EDL_Consolidated Financial Statements Dec 31, 2015 (English)

Financial Statement AUD0008162 JAN 11, 2017

Chanthavong,Thongkham Disclosed

Lao People's Democratic Republic - LA-Rural Electrification Phase II (English)

Implementation Completion Report Review ICRR0020108 DEC 09, 2016

IEG Review Team Disclosed

Lao People's Democratic Republic - Second Phase of the Rural Electrification Project (English)

Ratings for the Second Phase of the Rural Electrification Project for Lao People's Democratic Republic were as follows: outcomes were moderately satisfactory, the risk to development outcome was moderate, the Bank performance was moderately satisfactory, and the Borrower performance was also moderately satisfactory. ... See More +

Implementation Completion and Results Report ICR3582 DEC 17, 2015

Disclosed

Lao People's Democratic Republic - Second Phase of the Rural Electrification Project : implementation support mission - March 8 to 13, 2015 (English)

Aide Memoire 97459 MAR 13, 2015

Phonepraseuth,Vilayvanh Disclosed

Lao People's Democratic Republic - Second Phase of the Rural Electrification Project : financial statements for the year ended 31 December 2014 (English)

Auditing Document 98233 DEC 31, 2014

Disclosed

Laos - Second Phase of the Global Environment Facility (GEF) Rural Electrification Project : financial statements as of December 31, 2013 (English)

Auditing Document 89722 DEC 31, 2013

Disclosed

Lao - Second Phase of the Rural Electrification Project : restructuring (Vol. 2) : Data sheet (English)

The objectives of the Second Phase of the Rural Electrification Project are to increase access to electricity of rural households in villages of Project provinces and to further improve the financial performance of Electricite du Laos (EdL). ... See More +

Project Paper 82348 NOV 25, 2013

Disclosed

Official Documents- Amendment to the Financing Agreement for Grant H538-LA and GEF Grant Agreement for TF098662 (English)

Agreement NOV 22, 2013

Hristov,Manush A. Disclosed

Lao - Second Phase of the Rural Electrification Project : restructuring : Main report (English)

The objectives of the Second Phase of the Rural Electrification Project are to increase access to electricity of rural households in villages of Project provinces and to further improve the financial performance of Electricite du Laos (EdL). ... See More +

Project Paper 82348 OCT 28, 2013

Disclosed

Lao People's Democratic Republic - Rural Electrification Phase II Project of the Rural Electrification (APL) Program : P110978 - Implementation Status Results Report : Sequence 02 (English)

Implementation Status and Results Report SEP 28, 2011

Fraser,Julia M. Disclosed

Aide Memoire-Lao PDR REP-June 2011 (final2).pdf (English)

Aide Memoire JUN 30, 2011

Fraser,Julia M. Disclosed

Title Document Date Report No. Document Type Also available in
EDL_Consolidated Financial Statements Dec 31, 2015 (English)
See More +
JAN 11, 2017 AUD0008162 Financial Statement
Lao People's Democratic Republic - LA-Rural Electrification Phase II (English)
See More +
DEC 09, 2016 ICRR0020108 Implementation Completion Report Review
Lao People's Democratic Republic - Second Phase of the Rural Electrification Project (English)
See More +
DEC 17, 2015 ICR3582 Implementation Completion and Results Report
Lao People's Democratic Republic - Rural Electrification Phase II Project of the Rural Electrification (APL) Program : P110978 - Implementation Status Results Report : Sequence 07 (English)
See More +
JUN 15, 2015 ISR19064 Implementation Status and Results Report
Lao People's Democratic Republic - Second Phase of the Rural Electrification Project : implementation support mission - March 8 to 13, 2015 (English)
See More +
MAR 13, 2015 97459 Aide Memoire
Lao People's Democratic Republic - Second Phase of the Rural Electrification Project : financial statements for the year ended 31 December 2014 (English)
See More +
DEC 31, 2014 98233 Auditing Document
Lao People's Democratic Republic - Second Phase of the Rural Electrification Project : statement of receipts, disbursements and fund balance for the year ended 31 December 2014 (English)
See More +
DEC 31, 2014 98234 Auditing Document
Lao People's Democratic Republic - Rural Electrification Phase II Project of the Rural Electrification (APL) Program : P110978 - Implementation Status Results Report : Sequence 06 (English)
See More +
DEC 05, 2014 ISR17091 Implementation Status and Results Report
Lao People's Democratic Republic - Rural Electrification Phase II Project of the Rural Electrification (APL) Program : P110978 - Implementation Status Results Report : Sequence 05 (English)
See More +
JUN 14, 2014 ISR14295 Implementation Status and Results Report
Laos - Second Phase of the Global Environment Facility (GEF) Rural Electrification Project : financial statements as of December 31, 2013 (English)
See More +
DEC 31, 2013 89722 Auditing Document
Laos - Second Phase of the Global Environment Facility (GEF) Rural Electrification Project : statement of receipts, disbursements, and fund balance for the year ended 31 December, 2013 (English)
See More +
DEC 31, 2013 89728 Auditing Document
Lao - Second Phase of the Rural Electrification Project : restructuring (Vol. 2) : Data sheet (English)
See More +
NOV 25, 2013 82348 Project Paper
Official Documents- Amendment to the Financing Agreement for Grant H538-LA and GEF Grant Agreement for TF098662 (English)
See More +
NOV 22, 2013 Agreement
Lao - Second Phase of the Rural Electrification Project : restructuring : Main report (English)
See More +
OCT 28, 2013 82348 Project Paper
Lao People's Democratic Republic - Rural Electrification Phase II Project of the Rural Electrification (APL) Program : P110978 - Implementation Status Results Report : Sequence 04 (English)
See More +
OCT 22, 2013 ISR11104 Implementation Status and Results Report
Lao People's Democratic Republic - Rural Electrification Phase II Project of the Rural Electrification (APL) Program : P110978 - Implementation Status Results Report : Sequence 03 ()
See More +
DEC 10, 2012 ISR8137 Implementation Status and Results Report
Lao People's Democratic Republic - Second Phase of the Rural Electrification Project of the Rural Electrification Adaptable Program Loan (APL) Project : procurement plan (English)
See More +
JUN 28, 2012 80801 Procurement Plan
Lao People's Democratic Republic - Second Phase of the Rural Electrification Project of the Rural Electrification Adaptable Program Loan (APL) Project : procurement plan (English)
See More +
FEB 29, 2012 67423 Procurement Plan
Lao People's Democratic Republic - Rural Electrification Phase II Project of the Rural Electrification (APL) Program : P110978 - Implementation Status Results Report : Sequence 02 (English)
See More +
SEP 28, 2011 Implementation Status and Results Report
Aide Memoire-Lao PDR REP-June 2011 (final2).pdf (English)
See More +
JUN 30, 2011 Aide Memoire