Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Sudan : Sudan Social Safety Net Project PLAN General Information Country: Sudan Banks Approval Date of the Original Procurement Plan: 2016-09-29 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-03-01 Project ID: P148349 GPN Date: Project Name: Sudan Social Safety Net Project Loan / Credit No: TF / A0362 Executing Agency(ies): Ministry of Welfare and Social Security WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Strengthening the Implementation of the Ministry of Welfare and Social Security SD-MOWSS-1503-GO-RFQ / Request for Single Stage - One TF / A0362 Cash Transfer Program ($3.12 Post Limited 12,550.00 8,249.87 Completed 2016-09-16 2016-11-11 2016-09-04 2017-05-10 2016-09-07 Office Furniture for PCU Quotations Envelope million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of Welfare and Social Security SD-MOWSS-1502-GO-RFQ / Request for Single Stage - One TF / A0362 Cash Transfer Program ($3.12 Post Limited 15,000.00 6,122.81 Completed 2016-09-12 2016-11-07 2016-09-06 2017-05-06 2016-09-08 Office Tools and Stationery Quotations Envelope million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of SD-MOWSS-1494-GO-RFQ / Welfare and Social Security Request for Single Stage - One Procurement Of Two (2) 4X4 TF / A0362 Cash Transfer Program ($3.12 Post Limited 40,000.00 59,000.00 Completed 2016-09-14 2016-11-09 2016-09-25 2017-05-08 2017-01-12 Quotations Envelope double cabin pick Ups million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) SD-MOWSS-1501-GO-RFB / IT Component 1. Strengthening the Equipment, Hardware for PCU, Implementation of the Ministry of Procurement of Devices for the Welfare and Social Security Implementation of the model to Single Stage - One Under TF / A0362 Cash Transfer Program ($3.12 Prior Request for Bids Open - National 313,000.00 0.00 2016-10-01 2016-10-26 2016-10-06 2016-11-18 2016-11-17 2016-12-22 2016-12-17 2017-01-21 2017-07-20 capture real-time information (250 Envelope Implementation million, of which US$3.00 million Tablets), MIS / M&E Equipment Bank financed and US$120,000 for the implementation of the GoS contr.) PSN Pilot Component 1. Strengthening the SD-MOWSS-1500-GO-RFB / Implementation of the Ministry of Design and implementation of an Welfare and Social Security Single Stage - One Integrated Information System TF / A0362 Cash Transfer Program ($3.12 Prior Request for Bids Open - International 800,000.00 590,317.00 Signed 2016-10-16 2017-04-04 2016-10-21 2017-05-25 2016-12-02 2017-07-03 2017-01-01 2017-09-12 2017-02-05 2017-11-22 2017-08-04 Envelope For the Ministry of Welfare and million, of which US$3.00 million Social Security (MoWSS) Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of SD-MOWSS-1499-GO-RFQ / Welfare and Social Security Development of Certified LAN Request for Single Stage - One TF / A0362 Cash Transfer Program ($3.12 Post Limited 77,500.00 194,990.94 Signed 2016-10-07 2017-06-07 2016-12-02 2017-08-09 2017-05-31 Network for MoWSS and State Quotations Envelope million, of which US$3.00 million Offices Bank financed and US$120,000 GoS contr.) SD-MOWSS-1498-GO-RFB / 1/VPN Connectivity Services of Component 1. Strengthening the SDC with MoWSS, Implementing Implementation of the Ministry of Agencies and State Offices Welfare and Social Security 2/Third Party Data Center Single Stage - One Under TF / A0362 Cash Transfer Program ($3.12 Prior Request for Bids Open - National 319,038.00 0.00 2016-10-30 2016-11-09 2016-11-04 2017-01-26 2016-12-16 2017-01-15 2017-02-19 2017-08-18 Services for the interim period of Envelope Implementation million, of which US$3.00 million 2 Years Bank financed and US$120,000 3/Connectivity services to be GoS contr.) used on tablets for data synchronization Component 1. Strengthening the SD-MOWSS-1495-GO-RFQ / Implementation of the Ministry of Supply media requirements for Welfare and Social Security Public Information Campaign to Request for Single Stage - One Pending TF / A0362 Cash Transfer Program ($3.12 Post Limited 35,000.00 0.00 2016-10-07 2016-12-02 2017-05-31 support operational processes, Quotations Envelope Implementation million, of which US$3.00 million such as: Targeting, Payments, Bank financed and US$120,000 Case Management, etc.. GoS contr.) Component 1. Strengthening the SD-MOWSS-1497-GO-RFQ / Implementation of the Ministry of Procurement of Devices for the Welfare and Social Security Implementation of the model to Request for Single Stage - One TF / A0362 Cash Transfer Program ($3.12 Post Limited 10,000.00 12,335.25 Completed 2016-09-14 2016-11-09 2016-09-04 2017-05-08 2016-09-05 capture real-time information on Quotations Envelope million, of which US$3.00 million the field and identification of Bank financed and US$120,000 people. (25 Tablets) GoS contr.) Component 1. Strengthening the SD-MOWSS-1493-GO-RFQ / Implementation of the Ministry of Supply of Software for data Welfare and Social Security collection on Tablets for the Request for Single Stage - One TF / A0362 Cash Transfer Program ($3.12 Post Limited 85,000.00 41,117.50 Signed 2016-09-14 2016-11-09 2016-09-20 2017-05-08 model to capture real-time Quotations Envelope million, of which US$3.00 million information on the field and Bank financed and US$120,000 identification of people. GoS contr.) Page 1 Component 1. Strengthening the SD-MOWSS-2278-GO-RFQ / Implementation of the Ministry of Hardware for PCU: 15 Desktop Welfare and Social Security Computer, 3 - Multi-function Request for Single Stage - One TF / A0362 Cash Transfer Program ($3.12 Post Limited 70,000.00 86,897.20 Completed 2016-10-10 2016-12-05 2016-11-08 2017-06-03 2016-11-16 Printer, 15 - UPS 800VA, 3 - Quotations Envelope million, of which US$3.00 million UPS 1000VA, Photocopier and Bank financed and US$120,000 Fax Machine GoS contr.) Component 1. Strengthening the Implementation of the Ministry of SD-MOWSS-12024-GO-RFB / IT Welfare and Social Security Hardware Infrastructure for the Single Stage - One Under TF / A0362 Cash Transfer Program ($3.12 Post Request for Bids Open - National 173,450.00 0.00 2017-04-09 2017-12-21 2017-04-14 2017-05-26 2017-06-25 2017-07-30 2018-01-26 MoWSS Data Center and State Envelope Implementation million, of which US$3.00 million Offices Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of SD-MOWSS-16166-GO-RFQ / Welfare and Social Security Request for Single Stage - One supply of Tablet devices, covers TF / A0362 Cash Transfer Program ($3.12 Post Limited 100,000.00 80,000.00 Signed 2017-05-30 2017-07-25 2017-05-04 2018-01-21 Quotations Envelope and warranty million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-MOWSS-1496-NC-RFQ / Component 1. Strengthening the Technical course to train on the Implementation of the Ministry of development and implementation Welfare and Social Security Request for Single Stage - One Pending of practical tools for budgetary TF / A0362 Cash Transfer Program ($3.12 Post Limited 10,000.00 0.00 2016-10-21 2016-12-16 2017-06-14 Quotations Envelope Implementation management as well as efficient million, of which US$3.00 million monitoring and control of Bank financed and US$120,000 programs and project costs. GoS contr.) Component 1. Strengthening the SD-MOWSS-1492-NC-RFQ / Implementation of the Ministry of ICT Training for all offices of Welfare and Social Security MoWSS: Training for MoWSS Request for Single Stage - One TF / A0362 Cash Transfer Program ($3.12 Post Limited 50,000.00 36,829.12 Signed 2016-10-27 2016-12-22 2017-05-21 2017-06-20 Information Center Team, 18 x Quotations Envelope million, of which US$3.00 million State Offices Team and Locality Bank financed and US$120,000 Team GoS contr.) Component 1. Strengthening the Implementation of the Ministry of SD-MOWSS-2277-NC-RFQ / Welfare and Social Security Connectivity services to be used Request for Single Stage - One TF / A0362 Cash Transfer Program ($3.12 Post Limited 30,000.00 715.91 Completed 2016-10-10 2016-12-05 2016-11-02 2017-06-03 2016-11-08 on tablets for data Quotations Envelope million, of which US$3.00 million synchronization Bank financed and US$120,000 GoS contr.) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Strengthening the SD-MOWSS-1480-CS-CQS / Implementation of the Ministry of Project audit & PSN Project Welfare and Social Security Consultant Pending audit, to be conducted at the end TF / A0362 Cash Transfer Program ($3.12 Prior Qualification Open - National 21,700.00 0.00 2016-10-02 2016-10-23 2016-12-06 2017-01-05 2017-02-09 2017-08-08 Implementation of each of the three years of million, of which US$3.00 million Selection project implementation Bank financed and US$120,000 GoS contr.) SD-MOWSS-1479-CS-CQS / Component 2. Piloting a Technical Assistance: Productive Safety Net Approach Undertake required training Consultant (US$1.96, of which US$0.5 Pending activities on project principles TF / A0362 Prior Qualification Open - National 50,000.00 0.00 2016-10-16 2016-11-06 2016-12-20 2017-01-19 2017-02-23 2017-08-22 million Bank financed and Implementation and operational aspects Selection US$1.46 million GoS principles,operational aspects contribution) and sub-project design Component 2. Piloting a SD-MOWSS-1504-CS-CQS / Productive Safety Net Approach Evaluation: Development of a Consultant (US$1.96, of which US$0.5 baseline for the PSN pilot in year TF / A0362 Prior Qualification Open - National 65,000.00 54,694.26 Under Review 2016-12-04 2016-10-20 2016-12-25 2017-03-15 2017-02-07 2017-02-09 2017-03-09 2017-04-05 2017-04-13 2017-04-06 2017-10-10 million Bank financed and 1 and the final evaluation in year Selection US$1.46 million GoS 3. contribution) SD-MOWSS-1505-CS-CQS / Livelihoods Planning: Develop and train staff on household Component 2. Piloting a livelihood promotion. Undertake Productive Safety Net Approach Consultant assessment of household (US$1.96, of which US$0.5 Pending TF / A0362 Prior Qualification Open - National 50,000.00 0.00 2016-10-30 2016-11-20 2017-01-03 2017-02-02 2017-03-09 2017-09-05 livelihoods, value chains and million Bank financed and Implementation Selection service providers. Train CSU, MF US$1.46 million GoS service providers, locality & state contribution) staff on household livelihoods promotion SD-MOWSS-1506-CS-CQS / Component 2. Piloting a Consultancy to develop Public Productive Safety Net Approach Consultant Information Campaign to support (US$1.96, of which US$0.5 Pending TF / A0362 Prior Qualification Open - National 35,000.00 0.00 2016-10-09 2016-10-30 2016-12-13 2017-01-12 2017-02-16 2017-08-15 operational processes, such as: million Bank financed and Implementation Selection Targeting, Payments, Case US$1.46 million GoS Management, etc.. contribution) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Component 1. Strengthening the Implementation of the Ministry of Welfare and Social Security SD-MOWSS-1491-CS-INDV / Individual Consultant TF / A0362 Cash Transfer Program ($3.12 Prior Limited 42,000.00 126,000.00 Signed 2016-09-10 2016-10-05 2016-09-15 2016-02-09 2016-10-06 2016-10-13 2016-11-10 2016-02-10 2017-05-09 Project Coordinator Selection million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of SD-MOWSS-1490-CS-INDV / Welfare and Social Security Individual Consultant Under Targeting Operations and TF / A0362 Cash Transfer Program ($3.12 Post Limited 24,000.00 29,637.48 2016-09-10 2016-02-01 2016-09-15 2016-02-09 2016-10-06 2016-02-10 2016-11-10 2016-02-10 2017-05-09 Selection Implementation Logistics Specialist million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of SD-MOWSS-1481-CS-INDV / Welfare and Social Security Individual Consultant Communications and Advocacy TF / A0362 Cash Transfer Program ($3.12 Prior Limited 18,000.00 66,000.00 Signed 2016-09-10 2016-10-10 2016-09-15 2016-02-09 2016-10-06 2016-10-13 2016-11-10 2016-02-10 2017-05-09 Selection specialist million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of Welfare and Social Security SD-MOWSS-1489-CS-INDV / Individual Consultant Under TF / A0362 Cash Transfer Program ($3.12 Prior Limited 18,000.00 0.00 2016-09-10 2017-02-09 2016-09-15 2016-10-06 2016-11-10 2017-05-09 Payment Specialist Selection Implementation million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of Welfare and Social Security SD-MOWSS-1488-CS-INDV / Individual Consultant Under TF / A0362 Cash Transfer Program ($3.12 Prior Limited 36,000.00 72,000.00 2016-09-10 2016-10-10 2016-09-15 2016-06-13 2016-10-06 2016-10-13 2016-11-10 2016-07-17 2017-05-09 MIS Project Manager Selection Implementation million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of SD-MOWSS-1487-CS-INDV / Welfare and Social Security Individual Consultant Pending Environmental and social TF / A0362 Cash Transfer Program ($3.12 Prior Limited 12,000.00 0.00 2016-09-10 2016-09-15 2016-10-06 2016-11-10 2017-05-09 Selection Implementation safeguard specialist million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of SD-MOWSS-1486-CS-INDV / Welfare and Social Security Individual Consultant MIS Software Architect/Team TF / A0362 Cash Transfer Program ($3.12 Prior Limited 33,000.00 33,000.00 Signed 2016-09-10 2017-05-18 2016-09-15 2017-05-21 2016-10-06 2017-05-22 2016-11-10 2017-05-01 2017-05-09 Selection Lead million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of Welfare and Social Security SD-MOWSS-1485-CS-INDV / Individual Consultant Under TF / A0362 Cash Transfer Program ($3.12 Prior Limited 33,000.00 66,000.00 2016-09-10 2016-10-10 2016-09-15 2016-06-13 2016-10-06 2016-10-13 2016-11-10 2016-07-17 2017-05-09 Database Administrator Selection Implementation million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of Welfare and Social Security SD-MOWSS-1484-CS-INDV / M Individual Consultant TF / A0362 Cash Transfer Program ($3.12 Prior Limited 24,000.00 3,594.59 Signed 2016-09-10 2017-02-09 2016-09-15 2017-05-14 2016-10-06 2017-05-15 2016-11-10 2017-06-01 2017-05-09 & E Specialist Selection million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of Welfare and Social Security SD-MOWSS-1483-CS-INDV / Individual Consultant TF / A0362 Cash Transfer Program ($3.12 Prior Limited 30,000.00 90,000.00 Signed 2016-09-10 2016-10-10 2016-09-15 2016-02-09 2016-10-06 2016-10-13 2016-11-10 2016-02-10 2017-05-09 Financial Specialist Selection million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of Welfare and Social Security SD-MOWSS-1507-CS-INDV / Individual Consultant Pending TF / A0362 Cash Transfer Program ($3.12 Prior Limited 5,000.00 0.00 2016-12-25 2016-12-30 2017-01-20 2017-02-24 2017-08-23 Project Mid-Term Selection Implementation million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 1. Strengthening the Implementation of the Ministry of Welfare and Social Security SD-MOWSS-1482-CS-INDV / Individual Consultant TF / A0362 Cash Transfer Program ($3.12 Prior Limited 30,000.00 90,000.00 Signed 2016-09-10 2016-10-13 2016-09-15 2016-02-09 2016-10-06 2016-10-20 2016-11-10 2016-02-10 2017-05-09 Procurement Specialist Selection million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) SD-MOWSS-5726-CS-INDV / Component 2. Piloting a Technical Assistance: Productive Safety Net Approach Undertake required training (US$1.96, of which US$0.5 Individual Consultant TF / A0362 Post Limited 50,000.00 36,659.75 Signed 2017-01-22 2017-01-29 2017-01-27 2017-02-05 2017-02-17 2017-02-06 2017-03-24 2017-02-06 2017-09-20 activities on project principles, million Bank financed and Selection operational aspects and sub- US$1.46 million GoS project design contribution) Component 1. Strengthening the Implementation of the Ministry of SD-MOWSS-11020-CS-INDV / Welfare and Social Security Individual Consultant Under secretary and office TF / A0362 Cash Transfer Program ($3.12 Post Limited 12,000.00 12,000.00 2017-03-26 2017-04-10 2017-03-31 2017-05-14 2017-04-21 2017-05-14 2017-05-26 2017-05-01 2017-11-22 Selection Implementation administration assistance million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Page 3 Component 1. Strengthening the Implementation of the Ministry of Welfare and Social Security SD-MOWSS-16165-CS-INDV / Individual Consultant Under TF / A0362 Cash Transfer Program ($3.12 Post Limited 24,000.00 12,500.00 2017-05-25 2017-05-28 2017-05-30 2017-05-28 2017-06-20 2017-05-28 2017-07-25 2017-05-29 2018-01-21 Targeting Officer Selection Implementation million, of which US$3.00 million Bank financed and US$120,000 GoS contr.) Component 2. Piloting a Productive Safety Net Approach SD-MOWSS-47964-CS-CDS / (US$1.96, of which US$0.5 Pending Complimentary PSN Base line TF / A0362 Prior Direct Selection Direct 45,000.00 0.00 2018-02-07 2018-02-17 2018-04-23 2018-10-20 million Bank financed and Implementation Survey in North Kordofan State US$1.46 million GoS contribution) Page 4