency websites and/or newspaper of wide circulation. iii. All complaints on procurement related matters including complaints arising from procurement under Bank financed Projects whilst using National Procurement Procedures shall be dealt with in accordance with Article 33 of the Procurement Decree. Borrower shall put in place an effective complaints review mechanism for dealing with procurement related complaints, and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. 11 PROCUREMENT Lao People's Democratic Republic : Mekong Integrated Water Resources Management PLAN General Information Country: Lao People's Democratic Republic Bank’s Approval Date of the Original Procurement Plan: 2018-04-13 2019-09-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P104806 GPN Date: Project Name: Mekong Integrated Water Resources Management Loan / Credit No: IDA / H6750, IDA / H7620, IDA / 61180 Executing Agency(ies): Ministry of Natural Resource and Environment WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2.2.0.-CW-001 / Construction Works for Laboratory Building of the Regional Water Resources Single Stage - One Natural Resource and IDA / H6750 Prior Request for Bids Open - National 0.00 1,249,363.78 Signed Management Envelope Environment Institute (NREI): Component 2.2: MIWRMP C3.1.1/W/003 / Office Renovation at the PoNRE Regional Water Resources Request for Open - IDA / H6750 Prior 20,000.00 19,363.85 Signed Savanhnakhet - Component Management Quotations International 3.1.1 C3.1.1-W-01 / Construction Works for Component 3.1.1 Regional Water Resources Request for Open - IDA / H6750 Prior 0.00 258,165.53 Signed PONRE Office in Management Quotations International Khammouane Province C2.4-W-01 / Construction Works for the National Flood and Drought and Early Warning System Regional Water Resources Single Stage - One IDA / H6750 Prior Request for Bids Open - National 0.00 668,991.85 Signed Building of the Department Management Envelope of Meteorology and Hydrology (DMH): Component 2.4 LA-MONRE-72798-CW-RFQ Under / C2.4-W-003: Rehabilitation National Water Resources Request for Single Stage - One IDA / 61180 Post Open - National 150,000.00 0.00 Implementati 2018-09-08 2018-11-03 2019-05-02 of Provincial and Local Management Quotations Envelope on Offices in River Basins C3.1.2-W031 / Rehabilitation of Floodgates Improved Floodplain and Pending Single Stage - One in the Provinces of IDA / 61180 Aquatic Resources Post Request for Bids Open - National 650,000.00 0.00 Implementati 2018-10-29 2018-11-02 2018-12-03 2018-12-14 2018-12-25 2019-06-23 Envelope Khammouane and Management on Savannaketh LA-MONRE-72803-CW-RFQ / C3.1.2-W-004: Rehabilitation of Floodgates Improved Floodplain and Request for Single Stage - One in Houay Boungsan, IDA / 61180 Aquatic Resources Post Open - National 80,000.00 0.00 Canceled 2018-12-07 2019-02-01 2019-05-02 Quotations Envelope Nongbok District, Management KHammouane Province: Lot 4 LA-MONRE-72800-CW-RFQ / C3.1.2-W-001: Improved Floodplain and Rehabilitation of Floodgates Request for Single Stage - One IDA / 61180 Aquatic Resources Post Open - National 100,000.00 0.00 Canceled 2018-12-07 2019-02-01 2019-05-02 in Houay Nonglom, Nongbok Quotations Envelope Management District, KHammouane Province: Lot 1 Page 1 LA-MONRE-72804-CW-RFQ / C3.1.2-W-005: Improved Floodplain and Request for Single Stage - One Rehabilitation of Floodgates IDA / 61180 Aquatic Resources Post Open - National 80,000.00 0.00 Canceled 2018-12-07 2019-02-01 2019-05-02 Quotations Envelope in Xaibouly District, Management Savannakhet Province: Lot 5 LA-MONRE-72801-CW-RFQ / C3.1.2-W-002: Improved Floodplain and Rehabilitation of Floodgates Request for Single Stage - One IDA / 61180 Aquatic Resources Post Open - National 100,000.00 0.00 Canceled 2018-12-07 2019-02-01 2019-05-02 in Houay Deuth 1, Nongbok Quotations Envelope Management District, KHammouane Province: Lot 2 LA-MONRE-72802-CW-RFQ / C3.1.2-W-003: Improved Floodplain and Rehabilitation of Floodgates Request for Single Stage - One IDA / 61180 Aquatic Resources Post Open - National 100,000.00 0.00 Canceled 2018-12-07 2019-02-01 2019-05-02 in Houay Deuth 2, Nongbok Quotations Envelope Management District, KHammouane Province:: Lot 3 C3.1.1-W-006 / Office Pending National Water Resources Request for Single Stage - One Renovation of Component IDA / 61180 Post Open - National 20,000.00 0.00 Implementati 2018-12-08 2019-02-08 2019-06-08 Management Quotations Envelope Mgt Office in DWR on C2-4-W004 / New Improved Floodplain and Pending Single Stage - One Construction of 3 Hydromet IDA / 61180 Aquatic Resources Post Request for Bids Open - National 260,000.00 0.00 Implementati 2019-04-30 2019-05-05 2019-06-16 2019-07-16 2019-08-20 2020-02-16 Envelope offices Management on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2.3.0-G-04 / Supply Regional Water Resources Geography Data for C2.3- IDA / H6750 Prior Direct Selection Direct 0.00 18,037.25 Signed Management Modeling C2.4-ICB-G-001 / Supply and Installation of Hydrometeorological Regional Water Resources Open - Single Stage - One IDA / H6750 Prior Request for Bids 0.00 384,767.00 Signed Equipment and Data Management International Envelope Management Software with Technical Support C3.2.0-G-04 / Supply of Regional Water Resources 5,500 Kilos of PNG1-R1 Rice IDA / H6750 Prior Direct Selection Direct 0.00 4,742.43 Signed Management Seeds for Component 3.2 LA-MONRE-72795-GO-RFB Under / C2.2-G-002: Laboratory National Water Resources Single Stage - One IDA / 61180 Post Request for Bids Open - National 220,000.00 0.00 Implementati 2018-08-10 2018-08-15 2018-09-26 2018-10-26 2018-11-30 2019-05-29 Furniture-Customized and Management Envelope on Specialized LA-MONRE-72797-GO-DIR / Under C2.3-G-002: Data on National Water Resources IDA / 61180 Post Direct Selection Direct 30,000.00 0.00 Implementati 2018-09-03 2018-09-08 2018-10-13 2019-04-11 Geography and River Management on Network LA-MONRE-72799-GO-RFB / C3.1.2-G-012: Pontoon Mounted Electric Centrifugal Pump (75KW) for Irrigation Improved Floodplain and Under Single Stage - One Pumping Stations in the IDA / 61180 Aquatic Resources Post Request for Bids Open - National 450,000.00 0.00 Implementati 2018-09-03 2018-09-08 2018-10-08 2018-10-18 2018-10-25 2019-04-23 Envelope Catchment of Xebangfai, Management on Nongbok District, Khammouane and Savannaketh Province: Lot 5 Page 2 LA-MONRE-72805-GO-RFB / C3.1.2-G-022: Construction Materials for Canal Improved Floodplain and Under Single Stage - One Improvement (Nongbok and IDA / 61180 Aquatic Resources Post Request for Bids Open - National 350,000.00 0.00 Implementati 2018-10-01 2018-10-05 2018-11-05 2018-11-09 2018-11-14 2018-12-14 Envelope Xebangfai District, Management on Khammouane Province: Lot 5 LA-MONRE-72807-GO-RFB / C3.1.2-G-028: Construction Improved Floodplain and Pending Materials for Canal Single Stage - One IDA / 61180 Aquatic Resources Post Request for Bids Open - National 180,000.00 0.00 Implementati 2018-10-01 2018-10-05 2018-11-05 2018-11-09 2018-11-14 2018-12-14 Improvement (Xaibouly Envelope Management on District, Savannakhet Province): Lot 6 LA-MONRE-72808-GO-RFQ Improved Floodplain and Under Request for Single Stage - One / C3.1.2-G-027: Office IDA / 61180 Aquatic Resources Post Open - National 30,000.00 0.00 Implementati 2018-09-07 2018-10-17 2018-11-16 Quotations Envelope Equipment Management on LA-MONRE-72796-GO-DIR / Pending National Water Resources C2.3-G-003: Data on Hydro- IDA / 61180 Post Direct Selection Direct 10,000.00 0.00 Implementati 2018-10-01 2018-10-06 2018-11-10 2019-05-09 Management met with DMH on LA-MONRE-76685-GO-RFQ Pending National Water Resources Request for Single Stage - One / C2.1-G-001: Office IDA / 61180 Post Open - National 10,000.00 0.00 Implementati 2018-10-06 2018-12-07 2019-02-05 Management Quotations Envelope Equipment: Lot 1 on C 3.1.1-G002 / Office Pending Equipment for component National Water Resources Request for Single Stage - One IDA / 61180 Post Open - National 42,000.00 0.00 Implementati 2019-08-03 2019-09-28 2020-03-26 management, PoNRE, Management Quotations Envelope on DoNRE office C2.4-G007 / Purchase of replacement sensors and Improved Floodplain and Pending parts damaged during 2018 IDA / 61180 Aquatic Resources Post Direct Selection Direct 30,000.00 0.00 Implementati 2019-07-10 2019-07-15 2019-08-19 2020-02-15 flood in Sekong-Sedone Management on Station NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2/C/012 / Project Financial Regional Water Resources Least Cost Open - IDA / H6750 Prior 25,300.00 17,160.00 Canceled Audit Management Selection International MRC.C.28 / ANNUAL EXTERNAL INDEPENDENT Regional Water Resources Quality And Cost- Open - IDA / H6750 Prior 0.00 11,540.00 Signed AUDIT OF THE M- Management Based Selection International IWRM/MRC C.022 - 2 / Annual External Independent Audit Regional Water Resources Quality And Cost- Open - IDA / H6750 Prior 0.00 32,000.00 Signed of the M-IWRM/MRC Management Based Selection International Accounts 2014-2018 Page 3 C2.0.0-LCS-12 / Audit of Regional Water Resources Least Cost Open - IDA / H6750 Prior 0.00 13,199.00 Signed the Financial Statements Management Selection International C2.0.0-ICS-14 / Audit of the Financial Statements Regional Water Resources Least Cost Open - IDA / H6750 Prior 0.00 8,545.00 Signed from 01 January 2014 to 31 Management Selection International December 2014 C3.2.0-ICS-07 / Detailed Engineering Design and Construction Supervision for the Improvement and Consultant Regional Water Resources Open - Construction of Hatcheries in IDA / H6750 Prior Qualification 0.00 97,202.00 Signed Management International the provinces of Selection Champasack, Sekong and Attapeu for C3.2 Fisheries Management C2.0-ICS-017 / Audit of the Consultant Financial Statements for the Regional Water Resources Open - IDA / H6750 Prior Qualification 0.00 50,582.00 Signed period from 01 January Management International Selection 2015 to 31 March 2018 LA-MONRE-75073-CS-CQS / C3.1.1-CS-006: Technical Improved Floodplain and Consultant Under Assistance for Green Water IDA / 61180 Aquatic Resources Post Qualification Open - National 280,000.00 0.00 2018-09-14 2018-09-17 2018-10-17 2018-11-01 2018-11-21 2019-10-17 Implementation Resources Infrastructure Management Selection Investment LA-MONRE-76663-CS-CQS / C2.3.0-ICS-003: Detailed Designs Engineering and Consultant National Water Resources Under Construction Supervision IDA / 61180 Post Qualification Open - National 64,000.00 0.00 2018-09-14 2018-09-29 2018-11-12 2018-12-12 2019-01-16 2019-07-15 Management Implementation of the Modeling Development Selection and Water Resources Research Building LA-MONRE-75072-CS-QCBS / C3.1.1-CS-005: RTechnical Improved Floodplain and Quality And Cost- Assistance to Support River IDA / 61180 Aquatic Resources Prior Open - National 900,000.00 0.00 Canceled 2018-09-07 2018-09-17 2018-10-12 2018-11-11 2018-11-26 2018-12-26 2019-01-20 2020-02-20 Based Selection Basin Planning in Priority Management River Basins C2.3-ICS-007 / Decision Consultant National Water Resources Pending Support System Development IDA / 61180 Post Qualification Open - National 290,000.00 0.00 2019-07-08 2019-07-29 2019-09-11 2019-10-11 2019-11-15 2020-05-13 Management Implementation in Priority River Basins Selection Consultant C2.3-ICS-008 / Firm service National Water Resources Pending IDA / 61180 Post Qualification Open - National 290,000.00 0.00 2019-07-08 2019-07-29 2019-09-11 2019-10-11 2019-11-15 2020-05-13 for Models Development Management Implementation Selection C2.3-ICS-002 / Topographic Consultant and river cross-section National Water Resources Pending IDA / 61180 Post Qualification Open - National 160,000.00 0.00 2019-07-10 2019-07-10 2019-08-23 2019-09-12 2019-10-13 2020-04-10 survey: (XBF and XBH) and Management Implementation Selection (Sedon and Sekong) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual C3.1.1. - ICS - 001 / Regional Water Resources IDA / H6750 Prior Consultant Open 0.00 36,000.00 Signed National Project Coordinator Management Selection Page 4 C3.1.2-IC-002 / Individual Regional Water Resources SECRETARY/CASHIER FOR IDA / H6750 Prior Consultant Open 0.00 4,996.06 Signed Management COMPONENT 3.1.2 Selection C3.2-IC-008 / National Individual Financial Management Regional Water Resources IDA / H6750 Prior Consultant Open 0.00 24,926.86 Signed Consultant for Component 3- Management Selection 2 C 3.2.0_ICS-10 / Individual Regional Water Resources International Fishery IDA / H6750 Prior Consultant Open 0.00 51,935.00 Signed Management Management Consultant Selection C2.3-IC-SS-001 / Regional Water Resources International Modelling IDA / H6750 Prior Direct Selection Direct 0.00 32,240.00 Signed Management Advisor under C2.3 IC-002 / International Consultant for Hydro- Regional Water Resources IDA / H6750 Prior Direct Selection Direct 0.00 139,668.00 Signed Meteorology Early Warning Management Specialist C3.1.1-ICS-10 / Cashier of Individual Regional Water Resources C3.1.1 - PONRE - IDA / H6750 Prior Consultant Open 0.00 7,680.00 Signed Management Khammoune Selection C3.1.2-ICS-07 / Irrigation Regional Water Resources IDA / H6750 Prior Direct Selection Direct 0.00 26,648.58 Signed Pump Engineer Management 20 / International Modelling Regional Water Resources IDA / H6750 Prior Direct Selection Direct 100,000.00 32,240.00 Signed Consultant Management C2.11 / National Financial Individual Regional Water Resources Accounting Software IDA / H6750 Prior Consultant Open 20,000.00 31,000.00 Signed Management Consultant Selection C2.0.0-ICS-02 / Project Regional Water Resources Implementation Support IDA / H6750 Prior Direct Selection Direct 38,000.00 267,091.60 Signed Management Consultant C2.4.0-ICS-02 / National Individual Regional Water Resources Hydro-Meteorological Early IDA / H6750 Prior Consultant Open 112,100.00 16,576.32 Signed Management Warning Consultant Selection C3.1.2-ICS-04 / Senior Regional Water Resources IDA / H6750 Prior Direct Selection Direct 0.00 25,094.24 Signed Irrigation Engineer Management C3.1.2 - IC-SSS-006 / NATIONAL MONITORING Regional Water Resources IDA / H6750 Prior Direct Selection Direct 0.00 24,889.00 Signed & EVALUATION Management SPECIALIST FOR C3.1.2 C3.1.2 - SSS - 02 / Regional Water Resources International Fish Passage IDA / H6750 Prior Direct Selection Direct 0.00 30,310.00 Signed Management Consultant C2.0.0.ICS-15 - SSS / Regional Water Resources IDA / H6750 Prior Direct Selection Direct 24,000.00 53,020.00 Signed IWRMP SPECIALIST Management Individual C3.1.1-ICS-009 / National Regional Water Resources IDA / H6750 Prior Consultant Open 0.00 12,100.00 Signed Accountant Management Selection Page 5 C.052 - MRC / CNMC - National Advisor on the Regional Water Resources preparation of the National IDA / H6750 Prior Direct Selection Direct 0.00 9,500.00 Signed Management Indicative Plan (NIP) 2016- 2020 C.053 - MRC / National Advisor on the preparation Regional Water Resources IDA / H6750 Prior Direct Selection Direct 0.00 7,500.00 Signed of the National Indicative Management Plan (NIP) C.055 - MRC / VNMC - National Advisor on the Regional Water Resources preparation of the National IDA / H6750 Prior Direct Selection Direct 0.00 11,250.00 Signed Management Indicative Plan (NIP) 2016- 2020 C.054 - MRC / TNMC - National Advisor on the Regional Water Resources preparation of the National IDA / H6750 Prior Direct Selection Direct 0.00 11,250.00 Signed Management Indicative Plan (NIP) 2016- 2020 C3.2.0-ICS-17 / National Technical Advisor for the Regional Water Resources Fisheries Resources IDA / H6750 Prior Direct Selection Direct 0.00 19,840.00 Signed Management Management of Component 3.2 C.066 - MRC / Project Regional Water Resources IDA / H7620 Prior Direct Selection Direct 76,800.00 41,074.68 Signed Team Leader - MRC Management LA-MONRE-76665-CS-INDV Improved Floodplain and Individual Pending / C3.1.1-CS-012: National IDA / 61180 Aquatic Resources Post Consultant Open 28,000.00 0.00 2018-10-01 2018-11-15 2018-11-30 2018-12-31 2019-07-19 Implementation IWRM Specialist-Coordinator Management Selection LA-MONRE-76683-CS-INDV / C2.3-ICS-001: International Technical Individual Advisor on Modeling and National Water Resources Pending IDA / 61180 Post Consultant Open 90,000.00 0.00 2018-09-10 2018-10-16 2018-10-26 2018-11-15 2019-07-23 Decision Support System Management Implementation Selection (DSS) to Support water Resources Management and Planning Individual C3.1.1-CS-002 / National National Water Resources Pending IDA / 61180 Post Consultant Open 28,000.00 0.00 2018-11-26 2018-12-26 2019-01-05 2019-01-30 2019-10-07 IWRM Specialist Management Implementation Selection LA-MONRE-76661-CS-INDV Individual National Water Resources / C2.2-ICS-004: National IDA / 61180 Post Consultant Direct 20,000.00 0.00 Canceled 2018-09-21 2018-10-05 2018-10-12 2018-12-03 2019-04-02 Management expert on Bio-monitoring Selection Individual C2.3-ICS-001 / Modelling National Water Resources Pending IDA / 61180 Post Consultant Open 60,000.00 0.00 2019-06-20 2019-08-28 2019-09-25 2019-10-30 2020-04-27 Advisor Management Implementation Selection Page 6