21-Dec-2019 Date:______________________ H.E Geraldo João Martins Minister of Economy and Finances Ministry of Economy and Finances Av. Amilcar Cabral, Caixa Postal n. 67 Bissau, Guinea Bissau Subject: Guinea-Bissau: OMVG Interconnection Project Credit No. 5661-GW Amendment to Financing Agreement Excellency: 1. We refer to the Financing Agreement (the “Agreement”), dated June 23, 2015, between the Republic of Guinea Bissau (“Recipient”) and the International Development Association (“Association”). We also refer to your letter of August 22, 2019, requesting specific modifications to the Agreement. Please note that the capitalized terms used in this letter ("Amendment") and not defined herein have the meanings ascribed to them in the Agreement as applicable. 2. We are pleased to inform you that the Association proposes to amend the Agreement as follows: (a) The table in Section IV.A.2 of the Agreement is deleted and replaced in its entirety with the attached Annex 1 to this Amendment. (b) Section 1 of the Appendix is hereby amended to add the following definition and the remaining definitions are renumbered to maintain alphabetical order. “Resettlement Costs” means the allocated amount to cover the actual cash compensation costs associated with implementation of the OMVG Resettlement Action Plan for the OMVG Transmission Line in Guinea Bissau. 3. All the terms and conditions of the Agreement that have not been amended hereby shall remain unchanged and in full force and effect. 1818 H Street NW  Washington, DC 20433 USA -2- 4. Please confirm your agreement with the foregoing amendment, on behalf of the Recipient, by signing, dating and returning to the Association the enclosed copy of this Amendment. This Amendment shall become effective as of the date of its countersignature. Very truly yours, INTERNATIONAL DEVELOPMENT ASSOCIATION ______________________________________ Deborah L. Wetzel Director of Regional Integration Africa and Middle East & North Africa AGREED AND CONFIRMED: REPUBLIC OF GUINEA-BISSAU By :__________________________ H.E Geraldo João Martins Minister of Economy and Finances 21-Dec-2019 Date :__________________________ -3- Annex 1 Amount of the Credit Percentage of Allocated Expenditures to be Category (expressed in SDR ) Financed (inclusive of Taxes) (1) Goods, works, non-consulting services, 47,528,000.00 100% and consultants’ services for (a) Part 1.1 (i) of the Project for part of Lot 5: Mansoa – Tanaf, Mansoa-Bissau, Bambadinca-Mansoa, Saltinho-Bambadinca and Boké – Saltinho; and (b) Part 1.2(i) of the Project (2) Goods, works, non-consulting services, 1,500,000 100% and consultants’ services for Part 2.1 (ii) of the Project (3) Goods, works, non-consulting services, 100% and consultants’ services for Part 2.2 of the Project (a) for the first disbursement for Part 2.2 of the 700,000 Project 500,000 (b) for the second disbursement for Part 2.2 of the Project 400,000 (c) for the third disbursement for Part 2.2 of the Project 300,000 (d) for the fourth disbursement for Part 2.2 of the Project 200,000 (e) for the fifth disbursement for Part 2.2 of the Project (4) Resettlement Costs under Part 1(i) and (ii) - 4,372,000.00 100% TOTAL AMOUNT 55,500,000 /s1/ /s2/ /n2/ /t2/ /d2/