PROCUREMENT PLAN (Textual Part) Project information: Honduras- Honduras Pilot Program For Climate Resilience Phase 1 Grant-P157795 Project Implementation agency: Invest-H Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. PROCUREMENT Honduras : Honduras Pilot Program for Climate Resilience Phase 1 Grant PLAN General Information Country: Honduras Bank’s Approval Date of the Original Procurement Plan: 2017-09-22 2020-02-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157795 GPN Date: Project Name: Honduras Pilot Program for Climate Resilience Phase 1 Grant Loan / Credit No: TF / A4893, / Executing Agency(ies): Inversión Estratégica de Honduras WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-INVEST-H-24892-GO- RFQ / Adquisición Equipo de Technical and Financial Solicitud de Single Stage - One Cómputo para la Unidad TF / A4893 Management of the Phase 1 Posterior Limited 14,000.00 62.13 Finalizado 2017-10-14 2017-11-23 2017-12-23 cotizaciones Envelope Técnica Implementadora of the PPCR PPCR y FIP. HN-INVEST-H-61083-GO- RFQ / Adquisiciones de Technical and Financial Equipo de Computo Solicitud de Single Stage - One TF / A4893 Management of the Phase 1 Posterior Limited 4,516.00 2,141.23 Finalizado 2018-05-11 2018-06-11 2018-06-29 Complementario (2 cotizaciones Envelope of the PPCR computadoras de escritorio y una Videocámara) HN-INVEST-H-24893-GO- RFQ / Adquisición de Technical and Financial Mobiliario para la Oficina de Solicitud de Single Stage - One TF / A4893 Management of the Phase 1 Posterior Limited 6,000.00 2,306.29 Finalizado 2017-10-17 2018-06-11 2018-06-25 la Unidad Técnica cotizaciones Envelope of the PPCR Implementadora del PPCR y FIP. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-INVEST-H-101568-NC- RFQ / Adquisición de Component 3: Design and servicios de imprenta y implementation of a publicitarios como ser- participatory consultation at Solicitud de Single Stage - One banners, bifolios, boletines, TF / A4893 Posterior Limited 4,468.00 2,647.77 Firmado 2019-03-08 2019-03-26 2019-06-24 an institutional level, in the cotizaciones Envelope gorras, lápices, bolsos, context of SPCR d carpetas, camisas, usb, evelopment llaveros, tarjetas de presentación, entre otros). CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-INVEST-H-24899-CS- Component 1: Risk analysis QCBS / Análisis de Riesgo to strengthen climate Selección basada para Mejorar las Políticas y / Posterior Open - National 125,000.00 0.00 Cancelado 2017-10-23 2017-11-13 2017-12-27 2018-01-24 2018-02-23 2018-03-16 2018-04-03 2019-04-03 resilience programs and en calidad y costo Programas de Resiliencia policies. Climática. HN-INVEST-H-24913-CS- QCBS / Revisión y Propuestas para Component 2:Information for Modernización del marco the design of policy reforms Selección basada / Posterior Open - National 170,000.00 0.00 Cancelado 2017-11-06 2017-11-20 2017-12-20 2017-12-25 2018-01-24 2018-02-08 2018-02-18 2018-05-19 Normativo en Cambio and for institutional en calidad y costo Climático y Temas Asociados strengthening y de Fortalecimiento Institucional. HN-INVEST-H-24898-CS- QCBS / Realización de Estudios Técnicos de Component 4: Formulation Prefactibilidad de las of the SPCR accompanying Selección basada Inversiones Estratégicas / strategic investment plan Posterior Open - National 220,000.00 0.00 Cancelado 2017-10-09 2017-10-30 2017-12-13 2018-01-12 2018-02-12 2018-03-05 2018-03-21 2018-09-17 en calidad y costo Prioritarias, de acuerdo con built under a participatory requerimientos definidos en process el SPCR y la cartera de proyectos. HN-INVEST-H-76921-CS- CQS / "Diseño de un Proyecto de Inversión para Component 2:Information for actualizar el Balance Hídrico Selección basada the design of policy reforms de Honduras e Implementar TF / A4893 Posterior en calificaciones Open - National 80,000.00 0.00 Cancelado 2018-09-12 2018-10-12 2018-11-21 2018-12-03 2018-12-14 2019-09-09 and for institutional un Sistema de Gestión de de consultores strengthening Información Integrado para su Actualización dinámica y Continua" HN-INVEST-H-76922-CS- CQS / Diseño de dos (2) Proyectos Piloto de Inversión para Fortalecer la Gobernanza del Recurso Component 2:Information for Selección basada Hídrico y Mejorar La the design of policy reforms TF / A4893 Posterior en calificaciones Open - National 30,000.00 0.00 Cancelado 2018-09-07 2018-09-11 2018-11-29 2018-12-18 2019-01-08 2019-07-23 Resiliencia Climática de la and for institutional de consultores Gestión de los Servicios de strengthening Agua Potable y Saneamiento en la Zona Periurbana del Municipio del Distrito Central HN-INVEST-H-76924-CS- Component 4: Formulation CQS / Fortalecimiento del of the SPCR accompanying Selección basada Uso y la Sostenibilidad del TF / A4893 strategic investment plan Posterior en calificaciones Open - National 30,000.00 0.00 Cancelado 2018-09-04 2018-10-11 2018-11-29 2018-12-18 2019-01-08 2019-06-12 Sistema de Información de built under a participatory de consultores Agua y Saneamiento Rural process de Honduras (SIASAR). HN-INVEST-H-76925-CS- CQS / Fortalecimiento, Sostenibilidad e Component 2:Information for Selección basada Institucionalización del the design of policy reforms TF / A4893 Posterior en calificaciones Open - National 30,000.00 0.00 Cancelado 2018-09-07 2018-11-06 2018-12-09 2018-12-26 2018-12-28 2019-07-20 Sistema de Registro Público and for institutional de consultores de los Prestadores de strengthening Servicios de Agua Potable y Saneamiento del ERSAPS. Page 2 HN-INVEST-H-76936-CS- CQS / Estudio para el Diseño de un Prog. de Obras Resilientes al Cambio Component 4: Formulation Climático Mediante Embalses of the SPCR accompanying Selección basada de Agua de uso Múltiple y TF / A4893 strategic investment plan Posterior en calificaciones Open - National 37,200.00 0.00 Cancelado 2018-09-18 2018-10-19 2018-11-21 2018-12-10 2018-12-21 2019-06-04 Regularización del Diseño, built under a participatory de consultores Const., Operación, process Mantenimiento y Admon de Cosechas de Agua Para uso de Riego, y Otros Usos HN-INVEST-H-72620-CS- CQS / Diseño de Proyectos Piloto de Inversión para la Mejora de la Resiliencia Component 2:Information for Climática de los Sistemas de Selección basada the design of policy reforms Agua Potable, Aguas TF / A4893 Posterior en calificaciones Open - National 50,000.00 0.00 Cancelado 2018-08-09 2018-08-23 2018-11-01 2018-11-30 2018-12-03 2019-06-17 and for institutional Residuales y Drenaje Pluvial de consultores strengthening en Ciudades Medias localizadas en el Corredor Seco y Corredor de Inundaciones del País. HN-INVEST-H-72621-CS- CQS / Diseño de un Proyecto de Inversión para la Implementación de un Component 4: Formulation Sistema Comunitario of the SPCR accompanying Selección basada Mejorado de Monitoreo y TF / A4893 strategic investment plan Posterior en calificaciones Open - National 45,000.00 0.00 Cancelado 2018-08-21 2018-09-11 2018-11-14 2018-12-10 2018-12-17 2019-06-20 Alerta Temprana de la built under a participatory de consultores Sequía y Elaboración del process Inventario de Mejores Prácticas de Conservación de Agua y Suelos en el Corredor Seco de Honduras. HN-INVEST-H-72702-CS- CQS / Desarrollo de una Metodología para la Evaluación de Riesgos Component 1: Risk analysis Selección basada Climáticos en Zonas to strengthen climate TF / A4893 Posterior en calificaciones Open - National 25,000.00 0.00 Cancelado 2018-09-12 2018-09-28 2018-11-05 2018-11-26 2018-12-17 2019-05-28 Productoras de Agua en resilience programs and de consultores Subcuencas Hidrográficas e policies. Identificación de Acciones Integrales para su Resiliencia Climática HN-INVEST-H-73289-CS- CQS / Fortalecimiento de la Component 1: Risk analysis Selección basada gestión de datos e to strengthen climate TF / A4893 Posterior en calificaciones Open - National 60,000.00 0.00 Cancelado 2018-08-28 2018-08-30 2018-10-10 2018-11-19 2018-11-27 2019-06-05 información meteorológica, resilience programs and de consultores climática e hidrométrica y policies. productos y servicios. HN-INVEST-H-101509-CS- Component 1: Risk analysis CQS / Elaboración del Plan Selección basada to strengthen climate Local de Adaptación al TF / A4893 Posterior en calificaciones Open - National 100,000.00 98,257.59 Firmado 2019-02-20 2019-02-25 2019-03-18 2019-03-28 2019-04-02 2019-08-02 resilience programs and Cambio Climático del de consultores policies. Distrito Central HN-INVEST-H-101513-CS- CQS / Diagnóstico rápido para identificar sitios potenciales para cosechas o Component 4: Formulation embalses de agua, of the SPCR accompanying Selección basada elaboración del inventario de TF / A4893 strategic investment plan Posterior en calificaciones Open - National 180,000.00 0.00 Cancelado 2019-02-22 2019-02-26 2019-03-20 2019-04-02 2019-04-10 2019-09-05 mejores prácticas de built under a participatory de consultores conservación de agua y process suelos, así como el diseño de un proyecto de inversión para la implementación de un Sistema Page 3 HN-INVEST-H-101518-CS- CQS / Estudio para la repotenciación de la Represa Component 2:Information for Coyolar y su contribución Selección basada the design of policy reforms para la seguridad hídrica y TF / A4893 Posterior en calificaciones Open - National 283,000.00 0.00 Cancelado 2019-02-22 2019-02-26 2019-03-20 2019-04-02 2019-04-10 2019-09-10 and for institutional seguridad alimentaria con de consultores strengthening enfoque de resiliencia climática para el Valle de Comayagua. HN-INVEST-H-110392-CS- CQS / Diseño y evaluación Component 4: Formulation de impactos y riesgos of the SPCR accompanying Selección basada ambientales y sociales de TF / A4893 strategic investment plan Posterior en calificaciones Open - National 300,000.00 299,185.65 Firmado 2019-04-15 2019-05-06 2019-05-22 2019-05-28 2019-05-30 2019-09-30 sistemas integrales de agua built under a participatory de consultores segura en cuencas process hidrográficas priorizadas del Corredor Seco de Honduras. HN-INVEST-H-124329-CS- CQS / Diagnóstico para ampliar la capacidad y eficiencia de la represa el Component 2:Information for coyolar para incrementar el Selección basada the design of policy reforms aprovechamiento del TF / A4893 Posterior en calificaciones Open - National 283,000.00 282,703.07 Firmado 2019-07-25 2019-08-12 2019-09-02 2019-09-17 2019-09-26 2019-12-31 and for institutional potencial productivo y de consultores strengthening energético que promuevan la adaptación al cambio climático en el valle de Comayagua. HN-INVEST-H-124353-CS- CQS / Elaboración de un estudio de evaluación de Component 4: Formulation impacto ambiental y social of the SPCR accompanying Selección basada preliminar y anteproyecto de TF / A4893 strategic investment plan Posterior en calificaciones Open - National 78,364.88 62,331.31 Firmado 2019-07-26 2019-07-30 2019-08-20 2019-08-28 2019-09-10 2019-11-11 plan de gestión ambiental y built under a participatory de consultores social para mejoras a la process represa José Cecilio del Valle. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Design and HN-INVEST-H-24901-CS- implementation of a INDV / Especialista en participatory consultation at TF / A4893 Posterior Individual Limited 50,000.00 34,409.16 Finalizado 2017-10-16 2017-10-26 2017-11-16 2017-11-27 2018-05-28 Procesos Participativos, an institutional level, in the Comunicación y Género. context of SPCR d evelopment HN-INVEST-H-24905-CS- INDV / Identificación de Limitantes Criticas en Component 3: Design and Materia de Comunicación y implementation of a Sensibilización de Actores a participatory consultation at / Posterior Individual Limited 30,000.00 0.00 Cancelado 2017-10-23 2017-11-02 2017-11-23 2017-12-04 2018-06-04 Nivel Institucional que an institutional level, in the dificultan el Entendimiento context of SPCR d de los Riesgos Climáticos y evelopment la Formulación de Acciones Prioritarias. Component 4: Formulation HN-INVEST-H-24906-CS- of the SPCR accompanying INDV / Coordinador General TF / A4893 strategic investment plan Posterior Individual Limited 50,000.00 41,782.56 Finalizado 2017-09-25 2017-10-05 2017-10-20 2017-11-02 2018-10-28 de PPCR y FIP. built under a participatory process Page 4 Component 1: Risk analysis HN-INVEST-H-24910-CS- to strengthen climate INDV / Especialista en TF / A4893 Posterior Individual Limited 12,000.00 11,060.11 Finalizado 2017-10-27 2017-11-06 2017-11-16 2017-11-27 2018-11-22 resilience programs and Logística policies. HN-INVEST-H-24911-CS- Technical and Financial INDV / Oficial de TF / A4893 Management of the Phase 1 Previa Individual Limited 54,000.00 27,305.48 Finalizado 2017-09-25 2017-10-05 2017-10-25 2017-11-07 2018-11-02 Adquisiciones of the PPCR Component 4: Formulation HN-INVEST-H-25449-CS- of the SPCR accompanying INDV / Enlace Técnico TF / A4893 strategic investment plan Posterior Individual Limited 60,000.00 34,409.16 Finalizado 2017-10-11 2017-10-23 2017-11-13 2017-11-29 2018-11-26 Miambiente/INVEST-H built under a participatory process HN-INVEST-H-24908-CS- INDV / Sub-Coordinador Component 4: Formulation Técnico del PPCR y Control of the SPCR accompanying de Calidad de los Estudios TF / A4893 strategic investment plan Posterior Individual Limited 60,000.00 36,866.96 Finalizado 2017-10-26 2017-11-07 2017-11-28 2017-12-08 2018-12-13 de Pre-factibilidad a las built under a participatory Inversiones Estratégicas process Propuestas. Component 4: Formulation HN-INVEST-H-73123-CS- of the SPCR accompanying Selección directa CDS / Auditoria Final para TF / A4893 strategic investment plan Posterior Direct 23,800.00 0.00 Cancelado 2018-09-17 2018-10-17 2018-11-14 2019-05-13 de consultores el PPCR y FIP built under a participatory process HN-INVEST-H-77045-CS- INDV / Estudio sobre la Component 4: Formulation ecoeficiencia de los sistemas of the SPCR accompanying de riego de la represa el TF / A4893 strategic investment plan Posterior Individual Open 10,000.00 0.00 Cancelado 2018-09-24 2018-10-17 2018-11-02 2018-11-08 2019-04-09 coyolar y propuesta de built under a participatory modelo financiero para su process sostenibilidad. HN-INVEST-H-77047-CS- Component 4: Formulation INDV / Investigación y of the SPCR accompanying validación de nuevas TF / A4893 strategic investment plan Posterior Individual Open 10,000.00 0.00 Cancelado 2018-09-24 2018-10-29 2018-11-09 2018-11-15 2019-02-05 tecnologías resilientes al built under a participatory cambio climático process HN-INVEST-H-77048-CS- Component 3: Design and INDV / Diseño de la implementation of a estrategia de comunicación participatory consultation at para pueblos indígenas y TF / A4893 Posterior Individual Open 15,000.00 0.00 Cancelado 2018-11-01 2018-12-03 2018-12-14 2019-01-07 2019-04-30 an institutional level, in the afrohondureños con enfoque context of SPCR d de género para la resiliencia evelopment al cambio climático. Component 4: Formulation HN-INVEST-H-77055-CS- of the SPCR accompanying INDV / Contratación de TF / A4893 strategic investment plan Posterior Individual Open 10,000.00 0.00 Cancelado 2018-09-24 2018-10-10 2018-10-25 2018-11-12 2019-11-11 Asistente Administrativo. built under a participatory process Component 1: Risk analysis HN-INVEST-H-61263-CS- to strengthen climate Selección directa CDS / Especialista en TF / A4893 Posterior Direct 20,152.00 14,668.87 Firmado 2018-04-30 2018-04-30 2018-04-30 2018-12-31 resilience programs and de consultores Logística (re-contratación) policies. Component 4: Formulation HN-INVEST-H-101186-CS- of the SPCR accompanying Selección directa CDS / Auditoria Final para TF / A4893 strategic investment plan Posterior Direct 23,800.00 17,320.39 Firmado 2019-02-25 2019-03-01 2019-03-26 2020-03-31 de consultores el PPCR. built under a participatory process Page 5 Component 4: Formulation HN-INVEST-H-101521-CS- of the SPCR accompanying INDV / Especialista en TF / A4893 strategic investment plan Posterior Individual Open 15,000.00 0.00 Cancelado 2019-02-25 2019-03-13 2019-03-19 2019-03-27 2019-05-27 Salvaguardas Sociales. built under a participatory process Component 4: Formulation HN-INVEST-H-101529-CS- of the SPCR accompanying INDV / Contratación TF / A4893 strategic investment plan Posterior Individual Open 15,000.00 0.00 Cancelado 2019-02-25 2019-03-13 2019-03-19 2019-03-27 2019-05-27 Especialista en Salvaguardas built under a participatory Ambientales. process HN-INVEST-H-101530-CS- Component 3: Design and INDV / Diseño de la implementation of a estrategia de comunicación participatory consultation at para pueblos indígenas y TF / A4893 Posterior Individual Open 25,000.00 0.00 Cancelado 2019-02-20 2019-03-12 2019-03-18 2019-03-25 2019-07-25 an institutional level, in the afrohondureños con enfoque context of SPCR d de género para la resiliencia evelopment al cambio climático. Component 3: Design and HN-INVEST-H-101532-CS- implementation of a INDV / Diseñar la SPCR en participatory consultation at TF / A4893 Posterior Individual Open 15,000.00 0.00 Cancelado 2019-02-21 2019-03-13 2019-03-18 2019-03-26 2019-06-26 versión popular ( incluye su an institutional level, in the diseño gráfico). context of SPCR d evelopment HN-INVEST-H-101533-CS- Component 4: Formulation INDV / Contratación of the SPCR accompanying Asistente en Diseño TF / A4893 strategic investment plan Posterior Individual Open 11,000.00 0.00 Cancelado 2019-02-26 2019-03-20 2019-03-28 2019-04-22 2019-12-31 Diagramación de Gestión del built under a participatory Conocimiento. process HN-INVEST-H-25452-CS- Technical and Financial INDV / Especialista / Management of the Phase 1 Posterior Individual Limited 32,000.00 0.00 Cancelado 2018-01-02 2018-01-12 2018-02-02 2018-02-12 2019-02-07 Financiero of the PPCR HN-INVEST-H-104415-CS- Technical and Financial Selección directa INDV / Oficial de TF / A4893 Management of the Phase 1 Posterior Direct 8,064.00 8,190.16 Firmado 2019-03-27 2019-08-20 2019-08-28 2019-12-31 de consultores Adquisiciones of the PPCR Component 4: Formulation HN-INVEST-H-104412-CS- of the SPCR accompanying Selección directa INDV / Enlace Técnico Mi TF / A4893 strategic investment plan Posterior Direct 8,400.00 8,531.42 Firmado 2019-03-27 2019-08-28 2019-08-28 2020-01-31 de consultores ambiente/IINVEST-H built under a participatory process HN-INVEST-H-104230-CS- INDV / Contratación del Sub- Component 4: Formulation Coordinador Técnico del of the SPCR accompanying PPCR para el Control de Selección directa TF / A4893 strategic investment plan Posterior Direct 18,000.00 3,064.41 Firmado 2019-03-27 2019-06-24 2019-07-01 2019-12-31 Calidad de los Estudios de de consultores built under a participatory Pre factibilidad a las process Inversiones Estratégicas Propuestas. Component 3: Design and HN-INVEST-H-104232-CS- implementation of a INDV / Especialista en participatory consultation at Selección directa TF / A4893 Posterior Direct 22,400.00 22,880.96 Firmado 2019-03-27 2019-04-24 2019-04-30 2019-12-31 procesos participativos, an institutional level, in the de consultores comunicación y género. context of SPCR d evelopment Component 4: Formulation HN-INVEST-H-104233-CS- of the SPCR accompanying Selección directa INDV / Coordinador General TF / A4893 strategic investment plan Posterior Direct 30,600.00 31,247.96 Firmado 2019-03-27 2019-03-27 2019-04-01 2019-12-31 de consultores del PPCR. built under a participatory process Page 6 Component 4: Formulation HN-INVEST-H-104234-CS- of the SPCR accompanying Selección directa INDV / Especialista en TF / A4893 strategic investment plan Posterior Direct 21,600.00 22,067.21 Firmado 2019-03-27 2019-03-29 2019-04-01 2019-12-31 de consultores Logística. built under a participatory process HN-INVEST-H-108756-CS- INDV / Generación de Component 3: Design and insumos para el desarrollo implementation of a de una estrategia de participatory consultation at comunicación con perspectiva TF / A4893 Posterior Individual Open 25,000.00 24,000.00 Finalizado 2019-04-08 2019-04-25 2019-04-29 2019-05-02 2019-09-02 an institutional level, in the de género, dirigida a pueblos context of SPCR d indígenas y afrohondureños evelopment sobre cambio climático y resiliencia climática. HN-INVEST-H-110431-CS- INDV / Revisión y Component 4: Formulation actualización de Marco de of the SPCR accompanying Gestión Ambiental y Social TF / A4893 strategic investment plan Posterior Individual Open 25,000.00 0.00 Cancelado 2019-05-06 2019-05-23 2019-05-27 2019-06-03 2019-08-30 del Programa de Seguridad built under a participatory Hídrica en el Corredor Seco process de Honduras. HN-INVEST-H-110432-CS- INDV / Revisión y Component 4: Formulation actualización del Marco de of the SPCR accompanying Reasentamiento del TF / A4893 strategic investment plan Posterior Individual Open 12,509.00 0.00 Cancelado 2019-05-13 2019-05-31 2019-06-05 2019-06-12 2019-08-30 Programa de Seguridad built under a participatory Hídrica en el Corredor Seco process de Honduras. HN-INVEST-H-110433-CS- INDV / Revisión y Component 4: Formulation actualización del Marco de of the SPCR accompanying Pueblos Indígenas del TF / A4893 strategic investment plan Posterior Individual Open 13,346.00 0.00 Cancelado 2019-05-20 2019-06-17 2019-06-19 2019-06-25 2019-08-30 Programa de Seguridad built under a participatory Hídrica en el Corredor Seco process de Honduras. HN-INVEST-H-110434-CS- INDV / Revisión y Component 4: Formulation actualización del Plan de of the SPCR accompanying Participación de Partes TF / A4893 strategic investment plan Posterior Individual Open 27,510.00 0.00 Cancelado 2019-05-27 2019-06-24 2019-06-26 2019-07-01 2019-09-06 Interesadas y Procesos built under a participatory Laborales del Programa de process Seguridad Hídrica en el Corredor Seco de Honduras. Component 4: Formulation of the SPCR accompanying HN-INVEST-H-156138-CS- Ejecución TF / A4893 strategic investment plan Posterior Individual Limited 18,000.00 0.00 2020-02-05 2020-02-07 2020-02-18 2020-02-22 2020-08-19 INDV / Especialista Social pendiente built under a participatory process Component 4: Formulation HN-INVEST-H-156141-CS- of the SPCR accompanying Ejecución INDV / Especialista TF / A4893 strategic investment plan Posterior Individual Limited 18,000.00 0.00 2020-02-05 2020-02-07 2020-02-18 2020-02-22 2020-08-19 pendiente Ambiental built under a participatory process Component 4: Formulation HN-INVEST-H-156142-CS- of the SPCR accompanying Ejecución INDV / Especialista en Agua TF / A4893 strategic investment plan Posterior Individual Limited 24,000.00 0.00 2020-02-05 2020-02-07 2020-02-18 2020-02-22 2020-08-19 pendiente y Saneamiento built under a participatory process Page 7