Procurement Plan for TRANSIP (P151819) I. General 1. Bank’s approval Date of the procurement Plan: Original: March 25, 2015: Revision V1 of Updated Procurement Plan, April 24, 2017 2. Date of General Procurement Notice: October 22, 2015 3. Period covered by this procurement plan: The procurement period of project covered from year 2016-2017 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB / NCB (Goods) Above US$ 1.0/0.5m All 2. ICB / NCB (Works) Above US$ 5.0/7.0 m All 3. Non-Consultant Services NA 2. Pre-qualification. Bidders for not identified shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project: Transport Systems Improvement Project, February 2015 issued by AARTB 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preferenc by Bank US$ e (Prior / Post) million (yes/no) Summary of 20.7 3 No Prior the ICB (Works) Summary of 66.8 4 No Prior ITS and the ICB other (Goods) Goods April 27, 2017 Summary of 5.0 1 NA Prior the NCB (Works) Summary of 0.45 1 NA Post the NCB (Goods) Summary of 0 0 NA NA the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comment 1. Competitive Methods (Firms) Above US$ 200,000 2. Single Source (Firms) na 3. Individual Above US$ 100,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 39.0 22 Prior number of contracts that will be let under QCBS Summary of 1.93 5 Post IC number of contracts that will be let under other methods April 27, 2017 PROCUREMENT Ethiopia : Ethiopia: Transport Systems Improvement Project (TRANSIP) PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2016-07-26 2020-09-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151819 GPN Date: Project Name: Ethiopia: Transport Systems Improvement Project (TRANSIP) Loan / Credit No: IDA / 58160, IDA / Q9810 Executing Agency(ies): Addis Ababa Road & Transport Bureau WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component A: Traffic ET-AARTB-357-CW-RFB / Pending Management and Road Open - Single Stage - One Construction of Pedestrian IDA / 58160 Prior Request for Bids 10,000,000.00 0.00 Implementat 2018-02-13 2018-02-18 2018-04-01 2018-05-01 2018-06-05 2018-12-02 Safety in the City of Addis International Envelope Footbridges ion Ababa Component A: Traffic ET-AARTB-358-CW-RFB / Pending Management and Road Open - Single Stage - One Anbessa's operational IDA / 58160 Prior Request for Bids 10,700,000.00 0.00 Implementat 2018-10-16 2018-10-21 2018-12-02 2019-01-01 2019-02-05 2019-08-04 Safety in the City of Addis International Envelope facilities improvement ion Ababa Component A: Traffic ET-AARTB-356-CW-RFB / Pending Management and Road Single Stage - One Constructing A Building for IDA / 58160 Prior Request for Bids Open - National 5,000,000.00 0.00 Implementat 2018-01-16 2018-01-21 2018-03-04 2018-04-03 2018-05-08 2018-11-04 Safety in the City of Addis Envelope the Traffic Control Center ion Ababa GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AARTB-342-GO-RFB / Component A: Traffic Pending Supply & Install Traffic Management and Road Open - Single Stage - One IDA / 58160 Prior Request for Bids 35,000,000.00 0.00 Implementati 2020-08-25 2020-08-30 2020-10-11 2020-11-10 2020-12-15 2021-06-13 Signal System including Safety in the City of Addis International Envelope on traffic control center system Ababa Component A: Traffic Pending ET-AARTB-413-GO-RFB / Management and Road Single Stage - One IDA / 58160 Post Request for Bids Open - National 150,000.00 0.00 Implementati 2017-04-04 2017-04-09 2017-05-21 2017-06-20 2017-07-25 2018-01-21 Procurement of Documents Safety in the City of Addis Envelope on Ababa ET-AARTB-414-GO-RFB / Component A: Traffic Pending Procurement of Office Management and Road Single Stage - One IDA / 58160 Post Request for Bids Open - National 150,000.00 0.00 Implementati 2017-10-03 2017-10-08 2017-11-19 2017-12-19 2018-01-23 2018-07-22 Equipment (Computers and Safety in the City of Addis Envelope on Related accessories) for TMA Ababa ET-AARTB-341-GO-RFB / Supply and installation of Component A: Traffic Equipment and Software for Pending Management and Road Open - Single Stage - One electronic fare collection and IDA / 58160 Prior Request for Bids 12,300,000.00 0.00 Implementati 2018-07-30 2018-08-04 2018-09-15 2018-10-15 2018-11-19 2019-05-18 Safety in the City of Addis International Envelope ITS to support Anbessa on Ababa Operations and Management Anbessa City Bus Enterprise Page 1 Component A: Traffic ET-AARTB-344-GO-RFQ / Pending Management and Road Request for Single Stage - One Office furnitures, (executive IDA / Q9810 Post Limited 57,000.00 0.00 Implementati 2016-07-11 2016-07-19 2016-07-24 Safety in the City of Addis Quotations Envelope table and wooden shelf) on Ababa ET-AARTB-345-GO-RFQ / Component A: Traffic Office furniture (coffee Pending Management and Road Request for Single Stage - One table,guest chair, Metal IDA / Q9810 Post Limited 11,000.00 0.00 Implementati 2016-07-17 2016-09-11 2017-03-10 Safety in the City of Addis Quotations Envelope shelf, water distiller, table on Ababa coffee) ET-AARTB-346-GO-RFQ / Component A: Traffic Procurement of IT Management and Road Request for Single Stage - One IDA / Q9810 Post Limited 5,000.00 44,203.62 Completed 2016-07-17 2015-12-14 2016-09-11 2016-02-18 2017-03-10 2016-05-12 equipments ( Server, LCD Safety in the City of Addis Quotations Envelope Projector, UPS, Tablets) Ababa ET-AARTB-347-GO-RFQ / Procurement of IT Component A: Traffic Pending equipments (Desk top comp, Management and Road Request for Single Stage - One IDA / Q9810 Post Limited 29,000.00 0.00 Implementati 2016-07-17 2016-09-11 2017-03-10 laptop computer, Printer, Safety in the City of Addis Quotations Envelope on External hard disc and other Ababa computer peripherals) ET-AARTB-348-GO-RFQ / Procurement of Office Component A: Traffic furniture for FTA and PIU Pending Management and Road Request for Single Stage - One (Executive office table, IDA / Q9810 Post Limited 9,000.00 0.00 Implementati 2016-07-18 2016-09-12 2017-03-11 Safety in the City of Addis Quotations Envelope Woden shelf, executive on Ababa chaires, conference table, and conference chaires ) ET-AARTB-349-GO-RFQ / Procurement of IT equipments for FTA PIU ( Component A: Traffic Pending Desk top comp, laptop Management and Road Request for Single Stage - One IDA / Q9810 Post Limited 18,000.00 0.00 Implementati 2016-07-25 2016-09-19 2017-03-18 computer, LCD projector, Safety in the City of Addis Quotations Envelope on Color printer, All in one Ababa printer and other computer peripherals) Component A: Traffic ET-AARTB-350-GO-RFQ / Pending Management and Road Request for Single Stage - One Procurement of application IDA / Q9810 Post Limited 18,000.00 0.00 Implementati 2016-09-04 2016-10-30 2017-04-28 Safety in the City of Addis Quotations Envelope Software's on Ababa Component A: Traffic Pending ET-AARTB-352-GO-RFQ / Management and Road Request for Single Stage - One IDA / Q9810 Post Limited 5,000.00 0.00 Implementati 2016-08-20 2016-10-15 2017-04-13 Procurement of Books Safety in the City of Addis Quotations Envelope on Ababa ET-AARTB-351-GO-RFQ / Procurement of 4 units four Component A: Traffic wheel drive pick up double Management and Road Request for Single Stage - One IDA / Q9810 Post Limited 350,000.00 259,698.99 Signed 2016-07-18 2016-03-29 2016-09-12 2016-05-17 2017-03-11 cabin field vehicles (3 for Safety in the City of Addis Quotations Envelope Addis Ababa PIU and 1 for Ababa FTA PIU) Component A: Traffic ET-AARTB-409-GO-RFB / Management and Road Open - Single Stage - One Traffic Enforcement IDA / 58160 Prior Request for Bids 19,000,000.00 0.00 Canceled 2016-10-11 2016-10-16 2016-11-27 2016-12-27 2017-01-31 2017-07-30 Safety in the City of Addis International Envelope Equipments Ababa ET-AARTB-5968-GO-RFB / Component A: Traffic Supply and Installation of Management and Road Open - Single Stage - One IDA / 58160 Prior Request for Bids 10,000,000.00 7,247,035.40 Signed 2017-02-21 2018-06-22 2017-02-26 2018-07-16 2017-04-09 2018-10-02 2017-05-09 2019-05-08 2017-06-13 2019-06-30 2017-12-10 Communication System for Safety in the City of Addis International Envelope Traffic Enforcement Ababa ET-AARTB-5967-GO-RFB / Component A: Traffic Procurement of Vehicles and Management and Road UN Agencies IDA / 58160 Prior Direct 4,500,000.00 4,406,580.98 Completed 2017-04-03 2017-06-07 2017-04-08 2017-06-27 2017-05-13 2017-06-14 2017-11-09 2019-03-05 Motor cycles for Traffic Safety in the City of Addis (Direct) Police Enforcement Ababa Page 2 ET-AARTB-40074-RFQ / Component A: Traffic Pending Procurement of IT Management and Road Request for Single Stage - One IDA / 58160 Post Limited 70,000.00 0.00 Implementati 2018-01-23 2018-03-20 2018-09-16 Equipment for PIU and Safety in the City of Addis Quotations Envelope on AACRA Ababa ET-AARTB-42977-GO-UN / Component A: Traffic Procurement of Vehicles for Management and Road UN Agencies IDA / 58160 Prior Direct 1,000,000.00 602,208.66 Completed 2018-01-16 2018-02-22 2018-01-21 2018-04-18 2018-02-25 2018-03-26 2018-08-24 2019-06-06 Anbessa City Bus Service Safety in the City of Addis (Direct) Enterprise(ACBSE) Ababa ET-AARTB-40073-RFQ / Component A: Traffic Procurement of Office Management and Road Request for Single Stage - One IDA / 58160 Post Limited 45,000.00 8,602.75 Signed 2018-01-23 2015-12-18 2018-03-20 2015-12-28 2018-09-16 furniture for PIU and Safety in the City of Addis Quotations Envelope AACRA Ababa ET-AARTB-36632-GO-RFB / Component A: Traffic Procurement of Light Management and Road Open - Single Stage - One Detection and Ranging IDA / 58160 Prior Request for Bids 1,300,000.00 0.00 Canceled 2018-02-07 2018-02-28 2018-02-12 2018-04-18 2018-03-26 2018-04-25 2018-05-30 2018-11-26 Safety in the City of Addis International Envelope (LIDAR) Speed Measuring Ababa Devices for AAPC Component A: Traffic ET-AARTB-49178-GO-RFB / Management and Road Open - Single Stage - One Traffic enforcement uniforms IDA / 58160 Post Request for Bids 550,000.00 0.00 Canceled 2018-11-05 2019-02-12 2018-11-10 2018-12-22 2019-04-10 2019-01-21 2019-08-22 2019-02-25 2019-08-24 Safety in the City of Addis International Envelope for traffic police Ababa ET-AARTB-122486-GO-UN / Component A: Traffic Procurement of 17 units of Management and Road UN Agencies IDA / 58160 Prior Direct 2,100,000.00 613,286.33 Signed 2019-07-23 2019-07-30 2019-07-28 2019-08-06 2019-09-23 2019-09-19 2020-03-21 vehicles for Addis Ababa Safety in the City of Addis (Direct) Traffic police Ababa ET-AARTB-126997-GO-RFB Component A: Traffic / Procurement of Light Management and Road Open - Single Stage - One Detection Ranging (LIDAR) IDA / 58160 Prior Request for Bids 1,300,000.00 0.00 Canceled 2019-08-13 2019-08-18 2019-09-29 2019-10-29 2019-12-03 2020-05-31 Safety in the City of Addis International Envelope Speed Measuring Device for Ababa AAPC ET-AARTB-133497-GO-RFB Component A: Traffic / procurement of Light Management and Road Open - Single Stage - One Detection and Ranging ( IDA / 58160 Post Request for Bids 1,300,000.00 0.00 Canceled 2019-09-11 2019-09-19 2019-09-16 2019-10-28 2019-10-15 2019-11-27 2019-12-20 2020-01-01 2020-06-29 Safety in the City of Addis International Envelope LIDAR) speed measuring Ababa device ET-AARTB-135746-GO-RFB / Procurement of (Traffic Component A: Traffic Enforcement) Traffic Police Management and Road Single Stage - One IDA / 58160 Post Request for Bids Open - National 550,000.00 0.00 Canceled 2019-09-26 2019-10-01 2019-10-01 2019-11-12 2019-10-23 2019-12-12 2019-12-22 2020-01-16 2020-07-14 Uniform,Traffic Police Safety in the City of Addis Envelope Vest,Color Chalks and LED Ababa lencer M3R. ET-AARTB-170834-GO-RFQ / Procurement of COVID 19 Component A: Traffic Pending prevention materials suchas Management and Road Request for Single Stage - One IDA / 58160 Post Limited 325,000.00 0.00 Implementati 2020-04-27 2020-05-13 2020-05-28 50,000 liters of Hand Safety in the City of Addis Quotations Envelope on sanitizer and 50,000 liters of Ababa 96% Alcohol. ET-AARTB-170839-GO-RFQ / Procurement of Covid19 Component A: Traffic Pending prevention materials such as Management and Road Request for Single Stage - One IDA / 58160 Post Limited 325,000.00 0.00 Implementati 2020-04-27 2020-05-13 2020-05-28 50,000 pcs of high quality Safety in the City of Addis Quotations Envelope on face mask and 60,000 pcs of Ababa plastic gloves. ET-AARTB-170858-GO-RFQ Component A: Traffic / Procuerment of COVID 19 Pending Management and Road Request for Single Stage - One prevention material such as IDA / 58160 Post Limited 50,000.00 0.00 Implementati 2020-04-27 2020-05-15 2020-05-30 Safety in the City of Addis Quotations Envelope 10,000 liters of Bus cleaning on Ababa chemicals (Bleach). Page 3 ET-AARTB-170861-GO-RFQ / Procuerment of COVID19 prevention materials such as Component A: Traffic Pending 50 pcs of disinfectant back Management and Road Request for Single Stage - One IDA / 58160 Post Limited 50,000.00 0.00 Implementati 2020-04-27 2020-05-15 2020-05-30 pack-chemical sprayer,50 pcs Safety in the City of Addis Quotations Envelope on of disposable long sleeve Ababa water resistant gown and 50 pcs of full face shield safety. ET-AARTB-170846-GO-RFQ Component A: Traffic / Procurement of COVID19 Pending Management and Road Request for Single Stage - One prevention materials such as IDA / 58160 Post Limited 90,000.00 0.00 Implementati 2020-04-27 2020-05-15 2020-05-30 Safety in the City of Addis Quotations Envelope 300 pcs of Inferared on Ababa Thermometers. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Traffic ET-AARTB-362-CS-QCBS / Management and Road Quality And Cost- Open - Road Safety Awareness and IDA / 58160 Post 190,000.00 0.00 Canceled 2016-10-27 2016-11-17 2016-12-31 2017-01-28 2017-02-27 2017-04-03 2017-05-08 2018-05-08 Safety in the City of Addis Based Selection International Public Education Ababa ET-AARTB-366-CS-QCBS / Component A: Traffic Comprehensive road asset Management and Road Quality And Cost- Open - management system and IDA / 58160 Prior 2,500,000.00 3,293,627.43 Signed 2016-11-29 2016-11-24 2016-12-20 2017-01-17 2017-02-02 2018-02-15 2017-05-02 2018-05-29 2017-06-01 2018-12-01 2017-07-06 2019-01-14 2017-08-10 2019-01-31 2018-08-10 Safety in the City of Addis Based Selection International developing a road Ababa maintenance manual ET-AARTB-367-CS-QCBS / Component A: Traffic Updating road design Management and Road Quality And Cost- Open - Under manual, improving contract IDA / 58160 Prior 1,000,000.00 0.00 2016-11-15 2016-12-06 2019-07-10 2017-01-19 2017-04-18 2017-05-18 2017-06-22 2017-07-27 2018-07-27 Safety in the City of Addis Based Selection International Implementation management and associated Ababa capacity building ET-AARTB-369-CS-QCBS / Component A: Traffic Advisory assistance on Management and Road Quality And Cost- Open - Pending restructuring of AACRA and IDA / 58160 Prior 500,000.00 0.00 2017-01-24 2017-02-14 2017-03-30 2017-06-27 2017-07-27 2017-08-31 2017-10-05 2018-10-05 Safety in the City of Addis Based Selection International Implementation re-establishing its functional Ababa units Component A: Traffic ET-AARTB-370-CS-QCBS / Management and Road Quality And Cost- Open - Development of a drainage IDA / 58160 Prior 800,000.00 1,572,736.60 Signed 2016-11-15 2018-03-09 2016-12-06 2018-03-30 2017-01-19 2018-10-26 2017-04-25 2019-07-04 2017-05-25 2019-09-24 2017-06-29 2020-02-27 2017-08-03 2020-05-13 2018-08-03 Safety in the City of Addis Based Selection International master plan for Addis Ababa Ababa ET-AARTB-373-CS-QCBS / Component A: Traffic Advisory Assistance in Management and Road Quality And Cost- Open - Pending Establishing and Operating IDA / 58160 Prior 1,000,000.00 0.00 2017-01-31 2017-02-21 2017-04-06 2017-07-11 2017-08-10 2017-09-14 2017-10-19 2018-10-19 Safety in the City of Addis Based Selection International Implementation the Public and Freight Ababa Transport Authority (PFTA) Page 4 ET-AARTB-374-CS-QCBS / Component A: Traffic Support the implementation Management and Road Quality And Cost- Open - of Institutional and Policy IDA / 58160 Prior 1,000,000.00 1,108,178.54 Signed 2016-12-27 2018-10-26 2017-01-17 2018-10-23 2017-03-02 2019-03-02 2017-05-30 2019-05-16 2017-06-29 2019-09-06 2017-08-03 2019-12-02 2017-09-07 2019-12-13 2018-09-07 Safety in the City of Addis Based Selection International reform in the Provision of Ababa public Transport Service. ET-AARTB-376-CS-QCBS / Component A: Traffic Design and supervision of Management and Road Quality And Cost- Open - the installation of the IT IDA / 58160 Prior 2,000,000.00 1,943,386.57 Signed 2016-07-21 2016-08-17 2016-08-11 2016-09-29 2016-09-24 2017-02-16 2016-12-27 2017-01-26 2017-12-06 2017-03-02 2018-05-18 2017-04-06 2018-06-13 2018-04-06 Safety in the City of Addis Based Selection International infrastructure and systems Ababa for Anbessa bus operation. Component A: Traffic ET-AARTB-377-CS-QCBS / Management and Road Quality And Cost- Open - Advice on Optimization of IDA / 58160 Prior 1,000,000.00 1,406,572.44 Signed 2016-11-15 2017-07-27 2016-12-06 2017-12-22 2017-01-19 2018-05-16 2017-04-11 2018-09-06 2017-05-11 2018-10-26 2017-06-15 2019-02-12 2017-07-20 2019-02-22 2018-07-20 Safety in the City of Addis Based Selection International Anbessa Bus Management Ababa ET-AARTB-379-CS-QCBS / Component A: Traffic Design on improving Management and Road Quality And Cost- Open - Pending IDA / 58160 Prior 500,000.00 0.00 2017-03-17 2017-04-07 2017-05-21 2017-08-15 2017-09-14 2017-10-19 2017-11-23 2018-11-23 Anbessa's operational Safety in the City of Addis Based Selection International Implementation facilities Ababa Component A: Traffic ET-AARTB-382-CS-CQS / Consultant Management and Road Finance Receivable and IDA / 58160 Post Qualification Open - National 30,000.00 0.00 Canceled 2016-10-27 2016-11-17 2016-12-31 2017-01-30 2017-03-06 2017-09-02 Safety in the City of Addis Payable clearance of AACRA Selection Ababa ET-AARTB-407-CS-QCBS / Component A: Traffic Development of transit Management and Road Quality And Cost- Open - IDA / 58160 Prior 500,000.00 0.00 Canceled 2016-08-30 2016-09-20 2016-11-03 2016-12-01 2016-12-31 2017-02-04 2017-03-11 2018-03-11 oriented development (TOD) Safety in the City of Addis Based Selection International program for the city of AA. Ababa Component A: Traffic ET-AARTB-360-CS-QCBS / Management and Road Quality And Cost- Open - Prepare Parking Strategy IDA / 58160 Prior 750,000.00 1,448,770.00 Signed 2016-07-17 2016-08-05 2016-08-07 2016-09-20 2017-02-16 2016-12-18 2017-04-26 2017-01-17 2017-12-05 2017-02-21 2018-05-11 2017-03-28 2018-06-04 2018-03-28 Safety in the City of Addis Based Selection International and Implementation Program Ababa Component A: Traffic ET-AARTB-361-CS-QCBS / Management and Road Quality And Cost- Open - Pending Future Traffic Planning IDA / 58160 Prior 700,000.00 0.00 2017-06-19 2017-07-10 2017-08-23 2017-11-20 2017-12-20 2018-01-24 2018-02-28 2019-02-28 Safety in the City of Addis Based Selection International Implementation Studies Ababa ET-AARTB-375-CS-QCBS / Component A: Traffic Assistance in planning Management and Road Quality And Cost- Open - Pending /establishing an integrated IDA / 58160 Prior 2,500,000.00 0.00 2016-12-14 2017-01-04 2017-02-17 2017-05-08 2017-06-07 2017-07-12 2017-08-16 2018-08-16 Safety in the City of Addis Based Selection International Implementation Public Transport Systems for Ababa all modes. ET-AARTB-399-CS-QCBS / Component A: Traffic Development of Strategic Management and Road Quality And Cost- Open - IDA / 58160 Prior 4,000,000.00 4,182,747.51 Signed 2017-02-06 2017-12-22 2017-02-27 2018-01-31 2017-04-12 2018-06-27 2017-07-12 2017-08-11 2018-12-31 2017-09-15 2019-04-15 2017-10-20 2019-04-30 2018-10-20 transport master plan for Safety in the City of Addis Based Selection International the city of Addis Ababa Ababa Component A: Traffic ET-AARTB-359-CS-QCBS / Management and Road Quality And Cost- Open - Traffic study, design and IDA / 58160 Prior 6,000,000.00 22,233,705.94 Signed 2016-10-18 2016-11-08 2017-01-17 2016-12-22 2018-02-28 2017-02-28 2018-07-19 2017-03-30 2018-10-18 2017-05-04 2018-12-31 2017-06-08 2019-02-01 2017-07-25 Safety in the City of Addis Based Selection International construction supervision Ababa ET-AARTB-408-CS-QCBS / Component B: Improvement Advisory Assistance in of Integrated Urban Quality And Cost- Open - Pending Improving Metro Area IDA / 58160 Prior 1,000,000.00 0.00 2017-03-19 2017-04-09 2017-05-23 2017-07-06 2017-08-05 2017-09-09 2017-10-14 2018-10-14 Planning and Transport Based Selection International Implementation Master Plan and preparing System Local Development Plans Component A: Traffic ET-AARTB-405-CS-LCS / Management and Road Least Cost Under IDA / Q9810 Post Open - National 15,000.00 0.00 2016-07-20 2016-08-10 2016-09-23 2016-10-21 2016-11-20 2016-12-25 2017-01-29 2017-07-28 Annual Audit Safety in the City of Addis Selection Implementation Ababa Page 5 ET-AARTB-5966-CS-QCBS / Study, Design, and Component A: Traffic Construction Supervision of Management and Road Quality And Cost- Open - IDA / 58160 Prior 2,500,000.00 3,990,092.03 Signed 2017-02-14 2017-05-05 2017-03-07 2017-05-11 2017-04-20 2018-02-15 2017-06-07 2018-05-22 2017-07-07 2018-09-18 2017-08-11 2019-02-12 2017-09-15 2019-02-22 2018-09-15 Comprehensive Transport Safety in the City of Addis Based Selection International and Traffic Improvement Ababa Measures for Merkato Area ET-AARTB-16763-CS-CDS / Consultancy Service to Provide Training on Public Component A: Traffic Transport Development and Management and Road Non-Profit Pending IDA / 58160 Post Direct 120,000.00 0.00 2017-06-04 2017-07-14 2017-08-18 2018-02-14 Capacity Building Safety in the City of Addis Organizations Implementation Programme using Ababa International Association of Public Transportation /UITP/ ET-AARTB-23388-CS-NPO / Consultancy Service to Component A: Traffic provide training on Ticketing Management and Road Non-Profit Pending and Fare Management and IDA / 58160 Post Direct 32,000.00 0.00 2017-08-10 2017-09-19 2017-10-24 2018-04-22 Safety in the City of Addis Organizations Implementation Asset Management ( by Ababa International Association of Public Transport (UITP) ET-AARTB-365-CS-QCBS / Component A: Traffic Design and supervision of Management and Road Quality And Cost- Open - IDA / 58160 Prior 750,000.00 0.00 Canceled 2016-07-18 2016-09-05 2016-08-08 2016-09-21 2016-10-30 2016-11-29 2017-01-27 2016-12-29 2017-02-02 2017-03-09 2018-03-09 Pedestrian footbridges Safety in the City of Addis Based Selection International construction Ababa ET-AARTB-80356-GO-RFB / Component A: Traffic Pedestrians Crossing Facility Management and Road Quality And Cost- Open - Under IDA / 58160 Prior 750,000.00 0.00 2018-10-15 2018-11-01 2018-11-05 2018-12-04 2018-12-19 2020-01-02 2019-02-17 2020-06-18 2019-03-10 2020-09-01 2019-04-14 2019-05-19 2020-05-18 Planning and Detailed Safety in the City of Addis Based Selection International Implementation Engineering Design Ababa Component A: Traffic ET-AARTB-81969-CS-INDV Consultant Management and Road Under / ESIA and RAP consultant IDA / 58160 Post Qualification Open - National 77,500.00 0.00 2018-10-22 2018-08-01 2018-11-12 2018-12-26 2019-02-21 2019-01-25 2019-03-01 2019-08-28 Safety in the City of Addis Implementation for main ITS Selection Ababa ET-AARTB-81971-CS-INDV Component A: Traffic / ESIA and RAP consultant Consultant Management and Road Under for Comprehensive Transport IDA / 58160 Post Qualification Open - National 45,000.00 0.00 2018-10-22 2018-10-22 2018-11-12 2018-12-26 2019-01-25 2019-03-01 2019-08-28 Safety in the City of Addis Implementation and Traffic Improvement Selection Ababa Measures for Merkato Area ET-AARTB-104745-CS-CQS / Component A: Traffic Strategic Environmental and Consultant Management and Road Under Social Assessment (SESA) IDA / 58160 Post Qualification Open - National 25,000.00 0.00 2019-03-07 2019-03-13 2019-03-28 2019-05-11 2019-06-10 2019-07-15 2020-01-11 Safety in the City of Addis Implementation for Drainage Master Plan Selection Ababa for Addis Ababa ET-AARTB-104750-CS-CQS / Strategic Environmental and Component A: Traffic Social Assessment (SESA) Consultant Management and Road Under for Strategic Comprehensive IDA / 58160 Post Qualification Open - National 35,000.00 0.00 2019-03-14 2019-03-13 2019-04-04 2019-05-18 2019-06-17 2019-07-22 2020-01-18 Safety in the City of Addis Implementation Transport Development Plan Selection Ababa (SCTDP) for the City of Addis Ababa ET-AARTB-106550-CS-LCS / Component A: Traffic Consultancy Service for Management and Road Least Cost Under IDA / 58160 Post Open - National 25,000.00 0.00 2019-04-02 2019-04-16 2019-04-23 2019-06-16 2019-06-28 2019-07-14 2019-08-13 2019-09-17 2019-10-22 2020-04-19 TRANSIP External Audit for Safety in the City of Addis Selection Implementation 2018/19 and 2019/20 EFY Ababa Page 6 ET-AARTB-110998-CS-QCBS / Consultancy Service for Advisory Service on Component A: Traffic Developing an Improved Management and Road Quality And Cost- Open - Under IDA / 58160 Prior 780,000.00 0.00 2019-06-30 2019-07-21 2019-09-03 2019-10-01 2019-10-31 2019-12-05 2020-01-09 2021-01-08 Road Maintenance and Safety in the City of Addis Based Selection International Implementation Associated Funding Strategy Ababa for Addis Ababa city Road authority ET-AARTB-129212-CS-QCBS / Consultancy Services for Component A: Traffic Technical Assistance and Management and Road Quality And Cost- Open - Under IDA / 58160 Prior 2,136,450.00 0.00 2019-09-09 2019-09-02 2019-09-18 2019-09-04 2019-11-01 2020-01-03 2019-11-29 2020-03-12 2019-12-29 2020-09-02 2020-02-02 2020-03-08 2021-03-08 Review of Outputs from Safety in the City of Addis Based Selection International Implementation TRANSIP Sub- Ababa Projects/Activities ET-AARTB-135393-CS-CQS / Component A: Traffic Consultant Consultancy Service for Management and Road IDA / 58160 Post Qualification Open - National 80,000.00 0.00 Canceled 2019-10-16 2019-09-16 2019-11-06 2019-12-20 2020-01-19 2020-02-23 2020-05-23 TRANSIP Gender Based Safety in the City of Addis Selection Violence (GBV) Assessment Ababa ET-AARTB-162082-CS-QCBS / Consultancy Service for Component A: Traffic Urban Transport Human Management and Road Quality And Cost- Open - IDA / 58160 Prior 670,000.00 0.00 Under Review 2020-03-09 2020-03-07 2020-03-30 2020-05-18 2020-05-13 2020-06-10 2020-07-10 2020-08-14 2020-09-18 2022-01-11 Capital Development Safety in the City of Addis Based Selection International Framework Project (UT- Ababa HCDP) ET-AARTB-162742-CS-CQS / Component A: Traffic Consultant Consultancy Service for Management and Road IDA / 58160 Post Qualification Open - National 80,000.00 0.00 Canceled 2020-03-09 2020-03-06 2020-03-30 2020-05-13 2020-06-12 2020-07-17 2020-10-15 Gender Based Violence Safety in the City of Addis Selection assessment for TRANSIP Ababa ET-AARTB-163884-CS-QCBS Component B: Improvement / Consultancy Service for of Integrated Urban Quality And Cost- Open - Under IDA / 58160 Prior 1,500,000.00 0.00 2020-03-18 2020-09-01 2020-04-08 2020-06-06 2020-07-21 2020-09-04 2020-10-09 2020-11-13 2021-11-13 Transit-Oriented Planning and Transport Based Selection International Implementation Development (TOD) Project System ET-AARTB-166326-CS-QCBS Component A: Traffic / Consultancy Service for Management and Road Quality And Cost- Under IDA / 58160 Post Open - National 80,000.00 0.00 2020-03-31 2020-03-31 2020-04-21 2020-06-04 2020-07-02 2020-08-01 2020-09-05 2020-10-10 2021-10-10 TRANSIP Gender Based Safety in the City of Addis Based Selection Implementation Violence (GBV) Assessment Ababa ET-AARTB-178373-CS-QCBS Component A: Traffic / Consultancy Service for Management and Road Quality And Cost- Open - Under Preparation of BRT IDA / 58160 Prior 1,800,000.00 0.00 2020-06-15 2020-08-05 2020-07-06 2020-08-25 2020-08-29 2020-10-13 2020-11-22 2020-12-27 2021-01-31 2022-09-23 Safety in the City of Addis Based Selection International Implementation Development Strategy in the Ababa City of Addis Ababa INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AARTB-363-CS-INDV / Component A: Traffic Advisory Assistance in Individual Management and Road Pending Establishing and Operating IDA / 58160 Prior Consultant Open - National 500,000.00 0.00 2016-07-21 2016-09-19 2016-08-08 2016-08-15 2016-09-20 2017-08-29 Safety in the City of Addis Implementation the Trafic Management Selection Ababa Agency ( TMA ) Component A: Traffic ET-AARTB-371-CS-INDV / Individual Management and Road Pending Technical Assistance to IDA / 58160 Prior Consultant Open - National 500,000.00 0.00 2017-02-14 2017-04-04 2017-04-25 2017-05-30 2017-11-26 Safety in the City of Addis Implementation ACCRA Selection Ababa Page 7 Component A: Traffic Individual ET-AARTB-381-CS-INDV / Management and Road IDA / Q9810 Post Consultant Open - National 40,000.00 24,288.69 Signed 2016-07-19 2015-10-27 2016-09-06 2015-11-20 2016-09-27 2015-12-04 2016-11-01 2015-11-30 2017-04-30 Safeguard Consultancy Safety in the City of Addis Selection Ababa Component A: Traffic ET-AARTB-385-CS-INDV / Individual Management and Road Project Implementation IDA / Q9810 Post Consultant Open - National 10,000.00 0.00 Canceled 2016-10-04 2016-11-22 2016-12-13 2017-01-17 2017-03-18 Safety in the City of Addis Manual Preparation Selection Ababa Component A: Traffic Individual ET-AARTB-386-CS-INDV / Management and Road IDA / 58160 Post Consultant Open - National 80,000.00 0.00 Canceled 2016-10-25 2016-12-13 2017-01-03 2017-02-07 2017-08-06 Project Officer Safety in the City of Addis Selection Ababa Component A: Traffic Individual ET-AARTB-391-CS-INDV / Management and Road IDA / Q9810 Post Consultant Open - National 50,000.00 12,984.90 Signed 2016-07-19 2016-07-12 2016-08-03 2016-01-25 2016-08-19 2016-02-18 2016-08-25 2016-02-18 2016-12-29 Procurement Experts Safety in the City of Addis Selection Ababa Component A: Traffic Individual ET-AARTB-394-CS-INDV / Management and Road IDA / Q9810 Post Consultant Open - National 50,000.00 11,686.41 Signed 2016-07-19 2015-08-28 2016-08-07 2015-12-15 2016-08-18 2016-04-18 2016-08-02 2016-04-18 2017-08-02 Financial management expert Safety in the City of Addis Selection Ababa Component A: Traffic Individual ET-AARTB-395-CS-INDV / Management and Road IDA / Q9810 Post Consultant Open - National 50,000.00 1,527.91 Signed 2016-07-19 2016-07-19 2016-08-07 2018-02-09 2016-08-15 2018-03-01 2016-08-31 2018-03-01 2017-08-31 Social Safeguard specialist Safety in the City of Addis Selection Ababa ET-AARTB-396-CS-INDV / Component A: Traffic Individual Environmental Safeguard Management and Road IDA / Q9810 Post Consultant Open - National 50,000.00 27,958.82 Signed 2016-07-19 2016-07-28 2016-08-08 2017-08-15 2016-08-10 2017-08-21 2016-08-09 2017-12-01 2017-08-09 Specialist(One for FTA PIU Safety in the City of Addis Selection & One for AA PIU) Ababa Component A: Traffic Individual ET-AARTB-398-CS-INDV / Management and Road IDA / Q9810 Post Consultant Open - National 50,000.00 0.00 Canceled 2016-08-30 2017-01-31 2017-02-21 2017-03-28 2018-03-28 Finance Expert for FTA Safety in the City of Addis Selection Ababa Component A: Traffic ET-AARTB-402-CS-CDS / Management and Road IDA / Q9810 Post Direct Selection Direct 10,000.00 151,209.74 Signed 2016-08-25 2018-03-26 2016-09-04 2017-12-17 2016-11-08 2018-04-05 2016-11-08 Project Staff Training (Local) Safety in the City of Addis Ababa Component A: Traffic ET-AARTB-404-CS-CDS / Management and Road Pending Project Staff Training IDA / 58160 Post Direct Selection Direct 20,000.00 0.00 2016-11-10 2016-11-20 2017-01-24 2017-03-25 Safety in the City of Addis Implementation (Abroad) Ababa Component C: Road Safety ET-AARTB-700-CS-INDV / Interventions and Individual Senior Procurement specialist IDA / Q9810 Institutional Strengthening Prior Consultant Open - National 50,000.00 15,581.89 Signed 2016-07-27 2018-09-26 2016-09-14 2016-03-04 2016-10-05 2018-09-29 2016-11-09 2016-07-08 2017-11-09 for FTA PIU of Selected Federal Selection Transport Institutions Component A: Traffic ET-AARTB-390-CS-INDV / Individual Management and Road Senior Procurement specialist IDA / Q9810 Prior Consultant Open - National 50,000.00 15,586.78 Signed 2016-07-19 2018-09-24 2016-08-07 2016-07-04 2016-08-08 2018-09-24 2016-07-30 2016-07-08 2017-07-30 Safety in the City of Addis for AA PIU Selection Ababa Component A: Traffic ET-AARTB-5962-CS-INDV / Individual Management and Road Transport Planner for Addis IDA / 58160 Post Consultant Open 20,000.00 25,809.82 Signed 2017-02-09 2017-03-30 2017-10-13 2017-04-20 2017-11-20 2017-05-25 2017-12-01 2017-11-21 Safety in the City of Addis Ababa PIU Selection Ababa Page 8 Component A: Traffic ET-AARTB-5963-CS-INDV / Individual Management and Road Traffic Engineer for Addis IDA / 58160 Post Consultant Open 20,000.00 2,349.89 Signed 2017-02-10 2017-03-31 2017-08-15 2017-04-21 2017-11-23 2017-05-26 2017-12-01 2017-11-22 Safety in the City of Addis Ababa PIU Selection Ababa Component A: Traffic ET-AARTB-5964-CS-INDV / Individual Management and Road Road and Material Engineer IDA / 58160 Post Consultant Open 20,000.00 33,373.28 Signed 2017-02-13 2017-04-03 2018-04-27 2017-04-24 2018-07-05 2017-05-29 2018-07-17 2017-11-25 Safety in the City of Addis for Addis Ababa PIU Selection Ababa Component A: Traffic ET-AARTB-5965-CS-INDV / Individual Management and Road Intelligent Transport System IDA / 58160 Post Consultant Open 20,000.00 35,348.61 Signed 2017-02-14 2017-12-25 2017-04-04 2018-08-03 2017-04-25 2018-11-16 2017-05-30 2018-12-31 2017-11-26 Safety in the City of Addis Expert for Addis Ababa PIU Selection Ababa ET-AARTB-19423-CS-CDS / Capacity Building in Road Component A: Traffic Construction Management by Management and Road Ethiopian Institute of IDA / 58160 Post Direct Selection Direct 130,434.00 108,456.54 Signed 2017-09-11 2017-09-21 2017-11-25 2017-09-25 2018-05-24 Safety in the City of Addis Architecture, Building Ababa Construction and City Development (EiABC) ET-AARTB-21812-CS-INDV Component A: Traffic / Project Supervisor for Individual Management and Road Transport Infrastructure IDA / 58160 Post Consultant Open 50,000.00 1,880.11 Signed 2017-08-01 2017-10-05 2017-09-19 2018-02-09 2017-10-10 2018-04-06 2017-11-14 2018-04-16 2018-05-13 Safety in the City of Addis Asset Management System Selection Ababa Consultancy Service ET-AARTB-5961-CS-INDV / Component A: Traffic Individual Project Supervisor for Management and Road IDA / 58160 Post Consultant Open 30,000.00 0.00 Canceled 2017-02-03 2017-03-24 2017-04-14 2017-05-19 2017-11-15 Transport Infrastructure Safety in the City of Addis Selection Asset Management System Ababa ET-AARTB-40493-CS-CDS / Component A: Traffic External audit service for Management and Road FY2017/18 by A.W. Thomas IDA / 58160 Post Direct Selection Direct 8,500.00 8,415.72 Completed 2018-01-18 2018-01-28 2018-04-03 2018-07-26 2018-09-30 2018-09-10 Safety in the City of Addis LP Chartered Certified Ababa Accountants ET-AARTB-36648-CS-INDV Component A: Traffic / Senior Procurement Individual Management and Road Specialist to enhance IDA / 58160 Post Consultant Open 50,000.00 32,811.83 Signed 2018-01-17 2018-02-14 2018-03-07 2018-04-27 2018-03-28 2018-07-03 2018-05-02 2018-08-27 2018-10-29 Safety in the City of Addis AACRA's Internal Selection Ababa Procurement Capacity Component A: Traffic ET-AARTB-36622-CS-INDV Individual Management and Road / Gender Specialist for AA IDA / 58160 Post Consultant Open 40,000.00 1,668.31 Signed 2018-01-30 2018-03-20 2018-04-27 2018-04-10 2018-06-08 2018-05-15 2018-06-16 2018-11-11 Safety in the City of Addis PIU Selection Ababa ET-AARTB-49169-CS-INDV Component A: Traffic / Capacity building expert Individual Management and Road for research and technology IDA / 58160 Post Consultant Open 30,000.00 0.00 Canceled 2018-03-08 2018-04-26 2018-05-17 2018-06-21 2018-12-18 Safety in the City of Addis transfer ( AACRA's Capacity Selection Ababa Building) ET-AARTB-81978-CS-CDS / Training program on the Component B: Improvement revised city master plan for of Integrated Urban Under 720 City Management IDA / 58160 Prior Direct Selection Direct 200,000.00 0.00 2018-10-17 2018-02-15 2018-10-27 2018-08-09 2018-12-31 2019-06-29 Planning and Transport Implementation Executives and Line System Managers ( Level II and III Training Program) Component A: Traffic Individual ET-AARTB-106033-CS-INDV Management and Road Under IDA / 58160 Post Consultant Open 25,000.00 0.00 2019-03-26 2019-06-10 2019-05-14 2019-06-13 2019-07-18 2020-07-17 / Senior Finance Expert Safety in the City of Addis Implementation Selection Ababa Page 9 Component A: Traffic Individual ET-AARTB-39687-CS-INDV Management and Road IDA / 58160 Post Consultant Open 30,000.00 0.00 Canceled 2018-01-25 2018-03-15 2018-04-05 2018-05-10 2018-11-06 / Finance Expert for AACRA Safety in the City of Addis Selection Ababa Component A: Traffic ET-AARTB-39686-CS-INDV Individual Management and Road / Project Manager for AA IDA / 58160 Post Consultant Open 50,000.00 0.00 Canceled 2018-01-30 2018-03-20 2018-04-10 2018-05-15 2018-11-11 Safety in the City of Addis PIU Selection Ababa Component A: Traffic Individual ET-AARTB-106099-CS-INDV Management and Road Under IDA / 58160 Prior Consultant Open 30,000.00 0.00 2019-06-15 2019-07-19 2019-08-03 2019-09-02 2019-10-07 2021-09-26 / Procurement Expert Safety in the City of Addis Implementation Selection Ababa Component A: Traffic ET-AARTB-106102-CS-INDV Individual Management and Road Under / Senior Procurement IDA / 58160 Prior Consultant Open 54,000.00 0.00 2019-06-30 2019-07-19 2019-08-18 2019-09-17 2019-10-22 2021-10-11 Safety in the City of Addis Implementation Specialist Selection Ababa Component A: Traffic Individual ET-AARTB-106055-CS-INDV Management and Road Under IDA / 58160 Post Consultant Open 54,000.00 0.00 2019-05-15 2019-03-14 2019-07-03 2019-08-02 2019-09-06 2021-08-26 / Contract and Claim Expert Safety in the City of Addis Implementation Selection Ababa ET-AARTB-106036-CS-INDV Component A: Traffic Individual / Project Supervisor for Management and Road Under IDA / 58160 Post Consultant Open 54,000.00 0.00 2019-05-31 2019-11-06 2019-07-19 2019-08-18 2019-09-22 2021-09-11 Transport Infrastructure Safety in the City of Addis Implementation Selection Asset Management Ababa Component A: Traffic ET-AARTB-106039-CS-INDV Individual Management and Road Under / Senior Pavement/Material IDA / 58160 Post Consultant Open 64,000.00 0.00 2019-05-31 2019-03-21 2019-07-19 2019-08-18 2019-09-22 2021-09-11 Safety in the City of Addis Implementation Engineer Selection Ababa Component A: Traffic ET-AARTB-106041-CS-INDV Individual Management and Road Under / Senior Transport Planner/ IDA / 58160 Post Consultant Open 64,000.00 0.00 2019-05-31 2019-03-13 2019-07-19 2019-08-18 2019-09-22 2021-09-11 Safety in the City of Addis Implementation Traffic Engineer Selection Ababa Component A: Traffic ET-AARTB-106042-CS-INDV Individual Management and Road Under / Project Manager for Project IDA / 58160 Post Consultant Open 70,000.00 0.00 2019-05-31 2019-02-13 2019-07-19 2019-08-18 2019-09-22 2021-09-11 Safety in the City of Addis Implementation Implementation Unit (PIU) Selection Ababa Component A: Traffic Individual ET-AARTB-106050-CS-INDV Management and Road Under IDA / 58160 Post Consultant Open 54,000.00 0.00 2019-05-31 2019-03-01 2019-07-19 2019-08-18 2019-09-22 2021-09-11 / Contract and Claim Expert Safety in the City of Addis Implementation Selection Ababa ET-AARTB-106057-CS-INDV Component A: Traffic Individual / Senior Management and Road Under IDA / 58160 Post Consultant Open 54,000.00 0.00 2019-05-31 2019-01-15 2019-07-19 2019-08-18 2021-08-28 2023-08-18 Hydrologist/Hydraulic Safety in the City of Addis Implementation Selection Engineer Ababa Component A: Traffic Individual ET-AARTB-106059-CS-INDV Management and Road Under IDA / 58160 Post Consultant Open 64,000.00 0.00 2019-05-31 2019-03-14 2019-07-19 2019-08-18 2019-09-22 2021-09-11 / Senior Structural Engineer Safety in the City of Addis Implementation Selection Ababa Component A: Traffic Individual ET-AARTB-106060-CS-INDV Management and Road Under IDA / 58160 Post Consultant Open 54,000.00 0.00 2019-05-31 2019-06-03 2019-07-19 2019-08-18 2019-09-22 2021-09-11 / Senior Highway Engineer Safety in the City of Addis Implementation Selection Ababa Component A: Traffic ET-AARTB-106048-CS-INDV Individual Management and Road Under / Project Manager for IDA / 58160 Post Consultant Open 70,000.00 0.00 2019-05-31 2019-02-13 2019-07-19 2019-08-18 2019-09-22 2021-10-11 Safety in the City of Addis Implementation AACRA Selection Ababa Page 10 ET-AARTB-384-CS-INDV / Component A: Traffic Individual Financial Specialist for Management and Road IDA / Q9810 Prior Consultant Open - National 10,000.00 0.00 Canceled 2016-07-19 2016-09-06 2016-09-27 2016-11-01 2017-04-30 Preparation of Finance Safety in the City of Addis Selection Management Guideline Ababa ET-AARTB-392-CS-INDV / Component A: Traffic Senior Financial Individual Management and Road management specialist (one IDA / Q9810 Prior Consultant Open - National 11,000.00 0.00 Canceled 2016-07-19 2016-08-01 2016-08-14 2016-08-18 2016-09-15 2017-09-15 Safety in the City of Addis for FTA PIU and One for Selection Ababa AA PIU) ET-AARTB-36623-CS-INDV Component A: Traffic / Senior Procurement Individual Management and Road Specialist to enhance IDA / 58160 Post Consultant Open 50,000.00 0.00 Canceled 2018-01-17 2017-12-20 2018-03-07 2018-04-27 2018-03-28 2018-07-03 2018-05-02 2018-10-29 Safety in the City of Addis AACRA's Internal Selection Ababa Procurement Capacity Component A: Traffic Individual ET-AARTB-122352-CS-INDV Management and Road Under IDA / Q9810 Post Consultant Open - National 50,000.00 0.00 2019-07-18 2019-07-31 2019-08-19 2019-08-27 2019-09-12 2020-09-11 / Social Safeguard Specialist Safety in the City of Addis Implementation Selection Ababa ET-AARTB-111296-CS-CDS / Component A: Traffic Training on Transport Management and Road Pending IDA / 58160 Post Direct Selection Direct 150,000.00 0.00 2019-07-24 2019-08-03 2019-10-07 2020-04-04 Infrastructure Asset Safety in the City of Addis Implementation Management Systems Ababa ET-AARTB-145086-CS-INDV Component A: Traffic Individual / Transport Infrastructure Management and Road Under IDA / 58160 Post Consultant Open 30,000.00 0.00 2019-11-21 2019-11-15 2020-01-09 2020-01-30 2020-03-05 2021-03-05 Asset Management System Safety in the City of Addis Implementation Selection (TIAMS) project supervisor Ababa ET-AARTB-146340-CS-INDV Component A: Traffic Individual / International Consultant Management and Road Under IDA / 58160 Post Consultant Limited 20,000.00 0.00 2019-11-25 2019-11-01 2019-11-30 2019-12-21 2020-01-25 2020-03-25 for Mid Term Review of Safety in the City of Addis Implementation Selection TRANSIP Ababa Component A: Traffic ET-AARTB-146341-CS-INDV Individual Management and Road Under / Local Consultant for Mid- IDA / 58160 Post Consultant Limited 5,000.00 0.00 2019-11-25 2019-11-01 2019-11-30 2019-12-21 2020-01-25 2020-03-25 Safety in the City of Addis Implementation Term Review of TRANSIP Selection Ababa ET-AARTB-149650-CS-CDS / Component A: Traffic Experience Sharing and Management and Road Under IDA / 58160 Post Direct Selection Direct 78,000.00 0.00 2019-12-16 2019-12-11 2019-12-26 2020-02-29 2020-03-10 Training of Public Transport Safety in the City of Addis Implementation Best Practices in Korea Ababa Component A: Traffic ET-AARTB-152487-CS-INDV Individual Management and Road Under / Intelligent Transport IDA / 58160 Post Consultant Direct 35,000.00 0.00 2020-01-06 2020-01-03 2020-01-16 2020-02-06 2020-03-12 2021-03-12 Safety in the City of Addis Implementation System(ITS) Expert Selection Ababa ET-AARTB-182064-CS-INDV Component A: Traffic Individual / Transport Infrastructure Management and Road Pending IDA / 58160 Post Consultant Direct 30,000.00 0.00 2020-09-09 2020-09-19 2020-10-10 2020-11-14 2021-11-14 Asset Management System Safety in the City of Addis Implementation Selection (TIAMS) Project Supervisor Ababa Page 11