Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Congo, Democratic Republic of : DRC Urban Development Project FY13 PLAN General Information Country: Congo, Democratic Republic of Bank’s Approval Date of the Original Procurement Plan: 2018-02-08 2019-11-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P129713 GPN Date: Project Name: DRC Urban Development Project FY13 Loan / Credit No: IDA / H8420, IDA / 60340 Executing Agency(ies): Urban Development Project WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PDU-30331-CW-RFB / TRAVAUX Single Stage - One REHABILITATION ET IDA / H8420 Primary Infrastructure A posteriori Appel d'offres Open - National 1,664,686.60 1,664,686.60 Signé 2017-09-27 2017-09-28 2017-09-29 2017-09-30 2017-10-02 2017-10-26 Envelope MODERNISATION AVENUE IRAMBO (Ville de Bukavu) ZR-PDU-72491-CW-RFB / PDU_FADD_TRAVAUX DE REH. ET DE MODERN. _AVENUE GAZUMBU & Single Stage - One IDA / 60340 Primary Infrastructure A posteriori Appel d'offres Open - National 4,500,000.00 2,711,326.95 Signé 2018-08-08 2018-08-13 2018-09-12 2018-10-12 2018-11-16 2019-07-14 ASSAINISSEMENT Envelope _AVENUE LDK_ VILLE KOLWEZI _PROVINCE LUALABA ZR-PDU-72498-CW-RFB / PDU_FADD_TRAVAUX DE REH. ET DE MODERN. Single Stage - One _PROLONGEMENT BLD 30 IDA / 60340 Primary Infrastructure A posteriori Appel d'offres Open - National 4,000,000.00 3,174,071.26 Signé 2018-08-02 2018-08-07 2018-09-06 2018-10-06 2018-10-11 2019-06-08 Envelope JUIN _ VILLE KISANGANI _PROVINCE DE LA TSHOPO ZR-PDU-75121-CW-RFB / FADD- TRAVAUX REHABILITATION ET Single Stage - One IDA / 60340 Primary Infrastructure A posteriori Appel d'offres Open - National 4,000,000.00 0.00 Annulé 2018-08-26 2018-08-26 2018-10-07 2018-11-06 2018-12-11 2019-08-08 MODERNISATION DE LA Envelope VOIRIE CCLK -Ville GOMA-PROV NORD KIVU ZR-PDU-98155-CW-RFB / SC 2A Travaux réhabilitation et modernisation Lot 1_ EP 2 Urban Governance Single Stage - One En attente IDA / H8420 A posteriori Appel d'offres Open - National 350,000.00 0.00 2019-02-05 2019-02-10 2019-02-15 2019-02-25 2019-04-01 2019-09-28 KANZOMBI _ 14 Salles de (including PPA) Envelope d'exécution classe_ Bureau direction _ Aménagement cour_ Mur de clôture _Ville Kikwit ZR-PDU-98174-CW-RFB / SC 2A _ DAON 001 SP PDU TRVX _ Lot 2 Travaux réhabilitation et Urban Governance Single Stage - One En attente modernisation Ecole primaire IDA / H8420 A posteriori Appel d'offres Open - National 180,000.00 0.00 2019-02-05 2019-02-10 2019-02-15 2019-02-25 2019-04-01 2019-09-28 (including PPA) Envelope d'exécution VUKAMA 2 _6 Salles de classe _Aménagement de la cour _ Construction Mur de clôture_ Ville de KIKWIT Page 1 ZR-PDU-107337-CW-RFB / SC 2A LOT 3 _ TRAVAUX REHABILITATION ET MODERNISATION INSTITUT KANGULUMBA_ 18 SALLES DE CLASSE _ Urban Governance Single Stage - One En attente IDA / H8420 A posteriori Appel d'offres Open - National 550,000.00 0.00 2019-03-21 2019-03-21 2019-03-26 2019-03-31 2019-04-10 2019-10-07 SALLE POUR ATELIER (including PPA) Envelope d'exécution MECANIQUE_MUR CLOTURE_BATIMENT ADMINISTRATIF_AMENAGE MENT COUR _ Ville KIKWIT ZR-PDU-107563-CW-RFB / SC 2A LOT 1 Travaux réhabilitation et modernisation Institut Urban Governance Single Stage - One En attente LUFUNGULA_17 SALLES IDA / H8420 A posteriori Appel d'offres Open - National 600,000.00 0.00 2019-03-22 2019-03-22 2019-03-27 2019-04-01 2019-04-26 2019-10-23 (including PPA) Envelope d'exécution CLASSES _BATIMENT ADMINISTRATIF _MUR CLOTURE_VILLE DE KINDU ZR-PDU-107564-CW-RFB / SC 2A LOT 2 _TRAVAUX REHABILITATION ET MODERNISATION INSTITUT KAMA2_12 Urban Governance Single Stage - One En attente IDA / H8420 A posteriori Appel d'offres Open - National 350,000.00 0.00 2019-03-22 2019-03-27 2019-04-01 2019-04-06 2019-04-26 2019-10-23 SALLES (including PPA) Envelope d'exécution CLASSE_BATIMENT ADMINISTRATIF_MUR DE CLOTURE_ VILLE DE KINDU ZR-PDU-107565-CW-RFB / SC 2A LOT 3 _TRAVAUX REHABILITATION ET MODERNISATION EP Urban Governance Single Stage - One En attente KAMA 2_ 13 SALLES DE IDA / H8420 A posteriori Appel d'offres Open - National 370,000.00 0.00 2019-03-22 2019-03-27 2019-04-01 2019-04-06 2019-04-21 2019-10-18 (including PPA) Envelope d'exécution CLASSE_BATIMENT ADMINISTRATIF _ MUR DE CLOTURE_ VILLE DE KINDU ZR-PDU-107566-CW-RFB / SC 2A _ LOT 4 _TRAVAUX REHABILITATION ET MODERNISATION INSTITUT KANSILEMBO Urban Governance Single Stage - One En attente _12 SALLES CLASSE_ IDA / H8420 A posteriori Appel d'offres Open - National 450,000.00 0.00 2019-03-22 2019-03-27 2019-04-01 2019-04-06 2019-04-26 2019-10-23 (including PPA) Envelope d'exécution BATIMENT ADMINISTARTIF _ PAVILLON SANITAIRE_ MUR DE CLOTURE _VILLE DE KINDU ZR-PDU-107567-CW-RFB / SC 2A LOT 1_ TRAVAUX REHABILITATION ET MODERNISATION EP BONZENGA_ 10 SALLES Urban Governance Single Stage - One En attente DE CLASSE_ 3 BUREAUX IDA / H8420 A posteriori Appel d'offres Open - National 400,000.00 0.00 2019-03-22 2019-03-27 2019-04-01 2019-04-06 2019-04-21 2019-10-18 (including PPA) Envelope d'exécution _ CIRCULATION COUVERTE_ 3 BLOCS SANITAIRES_ AMENAGEMENT COUR _ Ville de MBANDAKA Page 2 ZR-PDU-107568-CW-RFB / SC 2A _ LOT 2 _ TRAVAUX REHABILITATION ET MODERNISATION EP Urban Governance Single Stage - One En attente MALEMBE_12 SALLES IDA / H8420 A posteriori Appel d'offres Open - National 500,000.00 0.00 2019-03-22 2019-03-27 2019-04-01 2019-04-06 2019-04-16 2019-10-13 (including PPA) Envelope d'exécution CLASSE_3 BUREAUX _2 BLOCS SANITATIRES _CIRCULATION COUVERTE _AMENANGEMENT COUR_VILLE MBANDAKA ZR-PDU-107569-CW-RFB / SC 2A _ LOT 3_ TRAVAUX DE REHABILITATION ET MODERNISATION INSTITUT MAINGOWA _8 Urban Governance Single Stage - One En attente SALLES DE CLASSES IDA / H8420 A posteriori Appel d'offres Open - National 380,000.00 0.00 2019-03-22 2019-03-27 2019-04-01 2019-04-06 2019-04-26 2019-10-23 (including PPA) Envelope d'exécution _BATIMENT ADMINISTRATIF_2 BLOCS SANITAIRES_ AMENAGEMENT COUR_ Ville de MBANDAKA GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PDU-52363-GO-RFQ / ACQUISITION UN GROUPE ELECTROGENE DE SECOURS DE 30 KVA Urban Governance Single Stage - One En cours IDA / H8420 A posteriori Demande de prix Limited 18,000.00 0.00 2018-03-09 2018-03-23 2018-03-26 SILENCIEUX POUR (including PPA) Envelope d'exécution BUREAUX DU SECRETARIAT PERMANENT DU PROJET ZR-PDU-122463-GO-RFB / S C 2 A FOURNITURE Urban Governance Single Stage - One DES MOBILIERS IDA / H8420 A posteriori Appel d'offres Open - National 800,000.00 0.00 Annulé 2019-07-11 2019-07-11 2019-07-21 2019-07-26 2019-08-05 2019-11-03 (including PPA) Envelope SCOLAIRES POUR 3 ECOLES DE LA VILLE DE MBANDAKA ZR-PDU-122464-GO-RFB / S C 2 A FOURNITURE Urban Governance Single Stage - One DES MOBILIERS IDA / H8420 A posteriori Appel d'offres Open - National 1,000,000.00 0.00 Annulé 2019-07-11 2019-07-11 2019-07-16 2019-07-21 2019-07-31 2019-10-29 (including PPA) Envelope SCOLAIRES POUR 4 ECOLES DE LA VILLE DE KINDU ZR-PDU-125597-GO-RFQ / Fourniture trois (3) véhicules dont deux (2) Pick-up (TT), double cabine, pour la mission de contrôle des Single Stage - One En attente travaux de voiries des villes IDA / H8420 Primary Infrastructure A posteriori Demande de prix Limited 150,000.00 0.00 2019-10-02 2019-10-27 2019-11-26 Envelope d'exécution de Kisangani et de Kolwezi ( 1 véhicule à Kisangani et 1 véhicule à Kolwezi) et un véhicule (Jeep) pour le Coordo . ZR-PDU-122459-GO-RFB / SC 2 A FOURNITURE DES Urban Governance Single Stage - One En attente MOBILIERS SCOLAIRES IDA / H8420 A posteriori Appel d'offres Open - National 50,000.00 0.00 2019-09-25 2019-09-30 2019-10-14 2019-10-24 2019-11-01 2020-01-30 (including PPA) Envelope d'exécution POUR 3 ECOLES DE LA VILLE DE KIKWIT Page 3 ZR-PDU-141311-GO-RFQ / ACQUISITION KIT COMPLET MATÉRIELS INFORMATIQUES ET MINI CENTRALE Urban Governance Single Stage - One En attente IDA / H8420 A posteriori Demande de prix Limited 30,000.00 0.00 2019-10-27 2019-11-30 2019-12-15 PANNEAUX (including PPA) Envelope d'exécution PHOTOVOLTAÏQUES POUR LES BUREAUX DES AGENTS DE LA MAIRIE DE LA VILLE DE GOMA NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PDU-65873-CS-CQS / Consultant (firme) -Etude Sélection fondée sur la gestion des Urban Governance sur les Open - IDA / H8420 A posteriori 200,000.00 0.00 Annulé 2018-06-24 2018-07-15 2018-07-25 2018-08-04 2018-08-19 2018-11-17 équipements marchands (including PPA) qualifications des International dans les villes cibles du consultants PDU ZR-PDU-72616-CS-QCBS / PDU ADD_MISSION DE CONTROLE DES TRAVAUX DE REHABILITATION ET Sélection fondée Open - DE MODERNISATION DES IDA / 60340 Primary Infrastructure A priori sur la qualité et 1,000,000.00 610,900.00 Signé 2018-08-02 2018-08-09 2018-08-21 2018-08-23 2018-08-30 2018-09-23 2018-10-07 2019-08-03 International VOIRIES CIBLEES DES le coût VILLES ADD GOMA_KISANGANI _KOLWEZI ZR-PDU-76691-CS-CQS / S/C 2A PDU -Mission d'Etudes tech & Contrôle Sélection fondée travaux de réhabil. et de Urban Governance sur les modern. des 10 écoles IDA / H8420 A posteriori Open - National 250,000.00 0.00 Annulé 2018-09-12 2018-10-03 2018-11-16 2018-12-16 2019-01-20 2019-07-19 (including PPA) qualifications des maternelles, de 2 Instituts , consultants de 2 Foyers sociaux et d'1 Centre des Jeunes de la ville de Bukavu. ZR-PDU-76692-CS-CQS / S/C 2A PDU -Mission d'Etudes tech & Contrôle Sélection fondée travaux de réhabil. et de Urban Governance sur les modern.des 4 écoles IDA / H8420 A posteriori Open - National 150,000.00 0.00 Annulé 2018-09-15 2018-10-06 2018-11-19 2018-12-19 2019-01-23 2019-07-22 (including PPA) qualifications des primaires de la ville de consultants Kalemie: MAENDELEO, MAHITO, ABATTOIR et KITUMAINI IV Page 4 ZR-PDU-76693-CS-CQS / S/C 2A PDU -Missions d'Etudes tech & Contrôle Sélection fondée travaux de réhabil. et de Urban Governance sur les modern.des 2 Instituts , des IDA / H8420 A posteriori Open - National 150,000.00 0.00 Annulé 2018-09-15 2018-10-06 2018-11-19 2018-12-19 2019-01-23 2019-07-22 (including PPA) qualifications des 2 Ecoles primaires EP1 et consultants EP2 et d'1 bibliothèque de l'Instituit Boboto -Ville Matadi ZR-PDU-76697-CS-CQS / S/C 2A PDU -Missions Sélection fondée d'Etudes tech & Contrôle Urban Governance sur les travaux de réhabil. et de IDA / 60340 A posteriori Open - National 150,000.00 0.00 Annulé 2018-09-17 2018-10-08 2018-11-21 2018-12-21 2019-01-25 2019-07-24 (including PPA) qualifications des modern.des 2 Ecoles consultants primaires et 4 Instituts de la ville de Goma. ZR-PDU-76699-CS-CQS / S/C 2A PDU -Missions Sélection fondée d'Etudes tech & Contrôle Urban Governance sur les travaux de réhabil. et de IDA / 60340 A posteriori Open - National 50,000.00 0.00 Annulé 2018-09-17 2018-10-08 2018-11-21 2018-12-21 2019-01-25 2019-07-24 (including PPA) qualifications des modern.d'1 Institut et d'1 consultants Centre de Promotion Sociale de la ville de Kisangani ZR-PDU-76701-CS-CQS / S/C 2A PDU -Missions d'Etudes tech & Contrôle Sélection fondée travaux de réhabil. et de Urban Governance sur les IDA / 60340 A posteriori Open - National 150,000.00 0.00 Annulé 2018-09-18 2018-10-09 2018-11-22 2018-12-22 2019-01-26 2019-07-25 modern.de 2 Instituts , d'1 (including PPA) qualifications des Complexe scolaire et d'1 consultants Ecole primaire de la ville de Kolwezi ZR-PDU-126983-CS-CQS / Sélection fondée RECRUTEMENT ONG EN Urban Governance sur les En attente IDA / H8420 A posteriori Open - National 200,000.00 0.00 2019-08-30 2019-09-13 2019-09-28 2019-10-03 2019-10-23 2020-02-20 CHARGE ENGAGEMENT (including PPA) qualifications des d'exécution CITOYEN DANS 4 VCP consultants ZR-PDU-129512-CS-CQS / SC 2A RECRUTEMENT D'UNE MAÎTRISE Sélection fondée D'OUVRAGE DÉLÉGUÉE Urban Governance sur les En attente IDA / H8420 A posteriori Open - National 400,000.00 0.00 2019-09-15 2019-09-29 2019-10-29 2019-11-08 2019-11-18 2020-05-16 POUR MISE EN OEUVRE (including PPA) qualifications des d'exécution DES NEUF SOUS- consultants PROJETS CIBLES DE LA VILLE DE GOMA ZR-PDU-129881-CS-CQS / SC 2A RECRUTEMENT D' UNE MAÎTRISE Sélection fondée D'OUVRAGE DÉLÉGUÉE Urban Governance sur les En attente IDA / H8420 A posteriori Open - National 300,000.00 0.00 2019-09-11 2019-09-25 2019-10-25 2019-11-04 2019-11-19 2020-05-17 POUR LA MISE EN (including PPA) qualifications des d'exécution OEUVRE DES 9 SOUS- consultants PROJETS DE LA VILLE DE BUKAVU 2 ZR-PDU-129882-CS-CQS / SC 2A RECRUTEMENT Sélection fondée D'UN MAÎTRE D'OUVRAGE Urban Governance sur les En attente DÉLÉGUÉ POUR LA IDA / H8420 A posteriori Open - National 300,000.00 0.00 2019-09-15 2019-09-20 2019-10-14 2019-11-03 2019-11-13 2020-05-11 (including PPA) qualifications des d'exécution MISE EN OEUVRE DES 9 consultants SOUS -PROJETS DE LA VILLE DE BUKAVU 1. Page 5 ZR-PDU-125576-CS-CQS / RECRUTEMENT UN CABINET EN CHARGE DE LA MISSION Sélection fondée D'ASSISTANCE Urban Governance sur les Open - En cours TECHNIQUE POUR IDA / H8420 A posteriori 350,000.00 0.00 2019-09-11 2019-09-25 2019-10-14 2019-11-13 2019-11-30 2020-04-28 (including PPA) qualifications des International d'exécution ACCOMPAGNER LE consultants PROCESSUS DE MISE EN PLACE DE LA CAISSE NATIONALE DE PEREQUATION EN RDC ZR-PDU-130535-CS-CQS / SC 2A RECRUTEMENT D'UNE MAÎTRISE Sélection fondée D'OUVRAGE DÉLÉGUÉE Urban Governance sur les En attente IDA / H8420 A posteriori Open - National 430,000.00 0.00 2019-09-15 2019-09-29 2019-10-19 2019-10-29 2019-11-13 2020-05-11 POUR LA MISE EN (including PPA) qualifications des d'exécution OEUVRE DES 10 SOUS- consultants PROJETS CIBLEES DE LA VILLE DE KIKWIT ZR-PDU-133778-CS-CQS / SC 2A RECRUTEMENT D'UN MAITRE D' OUVRAGE DELEGUE POUR LA MISE EN OEUVRE DE HUIT SOUS- Sélection fondée PROJETS DE LA VILLE Urban Governance sur les En attente IDA / H8420 A posteriori Open - National 300,000.00 0.00 2019-09-20 2019-10-04 2019-11-01 2019-11-11 2019-11-21 2020-05-19 DE MATADI CONSTITUES (including PPA) qualifications des d'exécution DE DEUX INSTITUTS, DE consultants DEUX EP, D'UNE BIBLIOTHEQUE, DE DEUX CS ET EQUIPEMENTS MORGUE PLUS CLOTURE MORGUE ZR-PDU-126981-CS-CQS / RECRUTEMENT CABINET Sélection fondée PR ASSISTANCE Urban Governance sur les En cours IDA / H8420 A posteriori Open - National 400,000.00 0.00 2019-08-20 2019-09-03 2019-09-18 2019-09-28 2019-10-13 2019-12-12 TECHNIQUE AUX 4 VCP (including PPA) qualifications des d'exécution PR MOBILISATION consultants RECETTES PROPRES ZR-PDU-138208-CS-CQS / RECRUTEMENT CABINET Sélection fondée EN CHARGE DE L'ETUDE Urban Governance sur les Open - En attente SUR LES IMPACTS SOCIO- IDA / H8420 A posteriori 200,000.00 0.00 2019-10-15 2019-11-05 2019-12-19 2020-01-03 2020-01-31 2020-03-16 (including PPA) qualifications des International d'exécution ÉCONOMIQUES DES consultants INVESTISSEMENTS DU PDU ZR-PDU-138495-CS-INDV / RECRUTEMENT D'UN Sélection fondée CABINET POUR L'ETUDE Urban Governance sur les Open - En attente IDA / H8420 A posteriori 200,000.00 0.00 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2020-04-07 DE SATISFACTION DES (including PPA) qualifications des International d'exécution BÉNÉFICIAIRES DU consultants PROJET PDU ZR-PDU-138201-CS-LCS / RECRUTEMENT CABINET Urban Governance Sélection au Open - En attente AUDIT EXTERNE DU PDU IDA / H8420 A posteriori 100,000.00 0.00 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2020-10-22 (including PPA) moindre coût International d'exécution EXERCICES 2019 2020 2021 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 6 ZR-PDU-30323-CS-CDS / MISSION SURVEILLANCE ET CONTROLE TRAVAUX Sélection de DE REHABILITATION ET En cours IDA / H8420 Primary Infrastructure A priori consultants par Direct 500,335.00 0.00 2017-09-27 2017-09-28 2017-10-01 2018-05-29 MODERNISATION DES d'exécution entente directe AVENUES IRAMBO(Ville Bukavu) ET ITELA (Ville de Mbandaka) ZR-PDU-65864-CS-INDV / Urban Governance En attente Recrutement d'un Comptable IDA / H8420 A posteriori Individuel Limited 40,000.00 0.00 2018-06-20 2018-06-25 2018-07-16 2018-08-20 2019-08-15 (including PPA) d'exécution pour le SP-PDU ZR-PDU-65866-CS-INDV / Recrutement Consultant ind -Revision Instruments Urban Governance En attente sauvegardes environ. et IDA / H8420 A posteriori Individuel Limited 50,000.00 0.00 2018-06-21 2018-06-26 2018-07-17 2018-08-21 2019-08-16 (including PPA) d'exécution sociale - Elaboration Plan renforcement capacités parties prenantes ZR-PDU-65868-CS-INDV / Consultant ind. pour audit de conformité et de Urban Governance En attente gouvernance environ. et IDA / H8420 A posteriori Individuel Limited 100,000.00 0.00 2018-06-13 2018-06-18 2018-07-09 2018-08-13 2018-09-27 (including PPA) d'exécution sociale -chantiers travaux modernisation voiries urbaines du PDU. ZR-PDU-65882-CS-INDV / Recrutement d'un Consultant en charge d'assurer Urban Governance En cours IDA / H8420 A posteriori Individuel Limited 30,000.00 0.00 2018-06-18 2018-06-23 2018-07-03 2018-07-18 2019-07-13 l'Assistance à la Maitrise (including PPA) d'exécution d'Ouvrage (AMO)/ Ville de Bukavu ZR-PDU-65883-CS-INDV / Recrutement d'un Consultant en charge d'assurer Urban Governance En cours IDA / H8420 A posteriori Individuel Limited 30,000.00 0.00 2018-06-20 2018-06-25 2018-07-05 2018-07-20 2019-07-15 l'Assistance à la Maitrise (including PPA) d'exécution d'Ouvrage (AMO)/ Ville de Kikwit ZR-PDU-65885-CS-INDV / Recrutement d'un Consultant en charge d'assurer Urban Governance IDA / H8420 A posteriori Individuel Limited 30,000.00 0.00 Annulé 2018-06-20 2018-06-25 2018-07-05 2018-07-20 2019-07-15 l'Assistance à la Maitrise (including PPA) d'Ouvrage (AMO)/ Ville de Kindu ZR-PDU-65886-CS-INDV / Recrutement d'un Consultant en charge d'assurer Urban Governance En cours IDA / H8420 A posteriori Individuel Limited 30,000.00 0.00 2018-06-17 2018-06-22 2018-07-02 2018-07-17 2019-07-12 l'Assistance à la Maitrise (including PPA) d'exécution d'Ouvrage (AMO)/ Ville de Matadi ZR-PDU-72617-CS-INDV / Mission d'assistance technique ponctuelle d'un IDA / 60340 Primary Infrastructure A posteriori Individuel Limited 90,000.00 0.00 Annulé 2018-08-07 2018-08-12 2018-08-27 2018-09-06 2019-07-03 consultant au SP.PDU _Travaux des infrastructures Page 7 ZR-PDU-72618-CS-CDS / Convention OVD _ Etudes tech. trx gare routière_ pavage artères Sélection de principales_tronçon route en IDA / 60340 Primary Infrastructure A posteriori consultants par Direct 100,000.00 0.00 Annulé 2018-08-10 2018-08-20 2018-09-14 2018-12-13 terre_Curage collecteurs_ rôle entente directe temporaire MdC voiries ciblées 3villes add avant mobilisation de la MdC....etc. ZR-PDU-72615-CS-CDS / MISSION EVRC DES 9 VILLES CIBLEES EN Sélection de Urban Governance RDC_CONTRAT IDA / 60340 A posteriori consultants par Direct 150,000.00 173,368.50 Signé 2018-08-12 2018-08-15 2018-08-20 2018-09-19 (including PPA) TECHNIPLAN entente directe INTERNATIONAL CONSULTING ZR-PDU-74563-CS-INDV / CONSULTANT IND EN Urban Governance En cours IDA / 60340 A posteriori Individuel Limited 50,000.00 0.00 2018-08-26 2018-08-31 2018-09-21 2018-10-26 2019-10-26 CHARGE DE LA (including PPA) d'exécution COMMUNICATION ZR-PDU-75126-CS-CDS / MISSION EVRC DANS NEUF VILLES POUR UNE Sélection de Urban Governance DUREE DE SIX MOIS - IDA / 60340 A priori consultants par Direct 1,000,000.00 0.00 Annulé 2018-08-26 2018-08-31 2018-09-25 2019-03-24 (including PPA) Cabinet TECHNIPLAN entente directe INTERNATIONAL CONSULTING ZR-PDU-107327-CS-INDV / RECRUTEMENT UN CONSULTANT INDIVIDUEL Urban Governance En cours IDA / H8420 A priori Individuel Open 300,000.00 0.00 2019-04-30 2019-05-26 2019-05-31 2019-06-26 2021-11-12 AU POSTE DE (including PPA) d'exécution COORDONNATEUR DU PDU ZR-PDU-113580-CS-CDS / RECRUTEMENT ENTENTE DIRECTE GROUPEMENT Sélection de Urban Governance En cours CABINETS BERD & SERF IDA / H8420 A posteriori consultants par Direct 310,000.00 0.00 2019-05-09 2019-05-11 2019-05-24 2019-07-02 (including PPA) d'exécution _MISSION EVALUATION entente directe ANNUELLE PERFORMANCES DES VCP ZR-PDU-65860-CS-INDV / Urban Governance Recrutement d'un Expert IDA / H8420 A posteriori Individuel Limited 50,000.00 0.00 Annulé 2019-05-12 2019-05-15 2019-05-18 2019-05-26 2020-05-20 (including PPA) infrastructures nº2 ZR-PDU-86047-CS-INDV / RECRUTEMENT CONSULTANT INDIVIDUEL POUR ASSISTANCE Urban Governance En cours IDA / 60340 A posteriori Individuel Limited 100,000.00 0.00 2019-05-26 2019-05-31 2019-06-10 2019-06-25 2019-10-13 TECHNIQUE EN GESTION (including PPA) d'examen DES FINANCES PUBLIQUES DANS LES VCP ZR-PDU-117935-CS-INDV / Recrutement d'un Spécialiste Urban Governance En cours IDA / H8420 A posteriori Individuel Limited 50,000.00 0.00 2019-06-10 2019-06-15 2019-06-25 2019-07-05 2020-06-29 en Passation des marchés (including PPA) d'exécution nº2 pour le SP.PDU ZR-PDU-117936-CS-INDV / RECRUTEMENT Urban Governance En cours INGENIEUR EN CHARGE IDA / H8420 A posteriori Individuel Limited 50,000.00 0.00 2019-06-10 2019-06-15 2019-06-25 2019-07-05 2020-06-29 (including PPA) d'exécution DES INFRASTRUCTURES AU SP.PDU Page 8 ZR-PDU-125714-CS-INDV / Recrutement un consultant Urban Governance En cours individuel en charge de la IDA / H8420 A posteriori Individuel Limited 30,000.00 0.00 2019-08-13 2019-08-18 2019-09-08 2019-10-13 2020-04-10 (including PPA) d'exécution mission de VBG au sein du SP PDU ZR-PDU-126060-CS-CQS / Recrutement d'un consultant individuel en violence basée sur le genre (VBG) Urban Governance En cours Spécialiste en cartographie IDA / H8420 A posteriori Individuel Limited 40,000.00 0.00 2019-08-18 2019-08-23 2019-08-28 2019-09-12 2019-12-11 (including PPA) d'exécution des services de VBG en République Démocratique du Congo (pour les villes de Matadi et Kikwit) ZR-PDU-126063-CS-INDV / Recrutement d'un consultant individuel en violence basée sur le genre (VBG) Urban Governance En attente Spécialiste en cartographie IDA / H8420 A posteriori Individuel Limited 40,000.00 0.00 2019-08-15 2019-08-20 2019-08-30 2019-09-14 2019-12-13 (including PPA) d'exécution des services de VBG en République Démocratique du Congo (pour les villes de Bukavu et Goma) ZR-PDU-126977-CS-INDV / Recrutement consultant individuel pr élaboration Urban Governance En cours IDA / H8420 A posteriori Individuel Limited 30,000.00 0.00 2019-08-20 2019-08-25 2019-09-04 2019-09-14 2019-10-14 plan pluriannuel de (including PPA) d'exécution formation des 4 VCP , OSC, OC ZR-PDU-126980-CS-INDV / Recrutement consultant individuel pr appuyer la Urban Governance En attente IDA / H8420 A posteriori Individuel Limited 30,000.00 0.00 2019-08-15 2019-08-20 2019-08-25 2019-09-04 2019-10-04 mise en place et (including PPA) d'exécution opérationalisation outil de suivi dossiers du PDU ZR-PDU-126985-CS-INDV / RECRUTEMENT CONSULTANT INDIVIDUEL POUR APPUYER OVD En cours IDA / H8420 Primary Infrastructure A posteriori Individuel Limited 30,000.00 0.00 2019-08-18 2019-08-23 2019-08-28 2019-09-07 2019-10-07 ETUDES TECHNIQUES d'exécution POUR VOIRIES CIBLEES DES VILLES DE MATADI ET KIKWIT ZR-PDU-126984-CS-INDV / RECRUTEMENT CONSULTANT INDIVIDUEL POUR APPUYER OVD DANS LES ETUDES En cours TECHNIQUES DES IDA / H8420 Primary Infrastructure A posteriori Individuel Limited 30,000.00 0.00 2019-09-15 2019-09-20 2019-09-30 2019-10-10 2019-11-09 d'exécution VOIRIES CIBLEES DES VILLES DE BUKAVU ET DE GOMA DANS LE CADRE DE LA COMPOSANTE 1 DU PDU ZR-PDU-138210-CS-INDV / RECRUTEMENT D'UN CONSULTANT INDIVIDUEL En attente EN CHARGE DE LA IDA / H8420 Primary Infrastructure A posteriori Individuel Limited 60,000.00 0.00 2019-10-15 2019-10-20 2019-11-04 2019-12-03 2020-01-17 d'exécution MISSION D'AUDIT TECHNIQUE DES OUVRAGES DU PDU Page 9 ZR-PDU-138202-CS-CDS / RENOUVELLEMENT CONTRAT DE MONSIEUR Sélection de Urban Governance En attente BACHIR OLOUDE _ IDA / H8420 A posteriori consultants par Direct 70,000.00 0.00 2019-10-15 2019-10-19 2019-10-25 2020-04-22 (including PPA) d'exécution ASSISTANT TECHNIQUE entente directe DU SP.PDU POUR UNE DURÉE DE 6 MOIS ZR-PDU-138507-CS-CDS / RENOUVELLEMENT DU CONTRAT DE LA Sélection de Urban Governance En attente SPÉCIALISTE EN IDA / H8420 A posteriori consultants par Direct 36,000.00 0.00 2019-10-07 2019-10-11 2019-10-16 2020-10-10 (including PPA) d'exécution COMMUNICATION Madame entente directe SOLANGE MWINJA AU SEIN DU SP.PDU ZR-PDU-138515-CS-CDS / RENOUVELLEMENT DU Sélection de CONTRAT DU COMPTABLE Urban Governance En attente IDA / H8420 A posteriori consultants par Direct 38,500.00 0.00 2019-10-10 2019-10-15 2019-10-28 2020-10-22 MONSIEUR CHRISTOPHE (including PPA) d'exécution entente directe MWAMBA KUNDA AU SEIN DU SP.PDU ZR-PDU-141299-CS-INDV / RECRUTEMENT UN CONSULTANT INDIVIDUEL Urban Governance En attente EN CHARGE DE LA IDA / H8420 A posteriori Individuel Limited 30,000.00 0.00 2019-10-22 2019-10-27 2019-11-01 2019-11-16 2020-11-10 (including PPA) d'exécution MISSION DE L'ENVIRONNEMENTALISTE N°2 AU SEIN DU SP PDU Page 10