NILE EQUATORIAL LAKES SUBSIDIARY ACTION PROGRAM (NELSAP PROCUREMENT PLAN 1st May 2017 to April 2018 I. General 1. Project information: - Country borrower: Nile Basin Initiative/Nile Equatorial Lakes Subsidiary Action Program - Project Name: Nile Cooperation for Results Project - Loan/Credit No:- TF13766 - Project Implementing Agency (PIA): Nile Equatorial Lakes Subsidiary Action Program 2. Bank’s approvalDate of the procurement Plan: 3. Date of General Procurement Notice: N/A 4. Period covered by this procurement plan: 12 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] No Procurement Method Threshold Prior Review Comments (Goods and Works) in US Dollars Threshold in US Dollars 1 ICB (Goods) N/A N/A 2 LIB (Goods) N/A N/A 3 NCB (Goods and Non Consultants N/A N/A Services) 4 Shopping (Goods and Non ≤100,000 ≤100,000 Consultants Services) 5 ICB (Works) N/A 6 NCB (Works) N/A 7 Shopping (Works) N/A 8 ICB(Non-Consultant Services) N/A 2. Prequalification. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: : Guidelines for procurement under IBRD loans and IDA credits, NBI Procurement and Disposal Manual 5. Any Other Special Procurement Arrangements: N/A 6. Procurement Packages with Methods and Time Schedule: N/A III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: III. Selection of Consultants 2. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Ceiling Prior Review Comment Method Threshold 1. QCBS >= 1,000,000 2. QBS N/A 3. LCS ≤200,000 4. CQS N/A 5. SSS ≥ 100,000 6. IC ≥300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule PROCUREMENT Africa : AFCC2/RI-Nile Cooperation for Results Project PLAN General Information Country: Africa Banks Approval Date of the Original Procurement Plan: 2017-08-01 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-03-06 Project ID: P130694 GPN Date: Project Name: AFCC2/RI-Nile Cooperation for Results Project Loan / Credit No: TF / 13767 Executing Agency(ies): Nile Basin Initiative/Nile Equatorial Lakes Subsidiary Program - Coordination Unit, Eastern Nile Technical Regional Office, Nile Basin Initiative Secretariat WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-ENTRO-23627-GO-RFQ / Service and supply of goods i.e 3. Promotion of Sustainable network cable re-installation & Request for Single Stage - One Pending TF / 13767 Development and Planning in the Post Limited 15,000.00 0.00 2017-08-20 2017-10-15 2018-02-12 maintenance For Upgrading the Quotations Envelope Implementation Eastern Nile Region existing network and electrical system ET-ENTRO-23630-GO-RFQ / Maintenance of backup power 3. Promotion of Sustainable Request for Single Stage - One Pending supply equipment and TF / 13767 Development and Planning in the Post Limited 30,000.00 0.00 2017-08-20 2017-10-15 2018-02-12 Quotations Envelope Implementation standardized installation Eastern Nile Region including supply of spare parts ET-ENTRO-23633-GO-RFQ / Supply and replacement of old 3. Promotion of Sustainable Request for Single Stage - One Pending network equipment, software and TF / 13767 Development and Planning in the Post Limited 85,000.00 0.00 2017-08-20 2017-10-15 2018-02-12 Quotations Envelope Implementation servers including maintenance Eastern Nile Region service ET-ENTRO-23658-GO-RFQ / Application software for 3. Promotion of Sustainable Request for Single Stage - One Pending Strengthen National Dam Safety TF / 13767 Development and Planning in the Post Limited 10,000.00 0.00 2018-01-20 2018-03-17 2018-05-16 Quotations Envelope Implementation Units and Developing Human Eastern Nile Region Resources Capacity ET-ENTRO-23659-GO-RFQ / 3. Promotion of Sustainable Request for Single Stage - One Pending Dam safety monitoring and TF / 13767 Development and Planning in the Post Limited 25,000.00 0.00 2018-02-20 2018-04-17 2018-06-16 Quotations Envelope Implementation inspection instrument/equipment Eastern Nile Region ET-ENTRO-23660-GO-RFQ / 3. Promotion of Sustainable Request for Single Stage - One Pending Dam safety reference TF / 13767 Development and Planning in the Post Limited 15,000.00 0.00 2017-11-06 2018-01-01 2018-03-02 Quotations Envelope Implementation books/Journals Eastern Nile Region UG-NBI-24732-GO-DIR / software tools for maintaining 1. Advancing Nile Basin-Wide Pending TF / 13767 Post Direct Selection Direct 5,000.00 0.00 2018-02-05 2018-02-10 2018-03-17 2018-09-13 user community portal and Cooperation and Analysis Implementation helpdesk UG-NBI-24733-GO-RFQ / 1. Advancing Nile Basin-Wide Request for Single Stage - One Pending TF / 13767 Post Limited 1,000.00 0.00 2017-10-10 2017-12-05 2018-06-03 Printing the Corporate Brochure Cooperation and Analysis Quotations Envelope Implementation UG-NBI-24734-GO-RFQ / 1. Advancing Nile Basin-Wide Request for Single Stage - One Pending TF / 13767 Post Limited 3,000.00 0.00 2017-10-25 2017-11-24 2017-11-28 Printing the NBI Corporate Report Cooperation and Analysis Quotations Envelope Implementation ET-ENTRO-23640-GO-RFQ / High performance Workstations,laptops,ups,... to 3. Promotion of Sustainable Single Stage - One Pending enhance and strengthen Eastern TF / 13767 Development and Planning in the Post Request for Bids Open - National 100,000.00 0.00 2017-12-15 2017-12-20 2018-01-31 2018-03-02 2018-04-06 2018-06-05 Envelope Implementation Nile Seasonal Forecasting and Eastern Nile Region Flood Forecasting- Early Warning UG-NBI-24249-GO-RFQ / 5.1.1 - 1. Advancing Nile Basin-Wide Request for Single Stage - One Pending High end computing facility TF / 13767 Post Limited 4,000.00 0.00 2018-01-10 2018-02-22 2018-03-16 Cooperation and Analysis Quotations Envelope Implementation (server) UG-NBI-37655-GO-RFQ / 1. Advancing Nile Basin-Wide Request for Single Stage - One Pending Procurement of Computer TF / 13767 Post Limited 2,500.00 0.00 2018-01-07 2018-03-04 2018-08-31 Cooperation and Analysis Quotations Envelope Implementation workstation/laptop RW-NELSAP-CU-21626-GO- 2. Promotion of Sustainable Request for Single Stage - One Pending RFQ / Supply of Bulk Files TF / 13767 Development and Planning in the Post Limited 33,800.00 0.00 2018-02-05 2018-03-10 2018-04-30 Quotations Envelope Implementation Archiving System Nile Equatorial Lakes Region 2. Promotion of Sustainable RW-NELSAP-CU-21630-GO- Request for Single Stage - One Pending TF / 13767 Development and Planning in the Post Limited 15,000.00 0.00 2018-02-01 2018-03-06 2018-04-05 RFQ / Printing of RATP Manuals Quotations Envelope Implementation Nile Equatorial Lakes Region UG-NBI-24552-GO-RFQ / 1. Advancing Nile Basin-Wide Request for Single Stage - One Pending Printing 2018 NBI Secretariat TF / 13767 Post Limited 3,000.00 0.00 2017-11-25 2018-01-19 2019-01-05 Cooperation and Analysis Quotations Envelope Implementation Calendars UG-NBI-24553-GO-RFQ / 1. Advancing Nile Basin-Wide Request for Single Stage - One Pending TF / 13767 Post Limited 1,500.00 0.00 2018-01-20 2018-02-12 2018-03-09 Printing the NBI Success Stories Cooperation and Analysis Quotations Envelope Implementation UG-NBI-24221-GO-DIR / 1.10.1.1 - Software tools for 1. Advancing Nile Basin-Wide Request for Single Stage - One Pending TF / 13767 Post Limited 5,000.00 0.00 2017-11-24 2017-11-29 2018-01-10 2018-02-09 2018-03-16 2018-09-12 developing the integrated website Cooperation and Analysis Proposals Envelope Implementation and databases UG-NBI-24247-GO-RFQ / 1. Advancing Nile Basin-Wide Request for Single Stage - One Pending TF / 13767 Post Limited 2,500.00 0.00 2017-12-02 2018-01-21 2018-02-18 5.1.1.1 - Laptops Cooperation and Analysis Quotations Envelope Implementation Page 1 UG-NBI-37577-GO-RFQ / 1. Advancing Nile Basin-Wide Request for Single Stage - One Pending TF / 13767 Post Limited 4,000.00 0.00 2018-01-15 2018-03-12 2018-09-08 Printing of the NBI Strategy Cooperation and Analysis Quotations Envelope Implementation UG-NBI-37654-GO-RFQ / 1. Advancing Nile Basin-Wide Request for Single Stage - One Pending Printing of the State of TF / 13767 Post Limited 1,000.00 0.00 2018-01-09 2018-03-06 2018-09-02 Cooperation and Analysis Quotations Envelope Implementation knowledge brochure NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-ENTRO-23651-NC-RFQ / 3. Promotion of Sustainable Printing for Documentation and Request for Single Stage - One Pending TF / 13767 Development and Planning in the Post Limited 5,000.00 0.00 2018-01-20 2018-03-17 2018-05-16 dissemination (training and Quotations Envelope Implementation Eastern Nile Region scaling up manuals) ET-ENTRO-23656-NC-RFQ / 3. Promotion of Sustainable Request for Single Stage - One Pending Production of Eastern Nile TF / 13767 Development and Planning in the Post Limited 15,000.00 0.00 2018-01-20 2018-03-17 2018-06-15 Quotations Envelope Implementation Ground Water preliminary Atlas Eastern Nile Region UG-NBI-22127-NC-RFB / IFMIS 1. Advancing Nile Basin-Wide Single Stage - One Under TF / 13767 Post Request for Bids Limited 30,000.00 0.00 2017-11-29 2018-01-22 2017-12-04 2018-04-08 2018-04-15 2018-05-06 2018-09-15 Software Cooperation and Analysis Envelope Implementation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-NELSAP-CU-21811-CS- CQS / Consultancy Services for Finalization of Preparation of 2. Promotion of Sustainable Consultant Environmental and Social Impact Under TF / 13767 Development and Planning in the Post Qualification Open - International 212,194.00 0.00 2017-07-25 2017-07-26 2017-08-15 2017-09-28 2017-09-18 2017-10-14 2017-10-19 2017-11-11 2018-05-10 Assessment (ESIA) and Implementation Nile Equatorial Lakes Region Selection Resettlement Action Plan (RAP) for the Sio Sango Irrigation and Watershed Management Project RW-NELSAP-CU-21857-CS- CDS / Consultancy Services for the External Audit of the 2. Promotion of Sustainable Pending Financial Statements of the TF / 13767 Development and Planning in the Post Least Cost Selection Open - National 10,000.00 0.00 2018-07-02 2018-07-23 2018-09-05 2018-10-03 2018-11-02 2018-12-07 2019-01-11 2019-07-10 Implementation NELSAP/NCORE Project CIWA Nile Equatorial Lakes Region Grant for the Period 1 July 2017 to 30 June 2018 RW-NELSAP-CU-21813-CS- CQS / Consultancy Services for Finalization of the Environmental 2. Promotion of Sustainable Consultant and Social Impact Assessment Pending TF / 13767 Development and Planning in the Post Qualification Open - International 203,854.00 0.00 2017-07-25 2017-08-15 2017-09-28 2017-10-13 2017-11-03 2018-05-02 (ESIA) and Resettlement Action Implementation Nile Equatorial Lakes Region Selection Plan (RAP) for the Kabuyanda Water Resources Development Project INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-NELSAP-CU-21841-CS- CQS / Consultancy Services for the Formulation of the Devolution of Functions and Duties of Three 2. Promotion of Sustainable Individual Consultant Under River Basin Management TF / 13767 Development and Planning in the Post Limited 25,000.00 0.00 2017-07-25 2016-11-08 2017-07-27 2017-07-27 2017-07-31 2017-08-24 2017-08-04 2017-10-03 Selection Implementation Projects to the Inter- Nile Equatorial Lakes Region Governmental Coordination Committees of the Riparian Countries. ET-ENTRO-22636-CS-INDV / 3. Promotion of Sustainable Team Leader/Knowledge Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 154,000.00 0.00 2017-08-07 2017-09-25 2017-10-16 2017-11-20 2019-11-20 management for Eastern Nile Selection Implementation Eastern Nile Region Knowledge Base Enhancement ET-ENTRO-23040-CS-INDV / 3. Promotion of Sustainable Web Designer/developer for Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 60,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2018-05-27 Eastern Nile Knowledge Base Selection Implementation Eastern Nile Region Enhancement ET-ENTRO-23041-CS-INDV / 3. Promotion of Sustainable Content management expert for Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 40,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2019-06-01 Eastern Nile Knowledge Base Selection Implementation Eastern Nile Region Enhancement ET-ENTRO-23047-CS-INDV / 3. Promotion of Sustainable Database and online service Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 48,600.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2019-06-01 expert for Eastern Nile Selection Implementation Eastern Nile Region Knowledge Base Enhancement ET-ENTRO-23052-CS-INDV / 3. Promotion of Sustainable Individual Consultant Pending Technical Writer for Eastern Nile TF / 13767 Development and Planning in the Post Open 40,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2018-05-27 Selection Implementation Knowledge Base Enhancement Eastern Nile Region ET-ENTRO-23056-CS-INDV / 3. Promotion of Sustainable Visualization expert for Eastern Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 24,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2019-02-01 Nile Knowledge Base Selection Implementation Eastern Nile Region Enhancement ET-ENTRO-23058-CS-INDV / 3. Promotion of Sustainable Spatial information expert for Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 45,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2019-04-22 Eastern Nile Knowledge Base Selection Implementation Eastern Nile Region Enhancement Page 2 ET-ENTRO-23060-CS-INDV / Team Leader/FEWS expert for 3. Promotion of Sustainable Individual Consultant Pending Eastern Nile Seasonal TF / 13767 Development and Planning in the Post Open 154,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2019-08-30 Selection Implementation Forecasting and Flood Eastern Nile Region Forecasting- Early Warning 3. Promotion of Sustainable ET-ENTRO-23079-CS-INDV / Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 70,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2019-03-23 Short term Flood forecast expert Selection Implementation Eastern Nile Region 3. Promotion of Sustainable ET-ENTRO-23082-CS-INDV / Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 9,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2018-03-28 Flood forecast expert Selection Implementation Eastern Nile Region ET-ENTRO-23084-CS-INDV / 3. Promotion of Sustainable Meteorologist for Eastern Nile Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 12,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2018-05-27 Seasonal Forecasting and Flood Selection Implementation Eastern Nile Region Forecasting- Early Warning ET-ENTRO-23086-CS-INDV / 3. Promotion of Sustainable Individual Consultant Pending Long term Seasonal forecast TF / 13767 Development and Planning in the Post Open 25,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2018-04-27 Selection Implementation expert Eastern Nile Region 3. Promotion of Sustainable ET-ENTRO-23091-CS-INDV / Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 16,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2018-05-27 Hydrologist/modeler Selection Implementation Eastern Nile Region ET-ENTRO-23098-CS-INDV / 3. Promotion of Sustainable Individual Consultant Pending Flood information packaging and TF / 13767 Development and Planning in the Post Open 15,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2018-03-28 Selection Implementation dissemination Eastern Nile Region 3. Promotion of Sustainable ET-ENTRO-23103-CS-INDV / Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 8,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2018-03-28 Remote Sensing Specialist Selection Implementation Eastern Nile Region 3. Promotion of Sustainable ET-ENTRO-23104-CS-INDV / Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 24,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2018-03-28 Surveyor(social) Selection Implementation Eastern Nile Region ET-ENTRO-23111-CS-INDV / Project Coordination and 3. Promotion of Sustainable Individual Consultant Pending supervision for Eastern Nile TF / 13767 Development and Planning in the Post Open 66,000.00 0.00 2017-08-15 2017-10-03 2017-10-24 2017-11-28 2018-05-27 Selection Implementation Internship/ Young Professional Eastern Nile Region Program ET-ENTRO-23245-CS-INDV / Regional Consultant for Impact 3. Promotion of Sustainable Assessment of piloted WSM Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 27,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-07-06 interventions for Watershed Selection Implementation Eastern Nile Region Management Best Practices Assessment ET-ENTRO-23251-CS-INDV / National Consultant for Impact 3. Promotion of Sustainable Assessment of piloted WSM Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 23,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-07-06 interventions for Watershed Selection Implementation Eastern Nile Region Management Best Practices Assessment (#1) ET-ENTRO-23269-CS-INDV / National Consultant for Impact 3. Promotion of Sustainable Assessment of piloted WSM Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 15,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-07-06 interventions for Watershed Selection Implementation Eastern Nile Region Management Best Practices Assessment (#2) ET-ENTRO-23317-CS-INDV / International Consultant to 3. Promotion of Sustainable Individual Consultant Pending Conduct a scoping and situation TF / 13767 Development and Planning in the Post Open 14,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-10-04 Selection Implementation analysis of the existing irrigation Eastern Nile Region developments ET-ENTRO-23319-CS-INDV / National consultant to Conduct a 3. Promotion of Sustainable Individual Consultant Pending scoping and situation analysis of TF / 13767 Development and Planning in the Post Open 13,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-10-04 Selection Implementation the existing irrigation Eastern Nile Region developments (#1) ET-ENTRO-23320-CS-INDV / National Consultant to Conduct a 3. Promotion of Sustainable Individual Consultant Pending scoping and situation analysis of TF / 13767 Development and Planning in the Post Open 13,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-10-04 Selection Implementation the existing irrigation Eastern Nile Region developments(#2) ET-ENTRO-23321-CS-INDV / National consultant to Conduct a 3. Promotion of Sustainable Individual Consultant Pending scoping and situation analysis of TF / 13767 Development and Planning in the Post Open 20,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-10-04 Selection Implementation the existing irrigation Eastern Nile Region developments (#3) ET-ENTRO-23398-CS-INDV / Develop options for improving the 3. Promotion of Sustainable performance of existing irrigation Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 45,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-10-04 systems for EN Irrigation Selection Implementation Eastern Nile Region Systems performance Assessment ET-ENTRO-23401-CS-INDV / International consultant to 3. Promotion of Sustainable Conduct a scoping study of Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 18,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-10-04 groundwater's in ENB for Ground Selection Implementation Eastern Nile Region Water Availability and Conjunctive Use Assessment ET-ENTRO-23403-CS-INDV / National consultant to Conduct 3. Promotion of Sustainable a scoping study of groundwater's Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 12,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-10-04 in ENB for Ground Water Selection Implementation Eastern Nile Region Availability and Conjunctive Use Assessment(#1 ) Page 3 ET-ENTRO-23405-CS-INDV / National consultant to Conduct 3. Promotion of Sustainable a scoping study of groundwater's Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 12,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-10-04 in ENB for Ground Water Selection Implementation Eastern Nile Region Availability and Conjunctive Use Assessment(#2 ) ET-ENTRO-23407-CS-INDV / National consultant to Conduct 3. Promotion of Sustainable a scoping study of groundwater's Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 12,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-10-04 in ENB for Ground Water Selection Implementation Eastern Nile Region Availability and Conjunctive Use Assessment(#3 ) ET-ENTRO-23409-CS-INDV / 3. Promotion of Sustainable Develop preliminary Eastern Nile Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 25,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-10-04 groundwater's Atlas and design Selection Implementation Eastern Nile Region groundwater monitoring system ET-ENTRO-23413-CS-INDV / 3. Promotion of Sustainable Individual Consultant Pending International Dam safety TF / 13767 Development and Planning in the Post Open 50,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-04-07 Selection Implementation Specialist Eastern Nile Region ET-ENTRO-23415-CS-INDV / 3. Promotion of Sustainable International Dam safety Individual Consultant Pending TF / 13767 Development and Planning in the Post Open 40,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-04-07 Instrumentation and Surveillance Selection Implementation Eastern Nile Region Specialist ET-ENTRO-23418-CS-INDV / 3. Promotion of Sustainable Individual Consultant Pending Regional Dam safety expert TF / 13767 Development and Planning in the Post Open 23,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-04-07 Selection Implementation (#1) Eastern Nile Region ET-ENTRO-23423-CS-INDV / 3. Promotion of Sustainable Individual Consultant Pending Regional Dam Safety Expert TF / 13767 Development and Planning in the Post Open 22,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-04-07 Selection Implementation (#2) Eastern Nile Region ET-ENTRO-23427-CS-INDV / Water Resource Specialist for capacity building(#1)- Resource 3. Promotion of Sustainable Individual Consultant Pending Person to perform training on TF / 13767 Development and Planning in the Post Open 10,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-04-07 Selection Implementation Cascade dams operation for Eastern Nile Region senior Officials & decision makers ET-ENTRO-23431-CS-INDV / Water Resource Specialist for capacity building(#2)- Resource 3. Promotion of Sustainable Individual Consultant Pending Person to perform training on TF / 13767 Development and Planning in the Post Open 10,000.00 0.00 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-04-07 Selection Implementation Cascade dams operation for Eastern Nile Region senior Officials & decision makers 2. Promotion of Sustainable RW-NELSAP-CU-23700-CS- Under TF / 13767 Development and Planning in the Post Direct Selection Direct 76,427.00 0.00 2017-06-08 2015-01-16 2017-06-18 2017-08-22 2018-02-18 CDS / Program Officer - WRM&D Implementation Nile Equatorial Lakes Region RW-NELSAP-CU-23702-CS- 2. Promotion of Sustainable CDS / Senior Pending TF / 13767 Development and Planning in the Post Direct Selection Direct 76,427.00 0.00 2017-06-08 2017-06-18 2017-08-22 2018-02-18 Economist/Monitoring and Implementation Nile Equatorial Lakes Region Evaluation Specialist 2. Promotion of Sustainable RW-NELSAP-CU-23690-CS- Under TF / 13767 Development and Planning in the Post Direct Selection Direct 76,427.00 0.00 2017-06-08 2015-01-16 2017-06-18 2017-08-22 2018-02-18 CDS / Program Officer -Power Implementation Nile Equatorial Lakes Region 2. Promotion of Sustainable RW-NELSAP-CU-23698-CS- Under TF / 13767 Development and Planning in the Post Direct Selection Direct 60,281.00 0.00 2017-06-08 2015-08-21 2017-06-18 2017-08-22 2018-02-18 CDS / Power Engineer Implementation Nile Equatorial Lakes Region RW-NELSAP-CU-23662-CS- 2. Promotion of Sustainable Under CDS / Finance and TF / 13767 Development and Planning in the Post Direct Selection Direct 73,879.00 0.00 2017-06-08 2012-11-13 2017-06-18 2017-08-22 2018-02-18 Implementation Adiministration Manager Nile Equatorial Lakes Region 2. Promotion of Sustainable RW-NELSAP-CU-23684-CS- Under TF / 13767 Development and Planning in the Post Direct Selection Direct 54,246.00 0.00 2017-06-08 2012-11-13 2017-06-18 2017-08-22 2018-02-18 CDS / Finance Officer Implementation Nile Equatorial Lakes Region RW-NELSAP-CU-23688-CS- 2. Promotion of Sustainable Under CDS / Water Resources Officer TF / 13767 Development and Planning in the Post Direct Selection Direct 62,103.00 0.00 2017-06-08 2012-11-13 2017-06-18 2017-08-22 2018-02-18 Implementation (Modeller/GIS) Nile Equatorial Lakes Region RW-NELSAP-CU-23664-CS- 2. Promotion of Sustainable Under CDS / Water Resources TF / 13767 Development and Planning in the Post Direct Selection Direct 60,281.00 0.00 2017-06-08 2012-11-13 2017-06-18 2017-08-22 2018-02-18 Implementation Engineer Nile Equatorial Lakes Region 2. Promotion of Sustainable RW-NELSAP-CU-23682-CS- Under TF / 13767 Development and Planning in the Post Direct Selection Direct 62,989.00 0.00 2017-06-08 2015-12-04 2017-06-18 2017-08-22 2018-02-18 CDS / Project Officer -Kagera Implementation Nile Equatorial Lakes Region RW-NELSAP-CU-23695-CS- 2. Promotion of Sustainable Under CDS / Water Resources Egineer TF / 13767 Development and Planning in the Post Direct Selection Direct 36,347.00 0.00 2017-06-08 2013-02-04 2017-06-18 2017-05-05 2017-08-22 2018-02-18 Implementation (JPO Kagera) Nile Equatorial Lakes Region RW-NELSAP-CU-23674-CS- 2. Promotion of Sustainable Under CDS / Project Officer - Mara TF / 13767 Development and Planning in the Post Direct Selection Direct 62,989.00 0.00 2017-06-08 2015-12-04 2017-06-18 2017-08-22 2018-02-18 Implementation Project Nile Equatorial Lakes Region 2. Promotion of Sustainable RW-NELSAP-CU-23680-CS- Under TF / 13767 Development and Planning in the Post Direct Selection Direct 62,989.00 0.00 2017-06-08 2015-12-04 2017-06-18 2017-08-22 2018-02-18 CDS / Project Officer - SMM Implementation Nile Equatorial Lakes Region RW-NELSAP-CU-23677-CS- 2. Promotion of Sustainable Under CDS / Water Reources Engineer TF / 13767 Development and Planning in the Post Direct Selection Direct 35,135.00 0.00 2017-06-08 2013-02-04 2017-06-18 2017-08-22 2018-02-18 Implementation (JPO SMM) Nile Equatorial Lakes Region RW-NELSAP-CU-23669-CS- 2. Promotion of Sustainable Under CDS / Social Development Office TF / 13767 Development and Planning in the Post Direct Selection Direct 35,000.00 0.00 2017-06-08 2017-06-14 2017-06-18 2017-08-22 2018-02-18 Implementation /Safeguards Nile Equatorial Lakes Region Page 4 RW-NELSAP-CU-21849-CS- LCS / Consultancy Services for External Audit of the Financial 2. Promotion of Sustainable Under Statements of the TF / 13767 Development and Planning in the Post Direct Selection Direct 10,000.00 0.00 2017-09-08 2017-09-04 2017-09-18 2017-09-14 2017-11-22 2018-05-21 Implementation NELSAP/NCORE Project CIWA Nile Equatorial Lakes Region Grant for the Period 1 July 2016 to 30 June 2017 UG-NBI-24551-CS-CDS / Graphic Designer (Long term Contract: Corporate report- 1200, 1. Advancing Nile Basin-Wide Pending Success Stories- 1200, Nile TF / 13767 Post Direct Selection Direct 5,000.00 0.00 2016-12-20 2016-12-30 2017-03-05 2017-09-01 Cooperation and Analysis Implementation News - 1200, Calendar - 800, Strategy document - 500 and Water Resources flyer - 100) UG-NBI-22000-CS-INDV / 6.2.1.1 A consultant to develop Inventory of relevant existing national committees and their 1. Advancing Nile Basin-Wide Individual Consultant Pending TF / 13767 Post Open 18,616.00 0.00 2018-01-19 2018-02-13 2018-02-18 2018-04-10 2018-06-05 mandates (including convening Cooperation and Analysis Selection Implementation power) and establish their capacity gaps in relation to trans boundary water cooperation UG-NBI-21887-CS-INDV / Consultant for regional and national training in Hydrodiplomacy, international 1. Advancing Nile Basin-Wide Individual Consultant Pending law & negotiations: Consultant TF / 13767 Post Open 6,000.00 0.00 2018-04-10 2018-05-10 2018-05-15 2018-05-28 2018-06-20 Cooperation and Analysis Selection Implementation trainer for 6days ( 3-days training, 2 preparations and 1 report) 10 meets in the countries and 1 regional meet- firm UG-NBI-22082-CS-INDV / 1. Advancing Nile Basin-Wide Individual Consultant Pending TF / 13767 Post Direct 2,700.00 0.00 2017-11-24 2017-12-04 2017-12-25 2018-01-15 2018-01-19 English-French Translation Cooperation and Analysis Selection Implementation UG-NBI-22086-CS-INDV / 1. Advancing Nile Basin-Wide Individual Consultant Pending English-French translation TF / 13767 Post Direct 1,000.00 0.00 2017-11-24 2017-12-04 2017-12-19 2018-01-13 2019-01-23 Cooperation and Analysis Selection Implementation Consultant -2 UG-NBI-22122-CS-INDV / 1. Advancing Nile Basin-Wide Individual Consultant Pending 2.1.2.3 - Project/National Liason TF / 13767 Post Direct 15,181.00 0.00 2017-06-10 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Cooperation and Analysis Selection Implementation Officer UG-NBI-22129-CS-INDV / Salary 1. Advancing Nile Basin-Wide Individual Consultant Pending for the Information Systems TF / 13767 Post Direct 29,400.00 0.00 2017-06-10 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Cooperation and Analysis Selection Implementation Specialist UG-NBI-22120-CS-INDV / 1. Advancing Nile Basin-Wide Individual Consultant Pending 5.3.1.1 - Consultant- Senior short- TF / 13767 Post Open 21,950.00 0.00 2018-02-08 2018-03-29 2018-04-19 2018-05-24 2018-11-20 Cooperation and Analysis Selection Implementation term river flow forecasting expert UG-NBI-21875-CS-INDV / 2.1.1.1 Consultant for developing 1. Advancing Nile Basin-Wide Individual Consultant Pending resource mobilisation strategy - TF / 13767 Post Open 12,222.00 0.00 2018-03-05 2018-03-30 2018-04-06 2018-04-15 2018-07-27 Cooperation and Analysis Selection Implementation international consultant for 20 days UG-NBI-21883-CS-INDV / 2.1.1.1 Consultant for technical support to NileSEC in fundraising 1. Advancing Nile Basin-Wide Individual Consultant Pending and specialized proposal TF / 13767 Post Open 8,846.00 0.00 2018-03-23 2018-04-20 2018-04-23 2018-04-30 2018-06-25 Cooperation and Analysis Selection Implementation development, international/regional consultant for 15 days, 2 engagements UG-NBI-24288-CS-INDV / 6.2.1.2 Stakeholder Database 1. Advancing Nile Basin-Wide Individual Consultant Pending Regional consultant - Support to TF / 13767 Post Open 24,468.00 0.00 2018-02-05 2018-03-08 2018-03-14 2018-03-22 2018-05-10 Cooperation and Analysis Selection Implementation trans boundary units, to improve coordination UG-NBI-24304-CS-INDV / 2.1.2.3Impact evaluation Consultant - Monitoring and 1. Advancing Nile Basin-Wide Individual Consultant Pending TF / 13767 Post Open 19,518.00 0.00 2018-01-05 2018-01-30 2018-02-06 2018-02-20 2018-04-24 evaluating implemetation of NBI Cooperation and Analysis Selection Implementation Strategy, strategic plan, programs and projects UG-NBI-24224-CS-INDV / 5.1.1.1 - Consultant - senior expert (climate change governance, water governance 1. Advancing Nile Basin-Wide Individual Consultant Pending TF / 13767 Post Open 20,820.00 0.00 2018-01-10 2018-02-06 2018-02-14 2018-02-25 2018-04-10 issues, to help in preparation of Cooperation and Analysis Selection Implementation state of knowledge report and design and faciliation of the CC- water experts meetings UG-NBI-24264-CS-INDV / 5.3.1.1 Consultant -Regional consultnat - WR analyst experience in river flow 1. Advancing Nile Basin-Wide Individual Consultant Pending forecasting - Develop and TF / 13767 Post Open 33,702.00 0.00 2018-01-25 2018-02-19 2018-02-22 2018-03-01 2018-11-09 Cooperation and Analysis Selection Implementation operationalize short-term to seasonal river flow forecasting - Requirements elaboration and preliminary design RW-NELSAP-CU-43197-CS- 2. Promotion of Sustainable Pending CDS / Environmental TF / 13767 Development and Planning in the Post Direct Selection Direct 60,000.00 0.00 2017-04-24 2017-05-01 2017-07-06 2018-04-30 Implementation Management Specialist Nile Equatorial Lakes Region RW-NELSAP-CU-43083-CS- 2. Promotion of Sustainable Pending CDS / Dam Design Engineer TF / 13767 Development and Planning in the Post Direct Selection Direct 20,000.00 0.00 2017-10-20 2017-11-07 2017-11-08 2018-04-30 Implementation (POE) Nile Equatorial Lakes Region 2. Promotion of Sustainable RW-NELSAP-CU-43219-CS- Pending TF / 13767 Development and Planning in the Post Direct Selection Direct 10,000.00 0.00 2017-10-20 2017-11-07 2017-11-08 2018-04-30 CDS / Hydrologist (POE) Implementation Nile Equatorial Lakes Region Page 5 RW-NELSAP-CU-43074-CS- 2. Promotion of Sustainable Pending CDS / Geotechnical Engineer TF / 13767 Development and Planning in the Post Direct Selection Direct 18,500.00 0.00 2017-10-20 2017-11-04 2017-11-19 2018-04-30 Implementation (POE) Nile Equatorial Lakes Region UG-NBI-37525-CS-INDV / 1. Advancing Nile Basin-Wide Individual Consultant Pending 5.3.1.1 - Consultant: senior short- TF / 13767 Post Open 21,950.00 0.00 2018-01-12 2018-03-02 2018-03-23 2018-04-27 2018-10-24 Cooperation and Analysis Selection Implementation term river flow forecasting expert UG-NBI-37574-CS-INDV / 04 1. Advancing Nile Basin-Wide Individual Consultant Pending TF / 13767 Post Open 24,000.00 0.00 2017-12-05 2018-01-23 2018-02-13 2018-03-20 2018-09-16 months salary (Modeler) Cooperation and Analysis Selection Implementation RW-NELSAP-CU-44585-CS- 2. Promotion of Sustainable Individual Consultant Pending INDV / Social Development TF / 13767 Development and Planning in the Post Open 35,000.00 0.00 2017-10-02 2017-11-04 2017-11-11 2017-12-01 2018-12-01 Selection Implementation Officer Nile Equatorial Lakes Region Page 6