PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2018-02-19 2020-01-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / V1150, IDA / D2860, IDA / 62130, TF / A7130 Executing Agency(ies): Ministry of Environnement/Directorate of Environment WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 39 / Aménagement de Component 4: National Single Stage - One bureaux pour l’unité de IDA / V1150 A posteriori Appel d'offres Open - National 90,000.00 81,133.59 Signé 2018-05-07 2018-05-12 2018-06-23 2018-07-23 2018-08-27 2019-02-23 Coordination Envelope gestion du projet WACA 59 / Travaux d'aménagement du R+1 des bureaux pour l'UGP, Construction du mur de séparation, d'un parking Component 4: National Single Stage - One En attente pour 10 voitures, un poste IDA / D2860 A posteriori Appel d'offres Open - National 190,000.00 0.00 2019-06-27 2019-07-02 2019-08-13 2019-09-12 2019-10-17 2020-04-14 Coordination Envelope d'exécution d'hébergement (des compteurs et du groupe électrogène) et aménagement de la cour (aires de circulation et jardin) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 35 / Acquisition de Component 4: National Single Stage - One IDA / V1150 A posteriori Demande de prix Limited 15,000.00 0.00 Annulé 2018-05-13 2018-07-08 2019-01-04 matériels informatiques Coordination Envelope 37 / Acquisition du mobilier Component 4: National Single Stage - One de bureau pour la IDA / V1150 A posteriori Demande de prix Limited 25,000.00 23,847.22 Signé 2018-07-17 2018-09-11 2019-03-10 Coordination Envelope coordination du projet 34 / Achat de fournitures de bureau, matériels de bureau et matériels d'entretien de bureau en 03 lots. Lot 1 fournitures de bureau Component 4: National Single Stage - One IDA / V1150 A posteriori Demande de prix Limited 10,000.00 7,637.09 Signé 2018-02-03 2018-03-31 2018-09-27 (papiers rames, bics,..) Coordination Envelope Lot 2 matériels de bureau (reliure) et Lot 3 matériels d'entretien de bureau (gel désinfectant, ...). Page 1 35 BIS / Acquisition de fournitures informatiques et de matériels informatiques en 02 lots : Lot 1 fournitures informatiques Component 4: National Single Stage - One (cartouches d'encre, antivirus, IDA / V1150 A posteriori Demande de prix Limited 27,000.00 26,469.61 Signé 2018-01-09 2018-03-06 2018-09-02 Coordination Envelope disques durs) et Lot 2 matériels informatiques (ordinateurs de bureau, ordinateurs portables, scanners ..) 41BIS / Le matériel roulant sera composé comme suit : Lot 1: 2 pick-up 4x4 double Component 4: National Single Stage - One En cours cabine tropicalisés pour les IDA / D2860 A posteriori Demande de prix Limited 294,000.00 0.00 2019-04-20 2019-06-15 2019-12-12 Coordination Envelope d'exécution missions de terrain, Lot2: 01 station wagon , Lot3: 01 mini bus. 74 / Acquisition de 2 Component 2: Strengthening véhicules de terrain pour Single Stage - One En attente IDA / D2860 the Policy and Institutional A posteriori Demande de prix Limited 85,000.00 0.00 2019-06-26 2019-08-21 2020-02-17 l'Agence Nationale de Envelope d'exécution Framework Gestion de l'Environnement 65 / Acquisition de matériel roulant (moto) pour les 7 Component 4: National Single Stage - One En attente TF / A7130 A posteriori Demande de prix Limited 40,000.00 0.00 2019-07-01 2019-08-26 2020-02-22 CPDD et le coursier de Coordination Envelope d'exécution l'UGP 66 / Acquisition de GPS pour les CPDD (07) et Component 4: National Single Stage - One En cours TF / A7130 A posteriori Demande de prix Limited 20,000.00 0.00 2019-07-02 2019-08-27 2020-02-23 l'unité de gestion du projet Coordination Envelope d'exécution (5) soit au total 12 GPS 58 / Acquisition de matériel et fourniture informatique pour le projet (Ordinateur bureau +portable en poste de trav, copieur, imprimante Component 4: National Single Stage - One IDA / D2860 A posteriori Demande de prix Limited 50,000.00 0.00 Annulé 2019-06-16 2019-08-11 2020-02-07 couleur, blanc noir, clé USB Coordination Envelope multi copieur, disque dure, vidéo projecteur, onduleurs, modem pour connexion Wifi, camera... NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 36 / Edition du plan d'investissement et du Component 4: National Single Stage - One document d'analyse du cadre IDA / V1150 A posteriori Demande de prix Limited 18,000.00 20,365.63 Signé 2018-02-21 2018-04-18 2018-10-15 Coordination Envelope juridique institutionnel de gestion intégrée du littoral 38 / Paramétrage du Passation de logiciel de gestion financière Component 4: National En cours IDA / V1150 A posteriori marché de gré à Direct 13,000.00 0.00 2018-07-05 2018-07-10 2018-08-14 2019-02-10 du PGICT pour le projet Coordination d'exécution gré WACA 17 BIS / Mise en place d'un système informatisé de Component 4: National Single Stage - One En cours suivi du projet (acquisition, IDA / D2860 A posteriori Appel d'offres Open - National 40,000.00 0.00 2019-02-20 2019-02-25 2019-04-08 2019-05-08 2019-06-12 2019-12-09 Coordination Envelope d'exécution installation et formation des utilisateurs) Page 2 52 / Recrutement d'un Component 4: National Single Stage - One En attente IDA / D2860 A posteriori Demande de prix Limited 4,000.00 0.00 2019-06-29 2019-08-24 2020-02-20 service d'entretien Coordination Envelope d'exécution 77 / Police d'assurance pour Component 4: National Single Stage - One En attente le personnel recruté par le IDA / D2860 A posteriori Demande de prix Limited 20,000.00 0.00 2019-11-25 2020-01-20 2020-07-18 Coordination Envelope d'exécution projet WACA ResIP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 14 / Etude de faisabilité Component 3: Strengthening Sélection fondée technique de la protection Open - IDA / V1150 National Physical and Social A priori sur la qualité et 2,000,000.00 0.00 Annulé 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 côtière du segment International Investments le coût transfrontalier Bénin-Togo 15 / Etude d'Impact Environnemental et Social Component 2: Strengthening Sélection fondée Open - (EIES) de la protection IDA / V1150 the Policy and Institutional A posteriori sur la qualité et 320,000.00 0.00 Annulé 2018-02-08 2018-03-01 2018-04-14 2018-05-12 2018-06-11 2018-07-16 2018-08-20 2019-08-20 International côtière du segment Framework le coût transfrontalier Bénin-Togo 19 / Etude d'Impact Environnemental et Social Sélection fondée Component 2: Strengthening (EIES) pour le curage sur les IDA / V1150 the Policy and Institutional A posteriori Open - National 200,000.00 0.00 Annulé 2018-09-25 2018-10-16 2018-11-29 2018-12-29 2019-02-02 2019-08-01 mécanique du chenal Gbaga qualifications des Framework et de restauration de ces consultants écosystèmes associés 46 / Evaluation du coût de Sélection fondée la dégradation historique de Component 2: Strengthening sur les En cours la côte y compris la IDA / D2860 the Policy and Institutional A posteriori Open - National 130,000.00 0.00 2019-01-17 2019-02-07 2019-03-23 2019-04-22 2019-05-27 2019-11-23 qualifications des d'exécution vulnérabilité des Framework consultants communautés côtières 42BIS / Etude de faisabilité technique de l'installation Component 3: Strengthening Sélection fondée d'une vanne au niveau du Open - IDA / D2860 National Physical and Social A priori sur la qualité et 650,000.00 0.00 Annulé 2019-03-05 2019-03-26 2019-05-09 2019-06-06 2019-07-06 2019-08-10 2019-09-14 2020-09-13 pont de la lagune d'Aného International Investments le coût et l'étude hydrodynamique du système fluvio-lagunaire 43 / Etude approfondie de Component 3: Strengthening Sélection fondée faisabilité du traitement des Open - IDA / 62130 National Physical and Social A priori sur la qualité et 600,000.00 0.00 Annulé 2019-03-12 2019-04-02 2019-05-16 2019-06-13 2019-07-13 2019-08-17 2019-09-21 2020-09-20 boues de phosphates rejetées International Investments le coût en mer Sélection fondée 44 / Elaboration du plan Component 4: National Open - IDA / D2860 A posteriori sur la qualité et 250,000.00 0.00 Annulé 2019-02-11 2019-03-04 2019-04-17 2019-05-15 2019-06-14 2019-07-19 2019-08-23 2020-08-22 spatial marin et côtier Coordination International le coût Component 2: Strengthening Sélection fondée 45 / Evaluation du capital Open - IDA / D2860 the Policy and Institutional A posteriori sur la qualité et 300,000.00 0.00 Annulé 2019-02-12 2019-03-05 2019-04-18 2019-05-16 2019-06-15 2019-07-20 2019-08-24 2020-08-23 naturel de la zone côtière International Framework le coût 49 / Audits financiers et Component 4: National Sélection au En cours comptables du projet - IDA / D2860 A posteriori Open - National 45,000.00 0.00 2019-02-11 2019-03-04 2019-04-17 2019-05-15 2019-06-14 2019-07-19 2019-08-23 2020-02-19 Coordination moindre coût d'exécution exercices 2017, 2018 et 2019 Page 3 3 BIS / Etudes de faisabilité techniques de dragage et de stabilisation Component 3: Strengthening Sélection fondée des berges de la lagune et Open - En cours IDA / D2860 National Physical and Social A posteriori sur la qualité et 250,000.00 0.00 2018-10-04 2018-10-25 2018-12-08 2019-01-05 2019-02-04 2019-03-11 2019-04-15 2020-04-14 du lac Togo, et pour la International d'exécution Investments le coût Construction et le curage de caniveau, de bassin d'orage, de retenue d'eau 48 / Etude d'Impact Environnemental et Social Sélection fondée Component 3: Strengthening (EIES) pour le curage sur les TF / A7130 National Physical and Social A posteriori Open - National 100,000.00 0.00 Annulé 2018-12-28 2019-01-18 2019-03-03 2019-04-02 2019-05-07 2019-11-03 mécanique du chenal Gbaga qualifications des Investments et de restauration de ces consultants écosystèmes associés 47B / Etude de faisabilité technique pour le curage Component 3: Strengthening Sélection fondée Open - En cours mécanique du chenal de TF / A7130 National Physical and Social A priori sur la qualité et 600,000.00 0.00 2019-04-26 2019-05-17 2019-06-30 2019-07-28 2019-08-27 2019-10-01 2019-11-05 2020-11-04 International d'exécution Gbaga et de la restauration Investments le coût de ces écosystèmes associés 47 / Etude de faisabilité technique du curage Component 3: Strengthening Sélection fondée Open - mécanique du chenal Gbaga TF / A7130 National Physical and Social A posteriori sur la qualité et 300,000.00 0.00 Annulé 2018-12-28 2019-01-18 2019-03-03 2019-03-31 2019-04-30 2019-06-04 2019-07-09 2020-07-08 International et de restauration de ces Investments le coût écosystèmes associés 48B / Etude d'Impact Environnemental et Social Sélection fondée Component 3: Strengthening (EIES) pour le curage sur les Open - En cours TF / A7130 National Physical and Social A posteriori 200,000.00 0.00 2019-04-26 2019-05-17 2019-06-30 2019-07-30 2019-09-03 2020-03-01 mécanique du chenal Gbaga qualifications des International d'exécution Investments et de restauration de ces consultants écosystèmes associés 40 / Surveillance et Sélection fondée contrôle des travaux Component 4: National sur les IDA / V1150 A posteriori Open - National 18,000.00 0.00 Annulé 2018-07-11 2018-08-01 2018-09-14 2018-10-14 2018-11-18 2019-05-17 d'aménagement des bureaux Coordination qualifications des du Projet WACA consultants 62 / Élaboration du plan Sélection fondée d'aménagement participatif Component 3: Strengthening sur les Open - En cours et des outils de gestion de TF / A7130 National Physical and Social A posteriori 140,000.00 0.00 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 qualifications des International d'examen la forêt communautaire Investments consultants d'Avévé  63 / Elaboration du plan Sélection fondée d'aménagement participatif Component 3: Strengthening sur les Open - En cours et des outils de gestion de TF / A7130 National Physical and Social A posteriori 150,000.00 0.00 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 qualifications des International d'exécution la forêt communautaire de Investments consultants Kodjo-Gati 60 / Recrutement d'une structure ( centre de Sélection fondée formation) pour la formation Component 3: Strengthening sur les En cours et l'accompagnement des TF / A7130 National Physical and Social A posteriori Open - National 55,000.00 0.00 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 qualifications des d'exécution acteurs communautaires sur Investments consultants les bonnes pratiques en gestion durable des terres. 40 C / Surveillance et contrôle des travaux d'aménagement du R + 1 Sélection fondée des bureaux de l'UGP, Component 4: National sur les En attente Construction du mur de IDA / D2860 A posteriori Open - National 20,000.00 0.00 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 Coordination qualifications des d'exécution séparation, d'un parking consultants pour 10 voitures, d'un poste d'achat et d'un aménagement de cour. Page 4 Sélection fondée 78 / Assistance technique Component 2: Strengthening sur les En attente et contrôle des activités TF / A7130 the Policy and Institutional A posteriori Open - National 220,982.00 0.00 2020-01-14 2020-02-04 2020-03-19 2020-04-18 2020-05-23 2020-11-19 qualifications des d'exécution communautaires Framework consultants 82 / Etude sur la situation des plantes envahissantes, Sélection fondée des modèles de gestion et de Component 3: Strengthening sur les Open - En attente valorisation dans la sous- TF / A7130 National Physical and Social A posteriori 80,000.00 0.00 2019-12-30 2020-01-20 2020-03-04 2020-04-03 2020-05-08 2020-11-04 qualifications des International d'exécution région et les applications Investments consultants possibles dans la zone du projet INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1 / Elaboration du Cadre Component 2: Strengthening de Gestion Environnementale IDA / V1150 the Policy and Institutional A posteriori Individuel Limited 27,500.00 23,893.15 Signé 2017-07-18 2017-07-23 2018-01-29 2018-03-05 2018-07-17 et Sociale (CGES) Framework 2 / Elaboration du Cadre Component 2: Strengthening de Politique de IDA / V1150 the Policy and Institutional A posteriori Individuel Limited 24,000.00 20,223.92 Signé 2017-06-22 2017-08-24 2017-09-29 2017-11-29 2018-01-12 Réinstallation (CPR) Framework 4 / Etude d'impact environnemental et social Component 2: Strengthening En cours des dragages et de la IDA / V1150 the Policy and Institutional A posteriori Individuel Limited 18,000.00 0.00 2017-11-12 2018-01-27 2018-02-17 2018-03-24 2018-04-24 d'exécution construction des ouvrages de Framework lutte contre les inondations 13 / Elaboration de la Sélection de Component 4: National stratégie de passation des IDA / V1150 A posteriori consultants par Direct 14,000.00 13,130.33 Signé 2017-12-12 2017-12-22 2018-02-09 2018-03-29 Coordination marchés (PPSD) entente directe 6 / Recrutement d'un Component 4: National spécialiste en passation des IDA / V1150 A posteriori Individuel Open 24,000.00 0.00 Annulé 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 Coordination marchés 8 / Recrutement d'un Component 4: National spécialiste en suivi- IDA / V1150 A posteriori Individuel Open 24,000.00 0.00 Annulé 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 Coordination évaluation 20 / Recrutement d'un Component 4: National En cours spécialiste en développement IDA / V1150 A posteriori Individuel Open 24,000.00 0.00 2018-06-03 2018-07-22 2018-08-12 2018-09-16 2019-03-15 Coordination d'exécution institutionnel 9 / Recrutement d'un Component 4: National spécialiste en sauvegarde IDA / V1150 A posteriori Individuel Open 24,000.00 0.00 Annulé 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 Coordination sociale 10 / Recrutement d'un Component 4: National IDA / V1150 A posteriori Individuel Open 24,000.00 0.00 Annulé 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 spécialiste en communication Coordination 9 BIS / Recrutement d'un Component 4: National En cours spécialiste en sauvegarde IDA / V1150 A posteriori Individuel Open 24,000.00 0.00 2018-04-26 2018-06-14 2018-07-05 2018-08-09 2019-02-05 Coordination d'exécution sociale 10 BIS / Recrutement d'un Component 4: National En cours IDA / V1150 A posteriori Individuel Open 24,000.00 0.00 2018-06-03 2018-07-22 2018-08-12 2018-09-16 2019-03-15 spécialiste en communication Coordination d'exécution Page 5 7 / Recrutement d'un Component 4: National En cours ingénieur génie civil (génie IDA / V1150 A posteriori Individuel Open 28,000.00 0.00 2018-05-17 2018-07-05 2018-07-26 2018-08-30 2019-02-26 Coordination d'exécution côtier) 27 / Recrutement d'un Component 4: National En cours IDA / V1150 A posteriori Individuel Open 24,000.00 0.00 2018-05-24 2018-07-12 2018-08-02 2018-09-06 2019-03-05 auditeur interne du projet Coordination d'exécution 11 / Recrutement de Component 4: National IDA / V1150 A posteriori Individuel Open 12,000.00 0.00 Annulé 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 secrétaire caissière Coordination 7 / Recrutement d'un Component 4: National ingénieur génie civil (génie IDA / V1150 A posteriori Individuel Open 24,000.00 0.00 Annulé 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 Coordination côtier) 3 / Réalisation d'études Component 3: Strengthening techniques d'ouvrages de IDA / V1150 National Physical and Social A posteriori Individuel Limited 53,000.00 0.00 Annulé 2017-11-08 2017-11-13 2018-03-26 2018-04-30 2018-10-27 lutte contre les inondations Investments 12 / Recrutement d'un Component 4: National IDA / V1150 A posteriori Individuel Limited 30,000.00 0.00 Annulé 2017-11-08 2017-11-13 2017-12-04 2018-01-08 2018-07-07 Assistant technique au projet Coordination 25 / Recrutement d'un Component 4: National assistant en passation des IDA / V1150 A posteriori Individuel Open 10,000.00 0.00 Annulé 2018-04-26 2018-06-14 2018-07-05 2018-08-09 2019-02-05 Coordination marchés 24 BIS / Recrutement d'un Component 4: National En cours spécialiste en gestion IDA / D2860 A posteriori Individuel Open 24,000.00 0.00 2018-08-29 2018-11-02 2018-11-23 2018-12-28 2019-06-26 Coordination d'exécution financière 24 / Recrutement d'un Component 4: National assistant au spécialiste en IDA / V1150 A posteriori Individuel Open 10,000.00 0.00 Annulé 2018-08-29 2018-10-31 2018-11-21 2018-12-26 2019-06-24 Coordination gestion financière 51 / Appui à la mise en Component 2: Strengthening En cours place du MRV de la zone IDA / D2860 the Policy and Institutional A posteriori Individuel Open 30,000.00 0.00 2019-02-04 2019-03-25 2019-04-15 2019-05-20 2019-11-16 d'exécution côtière Framework 50 / Etude pour la mise en place du système national d'informations côtières Component 2: Strengthening En cours (Définition et harmonisation IDA / D2860 the Policy and Institutional A posteriori Individuel Open 70,000.00 0.00 2019-04-02 2019-05-21 2019-06-11 2019-07-16 2020-01-12 d'exécution des standards de collecte, Framework traitement et diffusion de données pour l'observatoire) 6 BIS / Recrutement d'un Component 4: National En cours spécialiste en passation des IDA / D2860 A posteriori Individuel Open 24,000.00 0.00 2018-08-27 2018-10-31 2018-11-21 2018-12-26 2019-06-24 Coordination d'exécution marchés 69 / Actualisation des Component 2: Strengthening En cours manuels de procédure de IDA / D2860 the Policy and Institutional A posteriori Individuel Open 13,000.00 0.00 2019-06-17 2019-08-05 2019-08-26 2019-09-30 2020-03-28 d'exécution l'ANGE Framework 67 / Élaboration du plan de développement des Ressources Humaines du Component 2: Strengthening Ministère de En cours TF / A7130 the Policy and Institutional A posteriori Individuel Open 15,000.00 0.00 2019-06-19 2019-08-07 2019-08-28 2019-10-02 2020-03-30 l'Environnement, du d'exécution Framework Développement Durable et de la Protection de la Nature Page 6 64 / Appui à l'analyse institutionnelle du Ministère de l'Environnement, du Développement Durable et Component 2: Strengthening En cours de la Protection de la TF / A7130 the Policy and Institutional A posteriori Individuel Open 15,000.00 0.00 2019-06-19 2019-08-07 2019-08-28 2019-10-02 2020-03-30 d'exécution Nature relative à la mise en Framework œuvre des conventions internationales signées par le Togo Component 3: Strengthening 68 / Élaboration du cadre En cours TF / A7130 National Physical and Social A posteriori Individuel Open 24,000.00 0.00 2019-06-17 2019-08-05 2019-08-26 2019-09-30 2020-03-28 fonctionnel (procédural) d'exécution Investments 40B / Surveillance contrôle des Travaux d'aménagement du R+1 des bureaux pour l'UGP, Construction du mur de séparation, d'un parking Component 4: National IDA / V1150 A posteriori Individuel Open 9,000.00 0.00 Annulé 2019-06-20 2019-08-08 2019-08-29 2019-10-03 2020-03-31 pour 10 voitures, un poste Coordination d'hébergement (des compteurs et du groupe électrogène) et aménagement de la cour 61 / Élaboration des textes Component 2: Strengthening En cours d'application de la loi sur le IDA / D2860 the Policy and Institutional A posteriori Individuel Open 20,000.00 0.00 2019-06-20 2019-08-08 2019-08-29 2019-10-03 2020-03-31 d'exécution littoral Framework 53 / Recrutement d'un (01) Component 4: National En cours IDA / D2860 A posteriori Individuel Open 3,500.00 0.00 2019-06-26 2019-08-14 2019-09-04 2019-10-09 2020-04-06 coursier Coordination d'exécution 55 / Recrutement de deux Component 4: National En cours (2) chauffeurs de permis IDA / D2860 A posteriori Individuel Open 9,000.00 0.00 2019-07-12 2019-08-30 2019-09-20 2019-10-25 2020-04-22 Coordination d'exécution catégorie B 54 / Recrutement d'un (01) Component 4: National En cours chauffeur de permis IDA / D2860 A posteriori Individuel Open 5,500.00 0.00 2019-08-22 2019-10-10 2019-10-31 2019-12-05 2020-06-02 Coordination d'exécution catégorie C 75 / Recrutement d'un Component 4: National En cours Coordonnateur du projet IDA / D2860 A posteriori Individuel Open 33,000.00 0.00 2019-08-19 2019-10-07 2019-10-28 2019-12-02 2020-05-30 Coordination d'exécution WACA ResIP 75BIS / Recrutement de Component 4: National En attente coordonnateur pour le projet IDA / D2860 A posteriori Individuel Open 33,000.00 0.00 2019-11-20 2019-12-23 2020-01-06 2020-02-10 2020-08-08 Coordination d'exécution WACA ResIP Page 7