Hunan Integrated Management of Agricultural Land Pollution (P153115) Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Plan [original: June 27, 2017; 1st Revision: August 17, 2017; 2nd Revision: June 8, 2018; 3rd Revision: Aug. 10, 2018; 4th Revision: April 4, 2019; 5th Revision: December 20, 2019; 6th Revision: March 4, 2020; 7th Revision: March 30, 2020; 8th Revision: April 9, 2020; 9th Revision: May 21, 2020; 10th Update: June 5, 2020] 2. Date of General Procurement Notice: August 16, 2017 3. Period covered by this procurement plan: June 2020 to December 2020 II. Goods, Works, non-consulting services and Community participation in procurement under Component 1. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Procurement Method Threshold US$ US$ ICB and LIB (Goods and Non- Greater than or equal to US$ 1. Consulting Services ) All 10 million NCB (Goods and Non-Consulting Greater than or equal to US$ Greater than or equal to 2. Services ) 0.5 million 2 million Greater than or equal to US$ 3. ICB (Works) All 40 million Greater than or equal to US$ Greater than or equal to 4. NCB (Works) 0.5 million 10 million Community participation in to be specified in the 5 No Threshold procurement operation manual 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Detailed procedures for community participation are specified in operation manual. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P153115 has been prepared by Hunan PPMO. 5. Any Other Special Procurement Arrangements [including advance procurement and retroactive financing, if applicable]: None 6 Summary of the Procurement Packages planned during June 2020 to December 2020 . 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ (yes/no) (Prior / thousand Post) Summary of the National Competitive Bidding (Works) Summary of the Shopping (Works) Summary of the National Competitive Bidding (Goods) Summary of the Shopping 82.08 2 Post (Goods) Summary of the Shopping (Non- Consultant Services) Cancellation (Works) Cancellation (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Greater than or equal to US$ 1,000,000 2. Single Source (Firms) Greater than or equal to US$ 1,000,000 3. Individual Greater than or equal to US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements [including advance procurement and retroactive financing, if applicable or delete if not applicable]: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Estimated Review Description of Cost Ref. No. by Bank Assignment Packages Comments US$ (Prior / thousand Post) Summary of number of contracts that will be let under QCBS Summary of number of contracts that 85,075 1 IC will be let under other methods Cancellation PROCUREMENT China : Hunan Integrated Management of Agricultural Land Pollution Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2017-09-04 2020-06-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153115 GPN Date: 2017-08-16 Project Name: Hunan Integrated Management of Agricultural Land Pollution Project Loan / Credit No: IBRD / 87770, / Executing Agency(ies): Hunan Integrated Management of Agriculture PMO WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Contract Description Component Review Type Method Document Amount Amount qualification Document / Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Completion Type (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned HNYDG001 / Construction Component 1: Demonstration Under of drainage ditches, irrigation Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 495,870.00 0.00 Implementat 2017-09-15 2019-01-10 2017-11-10 2018-05-09 ditches, sand and gravel Quotations Envelope Land Pollution Management. ion traps. HNYXG001 / Construction Component 1: Demonstration Request for Single Stage - One of irrigation ditches, sand IBRD / 87770 of Risk-based Agricultural Post Limited 347,610.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 Quotations Envelope and gravel traps, field roads. Land Pollution Management. HNYXG002 / Construction Component 1: Demonstration Request for Single Stage - One of drainage ditches, sand IBRD / 87770 of Risk-based Agricultural Post Limited 171,190.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 Quotations Envelope and gravel traps. Land Pollution Management. HNYXG003 / Construction of irrigation ditches, drainage Component 1: Demonstration ditches, sand and gravel Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 419,250.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 traps, ecological interception Quotations Envelope Land Pollution Management. ditches and pumping stations. HNYXG004 / Construction Component 1: Demonstration Request for Single Stage - One of irrigation ditches, sand IBRD / 87770 of Risk-based Agricultural Post Limited 60,150.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 Quotations Envelope and gravel traps. Land Pollution Management. HNYXG005 / Construction Component 1: Demonstration Request for Single Stage - One of irrigation ditches and IBRD / 87770 of Risk-based Agricultural Post Limited 224,030.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 Quotations Envelope drainage ditches. Land Pollution Management. HNHYG001 / Construction Component 1: Demonstration Request for Single Stage - One of irrigation canals and IBRD / 87770 of Risk-based Agricultural Post Limited 310,700.00 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 Quotations Envelope ditches Land Pollution Management. HNHYG002 / Construction Component 1: Demonstration Request for Single Stage - One of irrigation canals and IBRD / 87770 of Risk-based Agricultural Post Limited 105,100.00 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 Quotations Envelope ditches. Land Pollution Management. HNHYG003 / Construction Component 1: Demonstration Request for Single Stage - One of irrigation canals and IBRD / 87770 of Risk-based Agricultural Post Limited 154,210.00 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 Quotations Envelope ditches. Land Pollution Management. HNHYG004 / Construction Component 1: Demonstration Request for Single Stage - One of Sand and gravel traps IBRD / 87770 of Risk-based Agricultural Post Limited 118,340.00 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 Quotations Envelope &Field roads. Land Pollution Management. Page 1 HNXXHYG001 / Construction of irrigation Component 1: Demonstration Pending Request for Single Stage - One system, gravel or dirt road, IBRD / 87770 of Risk-based Agricultural Post Open - National 316,190.00 0.00 Implementat 2019-03-06 2019-05-01 2019-10-28 Quotations Envelope Sediment desilting and Land Pollution Management. ion landfill in Huayuan county. HNXXHYG002 / Construction of irrigation Component 1: Demonstration Pending Request for Single Stage - One system, gravel or dirt road, IBRD / 87770 of Risk-based Agricultural Post Open - National 218,810.00 0.00 Implementat 2019-03-06 2019-05-01 2019-10-28 Quotations Envelope Sediment desilting and Land Pollution Management. ion landfill in Huayuan county. HNHNG001 / Construction of irrigation system, gravel Component 1: Demonstration Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Request for Bids Open - National 1,048,810.00 0.00 Canceled 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2020-06-21 Envelope desilting and landfill in Land Pollution Management. Hengnan county. HNZFG001 / Construction of irrigation system, gravel Component 1: Demonstration Under Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Open - National 302,990.00 0.00 Implementat 2019-03-06 2019-05-01 2019-12-27 Quotations Envelope desilting and landfill in Land Pollution Management. ion Zhongfang county. HNZFG002 / Construction of irrigation system, gravel Component 1: Demonstration Under Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Open - National 320,930.00 0.00 Implementat 2019-03-06 2019-05-01 2019-12-27 Quotations Envelope desilting and landfill in Land Pollution Management. ion Zhongfang county. HNLSTG001 / Construction of irrigation system, gravel Component 1: Demonstration Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Request for Bids Open - National 888,370.00 0.00 Canceled 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2020-06-21 Envelope desilting and landfill in Leng Land Pollution Management. Shuitan county. HNYSG001 / Construction of irrigation system ,gravel Component 1: Demonstration Pending Request for Single Stage - One or dirt road, sediment IBRD / 87770 of Risk-based Agricultural Post Open - National 452,330.00 0.00 Implementat 2019-03-06 2019-05-01 2019-11-01 Quotations Envelope desilting and landfill in Land Pollution Management. ion Yongshun county . Component 2: Strengthening HNHYG004-1 / Under Agricultural Environmental Request for Single Stage - One Reconstruction of heavy IBRD / 87770 Post Open - National 32,240.00 0.00 Implementat 2019-04-04 2019-05-30 2019-11-26 Monitoring and Quotations Envelope metal detection laboratory. ion Management. HNHYG002-1 / Construction Component 1: Demonstration of Irrigation system and Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Open - National 123,000.00 0.00 Canceled 2019-03-06 2019-05-01 2020-05-01 gravel or dirt road in Quotations Envelope Land Pollution Management. Hengyang county. HNHYG003-1 / Construction Component 1: Demonstration of Irrigation system and Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Open - National 375,480.00 0.00 Canceled 2019-03-06 2019-05-01 2020-05-01 gravel or dirt road in Quotations Envelope Land Pollution Management. Hengyang county. HNCLG001 / Construction of irrigation system, gravel Component 1: Demonstration Under Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Open - National 476,110.00 0.00 Implementat 2019-10-15 2019-12-10 2020-08-06 Quotations Envelope desilting and landfill in Cili Land Pollution Management. ion county. HNCLG003 / Construction of irrigation system, gravel Component 1: Demonstration Under Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Open - National 333,760.00 0.00 Implementat 2019-10-15 2019-12-10 2020-08-06 Quotations Envelope desilting and landfill in Cili Land Pollution Management. ion county. HNCLG004 / Construction of irrigation system, gravel Component 1: Demonstration Under Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Open - National 320,560.00 0.00 Implementat 2019-10-15 2019-12-10 2020-08-06 Quotations Envelope desilting and landfill in Cili Land Pollution Management. ion county. Page 2 HNCLG005 / Construction of irrigation system, gravel Component 1: Demonstration Under Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Open - National 90,710.00 0.00 Implementat 2019-10-15 2019-12-10 2020-08-06 Quotations Envelope desilting and landfill in Cili Land Pollution Management. ion county. HNCLG002-1 / Construction of irrigation system, gravel Component 1: Demonstration Under Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Request for Bids Open - National 653,460.00 0.00 Implementat 2019-10-10 2019-12-16 2019-10-15 2019-11-26 2020-01-10 2019-12-26 2020-01-10 2020-01-30 2020-09-26 Envelope desilting and landfill in Cili Land Pollution Management. ion county. HNCLG002 / Construction of irrigation system, gravel Component 1: Demonstration Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Open - National 492,150.00 0.00 Canceled 2019-10-15 2019-12-10 2020-08-06 Quotations Envelope desilting and landfill in Cili Land Pollution Management. county. HNBJG001-1 / Construction of irrigation system ,gravel Component 1: Demonstration Under Request for Single Stage - One or dirt road, sediment IBRD / 87770 of Risk-based Agricultural Post Open - National 286,570.00 0.00 Implementat 2019-10-20 2019-12-15 2020-06-12 Quotations Envelope desilting and landfill in Land Pollution Management. ion Baojing county . HNBJG001 / Construction of irrigation system ,gravel Component 1: Demonstration Single Stage - One or dirt road, sediment IBRD / 87770 of Risk-based Agricultural Post Request for Bids Open - National 672,420.00 0.00 Canceled 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2019-12-21 Envelope desilting and landfill in Land Pollution Management. Baojing county . HNQYG002 / Construction Component 1: Demonstration Pending of irrigation system and a Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 432,840.00 0.00 Implementat 2019-12-15 2020-02-09 2021-02-08 gravel or dirt road in Quotations Envelope Land Pollution Management. ion Qiyang county . HNQYG003 / Construction Component 1: Demonstration Pending of irrigation system and a Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 328,360.00 0.00 Implementat 2019-12-15 2020-02-09 2021-02-08 gravel or dirt road in Quotations Envelope Land Pollution Management. ion Qiyang county . HNHNG002 / Construction of irrigation system, gravel Component 1: Demonstration Under Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Open - National 291,040.00 0.00 Implementat 2019-11-15 2020-04-26 2020-01-10 2020-07-08 Quotations Envelope desilting and landfill in Land Pollution Management. ion Hengnan county. HNHYG001-1 / Construction of irrigation system and Component 1: Demonstration Pending Single Stage - One gravel or dirt road in Tai IBRD / 87770 of Risk-based Agricultural Post Request for Bids Open - National 880,000.00 0.00 Implementat 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2020-06-21 Envelope Yuan demostration area of Land Pollution Management. ion Hengyang county. HNHYG002-2 / Construction of irrigation system and Component 1: Demonstration Pending Request for Single Stage - One gravel or dirt road in Xi Du IBRD / 87770 of Risk-based Agricultural Post Limited 344,780.00 0.00 Implementat 2019-12-06 2020-01-31 2021-01-30 Quotations Envelope demostration area of Land Pollution Management. ion Hengyang county. HNHYG003-2 / Construction of irrigation system and Component 1: Demonstration Pending Request for Single Stage - One gravel or dirt road in Hong IBRD / 87770 of Risk-based Agricultural Post Limited 246,270.00 0.00 Implementat 2019-12-06 2020-01-31 2021-01-30 Quotations Envelope Shi demostration area of Land Pollution Management. ion Hengyang county. HNQYG001 / Construction Component 1: Demonstration Pending of irrigation system and a Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Open - National 253,700.00 0.00 Implementat 2020-01-06 2020-03-02 2021-03-02 gravel or dirt road in Quotations Envelope Land Pollution Management. ion Qiyang county . HNHNG003 / Construction of irrigation system, gravel Component 1: Demonstration Under Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Limited 388,060.00 0.00 Implementat 2020-01-04 2020-01-15 2020-02-29 2021-02-28 Quotations Envelope desilting and landfill in Land Pollution Management. ion Hengnan county. Page 3 HNHNG004 / Construction of irrigation system, gravel Component 1: Demonstration Under Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Limited 462,690.00 0.00 Implementat 2020-01-04 2020-04-15 2020-02-29 2021-02-28 Quotations Envelope desilting and landfill in Land Pollution Management. ion Hengnan county. HNYZG001 / Construction Component 1: Demonstration Pending of irrigation system and a Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 490,000.00 0.00 Implementat 2020-03-15 2020-05-10 2021-05-10 gravel or dirt road etc. in Quotations Envelope Land Pollution Management. ion Yizhang county . HNYDG002 / Field Engineering Construction of Wentang Neighborhood Component 1: Demonstration Pending Request for Single Stage - One Committee, Taiping Village, IBRD / 87770 of Risk-based Agricultural Post Open - National 477,610.00 0.00 Implementat 2020-03-15 2020-05-10 2021-05-10 Quotations Envelope Heitan Village, Dingjiazhuang Land Pollution Management. ion Village and Bajiao Village in yongding county. HNYDG003 / Field Engineering Construction of Component 1: Demonstration Pending Request for Single Stage - One Changtan Village, Hongxing IBRD / 87770 of Risk-based Agricultural Post Open - National 465,670.00 0.00 Implementat 2020-03-15 2020-05-10 2021-05-10 Quotations Envelope Village and Gaoping Village Land Pollution Management. ion in yongding county HNAHG001 / Construction of irrigation system, gravel Component 1: Demonstration Pending Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Request for Bids Open - National 655,070.00 0.00 Implementat 2020-04-10 2020-04-15 2020-05-27 2020-06-26 2020-07-31 2021-07-31 Envelope desilting etc. in Anhua Land Pollution Management. ion county. HNAHG002 / Construction of irrigation system, gravel Component 1: Demonstration Pending Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Limited 209,130.00 0.00 Implementat 2020-04-15 2020-06-10 2021-06-10 Quotations Envelope desilting etc. in Anhua Land Pollution Management. ion county. HNAHG003 / Construction of irrigation system, gravel Component 1: Demonstration Pending Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Limited 200,600.00 0.00 Implementat 2020-04-15 2020-06-10 2021-06-10 Quotations Envelope desilting etc. in Anhua Land Pollution Management. ion county. HNANG004 / Construction of irrigation system, gravel Component 1: Demonstration Pending Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Limited 228,130.00 0.00 Implementat 2020-04-15 2020-06-10 2021-06-10 Quotations Envelope desilting etc. in Anhua Land Pollution Management. ion county. HNAHG005 / Construction of irrigation system, gravel Component 1: Demonstration Pending Request for Single Stage - One or dirt road, Sediment IBRD / 87770 of Risk-based Agricultural Post Limited 357,610.00 0.00 Implementat 2020-04-15 2020-06-10 2021-06-10 Quotations Envelope desilting etc. in Anhua Land Pollution Management. ion county. HNQYG004 / Construction Component 1: Demonstration Pending of irrigation system and a Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 193,880.00 0.00 Implementat 2020-04-15 2020-06-10 2021-06-10 gravel or dirt road in Quotations Envelope Land Pollution Management. ion Qiyang county . HNLSTG002 / Construction Component 1: Demonstration Pending Request for Single Stage - One of field engineering in Leng IBRD / 87770 of Risk-based Agricultural Post Limited 455,220.00 0.00 Implementat 2020-06-04 2020-07-30 2021-01-26 Quotations Envelope Shuitan county. Land Pollution Management. ion GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 HNH002 / Procurement of sampling inspection vehicles Component 2: Strengthening to facilitate project Agricultural Environmental Request for Single Stage - One / Post Limited 492,540.00 0.00 Canceled 2017-12-13 2018-02-07 2018-08-06 management and supervion Monitoring and Quotations Envelope and sample transpotation in Management. 15 project counties. HNHYH002 / Procurement Component 1: Demonstration Request for Single Stage - One of comprehensive pest and IBRD / 87770 of Risk-based Agricultural Post Open - National 360,300.00 0.00 Canceled 2019-03-06 2019-05-01 2019-12-27 Quotations Envelope disease control equipment. Land Pollution Management. HNH001 / Procurement of desktop computers , laptops , multi func printers , scanners, digital cameras , Component 2: Strengthening Under DVs , projectors , GPS Agricultural Environmental Request for Single Stage - One IBRD / 87770 Post Limited 149,250.00 0.00 Implementati 2019-03-06 2019-06-26 2019-05-01 2019-07-30 locators , projection screens Monitoring and Quotations Envelope on and digital recorders , which Management. aims to promote the management efficency and ability of PMO staffs HNHYH001 / Procurement Component 2: Strengthening Pending of testing equipment for the Agricultural Environmental Request for Single Stage - One IBRD / 87770 Post Open - National 303,300.00 0.00 Implementati 2019-04-04 2019-05-30 2019-11-26 Agricultural Bureau in Monitoring and Quotations Envelope on Hengyang County. Management. HNH003 / Procurement of desktop computers , laptops , multi func printers , scanners, digital cameras , Component 2: Strengthening Pending DVs , projectors , GPS Agricultural Environmental Request for Single Stage - One IBRD / 87770 Post Open - National 74,630.00 0.00 Implementati 2019-10-25 2019-12-20 2020-02-18 locators , etc. , which aims Monitoring and Quotations Envelope on to promote the management Management. efficency and ability of Anhua county and Yizhang county PMO staffs. HNYSH001 / Procurement Component 1: Demonstration Pending of comprehensive pest and Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Open - National 119,400.00 0.00 Implementati 2020-03-15 2020-05-10 2020-10-31 disease control equipment in Quotations Envelope Land Pollution Management. on Yongshun county. HNLWH001 / Procurement Component 1: Demonstration Pending Request for Single Stage - One of integrated pest control IBRD / 87770 of Risk-based Agricultural Post Limited 29,850.00 0.00 Implementati 2020-03-15 2020-05-10 2020-11-06 Quotations Envelope equipment for Linwu county. Land Pollution Management. on HNHYH003 / Procurement of comprehensive agricultural Component 1: Demonstration Pending Single Stage - One pest and disease control IBRD / 87770 of Risk-based Agricultural Post Request for Bids Open - National 358,210.00 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-08-05 Envelope equipment in Hengyang Land Pollution Management. on county . HNAHH001 / Procurement Component 1: Demonstration Pending of comprehensive agricultural Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 141,790.00 0.00 Implementati 2020-04-20 2020-06-15 2021-06-15 pest and disease control Quotations Envelope Land Pollution Management. on equipment in Anhua county . HNQYH001 / Procurement of comprehensive agricultural Component 1: Demonstration Pending Request for Single Stage - One pest and disease control IBRD / 87770 of Risk-based Agricultural Post Limited 41,790.00 0.00 Implementati 2020-04-20 2020-06-15 2021-06-15 Quotations Envelope equipment in Qiyang county Land Pollution Management. on . Component 2: Strengthening HNQYH002 / Procurement Pending Agricultural Environmental Request for Single Stage - One of heavy metal detector in IBRD / 87770 Post Open - National 67,160.00 0.00 Implementati 2020-06-04 2020-07-30 2020-08-29 Monitoring and Quotations Envelope Qiyang county. on Management. Component 2: Strengthening HNBJH001 / Procurement Pending Agricultural Environmental Request for Single Stage - One of heavy metal detector in IBRD / 87770 Post Open - National 67,160.00 0.00 Implementati 2020-06-04 2020-07-30 2020-08-29 Monitoring and Quotations Envelope Baojing county. on Management. Page 5 Component 2: Strengthening HNXXHYH001 / Pending Agricultural Environmental Request for Single Stage - One Procurement of heavy metal IBRD / 87770 Post Limited 67,160.00 0.00 Implementati 2020-06-15 2020-08-10 2020-09-09 Monitoring and Quotations Envelope detector in Huayuan county. on Management. Component 1: Demonstration Pending HNLWH002 / Procurement Request for IBRD / 87770 of Risk-based Agricultural Post 14,920.00 0.00 Implementati 2020-06-15 2020-08-10 2020-09-09 of straw baler Quotations Land Pollution Management. on HNYSH002 / Procurement Component 2: Strengthening Pending of heavy metal rapid Agricultural Environmental Request for Single Stage - One IBRD / 87770 Post Open - National 67,160.00 0.00 Implementati 2020-07-10 2020-09-04 2020-10-04 measuring instrument in Monitoring and Quotations Envelope on Yongshun county . Management. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HNYDFZ001 / Sampling Component 1: Demonstration Request for Single Stage - One from fields and detection of IBRD / 87770 of Risk-based Agricultural Post Limited 28,940.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 Quotations Envelope the samples. Land Pollution Management. HNYXFZ001 / Detection of agricultural products, Component 1: Demonstration irrigation water, underground Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 13,490.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 water, air, sediment, organic Quotations Envelope Land Pollution Management. fertilizer, and pesticides for heavy matal determination. HNHYFZ001 / detection of agricultural products, Component 1: Demonstration irrigation water, underground Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 155,010.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 water, air, sediment, organic Quotations Envelope Land Pollution Management. fertilizer, and pesticides for heavy matal determination. HNYDFZ002 / detection of agricultural products, Component 1: Demonstration irrigation water, underground Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 92,250.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 water, air, sediment, organic Quotations Envelope Land Pollution Management. fertilizer, and pesticides for heavy matal determination HNYDFZ002-2-2 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments, agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 121,190.00 0.00 Implementati 2018-03-10 2018-09-06 2018-05-05 2019-06-30 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Yongding District and detection of the samples. HNYXFZ001-2-2 / Sampling of water, soil, crops, Component 1: Demonstration sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 36,790.00 0.00 Canceled 2018-03-10 2018-05-05 2019-06-30 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. Yongxing County and detection of the samples. HNJSFZ001-2 / Sampling of water, soil, crops, Component 1: Demonstration Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 26,040.00 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Jishou City and detection of the samples. Page 6 HNYSFZ001-2 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 30,450.00 0.00 Implementati 2018-03-10 2018-08-15 2018-05-05 2018-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Yongshun County and detection of the samples. HNBJFZ001-2 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 59,600.00 0.00 Implementati 2018-03-10 2018-08-24 2018-05-05 2018-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Baojing County and detection of the samples. HNXXHYFZ001-2 / Sampling of water, soil, crops, sediments,agriculture Component 1: Demonstration Under Request for Single Stage - One inputs, atmosphere IBRD / 87770 of Risk-based Agricultural Post Limited 30,600.00 0.00 Implementati 2018-03-10 2018-08-24 2018-05-05 2018-12-31 Quotations Envelope deposition, etc. in Huayuan Land Pollution Management. on County and detection of the samples. HNQYFZ001-2 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 24,330.00 0.00 Implementati 2018-03-10 2018-08-22 2018-05-05 2018-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Qiyang County and detection of the samples. HNCLFZ001-2 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 31,940.00 0.00 Implementati 2018-03-10 2018-08-17 2018-05-05 2018-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Cili County and detection of the samples. HNYZFZ001-2 / Sampling of water, soil, crops, Component 1: Demonstration sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 20,150.00 0.00 Canceled 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. Yizhang County and detection of the samples. HNZFFZ001-2 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 44,160.00 0.00 Implementati 2018-03-10 2018-08-31 2018-05-05 2018-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Zhongfang County and detection of the samples. HNAHFZ001-2 / Sampling of water, soil, crops, Component 1: Demonstration sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 31,340.00 0.00 Canceled 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. Anhua County and detection of the samples. HNLSTFZ001-2 / Sampling of water, soil, crops, Component 1: Demonstration Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 28,130.00 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Lengshuitan District and detection of the samples. HNYDFZ003 / Sampling of water, soil, crops, sediments, Component 1: Demonstration Under agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 356,270.00 0.00 Implementati 2019-03-06 2019-05-23 2019-05-01 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Yongding District and detection of the samples. HNQYFZ002 / Sampling of water, soil, crops, sediments, Component 1: Demonstration Under agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 262,690.00 0.00 Implementati 2019-03-06 2019-03-10 2019-05-01 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Qiyang county and detection of the samples. Page 7 HNLWFZ001-2 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 154,030.00 0.00 Implementati 2019-03-06 2019-04-22 2019-05-01 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Linwu County and detection of the samples. HNZFFZ002 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 296,670.00 0.00 Implementati 2019-03-06 2019-04-23 2019-05-01 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Zhongfang County and detection of the samples. HNLSTFZ002 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 235,630.00 0.00 Implementati 2019-03-06 2019-05-27 2019-05-01 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Leng Shuitan District and detection of the samples. HNXXHYFZ002 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 262,120.00 0.00 Implementati 2019-03-06 2019-07-22 2019-05-01 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Huayuan County and detection of the samples. HNBJFZ002 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 248,540.00 0.00 Implementati 2019-03-06 2020-03-19 2019-05-01 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Baojing County and detection of the samples. HNYSFZ002 / Sampling of water, soil, crops, Component 1: Demonstration Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 119,400.00 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Yongshun County and detection of the samples. HNHYFZ002 / Publicize the measures and effects of the project in Hengyang, so as to enhance the visibility of Component 1: Demonstration Pending the project and the value of Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 74,630.00 0.00 Implementati 2019-03-06 2019-05-01 2024-03-31 agricultural products in the Quotations Envelope Land Pollution Management. on project area, and popularize the knowledge of heavy metal pollution control at the same time. HNHNFZ001-2 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 477,610.00 0.00 Implementati 2019-03-06 2019-07-02 2019-05-01 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Hengnan County and detection of the samples. HNCLFZ002 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 239,530.00 0.00 Implementati 2019-03-06 2019-04-02 2019-05-01 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Cili County and detection of the samples. HNHYFZ001-2-2 / Sampling of water, soil, crops, Component 1: Demonstration Under sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 492,540.00 0.00 Implementati 2019-06-25 2019-06-27 2019-08-20 2024-04-20 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Hengyang County and detection of the samples. Page 8 HNLSTFZ003 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Under Request for Single Stage - One background, agronomic IBRD / 87770 Development and Knowledge Post Open - National 262,610.00 0.00 Implementati 2019-10-25 2019-12-20 2023-12-31 Quotations Envelope measures, and integrated Distribution. on pest ,disease control techniques, etc. in Leng Shuitan district. HNQYFZ003 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Under Request for Single Stage - One background, agronomic IBRD / 87770 Development and Knowledge Post Limited 280,600.00 0.00 Implementati 2019-10-25 2019-11-06 2019-12-20 2023-12-31 Quotations Envelope measures, and integrated Distribution. on pest ,disease control techniques, etc. in Qiyang county. HNYZFZ001 / Sampling of water, soil, crops, sediments, Component 1: Demonstration Under agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 222,940.00 0.00 Implementati 2019-11-15 2020-03-06 2020-01-10 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Yi Zhang County and detection of the samples. HNXXHYFZ003 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Under Request for Single Stage - One background, agronomic IBRD / 87770 Development and Knowledge Post Limited 134,330.00 0.00 Implementati 2020-01-04 2020-01-06 2020-02-29 2023-02-28 Quotations Envelope measures, and integrated Distribution. on pest ,disease control techniques, etc. in HuaYuan county. HNYSFZ003 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Pending Request for Single Stage - One background, agronomic IBRD / 87770 Development and Knowledge Post Limited 134,330.00 0.00 Implementati 2020-01-04 2020-02-29 2023-02-28 Quotations Envelope measures, and integrated Distribution. on pest ,disease control techniques, etc. in YongShun county. HNJSFZ003 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Under Request for Single Stage - One background, agronomic IBRD / 87770 Development and Knowledge Post Limited 134,330.00 0.00 Implementati 2020-01-04 2020-01-03 2020-02-29 2023-02-28 Quotations Envelope measures, and integrated Distribution. on pest ,disease control techniques, etc. in JiShou city. HNYZFZ002 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Under Request for Single Stage - One background, agronomic IBRD / 87770 Development and Knowledge Post Open - National 179,100.00 0.00 Implementati 2020-03-15 2020-05-10 2023-12-31 Quotations Envelope measures, and integrated Distribution. on pest ,disease control techniques, etc. in Yizhang county. HNJSFZ002 / Sampling of water, soil, crops, sediments, Component 1: Demonstration Pending agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 119,400.00 0.00 Implementati 2020-03-15 2020-05-10 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Jishou city and detection of the samples. Component 3: Capacity Pending HNLWFZ002 / Farmer Request for Single Stage - One IBRD / 87770 Development and Knowledge Post Open - National 205,970.00 0.00 Implementati 2020-03-15 2020-05-10 2023-12-31 training in linwu county. Quotations Envelope Distribution. on Page 9 HNAHFZ001 / Sampling of water, soil, crops, sediments, Component 1: Demonstration Pending agriculture inputs, Request for Single Stage - One IBRD / 87770 of Risk-based Agricultural Post Limited 179,100.00 0.00 Implementati 2020-04-15 2020-06-10 2023-12-31 atmosphere deposition, etc. in Quotations Envelope Land Pollution Management. on Anhua county and detection of the samples. HNHNFZ002 / Training of Component 3: Capacity Pending Farmers and Project Request for Single Stage - One IBRD / 87770 Development and Knowledge Post Limited 186,570.00 0.00 Implementati 2020-04-15 2020-06-10 2023-12-31 Managers in Hengnan Quotations Envelope Distribution. on county. HNHYFZ003 / Training of Component 3: Capacity Pending Request for Single Stage - One farmers in Hengyang county IBRD / 87770 Development and Knowledge Post Limited 210,820.00 0.00 Implementati 2020-06-04 2020-07-30 2023-12-31 Quotations Envelope . Distribution. on Component 3: Capacity Pending HNAHFZ002 / Training of Request for Single Stage - One IBRD / 87770 Development and Knowledge Post Limited 246,490.00 0.00 Implementati 2020-06-04 2020-07-30 2023-12-31 farmers in Anhua county. Quotations Envelope Distribution. on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HNYXZ001 / Screening of Component 1: Demonstration Consultant low metal-accumulating IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 44,790.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2021-01-28 variety. Land Pollution Management. Selection HNYDZ005 / Comparing the differences of heavy metal Component 1: Demonstration Consultant uptaking between the "with IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 15,650.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 project"and"without project" Land Pollution Management. Selection situations HNYDZ006 / Disseminate knowledge gained from Component 3: Capacity Consultant demonstrations for increasing IBRD / 87770 Development and Knowledge Post Qualification Open - National 37,300.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 awareness and building Distribution. Selection ability to make informed choices among alternatives. Component 4: Project Consultant HNYXZ002 / Project IBRD / 87770 Management and Monitoring Post Qualification Open - National 74,650.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 monitoring and evaluation. and Evaluation Selection Component 4: Project Consultant HNYXZ003 / Supervision of IBRD / 87770 Management and Monitoring Post Qualification Open - National 94,050.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 agronomic measures. and Evaluation Selection HNZ005 / Screening experiment on simultaneous Component 1: Demonstration Consultant Under passivation agents for IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 208,960.00 0.00 2018-06-10 2018-07-27 2018-07-01 2019-06-23 2018-08-14 2018-07-27 2018-09-13 2018-08-20 2018-10-18 2019-12-31 Implementation combined pollution of Land Pollution Management. Selection cadmium and arsenic. HNZ008 / Conduction of annual environmental Component 4: Project Consultant assessment (produce one IBRD / 87770 Management and Monitoring Post Qualification Open - National 283,580.00 0.00 Canceled 2018-11-10 2018-12-01 2019-01-14 2019-02-13 2019-03-20 2024-06-30 environmental assessment and Evaluation Selection report every six months) HNHYZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-07-14 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in Implementation Land Pollution Management. Selection Hengyang county. Page 10 HNHYZ002 / Experiment on the effect of harvesting at Component 1: Demonstration Consultant different maturity on Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 44,300.00 0.00 2019-03-01 2019-06-25 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2021-07-09 cadmium accumulation in Implementation Land Pollution Management. Selection rice, to be conducted in Hengyang county. HNHYZ003 / Comparison of effects of agronomic Component 1: Demonstration Consultant measures in different regions Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 47,000.00 0.00 2019-03-01 2019-06-25 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2023-12-31 and monitoring experiment of Implementation Land Pollution Management. Selection soil cadmium balance in Hengyang county. Component 2: Strengthening HNHYZ006 / Local policies Consultant Agricultural Environmental Pending and standards development IBRD / 87770 Post Qualification Open - National 89,550.00 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2023-12-31 Monitoring and Implementation in Hengyang county. Selection Management. Component 4: Project Consultant HNYDZ003 / Project IBRD / 87770 Management and Monitoring Post Qualification Open - National 52,250.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 monitoring and evaluation. and Evaluation Selection Component 4: Project Consultant HNYDZ007 / Supervision of IBRD / 87770 Management and Monitoring Post Qualification Open - National 189,650.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 agronomic measures. and Evaluation Selection HNQYZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-22 2019-03-22 2019-05-05 2019-04-05 2019-06-04 2019-04-25 2019-07-09 2022-07-09 accumulation varieties in Implementation Land Pollution Management. Selection Qiyang county. HNCLZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-21 2019-03-22 2019-05-05 2019-04-29 2019-06-04 2019-05-06 2019-07-09 2022-07-09 accumulation varieties in Cili Implementation Land Pollution Management. Selection county. HNHNZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-28 2019-03-22 2020-04-27 2019-05-05 2019-04-04 2019-06-04 2019-04-10 2019-07-09 2022-07-09 accumulation varieties in Implementation Land Pollution Management. Selection Hengnan county. HNZFZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-04-10 2019-03-22 2019-05-05 2019-05-20 2019-06-04 2019-05-25 2019-07-09 2022-07-09 accumulation varieties in Implementation Land Pollution Management. Selection Zhongfang county. HNLSTZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-25 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in Implementation Land Pollution Management. Selection Lengshuitan district. HNXXHYZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-25 2019-03-22 2019-05-05 2019-05-06 2019-06-04 2019-05-10 2019-07-09 2022-07-09 accumulation varieties in Implementation Land Pollution Management. Selection Huayuan county. HNYSZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in Implementation Land Pollution Management. Selection Yongshun county. HNZ001 / Development of a risk-based land management tool and use the tool to map all farmland sat the county Component 2: Strengthening and provincial levels to Agricultural Environmental Quality Based Under IBRD / 87770 Post Open - National 1,000,000.00 0.00 2019-03-10 2020-05-19 2019-03-31 2019-05-14 2019-06-11 2019-07-11 2019-08-10 2019-09-14 2022-09-14 classify areas with different Monitoring and Selection Implementation risk levels, crops for Management. different soil types and conditions, and identify risk management options. Page 11 HNZ002 / Studies on sustainable financing models Component 2: Strengthening Consultant and eco-compensation Agricultural Environmental IBRD / 87770 Post Qualification Open - National 74,630.00 0.00 Under Review 2019-03-17 2019-09-20 2019-03-27 2019-05-10 2019-06-09 2019-07-14 2022-07-14 mechanisms for long-term Monitoring and Selection agricultural land Management. management. HNZ003 / Establish a database of all relevant Component 2: Strengthening Consultant information, and give early Agricultural Environmental Under IBRD / 87770 Post Qualification Open - National 89,550.00 0.00 2019-03-17 2020-06-08 2019-04-07 2019-05-21 2019-06-20 2019-07-25 2021-07-25 warning of possible risks to Monitoring and Implementation Selection farmland and crops according Management. to data changes. HNZ004 / Monitoring the progress of project, finance, procurement and training.And summarize the situation of social tracking Component 4: Project Consultant monitoring, environmental IBRD / 87770 Management and Monitoring Post Qualification Open - National 223,880.00 0.00 Canceled 2018-11-10 2018-12-01 2019-01-14 2019-02-13 2019-03-20 2024-06-30 tracking monitoring and and Evaluation Selection project implementation effectiveness assessment (a report is produced every six months). HNZ006 / Monitoring the Component 1: Demonstration Consultant whole process of sampling Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 268,660.00 0.00 2018-08-13 2019-08-28 2018-09-03 2018-10-17 2018-11-16 2018-12-21 2023-12-31 and detection of the samples Implementation Land Pollution Management. Selection for quality control HNZ007 / Conduction of Social evaluation annually (tracking monitoring one Component 4: Project Consultant natural village per county Under IBRD / 87770 Management and Monitoring Post Qualification Open - National 268,660.00 0.00 2019-03-02 2019-05-08 2019-03-23 2019-05-06 2019-06-05 2019-07-10 2023-12-31 and produce a social Implementation and Evaluation Selection evaluation report each year) and dam safety assessment annually. HNZ009 / Screening experiment on simultaneous Component 1: Demonstration Consultant passivation agents for Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 253,730.00 0.00 2019-03-05 2019-03-27 2019-03-26 2019-05-09 2019-06-08 2019-07-13 2021-07-13 combined pollution of Implementation Land Pollution Management. Selection cadmium and arsenic for the second time. HNHYZ005 / Analysis and Component 1: Demonstration Consultant evaluation of heavy metal Pending IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 71,640.00 0.00 2019-03-05 2019-03-26 2019-05-09 2019-06-08 2019-07-13 2023-12-31 pollution data in Hengyang Implementation Land Pollution Management. Selection county. HNYDZ004 / Screening of Component 1: Demonstration Consultant Under low metal-accumulating IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-04-01 2019-03-22 2019-05-05 2019-04-30 2019-06-04 2019-05-20 2019-07-09 2022-07-09 Implementation variety in Yongding district. Land Pollution Management. Selection HNBJZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 98,510.00 0.00 Canceled 2019-03-02 2019-03-23 2019-05-06 2019-06-05 2019-07-10 2022-07-10 accumulation varieties in Land Pollution Management. Selection Baojing county. HNZ008-2 / Conduction of annual environmental Component 4: Project Quality And Cost- Open - Under assessment (produce one IBRD / 87770 Management and Monitoring Post 343,280.00 0.00 2019-04-01 2019-05-19 2019-04-22 2019-05-19 2019-06-05 2019-07-16 2019-07-03 2019-08-19 2019-08-02 2019-08-19 2019-09-06 2019-08-20 2019-10-11 2023-12-31 Based Selection International Implementation environmental assessment and Evaluation report every six months) HNLSTZ002 / Hire a third party to supervise the Component 1: Demonstration Consultant Under implementation of agronomic IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 156,720.00 0.00 2019-04-01 2019-03-15 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2023-12-31 Implementation measures in Leng Shuitan Land Pollution Management. Selection District. Page 12 HNQYZ003 / Hire a third Component 1: Demonstration Consultant party to supervise the Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 114,730.00 0.00 2019-03-25 2019-04-21 2019-04-15 2019-05-29 2019-04-30 2019-06-28 2019-05-30 2019-08-02 2023-12-31 implementation of agronomic Implementation Land Pollution Management. Selection measures in Qi Yang county. HNHNZ002 / Hire a third party to supervise the Component 1: Demonstration Consultant Under implementation of agronomic IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 231,690.00 0.00 2019-04-06 2019-05-05 2019-04-27 2019-06-10 2019-07-10 2019-08-14 2023-12-31 Implementation measures in Heng Nan Land Pollution Management. Selection county. HNLWZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 98,510.00 0.00 2019-04-10 2019-07-22 2019-05-01 2019-06-14 2019-07-14 2019-08-18 2022-08-18 accumulation varieties in Lin Implementation Land Pollution Management. Selection Wu county. HNZ004-2 / Evaluation of Component 4: Project Quality And Cost- Open - Under the implementation effect of IBRD / 87770 Management and Monitoring Post 522,390.00 0.00 2019-06-06 2019-06-26 2019-06-27 2019-07-09 2019-08-10 2019-08-09 2019-09-07 2019-10-16 2019-10-07 2019-10-16 2019-11-11 2019-12-16 2023-12-31 Based Selection International Implementation the project . and Evaluation HNXXHYZ002 / Hire a third party to provide Component 1: Demonstration Consultant technical support for the Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 44,780.00 0.00 2019-06-06 2019-12-02 2019-06-27 2019-08-10 2020-01-27 2019-09-09 2020-02-17 2019-10-14 2021-12-31 treatment of heavy metal Implementation Land Pollution Management. Selection contaminated farmland in Huayuan County. HNYSZ002 / Hire a third party to provide technical Component 1: Demonstration Consultant support for the treatment of Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 44,780.00 0.00 2019-06-06 2019-12-02 2019-06-27 2019-08-10 2019-09-09 2019-10-14 2021-12-31 heavy metal contaminated Implementation Land Pollution Management. Selection farmland in Yongshun County. HNJSZ001 / Hire a third party to provide technical Component 1: Demonstration Consultant Under support for the treatment of IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 44,780.00 0.00 2019-06-06 2019-12-02 2019-06-27 2019-08-10 2020-01-29 2019-09-09 2020-02-25 2019-10-14 2021-12-31 Implementation heavy metal contaminated Land Pollution Management. Selection farmland in Jishou City. HNHYZ007 / Hire a third party to supervise the Component 1: Demonstration Consultant Under implementation of IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 92,450.00 0.00 2019-06-06 2019-06-25 2019-06-27 2019-08-10 2019-09-09 2019-10-14 2023-12-31 Implementation agricultural measures in Land Pollution Management. Selection Hengyang County. HNJSZ002 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 89,550.00 0.00 2019-12-30 2020-01-01 2020-01-20 2020-03-04 2020-01-29 2020-04-03 2020-02-28 2020-05-08 2023-05-09 accumulation varieties in Implementation Land Pollution Management. Selection JiShou city. HNYSZ003 / Screening Component 1: Demonstration Consultant experiment of low cadmium Pending IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 89,550.00 0.00 2019-12-30 2020-01-20 2020-03-04 2020-04-03 2020-05-08 2023-05-09 accumulation varieties in Implementation Land Pollution Management. Selection YongShun county. HNXXHYZ003 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 89,550.00 0.00 2019-12-30 2019-04-01 2020-01-20 2020-03-04 2020-01-27 2020-04-03 2020-02-20 2020-05-08 2023-05-09 accumulation varieties in Implementation Land Pollution Management. Selection HuaYuan county. HNYZZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 104,480.00 0.00 2020-03-10 2020-03-05 2020-03-31 2020-05-14 2020-03-30 2020-06-13 2020-03-30 2020-07-18 2022-12-31 accumulation varieties in Implementation Land Pollution Management. Selection Yizhang county. HNYZZ002 / Hire a third Component 1: Demonstration Consultant party to supervise the Under IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 111,940.00 0.00 2020-03-10 2020-03-06 2020-03-31 2020-05-14 2020-03-30 2020-06-13 2020-04-03 2020-07-18 2023-12-31 implementation of agronomic Implementation Land Pollution Management. Selection measures in Yizhang county. Page 13 HNLWZ003 / Hire a third Component 1: Demonstration Consultant party to supervise the Pending IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 74,630.00 0.00 2020-03-10 2020-03-31 2020-05-14 2020-06-13 2020-07-18 2023-12-31 implementation of agronomic Implementation Land Pollution Management. Selection measures in Linwu county. HNAFZ001 / Screening Component 1: Demonstration Consultant experiment of low cadmium Pending IBRD / 87770 of Risk-based Agricultural Post Qualification Open - National 89,550.00 0.00 2020-05-30 2020-06-20 2020-08-03 2020-09-02 2020-10-07 2022-12-31 accumulation rice varieties in Implementation Land Pollution Management. Selection Anhua county. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HNQYZ002 / Technical guidance for district Component 1: Demonstration Individual Under treatment of cadmium - IBRD / 87770 of Risk-based Agricultural Post Consultant Open 44,780.00 0.00 2019-03-01 2019-05-10 2019-04-19 2019-05-10 2019-06-14 2022-06-14 Implementation arsenic compound pollution Land Pollution Management. Selection project in Qiyang county. HNCLZ002 / Technical guidance for district Component 1: Demonstration Individual Under treatment of cadmium - IBRD / 87770 of Risk-based Agricultural Post Consultant Open 44,780.00 0.00 2019-03-01 2019-07-20 2019-04-19 2019-06-14 2019-05-10 2019-06-24 2019-06-14 2022-06-14 Implementation arsenic compound pollution Land Pollution Management. Selection project in Cili county. HNLWZ002 / Technical guidance for regional Component 1: Demonstration Individual treatment of cadmium-arsenic Pending IBRD / 87770 of Risk-based Agricultural Post Consultant Open 89,550.00 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2022-06-14 combined pollution and Implementation Land Pollution Management. Selection arsenic pollution in linwu county. HNHNZ003 / Technical guidance for regional Component 1: Demonstration Individual treatment of cadmium-arsenic Under IBRD / 87770 of Risk-based Agricultural Post Consultant Open 89,550.00 0.00 2019-05-15 2019-05-01 2019-07-03 2019-06-06 2019-07-24 2019-06-20 2019-08-28 2021-12-31 combined pollution and Implementation Land Pollution Management. Selection arsenic pollution in Hengnan county. HNLSTZ003 / Technical guidance for treatment of Component 1: Demonstration Individual Under Heavy Metal contaminated IBRD / 87770 of Risk-based Agricultural Post Consultant Open 44,780.00 0.00 2019-05-15 2019-05-10 2019-07-03 2019-07-24 2019-08-28 2021-12-31 Implementation farmland in Lengshuitan Land Pollution Management. Selection district. HNYZZ003 / Technical Component 1: Demonstration Individual guidance for heavy metal Under IBRD / 87770 of Risk-based Agricultural Post Consultant Open 80,600.00 0.00 2020-03-10 2020-03-06 2020-04-28 2020-03-29 2020-05-19 2020-04-10 2020-06-23 2023-06-23 pollution control in Yizhang Implementation Land Pollution Management. Selection county. HNZFZ002 / Technical Component 1: Demonstration Individual guidance for heavy metal Pending IBRD / 87770 of Risk-based Agricultural Post Consultant Open 44,780.00 0.00 2020-03-10 2020-04-28 2020-05-19 2020-06-23 2023-06-23 pollution control in Implementation Land Pollution Management. Selection Zhongfang county HNAHZ001 / Technical guidance for district Component 1: Demonstration Individual Pending treatment of heavy metal IBRD / 87770 of Risk-based Agricultural Post Consultant Open 44,780.00 0.00 2020-04-10 2020-05-29 2020-06-19 2020-07-24 2023-07-25 Implementation pollution project in Anhua Land Pollution Management. Selection county. HNHYZ004 / Technical guidance for the Component 1: Demonstration Individual Pending implementation of agronomic IBRD / 87770 of Risk-based Agricultural Post Consultant Open 85,075.00 0.00 2020-06-10 2020-07-29 2020-08-19 2020-09-23 2023-12-31 Implementation measures in Hengyang Land Pollution Management. Selection county. Page 14