PROCUREMENT PLAN (Textual Part) Project information: Mozambique - P171449 - Maputo Urban Transformation Project Project Implementation agency: Maputo Municipal Council Date of the Procurement Plan: January 2020 Period covered by this Procurement Plan: January – June 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento 5/2016 of March 8, 2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not Applicable PROCUREMENT Mozambique : Maputo Urban Transformation Project PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2020-01-09 2021-01-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171449 GPN Date: Project Name: Maputo Urban Transformation Project Loan / Credit No: IDA / V3130 Maputo Municipal Council Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MZ-CMM-187003-CW-RFB / Pending Drainage, sanitation, mobility, Single Stage - One 38,000,000.0 2024-12- IDA / V3130 Informal Settlement Upgrade Prior Request for Bids Open - International 0.00 Implementat 2021-04-23 2021-04-28 2021-06-09 2021-07-09 2021-08-13 public spaces and urban Envelope 0 30 ion equipment works MZ-CMM-186992-CW-RFB / Land demarcation works, Pending Single Stage - One 24,000,000.0 2024-09- Network and Urban IDA / V3130 Sustainable Urban Growth Prior Request for Bids Open - International 0.00 Implementat 2022-06-06 2022-06-11 2022-07-23 2022-08-22 2022-09-26 Envelope 0 20 Infrastructure Systems and ion Basic Urbanization in KaTembe GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Under MZ-CMM-168529-GO-RFQ / Project Implementation and Request for Single Stage - One IDA / V3130 Post Limited 10,000.00 0.00 Implementati 2020-05-12 2020-06-10 2020-07-07 2020-09-05 Supply of Office Furniture Institutional Support Quotations Envelope on Under MZ-CMM-186679-GO-RFB / Project Implementation and Single Stage - One IDA / V3130 Post Request for Bids Open - National 150,000.00 0.00 Implementati 2020-08-10 2020-09-02 2020-08-15 2020-09-03 2020-09-26 2020-09-22 2020-10-26 2020-10-30 2020-11-30 2021-05-29 Pickup Double Cab Vehicles Institutional Support Envelope on MZ-CMM-167802-GO-RFP / Project Implementation and Request for Single Stage - One Acquisition of office IDA / V3130 Post Limited 40,000.00 0.00 Canceled 2020-05-12 2020-06-10 2020-07-07 2021-01-03 Institutional Support Quotations Envelope equipment Pending MZ-CMM-200806-GO-RFQ / Request for Single Stage - One IDA / V3130 Informal Settlement Upgrade Post Limited 40,100.00 0.00 Implementati 2020-11-08 2021-01-03 2021-07-02 Protection Equipment Quotations Envelope on Pending MZ-CMM-200807-GO-RFB / Single Stage - One IDA / V3130 Informal Settlement Upgrade Post Request for Bids Open - National 200,000.00 0.00 Implementati 2020-11-03 2020-11-08 2020-12-20 2021-01-19 2021-02-23 2021-08-22 200 Hand Wash Systems Envelope on MZ-CMM-194418-GO-RFQ / Project Implementation and Request for Single Stage - One IDA / V3130 Post Limited 40,000.00 0.00 Canceled 2020-09-23 2020-11-09 2021-05-08 IT Equipment Institutional Support Quotations Envelope Under MZ-CMM-213554-GO-RFB / Project Implementation and Single Stage - One IDA / V3130 Post Request for Bids Open - National 200,000.00 0.00 Implementati 2021-01-22 2021-01-18 2021-01-27 2021-01-27 2021-03-10 2021-03-25 2021-04-22 2021-10-19 IT Equipment and Software's Institutional Support Envelope on MZ-CMM-215207-GO-RFQ / Pending Project Implementation and Request for Single Stage - One Financial management IDA / V3130 Post Limited 50,000.00 0.00 Implementati 2021-01-30 2021-03-22 2021-09-18 Institutional Support Quotations Envelope Software on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-CMM-187000-NC-RFB / Pending Single Stage - One Implementation of the Land IDA / V3130 Informal Settlement Upgrade Prior Request for Bids Open - International 2,500,000.00 0.00 Implementati 2021-04-23 2021-04-28 2021-06-09 2021-07-09 2021-08-13 2024-08-22 Envelope Regularization on MZ-CMM-187002-NC-RFB / Implementation of Social Pending Single Stage - One Inclusion Plans and IDA / V3130 Informal Settlement Upgrade Prior Request for Bids Open - International 1,500,000.00 0.00 Implementati 2021-04-23 2021-04-28 2021-06-09 2021-07-09 2021-08-13 2024-05-31 Envelope Combating Gender-based on Violence MZ-CMM-186998-NC-RFB / Pending Implementation of the Social Maputo City Center Single Stage - One IDA / V3130 Prior Request for Bids Open - International 1,500,000.00 0.00 Implementati 2021-02-26 2021-03-03 2021-04-14 2021-05-14 2021-06-18 2023-12-22 Inclusion Plan in the Maputo Rehabilitation Envelope on Downtown area MZ-CMM-186995-NC-RFB / Pending Implementation of Regulatory Maputo City Center Single Stage - One IDA / V3130 Post Request for Bids Open - International 500,000.00 0.00 Implementati 2021-02-22 2021-02-27 2021-04-10 2021-05-10 2021-06-14 2023-12-22 and Institutional Drainage Rehabilitation Envelope on Reforms MZ-CMM-186990-NC-RFB / Pending Implementation of Reform to IDA / V3130 Sustainable Urban Growth Post Request for Bids 500,000.00 0.00 Implementati 2021-02-12 2021-02-17 2021-03-31 2021-07-18 2022-01-14 the construction licenses and on the issuance of DUATs MZ-CMM-186985-NC-RFB / Pending Implementation of Land Value Single Stage - One IDA / V3130 Sustainable Urban Growth Post Request for Bids Open - International 300,000.00 0.00 Implementati 2021-08-20 2021-08-25 2021-10-06 2021-11-05 2021-12-10 2024-09-30 Capture Instruments in Envelope on KaTembe MZ-CMM-186675-NC-RFB / Pending Project Implementation and Single Stage - One Implementation of Addressing IDA / V3130 Post Request for Bids Open - International 100,000.00 0.00 Implementati 2020-08-30 2020-09-04 2020-10-16 2020-11-15 2020-12-20 2023-11-30 Institutional Support Envelope System on Page 1 MZ-CMM-186987-NC-RFB / Pending Implementation of the Social Single Stage - One IDA / V3130 Sustainable Urban Growth Post Request for Bids Open - International 500,000.00 0.00 Implementati 2021-01-31 2021-02-05 2021-03-19 2021-04-18 2021-05-23 2023-12-22 Inclusion Plan at KaTembe Envelope on district MZ-CMM-186600-NC-RFB / Pending Implementation of the Multi- Single Stage - One IDA / V3130 Sustainable Urban Growth Post Request for Bids Open - International 200,000.00 0.00 Implementati 2020-10-30 2020-11-04 2020-12-16 2021-01-15 2021-02-19 2023-12-29 annual Expenditure Plan and Envelope on Programmatic budget MZ-CMM-186631-NC-RFB / Pending Project Implementation and Single Stage - One Implementation of the Unique IDA / V3130 Post Request for Bids Open - International 300,000.00 0.00 Implementati 2020-08-30 2020-09-04 2020-10-16 2020-11-15 2020-12-20 2023-12-20 Institutional Support Envelope Social Registry on MZ-CMM-186996-NC-RFB / Implementation of the Pending Maputo City Center Single Stage - One Reforms of IPRA, Physical- IDA / V3130 Post Request for Bids Open - International 1,000,000.00 0.00 Implementati 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2024-12-30 Rehabilitation Envelope Fiscal Registry and generic on Values Plant MZ-CMM-186674-NC-RFB / Pending Project Implementation and Single Stage - One Implementation of the Remote IDA / V3130 Post Request for Bids Open - International 100,000.00 0.00 Implementati 2020-08-25 2020-08-30 2020-10-11 2020-11-10 2020-12-21 2023-11-30 Institutional Support Envelope Urban Soil Monitoring System on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-CMM-168538-CS-QCBS / Consulting Services to Quality And Cost- Under prepare studies and projects IDA / V3130 Informal Settlement Upgrade Prior Open - International 1,500,000.00 0.00 2020-07-13 2020-04-24 2020-08-03 2020-05-18 2020-09-16 2020-11-05 2020-10-14 2020-11-13 2020-12-18 2021-01-22 2022-09-14 Based Selection Implementation on integrated intervention of informal settlements MZ-CMM-168537-CS-QCBS / Consultancy Services to Quality And Cost- Pending prepare studies and projects IDA / V3130 Sustainable Urban Growth Prior Open - International 750,000.00 0.00 2020-06-29 2020-07-20 2020-09-02 2020-09-30 2020-10-30 2020-12-04 2021-01-08 2022-01-08 Based Selection Implementation for the sustainable development of Katembe MZ-CMM-168536-CS-QCBS / Consultancy Services for Project Implementation and Quality And Cost- Pending addressing, preparing, IDA / V3130 Prior Open - International 500,000.00 0.00 2020-06-22 2020-07-13 2020-08-26 2020-09-23 2020-10-23 2020-11-27 2021-01-01 2022-01-01 Institutional Support Based Selection Implementation updating and expanding the physical and fiscal registration MZ-CMM-168539-CS-QCBS / Consultancy Services for Maputo City Center Quality And Cost- Under IDA / V3130 Prior Open - International 500,000.00 0.00 2020-06-10 2020-04-24 2020-07-01 2020-08-14 2020-09-11 2020-10-11 2020-11-15 2020-12-20 2022-08-12 drainage studies and projects Rehabilitation Based Selection Implementation for Baixa da Cidade MZ-CMM-168535-CS-QCBS / Consultancy Services to Project Implementation and Quality And Cost- Under IDA / V3130 Post Open - International 100,000.00 0.00 2020-05-20 2020-08-12 2020-06-10 2020-07-24 2020-08-21 2020-09-20 2020-10-25 2020-11-29 2021-11-29 develop unified social Institutional Support Based Selection Implementation Municipal cadaster. MZ-CMM-169355-CS-QCBS / Consulting Services Urban Maputo City Center Quality And Cost- IDA / V3130 Prior Open - International 500,000.00 0.00 Under Review 2020-04-27 2020-05-18 2020-07-01 2020-07-29 2020-08-28 2020-10-02 2020-11-06 2021-11-06 mobility studies and project Rehabilitation Based Selection for Baixa da Cidade MZ-CMM-169356-CS-QCBS / Consulting services for Maputo City Center Quality And Cost- Under public spaces and urban IDA / V3130 Prior Open - International 500,000.00 0.00 2020-04-27 2020-05-18 2020-07-01 2020-07-29 2020-08-28 2020-10-02 2020-11-06 2021-11-06 Rehabilitation Based Selection Implementation equipment studies and project for Baixa da Cidade MZ-CMM-171134-CS-QCBS / Development of Project Project Implementation and Quality And Cost- IDA / V3130 Post Open - International 50,000.00 0.00 Canceled 2020-05-03 2020-05-06 2020-05-24 2020-05-21 2020-07-07 2020-08-04 2020-09-03 2020-10-08 2020-11-12 2021-05-11 Information Management Institutional Support Based Selection System MZ-CMM-186410-CS-QCBS Quality And Cost- Pending / Works Supervision in IDA / V3130 Informal Settlement Upgrade Prior Open - International 1,900,000.00 0.00 2021-04-23 2021-05-14 2021-06-27 2021-07-25 2021-08-24 2021-09-28 2021-11-02 2024-11-01 Based Selection Implementation informal settlements MZ-CMM-186470-CS-QCBS / Development of Technical Maputo City Center Quality And Cost- Under Studies and Projects for IDA / V3130 Prior Open - International 1,000,000.00 0.00 2020-08-17 2020-10-27 2020-09-07 2020-10-28 2020-10-21 2020-11-18 2020-12-18 2021-01-22 2021-02-26 2022-02-26 Rehabilitation Based Selection Implementation Drainage and Sanitation for the Downtown area MZ-CMM-186481-CS-QCBS / Preparation of technical Maputo City Center Quality And Cost- Pending studies and projects for the IDA / V3130 Prior Open - International 1,000,000.00 0.00 2020-08-27 2020-09-17 2020-10-31 2020-11-28 2020-12-28 2021-02-01 2021-03-08 2022-03-08 Rehabilitation Based Selection Implementation improvement of public spaces and urban facilities MZ-CMM-186501-CS-QCBS Maputo City Center Quality And Cost- Pending IDA / V3130 Prior Open - International 2,250,000.00 0.00 2021-09-28 2021-10-19 2021-12-02 2021-12-30 2022-01-29 2022-03-05 2022-04-09 2024-12-24 / Works Supervision Rehabilitation Based Selection Implementation MZ-CMM-186533-CS-QCBS / Consulting services for Updating the Register, Quality And Cost- Pending Revising the Urban IDA / V3130 Sustainable Urban Growth Prior Open - International 500,000.00 0.00 2020-08-12 2020-09-02 2020-10-16 2020-11-13 2020-12-13 2021-01-17 2021-02-21 2022-02-21 Based Selection Implementation Management Plan, Preparation of PPs and Safeguards Instruments MZ-CMM-186540-CS-QCBS / Technical Studies and Quality And Cost- Pending Executive Project for IDA / V3130 Sustainable Urban Growth Prior Open - International 1,000,000.00 0.00 2021-07-07 2021-07-28 2021-09-10 2021-10-08 2021-11-07 2021-12-12 2022-01-16 2023-01-16 Based Selection Implementation Infrastructures Development in KaTembe Page 2 MZ-CMM-186554-CS-QCBS Quality And Cost- Pending / Works Supervision at IDA / V3130 Sustainable Urban Growth Prior Open - International 720,000.00 0.00 2022-06-06 2022-06-27 2022-08-10 2022-09-07 2022-10-07 2022-11-11 2022-12-16 2023-12-16 Based Selection Implementation KaTembe MZ-CMM-186629-CS-CQS / Consulting Services to support Consultant Project Implementation and Pending the implementation of the IDA / V3130 Post Qualification Open - International 170,000.00 0.00 2020-08-30 2020-09-20 2020-11-03 2020-12-03 2021-01-07 2023-12-20 Institutional Support Implementation Modernization of Selection Administrative Processes MZ-CMM-200796-CS-QCBS / Environmental and Social Quality And Cost- Pending IDA / V3130 Informal Settlement Upgrade Prior Open - International 500,000.00 0.00 2020-11-06 2020-11-27 2021-01-10 2021-02-07 2021-03-09 2021-04-13 2021-05-18 2022-05-18 Impact Assessment for Based Selection Implementation Components 1, 2 and 3 MZ-CMM-200797-CS-LCS / Project Implementation and Least Cost Under IDA / V3130 Post Open - National 300,000.00 0.00 2020-11-06 2020-10-24 2020-11-27 2020-10-27 2021-01-10 2021-02-07 2021-03-09 2021-04-13 2021-05-18 2021-11-14 External Auditing Institutional Support Selection Implementation MZ-CMM-200798-CS-QBS / Project Implementation and Quality Based Under IDA / V3130 Post Open - International 150,000.00 0.00 2020-11-06 2020-11-10 2020-11-27 2020-11-16 2021-01-10 2021-02-07 2021-03-09 2021-04-08 2021-05-13 2022-05-13 PBC's Verification Agent Institutional Support Selection Implementation MZ-CMM-213646-CS-QCBS / Consulting Services for Conception, Development and Implementation of an Project Implementation and Quality And Cost- IDA / V3130 Post Open - National 100,000.00 0.00 Under Review 2021-01-18 2021-01-19 2021-01-25 2021-03-01 2021-03-29 2021-04-28 2021-06-07 2021-07-12 2022-12-04 Integrated Information Institutional Support Based Selection Management System for Maputo Urban Transformation Project MZ-CMM-216360-CS-QCBS / Elaboration of Participatory Plans for Social Inclusion, Quality And Cost- Pending Gender Equality and for IDA / V3130 Informal Settlement Upgrade Prior Open - International 600,000.00 0.00 2021-01-29 2021-02-19 2021-04-04 2021-05-02 2021-06-01 2021-07-06 2021-08-10 2022-08-10 Based Selection Implementation Combating GBV for the Neighbourhoods in Informal Settlements INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual MZ-CMM-152216-CS-INDV / IDA / V3130 Informal Settlement Upgrade Prior Consultant Open 60,000.00 60,000.00 Signed 2020-01-10 2020-01-16 2020-02-28 2020-06-23 2020-03-20 2020-06-23 2020-04-24 2020-06-24 2021-04-24 Procurement Specialist Selection MZ-CMM-167544-CS-INDV / Individual Project Implementation and Senior Finance Municipal IDA / V3130 Post Consultant Open 60,000.00 152,000.00 Signed 2020-04-16 2020-04-18 2020-06-04 2020-08-20 2020-06-25 2020-10-06 2020-07-30 2020-10-08 2021-07-30 Institutional Support Management Advisor Selection Individual MZ-CMM-167545-CS-INDV / Project Implementation and Under IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-04-16 2020-04-21 2020-06-04 2020-06-25 2020-07-30 2021-07-30 Senior Urban Planning Advisor Institutional Support Implementation Selection Individual MZ-CMM-167546-CS-INDV / Project Implementation and Pending IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-06-03 2020-07-22 2020-08-12 2020-09-16 2021-09-16 Senior Governance Advisor Institutional Support Implementation Selection MZ-CMM-168533-CS-QCBS / Consultancy Services for the Individual Project Implementation and Under elaboration of legal and IDA / V3130 Post Consultant Open 100,000.00 0.00 2020-05-27 2020-10-01 2020-07-15 2020-08-05 2020-09-09 2021-03-08 Institutional Support Implementation technical studies for IPRA and Selection LVC revenues maximization MZ-CMM-171140-CS-INDV / Senior Technician in Spatial Individual Project Implementation and Under Planning and Urban Soil IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-05-05 2020-04-30 2020-06-23 2020-07-14 2020-08-18 2021-02-14 Institutional Support Implementation Management to integrate the Selection PTUM Technical Team MZ-CMM-171147-CS-INDV / Individual Project Implementation and Senior Technician in IDA / V3130 Post Consultant Open 60,000.00 67,500.00 Signed 2020-05-05 2020-04-30 2020-06-23 2020-08-28 2020-07-14 2020-09-02 2020-08-18 2020-09-30 2021-02-14 Institutional Support Architecture Selection Individual MZ-CMM-171150-CS-INDV / Project Implementation and Under IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-05-05 2020-04-30 2020-06-23 2020-11-03 2020-07-14 2020-11-05 2020-08-18 2021-02-14 Technical Team Leader Institutional Support Implementation Selection MZ-CMM-171151-CS-INDV / Individual Project Implementation and Under Senior Drain Technician of the IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-05-05 2020-04-30 2020-06-23 2020-09-16 2020-07-14 2020-11-05 2020-08-18 2021-02-14 Institutional Support Implementation technical team Selection MZ-CMM-171152-CS-INDV / Senior Technician in Social Individual Project Implementation and Under Inclusion and Gender to IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-06-02 2020-04-30 2020-07-21 2020-08-11 2020-09-15 2021-03-14 Institutional Support Implementation integrate the technical team Selection of PTUM Individual MZ-CMM-171156-CS-INDV / Project Implementation and Under IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-05-11 2020-04-30 2020-06-29 2020-07-20 2020-08-24 2021-02-20 Urban Mobility Consultant Institutional Support Implementation Selection MZ-CMM-172416-CS-INDV / Individual senior water and sanitation Project Implementation and Under IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-05-08 2020-05-08 2020-06-26 2020-08-25 2020-07-17 2020-08-21 2021-02-17 technician of the technical Institutional Support Implementation Selection team MZ-CMM-174529-CS-INDV / Individual consultancy for the elaboration of the Individual Under methodology for updating the IDA / V3130 Sustainable Urban Growth Post Consultant Open 60,000.00 0.00 2020-05-25 2020-05-21 2020-07-13 2020-08-03 2020-09-07 2021-03-06 Implementation physical tax register, the Selection generic figures map and the IPRA calculation Page 3 MZ-CMM-175939-CS-INDV / Individual Project Implementation and Under Senior Advisor for Gender and IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-06-02 2020-09-03 2020-07-21 2020-08-11 2020-09-15 2020-12-14 Institutional Support Implementation Social Inclusion Selection MZ-CMM-172422-CS-INDV / Individual Consultant for the Individual definition and implementation Project Implementation and IDA / V3130 Post Consultant Open 60,000.00 0.00 Canceled 2020-05-10 2020-05-08 2020-06-28 2020-07-19 2020-08-23 2021-02-19 of an integrated information Institutional Support Selection management system for the project MZ-CMM-176004-CS-INDV / Individual Project Implementation and Junior Technician in Social IDA / V3130 Post Consultant Open 30,000.00 58,618.26 Signed 2020-06-02 2020-06-04 2020-07-21 2020-09-02 2020-08-11 2020-09-08 2020-09-15 2020-09-21 2020-12-14 Institutional Support Inclusion and Gender Selection MZ-CMM-175981-CS-INDV / Individual Junior Water and Sanitation Project Implementation and IDA / V3130 Post Consultant Open 30,000.00 58,618.26 Signed 2020-06-02 2020-06-04 2020-07-21 2020-08-25 2020-08-11 2020-08-26 2020-09-15 2020-09-11 2020-12-14 Technician of the Project's Institutional Support Selection Technical Team MZ-CMM-176001-CS-INDV / Individual Junior Technician in Spatial Project Implementation and Under IDA / V3130 Post Consultant Open 30,000.00 0.00 2020-06-02 2020-06-04 2020-07-21 2020-08-11 2020-09-15 2020-12-14 Planning and Urban Soil Institutional Support Implementation Selection Management MZ-CMM-175990-CS-INDV / Individual Project Implementation and Junior Technician in IDA / V3130 Post Consultant Open 30,000.00 70,799.99 Signed 2020-06-02 2020-06-04 2020-07-21 2020-09-03 2020-08-11 2020-09-02 2020-09-15 2020-09-16 2020-12-14 Institutional Support Architecture Selection Individual MZ-CMM-175998-CS-INDV / Project Implementation and Under IDA / V3130 Post Consultant Open 30,000.00 0.00 2020-06-02 2020-06-04 2020-07-21 2020-08-11 2020-09-15 2020-12-14 Junior Drainage Technician Institutional Support Implementation Selection MZ-CMM-175992-CS-INDV / Individual Junior Technician of Mobility Project Implementation and Under IDA / V3130 Post Consultant 30,000.00 0.00 2020-06-02 2020-06-04 2020-07-21 2020-08-11 2020-09-15 2020-12-14 and Roads of the project's Institutional Support Implementation Selection Technical Team Individual MZ-CMM-186605-CS-INDV / Project Implementation and Under IDA / V3130 Post Consultant Open 120,000.00 0.00 2020-08-18 2020-09-14 2020-10-06 2020-10-27 2020-12-01 2022-11-21 Infrastructure Senior Advisor Institutional Support Implementation Selection MZ-CMM-186609-CS-INDV / Individual Senior Technical Advisor on Project Implementation and Under IDA / V3130 Post Consultant Open 120,000.00 0.00 2020-08-18 2020-10-07 2020-10-06 2020-10-27 2020-12-01 2022-11-21 Land Use Planning and Urban Institutional Support Implementation Selection Land Management MZ-CMM-186611-CS-INDV / Individual Project Implementation and Under Municipal Governance Senior IDA / V3130 Post Consultant Open 120,000.00 0.00 2020-08-19 2020-10-09 2020-10-07 2020-10-28 2020-12-02 2022-11-22 Institutional Support Implementation Advisor Selection Individual MZ-CMM-186617-CS-INDV / Project Implementation and Pending IDA / V3130 Post Consultant Open 120,000.00 0.00 2020-08-19 2020-10-07 2020-10-28 2020-12-02 2022-12-01 Senior Social Inclusion Advisor Institutional Support Implementation Selection MZ-CMM-191816-CS-INDV / Individual Consulting services for Project Implementation and Under IDA / V3130 Post Consultant Open 10,000.00 0.00 2020-09-10 2020-09-09 2020-10-13 2020-10-22 2020-11-26 2021-05-25 preparation of Project Institutional Support Implementation Selection Implementation Manual Individual MZ-CMM-200800-CS-INDV / Project Implementation and Under IDA / V3130 Prior Consultant Open 36,000.00 0.00 2020-10-30 2020-10-27 2020-12-18 2021-01-08 2021-02-12 2021-08-11 Procurement Assistant Institutional Support Implementation Selection MZ-CMM-200801-CS-INDV / Individual Project Implementation and Pending Solid Waste Management IDA / V3130 Post Consultant Open 160,000.00 0.00 2020-11-06 2020-12-25 2021-01-15 2021-02-19 2021-08-18 Institutional Support Implementation Advisor Selection MZ-CMM-200802-CS-INDV / Individual Project Implementation and Pending Senior Technician for Urban IDA / V3130 Post Consultant Open 120,000.00 0.00 2020-11-06 2020-12-25 2021-01-15 2021-02-19 2021-08-18 Institutional Support Implementation Mobility Selection MZ-CMM-200803-CS-INDV / Individual Project Implementation and Pending Solid Waste Management IDA / V3130 Post Consultant Open 120,000.00 0.00 2020-11-06 2020-12-25 2021-01-15 2021-02-19 2021-08-18 Institutional Support Implementation Senior Technician Selection MZ-CMM-200804-CS-INDV / Individual Project Implementation and Pending Junior Technician for Urban IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-11-06 2020-12-25 2021-01-15 2021-02-19 2021-08-18 Institutional Support Implementation Mobility Selection MZ-CMM-200805-CS-INDV / Individual Project Implementation and Pending Solid Waste Management IDA / V3130 Post Consultant Open 60,000.00 0.00 2020-11-06 2020-12-25 2021-01-15 2021-02-19 2021-08-18 Institutional Support Implementation Junior Technician Selection MZ-CMM-200799-CS-INDV / Individual Project Implementation and Under Environmental and Social IDA / V3130 Post Consultant Open 30,000.00 0.00 2020-11-02 2020-11-10 2020-12-21 2021-01-11 2021-02-15 2022-02-15 Institutional Support Implementation Safeguards Assistant Selection Page 4