Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: last approved PP on 2. Date of General Procurement Notice: June 07, 2017 3. Period covered by this procurement plan: The procurement period of project covered from year May 2016 until December 2013 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: To be updated accordingly Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) 2. NCB (Goods) 3. ICB (Works) 4. NCB (Works) 5. (Non-Consultant Services) [Add other methods if necessary] PROCUREMENT Brazil : BAHIA ROAD REHABILITATION AND MAINTENANCE PROJECT - 2ND PHASE PLAN General Information Country: Brazil Banks Approval Date of the Original Procurement Plan: 2017-01-19 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-06-25 Project ID: P147272 GPN Date: 2017-06-07 Project Name: BAHIA ROAD REHABILITATION AND MAINTENANCE PROJECT - 2ND PHASE Loan / Credit No: IBRD / 85800 Executing Agency(ies): Secretariat of Infrastructure of the State of Bahia WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEINFRA-BA-18665-CW- Component 2: Performance- RFB / Obras de Restauracao e Single Stage - One IBRD / 85800 based State Highway Prior Request for Bids Open - International 35,276,278.00 23,746,003.28 Signed 2017-06-20 2017-07-13 2017-06-25 2017-07-19 2017-08-06 2017-08-23 2017-09-05 2017-10-17 2017-10-10 2017-11-16 2018-04-08 Manutencao de Rodovias Grupo I Envelope Rehabilitation and Maintenance Lotes 1 e 2 BR-SEINFRA-BA-18669-CW- Component 2: Performance- RFB / Obras de Restauracao e Single Stage - One IBRD / 85800 based State Highway Prior Request for Bids Open - International 40,772,794.00 18,875,275.49 Signed 2017-06-20 2017-07-13 2017-06-25 2017-07-19 2017-08-06 2017-08-23 2017-09-05 2017-10-18 2017-10-10 2017-11-21 2018-04-08 Manutencao de Rodovias Grupo Envelope Rehabilitation and Maintenance II Lotes 1 e 2 BR-SEINFRA-BA-18670-CW- Component 2: Performance- RFB / Obras de Restauracao e Single Stage - One IBRD / 85800 based State Highway Prior Request for Bids Open - International 42,040,996.00 24,922,606.76 Signed 2017-06-20 2017-07-13 2017-06-25 2017-07-19 2017-08-06 2017-08-24 2017-09-05 2017-10-17 2017-10-10 2017-11-16 2018-04-08 Manutencao de Rodovias Grupo Envelope Rehabilitation and Maintenance III Lotes 1 e 2 BR-SEINFRA-BA-18672-CW- Component 2: Performance- RFB / Obras de Restauracao e Single Stage - One IBRD / 85800 based State Highway Prior Request for Bids Open - International 42,587,247.00 27,214,572.61 Signed 2017-06-20 2017-07-13 2017-06-25 2017-07-19 2017-08-06 2017-08-24 2017-09-05 2017-10-17 2017-10-10 2017-11-21 2018-04-08 Manutencao de Rodovias Grupo Envelope Rehabilitation and Maintenance IV Lotes 1 e 2 GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEINFRA-BA-54599-GO- ã RFB / Aquisiço ã e Manutenço Single Stage - One Pending IBRD / 85800 Component 4: Road Safety Post Request for Bids Open - National 2,591,463.00 0.00 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2021-06-23 de Equipamentos de Controle de Envelope Implementation Velocidade BR-SEINFRA-BA-54600-GO- Single Stage - One Pending RFB / Aquisiçoã e Manutencao IBRD / 85800 Component 4: Road Safety Post Request for Bids Open - National 500,000.00 0.00 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2020-12-25 Envelope Implementation de Etilômetros Ativos e Passivos BR-SEINFRA-BA-55182-GO- õ s e RFB / Instalaçe Single Stage - One Pending Equipamentos de Escritório para IBRD / 85800 Component 4: Road Safety Post Request for Bids Open - National 100,000.00 0.00 2018-03-21 2018-03-26 2018-05-07 2018-06-06 2018-07-11 2019-07-06 Envelope Implementation Agência-Líder em Segurança Viária NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEINFRA-BA-18633-NC- RFB / NCB Nº 001/2017 - ã Prestaço de serviços de Levantamento de Condiçe õ s de õ s de Superfície, Mediçe Component 1: : Institutional Single Stage - One IBRD / 85800 Post Request for Bids Open - National 1,676,829.00 0.00 Canceled 2017-06-19 2017-06-19 2017-07-18 2017-07-18 2017-08-07 2017-09-21 2017-09-07 2018-03-06 Deflexões Recuperáveis e Strengthening Envelope Irregularidade Longitudinal da Superfície dos pavimentos da malha rodoviária estadual pavimentada da Bahia. BR-SEINFRA-BA-54596-NC- RFP / Operacionalizaço ã do Sistema de Gestão de Pavimentos(SGP): Mediço ã de Irregularidade (IRI), de Deflexão Component 1: : Institutional Request for Single Stage - One Pending Recuperável (FWD) e das IBRD / 85800 Prior Open - National 914,634.00 0.00 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2023-06-13 Strengthening Proposals Envelope Implementation Condiçeõ s do Pavimento através Levantamento Visual Contínuo (LVC-DNIT PRO08/2004) ou Í dice de Gravidade Global (IGG - n DNIT) BR-SEINFRA-BA-54597-NC- ã RFP / Implantaço de Sistema Automático de Contagem de Request for Single Stage - One Pending IBRD / 85800 Component 4: Road Safety Post Open - National 1,829,268.00 0.00 2018-07-01 2018-07-06 2018-08-17 2018-09-16 2018-10-21 2021-10-05 ã Tráfego e Implantaço de Proposals Envelope Implementation Sistema Automático de Pesagem de Veículos. BR-SEINFRA-BA-54598-NC- RFP / Georreferenciamento de Ativos da Faixa de Domínio e Request for Single Stage - One Pending IBRD / 85800 Component 4: Road Safety Post Open - National 1,317,707.00 0.00 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2021-06-23 ã Contrataço de Empresa para Proposals Envelope Implementation Fiscalizaçoã da Faixa de Domínio BR-SEINFRA-BA-55181-NC- ã RFP / Implantaço de Marcos Component 1: : Institutional Request for Single Stage - One Pending IBRD / 85800 Post Open - National 792,683.00 0.00 2018-03-21 2018-03-26 2018-05-07 2018-06-06 2018-07-11 2019-07-06 Quilométricos em Toda Rede Strengthening Proposals Envelope Implementation Pavimentada CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Road Safety Component 3: Feeder Road Improvement Component 2: Performance- 7.179/2014 / Engineering Design based State Highway and Supervision of Road Rehabilitation and Maintenance Quality And Cost- IBRD / 85800 Prior Open - International N 0.00 1,512,085.26 Signed 2016-03-01 2016-04-19 Rehabilitation and Maintenance Component 1: : Institutional Based Selection Works Strengthening Front End Fee Unallocated Component 5: Project Management MI - 001/2017 / Manutencao do Plano Diretor de Logistica de Transportes, visando a atualizacao do conjunto de Component 1: : Institutional Quality And Cost- Pending IBRD / 85800 Prior Open - International 2,134,146.00 0.00 2017-06-07 2017-06-30 2017-08-13 2017-09-10 2017-10-10 2017-11-14 2017-12-19 2018-12-19 investimentos em infraestrutura Strengthening Based Selection Implementation de logistica de transportes apresentado no PDLT. BR-SEINFRA-BA-18582-CS- Component 2: Performance- QCBS / Execucao de Projeto de Quality And Cost- IBRD / 85800 based State Highway Prior Open - International 2,510,976.00 2,355,627.43 Signed 2017-07-13 2017-08-03 2017-09-16 2017-10-14 2017-11-13 2017-08-10 2017-12-18 2017-11-03 2018-01-22 2017-12-15 2019-01-22 Engenharia e Supervisao das Based Selection Rehabilitation and Maintenance Obras do CREMA GRUPO V BR-SEINFRA-BA-24799-CS- Component 2: Performance- QCBS / Execucao de Projeto de Quality And Cost- IBRD / 85800 based State Highway Prior Open - International 2,203,480.00 1,562,872.77 Signed 2017-08-14 2017-09-04 2017-10-18 2017-11-15 2017-07-17 2017-12-15 2018-01-19 2017-10-30 2018-02-23 2018-01-18 2021-02-07 Engenharia e Supervisao das Based Selection Rehabilitation and Maintenance obras do CREMA Grupo VI BR-SEINFRA-BA-24801-CS- Component 2: Performance- LCS / Execucao de Projeto de IBRD / 85800 based State Highway Post Least Cost Selection Open - International 1,427,143.00 1,352,485.88 Signed 2017-08-15 2016-10-21 2017-09-05 2017-10-19 2016-12-23 2017-11-16 2017-07-20 2017-12-16 2017-08-28 2018-01-20 2017-08-28 2018-02-24 2017-11-27 2021-02-08 Engenharia e Supervisao das Rehabilitation and Maintenance Obras do CREMA GRUPO VII BR-SEINFRA-BA-24802-CS- Component 2: Performance- LCS / Execucao de Projeto de IBRD / 85800 based State Highway Post Least Cost Selection Open - International 1,427,241.00 490,313.16 Signed 2017-08-15 2016-10-18 2017-09-05 2017-10-19 2016-12-23 2017-11-16 2017-07-20 2017-12-16 2017-08-18 2018-01-20 2017-09-06 2018-02-24 2017-11-27 2018-08-23 Engenharia e Supervisao das Rehabilitation and Maintenance Obras do CREMA - Grupo VIII BR-SEINFRA-BA-24803-CS- QCBS / Implantacao de um Component 1: : Institutional Quality And Cost- Pending IBRD / 85800 Post Open - International 313,480.00 0.00 2017-09-02 2017-09-23 2017-11-06 2017-12-04 2018-01-03 2018-02-07 2018-03-14 2019-03-14 Sistema de Base de Dados de Strengthening Based Selection Implementation Jazidas BR-SEINFRA-BA-24805-CS- QCBS / Suporte para Component 1: : Institutional Quality And Cost- Pending Implantacao de Reorganizacao IBRD / 85800 Post Open - International 344,828.00 0.00 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-02-06 2018-03-13 2018-12-08 Strengthening Based Selection Implementation Funcional da Superintendencia de Infraestrutura de Transportes BR-SEINFRA-BA-24809-CS- QCBS / Operacionalizacao do Sistema de Gestao de Component 1: : Institutional Quality And Cost- Pending IBRD / 85800 Post Open - International 313,480.00 0.00 2017-10-01 2017-10-22 2017-12-05 2018-01-02 2018-02-01 2018-03-08 2018-04-12 2024-03-11 Pavimentos (SGP) - Suporte para Strengthening Based Selection Implementation a Gestao/Atualizacao do Sistema Informatizado BR-SEINFRA-BA-24812-CS- QCBS / Estudo para Component 1: : Institutional Quality And Cost- Pending IBRD / 85800 Post Open - International 407,524.00 0.00 2018-01-02 2018-01-23 2018-03-08 2018-04-05 2018-05-05 2018-06-09 2018-07-14 2019-07-09 Readequacao da Malha Strengthening Based Selection Implementation Ferroviaria Estadual BR-SEINFRA-BA-24819-CS- QCBS / Estudo para Component 1: : Institutional Quality And Cost- Pending IBRD / 85800 Post Open - International 758,621.00 0.00 2018-01-02 2018-01-23 2018-03-08 2018-04-05 2018-05-05 2018-06-09 2018-07-14 2019-07-09 Potencializacao da Ferrovia de Strengthening Based Selection Implementation Integracao Oeste-Leste (FIOL) BR-SEINFRA-BA-24823-CS- QCBS / Estudo para Component 1: : Institutional Quality And Cost- Pending IBRD / 85800 Post Open - International 344,828.00 0.00 2018-01-02 2018-01-23 2018-03-08 2018-04-05 2018-05-05 2018-06-09 2018-07-14 2019-07-09 Potencializacao de Novos Strengthening Based Selection Implementation Terminais BR-SEINFRA-BA-24831-CS- Component 1: : Institutional Quality And Cost- Pending IBRD / 85800 Post Open - International 344,828.00 0.00 2017-10-01 2017-10-22 2017-12-05 2018-01-02 2018-02-01 2018-03-08 2018-04-12 2019-04-07 QCBS / Estudo sobre Biomassa Strengthening Based Selection Implementation BR-SEINFRA-BA-24859-CS- QCBS / Estudo de Component 1: : Institutional Quality And Cost- Pending IBRD / 85800 Post Open - International 344,828.00 0.00 2017-08-14 2017-09-04 2017-10-18 2017-11-15 2017-12-15 2018-01-19 2018-02-23 2018-12-20 Potencialidades da Faixa de Strengthening Based Selection Implementation Dominio BR-SEINFRA-BA-24881-CS- QCBS / Pesquisa de Satisfacaoo dos Usuarios das Rodovias Component 1: : Institutional Quality And Cost- Pending IBRD / 85800 Post Open - National 413,793.00 0.00 2017-08-14 2017-09-04 2017-10-18 2017-11-15 2017-12-15 2018-01-19 2018-02-23 2019-02-18 Estaduais com os Resultados a Strengthening Based Selection Implementation Serem Publicados no Site da SEINFRA/SIT BR-SEINFRA-BA-24888-CS- QCBS / Banco de Dados sobre Quality And Cost- Pending Seguranca Viaria e Sistema de IBRD / 85800 Component 4: Road Safety Prior Open - International 2,000,000.00 0.00 2017-08-14 2017-09-04 2017-10-18 2017-11-15 2017-12-15 2018-01-19 2018-02-23 2019-08-17 Based Selection Implementation Policiamento - Re- Desenvolvimento e Treinamento BR-SEINFRA-BA-24997-CS- QCBS / Estabelecimento de Planos e Documentaço ã para Criar Agencia Lider em Segurança Viaria / Quality And Cost- Pending IBRD / 85800 Component 4: Road Safety Post Open - International 246,771.00 0.00 2018-06-05 2018-06-26 2018-08-09 2018-09-06 2018-10-06 2018-11-10 2018-12-15 2019-12-10 Desenvolvimento de Estrategia Based Selection Implementation de Longo Prazo para Seguranca Viaria / Monitoramento e Auditoria dos Resultados dos Programas de Segurança Viaria Page 2 BR-SEINFRA-BA-25004-CS- QCBS / Treinamento em Quality And Cost- Pending Seguranca Viaria do Pessoal da IBRD / 85800 Component 4: Road Safety Post Open - National 300,000.00 0.00 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2019-02-19 Based Selection Implementation SIT, Policia Rodoviaria e dos Municipios BR-SEINFRA-BA-25007-CS- QCBS / Execucao Projeto para Obras Corredores-Piloto Seguranca Viaria Lote 1: BA502 (Feira de Santana a BR101) Component 5: Project Quality And Cost- Pending IBRD / 85800 Post Open - International 651,950.00 0.00 2017-09-02 2017-09-23 2017-11-06 2017-12-04 2018-01-03 2018-02-07 2018-03-14 2018-07-12 Lote 2: BR420 (BR324 a Sao Management Based Selection Implementation Felix) Lote 3 - BA262 (Vitoria da Conquista a Brumado) Lote 4 - BA-263(Conquista a Itambe) BR-SEINFRA-BA-25012-CS- QCBS / Programa de Component 1: : Institutional Quality And Cost- Pending IBRD / 85800 Post Open - National 689,655.00 0.00 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2021-02-08 Capacitacao da Consultoria do Strengthening Based Selection Implementation Pessoal da SEINFRA BR-SEINFRA-BA-25018-CS- Component 1: : Institutional Quality And Cost- Pending QCBS / Pesquisa Origem- IBRD / 85800 Post Open - International 1,137,931.00 0.00 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-02-06 2018-03-13 2019-01-07 Strengthening Based Selection Implementation Destino Ilhéus-Itabuna BR-SEINFRA-BA-25019-CS- Component 1: : Institutional Quality And Cost- Pending QCBS / Logistica Urbana Ilheus- IBRD / 85800 Post Open - International 344,828.00 0.00 2018-01-02 2018-01-23 2018-03-08 2018-04-05 2018-05-05 2018-06-09 2018-07-14 2019-07-09 Strengthening Based Selection Implementation Itabuna BR-SEINFRA-BA-24212-CS- QCBS / PDLT Manutencao do Component 1: : Institutional Quality And Cost- Pending IBRD / 85800 Post Open - National 1,410,658.00 0.00 2017-08-07 2017-08-28 2017-10-11 2017-11-08 2017-12-08 2018-01-12 2018-02-16 2019-02-16 Plano Diretor de Logistica de Strengthening Based Selection Implementation Transportes BR-SEINFRA-BA-24995-CS- FBS / Operacionalizacao e Component 1: : Institutional Fixed Budget Pending Desenvolvimento do Sistema de IBRD / 85800 Post Open - International 313,480.00 0.00 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2019-02-19 Strengthening Selection Implementation Gestao de Obras de Arte Especiais BR-SEINFRA-BA-25000-CS- Consultant CQS / Auditoria / Fiscalizacao Pending IBRD / 85800 Component 4: Road Safety Post Qualification Open - International 50,000.00 0.00 2017-11-02 2017-11-23 2018-01-06 2018-02-05 2018-03-12 2020-08-28 para Obras dos Corredores-Piloto Implementation Selection de Segurança Viaria BR-SEINFRA-BA-24211-CS- QCBS / PDLT Atualizacao do Component 1: : Institutional Quality And Cost- Under IBRD / 85800 Post Open - International 1,692,790.00 0.00 2017-08-07 2017-04-18 2017-08-28 2017-10-11 2017-10-02 2017-11-08 2017-11-21 2017-12-08 2017-12-19 2018-01-12 2018-02-02 2018-02-16 2019-02-16 Plano Diretor de Logistica de Strengthening Based Selection Implementation Transportes BR-SEINFRA-BA-24213-CS- LCS / iRAP Levantamento, Pending IBRD / 85800 Component 4: Road Safety Post Least Cost Selection Open - International 1,250,000.00 0.00 2017-08-07 2017-08-28 2017-10-11 2017-11-08 2017-12-08 2018-01-12 2018-02-16 2018-08-15 Codificacao e Analise de 4200 Implementation km BR-SEINFRA-BA-32915-CS- QCBS / Supervisão Ambiental: Component 2: Performance- Quality And Cost- ã apoio à Coordenaço de Meio IBRD / 85800 based State Highway Prior Open - International 2,037,618.00 0.00 Under Review 2017-10-19 2017-11-09 2017-12-23 2018-01-20 2017-02-06 2018-02-19 2018-03-26 2018-04-30 2019-04-30 Based Selection Ambiente nas Obras de CREMA Rehabilitation and Maintenance e em Vicinais BR-SEINFRA-BA-24873-CS- ã CDS / Metodologia de Avaliaço Component 1: : Institutional Quality And Cost- Pending do Impacto Socioeconômico IBRD / 85800 Post Open - National 344,828.00 0.00 2018-03-16 2018-04-06 2018-05-20 2018-06-17 2018-07-17 2018-08-21 2018-09-25 2019-09-25 Strengthening Based Selection Implementation õ s Provocado pelas Intervençe nas Estradas Vicinais BR-SEINFRA-BA-24854-CS- QCBS / Consultoria para Component 1: : Institutional Quality And Cost- Manuais Técnicos da IBRD / 85800 Post Open - International 344,828.00 0.00 Canceled 2017-08-14 2017-09-04 2017-10-18 2017-11-15 2017-12-15 2018-01-19 2018-02-23 2024-01-23 Strengthening Based Selection Coordenacao de Meio Ambiente (CMAM) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEINFRA-BA-25022-CS- INDV / Reforço da Diretoria de Component 3: Feeder Road Individual Consultant Pending IBRD / 85800 Post Limited 192,000.00 0.00 2017-10-02 2017-10-07 2017-10-28 2017-12-02 2019-11-22 Construcoes e Manutencao - Improvement Selection Implementation Apoio as Obras Vicinais BR-SEINFRA-BA-25023-CS- Component 1: : Institutional Individual Consultant Pending INDV / Estabelecimento do IBRD / 85800 Post Open 10,282.00 0.00 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2018-06-13 Strengthening Selection Implementation Regimento do Fundo Rodoviario BR-SEINFRA-BA-25024-CS- INDV / Reforço da Diretoria de Component 3: Feeder Road Individual Consultant Pending IBRD / 85800 Post Open 192,267.00 0.00 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2019-12-06 Construcoes e Manutencao - Improvement Selection Implementation Apoio Vicinais BR-SEINFRA-BA-25025-CS- Component 2: Performance- Individual Consultant Pending INDV / Biologo para Reforco da IBRD / 85800 based State Highway Post Open 96,000.00 0.00 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2019-02-09 Selection Implementation Coordenacao de Meio Ambiente Rehabilitation and Maintenance BR-SEINFRA-BA-25026-CS- INDV / Estatistico para Reforco Individual Consultant Pending IBRD / 85800 Component 4: Road Safety Post Open 96,000.00 0.00 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2018-12-10 da Diretoria de Operacoes e Selection Implementation Trafego BR-SEINFRA-BA-25027-CS- INDV / Auditoria Tecnica da PPP- Component 2: Performance- Individual Consultant Pending CREMA, apoio a AGERBA e IBRD / 85800 based State Highway Post Open 192,000.00 0.00 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2019-12-05 Selection Implementation SEINFRA na execucao do Rehabilitation and Maintenance contrato Page 3 BR-SEINFRA-BA-25028-CS- INDV / Especialista em Procedimentos e Controles Component 5: Project Individual Consultant Pending IBRD / 85800 Post Open 84,639.00 0.00 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2018-12-10 Internos para Reforco do Management Selection Implementation Gabinete da Superinetencia de Infraestrutura de Transportes BR-SEINFRA-BA-25029-CS- INDV / Estudo de Longo Prazo Component 1: : Institutional Individual Consultant Pending IBRD / 85800 Post Open 25,705.00 0.00 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2018-12-10 para Estruturacao do Fundo Strengthening Selection Implementation Rodoviario BR-SEINFRA-BA-24800-CS- CDS / iRAP - Controle e Pending Auditoria dos Processos de IBRD / 85800 Component 4: Road Safety Post Direct Selection Direct 156,740.00 0.00 2017-08-14 2017-08-24 2017-10-28 2018-10-23 Implementation Levantamento, Analise e Codificacao de Seguranca Viaria BR-SEINFRA-BA-54437-CS- ã INDV / Reforço da Coordenaço Component 1: : Institutional Individual Consultant Pending IBRD / 85800 Post Open 106,707.00 0.00 2018-05-07 2018-06-25 2018-07-16 2018-08-20 2019-02-16 de Meio Ambiente (CMAM) - Strengthening Selection Implementation Manuais Técnicos Page 4