Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Brazil : BRAZIL BAHIA SUSTAINABLE RURAL DEVELOPMENT PROJECT PLAN General Information Country: Brazil Banks Approval Date of the Original Procurement Plan: 2017-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-06-26 Project ID: P147157 GPN Date: Project Name: BRAZIL BAHIA SUSTAINABLE RURAL DEVELOPMENT PROJECT Loan / Credit No: IBRD / 84150 Executing Agency(ies): Company for Development and Regional Affairs of the State of Bahia, Company for Water Engeneering and for Sanitation of Bahia, Luis Eduardo Magalhaes Foundation WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-NA-155-O-#TIT_LPN# / Obras para os subprojetos de Post Request for Bids Open - National 8,796,992.00 0.00 Canceled 2015-06-08 2015-06-17 2015-06-19 2015-06-22 2015-07-01 2016-07-01 á ua e abastecimento de g esgotamento . BR-CERB-BA-24986-CW-RFP / Single Stage - One Pending ã NCB para Recuperaço e IBRD / 84150 Household Water and Sanitation Post Request for Bids Open - National 6,060,606.00 0.00 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 2019-05-19 Envelope Implementation ã Ampliaço de SAA 2018 BR-CERB-BA-24987-CW-RFP / Single Stage - One Pending ã NCB para implantaço de SAA IBRD / 84150 Household Water and Sanitation Post Request for Bids Open - National 11,666,667.00 0.00 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 2019-05-19 Envelope Implementation 2018 BR-CERB-BA-24985-CW-RFP / ã NCB 002/2017 para ampliaço e Single Stage - One adequaçoã de 51 de SAAs, 750 IBRD / 84150 Household Water and Sanitation Post Request for Bids Open - National 4,690,000.00 2,561,829.74 Signed 2017-08-30 2017-11-14 2017-11-30 2018-03-15 2017-11-14 2018-04-14 2018-04-05 2018-05-19 2018-06-07 2019-05-14 Envelope MSDS com serviço social (região central de Jacobina). BR-CERB-BA-24984-CW-RFP / NCB 003/2017 para adequaçoã e Single Stage - One ã ampliaço de 61 SAAs, 750 IBRD / 84150 Household Water and Sanitation Post Request for Bids Open - National 5,392,000.00 3,155,904.16 Signed 2017-08-30 2018-03-19 2017-11-30 2017-12-29 2018-01-22 2018-01-28 2018-02-07 2018-03-04 2018-05-28 2019-02-27 Envelope MSDs com serviço social (região da central de Seabra). BR-CERB-BA-55632-CW-RFB / ã NCB 001/2018 - Construço de Single Stage - One ã 150 poços - Em substituiço da IBRD / 84150 Household Water and Sanitation Post Request for Bids Open - National 1,192,357.00 1,009,110.36 Signed 2018-03-23 2018-02-09 2018-03-23 2018-04-03 2018-03-23 2018-03-12 2018-03-23 2018-03-13 2018-04-13 2018-03-23 2018-10-10 Envelope ã licitaço fracassada BR-CERB- BA-22146-CW-RFP. BR-CERB-BA-22146-CW-RFP / NCB 001/2017 PARA Single Stage - One IBRD / 84150 Household Water and Sanitation Post Request for Bids Open - National 1,818,182.00 0.00 Canceled 2017-08-30 2018-03-13 2017-09-04 2017-11-30 2017-12-30 2018-02-03 2018-08-02 CONSTRUÇOÃ DE POÇOS Envelope TUBULARES. GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-NA-227-B-#TIT_LPN# / Aquisiço ã de 100 veículos Prior Request for Bids Open - National 1,755,969.00 0.00 Canceled 2015-10-20 2015-11-03 2015-11-03 2015-11-10 2015-11-20 2016-05-20 utilitários, duas VANS e dois veículos tipo pick up. BR-CERB-BA-24488-GO-RFB / ã Aquisiço de materiais para Single Stage - One IBRD / 84150 Household Water and Sanitation Post Request for Bids Open - National 2,387,812.00 1,605,136.05 Signed 2017-08-30 2017-11-23 2017-09-04 2018-05-11 2017-12-12 2017-12-12 2018-01-11 2018-04-03 2018-02-15 2018-05-18 2018-08-14 sistemas, Pregão Eletrônico Envelope 170079 BR-CERB-BA-24487-GO-RFB / ã Aquisiço de materiais para Single Stage - One IBRD / 84150 Household Water and Sanitation Prior Request for Bids Open - National 4,386,797.00 0.00 Canceled 2017-12-27 2018-01-01 2018-02-12 2018-03-14 2018-04-18 2018-10-15 sistema, Pregão Eletrônico Envelope 170078 BR-CERB-BA-60625-GO-RFB / ã Aquisiço de materiais para Single Stage - One Under sistemas, Pregão Eletrônico IBRD / 84150 Household Water and Sanitation Prior Request for Bids Open - National 4,541,614.99 0.00 2018-05-11 2018-06-04 2018-05-11 2018-06-22 2018-07-22 2018-08-26 2019-02-22 Envelope Implementation ã 180024 (em substituiço ao BR- CERB-BA-24487-GO-RFB) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-CERB-BA-16687-NC-RFQ / Single Stage - One Pregão Eletrônico para Analises IBRD / 84150 Household Water and Sanitation Post Request for Bids Open - National 223,200.00 52,957.56 Signed 2017-08-30 2018-02-09 2017-09-04 2017-10-16 2018-03-13 2017-11-15 2018-03-12 2017-12-20 2018-04-09 2018-12-15 Envelope Á ua. Fisico Quimica de g BR-CERB-BA-26127-NC-RFB / Pregão Eletrônico para Testes de Single Stage - One IBRD / 84150 Household Water and Sanitation Post Request for Bids Open - National 230,000.00 170,530.29 Signed 2017-08-30 2018-02-09 2017-09-04 2017-10-16 2018-03-14 2017-11-15 2018-03-09 2017-12-20 2018-04-17 2018-10-16 Bombeamento de poços Envelope existentes. BR-FLEM-29324-NC-RFQ / Institutional Development, ã Contrataço de empresa de Request for Single Stage - One Pending IBRD / 84150 Technical Assistance and Post Limited 96,153.85 0.00 2017-12-08 2018-02-17 2019-02-12 ã prestaço de serviços para Quotations Envelope Implementation Project Management vídeos para TV e Mídias Sociais. BR-NA-279-S-LOC / Institutional Development, ã Contrataço de empresa para Pending IBRD / 84150 Technical Assistance and Post E-Auctions Open 320,512.82 0.00 2017-10-16 2017-11-04 2017-12-09 2018-06-07 coleta de dados para a Linha de Implementation Project Management Base do Projeto Bahia Produtiva. Page 1 BR-FLEM-29322-NC-RFQ / ã Contrataço de empresa para Institutional Development, Request for Single Stage - One Pending ã prestaço de serviços de IBRD / 84150 Technical Assistance and Post Open - National 174,000.00 0.00 2018-05-30 2018-07-09 2018-12-06 Quotations Envelope Implementation ã regularizaço fundiária e Project Management ambiental. BR-CERB-BA-65686-NC-RFB / Pregao Eletronico para Single Stage - One Pending IBRD / 84150 Household Water and Sanitation Post Request for Bids Open - National 236,593.06 0.00 2018-07-30 2018-08-04 2018-09-15 2018-10-15 2018-11-19 2019-05-18 Contratacao de Servico de Envelope Implementation Topografia. BR-CERB-BA-66382-NC-RFB / Pregão eletrônico para Single Stage - One Pending IBRD / 84150 Household Water and Sanitation Post Request for Bids Open - National 236,593.06 0.00 2018-07-30 2018-08-04 2018-09-15 2018-10-15 2018-11-19 2019-05-18 ã Contrataço de Serviço de Envelope Implementation Geotécnia. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-NA-70-CF-SBCC / ã Contrataço de empresa Quality And Cost- Pending especializada para fiscalizar a Post Open - National 172,000.00 0.00 2014-11-03 2014-11-03 2014-11-03 2014-11-03 2015-12-31 Based Selection Implementation ã execuço dos subprojetos de abastecimento de gá ua. BR-NA-225-CF-SCC / ã Contrataço de empresa Institutional Development, Consultant especializada para prestaçoã de Under Technical Assistance and Post Qualification Open - National 815,789.00 0.00 2016-01-05 2016-02-23 2017-02-23 serviços de Assistência Técnica Implementation Project Management Selection Agropecuária e Extensão Rural (Equipe Multidisciplinar). BR-NA-280-CF-SCC / Contrataçoã de empresa para a ã elaboraço dos Planos de Negócios dos empreendimentos Consultant coletivos dos Editais voltados Post Qualification Open - National 552,632.00 0.00 Canceled 2016-11-10 2016-12-19 2017-12-19 aos Subprojetos Orientados para Selection o Mercado referentes ao Componente 01- Inclusão Produtiva e Acesso a Mercados. BR-NA-68-CF-SBCC / ã Contrataço de empresa Quality And Cost- especializada para elaborar e Post Open - National 258,000.00 0.00 Canceled 2015-12-01 2016-01-04 2016-01-06 2016-01-08 2015-03-31 Based Selection analisar subprojetos de abastecimento de g á ua BR-FLEM-26542-CS-CQS / ã Contrataço de Empresa para o Institutional Development, Consultant Pending Desenvolvimento de Sistema de IBRD / 84150 Technical Assistance and Post Qualification Open - National 128,205.13 0.00 2017-09-06 2017-09-16 2017-10-01 2017-10-16 2017-11-15 2018-11-10 Implementation Compras que será utilizado no Project Management Selection â bito dos Subprojetos. m BR-NA-284-CF-SCC / Contrataço ã de empresa para Consultant elaboraço ã do plano de Post Qualification Open - National 20,000.00 0.00 Canceled 2016-10-04 2016-11-18 2017-11-18 emancipaço ã dos distritos de Selection ã . irrigaço BR-NA-283-CF-SCC / Contrataçoã de empresa para a Consultant ã realizaço de estudo, análise, Post Qualification Open - National 20,000.00 0.00 Canceled 2016-09-23 2016-11-18 2017-11-18 ã formaço e acompanhamento Selection dos subprojetos das cadeias produtivas do Bahia Produtiva. BR-NA-285-CF-SCC / ã Contrataço de empresa para Consultant ã formaço dos Conselhos Post Qualification Open - National 20,000.00 0.00 Canceled 2016-09-14 2016-10-28 2016-10-28 Municipais por meio de Selection plataforma EAD. BR-FLEM-29323-CS-CQS / Institutional Development, Consultant Contrataço ã de empresa para Pending IBRD / 84150 Technical Assistance and Post Qualification Open - National 128,205.12 0.00 2017-09-24 2017-10-15 2017-11-28 2017-12-28 2018-02-01 2018-04-02 prestaço ã de serviços de Implementation Project Management Selection ã Avaliaço de Meio Termo. BR-CERB-BA-38782-CS-QCBS ã / Consultoria para delimitaço de Quality And Cost- perímetro de segurança da IBRD / 84150 Household Water and Sanitation Post Open - National 270,000.00 0.00 Canceled 2017-11-30 2018-02-20 2018-04-05 2018-05-03 2018-06-02 2018-07-07 2018-08-11 2019-08-11 Based Selection provincia uranifera de Caétite/Lagoa Real. BR-FLEM-64080-CS-CQS / Contrataço ã de empresa para ã realizaço õ s e atividades de açe de apoio à concepço ã , Institutional Development, Consultant Pending elaboraço ã , gestão e IBRD / 84150 Technical Assistance and Post Qualification Open - National 61,778.53 0.00 2018-05-29 2018-06-12 2018-07-17 2018-07-22 2018-08-04 2020-07-24 Implementation implementaço ã do Plano de Project Management Selection ã Aço para Promoço ã de Segurança Alimentar e Nutricional. BR-CERB-BA-24988-CS-QCBS Under IBRD / 84150 Household Water and Sanitation Post Least Cost Selection Open - National 3,065,330.00 0.00 2018-06-30 2018-06-07 2018-07-21 2018-09-03 2018-10-01 2018-10-31 2018-12-05 2019-01-09 2020-01-04 õ s Sociais / Consultoria para Açe Implementation BR-CERB-BA-24990-CS-QCBS Pending / Consultoria para Supervisão de IBRD / 84150 Household Water and Sanitation Post Least Cost Selection Open - National 3,282,646.29 0.00 2018-06-30 2018-07-21 2018-09-03 2018-10-01 2018-10-31 2018-12-05 2019-01-09 2020-01-04 Implementation Obras e Elaboraçoã de Projetos BR-CERB-BA-26128-CS-QCBS Quality And Cost- ã / Consultoria para elaboraço de IBRD / 84150 Household Water and Sanitation Post Open - National 1,000,000.00 0.00 Canceled 2017-09-30 2017-10-21 2017-12-04 2018-01-01 2018-01-31 2018-03-07 2018-04-11 2019-04-06 Based Selection projetos. Page 2 BR-CERB-BA-67167-CS-QCBS ã / Consultoria para delimitaço de Quality And Cost- Pending perímetro de segurança da IBRD / 84150 Household Water and Sanitation Post Open - National 721,585.71 0.00 2018-06-19 2018-09-09 2018-10-23 2018-11-20 2018-12-20 2019-01-24 2019-02-28 2020-02-28 Based Selection Implementation provincia uranifera de Caétite/Lagoa Real. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-NA-183-CI-3CV / ã Contrataço de consultoria para prestar serviços de capacitaço ã ao Projeto Bahia Produtiva, com o objetivo de apoiar o Individual Consultant Under Post Limited 63,000.00 0.00 2015-07-30 2017-07-30 planejamento, implementaço ã , Selection Implementation acompanhamento e avaliaço ã dos processos de capacitaço ã de gestores, colaboradores e equipe ã BR-NA-65-CI-IC / Contrataço de consultoria para o Individual Consultant Pending Desenvolvimento de Designer e Post Limited 10,000.00 0.00 2014-08-01 2015-12-31 Selection Implementation embalagens da agricultura familiar BR-NA-203-CI-IC / Contrataçoã de consultor para desenvolvimento de sistema Individual Consultant Pending Post Limited 40,000.00 0.00 2015-10-16 2016-01-16 ã informatizado para elaboraço de Selection Implementation projetos de desenvolvimento subterritorial. BR-NA-229-CI-IC / Assessorar a equipe do Projeto Bahia Produtiva no processo de ã seleço de profissionais especializados em Planos de Individual Consultant Under Post Limited 60,000.00 0.00 2016-01-11 2017-01-11 Negócios, orientar e acompanhar Selection Implementation ã a elaboraço dos Planos de Negócios por esses profissionais. O consultor também irá supervisi BR-NA-208-CI-IC / Análise e Individual Consultant estudo da cadeia produtiva de Post Limited 10,000.00 0.00 Canceled 2015-11-30 2016-11-30 Selection fruticultura. BR-NA-188-CI-IC / Análise e Individual Consultant estudo da cadeia produtiva de Post Limited 25,000.00 0.00 Canceled 2015-06-01 2015-10-01 Selection bovinocultura do leite. BR-NA-206-CI-IC / Análise e Individual Consultant estudo da cadeia produtiva de Post Limited 10,000.00 0.00 Canceled 2015-11-30 2016-11-30 Selection oleaginosas. BR-NA-182-CI-IC / Estudo e mapeamento do potencial hídrico Individual Consultant dos municípios de abrangência Post Limited 40,000.00 0.00 Canceled 2015-05-19 2016-11-19 Selection do componente 2 do Projeto Bahia Produtiva. BR-NA-209-CI-3CV / Análise e Individual Consultant estudo da cadeia produtiva de Post Limited 10,000.00 0.00 Canceled 2016-01-07 2017-01-07 Selection mandiocultura BR-NA-189-CI-IC / Análise e Individual Consultant estudo da cadeia produtiva de Post Limited 40,000.00 0.00 Canceled 2015-10-20 2015-12-20 Selection caprinocultura. BR-NA-187-CI-IC / Análise de Individual Consultant Post Limited 50,000.00 0.00 Canceled 2015-10-14 2016-10-14 ã . projetos de irrigaço Selection BR-NA-184-CI-3CV / ã Contrataço de consultoria para prestar suporte técnico na implementaço ã ã da Avaliaço de Impacto do Projeto Bahia Individual Consultant Post Limited 29,000.00 0.00 Canceled 2015-07-29 2017-07-29 Produtiva. O consultor irá apoiar Selection a Avaliaço ã de Impacto prestando suporte ao pesquisador principal e à equipe do Projeto na BR-NA-185-CI-3CV / Contrataço ã de consultoria para prestar suporte técnico durante a Individual Consultant fase de implementaço ã da Post Limited 15,000.00 0.00 Canceled 2015-07-29 2017-07-29 Selection ã Avaliaço de Impacto do Projeto Bahia Produtiva._x000D_ Apoio a Avaliaço ã de Impacto. BR-NA-274-CI-IC / Contrataço ã de consultor especialista em desenvolvimento territorial para Individual Consultant elaborar a estratégia de arranjos Post Limited 52,632.00 0.00 Canceled 2016-08-24 2017-08-24 Selection produtivos territoriais integrados aos Planos Territoriais de Desenvolvimento Sustentável. BR-NA-272-CI-IC / Contrataçoã de consultor especialista em desenvolvimento territorial para Individual Consultant Post Limited 47,740.00 0.00 Canceled 2016-10-04 2017-10-04 õ s desenvolver as orientaçe Selection metodológicas de Planejamento Territorial. Page 3 ã BR-NA-246-CI-IC / Contrataço Individual Consultant de consultor especialista em Post Limited 55,000.00 0.00 Canceled 2016-09-02 2017-09-02 Selection ã . Tecnologia da Informaço BR-NA-276-CI-IC / Contrataçoã de consultor especialista em desenvolvimento territorial para Individual Consultant Post Limited 31,579.00 0.00 Canceled 2016-09-22 2017-09-22 desenvolvimento do Sistema de Selection õ s Territoriais do Informaçe estado da Bahia. ã BR-NA-277-CI-IC / Contrataço de consultor especialista em mercado para desenvolvimento Institutional Development, Individual Consultant Pending ã da estratégia de atuaço do IBRD / 84150 Technical Assistance and Post Limited 50,000.00 0.00 2017-11-28 2017-12-18 2017-12-23 2018-01-08 2019-01-08 Selection Implementation Projeto no mercado de Project Management orgânicos, fair trade e õ s. exportaçe ã BR-NA-275-CI-IC / Contrataço de consultor especialista em mercado para desenvolvimento Individual Consultant Post Limited 39,100.00 0.00 Canceled 2016-10-05 2017-10-05 ã da estratégia de atuaço do Selection Projeto na implementaço ã de alianças produtivas. BR-FLEM-28898-CS-INDV / ã Contrataço de consultor para assessorar na concepço ã e planejamento, na implementaço ã Institutional Development, e gestão de processo de Individual Consultant Pending IBRD / 84150 Technical Assistance and Post Limited 102,946.88 0.00 2017-09-25 2017-09-30 2017-10-21 2017-11-25 2019-05-19 ã formaço de servidores da CAR e Selection Implementation Project Management membros vinculados ao CODETER E CMDS, em atendimento a implementaço ã do BP. BR-NA-287-CF-CD / ã Contrataço de consultor individual para o desenvolvimento Institutional Development, ã de aplicativo para realizaço de Individual Consultant Pending IBRD / 84150 Technical Assistance and Post Direct 8,785.45 0.00 2017-10-09 2017-10-09 2017-10-09 2017-10-09 2017-11-30 compras on-line das aqusiçe õ s a Selection Implementation Project Management serem realizadas pelas entidades beneficiadas pelo Projeto. BR-FLEM-29316-CS-INDV / ã Contrataço de Consultor para Institutional Development, desenvolvimento de metodologia Individual Consultant Pending IBRD / 84150 Technical Assistance and Post Limited 35,000.00 0.00 2017-11-10 2017-11-20 2017-11-25 2017-11-30 2018-01-30 das expediçe õ s de gastronomia Selection Implementation Project Management õ s comerciais com e das relaçe os restaurantes. BR-FLEM-29318-CS-INDV / Contrataço ã de Consultor para Institutional Development, Individual Consultant Pending elaboraçoã de plano de IBRD / 84150 Technical Assistance and Post Limited 134,660.25 0.00 2017-10-09 2017-10-09 2017-10-09 2017-10-09 2018-08-25 Selection Implementation emancipaço ã dos distritos de Project Management ã irrigaço BR-FLEM-53290-CS-INDV / Consultor Individual para assessorar a equipe do Projeto Bahia Produtiva no Institutional Development, Individual Consultant Pending desenvolvimento e aplicaçoã das IBRD / 84150 Technical Assistance and Post Direct 118,230.46 0.00 2018-03-16 2018-03-22 2018-03-24 2018-03-28 2020-03-27 Selection Implementation õ s para estratégias e açe Project Management fortalecimento e qualificaçoã do Componente 1 Inclusão Produtiva e Acesso aos Mercados. BR-CERB-BA-63416-CS-INDV / Contrataço ã de um Consultor Individual (CI) para assessorar a Individual Consultant Pending IBRD / 84150 Household Water and Sanitation Post Open 131,517.94 0.00 2018-09-30 2018-11-18 2018-12-09 2019-01-13 2019-07-12 CERB na criaço ã ã , estruturaço e Selection Implementation ã capacitaço da CENTRAL Caetité Page 4