REPUBLIC OF MOZAMBIQUE MINISTRY OF LAND, ENVIRONMENT AND RURAL DEVELOPMENT Agriculture and Natural Resources Landscape Management Project (ANRLMP) Project No: P149620 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: April 2017] 2. Date of General Procurement Notice: July 26, 2016. 3. Period covered by this procurement plan: April 2017 to October 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) and (Non- Above US$ 1,500,000 All Consultant Services) 3. ICB (Works) Above US$ 5,000,000 All 4. NCB (Works) Above US$ 5,000,000 All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As per paragraphs 3.17 of the Guidelines and Project Procurement Manual. 4. Reference to (if any) Project Operational/Procurement Manual: Items to be financed under this Credit/Grants will be procured in line with rules in the Operational Manual, Credit/Grants Agreement and Project Procurement Manual. 5. Any Other Special Procurement Arrangements: Not Applicable. 1 Date: April 19, 2017 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness. 1 2 3 4 5 6 7 Estimated Review Domestic Ref. Cost by Bank Description Packages Preference Comments No. US$ (Prior / (yes/no) thousands Post) Summary of the NCB 1 1,791,00 5 No Post (Works) Summary of NCB 2 1,822,60 7 No Post (Goods) Summary of the NCB 3 (Non-Consulting 775,00 1 No Prior Services) Summary of the 4 249,6 6 No Post Shopping (Goods) Summary of the 5 Shopping (Non- 20,00 1 No Post Consulting Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods (Firms) ≥ 200,000 2. Individual ≥ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 2 Date: April 19, 2017 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Estimated Review Description of Ref. No. Cost by Bank Assignment Packages Comments US$ (Prior / thousands Post) Summary of number of 17.800,00 6 Prior 1 contracts that will be let under QCBS 2 Individuals 495.00 6 Prior 3 Individuals 2.210,8 32 Post 3 Date: April 19, 2017 PROCUREMENT Mozambique : Moz Agriculture and Natural Resources Landscape Management Project PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2016-07-13 2020-02-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149620 GPN Date: 2016-07-28 Project Name: Moz Agriculture and Natural Resources Landscape Management Project Loan / Credit No: IDA / 58550, IDA / Q9900, IDA / D1190, IDA / D5020 Executing Agency(ies): MINISTRY OF LAND, ENVIRONMENT AND RURAL DEVELOPMENT - International Funds Management Unit WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 64/W/ANRLMP/17 / Securing Land Tenure Single Stage - One Rehabilitation of the data IDA / 58550 Rights and Increasing Post Request for Bids Open - National 372,560.56 Signed 2017-06-30 2017-07-17 2017-07-07 2017-08-18 2017-09-18 2017-10-12 2017-10-23 2017-11-16 2018-04-23 Envelope center Natural Resources Resilience Agriculture and Forest- 01/ARLMP/W/16 / Rural Single Stage - One IDA / 58550 Based Value Chain Post Request for Bids Open - National 213,326.94 Signed 2017-06-12 2017-07-10 2017-06-19 2017-07-31 2017-08-08 2017-08-30 2017-08-23 2017-10-04 2017-09-20 2018-04-02 Roads Spot Improvements Envelope Development Agriculture and Forest- 02/W/ARLNMP/16 / Rural Single Stage - One IDA / 58550 Based Value Chain Post Request for Bids Open - National 205,391.14 Signed 2017-06-15 2017-07-10 2017-06-21 2017-08-02 2017-08-08 2017-09-01 2017-08-25 2017-10-06 2017-09-26 2018-04-04 Roads Spot Improvement Envelope Development 79/W/ANRLMP/17 / Agriculture and Forest- Request for Single Stage - One Constructions of PACES IDA / D1190 Based Value Chain Post Open - National 0.00 Canceled 2018-04-09 2018-06-06 2018-12-03 Quotations Envelope Warehouses Development 153/W/ANRLMP/19 / Rural Agriculture and Forest- Under Single Stage - One Roads Spot Improvement - IDA / 58550 Based Value Chain Post Request for Bids Open - National 0.00 Implementati 2019-05-01 2019-04-01 2019-05-06 2019-06-17 2019-05-23 2019-07-17 2019-09-20 2019-08-21 2020-04-17 Envelope Nampula Province Development on 151/W/ANRLMP/19 / Rural Agriculture and Forest- Under Single Stage - One Roads Spot Improvement - IDA / 58550 Based Value Chain Post Request for Bids Open - National 0.00 Implementati 2019-05-01 2019-04-25 2019-05-06 2019-06-17 2019-05-29 2019-07-17 2019-08-21 2020-04-17 Envelope Zambezia Province Development on 156/W/ANRLMP/19 / Agriculture and Forest- Pending Rehabilitation of existing Single Stage - One IDA / D1190 Based Value Chain Post Request for Bids Open - National 0.00 Implementati 2019-09-02 2019-09-09 2019-10-21 2019-11-20 2019-12-25 2020-12-24 Irrigation Schemes - Envelope Development on Nampula Province 157/W/ANRLMP/19 / Agriculture and Forest- Under Rehabilitation of existing Single Stage - One IDA / D1190 Based Value Chain Post Request for Bids Open - National 0.00 Implementati 2019-09-02 2019-04-25 2019-09-09 2019-10-21 2019-05-23 2019-11-20 2019-12-25 2020-06-22 Irrigation Schemes - Envelope Development on Zambezia Province GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Coordination and Single Stage - One 01/G/ANRLMP/16 / Vehicles IDA / Q9900 Post Request for Bids Open - National 255,031.59 Signed 2016-08-29 2016-08-29 2016-09-03 2016-10-15 2016-10-11 2016-11-14 2016-11-07 2017-03-20 2016-12-30 2017-09-16 Management Envelope Page 1 Securing Land Tenure 10/G/ANRLMP/16 / Satelite Single Stage - One IDA / 58550 Rights and Increasing Prior Request for Bids Open - National 0.00 Canceled 2016-11-01 2016-11-07 2016-12-20 2017-01-19 2017-02-23 2017-08-22 picture aquisition Envelope Natural Resources Resilience 6/G/ARLNMP/16 / IT Project Coordination and Single Stage - One IDA / 58550 Post Request for Bids Open - National 133,711.91 Signed 2017-03-30 2017-04-04 2017-05-16 2017-10-27 2017-06-15 2017-11-13 2017-10-19 2017-11-30 2018-02-12 Equipament Management Envelope Pending 09/G/ARLNMP/16 / Office Project Coordination and Request for Single Stage - One IDA / D1190 Post Open - National 0.00 Implementati 2017-04-04 2017-05-30 2017-11-26 Supplies Management Quotations Envelope on Pending 60/G/ANRLMP/2016 / Office Project Coordination and Request for Single Stage - One IDA / Q9900 Post Limited 0.00 Implementati 2016-12-14 2017-02-08 2017-08-07 Suplies Management Quotations Envelope on 73/G/ANRLMP/17 / Aquisition for tractors and Agriculture and Forest- Single Stage - One accessories for Small IDA / D1190 Based Value Chain Post Request for Bids Open - National 952,461.70 Signed 2017-05-19 2017-05-23 2017-05-24 2017-07-05 2017-06-22 2017-08-04 2017-08-01 2017-09-08 2017-09-11 2018-03-07 Envelope Emerging Commercial Development Farmers 71/G/ANRLMP/17 / IT Project Coordination and Request for Single Stage - One Equipament for Matching IDA / D1190 Post Limited 24,285.55 Signed 2017-06-08 2017-06-12 2017-06-29 2017-06-22 2017-12-26 Management Quotations Envelope Grant Unit Securing Land Tenure 07/G/ARLNMP/16 / Single Stage - One IDA / D1190 Rights and Increasing Post Request for Bids Open - National 51,789.28 Signed 2017-10-02 2017-08-16 2017-10-09 2017-11-21 2017-10-27 2017-12-21 2017-11-17 2018-01-25 2017-11-30 2018-07-24 Motorcycles Envelope Natural Resources Resilience 86/G/ANRLMP/17 / Agriculture and Forest- Motorcycle for production Request for Single Stage - One IDA / D1190 Based Value Chain Post Open - National 79,226.22 Signed 2017-11-27 2018-01-22 2017-10-23 2018-07-21 officer and market Quotations Envelope Development liaison/Zambezia Province 85/G/ANRLMP/17 / Agriculture and Forest- Request for Single Stage - One Acquisition of combine IDA / 58550 Based Value Chain Post Open - National 67,384.96 Signed 2017-12-13 2018-02-07 2017-11-13 2018-08-06 Quotations Envelope harvester/tresher Development Agriculture and Forest- 87/G/ANRLMP/17 / Request for Single Stage - One IDA / 58550 Based Value Chain Post Open - National 32,256.77 Signed 2017-12-20 2018-02-14 2017-11-03 2018-08-13 Acquisition Irrigation kits Quotations Envelope Development 72/G/ANRLMP/17 / IT Project Coordination and Request for Single Stage - One Equipament for Agriculture IDA / D1190 Post Limited 87,160.96 Signed 2018-03-21 2018-05-09 2018-05-16 2018-07-09 2018-11-12 Management Quotations Envelope Hidraulic/Irrigation team Project Coordination and Single Stage - One 08/ARLNMP/G/16 / Vehicles IDA / 58550 Post Request for Bids Open - National 0.00 Canceled 2017-10-31 2017-11-07 2017-12-19 2018-01-18 2018-05-24 2018-11-20 Management Envelope 94/G/ANRLMP/17 / Office Agriculture and Forest- Request for Single Stage - One Furniture for new staff for IDA / D1190 Based Value Chain Post Limited 28,910.86 Signed 2018-02-11 2018-04-13 2018-04-19 2018-05-25 2018-10-16 Quotations Envelope PIU nampula Development Agriculture and Forest- 93/G/ANRLMP/17 / Request for Single Stage - One IDA / D1190 Based Value Chain Post Limited 21,506.59 Signed 2018-02-12 2018-05-09 2018-04-09 2018-06-22 2018-10-06 Acquisition IT Equipment Quotations Envelope Development 95/G/ANRLMP/17 / Agriculture and Forest- Motorcycle for Production Request for Single Stage - One IDA / D1190 Based Value Chain Post Open - National 77,990.19 Signed 2018-02-06 2018-04-04 2017-10-23 2018-10-01 officer and market liaison - Quotations Envelope Development Nampula Province Page 2 113/G/ANRLMP/18 / Agriculture and Forest- Acquisition of plants for Request for Single Stage - One IDA / D1190 Based Value Chain Post Limited 20,186.61 Signed 2018-03-16 2018-02-27 2018-05-11 2018-02-28 2018-11-09 forest restoration for Quotations Envelope Development Nampula Province 111/G/ANRLMP/18 / Agriculture and Forest- Acquisition of Plants for Request for Single Stage - One IDA / D1190 Based Value Chain Post Limited 30,344.83 Signed 2018-01-30 2018-01-18 2018-03-27 2018-01-31 2018-09-24 Forest Restoration at Quotations Envelope Development Zambezia Province 92/G/ANRLMP/17 / Vehicles Agriculture and Forest- Single Stage - One for PIU/Nampula and IDA / D1190 Based Value Chain Post Request for Bids Open - National 234,333.75 Signed 2018-03-15 2018-04-02 2018-03-26 2018-05-08 2018-05-02 2018-06-07 2018-04-25 2018-07-12 2018-06-06 2019-01-08 Envelope Zambezia Provinces Development 114/G/ANRLMP/18 / Aquisition of seedlings for Agriculture and Forest- Single Stage - One restoration of degraded areas IDA / D1190 Based Value Chain Post Request for Bids Limited 100,693.60 Signed 2018-07-02 2018-07-02 2018-07-18 2018-07-12 2018-09-06 2018-08-09 2018-10-16 2018-08-31 2018-11-20 2018-09-04 2019-11-20 Envelope in the Provinces of Nampula Development and Zambezia 128/G/ANRLM/18 / Printing Project Coordination and Request for Single Stage - One of the project Pogress report- IDA / D1190 Post Limited 28,255.62 Signed 2018-11-06 2018-11-08 2019-01-01 2018-11-29 2019-07-01 Management Quotations Envelope First Production cycle report 91/G/ANRLMP/17 / Agriculture and Forest- Acquisition for Trucks for Single Stage - One IDA / D1190 Based Value Chain Post Request for Bids Open - National 0.00 Canceled 2018-10-31 2018-11-12 2018-12-31 2019-01-30 2019-03-06 2019-09-02 Emerging Commercial Envelope Development Farmers 89/G/ANRLMP/17 / Agriculture and Forest- Acquisition for tractor for Single Stage - One IDA / D1190 Based Value Chain Post Request for Bids Open - National 0.00 Canceled 2018-10-31 2018-11-08 2018-12-20 2019-01-21 2019-02-25 2019-08-26 Small Emerging Commercial Envelope Development Farmers 90/G/ANRLMP/17 / Acquisition of Agricultural Agriculture and Forest- Single Stage - One implements and trailers for IDA / D1190 Based Value Chain Post Request for Bids Open - National 0.00 Canceled 2018-09-03 2018-09-08 2018-10-22 2018-11-21 2018-12-26 2019-06-24 Envelope Small Emerging Commercial Development Farmers 05/G/ARLNMP/16 / IT Project Coordination and Request for Single Stage - One IDA / D1190 Post Open - National 0.00 Canceled 2018-04-09 2018-06-04 2018-12-05 Equipament Management Quotations Envelope 154-1/CER/NCS/ANRLMP/19 / Hiring Service Provider to Contingency Emergency UN Agencies execute the Agricultural and IDA / D1190 Prior Direct 10,000,000.00 Signed 2019-05-03 2019-05-08 2019-06-12 2019-05-07 2019-12-09 Response (Direct) Livestock Recovery Plan post cyclone IDAI 61/G/ANRLMP/17 / IT Securing Land Tenure Pending Equipment for revitalization Single Stage - One IDA / 58550 Rights and Increasing Post Request for Bids Open - National 0.00 Implementati 2020-02-27 2020-03-05 2020-04-16 2020-05-17 2020-06-21 2020-12-18 of the data center in the Envelope Natural Resources Resilience on field of institutional support 63/G/ANRLMP/17 / Securing Land Tenure Pending Single Stage - One Equipment for datacenter IDA / 58550 Rights and Increasing Post Request for Bids Open - National 0.00 Implementati 2020-03-02 2020-03-09 2020-04-21 2020-05-21 2020-06-25 2020-12-22 Envelope revitalization Natural Resources Resilience on 62/G/ANRLMP/17 / Office Securing Land Tenure Pending Request for Single Stage - One furniture in the scope of IDA / 58550 Rights and Increasing Post Limited 0.00 Implementati 2020-02-01 2020-03-28 2020-09-24 Quotations Envelope institutional support Natural Resources Resilience on NON CONSULTING SERVICES Page 3 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Securing Land Tenure 10/NC/ANRLMP/16 / Single Stage - One IDA / 58550 Rights and Increasing Prior Request for Bids Open - National 621,474.24 Signed 2016-11-01 2016-10-13 2016-11-04 2016-10-27 2016-12-16 2016-11-15 2017-01-16 2017-01-30 2017-02-20 2017-05-17 2017-08-19 Satelite Picture Aquisition Envelope Natural Resources Resilience 21/NC/ANRLMP/16 / Hiring Project Coordination and Request for Single Stage - One a company to create the IDA / D1190 Post Open - National 0.00 Canceled 2016-10-16 2016-12-11 2017-06-09 Management Quotations Envelope slogan, website, logo. 83/NCS/ANRLMP/17 / Project Coordination and Request for Single Stage - One IDA / D1190 Post Open - National 43,882.07 Signed 2017-10-09 2017-12-04 2017-10-24 2018-06-02 Translation Service Management Quotations Envelope 20/NC/ANRLMP/16 / Hiring company to advertise Project Coordination and Request for Single Stage - One material supply (Posters, IDA / D1190 Post Open - National 0.00 Canceled 2018-02-28 2018-04-25 2019-04-25 Management Quotations Envelope Printing, Flyers and other placartes) 123/NC/ANRLMP/18 / Acquisition of Aerial Images Securing Land Tenure Open - Single Stage - One for Systematic Land IDA / 58550 Rights and Increasing Prior Request for Bids 0.00 Canceled 2018-08-30 2018-09-11 2018-10-23 2018-11-22 2018-12-27 2021-12-11 International Envelope Regularization in Zambezia Natural Resources Resilience and Nampula provinces 124/NC/ANRLMP/18 / Acquisition of Aerial Images Securing Land Tenure Open - Single Stage - One for Systematic Land IDA / 58550 Rights and Increasing Post Request for Bids 0.00 Canceled 2018-08-10 2018-08-13 2018-08-15 2018-09-26 2018-09-12 2018-10-26 2018-10-18 2018-11-30 2019-05-29 International Envelope Regularization in Zambezia Natural Resources Resilience and Nampula provinces 154/CER/NCS/ANRLMP/19 / Hiring Service Provider to Contingency Emergency UN Agencies execute the Agricultural and IDA / D1190 Prior Direct 0.00 Canceled 2019-04-24 2019-04-29 2019-06-03 2020-01-29 Response (Direct) Livestock Recovery Plan post cyclone IDAI 124/NC/ANRLMP/18-2 / Aerial Images for Systematic Securing Land Tenure Open - Single Stage - One Regularization of Lands in IDA / 58550 Rights and Increasing Post Request for Bids 780,000.00 Signed 2019-08-22 2018-08-13 2019-08-27 2019-10-08 2018-09-12 2019-11-07 2018-10-18 2019-12-12 2019-01-31 2020-06-09 International Envelope the Provinces of Nampula Natural Resources Resilience and Zambézia. 163/NCS/ANRLMP/19 / Pending Project Coordination and Request for Single Stage - One Renovation of project design IDA / D1190 Post Limited 0.00 Implementati 2020-01-20 2020-03-16 2020-09-12 Management Quotations Envelope software licenses on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 18/ARLNMP/C/16 / Design Securing Land Tenure Quality And Cost- Open - and Supervision of Irrigation IDA / 58550 Rights and Increasing Prior 0.00 Canceled 2016-08-08 2016-12-14 2016-08-29 2016-10-12 2016-11-09 2016-12-09 2017-01-13 2017-02-17 2018-02-17 Based Selection International Schemes (Rehabilitation) Natural Resources Resilience 19/CS/ANRLMP/16 / Service Securing Land Tenure Quality And Cost- Open - Provider for Sistematic IDA / 58550 Rights and Increasing Prior 6,310,924.41 Signed 2016-08-26 2016-09-30 2016-09-01 2016-09-27 2017-01-09 2016-10-25 2017-03-14 2016-11-24 2017-04-15 2016-12-29 2017-10-04 2017-02-02 2017-10-06 2018-02-02 Based Selection International community land delimitation Natural Resources Resilience Page 4 Agriculture and Forest- Consultant 14-CS/ANRLMP/16 / River Open - IDA / 58550 Based Value Chain Prior Qualification 0.00 Canceled 2016-08-16 2016-09-06 2016-10-20 2016-11-19 2016-12-22 2017-10-30 basin Studies International Development Selection Agriculture and Forest- Consultant 15-CS/ANRLMP/16 / River Open - IDA / 58550 Based Value Chain Prior Qualification 0.00 Canceled 2016-08-16 2016-09-06 2016-10-20 2016-11-21 2016-12-26 2017-06-24 basin studies International Development Selection Agriculture and Forest- 14/CS/ANRLMP/16 / River Quality And Cost- Open - IDA / D1190 Based Value Chain Prior 788,705.62 Signed 2016-08-29 2016-09-28 2016-09-19 2016-11-02 2016-12-07 2016-11-30 2017-02-16 2016-12-30 2017-04-06 2017-02-03 2017-08-24 2017-03-10 2017-09-06 2018-03-10 Basin Studies Based Selection International Development Agriculture and Forest- 15/CS/ANRLMP/16 / River Quality And Cost- Open - IDA / D1190 Based Value Chain Prior 819,643.12 Signed 2016-08-29 2016-09-29 2016-09-19 2016-11-02 2016-12-07 2016-11-30 2017-02-16 2016-12-30 2017-03-30 2017-02-03 2017-08-24 2017-03-10 2017-09-06 2018-03-10 Basin Studies Based Selection International Development 18/CS/ANRLMP/16 / Service Securing Land Tenure Consultant Open - Provider for systematic IDA / 58550 Rights and Increasing Prior Qualification 0.00 Canceled 2016-08-16 2016-09-06 2016-10-22 2016-11-21 2016-12-26 2017-06-24 International community land delimitation Natural Resources Resilience Selection 32-CS/ANRLMP/16 / Project Coordination and Quality And Cost- IDA / Q9900 Post Open - National 0.00 Canceled 2016-08-30 2016-08-29 2016-09-20 2016-11-03 2016-12-01 2017-01-01 2017-02-05 2017-03-12 2018-03-12 Baseline Survey Management Based Selection 32/CS/ANRLMP/16 / Project Coordination and Quality And Cost- Open - IDA / Q9900 Prior 345,948.67 Signed 2016-10-06 2016-09-30 2016-10-27 2016-10-06 2016-12-09 2017-03-20 2017-01-06 2017-04-21 2017-02-06 2017-07-10 2017-03-13 2018-01-29 2017-04-17 2018-03-12 2018-04-17 Baseline Sutudy Management Based Selection International 21/CS/ANRLMP/16 / Hiring Consultant Project Coordination and a company to create the IDA / D1190 Post Qualification Open - National 0.00 Canceled 2016-10-10 2016-10-31 2016-12-14 2017-01-14 2017-02-18 2017-08-17 Management slogan, website,logo Selection MZ-UGFI-4758-CS-QCBS / Agriculture and Forest- Hire service provider to Quality And Cost- Open - IDA / D1190 Based Value Chain Prior 436,412.61 Signed 2017-01-16 2017-01-25 2017-02-06 2017-02-01 2017-03-22 2017-05-09 2017-04-19 2017-06-23 2017-05-19 2017-08-01 2017-06-26 2018-01-29 2017-07-31 2018-03-13 2018-07-31 administer the partial credit Based Selection International Development guarantee scheme 11/CS/ANRLMP/16 / Service Agriculture and Forest- Quality And Cost- Open - Provider for Value Chain IDA / D1190 Based Value Chain Prior 0.00 Canceled 2016-08-26 2016-08-31 2016-09-16 2016-10-30 2016-12-27 2016-11-27 2017-03-07 2016-12-27 2017-04-15 2017-01-31 2017-10-13 2017-03-07 2018-03-07 Based Selection International development Development 97/CS/ANRLMP/17 / Service Agriculture and Forest- Quality Based Open - Provider for Quality Control IDA / D1190 Based Value Chain Prior 1,811,368.75 Signed 2017-12-11 2018-02-07 2018-01-08 2018-02-14 2018-02-27 2018-06-15 2018-03-27 2018-07-18 2018-04-26 2018-08-23 2018-05-28 2018-10-26 2018-07-02 2018-10-29 2020-07-01 Selection International and Finance Development 12/CS/ANRLMP/16 / Service Agriculture and Forest- Quality And Cost- Open - Provider-Restauration of IDA / 58550 Based Value Chain Prior 0.00 Canceled 2017-01-16 2017-02-06 2017-03-22 2017-04-19 2017-05-19 2017-06-23 2017-07-28 2018-07-28 Based Selection International degraded land Development 130/CQS/ANRLMP/18 / Provision of service for Agriculture and Forest- Consultant training young people in IDA / 58550 Based Value Chain Post Qualification Open - National 0.00 Canceled 2019-02-01 2019-02-22 2019-04-08 2019-05-08 2019-06-12 2019-12-09 sustainable entrepreneurship Development Selection in agribusiness INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual 38/IC/ANRLMP/16 / Project Coordination and IDA / 58550 Post Consultant Open 60,000.00 Signed 2016-10-19 2016-08-29 2016-12-07 2017-01-18 2016-12-28 2017-01-24 2017-02-01 2017-02-01 2017-07-31 Matching Grants Manager Management Selection Page 5 41/IC/ANRLMP/16 / Individual Project Coordination and Financial and Admnistrative IDA / 58550 Post Consultant Open 36,000.00 Signed 2016-10-19 2017-02-28 2016-12-07 2017-04-18 2016-12-28 2017-04-20 2017-02-01 2017-04-21 2017-07-31 Management Officer Selection 53/IC/ANRLMP/16 / Individual Project Coordination and Administrative and Financial IDA / Q9900 Post Consultant Open 7,200.00 Signed 2017-12-26 2017-05-19 2018-02-13 2017-08-25 2018-03-06 2017-08-25 2018-04-10 2017-08-30 2018-10-07 Management Assistant Selection Individual 36/IC/ANRLMP/16 / Finance Project Coordination and IDA / Q9900 Prior Consultant Open 0.00 Canceled 2017-02-13 2017-08-28 2017-04-03 2017-04-24 2017-05-29 2018-11-20 Assistant Management Selection 40/IC/ANRLMP/16 / Individual Project Coordination and Technical Advisor for IDA / 58550 Post Consultant Open 48,000.00 Signed 2017-02-14 2017-02-27 2017-04-04 2017-04-18 2017-04-25 2017-04-20 2017-05-30 2017-05-01 2018-11-21 Management Matching Grant Selection 47/IC/ANRLMP/16 / Individual Project Coordination and Administrative and Financial IDA / Q9900 Post Consultant Open 0.00 Canceled 2018-02-14 2018-04-04 2018-04-25 2018-05-30 2019-11-21 Management Assistant Selection 39/IC/ANRLMP/16 / Individual Project Coordination and Technical Advisor for IDA / 58550 Post Consultant Open 48,000.00 Signed 2017-02-14 2017-02-27 2017-04-04 2017-04-18 2017-04-25 2017-04-20 2017-05-30 2017-04-21 2018-11-21 Management Matching Grant Selection Individual CS23 / Procurement Project Coordination and IDA / Q9900 Prior Consultant Open - National 0.00 Canceled 2016-07-13 2016-07-13 2016-08-31 2016-09-21 2016-10-26 2018-06-30 Specialist Management Selection Individual 74/IC/ANRLMP/17 / Project Project Coordination and IDA / D1190 Post Consultant Open 0.00 Canceled 2017-06-05 2017-06-02 2017-06-19 2017-06-19 2017-07-10 2018-01-06 Coordinator for ANRLMP Management Selection 65/IC/ANRLMP/17 / Senior Individual Project Coordination and Agricultural Hidraulics IDA / D1190 Post Consultant Open 81,000.00 Canceled 2017-04-05 2017-04-25 2017-05-01 2017-07-07 2017-05-08 2017-07-17 2017-06-05 2017-08-15 2017-12-02 Management Specialist Selection Individual 23/IC/ANRLMP/16 / Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-05-30 2017-07-18 2017-08-08 2017-09-12 2018-03-11 National Coordinator Management Selection 29/IC/ANRLMP/16 / Individual Project Coordination and Environmental/Resilience IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Management Specialist Selection Individual 26/IC/ANRLMP/16 / Rural Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Development Specialist Management Selection Individual 31/IC/ANRLMP/16 / Project Coordination and IDA / Q9900 Prior Consultant Open 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Procurement Manager Management Selection Individual 27/IC/ANRLMP/16 / Land Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Administration Specialist Management Selection 52/IC/ANRLMP/16 / Natural Individual Project Coordination and Resaurce Specialist Field IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Operator Selection Individual 35/IC/ANRLMP/16 / Project Coordination and IDA / Q9900 Prior Consultant Open 0.00 Canceled 2017-12-29 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Procurement Assistant Management Selection Page 6 Individual 42/IC/ANRLMP/16 / Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-08-02 2017-09-20 2017-10-11 2017-11-15 2018-05-14 Provincial Coordinator Management Selection Individual 33/IC/ANRLMP/16 / Project Coordination and IDA / Q9900 Prior Consultant Open 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Procurement Assistant Management Selection Individual 37/IC/ANRLMP/16 / M&E Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-05-02 2017-05-19 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Specialist Management Selection Individual 25/IC/ANRLMP/16 / Value Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 Chain Specialist Management Selection Individual 30/IC/ANRLMP/16 / GIS Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-07-03 2017-08-21 2017-09-11 2017-10-16 2018-04-14 Specialist Management Selection Individual 28/IC/ANRLMP/16 / Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-10-04 2017-11-22 2017-12-13 2018-01-17 2018-07-16 Communication Specialist Management Selection Individual 51/IC/ANRLMP/16 / Land Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Specialist Field Operator Management Selection 50/IC/ANRLMP/16 / Value Individual Project Coordination and Chain Specialist Field IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Operator Selection 49/IC/ANRLMP/16 / Individual Project Coordination and Infraestruture Specialist IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Field Operator Selection 44/IC/ANRLMP/16 / Value Individual Project Coordination and Chain Specialist Field IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Operator Selection Individual 48/IC/ANRLMP / Provincial Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-08-02 2017-09-20 2017-10-11 2017-11-15 2018-05-14 Coordinator Management Selection 46/IC/ANRLMP/16 / Natural Individual Project Coordination and Resaurce Specialist Field IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Operator Selection Individual 45/IC/ANRLMP/16 / Land Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Specialist Field Operator Management Selection 35/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Prior Direct Selection Direct 104,000.00 Signed 2017-05-30 2017-06-22 2017-06-09 2018-06-22 2017-08-14 2017-06-01 2019-08-04 Procurement Assistant Management 37/SS/ANRLMP/17 / M&E Project Coordination and IDA / D1190 Post Direct Selection Direct 120,000.00 Signed 2017-05-29 2017-06-01 2017-06-08 2017-05-19 2017-08-12 2017-06-01 2019-08-02 Specialist Management 48/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Post Direct Selection Direct 120,000.00 Signed 2017-06-30 2017-06-22 2017-07-10 2017-08-14 2017-09-13 2017-08-24 2019-09-03 Provincial Coordinator Management 29/SS/ANRLMP/17 / Project Coordination and Environment and Social IDA / D1190 Post Direct Selection Direct 144,000.00 Signed 2017-05-29 2017-06-01 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 Management Safeguards Specialist Page 7 31/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Prior Direct Selection Direct 130,000.00 Signed 2017-05-29 2017-06-05 2017-06-12 2017-06-22 2017-08-16 2017-06-01 2019-08-06 Procurement Manager Management 24/SS/ANRLMP/17 / Natural Project Coordination and resaurces and forestry IDA / D1190 Post Direct Selection Direct 144,000.00 Signed 2017-05-29 2017-06-01 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 Management Specialist 27/SS/ANRLMP/17 / Land Project Coordination and IDA / D1190 Post Direct Selection Direct 144,000.00 Signed 2017-05-29 2017-06-02 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 Administration Specialist Management 28/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Post Direct Selection Direct 144,000.00 Signed 2017-07-05 2017-06-01 2017-07-17 2017-08-31 2017-09-20 2017-09-04 2019-09-10 Communications Specialist Management 26/SS/ANRLMP/17 / Rural Project Coordination and IDA / D1190 Post Direct Selection Direct 144,000.00 Signed 2017-05-29 2017-06-01 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 Development Specialist Management 30/SS/ANRLMP/17 / GIS Project Coordination and IDA / D1190 Post Direct Selection Direct 96,000.00 Signed 2017-07-05 2017-06-05 2017-07-17 2017-09-18 2017-09-20 2017-09-26 2019-09-10 Specialist Management 33/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Prior Direct Selection Direct 96,000.00 Signed 2017-11-15 2018-03-11 2017-11-27 2018-03-15 2018-01-31 2018-02-02 2020-01-21 Procurement Assistant Management 51/SS/ANRLMP/17 / Land Project Coordination and Administration Specialist IDA / D1190 Post Direct Selection Direct 84,000.00 Signed 2018-08-15 2017-06-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2019-04-29 Management Field Operator 44/SS/ANRLMP/17 / Value Project Coordination and Chain Specialist Field IDA / D1190 Post Direct Selection Direct 84,000.00 Signed 2018-08-15 2017-05-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Operator 49/SS/ANRLMP/17 / Project Coordination and Infraestruture Specialist IDA / D1190 Post Direct Selection Direct 84,000.00 Signed 2018-08-15 2017-05-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Field Operator 52/SS/ANRLMP/17 / Natural Project Coordination and Resaurces and Forestry IDA / D1190 Post Direct Selection Direct 84,000.00 Signed 2018-08-15 2017-06-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Specialist Field Operator 45/SS/ANRLMP/17 / Land Project Coordination and Administration Specialist IDA / D1190 Post Direct Selection Direct 84,000.00 Signed 2018-08-15 2017-05-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Field Operator 46/SS/ANRLMP/17 / Natural Project Coordination and Resaurces and Forestry IDA / D1190 Post Direct Selection Direct 84,000.00 Signed 2018-08-15 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Specialist Field Operator 50/SS/ANRLMP/17 / Value Project Coordination and Chain Specialist Field IDA / D1190 Post Direct Selection Direct 84,000.00 Signed 2018-08-15 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Operator 43/SS/ANRLMP/17 / Project Coordination and Infraestruture Specialist IDA / D1190 Post Direct Selection Direct 84,000.00 Signed 2018-08-15 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 Management Field Operator 23/SS/ANRLMP/17 / Project Coordination and Under IDA / D1190 Post Direct Selection Direct 0.00 2017-05-29 2017-06-01 2017-06-12 2017-08-16 2019-08-06 National Coordinator Management Implementation 17/IC/ANRLMP/16 / Securing Land Tenure Individual Facilitation of the IDA / 58550 Rights and Increasing Post Consultant Open 0.00 Canceled 2017-03-10 2017-05-01 2017-05-22 2017-06-26 2017-09-24 development of a Common Natural Resources Resilience Selection Landscape Vision Page 8 Individual 24/IC/ANRLMP/16 / Forest Project Coordination and IDA / Q9900 Post Consultant Open 0.00 Canceled 2017-05-01 2017-06-19 2017-07-10 2017-08-14 2018-02-10 Specialist Management Selection 34/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Post Direct Selection Direct 120,000.00 Signed 2017-07-31 2017-02-27 2017-08-14 2017-03-13 2017-10-18 2017-03-23 2019-08-09 Financial Manager Management 69/IC/ANRLMP/17 / Individual Project Coordination and Environmental and Social IDA / D1190 Post Consultant Open 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 Management Safeguard Specialist Selection Individual 68/IC/ANRLMP/17 / GIS Project Coordination and IDA / D1190 Post Consultant Open 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 Specialist Management Selection Individual 67/IC/ANRLMP/17 / Project Coordination and IDA / D1190 Post Consultant Open 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 Topographer Management Selection 76/IC/ANRLMP/17 / Individual Project Coordination and safeguard social and IDA / D1190 Post Consultant Open 50,400.00 Signed 2017-10-02 2017-09-27 2017-12-04 2017-12-21 2017-12-25 2017-12-21 2018-01-29 2017-12-28 2018-07-28 Management environmental specialist Selection 77/IC/ANRLMP/17 / Agriculture and Forest- Individual Agribusiness Expert (Member IDA / D1190 Based Value Chain Post Consultant Open 2,400.00 Signed 2017-09-24 2017-11-01 2017-09-26 2017-11-15 2017-09-27 2017-12-20 2017-09-28 2018-06-18 of Investiment Committee) Development Selection 78/IC/ANRLMP/17 / Agriculture and Forest- Individual Agribusiness Community IDA / D1190 Based Value Chain Post Consultant Open 2,400.00 Signed 2017-09-24 2017-09-12 2017-10-30 2017-09-26 2017-11-14 2017-09-27 2017-12-19 2017-09-28 2018-06-17 representative (Member of Development Selection the Investiment Committee) 82/CS/ANRLMP/17 / Agriculture and Forest- Supervision for works of IDA / D1190 Based Value Chain Post Direct Selection Direct 69,301.25 Signed 2017-10-20 2017-12-19 2017-10-30 2018-06-06 2018-01-03 2018-03-30 2018-07-02 rural roads spot Development improvement/Zambezia 81/CS/ANRLMP/17 / Agriculture and Forest- Supervision for works of IDA / D1190 Based Value Chain Post Direct Selection Direct 31,302.14 Signed 2017-10-20 2017-12-19 2017-10-30 2018-01-03 2018-03-30 2018-07-02 Rural roads spot Development improvement/Nampula 96/IC/ANRLMP/17 / Hiring a consultant to support Agriculture and Forest- MSME to develop Business IDA / D1190 Based Value Chain Post Direct Selection Direct 98,784.00 Signed 2017-11-29 2017-12-04 2017-12-11 2017-12-14 2018-02-14 2018-02-28 2018-08-13 Plans for Non-timber Forest Development Products in Nampula and Zambezia Provinces 98/IC/ANRLMP/17 / Agriculture and Forest- Individual Specialist in Business IDA / D1190 Based Value Chain Post Consultant Open 92,400.00 Signed 2017-11-30 2017-12-04 2018-01-20 2017-12-29 2018-02-12 2018-01-05 2018-03-19 2018-01-19 2020-03-18 Development Development Selection Agriculture and Forest- Individual 99/IC/ANRLMP/17 / IDA / D1190 Based Value Chain Post Consultant Open 92,400.00 Signed 2017-11-30 2017-12-04 2018-01-22 2017-12-29 2018-02-12 2018-01-05 2018-03-19 2018-01-19 2020-03-18 Knowledge transfer Specialist Development Selection 101/IC/ANRLMP/17 / Agriculture and Forest- Individual Financial IDA / D1190 Based Value Chain Post Consultant Open 66,000.00 Signed 2017-11-30 2017-12-04 2018-01-22 2018-01-29 2018-02-12 2018-01-05 2018-03-19 2018-01-19 2020-03-18 administration/Nampula Development Selection Province 102/IC/ANRLMP/17 / Agriculture and Forest- Individual Financial IDA / D1190 Based Value Chain Post Consultant Open 66,000.00 Signed 2017-11-30 2017-12-04 2018-01-22 2017-12-29 2018-02-12 2018-01-15 2018-03-19 2018-01-19 2020-03-18 administration/Zambezia Development Selection Province Page 9 103/IC/ANRLMP/17 / Agriculture and Forest- Individual Accountants (3 for Nampula IDA / D1190 Based Value Chain Post Consultant Open 51,921.60 Signed 2017-11-30 2017-12-04 2018-01-22 2018-05-14 2018-02-12 2018-05-17 2018-03-19 2018-05-29 2020-03-18 Province and 3 for Zambezia Development Selection Province) 104/IC/ANRLMP/17 / Provincial Assistant of Value Agriculture and Forest- Individual Chain IDA / D1190 Based Value Chain Post Consultant Open 84,000.00 Signed 2017-12-20 2018-02-07 2017-12-29 2018-02-28 2018-01-05 2018-04-04 2018-01-19 2018-10-01 Implementation/Nampula Development Selection Province 105/IC/ANRLMP/17 / Provincial Assistant of Value Agriculture and Forest- Individual Chain IDA / D1190 Based Value Chain Post Consultant Open 84,000.00 Signed 2017-12-20 2018-02-07 2017-12-29 2018-02-28 2018-01-05 2018-04-04 2018-01-19 2018-10-01 Implementation/Zambezia Development Selection Province 80/IC/ANRLMP/17 / Agriculture and Forest- Individual Elaboration of the IDA / D1190 Based Value Chain Post Consultant Open 0.00 Canceled 2018-01-31 2018-03-21 2018-04-11 2018-05-16 2018-11-12 Warehouse Construction Development Selection Project for the PACES Individual 66/IC/ANRLMP/17 / Civil Project Coordination and IDA / D1190 Post Consultant Open 0.00 Canceled 2018-02-01 2018-03-26 2018-04-16 2018-05-21 2020-05-10 Engineer Management Selection 84/IC/ANRLMP/17 / Agriculture and Forest- Individual Supervision of Warehouse IDA / D1190 Based Value Chain Post Consultant Open 0.00 Canceled 2018-02-01 2018-03-26 2018-04-16 2018-05-21 2018-11-17 Construction Development Selection 42/SS/ANRLMP/17 / Project Coordination and IDA / D1190 Post Direct Selection Direct 120,000.00 Signed 2017-06-30 2017-06-22 2017-07-10 2017-08-14 2017-09-13 2017-08-24 2019-09-03 Provincial Coordinator Management Individual 34/IC/ANRLMP/16 / Finance Project Coordination and IDA / Q9900 Prior Consultant Open 0.00 Canceled 2017-03-18 2017-03-23 2017-05-08 2017-05-29 2017-07-03 2017-12-30 Manager Management Selection 65/IC/ ANRLMP/17 / Senior Securing Land Tenure Individual Agricultural hidraulics IDA / D1190 Rights and Increasing Post Consultant Open 0.00 Canceled 2017-06-13 2017-08-01 2017-08-22 2017-09-26 2018-09-26 Specialist Natural Resources Resilience Selection 43/IC/ANRLMP/16 / Individual Project Coordination and Infraestruture Specialist IDA / Q9900 Post Consultant Open 0.00 Canceled 2018-04-09 2018-05-28 2018-06-18 2018-07-23 2019-01-19 Management Field Operator Selection 25/SS/ANRLMP/17 / Value Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 0.00 2017-11-01 2017-11-13 2018-01-17 2020-01-07 Chain Specialist Management Implementation 110/SS/ANRLMP/17 / Consultant for the Review of Agriculture and Forest- the Business Plans of the IDA / 58550 Based Value Chain Post Direct Selection Direct 12,160.00 Signed 2018-01-17 2018-01-26 2018-02-05 2017-12-27 2018-04-11 2018-02-28 2018-10-08 PACES of the Provinces of Development Nampula and Zambezia covered by PGIARN 118/SS/ANRLMP/18 / Project Coordination and Pending Administrative and financial IDA / 58550 Post Direct Selection Direct 0.00 2018-06-27 2018-07-09 2018-09-12 2020-09-11 Management Implementation assistant - Zambezia 83/IC/ANRLMP/17 / Securing Land Tenure Individual Supervision for works IDA / D1190 Rights and Increasing Post Consultant Open 15,074.38 Signed 2018-08-31 2018-08-17 2018-10-22 2018-07-31 2018-11-12 2018-11-21 2018-12-17 2018-11-21 2019-03-17 rehabilitation of the data Natural Resources Resilience Selection center in Nampula Province Page 10 124/IC/ANRLM/18 / Securing Land Tenure Individual Supervision for works IDA / D1190 Rights and Increasing Post Consultant Open 18,375.72 Signed 2018-08-31 2018-08-17 2018-10-22 2018-05-24 2018-11-12 2018-11-16 2018-12-17 2018-11-16 2019-03-17 rehabilitation of the data Natural Resources Resilience Selection center in Zambezia Province 126/SS/ANRLMP/18 / Project Coordination and Advisor for Institutional IDA / 58550 Post Direct Selection Direct 28,800.00 Signed 2018-08-31 2018-09-12 2018-09-11 2018-09-21 2018-09-20 2018-09-28 2019-03-19 Management Relations and Cooperation 127/IC/ANRLMP/18 / Individual Project Coordination and Operational Chief for IDA / 58550 Post Consultant Open 120,000.00 Signed 2018-09-20 2018-09-12 2018-11-12 2018-09-26 2018-12-03 2018-09-24 2019-01-07 2018-10-12 2020-12-27 Management ANRLMP Selection 117/SS/ANRLMP/18 / Project Coordination and Technical Adviser for IDA / 58550 Post Direct Selection Direct 0.00 Canceled 2018-06-27 2018-03-08 2018-07-09 2018-09-12 2019-09-12 Management Matching Grants Unit 116/SS/ANRLMP/18 / Project Coordination and Technical Adviser for IDA / 58550 Post Direct Selection Direct 0.00 Canceled 2018-06-27 2018-05-10 2018-07-09 2018-09-12 2019-09-12 Management Matching Grants Unit 115/SS/ANRLMP/18 / Project Coordination and Matching Grants Unit IDA / 58550 Post Direct Selection Direct 0.00 Canceled 2018-06-27 2018-07-09 2018-09-12 2019-03-11 Management Manager 122/SS/ANRLMP/18 / Project Coordination and Financial and Administrative IDA / 58550 Post Direct Selection Direct 0.00 Canceled 2018-08-30 2018-09-10 2018-11-14 2019-11-09 Management Officer (MGU) 149/IC/ANRLMP/19 / Individual Project Coordination and Executive Secretary for IDA / 58550 Post Consultant Open 18,000.00 Signed 2019-05-15 2019-03-28 2019-07-03 2019-06-19 2019-07-24 2019-06-19 2019-08-28 2019-07-24 2020-08-27 Management Zambezia Province Selection 150/IC/ANRLMP/19 / Individual Project Coordination and Platform Assistant for IDA / 58550 Post Consultant Open 6,000.00 Signed 2019-05-15 2019-03-28 2019-07-03 2019-07-31 2019-07-24 2019-08-02 2019-08-28 2019-08-02 2020-08-27 Management Zambezia Province Selection 148/IC/ANRLMP/19 / Individual Project Coordination and Under Platform Assistant for IDA / 58550 Post Consultant Open 0.00 2019-05-15 2019-03-28 2019-07-03 2019-07-24 2019-08-28 2020-08-27 Management Implementation Nampula Province Selection 146/SSS/ANRLMP/19 / Consultancy for the updating of the instruments of Project Coordination and IDA / 58550 Post Direct Selection Direct 16,100.00 Signed 2019-03-15 2019-03-15 2019-03-25 2019-03-19 2019-05-29 2019-05-27 2019-07-28 environmental and social Management safeguards for the ANRLMP- Additional Financing 147/IC/ANRLMP/19 / Individual Project Coordination and Under Executive Secretary for IDA / 58550 Post Consultant Open 0.00 2019-05-15 2019-03-28 2019-07-03 2019-07-24 2019-08-28 2020-02-24 Management Implementation Nampula Province Selection Individual 155/IC/ANRLMP/19 / Project Coordination and IDA / 58550 Prior Consultant Open 0.00 Canceled 2019-06-21 2019-05-30 2019-08-12 2019-07-31 2019-09-02 2019-10-07 2020-10-06 Procurement specialist Management Selection 160/SSS/ ANRLM/2019 / Project Coordination and IDA / D1190 Prior Direct Selection Direct 120,000.00 Signed 2019-08-06 2019-08-07 2019-08-20 2019-07-19 2019-10-24 2019-08-01 2021-10-13 Procurement Specialist II Management 161/SSS/ANRMP?2019 / Project Coordination and IDA / D1190 Prior Direct Selection Direct 96,000.00 Signed 2019-08-06 2019-08-07 2019-08-16 2019-07-19 2019-10-21 2019-08-01 2021-10-10 Procurement Specialist III Management Page 11 162/SS/ANRLMP/19 / Training of technicians and beneficiaries of the Securing Land Tenure Individual SUSTENTA Project on Under IDA / D5020 Rights and Increasing Post Consultant Limited 0.00 2019-10-31 2019-10-01 2019-11-05 2019-11-28 2019-11-26 2019-12-31 2020-06-28 restoration approach and Implementation Natural Resources Resilience Selection agroforestry systems in Nampula and Zambezia landscapes 119/SS/ANRLMP/18 / Recruitment of consultant to carry out Qualitative Project Coordination and evaluation of the Mid-term IDA / D1190 Post Direct Selection Direct 0.00 Canceled 2018-06-27 2018-07-11 2018-09-14 2018-09-29 Management Review Report of the SUSTAINABILITY Implementation 152/SSS/ANRLMP/19 / Agriculture and Forest- Recruitment of consultant to IDA / 58550 Based Value Chain Post Direct Selection Direct 0.00 Canceled 2019-05-23 2019-06-04 2019-08-08 2020-03-05 support the implementation Development of the Guarantee Fund 161/IC/ANRLMP/19 / Consultant for risk Individual assessment of gender based Project Coordination and IDA / D5020 Post Consultant Open 0.00 Canceled 2019-09-19 2019-09-19 2019-11-08 2019-11-29 2020-01-03 2020-04-01 violence at the Project area, Management Selection Additional Financing Project . 161-2/SSS/ANRLMP/19 / Consultant for risk Agriculture and Forest- Under assessment of gender based IDA / D5020 Based Value Chain Post Direct Selection Direct 0.00 2019-11-10 2019-11-10 2019-11-20 2020-01-24 2020-07-22 Implementation violence at the Project area, Development additional financing Project Individual 155/IC/ANRLMP/19-2 / Project Coordination and Under IDA / 58550 Prior Consultant Open 0.00 2019-12-09 2020-01-22 2020-01-30 2020-02-20 2020-03-26 2021-03-26 Procurement Specialist IV Management Implementation Selection 129/IC/ANRLMP/18 / Individual Project Coordination and Financial Administrative IDA / 58550 Post Consultant Open 0.00 Canceled 2018-11-15 2019-01-07 2019-01-28 2019-03-04 2020-03-03 Management Assistant/Zambezia Province Selection Page 12