The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) Bihar Rural Roads Project (P155522) SOUTH ASIA | India | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 6 | ARCHIVED on 10-Sep-2019 | ISR38059 | Implementing Agencies: Rural Works Department, Bihar, Republic of India Key Dates Key Project Dates Bank Approval Date: 21-Dec-2016 Effectiveness Date: 31-Aug-2017 Planned Mid Term Review Date: 30-Apr-2020 Actual Mid-Term Review Date: Original Closing Date: 31-Dec-2022 Revised Closing Date: 31-Dec-2022 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The PDO is to improve rural road connectivity in project districts, and enhance management of rural roads in Bihar. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Rural Roads Improvement:(Cost $320.00 M) Asset Management and Institutional Effectiveness:(Cost $15.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions About 859 km out of a total 1,052 km connecting 361 habitations under Batch I roads has been completed. Balance works under Batch I roads are expected to be completed by December 2019. Procurement of Batch II roads are currently underway wherein some packages (around 8 of them) are to be re-tendered due to non-responsiveness. A major part of the Batch II roads (total around 500 km) are expected to be awarded by end-July 2019 / early-August 2019 and the balance (the one to be re-tendered) are expected to be awarded by end-September 2019. Procurement for Batch III roads are yet to commence. Detailed Project Reports are currently under finalization for 300 km of roads and for the balance 700 km, the DPR consultants are yet to be engaged. In addition to the above, BRRDA is in the process of implementing the Asset Management Policy and Plan and the Rural Road Safety Action Plan which has been endorsed / approved by the Government of Bihar. On Component 2, there was a general lack of awareness about the full extent of the scope of this critically important component, it was agreed that BRRDA would develop an implementation matrix for the activities under Component 2, with the aim of defining actions, responsible parties, and 9/10/2019 Page 1 of 6 The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) timing, to achieve the remaining activities in relation to the expected project outcomes. The project was advised and agreed to consider deploying a consultant to assist in the implementation of the component. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Moderate Moderate Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Moderate Moderate Institutional Capacity for Implementation and Sustainability Substantial Substantial Substantial Fiduciary Moderate Moderate Moderate Environment and Social Moderate Moderate Moderate Stakeholders Moderate Moderate Moderate Other Low -- -- Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes Increased road connectivity to Habitations IN00729069 ►Increased road connectivity to habitations (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 60,280.00 391.00 361.00 62,000.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 To be updated after the implementation support mission. Comments: IN00729079 ►Roads in good and fair condition as a share of total classified roads (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 40.00 0.00 0.00 50.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 9/10/2019 Page 2 of 6 The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) To be updated after the implementation support mission. Comments: IN00729078 ►Improved effectiveness of project expenditure - Project roads designed using cost-effective measures. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 IN00729080 ►Improved asset management - number of districts that have developed and are using asset management system (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 Intermediate Results Indicators by Components Rural Roads Improvement IN00729081 ►Roads constructed, Rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 700.00 859.00 2,500.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 IN00729083 ►Improved quality of built Infrastructure - Project roads delivered with satisfactory quality certified through independent quality reviews (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 85.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 To be updated after the implementation support mission. Comments: IN00729085 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 129,315.00 129,315.00 1,200,000.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 IN00729088 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target 9/10/2019 Page 3 of 6 The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) Value 0.00 0.00 0.00 48.00 IN00729089 ►Road Safety improvement scheme related audits undertaken on priority roads (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,000.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 Asset Management and Institutional Effectiveness IN00729082 ►Length of roads subject to planned maintenance contracting (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4,600.00 100.00 100.00 10,000.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 To be updated after the implementation support mission. Comments: IN00729084 ►RWD staff received at least six (6) weeks of professional training during the entire project duration. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 400.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 IN00729086 ►Effective Citizen Feedback Mechanism (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 85.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 To be updated after the implementation support mission. Comments: IN00729087 ►Network level climate vulnerability assessment undertaken with special focus on floods (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,000.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 To be updated after the implementation support mission. Comments: IN00729090 ►Gender-based capacity enhancement (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 9/10/2019 Page 4 of 6 The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) Value 0.00 0.00 0.00 30.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 To be updated after the implementation support mission. Comments: IN00729091 ►GIS based road and bridge inventory and condition database (including videography) established in project districts (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 30-Sep-2016 31-May-2019 29-Jun-2019 30-Sep-2022 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P155522 IDA-59380 Effective USD 235.00 235.00 0.00 57.75 177.25 25% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P155522 IDA-59380 Effective 21-Dec-2016 29-May-2017 31-Aug-2017 31-Dec-2022 31-Dec-2022 Cumulative Disbursements 9/10/2019 Page 5 of 6 The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 9/10/2019 Page 6 of 6