Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan Original: May 21, 2011. Revision of Updated Procurement Plan: December 2016 2. Date of General Procurement Notice: June 19, 2012 3. Period covered by this procurement plan: August 2017 to October 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 5 million All 2. NCB (Goods) Above US$ 4 million First contract 3. (Non-Consultant Services) Below US$ 4 million First contract 2. Reference to (if any) Project Operational/Procurement Manual: Operational Manual dated April 2013 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 2 million First Process 2. Single Source (Firms) All 3. Individual Above US$ 400,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 1,500,00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods PROCUREMENT Brazil : BR Federal Integrated Water - Interaguas PLAN General Information Country: Brazil Banks Approval Date of the Original Procurement Plan: 2017-08-30 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-11-07 Project ID: P112073 GPN Date: Project Name: BR Federal Integrated Water - Interaguas Loan / Credit No: IBRD / 80740 Executing Agency(ies): National Water Agency, Ministry of Cities, Ministry of Integration, Ministry of Environment WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-MMA-24641-NC-RFP / Request for Single Stage - One Pending IBRD / 80740 Water Resources Management Post Open - National 19,189.00 0.00 2017-11-25 2018-01-20 2018-07-19 Seminario 20 anos do CNRH Quotations Envelope Implementation BR-MMA-24636-NC-RFP / Seminario Avanço no Request for Single Stage - One Pending IBRD / 80740 Water Resources Management Post Open - National 12,793.00 0.00 2017-11-25 2018-01-20 2018-07-19 Conhecimento dos Principais Quotations Envelope Implementation Aquiferos Brasileiros BR-MMA-24642-NC-RFP / Intersectoral Coordination and Request for Single Stage - One Pending Oficina Uso Racional e Reuso IBRD / 80740 Post Open - National 19,189.00 0.00 2017-09-23 2017-11-18 2018-05-17 Integrated Planning Quotations Envelope Implementation Domestico da Agua BR-MMA-27168-NC-DIR / Intersectoral Coordination and Pending Participacao da SRHQ no IBRD / 80740 Integrated Planning Post Direct Selection Direct 17,590.00 0.00 2017-10-15 2017-10-20 2017-11-24 2018-05-23 Implementation Congresso da ABES Water Resources Management 6 / Contrataçoã de serviços técnicos especializados de coleta de dados para Water, Irrigation, and Hazard Single Stage - One Pending implementaço ã do Sistema de IBRD / 80740 Post Request for Bids Open - National 1,428,571.00 0.00 2017-10-23 2017-11-07 2017-12-08 2017-12-19 2018-01-05 2018-10-23 Management Envelope Implementation ã Informaço Á ua e de g Saneamento Rural - SIASAR no estado do Ceará. BR-MMA-30405-NC-DIR / Participacao da SRHQ no Pending IBRD / 80740 Water Resources Management Post Direct Selection Direct 11,898.00 0.00 2017-11-15 2017-11-20 2017-12-25 2018-06-23 Congresso da ABRH - Implementation Florianopolis CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management, Monitoring and Evaluation Water Resources Management PNSH - Ata e Minuta rubricada / Water, Irrigation, and Hazard Quality And Cost- IBRD / 80740 Prior Open - International N 2,388,153.00 2,475,662.86 Signed 2014-07-16 2014-08-29 NO Ata e Minuta rubricada Management Based Selection Water Supply and Sanitation Intersectoral Coordination and Integrated Planning 001/2017 / Projeto de Gestão das perdas de gá ua e do Uso Quality And Cost- Pending Eficiente de Energia Eletrica, IBRD / 80740 Water Supply and Sanitation Prior Open - International 6,000,000.00 0.00 2017-08-01 2017-08-01 2017-08-01 2017-08-29 2017-09-28 2017-11-02 2017-12-07 2018-12-07 Based Selection Implementation adotando o modelo do COM+AGUA (Fase II) 1 / RAMAL DO PIANCÓ - ELABORAÇOà DOS ESTUDOS DE VIABILIDADE TÉCNICA E AMBIENTAL PARA O Water, Irrigation, and Hazard Quality And Cost- Under IBRD / 80740 Post Open - National 507,937.00 0.00 2017-01-11 2017-08-31 2017-01-14 2017-02-04 2017-03-04 2017-04-03 2017-05-08 2017-06-12 2018-06-12 ABASTECIMENTO DA BACIA Management Based Selection Implementation HIDROGRÁFICA DO ALTO PIANCÓ E BACIAS LIMÍTROFES 2 / Estudos de alternativas de Water, Irrigation, and Hazard Quality And Cost- Under IBRD / 80740 Post Open - National 645,560.00 0.00 2017-08-08 2017-08-31 2017-08-11 2017-08-18 2017-09-15 2017-10-14 2017-11-19 2017-12-24 2018-12-24 energia eletrica para o PISF. Management Based Selection Implementation ã 002/2018 / Contrataço de empresa especializada para ã elaboraço de modelos de Quality And Cost- Pending documentos de Documentos de IBRD / 80740 Water Supply and Sanitation Post Open - National 500,000.00 0.00 2017-12-04 2017-12-25 2018-01-09 2018-02-06 2018-02-16 2018-03-08 2018-03-20 2018-09-16 Based Selection Implementation ã Referência para Contrataço de Á ua e PPP's para serviços de g Esgotos. BR-MCID-25765-CS-QCBS / Contrataçoã de empresa de Quality And Cost- Pending consultoria especializada pessoa IBRD / 80740 Water Supply and Sanitation Post Open - National 570,000.00 0.00 2017-09-18 2017-10-09 2017-10-29 2017-11-19 2017-11-29 2017-12-19 2017-12-31 2018-10-07 Based Selection Implementation jurídica para Revisão do PLANSAB. Page 1 BR-ANA-26543-CS-QCBS / Intersectoral Coordination and Quality And Cost- Pending Conclusão do Plano Nacional de IBRD / 80740 Post Open - National 1,250,000.00 0.00 2017-08-29 2017-09-19 2017-11-02 2017-11-30 2017-12-30 2018-02-03 2018-03-10 2019-03-10 Integrated Planning Based Selection Implementation Segurança Hídrica. 3 / Gestão de Risco PISF - Estudo para Elaboraçoã de Estudo de Análise de Riscos Water, Irrigation, and Hazard Quality And Cost- Under ã para o Projeto de Integraço do IBRD / 80740 Post Open - National 519,600.00 0.00 2017-08-31 2017-09-04 2017-09-25 2017-10-25 2017-11-06 2017-11-20 2017-12-11 2018-09-09 Management Based Selection Implementation rio São Francisco com Bacias Hidrográficas do Nordeste Setentrional - PISF. 4 / Revitalizacao PISF Indicadores - desenvolver ferramenta de planejamento e monitoramento das açe õ s que Water, Irrigation, and Hazard Quality And Cost- Pending ã contribuem para a revitalizaço IBRD / 80740 Post Open - National 1,269,841.00 0.00 2017-08-31 2017-09-04 2017-09-28 2017-10-30 2017-11-13 2017-11-30 2017-12-18 2018-10-17 Management Based Selection Implementation da Bacia Hidrográfica do rio São Francisco e constituir linguagem comum para convergência dos planejamentos setoriais. 5 / Revitalizacao PISF Modelagem - desenvolvimento de modelagem para contrataço ã de organismos privados para a aço ã Water, Irrigation, and Hazard Quality And Cost- Pending integrada de recuperaçoã de IBRD / 80740 Post Open - National 317,460.00 0.00 2017-08-31 2017-09-04 2017-09-28 2017-10-30 2017-11-13 2017-11-30 2017-12-18 2018-10-17 Management Based Selection Implementation á eas degradadas, capacitaço r ã e ã educaço ambiental e suporte à ã preservaço de APP em microbacias com condiçe õ s favo BR-ANA-26540-CS-QCBS / ã Contrataço de consultoria especializada em administraço ã de recursos materiais, humanos Quality And Cost- Pending e financeiros para desenvolver IBRD / 80740 Water Resources Management Post Open - National 125,000.00 0.00 2017-08-29 2017-09-19 2017-09-21 2017-09-22 2017-09-23 2017-09-25 2017-09-28 2018-01-26 Based Selection Implementation uma metodologia para estimativa do custeio administrativo de Entidades Delegatárias de õ s de Agência de g funçe Á ua. SDP 03/2017 / Realizacao de estudo sobre alternativas do setor industrial e agroindustrial e mecanismos de inducao e apoio Intersectoral Coordination and Quality And Cost- Pending do poder publico e da IBRD / 80740 Post Open - National 430,750.00 0.00 2017-07-27 2017-07-27 2017-08-29 2017-09-26 2017-10-26 2017-11-16 2017-12-21 2018-12-21 Integrated Planning Based Selection Implementation representacao setorial de reducao do consumo de agua e da geracao de efluentes e ampliacao do reuso de agua ã 006/2017 / Contrataço de empresa de consultoria para apoio técnico especializado em Quality And Cost- Under õ s de Educaço açe ã à Distância IBRD / 80740 Water Supply and Sanitation Post Open - National 315,000.00 0.00 2017-09-13 2017-09-13 2017-10-02 2017-10-09 2017-11-06 2017-11-16 2017-12-06 2017-12-18 2018-07-26 Based Selection Implementation para o Sistema Nacional de Informaçeõ s em Saneamento - SINISA. 7 / TERMO DE REFERÊNCIA PARA CONTRATAÇO à DE CONSULTORIA PARA ELABORAÇOà DE "PLANO Intersectoral Coordination and à TERRITORIAL DE OTIMIZAÇO Integrated Planning Quality And Cost- Pending DE RECURSOS HÍDRICOS DO IBRD / 80740 Post Open - National 385,526.40 0.00 2017-10-23 2017-11-06 2018-01-08 2018-02-08 2018-02-19 2018-03-05 2018-03-16 2018-09-16 Water, Irrigation, and Hazard Based Selection Implementation SERTÃO DO INHAMUNS- Management CEARÁ, COM FOCO NA SEGURANÇA HÍDRICA DA OVINOCAPRINOCULTURA - ROTA DO CORDEIRO". INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-MMA-24637-CS-INDV / Diagnostico e avaliacao da Individual Consultant Pending IBRD / 80740 Water Resources Management Post Open 47,973.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2018-10-27 situacao dos Planos Estaduais Selection Implementation de Recursos Hidricos BR-MMA-24634-CS-INDV / Estrategia para construcao do Individual Consultant Pending Plano Nacional de Recursos IBRD / 80740 Water Resources Management Post Open 47,973.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2018-10-27 Selection Implementation Hidricos com horizontes temporal a partir de 2021 BR-MMA-24643-CS-INDV / Individual Consultant Pending Plano de Comunicacao do CNRH IBRD / 80740 Water Resources Management Post Open 47,973.00 0.00 2017-12-15 2018-02-02 2018-02-23 2018-03-30 2018-09-26 Selection Implementation e do PNRH BR-MMA-24635-CS-INDV / Estado da arte do conhecimento Individual Consultant Pending IBRD / 80740 Water Resources Management Post Open 41,577.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2018-10-27 sobre aguas subterraneas no Selection Implementation Brasil BR-MMA-24638-CS-INDV / Individual Consultant Pending Normas para o CNRH sobre o IBRD / 80740 Water Resources Management Post Open 47,973.00 0.00 2017-10-15 2017-12-03 2017-12-24 2018-01-28 2018-07-27 Selection Implementation Uso Racional e Reuso da Agua BR-MMA-24640-CS-INDV / Definicao de criterios tecnicos para aplicacao do roteiro Intersectoral Coordination and Individual Consultant Pending IBRD / 80740 Post Open 63,965.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2018-10-27 metodologico do Zoneamento Integrated Planning Selection Implementation Ambiental Municipal em uma unidade federativa selecionada Page 2 BR-MMA-24639-CS-INDV / Diretrizes para a integracao das politicas de recursos hidricos e Individual Consultant Pending de uso e ocupacao do solo IBRD / 80740 Water Resources Management Post Open 19,189.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2018-10-27 Selection Implementation urbano, a partir do estudo dos municipios pertencentes a bacia do Rio Descoberto BR-MCID-25764-CS-INDV / Consultor individual para apoio técnico especializado ao acompanhamento e à elaboraço ã de documentos referentes s à Individual Consultant Pending IBRD / 80740 Water Supply and Sanitation Post Open 70,000.00 0.00 2017-10-15 2017-12-03 2017-12-24 2018-01-28 2018-07-27 õ s de reduço açe ã e controle de Selection Implementation perdas de gá ua e uso eficiente de energia elétrica em sistemas de abastecimento de g á ua (Fase II). 002/2017 / Consultor individual para apoio técnico especializado ã no desenvolvimento e aplicaço prática de Roteiro para Individual Consultant Pending IBRD / 80740 Water Supply and Sanitation Post Open 66,000.00 0.00 2017-10-02 2017-10-26 2017-10-31 2017-11-07 2018-09-23 ã Elaboraço de Plano Municipal Selection Implementation de Saneamento Básico (PMSB) para municípios de pequeno porte". 003/2017 / Consultor individual para apoio técnico especializado à açe s ã õ s de elaboraço e análise de estudos e projetos de Individual Consultant Pending IBRD / 80740 Water Supply and Sanitation Post Open 20,000.00 0.00 2017-10-01 2017-10-25 2017-10-30 2017-11-06 2018-09-22 concessões e parcerias público- Selection Implementation privadas voltadas ao manejo de resíduos sólidos urbanos (RSU). Area Engenharia 004/2017 / Consultor individual para apoio técnico especializado à açe s ã õ s de elaboraço e análise de estudos e projetos de Individual Consultant Pending IBRD / 80740 Water Supply and Sanitation Post Open 20,000.00 0.00 2017-10-01 2017-10-25 2017-10-30 2017-11-06 2018-09-22 concessões e parcerias público- Selection Implementation privadas voltadas ao manejo de resíduos sólidos urbanos (RSU). rÀ ea - Especialista Jurídico. 005/2017 / Consultor individual para apoio técnico especializado à açe s ã õ s de elaboraço e análise de estudos e projetos de Individual Consultant Pending concessões e parcerias público- IBRD / 80740 Water Supply and Sanitation Post Open 20,000.00 0.00 2017-10-02 2017-10-26 2017-10-31 2017-11-07 2018-09-23 Selection Implementation privadas voltadas ao manejo de resíduos sólidos urbanos (RSU). rÀ ea - Especialista Economico- Financeiro. BR-MCID-25767-CS-INDV / Consultor individual especializado em esgotamento Individual Consultant Pending IBRD / 80740 Water Supply and Sanitation Post Open 20,000.00 0.00 2017-09-18 2017-10-17 2017-10-22 2017-10-31 2018-04-29 sanitário, para estudos sobre Selection Implementation ã reduço da ociosidade das redes de esgoto. BR-MCID-25768-CS-INDV / Consultor individual para apoio técnico especializado relacionado à modelagem e Individual Consultant Pending IBRD / 80740 Water Supply and Sanitation Post Open 15,000.00 0.00 2017-09-04 2017-10-03 2017-10-10 2017-10-19 2018-04-17 concessão da prestaço ã de Selection Implementation serviços públicos de abastecimento de g á ua e esgotamento sanitário. BR-ANA-26548-CS-INDV / Realizaçoã de análise sobre os esforços para melhorar o planejamento e gestão dos recursos hídricos, desde a Intersectoral Coordination and Individual Consultant Pending IBRD / 80740 Post Open 57,000.00 0.00 2017-08-29 2017-10-06 2017-10-27 2017-12-01 2018-05-30 implementaço ã de estratégias, Integrated Planning Selection Implementation ã criaço de novos programas ou aperfeiçoamento dos instrumentos de gestão e seus planos frente ao ACT 02/2014. à 14 / CONTRATAÇO PF - CONTEÚDO AUDIO VISUAL COORDENADOR - CONTRATAÇOà DE SERVIÇOS DE Project Management, Monitoring Individual Consultant Under IBRD / 80740 Post Open 80,000.00 0.00 2017-08-08 2017-08-22 2017-09-01 2017-08-25 2017-09-08 2017-09-15 2018-03-14 CONSULTORIA INDIVIDUAL and Evaluation Selection Implementation PARA A ELABORAÇO à DE PROPOSTA DE CONTEÚDO TÉCNICO E MATERIAL AUDIOVISUAL . 23 / Contrataçeõ s PF 2 - ã Contrataço de consultor para ã Produço de conteúdo técnico Project Management, Monitoring Individual Consultant Pending IBRD / 80740 Post Open 38,095.20 0.00 2017-08-09 2017-08-22 2017-08-25 2017-09-15 2018-03-14 ã para elaboraço do material final and Evaluation Selection Implementation do projeto Interáguas diante das õ s executadas pela MMA açe 24 / Contrataço ã PF 3 - Contrataçoã de consultor para ã Produço de conteúdo técnico Project Management, Monitoring Individual Consultant Pending para elaboraçoã do material final IBRD / 80740 Post Open 38,095.20 0.00 2017-08-09 2017-08-22 2017-08-25 2017-09-15 2018-03-14 and Evaluation Selection Implementation do projeto Interáguas diante das õ s executadas pelo açe Ministério das Cidades à 21 / CONTRATAÇO PF EDITORAÇOà TÉCNICO 2 - CONTRATAÇO à DE SERVIÇOS DE CONSULTORIA INDIVIDUAL Project Management, Monitoring Individual Consultant Pending IBRD / 80740 Post Open 40,000.00 0.00 2017-08-08 2017-08-22 2017-08-25 2017-09-15 2018-03-14 PARA A ELABORAÇO à DE and Evaluation Selection Implementation MATERIAIS FINAIS ORIUNDOS CONTRATOS CELEBRADOS NO M BITO DO PROJETO INTERÁGUAS Page 3 11 / Especialista em projetos - SIH - APOIO TÉCNICO ESPECIALIZADO AO ACOMPANHAMENTO E Water, Irrigation, and Hazard Individual Consultant Pending MONITORAMENTO DE IBRD / 80740 Post Open 38,095.24 0.00 2017-08-08 2017-08-22 2017-08-25 2017-09-01 2018-08-31 Management Selection Implementation CONTRATOS FORMALIZADOS  BITO DA SECRETARIA NO M DE INFRAESTRUTURA HÍDRICA PARA O PROJETO ã 16 / Contrataço de consultor para Produçoã de conteúdo técnico para elaboraço ã do Project Management, Monitoring Individual Consultant Pending IBRD / 80740 Post Open 38,095.20 0.00 2017-08-09 2017-08-22 2017-08-25 2017-09-15 2018-03-14 material final do projeto and Evaluation Selection Implementation Interáguas diante das açe õ s executadas pela ANA. 25 / Contrataçoã PF 4 - ã Contrataço de consultor para ã Produço de conteúdo técnico Project Management, Monitoring Individual Consultant Pending IBRD / 80740 Post Open 38,095.20 0.00 2017-08-09 2017-08-22 2017-08-25 2017-09-15 2018-03-14 ã para elaboraço do material final and Evaluation Selection Implementation do projeto Interáguas diante das õ s executadas pela MI açe ã 10 / Contribuir como facilitaço técnica junto as SDR e seus servidores para o alcance dos Project Management, Monitoring Individual Consultant Pending IBRD / 80740 Post Open 53,968.00 0.00 2017-08-08 2017-08-08 2017-08-13 2017-08-13 2018-07-12 objetivos do projeto por meio do and Evaluation Selection Implementation acompanhamento técnico e monitoramento das açe õ s 27 / CONSULTORIA INDIVIDUAL PARA AVALIAR AS ROTINAS E OS PROCEDIMENTOS UTILIZADOS NO SISTEMA DE PROGRAMAS SOCIAIS - SPS, NO M BITO Project Management, Monitoring Individual Consultant Pending DO PROGRAMA G Á UA PARA IBRD / 80740 Post Open 38,095.25 0.00 2017-09-22 2017-10-10 2017-10-13 2017-10-20 2018-10-15 and Evaluation Selection Implementation TODOS, PROPONDO ADAPTAÇEÕ S AO MODELO UTILIZADO, VISANDO APERFEIÇOAMENTO DA IMPLEMENTAÇO à DA FERRAMENTA ã 18 / Consultor 1: Contrataço de engenheiro civil, especialista em recursos hídricos, para acompanhamento técnico dos Water, Irrigation, and Hazard Individual Consultant Pending IBRD / 80740 Post Open 38,095.24 0.00 2017-08-08 2017-08-31 2017-09-08 2017-09-15 2018-09-14 contratos do Ramal do Piancó, Management Selection Implementation Gestão de Riscos e PLANERB firmados no Projeto Interáguas por meio da SIH ã 19 / Consultor 2: Contrataço de engenheiro eletricista, especialista em economia, para acompanhamento técnico dos Water, Irrigation, and Hazard Individual Consultant Pending contratos de Energia Renováveis, IBRD / 80740 Post Open 38,095.00 0.00 2017-08-08 2017-08-31 2017-09-08 2017-09-15 2018-09-14 Management Selection Implementation Ramal do Piancó, Gestão de Riscos e PLANERB firmados no Projeto Interáguas por meio da SIH ã 9 / Contrataço PF SIASAR- à Consultor 1 VALIDAÇO DE Project Management, Monitoring Individual Consultant Pending DADOS COLETADOS EM IBRD / 80740 Post Open 16,500.00 0.00 2017-09-29 2017-10-12 2017-10-15 2017-11-05 2018-05-04 and Evaluation Selection Implementation COMUNIDADES RURAIS DO ESTADO DO CEARÁ. 12 / Especialista em projetos - SEDEC - APOIO TÉCNICO ESPECIALIZADO AO ACOMPANHAMENTO E Project Management, Monitoring Individual Consultant Pending IBRD / 80740 Post Open 38,095.00 0.00 2017-08-08 2017-08-22 2017-08-25 2017-09-15 2018-03-14 MONITORAMENTO DE and Evaluation Selection Implementation CONTRATOS FORMALIZADOS  BITO DA SECRETARIA NO M DE Defesa Civil. 13 / Analisar e avaliar as informaçeõ s disponibilizadas pelos Entes Federados e Entidades do Governo Federal que são responsáveis pela Project Management, Monitoring Individual Consultant Pending IBRD / 80740 Post Open 38,095.25 0.00 2017-11-06 2017-11-24 2017-11-27 2017-12-04 2018-11-29 execuçoã do Programa g Á ua and Evaluation Selection Implementation Para Todos, em relaço ã a tecnologia implementada no Programa e ao efetivo atendimento ao público. ã 30 / Contrataço PF SIASAR- à Consultor 2 VALIDAÇO DE Project Management, Monitoring Individual Consultant Pending DADOS COLETADOS EM IBRD / 80740 Post Open 16,500.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 and Evaluation Selection Implementation COMUNIDADES RURAIS DO ESTADO DO CEARÁ. ã 31 / Contrataço PF SIASAR- à Consultor 3 VALIDAÇO DE Project Management, Monitoring Individual Consultant Pending DADOS COLETADOS EM IBRD / 80740 Post Open 16,500.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 and Evaluation Selection Implementation COMUNIDADES RURAIS DO ESTADO DO CEARÁ. ã 32 / Contrataço PF SIASAR- à Consultor 4 VALIDAÇO DE Project Management, Monitoring Individual Consultant Pending DADOS COLETADOS EM IBRD / 80740 Post Open 16,500.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 and Evaluation Selection Implementation COMUNIDADES RURAIS DO ESTADO DO CEARÁ. ã 33 / Contrataço PF SIASAR- à Consultor 5 VALIDAÇO DE Project Management, Monitoring Individual Consultant Pending DADOS COLETADOS EM IBRD / 80740 Post Open 16,500.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 and Evaluation Selection Implementation COMUNIDADES RURAIS DO ESTADO DO CEARÁ. Page 4 ã 34 / Contrataço PF SIASAR- à Consultor 6 VALIDAÇO DE Project Management, Monitoring Individual Consultant Pending DADOS COLETADOS EM IBRD / 80740 Post Open 16,500.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 and Evaluation Selection Implementation COMUNIDADES RURAIS DO ESTADO DO CEARÁ. ã 26 / Contrataço PF 5 - Contrataçoã de consultor para ã gerenciar a produço de textos e Project Management, Monitoring Individual Consultant Pending IBRD / 80740 Post Open 50,000.00 0.00 2017-08-09 2017-08-22 2017-08-25 2017-11-06 2018-10-15 conteúdo audiovisual para and Evaluation Selection Implementation ã elaboraço dos produtos institucionais do Projeto à 15 / CONTRATAÇO PF EDITORAÇOà TÉCNICO PRINCIPAL - CONTRATAÇO à DE SERVIÇOS DE CONSULTORIA INDIVIDUAL Project Management, Monitoring Individual Consultant Pending IBRD / 80740 Post Open 60,000.00 0.00 2017-08-08 2017-08-22 2017-08-25 2017-09-15 2018-09-21 PARA A ELABORAÇO à DE and Evaluation Selection Implementation MATERIAIS FINAIS ORIUNDOS CONTRATOS CELEBRADOS NO M BITO DO PROJETO INTERÁGUAS 28 / Obj. geral: analisar e avaliar õ s disponibilizadas as informaçe pelos Entes Federados e Entidades do Governo Federal Project Management, Monitoring Individual Consultant Pending que são responsáveis pela IBRD / 80740 Post Open 38,095.25 0.00 2017-11-06 2017-11-20 2017-11-27 2017-12-01 2018-09-28 and Evaluation Selection Implementation ã execuço do Programa Agua para todos em relaçoã a indicadores e diretrizes - Região 1 29 / Analisar e avaliar as informaçeõ s disponibilizadas pelos Entes Federados e Entidades do Governo Federal que são responsáveis pela Project Management, Monitoring Individual Consultant Pending IBRD / 80740 Post Open 38,095.25 0.00 2017-11-06 2017-11-25 2017-11-30 2017-12-04 2018-09-28 execuçoã do Programa g Á ua and Evaluation Selection Implementation Para Todos, em relaço ã aos indicadores e diretrizes do Programa e atendimento ao público-REGIÃO 2 Page 5