The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) SOUTH ASIA | Afghanistan | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2019 | Seq No: 1 | ARCHIVED on 19-Mar-2019 | ISR36010 | Implementing Agencies: Ministry of Economy, Ministry of Finance, Aid Management Directorate Key Dates Key Project Dates Bank Approval Date: 19-Dec-2018 Effectiveness Date: 06-Feb-2019 Planned Mid Term Review Date: 31-Oct-2021 Actual Mid-Term Review Date: -- Original Closing Date: 31-Dec-2023 Revised Closing Date: 31-Dec-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to strengthen the enabling environment for economic opportunities in cities where there is a high influx of displaced people. This will be pursued by increasing the returnees' access to civil documents, providing short-term employment opportunities, improving market enabling infrastructure, and supporting investor friendly regulatory reforms. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Regional and National Integration of Displaced Persons:(Cost $4.50 M) Short Term Employment Opportunities, Reforms, and Market Enabling Infrastructure under IDLG:(Cost $120.50 M) Prioritized Urban Investments in Four Provincial Capital Cities:(Cost $25.00 M) Market Enabling Infrastructure and Reforms for Kabul Municipality:(Cost $40.00 M) Red Carpet and Program Coordination:(Cost $10.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Satisfactory Overall Implementation Progress (IP) -- Satisfactory Overall Risk Rating -- High Implementation Status and Key Decisions The Financing Agreement for the IDA Grant and the Grant Agreement for the Afghanistan Reconstruction Trust Fund (ARTF) co-financing were signed on February 6, 2019, concurrently making the project effective. The Project Steering Committee, comprising Deputy Minister and Deputy Mayor level representatives from MoEC, MoFA, IDLG, and Kabul Municipality has been established with the first meeting taking place on February 9, 2019. The first implementation support mission is scheduled for April 2019 to assess the status of project rollout and provide further support to 3/19/2019 Page 1 of 12 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) the PIUs for the early implementation of component activities. The project consists of (a) assistance to MoFA missions in Pakistan to provide consular services and communications activities; (b) labor intensive public works; (c) market enabling investment grants to Gozars and business Gozars; (d) priority investment projects in Kabul and four Provincial Capital Cities; and (e) support for investor friendly regulatory reforms. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High -- High Macroeconomic High -- High Sector Strategies and Policies High -- High Technical Design of Project or Program Substantial -- Substantial Institutional Capacity for Implementation and Sustainability Substantial -- Substantial Fiduciary High -- High Environment and Social Substantial -- Substantial Stakeholders Substantial -- Substantial Other Substantial -- Substantial Overall High -- High Results PDO Indicators by Objectives / Outcomes ACCESS TO CIVIL DOCUMENTS IN00669578 ►Percentage of Afghan Passport Applications in Pakistan Processed (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 During the project implementation period, number of Afghan Passport Applications in Pakistan processed, Comments: divided by the number of Afghan Passport Application received in Pakistan IN00669581 Percentage of Afghan Passport Applications in Pakistan Processed (for female applicants) (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 3/19/2019 Page 2 of 12 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) SHORT-TERM EMPLOYMENT OPPORTUNITIES IN00669577 ►Number of vulnerable households in high IDP/returnee cities provided with short term employment support (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80,000.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Number of households that have participated in labor intensive public works undertaken through MCCG Comments: subprojects IN00669579 Of which IDP/Returnee households (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 10,000.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 RED CARPET REFORMS AND MARKET FACILITATING INVESTMENTS IN00669576 ►Number of market enabling infrastructure built or upgraded (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1,115.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Number of infrastructure built, upgraded, or maintained through MCCG, Gozar and Business Gozar Comments: Grants, and Priority Projects IN00669580 Of which at the community level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 900.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669582 Of which at the Gozar level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 180.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669583 Of which at the Business Gozar level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 30.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669584 3/19/2019 Page 3 of 12 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Of which at the city level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 5.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669585 ►Number of processing steps reduced for specific Doing Business reform indicators in four cities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 13.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Comments: Number of processing steps reduced for obtaining construction permits for commercial properties IN00669586 Of which in the three cities of Jalalabad, Herat, and Kandahar (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 10.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669587 Of which in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 3.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Intermediate Results Indicators by Components Support for Afghan Refugees in Pakistan IN00669588 ►Number of passports issued to Afghan refugees in Pakistan during the project implementation period (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1,500,000.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Number of machine-readable passports issued for the applications received at the Afghan Embassy and Comments: consulates in Pakistan. IN00669592 of which women (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 600,000.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 3/19/2019 Page 4 of 12 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) IN00669597 ►Percentage of passport applications processed within ten (10) working days (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 The number of machine-readable passports issued within 10 working days of application received, divided by the number of complete passport applications received during the reporting period at the Afghan Comments: Embassy and consulates in Pakistan. The baseline is zero, as machine-readable passports have not been IN00669599 issued in Pakistan, and there is no monitoring system in place. of which women (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669603 ►Number of people reached through communications activities implemented through the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 750,000.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Sum of the numbers of (a) followers of the social media accounts created by the project; (b) help/support Comments: cases logged by helplines and information centers; (c) people reached by awareness campaigns. IN00669607 of which women (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 300,000.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Short-Term Employment Opportunities IN00669593 ►% of CDC members who are women (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 40.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Number of women in the CDCs established under the project, divided by the total number of members of Comments: the CDCs established under the project. Market Facilitating Investments IN00669590 ►Number of municipalities where IDLG holds EZ-Kar coordination meetings with government authorities, Gozar assemblies and Business Gozar assemblies (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 3/19/2019 Page 5 of 12 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Value 0.00 -- 0.00 11.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Number of cities that have held meetings with EZ-Kar stakeholders in the cities where Gozar and Comments: Business Gozar Grants are implemented. IN00669594 ►Number of Gozars (hh and business) that have prepared their Gozar economic development plans (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 276.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Comments: Number of approved Gozar Economic Development Plans IN00669596 ►Businesses in urban areas provided with access to “Improved Water Sources” under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Number of businesses that are provided with access to improved water sources through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project Comments: takes on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by IN00669600 the mid-term review by when there will be more information from implementation. Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669604 Of which through Priority Projects in the four cities of Herat, Kandahar, Khost, and Jalalabad (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669608 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669610 ►Businesses in urban areas provided with access to "Improved Sanitation" under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 3/19/2019 Page 6 of 12 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Number of businesses that are provided with access to improved sanitation through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project takes Comments: on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the IN00669612 mid-term review by when there will be more information from implementation. Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669613 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669615 ►Businesses in urban areas provided with access to all-season roads within a 500-meter range under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Number of businesses that are provided with access to all-season roads within a 500-meter range through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, Comments: since this Project takes on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target IN00669616 value may be set by the mid-term review by when there will be more information from implementation. KM of roads constructed (Kilometers, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 IN00669617 KM of roads rehabilitated (Kilometers, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 IN00669618 ►Businesses in urban areas provided with access to regular solid waste collection at the markets under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 3/19/2019 Page 7 of 12 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Number of businesses that are provided with access to regular solid waste collection through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Comments: Project takes on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be IN00669619 set by the mid-term review by when there will be more information from implementation. Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669620 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669621 ►Businesses in urban areas provided with access to electricity under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Number of businesses that are provided with access to electricity through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project takes Comments: on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the IN00669622 mid-term review by when there will be more information from implementation. Generation Capacity of Renewable Energy (other than hydropower) rehabilitated under the project (Megawatt, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 IN00669623 Generation Capacity of Renewable Energy (other than hydropower) constructed under the project (Megawatt, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 IN00669624 ►Businesses with improved access to ICT services under the project (number of business subscribers) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Comments: Number of businesses that are provided with access to ICT services through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project takes on a demand-driven approach and the types and numbers of subprojects to be implemented under the 3/19/2019 Page 8 of 12 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN00669625 Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669626 Of which through Priority Projects in the four cities of Herat, Kandahar, Khost, and Jalalabad (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669627 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 0.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669628 ►Number of market enabling investments under the project that address the gender gap in access to urban economic centers/ markets (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 35.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Number of market enabling investments under the project that close gender gaps in women’s access to markets, which can be in the form of (i) specific subprojects exclusively for women, e.g. restoration of Comments: women's markets, rehabilitation of toilet facilities for markets; or (ii) subprojects that are inclusive for (and do not exclude) women, such as extension and upgrading of pedestrian walkways, bus stops and street IN00669629 lighting that link to markets. Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669630 Of which through Priority Projects in the four cities of Herat, Jalalabad, Kandahar, and Khost (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 4.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669631 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target 3/19/2019 Page 9 of 12 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Value 0.00 -- 0.00 30.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Red Carpet Reforms IN00669589 ►Number of reform implementation plans prepared (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 5.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Comments: Number of construction permit reform implementation plans prepared IN00669591 Of which at national level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669595 Of which in the three cities of Herat, Jalalabad, and Kandahar (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 3.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669598 Of which in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669601 ►Reduction in time taken to obtain a construction permit for commercial properties in Jalalabad, Kandahar, Herat, and Kabul (Days, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 77.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Comments: Number of average days reduced for obtaining construction permits for commercial properties IN00669605 Of which in Jalalabad (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 14.00 3/19/2019 Page 10 of 12 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669609 Of which in Kandahar (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 6.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669611 Of which in Herat (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 18.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 IN00669614 Of which in Kabul (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 39.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Project Management IN00669602 ►Number of access to information inquiries responded to within agreed service standards (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 Number of individuals and organizations (including media and NGOs) that received project related Comments: information in accordance with agreed service standards. IN00669606 ►Percentage of complaints / grievances resolved following agreed EZ-Kar service standards (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 Date 01-Nov-2018 -- 11-Feb-2019 31-Dec-2023 The number of project related complaints or grievances resolved in accordance with EZ-Kar service Comments: standards, divided by the number of project related complaints or grievances received. Data on Financial Performance Disbursements (by loan) 3/19/2019 Page 11 of 12 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P166127 IDA-D4160 Effective USD 150.00 150.00 0.00 0.00 150.58 0% P166127 TF-A9092 Effective USD 50.00 50.00 0.00 0.00 50.00 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P166127 IDA-D4160 Effective 19-Dec-2018 06-Feb-2019 06-Feb-2019 31-Dec-2023 31-Dec-2023 P166127 TF-A9092 Effective 19-Dec-2018 06-Feb-2019 06-Feb-2019 31-Dec-2023 31-Dec-2023 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 3/19/2019 Page 12 of 12