Public Disclosure Copy The World Bank Implementation Status & Results Report Lao PDR Southeast Asia Disaster Risk Management Project (P160930) Lao PDR Southeast Asia Disaster Risk Management Project (P160930) EAST ASIA AND PACIFIC | Lao People's Democratic Republic | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 1 | APPROVED | ISR29183 | Implementing Agencies: Key Dates Key Project Dates Bank Approval Date:06-Jul-2017 Effectiveness Date:-- Planned Mid Term Review Date:24-Feb-2020 Actual Mid-Term Review Date:-- Original Closing Date:31-Oct-2022 Revised Closing Date:31-Oct-2022 Project Development Objectives Project Development Objective (from Project Appraisal Document) To reduce the impacts of flooding in Muang Xay and enhance the Government’s capacity to provide hydro-meteorological services and disaster response. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Integrated Urban Flood Risk Management:(Cost $13.50 M) Hydromet Modernization and Early Warning Systems:(Cost $10.00 M) Financial Planning for Disaster Resilience:(Cost $6.00 M) Knowledge and Coordination:(Cost $1.50 M) Contingent Emergency Response Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  --  Satisfactory Overall Implementation Progress (IP)  --  Satisfactory Overall Risk Rating  --  Substantial 8/23/2017 Page 1 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Lao PDR Southeast Asia Disaster Risk Management Project (P160930) Implementation Status and Key Decisions The project was approved by the World Bank Board on July 6, 2017. Steps towards meeting effectiveness conditions are being taken. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Substantial  --  Substantial Macroeconomic  Substantial  --  Substantial Sector Strategies and Policies  Moderate  --  Moderate Technical Design of Project or Program  Substantial  --  Substantial Institutional Capacity for Implementation and Sustainability  Substantial  --  Substantial Fiduciary  High  --  High Environment and Social  Moderate  --  Moderate Stakeholders  Moderate  --  Moderate Other  --  --  -- Overall  Substantial  --  Substantial Results Project Development Objective Indicators PHINDPDOTBL  Percentage of urban population in Muang Xay protected from floods (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 -- 30.00 70.00 Date 30-Jun-2017 -- 31-Jul-2017 30-Jun-2022 PHINDPDOTBL  of which are female (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target 8/23/2017 Page 2 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Lao PDR Southeast Asia Disaster Risk Management Project (P160930) Value 50.00 -- 50.00 50.00 PHINDPDOTBL  Satisfaction of weather information end-users increased (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 30-Jun-2017 -- 31-Jul-2017 30-Jun-2022 PHINDPDOTBL  Lao PDR has information and capacity to access sovereign disaster risk insurance (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 30-Jun-2017 -- 31-Jul-2017 30-Jun-2022 Overall Comments Intermediate Results Indicators PHINDIRITBL  Length of embankment rehabilitated (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 8.00 Date 30-Jun-2017 -- 31-Jul-2017 30-Jun-2022 8/23/2017 Page 3 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Lao PDR Southeast Asia Disaster Risk Management Project (P160930) PHINDIRITBL  Risk informed spatial and urban plans for a city in the Nam Ou Basin developed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 30-Jun-2017 -- 31-Jul-2017 30-Jun-2022 PHINDIRITBL  Accuracy of weather forecast improved (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 30-Jun-2017 -- 31-Jul-2017 30-Jun-2022 PHINDIRITBL  Validated hydormet data is accessible on a centralized online data management platform (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 30-Jun-2017 -- 31-Jul-2017 30-Jun-2022 PHINDIRITBL  National disaster risk finance strategy developed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 30-Jun-2017 -- 31-Jul-2017 30-Jun-2022 8/23/2017 Page 4 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Lao PDR Southeast Asia Disaster Risk Management Project (P160930) PHINDIRITBL  Participants in consultation activities during project implementation (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 500.00 Date 02-Oct-2017 -- 31-Jul-2017 30-Jun-2022 PHINDIRITBL  of which women (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 40.00 PHINDIRITBL  Grievances registered related to delivery of project benefits addressed (%) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 Date 30-Jun-2017 -- 31-Jul-2017 30-Jun-2022 PHINDIRITBL  Grievances related to delivery of project benefits that are addressed-(number) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 100.00 Overall Comments 8/23/2017 Page 5 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Lao PDR Southeast Asia Disaster Risk Management Project (P160930) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed Not P160930 IDA-61200 USD 30.00 30.00 0.00 0.00 30.79 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P160930 IDA-61200 06-Jul-2017 -- -- 31-Oct-2022 31-Oct-2022 Effective Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) 8/23/2017 Page 6 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Lao PDR Southeast Asia Disaster Risk Management Project (P160930) There are no related projects. 8/23/2017 Page 7 of 7 Public Disclosure Copy