Costa Rica FCPF REDD READINESS (P123702) FCPF only: Readiness Package Assessment 30-Nov-2015 PROCUREMENT Costa Rica : Costa Rica FCPF REDD READINESS PLAN General Information Country: Costa Rica Banks Approval Date of the Original Procurement Plan: 2016-09-15 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-04-24 Project ID: P123702 GPN Date: Project Name: Costa Rica FCPF REDD READINESS Loan / Credit No: TF / 12692, TF / A2303 Executing Agency(ies): National Forestry Financing Fund WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CR-FONAFIFO-2225-GO-RFQ / Request for Single Stage - One Pending Computadoras de campo (Equipo TF / A2303 Post Open - National 5,000.00 0.00 2017-04-17 2017-06-12 2017-12-09 Quotations Envelope Implementation medición de campo) CR-FONAFIFO-2227-GO-RFQ / Request for Single Stage - One Under Escritorios (Modulares) TF / A2303 Post Open - National 4,200.00 0.00 2017-03-28 2017-05-23 2017-11-19 Quotations Envelope Implementation SNMCUDLT CR-FONAFIFO-2228-GO-RFQ / Request for Single Stage - One Under Archivo legal 4 gavetas, TF / A2303 Post Open - National 300.00 280.00 2016-10-25 2016-12-20 2017-06-18 Quotations Envelope Implementation SNMCDLT CR-FONAFIFO-2229-GO-RFP / Request for Single Stage - One Under TF / A2303 Post Open - National 75,900.00 0.00 2017-09-20 2017-07-07 2017-09-25 2017-11-06 2017-12-06 2018-01-10 2018-07-09 Vehículos Proposals Envelope Implementation CR-FONAFIFO-2234-GO-RFQ / Equipo de cómputo, impresora y Request for Single Stage - One Under microcomputadoras, 2016. TF / A2303 Post Open - National 8,500.00 0.00 2017-02-13 2017-04-10 2017-10-07 Quotations Envelope Implementation (Se separa del 2017 por motivos de presupuesto interno) CR-FONAFIFO-2236-GO-RFQ / Equipo de seguridad Meraki, Request for Single Stage - One Under 2016 TF / A2303 Post Open - National 15,000.00 0.00 2017-03-21 2017-05-16 2017-11-12 Quotations Envelope Implementation (Se separa del 2017 por motivos de presupuesto interno) CR-FONAFIFO-2237-GO-RFQ / Request for Single Stage - One Under Mesa para reuniones y video TF / A2303 Post Open - National 600.00 0.00 2017-02-20 2017-04-17 2017-10-14 Quotations Envelope Implementation conferencia Fonafifo, 2016. CR-FONAFIFO-2238-GO-RFQ / Servidores, renovación equipo de Request for Single Stage - One Under cómputo 2016, TF / A2303 Post Open - National 24,000.00 0.00 2017-03-28 2017-05-23 2017-11-19 Quotations Envelope Implementation (se separa del 2017 por motivos de presupuesto interno) CR-FONAFIFO-2241-GO-RFQ / Equipo de cómputo 2017, impresora láser, computador Request for Single Stage - One Under TF / A2303 Post Open - National 27,950.00 0.00 2017-06-12 2017-08-07 2018-02-03 portátil microcomputadoras. Quotations Envelope Implementation (se separa del 2016 por motivos de presupuesto interno) CR-FONAFIFO-2242-GO-RFQ / Request for Single Stage - One Pending Swich, renovación equipo de TF / A2303 Post Open - National 5,000.00 0.00 2017-08-15 2017-10-10 2018-04-08 Quotations Envelope Implementation cómputo 2017 CR-FONAFIFO-2243-GO-RFQ / Servidores, renovación equipo de Request for Single Stage - One Pending cómputo, Fonafifo 2017. TF / A2303 Post Open - National 24,000.00 0.00 2017-07-17 2017-09-11 2018-03-10 Quotations Envelope Implementation (por motivos de presupuesto interno se separa del año 20179. CR-FONAFIFO-2249-GO-RFQ / Request for Single Stage - One Under Equipo y mobiliario de oficina TF / A2303 Post Open - National 2,380.00 0.00 2017-03-21 2017-05-16 2017-11-12 Quotations Envelope Implementation para SIMODICUTE. CR-FONAFIFO-2251-GO-RFQ / Request for Single Stage - One Pending TF / A2303 Post Open - National 8,300.00 0.00 2017-06-26 2017-08-21 2018-02-17 Central Telefónica Quotations Envelope Implementation CR-FONAFIFO-2342-GO-RFQ / Equipo de Cómputo Request for Single Stage - One Under SIMODICUTE (ArcGis, TF / A2303 Post Open - National 25,000.00 0.00 2017-07-04 2017-08-29 2018-02-25 Quotations Envelope Implementation computadoras, escritorio, laptop, video beam,) CR-FONAFIFO-2226-GO-RFQ / Request for Single Stage - One Under Servidores de almacenamiento TF / A2303 Post Open - National 5,000.00 0.00 2017-07-23 2017-09-17 2018-03-16 Quotations Envelope Implementation de datos (FONAFIFO). CR-FONAFIFO-2235-GO-RFQ / Switch, renovación equipo de Pending cómputo, 2016. TF / A2303 Post Direct Selection Direct 2,500.00 0.00 2017-01-18 2017-01-23 2017-02-27 2017-08-26 Implementation Por motivos de presupuesto interno se separa del 2017. CR-FONAFIFO-2239-GO-RFQ / Pantalla/Monitor, monitoreo TF / A2303 Post Direct Selection Direct 750.00 0.00 Canceled 2017-04-27 2017-05-02 2017-06-06 2017-12-03 tráfico red interna y rendimiento servidores. 2016. CR-FONAFIFO-2224-GO-DIR / TF / A2303 Post Direct Selection Direct 3,000.00 0.00 Canceled 2017-05-08 2017-05-13 2017-06-17 2017-12-14 Forcípulas dígitales CR-FONAFIFO-4235-GO-RFQ / Request for Single Stage - One Under Switch para cómputo, pantalla TF / A2303 Post Open - National 3,250.00 0.00 2017-04-08 2017-06-03 2017-11-30 Quotations Envelope Implementation monitor tráfico red interna. Page 1 CR-FONAFIFO-2123-GO-DIR / TF / A2303 Post Direct Selection Direct 4,000.00 0.00 Canceled 2017-05-24 2017-05-29 2017-07-03 2017-12-30 Hipsómetros Vertex CR-FONAFIFO-2253-GO-RFQ / Equipo para el sistema SINIA - SINAC (PC SIG, monitor SIG, Request for Single Stage - One Under TF / A2303 Post Open - National 40,573.12 0.00 2017-06-05 2017-07-31 2018-01-27 laptop, lector de disco, discos Quotations Envelope Implementation duros, ups, computadoras, licencias) CR-FONAFIFO-11539-GO-RFQ / Request for Single Stage - One Under TF / A2303 Post Limited 900.00 0.00 2017-12-06 2018-01-31 2018-07-30 Archivadores Dirección REDD+ Quotations Envelope Implementation CR-FONAFIFO-11543-GO-RFQ / Mesa para reuniones y sus Request for Single Stage - One Under TF / A2303 Post Limited 15,000.00 0.00 2017-06-19 2017-08-14 2018-02-10 respectivas sillas-Dirección Quotations Envelope Implementation REDD+ CR-FONAFIFO-11550-GO-RFQ / Request for Single Stage - One Pending TF / A2303 Post Open - National 6,000.00 0.00 2017-09-25 2017-11-20 2018-05-19 Laptop, videobeam Covirenas. Quotations Envelope Implementation CR-FONAFIFO-11534-GO-RFQ / Request for Single Stage - One Pending TF / A2303 Post Open - National 727.00 0.00 2017-12-10 2018-02-04 2018-08-03 Biblioteca Dirección REDD+ Quotations Envelope Implementation CR-FONAFIFO-11456-GO-RFQ / Request for Single Stage - One Under Equipo de cómputo para la TF / A2303 Post Open - National 22,686.00 0.00 2017-10-17 2017-12-12 2018-06-10 Quotations Envelope Implementation Dirección REDD+ CR-FONAFIFO-11457-GO-RFQ / Request for Single Stage - One Under TF / A2303 Post Open - National 690.00 0.00 2017-10-25 2017-12-20 2018-06-18 Cámara Fotográfica Quotations Envelope Implementation CR-FONAFIFO-35187-GO-RFQ / Drones para la toma de información geoespacial de Request for Single Stage - One Pending TF / A2303 Post Open - National 15,000.00 0.00 2018-01-09 2018-03-06 2018-04-26 plantaciones forestales con su Quotations Envelope Implementation respectivo sofware y capacitación. CR-FONAFIFO-4237-GO-RFQ / Request for Single Stage - One TF / A2303 Post Open - National 4,000.00 0.00 Canceled 2017-04-04 2017-05-30 2017-11-26 Hipsómetros Quotations Envelope CR-FONAFIFO-4238-GO-RFQ / Request for Single Stage - One TF / A2303 Post Open - National 3,000.00 0.00 Canceled 2017-04-24 2017-06-19 2017-12-16 Forcípulas Digitales Quotations Envelope CR-FONAFIFO-35227-GO-RFQ / Request for Single Stage - One Pending Modular pequeño de madera para TF / A2303 Post Open - National 250.00 0.00 2018-01-23 2018-03-20 2018-04-20 Quotations Envelope Implementation ordenar expedientes. CR-FONAFIFO-35399-GO-RFQ / Request for Single Stage - One Pending Licencias Microsoft Office TF / A2303 Post Open - National 5,750.00 0.00 2018-03-19 2018-05-14 2018-06-13 Quotations Envelope Implementation Bussiness -Antivirus- CR-FONAFIFO-35400-GO-RFQ / Request for Single Stage - One Pending Licencia Stat Planet para el TF / A2303 Post Open - National 2,000.00 0.00 2017-12-10 2018-02-04 2018-03-22 Quotations Envelope Implementation analisis geoespacial, SIMOCUTE CR-FONAFIFO-35402-GO-RFQ / Arcgis el cual contemple mantenimiento por 2 años, Request for Single Stage - One Pending TF / A2303 Post Open - National 8,050.00 0.00 2018-03-11 2018-05-06 2018-05-30 extensión de Data Quotations Envelope Implementation Interoperability,mantenimiento de modulo y capacitación de Arcgis. CR-FONAFIFO-35407-GO-RFQ / Request for Single Stage - One Pending Sillas de espera para la TF / A2303 Post Open - National 600.00 0.00 2018-01-09 2018-02-27 2018-03-21 Quotations Envelope Implementation Secretaría REDD+ CR-FONAFIFO-36532-GO-RFQ / Request for Single Stage - One Pending Pantalla para proyecciones TF / A2303 Post Open - National 103.00 0.00 2018-02-12 2018-03-26 2018-04-26 Quotations Envelope Implementation videobeam CR-FONAFIFO-35211-GO-RFQ / Tabletas robustas para trabajo en campo para manitoreo de Request for Single Stage - One Pending TF / A2303 Post Open - National 11,500.00 0.00 2018-05-24 2018-07-07 2018-08-07 PSA (Fomento) y seguimiento en Quotations Envelope Implementation campo relacionadas al MGAS, SIS y MIRI CR-FONAFIFO-57490-GO-DIR / Compra de Imágenes Satelitales de alta resolución para eventos Pending de monitoreo de reduccciones de TF / A2303 Post Direct Selection Direct 52,000.00 0.00 2018-07-02 2018-07-07 2018-08-11 2018-11-13 Implementation emisiones para el reporte del país en diversos informes nacionales NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CR-FONAFIFO-2073-NC-RFQ / Request for Single Stage - One Pending Talleres con el sector TF / A2303 Post Open - National 13,650.00 0.00 2017-05-28 2017-07-23 2018-01-19 Quotations Envelope Implementation agroforestal (2016) CR-FONAFIFO-2075-NC-RFQ / Request for Single Stage - One Pending Talleres con el sector de las TF / A2303 Post Open - National 6,350.00 0.00 2017-05-30 2017-07-25 2018-01-21 Quotations Envelope Implementation PIR´s. (2016) CR-FONAFIFO-2082-NC-RFQ / Request for Single Stage - One Pending Talleres de priorización del PSA TF / A2303 Post Open - National 5,000.00 0.00 2017-09-25 2017-11-20 2018-05-19 Quotations Envelope Implementation (2017) CR-FONAFIFO-2084-NC-RFQ / Request for Single Stage - One Pending Taller para análisis de datos para TF / A2303 Post Open - National 4,000.00 0.00 2017-03-28 2017-05-23 2017-11-19 Quotations Envelope Implementation el SIMUDECUTE CR-FONAFIFO-2086-NC-RFQ / Taller para aspectos Request for Single Stage - One Pending TF / A2303 Post Open - National 4,000.00 0.00 2017-08-08 2017-10-03 2018-04-01 geoespaciales para el Quotations Envelope Implementation SIMUDECUTE Page 2 CR-FONAFIFO-2087-NC-RFQ / Taller para identificación de Request for Single Stage - One Pending arreglos institucionales en el TF / A2303 Post Open - National 4,000.00 0.00 2017-04-18 2017-06-13 2017-12-10 Quotations Envelope Implementation manejo de la información del SIMUDECUTE. CR-FONAFIFO-2351-NC-RFQ / Diálogo continuo y creación de Request for Single Stage - One Pending TF / A2303 Post Open - National 30,000.00 0.00 2017-06-27 2017-08-22 2018-02-18 capacidades al sector forestal y Quotations Envelope Implementation agroforestal (2017) CR-FONAFIFO-2353-NC-DIR / Taller para el diálogo contínuo y Under TF / A2303 Post Direct Selection Direct 29,000.00 0.00 2017-03-16 2017-03-21 2017-04-25 2017-10-22 creación de capacidades al Implementation sector campesino ICAES 2017 CR-FONAFIFO-2363-NC-RFQ / Servicio de impresión de Request for Single Stage - One Pending TF / A2303 Post Open - National 10,000.00 0.00 2017-05-02 2017-06-27 2017-12-24 materiales relativos al Quotations Envelope Implementation SIMOCUTE CR-FONAFIFO-2070-NC-DIR / Impresión y publicación de TF / A2303 Post Direct Selection Direct 35,000.00 0.00 Canceled 2017-05-26 2017-05-31 2017-07-05 2018-01-01 folletos y materiales informativos CR-FONAFIFO-2071-NC-DIR / Impresión de documentos finales TF / A2303 Prior Direct Selection Direct 60,000.00 0.00 Canceled 2017-11-30 2017-12-05 2018-01-09 2018-07-08 de Estrategia REDD CR-FONAFIFO-2072-NC-RFQ / Taller de lanzamiento de la TF / A2303 Post Direct Selection Direct 15,000.00 0.00 Canceled 2017-04-28 2017-05-03 2017-06-07 2017-12-04 Estrategia REDD+ CR-FONAFIFO-4241-NC-RFQ / Request for Single Stage - One Pending Taller de lanzamiento de la TF / A2303 Post Open - National 15,000.00 0.00 2017-05-01 2017-06-26 2017-12-23 Quotations Envelope Implementation Estrategia REDD+ CR-FONAFIFO-2078-NC-DIR / Talleres para consideraciones de TF / A2303 Post Direct Selection Direct 10,000.00 0.00 Canceled 2017-10-11 2017-10-16 2017-11-20 2018-05-19 género CR-FONAFIFO-2115-NC-RFQ / Actualización en tiempo real de SIGEREFO, tal que se garantice el acceso a la información para TF / A2303 Post Direct Selection Direct 10,000.00 0.00 Canceled 2017-06-29 2017-07-04 2017-08-08 2018-02-04 la toma oportuna de decisiones en el control y fiscalización de las actividades regeciales (2017) CR-FONAFIFO-4244-NC-RFQ / Actualización en tiempo real de SIGEREFO, tal que se garantice Request for Single Stage - One Pending el acceso a la información para TF / A2303 Post Open - National 10,000.00 0.00 2017-05-30 2017-07-25 2018-01-21 Quotations Envelope Implementation la toma oportuna de decisiones en el control y fiscalización de las actividades regenciales CR-FONAFIFO-2246-NC-DIR / Instalación de puntos de Redd TF / A2303 Post Direct Selection Direct 3,000.00 0.00 Canceled 2017-04-19 2017-04-24 2017-05-29 2017-11-25 con certificación. CR-FONAFIFO-4246-NC-RFQ / Instalación de puntos de red con Request for Single Stage - One Under TF / A2303 Post Open - National 3,000.00 0.00 2017-08-01 2017-09-26 2018-03-25 certificación; proyecto Estrategia Quotations Envelope Implementation REDD+ CR-FONAFIFO-2340-NC-RFQ / Almacenamiento de datos TF / A2303 Post Direct Selection Direct 400.00 0.00 Canceled 2017-04-20 2017-04-25 2017-05-30 2017-11-26 SNMCUDLT CR-FONAFIFO-2116-NC-RFQ / Visor (Informático para dar TF / A2303 Post Direct Selection Direct 5,000.00 0.00 Canceled 2017-05-31 2017-06-05 2017-07-10 2018-01-06 mantenimiento y actualización del visor geográfico) CR-FONAFIFO-4288-NC-RFQ / Request for Single Stage - One Pending TF / A2303 Post Open - National 5,000.00 0.00 2017-05-22 2017-07-17 2018-01-13 Visor Informático, pág web Quotations Envelope Implementation CR-FONAFIFO-2360-NC-DIR / Talleres de presentación y retroalimentación con gobierno, academia y sector privado para TF / A2303 Post Direct Selection Direct 8,000.00 0.00 Canceled 2017-09-21 2017-09-26 2017-10-31 2018-04-29 el diseño del sistema de monitoreo de las políticas ligadas a REDD+ CR-FONAFIFO-4289-NC-RFQ / Talleres de presentación y retroalimentación con gobierno, Request for Single Stage - One Pending academia y sector privado para TF / A2303 Post Open - National 8,000.00 0.00 2017-04-17 2017-06-12 2017-12-09 Quotations Envelope Implementation el diseño del sistema de monitoreo de las políticas ligadas a REDD+ CR-FONAFIFO-2361-NC-RFQ / Talleres para la presentación del mecanismo de trazabilidad de TF / A2303 Post Direct Selection Direct 6,000.00 0.00 Canceled 2017-04-20 2017-04-25 2017-05-30 2017-11-26 las tierras públicas en diversos usos de la tierra. CR-FONAFIFO-4293-NC-RFQ / Talleres para la presentación del Request for Single Stage - One Pending mecanismo de trazabilidad de TF / A2303 Post Open - National 6,000.00 0.00 2017-03-27 2017-05-22 2017-11-18 Quotations Envelope Implementation las tierras públicas en diversos usos de la tierra CR-FONAFIFO-2364-NC-DIR / Contratación de servicio de TF / A2303 Post Direct Selection Direct 1,920.00 0.00 Canceled 2017-06-22 2017-06-27 2017-08-01 2018-01-28 internet para el CENIGA CR-FONAFIFO-2365-NC-DIR / Reparación plotter para la impresión de mapas y otros TF / A2303 Post Direct Selection Direct 400.00 0.00 Canceled 2017-06-21 2017-06-26 2017-07-31 2018-01-27 materiales requeridos en el SIMOCUTE Page 3 CR-FONAFIFO-2362-NC-DIR / Contratación de servicios de TF / A2303 Post Direct Selection Direct 3,000.00 0.00 Canceled 2017-05-25 2017-05-30 2017-07-04 2017-12-31 hosting para albergar información del CENIGA CR-FONAFIFO-2080-NC-RFQ / Talleres para capacitación de los TF / A2303 Post Direct Selection Direct 5,000.00 0.00 Canceled 2017-03-31 2017-04-05 2017-05-10 2017-11-06 Covirenas (2016) CR-FONAFIFO-2461-NC-RFQ / Request for Single Stage - One Suministros varios para equipo TF / A2303 Post Open - National 1,394.04 0.00 Canceled 2017-03-05 2017-04-30 2017-10-27 Quotations Envelope de oficina CR-FONAFIFO-4242-NC-RFQ / Request for Single Stage - One Talleres para consideraciones de TF / A2303 Post Open - National 10,000.00 0.00 Canceled 2017-05-22 2017-07-17 2018-01-13 Quotations Envelope género CR-FONAFIFO-4300-NC-RFQ / Request for Single Stage - One Talleres para capacitación de los TF / A2303 Post Open - National 5,000.00 0.00 Canceled 2017-04-25 2017-06-20 2017-12-17 Quotations Envelope Covirenas 2016 CR-FONAFIFO-2081-NC-RFQ / Request for Single Stage - One Talleres para capacitación de los TF / A2303 Post Open - National 10,000.00 0.00 Canceled 2017-07-05 2017-08-30 2018-02-26 Quotations Envelope Covirenas (2017) CR-FONAFIFO-2112-NC-RFQ / Elaborar y ejecutar un plan de capacitación y participación comunitaria en el control y Request for Single Stage - One protección de los recursos TF / A2303 Post Open - National 15,000.00 0.00 Canceled 2017-04-05 2017-05-31 2017-11-27 Quotations Envelope naturales y la biodiversidad en las ASP, que contemple el desarrollo y validación de módulos de capacitación. (2016) CR-FONAFIFO-2114-NC-RFQ / Elaborar y ejecutar un plan de capacitación y participación comunitaria en el control y protección de los recursos Request for Single Stage - One TF / A2303 Post Open - National 15,000.00 0.00 Canceled 2017-12-10 2018-02-04 2018-08-03 naturales naturales y la Quotations Envelope biodiversidad en las ASP, que contemple el desarrollo y validación de módulos de capacitación. (2018) CR-FONAFIFO-11248-NC-RFQ / Request for Single Stage - One Pending Talleres de capacitación TF / A2303 Post Limited 20,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Quotations Envelope Implementation COVIRENAS. CR-FONAFIFO-2083-NC-RFQ / Talleres de capacidades en el Request for Single Stage - One TF / A2303 Post Open - National 21,000.00 0.00 Canceled 2017-05-30 2017-07-25 2018-01-21 Sistema de Monitoreo de Quotations Envelope Incendios Forestales (2017) CR-FONAFIFO-11434-NC-RFQ / Desarrollo e implementación de Request for Single Stage - One Pending las mesas técnicas de diseño y TF / A2303 Post Limited 7,600.00 0.00 2017-09-26 2017-11-21 2018-05-20 Quotations Envelope Implementation construcción de las mejoras del IFN. CR-FONAFIFO-11436-NC-RFQ / Análisis de los proyectos pilotos desarrollados en el marco del Request for Single Stage - One Pending TF / A2303 Post Open - National 10,200.00 0.00 2017-11-27 2018-01-22 2018-07-21 SIMOCUTE, para el uso de Quotations Envelope Implementation sensores remotos en el diseño de muestreo. CR-FONAFIFO-11438-NC-RFQ / Vincular los sistemas de Request for Single Stage - One Pending monitoro de políticas de la TF / A2303 Post Open - National 6,000.00 0.00 2017-11-01 2017-12-27 2018-06-25 Quotations Envelope Implementation Estrategia REDD+ y el SIMOCUTE. CR-FONAFIFO-11440-NC-RFQ / Desarrollo e implementación de 13 talleres en temas relacionados con el desarrollo e Request for Single Stage - One Pending implementación del SIMOCUTE TF / A2303 Post Open - National 20,500.00 0.00 2017-12-18 2018-02-12 2018-08-11 Quotations Envelope Implementation (IFN, sensores remotos, clasificacion uso de la tierra, MRV, seguimiento de politicas y sostenibilidad financiera) CR-FONAFIFO-11441-NC-RFQ / Publicaciones sobre las modificaciones a los manuales de campo y metodologia del Inventario Nacional Forestal, Request for Single Stage - One Pending TF / A2303 Post Open - National 13,500.00 0.00 2017-12-19 2018-02-13 2018-08-12 estudios pilotos con sensores Quotations Envelope Implementation remotos sobre la clasificacion de uso de la tierra a utilizar en el SIMOCUTE y los procesos de recomedaciones a CR-FONAFIFO-11348-NC-RFQ / Request for Single Stage - One Pending Análisis y actualización de TF / A2303 Post Limited 5,000.00 0.00 2017-12-05 2018-01-30 2018-07-29 Quotations Envelope Implementation imágines espaciales CR-FONAFIFO-11435-NC-RFQ / Inclusión de las 5 actividades REDD+, desarrollar capacidades y apoyar procesos del primer Request for Single Stage - One Pending evento de monitoreo del FREL y TF / A2303 Post Open - National 11,200.00 0.00 2017-11-29 2018-01-24 2018-07-23 Quotations Envelope Implementation posteriores recomentaciones en futuras actualizaciones en el marco del SIMOCUTE con el uso de sensores remotos. CR-FONAFIFO-11449-NC-RFQ / Servicios de apoyo en la implementación de talleres, para Request for Single Stage - One Pending TF / A2303 Post Open - National 30,000.00 0.00 2017-12-17 2018-02-11 2018-08-10 la coordinacion de consulta con Quotations Envelope Implementation territorios indigenas del SUR del pais CR-FONAFIFO-11452-NC-RFQ / Request for Single Stage - One Pending Servicios de traduccion oficial de TF / A2303 Post Limited 3,000.00 0.00 2018-04-23 2018-06-18 2018-12-15 Quotations Envelope Implementation documentos Page 4 CR-FONAFIFO-2074-NC-RFQ / Request for Single Stage - One Talleres con el sector indígena TF / A2303 Post Open - National 10,000.00 0.00 Canceled 2017-05-02 2017-06-27 2017-12-24 Quotations Envelope (2016) CR-FONAFIFO-2076-NC-RFQ / Request for Single Stage - One Talleres y diálogos con el sector TF / A2303 Post Open - National 20,000.00 0.00 Canceled 2017-06-06 2017-08-01 2018-01-28 Quotations Envelope privado (2016) CR-FONAFIFO-2107-NC-RFQ / Diálogo continuo y creación de Request for Single Stage - One TF / A2303 Post Open - National 30,000.00 0.00 Canceled 2017-06-05 2017-07-31 2018-01-27 capacidades al sector forestal y Quotations Envelope agroforestal (2016) CR-FONAFIFO-35196-NC-RFQ / Request for Single Stage - One Pending Servicio de traducción para TF / A2303 Post Open - National 15,000.00 0.00 2018-01-16 2018-02-07 2019-02-20 Quotations Envelope Implementation Estrategia REDD+ CR-FONAFIFO-2358-NC-RFQ / Talleres de presentación y retroalimentación con indígenas Request for Single Stage - One TF / A2303 Post Open - National 10,000.00 0.00 Canceled 2017-06-27 2017-08-22 2018-02-18 para el diseño del sistema de Quotations Envelope monitoreo de las políticas ligadas a REDD+ CR-FONAFIFO-2077-NC-RFQ / Request for Single Stage - One Pending Talleres y diálogos con el sector TF / A2303 Post Open - National 26,000.00 0.00 2018-01-14 2018-02-28 2018-08-27 Quotations Envelope Implementation privado (2017) CR-FONAFIFO-2359-NC-RFQ / Talleres de presentación y retroalimentación con pequeños Request for Single Stage - One productores forestales y TF / A2303 Post Open - National 10,000.00 0.00 Canceled 2017-06-13 2017-08-08 2018-02-04 Quotations Envelope agroforestales para el diseño del sistema de monitoreo de las políticas ligadas a REDD+ CR-FONAFIFO-11439-NC-RFQ / Desarrollo de mesas de Request for Single Stage - One Pending TF / A2303 Post Open - National 6,000.00 0.00 2018-05-28 2018-07-16 2019-01-12 discusión sobre la sostenibilidad Quotations Envelope Implementation financiera para el SIMOCUTE CR-FONAFIFO-36259-NC-RFQ / Desarrollo de mesas técnicas Request for Single Stage - One Pending TF / A2303 Post Open - National 13,000.00 0.00 2018-04-23 2018-06-11 2018-12-08 sobre discusión sobre arreglos Quotations Envelope Implementation institucionales para SIMOCUTE. CR-FONAFIFO-36535-NC-RFQ / Talleres y reuniones de trabajo con funcionarios, miembros Request for Single Stage - One Pending TF / A2303 Post Open - National 25,000.00 0.00 2018-04-21 2018-06-07 2019-03-20 CORAC, comunidades, Quotations Envelope Implementation instituciones públicas, ong´s y otros actores relevantes CR-FONAFIFO-36537-NC-RFQ / Diseño y publicación de la Guía Request for Single Stage - One Pending de planes específicos de TF / A2303 Post Open - National 9,000.00 0.00 2018-05-28 2018-07-17 2018-09-28 Quotations Envelope Implementation mitigación y adaptación de las ASP ante el cambio climático CR-FONAFIFO-37249-NC-RFQ / Servicios de impresión de Request for Single Stage - One Pending TF / A2303 Post Open - National 4,000.00 0.00 2018-02-26 2018-04-23 2018-07-18 materiales para las sesiones de Quotations Envelope Implementation capacitación y talleres ONF CR-FONAFIFO-37282-NC-RFQ / Taller de consulta de la propuesta de constitución del Request for Single Stage - One Pending clúster forestal de la región TF / A2303 Post Open - National 1,800.00 0.00 2018-04-23 2018-06-18 2018-09-05 Quotations Envelope Implementation Huetar Norte y 1 taller de socialización de la constitución del clúster. CR-FONAFIFO-37285-NC-RFQ / Taller de consulta del programa de formación y certificación de asesores en diseño y Request for Single Stage - One Pending construcción con madera y 1 TF / A2303 Post Open - National 1,800.00 0.00 2018-05-29 2018-07-24 2018-09-26 Quotations Envelope Implementation taller de socialización de resultados del programa de formación y certificación de asesores. CR-FONAFIFO-36536-NC-RFQ / Sociabilización de los productos, con funcionarios, miembros Request for Single Stage - One Pending TF / A2303 Post Open - National 5,000.00 0.00 2018-06-18 2018-08-03 2018-10-25 CORAC, comunidades, Quotations Envelope Implementation instituciones públicas, ong´s y otros actores relevantes. CR-FONAFIFO-36251-NC-RFQ / Request for Single Stage - One Pending Talleres para socialización de la TF / A2303 Post Open - National 15,000.00 0.00 2018-05-14 2018-07-02 2018-12-29 Quotations Envelope Implementation APP con las PIRs CR-FONAFIFO-54865-NC-DIR / Taller de consulta del diagnóstico, situación actual, plan estratégico y plan operativo Pending del clúster forestal en la Región TF / A2303 Post Direct Selection Direct 1,800.00 0.00 2018-08-23 2018-08-28 2018-10-02 2019-03-31 Implementation huetar Norte y 1 taller de socialización del plan estratégico y operativo del clúster forestal en la Región Huetar Norte CR-FONAFIFO-54866-NC-DIR / Taller de consulta del diagnóstico y 1 taller de socialización de Pending resultados del diagnóstico de TF / A2303 Post Direct Selection Direct 1,800.00 0.00 2018-07-26 2018-07-31 2018-09-04 2018-12-05 Implementation corto plazo para aumentar el uso de madera nacional en la industria de la construcción. CR-FONAFIFO-54868-NC-DIR / 1 taller de consulta del plan de acción de corto plazo y 1 taller Pending de socialización de resultados TF / A2303 Post Direct Selection Direct 1,800.00 0.00 2018-07-26 2018-07-31 2018-09-04 2018-10-25 Implementation del plan de acción para aumentar el uso de madera nacional en la industria de la construcción. Page 5 CR-FONAFIFO-54870-NC-DIR / Taller de consulta del diseño de Pending la plataforma en línea y 1 taller TF / A2303 Post Direct Selection Direct 1,800.00 0.00 2018-07-19 2018-07-24 2018-08-28 2018-11-14 Implementation de socialización de la plataforma en línea producida. CR-FONAFIFO-54445-NC-RFQ / Talleres para actividadesde seguimiento y coordinación con Request for Single Stage - One Pending los actores de tierras publicas TF / A2303 Post Open - National 15,000.00 0.00 2018-08-19 2018-10-10 2018-12-31 Quotations Envelope Implementation que estén vinculados al catastro de tierras del Patrimonio Natural del Estado CR-FONAFIFO-54446-NC-RFQ / Instalación de puntos de red con certificación, proyecto Estrategia Request for Single Stage - One Pending REDD+, (Plan de Adquisiciones, TF / A2303 Post Open - National 5,000.00 0.00 2018-05-21 2018-07-16 2018-08-23 Quotations Envelope Implementation proyecto Estrategia REDD+ / Renovación de equipo de cómputo, según PTIC 2015-2018) CR-FONAFIFO-54452-NC-DIR / Capacitación a instituciones Pending TF / A2303 Post Direct Selection Direct 3,500.00 0.00 2018-09-20 2018-09-25 2018-10-30 2018-11-07 vinculadas al reporte de REDD+ Implementation en le uso de software R. CR-FONAFIFO-2069-NC-RFQ / Actividades de capacitación Request for Single Stage - One sobre el sistema de monitoreo a TF / A2303 Post Open - National 5,000.00 0.00 Canceled 2017-03-27 2017-05-22 2017-11-18 Quotations Envelope funcionarios de FONAFIFO (2017) CR-FONAFIFO-4240-NC-RFQ / Impresión, publicación de Single Stage - One folletos y materiales informativos, TF / A2303 Post Request for Bids Open - National 95,000.00 0.00 Canceled 2017-05-24 2017-05-29 2017-07-10 2017-08-09 2017-09-13 2018-03-12 Envelope documentos finales de Estrategia REDD. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CR-FONAFIFO-2053-CS-CDS / Inventario y catastro de tierras Quality And Cost- Pending TF / A2303 Post Open - National 97,000.00 0.00 2017-10-03 2017-10-24 2017-12-07 2018-01-04 2018-02-03 2018-03-10 2018-04-14 2019-04-14 públicas en los diversos usos de Based Selection Implementation la tierra en Costa Rica (2017) CR-FONAFIFO-2062-CS-LCS / Pending Auditoría financiera de la TF / A2303 Post Least Cost Selection Open - National 12,000.00 0.00 2017-04-26 2017-05-17 2017-06-30 2017-07-28 2017-08-27 2017-10-01 2017-11-05 2018-05-04 Implementation Donación TF 0A2303. CR-FONAFIFO-2050-CS-CDS / Desarrollo de un marco de contabilidad para los productos Quality And Cost- maderables ("Harvested wood TF / A2303 Post Open - National 50,000.00 0.00 Canceled 2017-04-27 2017-05-18 2017-07-01 2017-07-29 2017-08-28 2017-10-02 2017-11-06 2018-11-06 Based Selection products") para guiar la estrategia de incremento de uso de la madera. CR-FONAFIFO-11296-CS-QCBS / Diseño del Sistema de Quality And Cost- Under Monitoreo de Incendios TF / A2303 Post Open - National 100,000.00 0.00 2017-11-30 2017-08-16 2017-12-21 2018-02-03 2018-03-03 2018-04-02 2018-05-07 2018-06-11 2019-06-11 Based Selection Implementation Forestales (Sistema Alerta Temprana) CR-FONAFIFO-2057-CS-QCBS / Establecimiento de parcela para la estimación del impacto Quality And Cost- del aprovechamiento forestal de TF / A2303 Post Open - National 95,000.00 0.00 Canceled 2017-04-28 2017-05-19 2017-07-02 2017-07-30 2017-08-29 2017-10-03 2017-11-07 2018-11-07 Based Selection bosques naturales sobre el stock de carbono, estructura y composición florística. CR-FONAFIFO-2055-CS-QCBS / Desarrollo del Sistema de Quality And Cost- TF / A2303 Post Open - National 200,000.00 0.00 Canceled 2017-04-19 2017-05-10 2017-06-23 2017-07-21 2017-08-20 2017-09-24 2017-10-29 2018-10-29 Monitoreo de Cambio de uso de Based Selection la Tierra (2017) CR-FONAFIFO-2117-CS-QCBS / Desarrollo del Sistema de Quality And Cost- TF / A2303 Post Open - National 180,000.00 0.00 Canceled 2018-08-16 2018-09-06 2018-10-20 2018-11-17 2018-12-17 2019-01-21 2019-02-25 2020-02-25 Monitoreo de Cambio de uso de Based Selection la Tierra (2018) CR-FONAFIFO-2118-CS-QCBS / Desarrollo de módulos de información para el Sistema de Quality And Cost- TF / A2303 Post Open - National 150,000.00 0.00 Canceled 2017-11-28 2017-12-19 2018-02-01 2018-03-01 2018-03-31 2018-05-05 2018-06-09 2019-06-09 Monitoreo de Cambio de uso de Based Selection la Tierra que responda a las necesidades de REDD+2018 CR-FONAFIFO-2056-CS-QCBS / Fortalecimiento de las capacidades del sistema de Quality And Cost- TF / A2303 Post Open - National 150,000.00 0.00 Canceled 2017-04-28 2017-05-19 2017-07-02 2017-07-30 2017-08-29 2017-10-03 2017-11-07 2018-11-07 trazabilidad de los productos Based Selection (Módulos de Industria Forestal) (2017) CR-FONAFIFO-11432-CS-QCBS / Desarrollo de una firma espectral para la identificación Quality And Cost- TF / A2303 Post Open - National 195,000.00 0.00 Canceled 2017-10-25 2017-11-15 2017-12-29 2018-01-26 2018-02-25 2018-04-01 2018-05-06 2019-05-06 de cultivos de palma, a travéz de Based Selection sensores remotos e in situ en Costa Rica. CR-FONAFIFO-2054-CS-CDS / Inventario y catastro de tierras Quality And Cost- TF / A2303 Post Open - National 97,000.00 0.00 Canceled 2017-07-26 2017-08-16 2017-09-29 2017-10-27 2017-11-26 2017-12-31 2018-02-04 2019-02-04 públicas en los diversos usos de Based Selection la tierra en Costa Rica (2018) CR-FONAFIFO-4384-CS-QCBS / Desarrollo de un nuevo sistema de monitoreo y verificación para Quality And Cost- plantaciones forestales y rá boles TF / A2303 Post Open - National 83,000.00 0.00 Canceled 2018-02-14 2018-03-07 2018-04-20 2018-05-18 2018-06-17 2018-07-22 2018-08-26 2019-08-26 Based Selection en sistemas agroforestales, financiados con el programa de Pago por Servicios Ambientales Page 6 CR-FONAFIFO-4409-CS-QCBS / Registro de reducción de Quality And Cost- Pending emisiones REDD+: para avanzar TF / A2303 Post Open - National 150,000.00 0.00 2018-07-19 2018-08-09 2018-09-22 2018-10-20 2018-10-31 2018-11-21 2018-11-29 2019-03-29 Based Selection Implementation hacia el registro de la C- Neutralidad. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual No objecion No. 027-2014 / Formulacion de la estrategia de Individual Consultant control, proteccion forestal, TF / 12692 Prior Open N 0.00 49,900.00 Signed 2014-05-07 2014-06-11 Selection control de la tala ilegal en Costa Rica No. 031-2014 / Desarrollo de un sistema digital de cadena de custodia aprovechamiento TF / 12692 Prior Direct Selection Direct N 0.00 54,516.00 Signed 2014-08-21 forestal contexto estrategia control tala ilegal CR-FONAFIFO-1867-CS-INDV / Apoyo en comunicación para el Individual Consultant Pending TF / A2303 Post Open 12,500.00 0.00 2018-03-06 2018-04-24 2018-05-15 2018-06-19 2018-12-16 fortalecimiento el desarrollo de la Selection Implementation Estrategia REDD+, 2018. CR-FONAFIFO-1881-CS-INDV / Individual Consultant Under 16-Apoyo a la Estrategia REDD+ TF / A2303 Prior Direct 24,000.00 0.00 2016-11-01 2016-11-11 2016-12-02 2017-01-06 2017-07-05 Selection Implementation 2016. CR-FONAFIFO-1893-CS-INDV / Individual Consultant Pending Apoyo legal al sector sociedad TF / A2303 Post Open 18,000.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 Selection Implementation civil y terrenos en sobreuso. CR-FONAFIFO-1895-CS-INDV / Fortalecimiento para el desarrollo del sistema multicriterio y modelo de decisiones Individual Consultant Pending TF / A2303 Post Open 35,000.00 0.00 2017-03-23 2017-05-11 2017-06-01 2017-07-06 2018-01-02 geoespacial, que permita la Selection Implementation ubicación y aplicación de los criterios de priorización e impacto del PSA. CR-FONAFIFO-1896-CS-INDV / Individual Consultant Pending Comprobación de campo para la TF / A2303 Post Direct 35,000.00 0.00 2017-07-03 2017-07-13 2017-08-03 2017-09-07 2018-03-06 Selection Implementation priorización del PSA. CR-FONAFIFO-1899-CS-INDV / Apoyo al Sistema Nacional de Individual Consultant Pending Monitoreo de la Dinamica de TF / A2303 Post Open 12,000.00 0.00 2017-06-01 2017-07-20 2017-08-10 2017-09-14 2018-03-13 Selection Implementation Cobertura del Uso de la Tierra y Ecosistemas (SIMODICUTE) CR-FONAFIFO-1900-CS-INDV / Actualización del Sistema de Indicadores ambientales del CENIGA, para el Sistema Individual Consultant Under TF / A2303 Post Open 20,000.00 0.00 2017-05-10 2017-06-29 2017-06-28 2017-07-19 2017-08-23 2018-02-19 Nacional de Monitoreo de la Selection Implementation Dinamica de Cobertura del Uso de la Tierra y Ecosistemas (SIMODICUTE) CR-FONAFIFO-1902-CS-INDV / Fiscalización de las actividades Individual Consultant Under forestales ampliando TF / A2303 Post Open 30,000.00 0.00 2017-06-21 2017-08-09 2017-08-30 2017-10-04 2018-04-02 Selection Implementation inspecciones a proyectos gerenciales, 2017 CR-FONAFIFO-1904-CS-INDV / Fiscalización de las actividades Individual Consultant Under forestales ampliando TF / A2303 Post Open 35,000.00 0.00 2017-05-24 2017-07-12 2017-08-02 2017-09-06 2018-03-05 Selection Implementation inspecciones a proyectos regenciales. CR-FONAFIFO-1910-CS-INDV / á eas de Digitalización de r Individual Consultant Pending bosque y base de datos de TF / A2303 Post Open 45,000.00 0.00 2017-06-01 2017-07-20 2017-08-10 2017-09-14 2018-03-13 Selection Implementation planes de manejo forestal 1997- 2014 CR-FONAFIFO-1959-CS-INDV / Armonización del Plan Nacional de Desarrollo Forestal y REDD+ Individual Consultant Under TF / A2303 Post Open 45,000.00 0.00 2017-04-05 2017-05-24 2017-06-14 2017-07-19 2018-01-15 (incluyendo evaluación de Selection Implementation desempeño, inclusión de capítulo indígena y capítulo ASP) (2017) CR-FONAFIFO-1967-CS-INDV / Individual Consultant Under Actualización del Portal del TF / A2303 Post Open 30,000.00 0.00 2017-06-22 2017-06-30 2017-08-10 2017-08-31 2017-10-05 2018-04-03 Selection Implementation SINIA CR-FONAFIFO-1973-CS-INDV / Articulación de resultados de Individual Consultant Pending TF / A2303 Post Open 30,000.00 0.00 2017-11-22 2018-01-10 2018-01-31 2018-03-07 2018-09-03 consultorías del sector forestal a Selection Implementation la estrategia REDD+ (2017) CR-FONAFIFO-1977-CS-INDV / Apoyo legal a procesos internos en Fonafifo para el ingreso de Individual Consultant Pending contratos de PSA, en el marco TF / A2303 Post Open 42,400.00 0.00 2017-04-12 2017-05-31 2017-06-21 2017-07-26 2018-01-22 Selection Implementation de la implementación del Programa Reducción de Emisiones 2017, CR-FONAFIFO-2119-CS-INDV / Diseño e implementación de la Individual Consultant Pending estrategia de comunicación del TF / A2303 Post Open 24,000.00 0.00 2017-06-29 2017-08-17 2017-09-07 2017-10-12 2018-04-10 Selection Implementation Sistema Nacional de Información Ambiental (SINIA) CR-FONAFIFO-2462-CS-INDV / Individual Consultant Pending Fortalecimiento del desarrollo de TF / A2303 Post Open 24,000.00 0.00 2017-03-23 2017-05-11 2017-06-01 2017-07-06 2018-01-02 Selection Implementation la Estrategia REDD 2017 Page 7 CR-FONAFIFO-1901-CS-INDV / Apoyo al sistema nacional de Individual Consultant Under TF / A2303 Post Open 48,000.00 0.00 2017-05-31 2017-07-19 2017-08-09 2017-04-28 2017-09-13 2018-03-12 cambio de uso de la tierra y Selection Implementation ecosistemas CR-FONAFIFO-2063-CS-CDS / Auditoría Financiera de la TF / A2303 Post Direct Selection Direct 6,500.00 0.00 Canceled 2018-03-13 2018-03-23 2018-05-27 2018-11-23 Donación TF 0A2303 (2018) CR-FONAFIFO-1980-CS-CDS / Desarrollo de un nuevo sistema de monitoreo y verificación para plantaciones forestales y rá boles TF / A2303 Prior Direct Selection Direct 168,000.00 0.00 Canceled 2017-06-14 2017-06-24 2017-08-28 2018-02-24 en sistemas agroforestales, financiados con el programa de Pago por Servicios Ambientales (2017) CR-FONAFIFO-1912-CS-INDV / Sistematización y desarrollo de los planes de gestión, para la incorporación de las restantes Individual Consultant TF / A2303 Post Open 35,000.00 0.00 Canceled 2017-04-28 2017-06-16 2017-07-07 2017-08-11 2018-02-07 medidas de mitigación de Selection REDD+ en el Nivel Nacional de Referencia de Emisiones de Degradación. CR-FONAFIFO-1883-CS-INDV / Apoyo administrativo a la Individual Consultant donación para el fortalecimiento TF / A2303 Prior Direct 75,000.00 0.00 Canceled 2017-12-28 2018-01-07 2018-01-28 2018-03-04 2018-08-31 Selection el desarrollo de la Estrategia REDD+, 2017-2018 CR-FONAFIFO-1866-CS-INDV / Apoyo en comunicación para el Individual Consultant TF / A2303 Prior Direct 48,000.00 0.00 Canceled 2016-10-28 2016-11-07 2016-11-28 2017-01-02 2017-07-01 fortalecimiento el desarrollo de la Selection Estrategia REDD+, 2017. CR-FONAFIFO-1864-CS-INDV / Asesoría en aspectos indígenas Individual Consultant para el fortalecimiento el TF / A2303 Prior Direct 40,000.00 0.00 Canceled 2016-11-17 2016-11-27 2016-12-18 2017-01-22 2017-07-21 Selection desarrollo de la Estrategia REDD+ CR-FONAFIFO-1869-CS-INDV / Individual Consultant TF / A2303 Prior Direct 48,000.00 0.00 Canceled 2017-01-11 2017-01-21 2017-02-11 2017-03-18 2017-09-14 Apoyo al sistema de MRV 2017. Selection CR-FONAFIFO-4399-CS-INDV / Apoyo al sistema de MRV para Individual Consultant Pending TF / A2303 Post Open 48,000.00 0.00 2017-03-21 2017-05-09 2017-05-30 2017-07-04 2017-12-31 el fortalecimiento el desarrollo de Selection Implementation la Estrategia REDD+. CR-FONAFIFO-1870-CS-INDV / Coordinación Estrategia REDD+ Individual Consultant para el fortalecimiento el TF / A2303 Prior Direct 40,000.00 0.00 Canceled 2016-10-13 2016-10-23 2016-11-13 2016-12-18 2017-06-16 Selection desarrollo de la Estrategia REDD+ 2017 CR-FONAFIFO-2457-CS-INDV / Apoyo al componente social para Individual Consultant TF / A2303 Prior Direct 45,000.00 0.00 Canceled 2017-01-03 2017-01-13 2017-02-03 2017-03-10 2017-09-06 el fortalecimiento el desarrollo de Selection la Estrategia REDD+, 2017 CR-FONAFIFO-4403-CS-INDV / Apoyo al componente social para Individual Consultant Pending TF / A2303 Post Open 45,000.00 0.00 2017-03-22 2017-05-10 2017-05-31 2017-07-05 2018-01-01 el fortalecimiento el desarrollo de Selection Implementation la Estrategia REDD+. CR-FONAFIFO-1885-CS-INDV / Asesor legal para el Individual Consultant TF / A2303 Prior Direct 35,000.00 0.00 Canceled 2016-12-20 2016-12-30 2017-01-20 2017-02-24 2017-08-23 fortalecimiento el desarrollo de la Selection Estrategia REDD+, 2016 CR-FONAFIFO-2058-CS-QCBS / Modelo espacial como herramienta de sustento para la TF / A2303 Prior Direct Selection Direct 150,000.00 0.00 Canceled 2016-10-19 2016-10-29 2017-01-02 2017-07-01 Estrategia REDD+, con n é fasis en el riesgo de deforestación y beneficios-no carbono CR-FONAFIFO-2049-CS-CDS / Registro de reducción de emisiones REDD+: Para avanzar TF / A2303 Prior Direct Selection Direct 198,000.00 0.00 Canceled 2017-05-30 2017-06-09 2017-08-13 2018-02-09 hacia el registro de la C- Neutralidad. CR-FONAFIFO-4397-CS-INDV / Sistematización y desarrollo de los planes de gestión, para la incorporación de las restantes Individual Consultant Under TF / A2303 Post Direct 35,000.00 0.00 2017-01-10 2017-01-20 2017-02-10 2017-01-23 2017-03-17 2017-09-13 medidas de mitigación de Selection Implementation REDD+ en el Nivel Nacional de Referencia de Emisiones de Degradación. CR-FONAFIFO-4394-CS-INDV / Apoyo en comunicación y Individual Consultant Under coordinación del componente TF / A2303 Post Direct 48,000.00 0.00 2017-01-26 2017-02-05 2017-02-26 2017-01-25 2017-04-02 2017-09-29 Selection Implementation social para el desarrollo de la Estrategia REDD+. CR-FONAFIFO-4396-CS-INDV / Asesoría en aspectos indígenas Individual Consultant Under para el fortalecimiento del TF / A2303 Post Direct 40,000.00 0.00 2017-01-25 2017-02-04 2017-02-25 2017-01-24 2017-04-01 2017-09-28 Selection Implementation desarrollo de la Estrategia REDD+. CR-FONAFIFO-4398-CS-INDV / Individual Consultant Under TF / A2303 Post Direct 24,000.00 0.00 2017-01-25 2017-02-04 2017-02-25 2017-04-01 2017-09-28 Apoyo a la Estrategia REDD+ Selection Implementation CR-FONAFIFO-4401-CS-INDV / Coordinación Estrategia REDD+ Individual Consultant Under para el fortalecimiento el TF / A2303 Post Direct 40,000.00 0.00 2017-01-26 2017-02-05 2017-02-26 2017-01-24 2017-04-02 2017-09-29 Selection Implementation desarrollo de la Estrategia REDD+. CR-FONAFIFO-4404-CS-INDV / Asesor legal para el Individual Consultant Under TF / A2303 Post Direct 35,000.00 0.00 2017-01-18 2017-01-28 2017-02-18 2017-01-23 2017-03-25 2017-09-21 fortalecimiento el desarrollo de la Selection Implementation Estrategia REDD+, 2016 Page 8 CR-FONAFIFO-1889-CS-INDV / Individual Consultant Desarrollo de modelo de negocio TF / A2303 Post Open 62,000.00 0.00 Canceled 2017-04-04 2017-05-23 2017-06-13 2017-07-18 2018-01-14 Selection en construcción. CR-FONAFIFO-1891-CS-INDV / Individual Consultant Desarrollo de modeo de negocios TF / A2303 Post Open 58,000.00 0.00 Canceled 2017-05-01 2017-06-19 2017-07-10 2017-08-14 2018-02-10 Selection en mueblería. CR-FONAFIFO-4393-CS-INDV / Apoyo administrativo a la Individual Consultant Under donación para el fortalecimiento TF / A2303 Post Direct 75,000.00 0.00 2017-01-11 2017-01-21 2017-02-11 2017-01-20 2017-03-18 2017-09-14 Selection Implementation al desarrollo de la estrategia REDD+ CR-FONAFIFO-1892-CS-INDV / Desarrollo de un plan que permita incorporar el enfoque de Individual Consultant TF / A2303 Post Open 35,000.00 0.00 Canceled 2017-03-30 2017-05-18 2017-06-08 2017-07-13 2018-01-09 género, dentro de las actividades Selection de preparación de REDD+ en forma equitativa. CR-FONAFIFO-1965-CS-INDV / Catastro para el manejo de información de terrenos privados Individual Consultant TF / A2303 Post Open 50,500.00 0.00 Canceled 2017-10-26 2017-12-14 2018-01-04 2018-02-08 2018-08-07 en rá eas silvestres protegidas, Selection con problemas de titulación de tierras (2017) CR-FONAFIFO-1964-CS-INDV / Catastro para el manejo de información de terrenos privados Individual Consultant TF / A2303 Post Open 30,000.00 0.00 Canceled 2017-03-15 2017-05-03 2017-05-24 2017-06-28 2017-12-25 en rá eas silvestres protegidas, Selection con problemas de titulación de tierras (2016) CR-FONAFIFO-1894-CS-INDV / Elaborar y ejecutar un plan de capacitación y participación comunitaria en el control y protección de los recursos Individual Consultant TF / A2303 Post Open 30,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 naturales naturales y la Selection biodiversidad en las ASP, que contemple el desarrollo y validación de módulos de capacitación. (2017) CR-FONAFIFO-11249-CS-INDV / Desarrollo de un marco de contabilidad para los productos Individual Consultant Pending maderables ("Harvested wood TF / A2303 Post Open 50,000.00 0.00 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 Selection Implementation products") para guiar la estrategia de incremento de uso de la madera. CR-FONAFIFO-1897-CS-INDV / Elaboración de diagnóstico para identificar los insumos que debe Individual Consultant TF / A2303 Post Open 24,000.00 0.00 Canceled 2017-05-03 2017-06-21 2017-07-12 2017-08-16 2018-02-12 tener un sistema de alerta Selection temprana de incendios en r á eas forestales. CR-FONAFIFO-1898-CS-INDV / Diseño del Sistema de Monitoreo Individual Consultant TF / A2303 Post Open 55,000.00 0.00 Canceled 2017-05-11 2017-06-29 2017-07-20 2017-08-24 2018-02-20 de Incendios Forestales Selection (Sistema Alerta Temprana). CR-FONAFIFO-1974-CS-INDV / Levantamiento de datos de Individual Consultant TF / A2303 Post Open 60,000.00 0.00 Canceled 2017-03-22 2017-05-10 2017-05-31 2017-07-05 2018-01-01 plantaciones sin PSA en fincas Selection privadas (2016) CR-FONAFIFO-1975-CS-INDV / Levantamiento de datos de Individual Consultant TF / A2303 Post Open 55,000.00 0.00 Canceled 2017-11-14 2018-01-02 2018-01-23 2018-02-27 2018-08-26 plantaciones sin PSA en fincas Selection privadas (2017) CR-FONAFIFO-1911-CS-INDV / Diseño experimental y análisis para la estimación del impacto Individual Consultant del aprovechamiento forestal de TF / A2303 Post Open 30,000.00 0.00 Canceled 2017-03-31 2017-05-19 2017-06-09 2017-07-14 2018-01-10 Selection bosques naturales sobre el stock de carbono e indicadores de biodiversidad. CR-FONAFIFO-1906-CS-INDV / Creación de Geobase de datos Individual Consultant de plantaciones para TF / A2303 Post Open 50,000.00 0.00 Canceled 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2018-03-12 Selection establecimiento de nivel de referencia. CR-FONAFIFO-1907-CS-INDV / Diseño estadístico y análisis de Individual Consultant la información para estimación TF / A2303 Post Open 30,000.00 0.00 Canceled 2017-07-03 2017-08-21 2017-09-11 2017-10-16 2018-04-14 Selection del stock de carbono en plantaciones forestales. CR-FONAFIFO-1909-CS-INDV / Establecimiento de 1500 Individual Consultant parcelas para estimación del TF / A2303 Post Open 30,000.00 0.00 Canceled 2017-06-08 2017-07-27 2017-08-17 2017-09-21 2018-03-20 Selection stock de carbono y crecimiento en teca. CR-FONAFIFO-1908-CS-INDV / Establecimiento de 1500 Individual Consultant parcelas para estimación del TF / A2303 Post Open 45,000.00 0.00 Canceled 2017-05-25 2017-07-13 2017-08-03 2017-09-07 2018-03-06 Selection stock de carbono y crecimiento en melina CR-FONAFIFO-1976-CS-INDV / Establecimiento de 2000 Individual Consultant parcelas para estimación del TF / A2303 Post Open 85,000.00 0.00 Canceled 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 Selection stock de carbono y crecimiento en otras especies forestales. CR-FONAFIFO-1905-CS-INDV / Individual Consultant á ea plantada TF / A2303 Digitalizacion de r Post Open 60,000.00 0.00 Canceled 2017-05-18 2017-07-06 2017-07-27 2017-08-31 2018-02-27 Selection con PSA 1997-2010 Page 9 CR-FONAFIFO-1913-CS-INDV / Sistematización y desarrollo de los planes de gestión, para la incorporacion de las restantes Individual Consultant TF / A2303 Post Open 40,000.00 0.00 Canceled 2017-04-03 2017-05-22 2017-06-12 2017-07-17 2018-01-13 medidas de mitigación de Selection REDD+ en el Nivel Nacional de Referencia de Emisiones Manejo Forestal Sostenible CR-FONAFIFO-1914-CS-INDV / Sistematización y desarrollo de los planes de gestión, para la incorporacion de las restantes Individual Consultant TF / A2303 Post Open 40,000.00 0.00 Canceled 2017-04-03 2017-05-22 2017-06-12 2017-07-17 2018-01-13 medidas de mitigación de Selection REDD+ en el Nivel Nacional de Referencia de Emisiones en Plantaciones. CR-FONAFIFO-1957-CS-INDV / Sistematización y coordinación de los planes de acción para el fortalecimiento de las actividades Individual Consultant TF / A2303 Post Open 40,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 de manejo sostenible y Selection degradación y aumento de las reservas de carbono en plantaciones forestales. CR-FONAFIFO-11335-CS-INDV / Visita de campo de 617 puntos Individual Consultant Under para separar las plantaciones TF / A2303 Post Open 40,000.00 0.00 2017-12-01 2017-06-12 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Selection Implementation forestales del bosque secundario, en zona B CR-FONAFIFO-11336-CS-INDV / Visita de campo de 618 puntos Individual Consultant Under para separar las plantaciones TF / A2303 Post Open 40,000.00 0.00 2017-12-01 2017-06-12 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Selection Implementation forestales del bosque secundario, en zona C CR-FONAFIFO-11341-CS-INDV / Estudio de parcelas temporales para estimar el stock de carbono Individual Consultant Pending TF / A2303 Post Open 47,500.00 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 en bosques intactos, degradados Selection Implementation y altamente degradados en zona A CR-FONAFIFO-11342-CS-INDV / Estudio de parcelas temporales para estimar el stock de carbono Individual Consultant Pending TF / A2303 Post Open 47,500.00 0.00 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 en bosques intactos, degradados Selection Implementation y altamente degradados en zona B CR-FONAFIFO-11343-CS-INDV / Verificacion de campo de parcelas temporales de Individual Consultant Pending TF / A2303 Post Open 30,000.00 0.00 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 degradación en 45 bosques Selection Implementation primarios y 105 bosques secundarios CR-FONAFIFO-1961-CS-INDV / Fortalecimiento del Sistema de Individual Consultant TF / A2303 Post Open 30,000.00 0.00 Canceled 2017-03-30 2017-05-18 2017-06-08 2017-07-13 2018-01-09 Información de los Recursos Selection Forestales (SIREFOR) CR-FONAFIFO-1962-CS-INDV / Fortalecimiento del Sistema de Individual Consultant TF / A2303 Post Open 60,000.00 0.00 Canceled 2017-06-14 2017-08-02 2017-08-23 2017-09-27 2018-03-26 Información de los Recursos Selection Forestales (SIREFOR) (2017) CR-FONAFIFO-11345-CS-INDV / Apoyo al sistema nacional de Individual Consultant Pending TF / A2303 Post Open 38,000.00 0.00 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 cambios de uso de la tierra y Selection Implementation ecosistemas (2018) CR-FONAFIFO-11549-CS-INDV / Preparación de actores locales interesados en la conformación de los comités de vigilancia de recursos naturales Individual Consultant Under TF / A2303 Post Open 50,000.00 0.00 2017-12-06 2018-01-24 2018-02-14 2018-03-21 2018-09-17 (COVIRENAS) como parte de la Selection Implementation participación ciudadana en el control y vigilancia de la tala ilegal y la biodiversidad, dentro y fuera de rá eas CR-FONAFIFO-11557-CS-INDV / Coordinación general de la implementación del plan de Individual Consultant Under mejora para el Nivel de TF / A2303 Post Direct 55,000.00 0.00 2017-07-26 2017-06-08 2017-08-05 2017-08-26 2017-09-30 2018-03-29 Selection Implementation Referencia (Plantaciones Forestales, Bosque Secundario, Degradacion Forestal) CR-FONAFIFO-1960-CS-INDV / Fortalecimiento de las capacidades del sistema de Individual Consultant TF / A2303 Post Open 30,000.00 0.00 Canceled 2017-03-28 2017-05-16 2017-06-06 2017-07-11 2018-01-07 trazabilidad de los productos Selection (Módulos de Industria Forestal) (2017) CR-FONAFIFO-11330-CS-INDV / Evaluación visual multitemporal Individual Consultant Under del uso de la tierra, cambio en el TF / A2303 Post Open 40,000.00 0.00 2017-10-31 2017-06-30 2017-12-19 2018-01-09 2018-02-13 2018-08-12 Selection Implementation uso de la tierra y cobertura de la tierra en 5.083 puntos en zona A CR-FONAFIFO-11331-CS-INDV / Evaluación visual multitemporal Individual Consultant Under del uso de la tierra, cambio en el TF / A2303 Post Open 40,000.00 0.00 2017-11-30 2017-06-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 Selection Implementation uso de la tierra y cobertura de la tierra en 5.083 puntos en zona B CR-FONAFIFO-11333-CS-INDV / Estimación de la relación Individual Consultant Under densidad de copas / stock de TF / A2303 Post Open 30,000.00 0.00 2017-11-02 2017-12-21 2018-01-11 2018-02-15 2018-08-14 Selection Implementation carbono (utilizando parcelas de muestra NFI) Page 10 CR-FONAFIFO-11339-CS-INDV / Establecimiento de parcelas Individual Consultant Pending temporales para estimar el stock TF / A2303 Post Open 50,000.00 0.00 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 Selection Implementation de carbono en bosques secundarios en zona C CR-FONAFIFO-11340-CS-INDV / Establecimiento de parcelas Individual Consultant Pending temporales para estimar el TF / A2303 Post Open 50,000.00 0.00 2017-11-29 2018-01-17 2018-02-07 2018-03-14 2018-09-10 Selection Implementation stock de carbono en bosques secundarios, en zona D CR-FONAFIFO-11346-CS-INDV Individual Consultant Pending / Elaboración del mapa de uso y TF / A2303 Post Open 38,000.00 0.00 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 Selection Implementation cobertura de la tierra año 2018 CR-FONAFIFO-11334-CS-INDV / Visita de campo de 617 puntos Individual Consultant Under para separar las plantaciones TF / A2303 Post Open 40,000.00 0.00 2017-11-29 2017-06-12 2018-01-17 2018-02-07 2018-03-14 2018-09-10 Selection Implementation forestales del bosque secundario, en zona A CR-FONAFIFO-11337-CS-INDV / Establecimiento de parcelas Individual Consultant Pending temporales para estimar el stock TF / A2303 Post Open 50,000.00 0.00 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 Selection Implementation de carbono en bosques secundarios en zona A CR-FONAFIFO-11338-CS-INDV / Establecimiento de parcelas Individual Consultant Pending temporales para estimar el stock TF / A2303 Post Open 50,000.00 0.00 2017-11-29 2018-01-17 2018-02-07 2018-03-14 2018-09-10 Selection Implementation de carbono en bosques secundarios en zona B CR-FONAFIFO-11563-CS-CDS / Desarrollo de cadena de custodia para el aprovechamiento forestal Under como módulos estadísticos TF / A2303 Post Direct Selection Direct 150,000.00 0.00 2017-11-23 2017-06-30 2017-12-03 2018-02-06 2018-08-05 Implementation asociados y manejados sobre una plataforma portal web en el SIREFOR. CR-FONAFIFO-22889-CS-INDV / Apoyo en comunicación y coordinación del componente Individual Consultant Under social para el proceso de TF / A2303 Post Direct 20,000.00 0.00 2017-09-13 2017-10-23 2017-09-23 2017-10-14 2017-11-18 2018-05-17 Selection Implementation consulta del capítulo indígena de la Estrategia REDD+ , adendum Natalia Díaz. CR-FONAFIFO-22892-CS-INDV / Asesor indígena para la fase Individual Consultant Under TF / A2303 Post Direct 20,000.00 0.00 2017-09-29 2017-10-20 2017-10-09 2017-10-30 2017-12-04 2018-06-02 final del capítulo de la Estrategia Selection Implementation REDD+, Adendum Levi Sucre CR-FONAFIFO-2061-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas, para la validacion de Pending TF / A2303 Post Direct Selection Direct 49,000.00 0.00 2017-10-31 2017-11-10 2018-01-14 2018-07-13 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena China Kicha CR-FONAFIFO-2059-CS-CDS / Desarrollo del plan de consulta TF / A2303 Post Direct Selection Direct 35,000.00 0.00 Canceled 2017-07-13 2017-07-23 2017-09-26 2018-03-25 SALITRE. CR-FONAFIFO-2060-CS-CDS / Desarrollo del plan de consulta TF / A2303 Post Direct Selection Direct 35,000.00 0.00 Canceled 2017-04-27 2017-05-07 2017-07-11 2018-01-07 TERRABA. CR-FONAFIFO-22893-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas, para la validacion de Under TF / A2303 Post Direct Selection Direct 26,000.00 0.00 2017-11-16 2017-10-12 2017-11-26 2018-01-30 2018-07-29 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Boruca. CR-FONAFIFO-22894-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas, para la validacion de Under TF / A2303 Post Direct Selection Direct 14,000.00 0.00 2017-11-16 2017-10-12 2017-11-26 2018-01-30 2018-07-29 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Ujarras. CR-FONAFIFO-22895-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Under TF / A2303 Post Direct Selection Direct 26,000.00 0.00 2017-11-30 2017-10-12 2017-12-10 2018-02-13 2018-08-12 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Cabagra CR-FONAFIFO-22896-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas, para la validacion de Under TF / A2303 Post Direct Selection Direct 45,000.00 0.00 2017-11-30 2017-10-12 2017-12-10 2018-02-13 2018-08-12 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el Bloque Regional Pacifico Sur. CR-FONAFIFO-22897-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas, para la validacion de Under TF / A2303 Post Direct Selection Direct 26,000.00 0.00 2017-11-30 2017-10-10 2017-12-10 2018-02-13 2018-08-12 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Rey Curré Page 11 CR-FONAFIFO-22898-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Under TF / A2303 Post Direct Selection Direct 10,000.00 0.00 2017-11-30 2017-10-10 2017-12-10 2018-02-13 2018-08-12 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Zapatón CR-FONAFIFO-22899-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Under TF / A2303 Post Direct Selection Direct 10,000.00 0.00 2017-11-30 2017-10-12 2017-12-10 2018-02-13 2018-08-12 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Matambú. CR-FONAFIFO-22900-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas, para la validacion de Pending TF / A2303 Post Direct Selection Direct 9,000.00 0.00 2017-11-30 2017-12-10 2018-02-13 2018-08-12 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Malecu. CR-FONAFIFO-26538-CS-CDS / Acompañamiento técnico y científico a la secretaría REDD+, para dar cumplimiento a las observaciones de la resolución Under TF / A2303 Post Direct Selection Direct 195,000.00 0.00 2017-11-01 2017-10-04 2017-11-11 2018-01-15 2018-07-14 CFM/14/2016/2 y atender las Implementation recomendaciones del resumen del Presidente de la reunión del Fondo de Carbono N°14 (Winrock) CR-FONAFIFO-4406-CS-CDS / Acompañamiento técnico y científico a la secretaría REDD+, para dar cumplimiento a las observaciones de la resolución TF / A2303 Post Direct Selection Direct 185,000.00 0.00 Canceled 2017-02-22 2017-03-04 2017-05-08 2017-11-04 CFM/14/2016/2 y atender las recomendaciones del resumen del Presidente de la reunión del Fondo de Carbono N°14 CR-FONAFIFO-11236-CS-INDV / Sistema para la Gestión de la Tenencia de la Tierra en Terrenos Individual Consultant Pending Patrimonio Natural del Estado y TF / A2303 Post Open 80,500.00 0.00 2018-01-31 2018-03-14 2018-03-15 2018-03-22 2019-03-12 Selection Implementation Á eas Silvestres Protegidas del r Sistema Nacional de rÁ eas de Conservación CR-FONAFIFO-2064-CS-INDV / Supervisión técnica de los proyectos de Pago por Servicios Individual Consultant TF / A2303 Post Open 34,000.00 0.00 Canceled 2017-04-12 2017-05-31 2017-06-21 2017-07-26 2018-01-22 Ambientales en las Oficinas Selection Regionales de San José y Nicoya 2016. CR-FONAFIFO-2066-CS-INDV / Supervisión técnica de los proyectos de Pago por Servicios Individual Consultant TF / A2303 Post Open 34,000.00 0.00 Canceled 2017-11-23 2018-01-11 2018-02-01 2018-03-08 2018-09-04 Ambientales en las Oficinas Selection Regionales de San José y Nicoya 2017. CR-FONAFIFO-2067-CS-INDV / Supervisión técnica de los proyectos de Pago por Servicios Individual Consultant TF / A2303 Post Open 34,000.00 0.00 Canceled 2017-11-29 2018-01-17 2018-02-07 2018-03-14 2018-09-10 Ambientales en las Oficinas Selection Regionales de Palmar Norte y San Carlos 2017. CR-FONAFIFO-35185-CS-INDV / Apoyo para las acciones Individual Consultant Pending TF / A2303 Post Open 40,000.00 0.00 2018-01-03 2018-02-08 2018-02-08 2018-02-23 2018-09-10 dentro del Pago de Servicios Selection Implementation Ambientales CR-FONAFIFO-35192-CS-INDV / Sistematización y diseño de información generada en el Individual Consultant Pending TF / A2303 Post Open 30,000.00 0.00 2018-01-03 2018-01-18 2018-01-23 2018-02-05 2018-10-08 desarrollo de la Estrategia Selection Implementation REDD+ para compartir lecciones aprendidas. CR-FONAFIFO-35210-CS-INDV / Promocion y capacitación de Individual Consultant Pending sistemas agroforestales y TF / A2303 Post Open 42,000.00 0.00 2018-01-08 2018-01-30 2018-02-02 2018-02-20 2019-02-20 Selection Implementation plantaciónes con pequeños productores a nivel nacional CR-FONAFIFO-2065-CS-INDV / Supervisión técnica de los proyectos de Pago por Servicios Individual Consultant Pending TF / A2303 Post Open 35,000.00 0.00 2018-01-04 2018-01-19 2018-01-23 2018-02-09 2019-02-06 Ambientales en las Oficinas Selection Implementation Regionales de Palmar Norte y San Carlos CR-FONAFIFO-2120-CS-INDV / Sistematización, divulgación y Individual Consultant posicionamiento de los modelos TF / A2303 Post Open 85,000.00 0.00 Canceled 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2018-03-12 Selection de negocio desarrollados para el sector privado ante la sociedad. CR-FONAFIFO-22901-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas, para la validacion de TF / A2303 Post Direct Selection Direct 56,000.00 0.00 Canceled 2017-11-30 2017-12-10 2018-02-13 2018-08-12 los 5 temas especiales en el marco de la Estrategia Nacional REDD+, para el territorio indígena RIBCA. CR-FONAFIFO-35239-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Pending TF / A2303 Post Direct Selection Direct 11,150.00 0.00 2017-12-06 2017-12-20 2018-03-03 2018-08-30 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Tainy Page 12 CR-FONAFIFO-35243-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Pending TF / A2303 Post Direct Selection Direct 11,150.00 0.00 2017-12-06 2017-12-16 2018-02-19 2018-08-18 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Nairy Awary CR-FONAFIFO-35246-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Pending TF / A2303 Post Direct Selection Direct 11,150.00 0.00 2017-12-06 2017-12-11 2018-01-31 2018-07-30 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Alto Chirripó CR-FONAFIFO-35250-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Pending TF / A2303 Post Direct Selection Direct 11,150.00 0.00 2017-12-11 2017-12-16 2018-02-05 2018-08-04 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Kekoldi CR-FONAFIFO-35254-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Pending TF / A2303 Post Direct Selection Direct 11,150.00 0.00 2017-12-06 2017-12-11 2018-01-10 2018-07-09 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Talamanca Cabecar CR-FONAFIFO-35258-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Pending TF / A2303 Post Direct Selection Direct 11,150.00 0.00 2017-12-06 2017-12-16 2018-02-19 2018-08-18 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Telire CR-FONAFIFO-35263-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Pending TF / A2303 Post Direct Selection Direct 11,150.00 0.00 2017-12-06 2017-12-16 2018-02-19 2018-08-18 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Bajo Chirripó CR-FONAFIFO-35267-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Pending TF / A2303 Post Direct Selection Direct 9,500.00 0.00 2017-12-06 2017-12-11 2018-01-31 2018-07-30 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Quitirrisí CR-FONAFIFO-35269-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Pending TF / A2303 Post Direct Selection Direct 15,000.00 0.00 2017-12-06 2017-12-11 2018-01-31 2018-07-30 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Terraba CR-FONAFIFO-35270-CS-CDS / Etapa de finalización del proceso de consulta en los territorios indígenas para la validacion de Pending TF / A2303 Post Direct Selection Direct 15,000.00 0.00 2017-12-06 2017-12-11 2018-01-24 2018-07-23 los 5 temas especiales en el Implementation marco de la Estrategia Nacional REDD+, para el territorio indígena Salitre CR-FONAFIFO-11433-CS-INDV Individual Consultant Pending / Apoyo en la coordinación y TF / A2303 Post Open 32,000.00 0.00 2018-02-14 2018-03-20 2018-04-10 2018-05-09 2018-11-30 Selection Implementation desarrollo del SIMOCUTE. CR-FONAFIFO-16603-CS-INDV / Diseño de una estructura organizativa para la ejecución, seguimiento y coordinación de Individual Consultant Pending las actividades de la Estrategia TF / A2303 Post Open 8,217.39 0.00 2018-02-01 2018-02-22 2018-02-28 2018-03-15 2018-05-17 Selection Implementation REDD+, por parte de la Secretaría en el marco institucional de FONAFIFO y SINAC como ejecutores. CR-FONAFIFO-36533-CS-INDV / Desarrollar un plan de fortalecimiento de capacidades en las ASP en REDD+, incluyendo el diseño de al menos Individual Consultant Pending dos planes especificos piltoto de TF / A2303 Post Open 60,000.00 0.00 2018-01-31 2018-03-21 2018-03-23 2018-04-06 2019-02-28 Selection Implementation acciones de mitigación y adaptación de ecosistemas forestales en el marco de REDD+ en ASP consideradas como crít CR-FONAFIFO-37123-CS-CDS / Diseñar y ejecutar un plan de formación enfocado en la gestión del diseño de productos Pending maderables con valor agregado, TF / A2303 Post Direct Selection Direct 80,000.00 0.00 2018-02-07 2018-02-17 2018-03-29 2018-12-05 Implementation con né fasis en los procesos de fabricación digital y prototipado como aporte a la competitividad del sector forestal productivo. CR-FONAFIFO-37248-CS-CDS / Desarrollar un programa de formación y certificación de asesores en diseño y Pending construcción con madera e TF / A2303 Post Direct Selection Direct 48,000.00 0.00 2018-03-28 2018-04-07 2018-06-11 2019-02-20 Implementation implementar una plataforma en línea para su difusión y propiciar la formación de profesionales a través de una cátedra. Page 13 CR-FONAFIFO-35194-CS-INDV / Diseño e implementacion de un Individual Consultant Pending inventario y catastro de tierras TF / A2303 Post Open 45,000.00 0.00 2018-05-10 2018-05-26 2018-06-28 2018-07-10 2018-12-14 Selection Implementation públicas en los diversos usos de la tierra en Costa Rica CR-FONAFIFO-1968-CS-INDV / Articulación de resultados de Individual Consultant Pending TF / A2303 Post Open 12,000.00 0.00 2017-05-24 2017-07-12 2017-08-02 2017-09-06 2018-03-05 consultorías del sector forestal a Selection Implementation la estrategia REDD+ CR-FONAFIFO-37241-CS-CDS / Fortalecer las capacidades en materia gerencial, producción y comercialización de productos Pending TF / A2303 Post Direct Selection Direct 32,000.00 0.00 2018-04-11 2018-04-21 2018-06-25 2018-12-21 maderables con valor agregado, Implementation para los actores identificados del clúster forestal en la región Huétar Norte. CR-FONAFIFO-37251-CS-CDS / Dirigir e integrar las consultorías ligadas al plan de formación enfocado en la gestión del diseño de productos maderables, Pending TF / A2303 Post Direct Selection Direct 20,000.00 0.00 2018-05-16 2018-05-26 2018-07-30 2018-11-07 sumado a lo relacionado con el Implementation clúster forestal en la Región Huetar Norte y lo ligado al uso de la madera nacional en la industria CR-FONAFIFO-54448-CS-INDV / Contratación de servicios Individual Consultant Pending TF / A2303 Post Open 30,000.00 0.00 2018-07-19 2018-08-22 2018-09-05 2018-10-10 2019-01-24 informáticos para el ajuste de la Selection Implementation página web de REDD+ CR-FONAFIFO-11559-CS-INDV / Coordinacion general de implementacion de plan de mejora de Nivel de Referencia Individual Consultant Pending TF / A2303 Post Direct 55,000.00 0.00 2018-04-19 2018-04-29 2018-05-20 2018-06-24 2018-12-21 (HWP, Incendios Forestales, Selection Implementation Ferilizacion Plantaciones Forestales, Manejo de Bosque Natural) CR-FONAFIFO-37246-CS-INDV / Realizar un diagnóstico y plan de acción de corto plazo para aumentar el uso de madera Individual Consultant Pending nacional en la industria de la TF / A2303 Post Open 20,000.00 0.00 2018-04-23 2018-06-11 2018-07-02 2018-08-06 2018-12-19 Selection Implementation construcción y de esta forma contribuir a la gestión sostenible de los bosques y el aumento de las reservas de carbono forestal. CR-FONAFIFO-54830-CS-INDV / Apoyo legal a procesos internos en Fonafifo para el Individual Consultant Pending ingreso de contratos de PSA en TF / A2303 Post Direct 40,000.00 0.00 2018-04-03 2018-04-13 2018-05-04 2018-06-08 2019-02-20 Selection Implementation el marco de la implementación del Programa Reducción de Emisiones 2017, CR-FONAFIFO-1958-CS-INDV / Armonización del Plan Nacional de Desarrollo Forestal y REDD+ Individual Consultant Pending TF / A2303 Post Open 40,000.00 0.00 2017-04-26 2017-06-14 2017-07-05 2017-08-09 2018-02-05 (incluyendo evaluación de Selection Implementation desempeño, inclusion de capítulo indígena y capítulo ASP) CR-FONAFIFO-54844-CS-INDV / Desarrollo de un plan de acción Individual Consultant Pending administrativo finanicero con TF / A2303 Post Open 25,000.00 0.00 2018-07-12 2018-08-30 2018-09-20 2018-10-25 2019-02-13 Selection Implementation miras al manejo de recursos del ERPA bajo la FUNBAM CR-FONAFIFO-54845-CS-INDV / Contratación de servicios Individual Consultant Pending profesionales para el apoyo en TF / A2303 Post Open 36,000.00 0.00 2018-04-18 2018-06-06 2018-06-27 2018-08-01 2019-03-28 Selection Implementation comunicación para la Estrategia REDD+ CR-FONAFIFO-11232-CS-INDV / Desarrollar las acciones que permitan un reconocimiento y empoderamiento de las mujeres Individual Consultant TF / A2303 Post Open 45,000.00 0.00 Canceled 2017-10-18 2017-12-06 2017-12-20 2018-01-24 2018-07-23 y hombres como Partes Selection Interesadas Relevantes en el desarrollo de la Estrategia Nacional REDD+. CR-FONAFIFO-1978-CS-INDV / Diseño de un sistema de monitoreo de plantaciones Individual Consultant TF / A2303 Post Open 43,000.00 0.00 Canceled 2017-05-18 2017-07-06 2017-07-27 2017-08-31 2018-02-27 forestales bajo la modalidad de Selection créditos y Pago de Servicios Ambientales. CR-FONAFIFO-11448-CS-INDV / Apoyo al proceso de finalización de documento de la Individual Consultant TF / A2303 Post Open 35,000.00 0.00 Canceled 2017-12-18 2018-02-05 2018-02-26 2018-04-02 2018-09-29 Estrategia Nacional REDD+, e Selection incorporación de observaciones al Plan de Implementación. CR-FONAFIFO-36261-CS-INDV / Apoyo en Sistemas de Información al IMN en el proceso de eleboración de seguimiento al Individual Consultant mapa de cobertura 2015 y los TF / A2303 Post Open 27,600.00 0.00 Canceled 2018-02-14 2018-03-19 2018-03-27 2018-04-13 2019-01-31 Selection respectivos informes para la preparación del reporte bianual ante la convenio que incluya el capitulo de REDD+. CR-FONAFIFO-1979-CS-INDV / Diseño del Sistema Nacional de Individual Consultant Monitoreo de Cobertura y Uso de TF / A2303 Post Open 27,600.00 0.00 Canceled 2017-03-31 2017-06-30 2017-05-19 2017-06-09 2017-07-14 2018-01-10 Selection la Tierra y Ecosistemas (SIMODICUTE) Page 14 CR-FONAFIFO-54863-CS-INDV / Asesor legal para la formalización de la entidad que Individual Consultant Pending representará a las partes TF / A2303 Post Open 6,000.00 0.00 2018-09-04 2018-10-01 2018-10-03 2018-10-30 2018-12-19 Selection Implementation interesadas relevantes e implementará el clúster forestal del la Región Huetar Norte. CR-FONAFIFO-37127-CS-CDS / Desarrollar un plan estratégico y operativo para el clúster forestal de la región Huetar Norte con el Pending TF / A2303 Post Direct Selection Direct 32,000.00 0.00 2018-04-05 2018-04-15 2018-06-19 2018-11-15 fin de contribuir a la gestión Implementation sostenible de los bosques y el aumento de las reservas de carbono forestal. CR-FONAFIFO-25170-CS-CDS / Desarrollo de una firma espectral Pending para la identificación de cultivos TF / A2303 Post Direct Selection Direct 150,000.00 0.00 2018-07-11 2018-07-21 2018-09-24 2019-03-23 Implementation de palma, a travéz de sensores remotos e in situ en Costa Rica. CR-FONAFIFO-36260-CS-INDV / Apoyo en el desarrollo y seguimiento de las mesas técnicas para el Sistema Individual Consultant TF / A2303 Post Open 12,000.00 0.00 Canceled 2018-02-07 2018-03-05 2018-03-22 2018-04-13 2019-03-06 Nacional de Monitoreo de la Selection Dinamica de Cobertura del Uso de la Tierra y Ecosistemas 2018 (SIMODICUTE) CR-FONAFIFO-57812-CS-INDV / Apoyo en el desarrollo y seguimiento de las mesas técnicas para el Sistema Individual Consultant Pending TF / A2303 Post Direct 12,000.00 0.00 2018-05-16 2018-05-26 2018-06-16 2018-07-21 2019-03-29 Nacional de Monitoreo de la Selection Implementation Dinamica de Cobertura del Uso de la Tierra y Ecosistemas 2018 (SIMODICUTE) Page 15