FEDERAL REPUBLIC OF NIGERIA Nigeria Erosion and Watershed Management Project (NEWMAP) PROCUREMENT PLAN I. GENERAL 1. Project information: Country: Nigeria Borrower: Federal Government of Nigeria Project Name: Nigeria Erosion and Watershed Management Project-(NEWMAP) Loan / Credit No.: PIA: National NEWMAP Coordinating Unit. 2. Bank’s approval Date of the procurement Plan: March, 2012 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments (US$ equivalent) 1. ICB and LIB (Goods and services other > 750,000.00 ALL than consultancy services) 2. NCB 50,000.00 ≤ 750,000.00 NONE 3. ICB (Works) > 5,000,000.00 ALL 4. NCB (Works) 200,000 ≤ 5,000,000.00 NONE 5 Shopping-Goods < 50,000.00 NONE 6 Shopping-Works < 100,000.00 NONE 7 Training, Workshops, Study Tours All Values Based on Annual Work Plans & Budgets 2. Prequalification. Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Shall apply 4. Reference to (if any) Project Operational/Procurement Manual: shall apply 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages with Methods and Time Schedule Procurement of Goods : 1 2 3 4 5 6 7 8 9 Re Contract Estimate Procure Prequalificati Domestic Review Expected Comments f. (Description) d ment on (yes/no) Preference by Bank Bid- No Cost Method (yes/no) (Prior / Post) Opening . US$’000 Date 1 Computer Systems, Office, software and Accessories Computers and 684 NCB NO NO POST June 7, Procureme Accessories, software (see 2012 nt by each remark of the 7 packages, Photo- Colum) SPMU & copiers, UPS, Printers FPMU is and Scanners, Fax estimated Machines, Laptops, at ( USD Stationeries, 85.5) Consumables, LAN, Telephony,Lasers Software Licenses and Application,. 2 Office Furniture’s and Equipment Computer workstations 680 NCB NO NO PRIOR June 7, Procureme and Office Furniture (see 2012 nt by each remark of the 7 Water Dispenser, Colum) SPMU & Refrigerators, FPMU is Airconditioners, estimated Tables, Chairs, etc at ( USD 85) 3 Operational Vehicles 4-WD Vehicles (32 1440 NCB NO NO PRIOR June 7, Procureme units) (see 2012 nt by each remark of the 7 Colum) SPMU & FPMU is estimated at (180USD 4 Generator 40KVA Sound-Proof 240 NS NO NO PRIOR June 7, Procureme Electricity Generating (see 2012 nt by each Set-Purchase and remark of the 7 Installation (8 units) Colum) SPMU & FPMU is estimated at (30 USD 5 Training Communication, Presentation, Media Equipment and materials, etc Multimedia 364 NS NO NO PRIOR June 7, Procureme Projectors, (see 2012 nt by each remark of the 7 Flip Chart Stands, Colum) SPMU & Boards, GSM FPMU is TV/Video/Radio/Reco estimated rders and Digital at (45.5 Cameras, Internet USD Facilities, GPS, Raincoats and Enumerators bags, Program information kit, Program posters Community oriented Implementation manual 6 Field Equipment Purchase of Weather 2,400 NCB NO NO PRIOR June 7, Procureme Monitoring Stations, (see 2012 nt by each GPSs, Laser Measures, remark of the 7 Measuring Wheels, 1- Colum) SPMU & 2km Range Radios and FPMU is other survey equipment estimated and tools to gauge and at (300 trace watershed, USD terrestrial carbon and water flow 7 Geographic Information System Purchase of GIS 3520 NCB NO NO PRIOR June 7, Procureme data/Satellite Imagery,, (see 2012 nt by each Overhead photography, remark of the 7 etc Colum) SPMU & FPMU is estimated at (440 USD Sub Total 9,328.00 Procurement of Civil Works 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procure Prequalificati Domestic Review Expected Comments No. (Description) Cost ment on (yes/no) Preference by Bank Bid- US$’000 Method (yes/no) (Prior / Post) Opening Date 1 Civil works, and 252,000.00 ICB NO YES PRIOR October Procureme maintenance of flood 12, 2012 nt by ICB and gully erosion sites for all 7 SPMU 2 Office accommodation 240,000 NS NO NO PRIOR July, 2012 for 7 SPMU & FPCU SUB TOTAL 252,240.00 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1 Consultant Services-QCBS- All Values ALL International 2 Consultant Services-QCBS-National > 200,000.00 ALL 3 Consultant Services-CQS < 200,000.00 NONE 4 Consultant Services-lC > 50,000.00 ALL 5 Consultant Services-lC < 50,000.00 ToR only but ALL 6 Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref. Description of Assignment Estimated Selection Review Expected Comments No. Method by Bank Proposals Cost. (Prior / Submission US$’000 Post) Date 1 Consultancy for the detailed 3,395.24 QCBS Prior On-going Consultancy for Engineering designs and data (see remark Priority sites collation for 35 sites Colum by each of the 7 SPMU (see each State Proc. Plan). 2 Consultancy for the supervision 6,824.47 QCBS Prior September Consultancy for of Civil Works for 35sites (see remark 2012 Priority sites Colum by each of the 7 SPMU (see each State Proc. Plan). 3 Consultancy for the RAP study 875.00 IC Prior On-going Consultancy for for 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at (25 USD. 4 Consultancy for the ESIA study 875.00 IC Prior On-going Consultancy for for 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at (25 USD. 5 Consultancy for the Socio- 875.00 IC Prior On-going Consultancy for Economic study 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at 25 USD per site 6 Consultancy for GIS data 875.00 IC Prior On-going Consultancy for collection and Mapping for 35 (see remark Priority sites sites Colum by each of the 7 SPMU is estimated at 75 USD per site 7 Consultancy for the detailed 3500.00 QCBS Prior August, 2012 Consultancy for Engineering designs and data (see remark 5 additional collation for additional 35sites Colum sites by each of the 7 SPMU is estimated at 100 USD per site 8 Consultancy for the detailed 2625.00 QCBS Prior June, 2013 Consultancy for ESIA, RAP and Socio (see remark 5 additional Economic Studies for Colum sites by each of additional 35 sites the 7 SPMU is estimated at 75 USD per site 9 Environmental engineering and 800 QCBS 9 design consultancy, 10 Procurement consultancy for 800 QCBS 10 June 1012 support of FPMU and SPMUs 11 M&E consultancy 400 QCBS 11 12 Consultancy for the support of 800.00 QCBS 12 Sept., 2012 Consultancy by SPMUs and FPMU (see remark each of the 7 Colum SPMU & FPMU is estimated at (100 USD 13 Consultancy for Legal Services 800.00 IC 13 Sept., 2012 Consultancy by each of the 7 (see remark SPMU & Colum FPMU is estimated at (100 USD 14 Consultancy for valuation and 3500.00 14 Sept., 2012 Consultancy by resettlement implementation (see remark each of the 7 Colum SPMU, to cover all sites is estimated at (500 USD per SPMU 15 Consultancy for Training and 1600.00 QCBS Prior August, 2012 Consultancy by Capacity Building (see remark each of the 7 Colum SPMU & FPMU is estimated at (200 USD 16 Consultancy-External Auditor 400.00 QCBS Prior March, 2013 Consultancy by (see remark FPMU to cover Colum each SPMU 17 Consultancy on Community 800.00 IC Prior Sept., 2012 Consultancy by consultation, Public Education (see remark each of the 7 and Erosion Management and Colum SPMU & awareness Techniques, FPMU is estimated at (100 USD Sub Total 27,744.71 IV. Implementing Agency Capacity Building Activities with Time Schedule 1. In this section the agreed Capacity Building Activities are listed with time schedule below; No. Expected outcome / Estimated Estimated Start Date Com Activity Description Cost US$ Duration m ‘000 e n t s A. TRAINING 1 3. Nos. Training courses for August 2012 Capacity Building PMU staff; Project activities for each Coordinator, Procurement of the 7 SPMU & Specialist, and financial mgt, FPMU is estimated at (90 USD M&E, Environmental specialists, Communication, Livelihood, Engineering 720.00(see 2WKS, specialists remark Colum each 2 Training of project finance August 2012 Capacity Building staff(FMS, APA, FO, IA) on 160.00(see activities for each flexible accounting software remark Colum 1wk of the 7 SPMU & FPMU is estimated at (20 USD B. WORKSHOP 3 September Capacity Building 2012 activities for each of the 7 SPMU & Capacity Building for key 240.00(see FPMU is estimated stakeholders remark Colum 3 days at (30 USD 4 September, Capacity Building 2012 activities for each of the 7 SPMU & 160(see FPMU is estimated ICT Training remark Colum 1 wk at (20 USD 5 Various Capacity Building activities for each Professional of the 7 SPMU & Seminars/Workshops/ 120.00(see FPMU is estimated subscriptions remark Colum Various at (15 USD 6 September Capacity Building 2 Days Sensitization/ activities for each 2012 Workshop for State and Local of the 7 SPMU & Govt. Officials on erosion and 200.00(see FPMU is estimated watershed management remark Colum 2 days at (25 USD 7 October Capacity Building 3 Day workshop for Line activities for each 2012 Ministries and MDAs on of the 7 SPMU & addressing and prevention of 240.00(see FPMU is estimated Land Degradation remark Colum 3- days at (30 USD 8 3 Day workshop for local October Capacity Building Govt. Focal Persons and 2012 activities for each Community Erosion watch of the 7 SPMU & Dogs on prevention of erosion FPMU is estimated 240.00(see at (30 USD and land degradation remark Colum 3-days 9 2013 Capacity Building activities for each Capacity Building on use of of the 7 SPMU & Metrological and GPS 200.00(see FPMU is estimated Equipment remark Colum 5-days at (25 USD C. STUDY/TOURS 10 240.00(see Various October Capacity Building remark Colum times 2012 activities for each Baseline survey/ Community of the 7 SPMU & needs assessment and capacity FPMU is estimated building at (30 USD 11 240.00(see Various August, Capacity Building remark Colum times 2012 activities for each Sensitization/ Awareness of the 7 SPMU & creation of NEWMAP in the FPMU is estimated 18 LGA at (30 USD 12 160.00(see WB and Capacity Building remark Colum FAO to activities for each Participation in watershed of the 7 SPMU & determine studies organized by the world FPMU is estimated bank and FAO at (20 USD 13 240.00(see Various December, Capacity Building remark Colum 2012 activities for each of the 7 SPMU & Launching of ESIA and RAP FPMU is estimated for priority sites at (30 USD 14 160.00(see Various Oct., 2012 Capacity Building remark Colum activities for each of the 7 SPMU & FPMU is estimated livelihood studies at (20 USD 15 160.00(see Various World Bank Capacity Building Participation in remark Colum activities for each determined Biodiversity/forest carbon of the 7 SPMU & study organized by the World FPMU is estimated Bank at (20 USD 16 120.00(see 4-days each July 2012 Capacity Building remark Colum activities for each Recognizance survey of of the 7 SPMU & Project sites (Erosion and FPMU is estimated Watershed) at (15 USD 17 2480.00(see 4-wks February., Capacity Building remark Colum 2013 activities for each of the 7 SPMU & International Training and FPMU is estimated study tours at (310 USD 18 Various World Bank Capacity Building determined activities for each Attendance of World Bank of the 7 SPMU & Organized training, meetings, 800.00(see FPMU is estimated seminar and workshops remark Colum at (100 USD Sub Total 6,880.00 PROCUREMENT Nigeria : Nigeria Erosion and Watershed Management Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2017-07-14 2020-03-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P124905 GPN Date: Project Name: Nigeria Erosion and Watershed Management Project Loan / Credit No: IDA / 51050, IDA / 62770 Executing Agency(ies): NEWMAP - Federal Projects Management Unit WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NEWMAP-FPMU-78533- Component 2: Erosion and CW-RFB / Rehabilitation and Pending Watershed Management Single Stage - One development of underground IDA / 51050 Post Request for Bids Open - National 450,000.00 0.00 Implementati 2019-03-12 2019-03-17 2019-04-28 2019-05-28 2019-07-02 2019-12-29 Institutions and Information Envelope water monitoring systems on Services (including instrumentation) NG-NEWMAP-FPMU-102206- Under Component 4: Project Request for Single Stage - One CW-RFQ / Renovation of IDA / 51050 Post Limited 100,000.00 80,589.08 Implementati 2019-04-02 2019-04-05 2019-05-28 2019-11-24 Management Quotations Envelope New and Old Offices on NG-NEWMAP-FPMU-115677- Pending CW-RFB / Rehabilitation and Component 4: Project Single Stage - One IDA / 51050 Post Request for Bids Open - National 3,000,000.00 0.00 Implementati 2019-07-15 2019-07-20 2019-08-31 2019-09-30 2019-11-04 2020-05-02 Renovation of EIA Building Management Envelope on FMEVN NG-NEWMAP-FPMU-154708- CW-RFQ / Procurement and Pending Component 3: Climate Request for Single Stage - One Installation of solar-powered IDA / 51050 Post Limited 180,000.00 0.00 Implementati 2020-01-29 2020-02-24 2020-03-30 Change Response Quotations Envelope borehole and installation of on drip irrigation system NG-NEWMAP-FPMU-154901- CW-RFQ / Procurement of Bamboo Charcoal making Pending machines(including Housing Component 3: Climate Request for Single Stage - One IDA / 51050 Post Limited 180,000.00 0.00 Implementati 2020-01-27 2020-02-25 2020-03-25 and Installation) &Provision Change Response Quotations Envelope on of solar-powered borehole in an identified community in Abia State. NG-NEWMAP-FPMU-154971- CW-RFQ / Procurement of Pending solar meat driers and Component 3: Climate Request for Single Stage - One IDA / 51050 Post Limited 180,000.00 0.00 Implementati 2020-02-05 2020-02-24 2020-03-30 construction of fuel-efficient Change Response Quotations Envelope on kilns with Motorised Borehole and overhead tank. NG-NEWMAP-FPMU-154644- CW-RFQ / Provision & Installation of a solarized Pending cassava-processing machines Component 3: Climate Request for Single Stage - One IDA / 51050 Post Limited 120,000.00 0.00 Implementati 2020-03-31 2020-05-12 2020-06-09 with Housing for Change Response Quotations Envelope on smallholder farmers in identified community in Kogi State NG-NEWMAP-FPMU-165875- Pending CW-RFQ / Office Space Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 200,000.00 0.00 Implementati 2020-04-17 2020-06-12 2020-09-11 Renovation/ Rehabilitation Management Quotations Envelope on UNILAG Page 1 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NEWMAP-FPMU-19584- GO-RFQ / Production of IEC Materials & Newsletters Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 96,000.00 72,839.57 Completed 2017-07-30 2017-09-24 2019-04-10 2018-03-23 2019-05-02 on Activities of NEWMAP Management Quotations Envelope (for Awareness Raising and Advocacy purposes) NG-NEWMAP-FPMU-19572- Component 2: Erosion and GO-RFB / Procurement of Pending Watershed Management Single Stage - One statistical and analytical IDA / 51050 Post Request for Bids Open - National 250,000.00 0.00 Implementati 2017-08-07 2017-08-12 2017-09-23 2017-10-23 2017-11-27 2018-05-26 Institutions and Information Envelope software tools and equipment on Services for DPRS of the FMEnv Component 2: Erosion and NG-NEWMAP-FPMU-19537- Watershed Management Single Stage - One GO-RFB / Upscaling of IDA / 51050 Post Request for Bids Open - National 138,000.00 0.00 Canceled 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 Institutions and Information Envelope National EA Portal Services NG-NEWMAP-FPMU-19516- GO-RFB / Operationalisation Component 3: Climate Single Stage - One of National Climate Change IDA / 51050 Post Request for Bids Open - National 175,000.00 0.00 Canceled 2017-08-16 2017-08-21 2017-10-02 2017-11-01 2017-12-06 2018-06-04 Change Response Envelope GHG Data Management System- NG-NEWMAP-FPMU-19527- Pending GO-RFQ / Procurement of Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 40,000.00 0.00 Implementati 2017-07-22 2017-09-16 2018-03-15 ICT equipment for GEF Management Quotations Envelope on desk office NG-NEWMAP-FPMU-83102- GO-RFQ / Stationaries, File Pending Component 3: Climate Request for Single Stage - One Jackets, Folders & Branded IDA / 51050 Post Limited 5,000.00 0.00 Implementati 2019-01-28 2019-03-25 2019-09-21 Change Response Quotations Envelope Notepads,Green Bond on Secretariat. NG-NEWMAP-FPMU-83087- Pending GO-RFQ / Support to Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 486,000.00 0.00 Implementati 2019-02-15 2019-04-12 2019-10-09 Steering committee (FMenv), Management Quotations Envelope on Procurement of 2No. SUVs NG-NEWMAP-FPMU-83059- Pending Component 3: Climate Request for Single Stage - One GO-RFQ / Nigeria's Green IDA / 62770 Post Limited 98,360.00 0.00 Implementati 2019-02-17 2019-04-14 2019-10-11 Change Response Quotations Envelope Bond Story on NG-NEWMAP-FPMU-83090- Pending Component 3: Climate Request for Single Stage - One GO-RFQ / Prospectus Green IDA / 51050 Post Limited 8,196.00 0.00 Implementati 2019-01-26 2019-03-23 2019-09-19 Change Response Quotations Envelope Bond Second Issuance. on NG-NEWMAP-FPMU-83085- GO-RFQ / Procurement of 1 Pending Component 3: Climate Request for Single Stage - One No. 16 Seater Bus for Green IDA / 51050 Post Limited 91,803.00 0.00 Implementati 2019-02-02 2019-03-30 2019-09-26 Change Response Quotations Envelope Bond Monitoring & on verification of Projects. NG-NEWMAP-FPMU-83091- Pending GO-RFQ / Green Bond Component 3: Climate Request for Single Stage - One IDA / 51050 Post Limited 3,279.00 0.00 Implementati 2019-02-23 2019-04-20 2019-10-17 Manual Green Bond Second Change Response Quotations Envelope on Issuance. Page 2 NG-NEWMAP-FPMU-83060- GO-RFQ / Procurement of Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 166,000.00 137,646.00 Completed 2019-02-02 2019-01-31 2019-03-30 2019-02-28 2019-09-26 2019-03-15 2No. 4x4wd Pick Up Van Management Quotations Envelope for FPMU NG-NEWMAP-FPMU-83113- Pending GO-RFQ / Facts behind the Component 3: Climate Request for Single Stage - One IDA / 51050 Post Limited 3,279.00 0.00 Implementati 2019-04-24 2019-06-19 2019-12-16 figures Green Bond Second Change Response Quotations Envelope on Issuance. NG-NEWMAP-FPMU-83066- GO-RFQ / Procurement of 3 Pending Component 3: Climate Request for Single Stage - One No. professional Still IDA / 51050 Post Limited 3,442.00 0.00 Implementati 2019-03-04 2019-04-29 2019-10-26 Change Response Quotations Envelope cameras with high resolution on for Green Bond Secretariat. NG-NEWMAP-FPMU-102202- GO-RFQ / Production of Pending Component 3: Climate Request for Single Stage - One guidance manual  for IDA / 51050 Post Limited 50,000.00 0.00 Implementati 2019-04-14 2019-06-09 2019-12-06 Change Response Quotations Envelope Climate Change response  on Agenda NG-NEWMAP-FPMU-102207- Pending Component 4: Project Request for Single Stage - One GO-RFQ / Office Equipment IDA / 51050 Post Limited 350,000.00 0.00 Implementati 2019-03-05 2019-04-30 2019-10-27 Management Quotations Envelope and Furniture on NG-NEWMAP-FPMU-103297- Pending Component 4: Project Request for Single Stage - One GO-RFQ / Office IDA / 51050 Post Limited 30,000.00 0.00 Implementati 2019-06-05 2019-07-31 2019-10-22 Management Quotations Envelope Consumables. on NG-NEWMAP-FPMU-127610- Pending GO-RFQ / Procurement 2No. Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 166,000.00 0.00 Implementati 2019-10-21 2019-11-20 2019-12-04 4x4wd Pick Up Vans for EA Management Quotations Envelope on Department, FMENV NG-NEWMAP-FPMU-165802- Pending Component 3: Climate Request for Single Stage - One GO-RFQ / Production of Bio IDA / 51050 Post Limited 30,000.00 0.00 Implementati 2020-07-07 2020-08-04 2020-09-04 Change Response Quotations Envelope Engineering Manual on NG-NEWMAP-FPMU-165861- Component 2: Erosion and GO-RFQ / Procurement of Pending Watershed Management Request for Single Stage - One Set-up -3 High Configuration IDA / 51050 Post Limited 86,000.00 0.00 Implementati 2020-04-13 2020-05-19 2020-06-02 Institutions and Information Quotations Envelope Server and Installation of on Services Network Devices NG-NEWMAP-FPMU-165851- Pending GO-RFQ / Procurement of Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 84,000.00 0.00 Implementati 2020-04-13 2020-05-19 2020-06-02 Vehicles : 1 No. bus  for Management Quotations Envelope on UNILAG centre of excellence NG-NEWMAP-FPMU-165852- Pending GO-RFQ / Procurement and Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 30,000.00 0.00 Implementati 2020-04-13 2020-05-19 2020-06-02 installation of 1 No. 100KVA Management Quotations Envelope on Generator (UNILAG) . NG-NEWMAP-FPMU-165876- GO-RFQ / Procurement, installation of furniture’s Pending Component 4: Project Request for Single Stage - One and office equipment’s at the IDA / 51050 Post Limited 78,000.00 0.00 Implementati 2020-04-13 2020-05-19 2020-06-02 Management Quotations Envelope new office Administration on block and laboratory (UNILAG) NON CONSULTING SERVICES Page 3 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NEWMAP-FPMU-19582- Component 2: Erosion and NC-RFB / Consultancy Watershed Management Single Stage - One IDA / 51050 Post Request for Bids Open - National 250,000.00 304,222.46 Signed 2017-07-03 2016-09-14 2017-07-08 2017-08-19 2016-12-09 2017-09-18 2017-08-22 2017-10-23 2018-01-17 2018-04-21 Services for EA Archiival Institutions and Information Envelope Digital cataloguing Services NG-NEWMAP-FPMU-19575- Component 2: Erosion and NC-RFB / Bathymetry & Pending Watershed Management Open - Single Stage - One Geomorphological Study of IDA / 51050 Prior Request for Bids 1,400,000.00 0.00 Implementati 2017-07-03 2017-07-08 2017-08-19 2017-09-18 2017-10-23 2018-04-21 Institutions and Information International Envelope the River Benue System & on Services Kiridam NG-NEWMAP-FPMU-102204- NC-RFQ / Engagement of a Pending Component 4: Project Request for Single Stage - One service provider for the IDA / 51050 Post Limited 20,000.00 0.00 Implementati 2019-04-03 2019-05-29 2019-11-25 Management Quotations Envelope maintenance of Project on Vehicles CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NEWMAP-FPMU-19512- CS-QCBS / Extension of Component 4: Project Quality And Cost- Open - Pending IDA / 51050 Prior 1,500,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 Procurement Consultancy Management Based Selection International Implementation Firm NG-NEWMAP-FPMU-19539- CS-QCBS / Federal Quality Control and Engineering Design Firm (FQCEDF)- Component 1: Erosion and EXTENSION- for additional Quality And Cost- Open - Pending IDA / 51050 Watershed Management Prior 1,100,000.00 0.00 2017-07-03 2017-07-24 2017-09-06 2017-10-04 2017-11-03 2017-12-08 2018-01-12 2019-01-12 area for the aerial Based Selection International Implementation Infrastructure Investments photography/survey of erosion sites Including capacity building and GIS software, archiving system. NG-NEWMAP-FPMU-19567- CS-QCBS / Consulting services for the development of framework for the Component 3: Climate Quality And Cost- Open - adoption of LPG as Low IDA / 51050 Prior 3,500,000.00 3,011,027.28 Signed 2017-02-06 2017-02-27 2017-04-12 2017-05-10 2017-06-09 2017-07-14 2018-01-09 2017-08-18 2018-01-29 2018-08-18 Change Response Based Selection International Carbon Alternative to Firewood and Kerosene and Supervision of the Implementation. NG-NEWMAP-FPMU-19578- CS-QCBS / Federal quality Component 1: Erosion and control and engineering Quality And Cost- Open - Under IDA / 51050 Watershed Management Prior 3,000,000.00 0.00 2017-07-17 2019-01-22 2017-08-07 2019-02-05 2017-09-20 2019-04-10 2017-10-18 2019-07-16 2017-11-17 2019-10-18 2017-12-22 2018-01-26 2019-01-26 design firm of erosion Based Selection International Implementation Infrastructure Investments control sites Old and New States. NG-NEWMAP-FPMU-19589- CS-QCBS / Procurement of Component 4: Project Quality And Cost- Open - Under IDA / 51050 Prior 2,000,000.00 0.00 2017-09-29 2018-08-12 2017-10-20 2019-02-05 2017-12-03 2019-04-10 2017-12-31 2019-07-18 2018-01-30 2019-10-01 2018-03-06 2020-01-16 2018-04-10 2019-04-10 Procurement firm in Old Management Based Selection International Implementation and New States. Page 4 NG-NEWMAP-FPMU-19580- CS-QCBS / Spatial Baseline Modelling of Electricity Infrastructure for Remote Component 3: Climate Quality And Cost- Open - IDA / 51050 Prior 3,000,000.00 0.00 Canceled 2017-07-26 2017-08-16 2017-09-29 2017-10-27 2017-11-26 2017-12-31 2018-02-04 2019-02-04 and Off-Grid Power Supply Change Response Based Selection International and Demonstration Projects on Low Carbon Off-Grid/mini- grid options NG-NEWMAP-FPMU-19586- CS-CQS / Technology Needs Consultant Component 3: Climate Assessment for Climate IDA / 51050 Post Qualification Open - National 100,000.00 0.00 Canceled 2017-07-22 2017-08-12 2017-09-25 2017-10-25 2017-11-29 2018-05-28 Change Response Change in Nigeria Towards Selection low Carbon Development NG-NEWMAP-FPMU-19533- Consultant Component 3: Climate CS-CQS / Development of IDA / 51050 Post Qualification Open - National 100,000.00 0.00 Canceled 2017-07-22 2017-08-12 2017-09-25 2017-10-25 2017-11-29 2018-05-28 Change Response Climate Smart Agriculture. Selection NG-NEWMAP-FPMU-19585- CS-CQS / Procurement of Component 2: Erosion and Consultant Consultant for the Spatial Watershed Management IDA / 51050 Post Qualification Open - National 290,000.00 0.00 Canceled 2017-08-21 2017-09-11 2017-10-25 2017-11-24 2017-12-29 2018-06-27 Knowledge Information Institutions and Information Selection System on Erosion and Services Watershed Component 2: Erosion and NG-NEWMAP-FPMU-19561- Watershed Management Quality And Cost- Open - CS-QCBS / Engagement of IDA / 51050 Prior 500,000.00 0.00 Canceled 2017-03-20 2017-04-10 2017-05-24 2017-06-21 2017-07-21 2017-08-25 2017-09-29 2018-09-29 Institutions and Information Based Selection International IUCN Services NG-NEWMAP-FPMU-19530- CS-QCBS / Vulnerability Component 3: Climate Quality And Cost- Open - IDA / 51050 Prior 500,000.00 0.00 Canceled 2017-09-04 2017-09-25 2017-11-08 2017-12-06 2018-01-05 2018-02-09 2018-03-16 2019-03-16 Mapping and Action Plan for Change Response Based Selection International Nigeria. NG-NEWMAP-FPMU-83088- CS-QCBS / Strategy Development for the Component 3: Climate Quality And Cost- Open - Pending Commercialization of 50 Nos. IDA / 51050 Prior 3,901,095.00 0.00 2019-03-20 2019-04-10 2019-05-24 2019-06-21 2019-07-21 2019-08-25 2019-09-29 2020-09-28 Change Response Based Selection International Implementation Flared Associated Gas Sites in Crude Oil Exploration in Nigeria NG-NEWMAP-FPMU-83063- CS-QCBS / Project Management Consultancy provide technical and administrative support to the FPMU NEWMAP in the Component 4: Project Quality And Cost- Open - IDA / 51050 Prior 3,000,000.00 0.00 Under Review 2019-02-27 2019-07-28 2019-03-20 2019-10-07 2019-05-03 2019-05-31 2019-06-30 2019-08-04 2019-09-08 2020-09-07 areas of Erosion and Management Based Selection International Watershed Management Investments, Erosion and Watershed Management Institution and Information Services, NG-NEWMAP-FPMU-100131- Component 2: Erosion and CS-QCBS / Procurement of Watershed Management Quality And Cost- Open - Under an Umbrella NGO for the IDA / 51050 Prior 900,000.00 0.00 2019-02-14 2019-03-19 2019-03-07 2019-05-18 2019-04-20 2019-12-31 2019-05-18 2019-06-17 2019-07-22 2019-08-26 2020-08-25 Institutions and Information Based Selection International Implementation Old and New States of Services NEWMAP NG-NEWMAP-FPMU-98274- Consultant Component 3: Climate Pending CS-CDS / Legal Adviser IDA / 51050 Prior Qualification Open - National 82,000.00 0.00 2019-02-15 2019-03-08 2019-04-21 2019-05-21 2019-06-25 2019-12-22 Change Response Implementation Green Bond Second Issuance. Selection NG-NEWMAP-FPMU-102200- Consultant CS-CQS / Inventorisation of Component 3: Climate Pending IDA / 51050 Post Qualification Open - National 250,000.00 0.00 2019-03-21 2019-04-11 2019-05-25 2019-06-24 2019-07-29 2020-01-25 GHG emissions of NEWMAP Change Response Implementation Selection intervention sites . Page 5 NG-NEWMAP-FPMU-102203- CS-QCBS / Engagement of Component 3: Climate Quality And Cost- Pending IDA / 51050 Prior Open - National 782,000.00 0.00 2019-04-15 2019-05-06 2019-06-19 2019-07-17 2019-08-16 2019-09-20 2019-10-25 2020-10-24 Firm for Green Bond Third Change Response Based Selection Implementation Issuance NG-NEWMAP-FPMU-102209- CS-QCBS / Consultancy services for the Study of the Component 3: Climate Quality And Cost- Open - adoption of gas based (CNG IDA / 51050 Prior 3,300,000.00 0.00 Under Review 2019-05-29 2019-07-30 2019-06-19 2019-10-21 2019-08-02 2019-08-30 2019-09-29 2019-11-03 2019-12-08 2020-12-07 Change Response Based Selection International and LPG) fuels in road transportation and carbon capture sequenstration. NG-NEWMAP-FPMU-19531- Component 2: Erosion and CS-QCBS / Engagement of Watershed Management Quality And Cost- Open - IDA / 51050 Prior 600,000.00 0.00 Canceled 2017-09-29 2018-01-15 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 an Umbrella NGO in Old Institutions and Information Based Selection International and New States. Services NG-NEWMAP-FPMU-95582- Consultant CS-CDS / Engagement of Component 3: Climate Pending IDA / 51050 Post Qualification Open - National 196,722.00 0.00 2019-02-15 2019-03-08 2019-04-21 2019-05-21 2019-06-25 2019-12-22 Financial Adviser Green Change Response Implementation Selection Bond Second Issuance. NG-NEWMAP-FPMU-115686- CS-QCBS / Inventorisation of Component 3: Climate Quality And Cost- Open - IDA / 51050 Prior 1,000,000.00 0.00 Under Review 2019-06-17 2019-09-11 2019-07-08 2019-12-17 2019-08-21 2019-09-18 2019-10-18 2019-11-22 2019-12-27 2020-12-26 GHG emissions of NEWMAP Change Response Based Selection International intervention sites. NG-NEWMAP-FPMU-102198- CS-QCBS / Consultancy Component 4: Project Quality And Cost- services to carry out the re- IDA / 51050 Post Open - National 400,000.00 0.00 Under Review 2019-05-07 2020-03-17 2019-05-28 2019-07-11 2019-08-08 2019-09-07 2019-10-12 2019-11-16 2020-11-15 Management Based Selection evaluation of the capacity of the FPMU and States NG-NEWMAP-FPMU-115678- Component 3: Climate Quality And Cost- Open - Under CS-QCBS / Climate Smart IDA / 51050 Prior 900,000.00 0.00 2019-09-04 2020-02-10 2019-09-25 2019-11-08 2019-12-06 2020-01-05 2020-02-09 2020-03-15 2021-03-15 Change Response Based Selection International Implementation Agriculture Atlas NG-NEWMAP-FPMU-165797- Consultant CS-CQS / Engagement of an Component 4: Project Pending IDA / 51050 Post Qualification Limited 295,000.00 0.00 2020-03-31 2020-04-07 2020-04-21 2020-05-05 2020-06-30 External Audit Firm for Management Implementation Selection FPMU NG-NEWMAP-FPMU-165836- CS-CQS / Consultancy services for the review of existing road designs Component 1: Erosion and Consultant standards and construction Pending IDA / 51050 Watershed Management Post Qualification Limited 295,000.00 0.00 2020-04-14 2020-04-28 2020-05-12 2020-06-02 2020-09-02 and maintenance practices in Implementation Infrastructure Investments Selection order to identify causes of soil erosion linked to road in the Federal Republic of Nigeria NG-NEWMAP-FPMU-165882- CS-CQS / 2 No. thematic Component 2: Erosion and Consultant Guidelines for Strengthening Watershed Management Pending IDA / 51050 Post Qualification Limited 138,000.00 0.00 2020-05-25 2020-06-08 2020-06-22 2020-07-06 2020-08-17 Technical effectiveness of Institutions and Information Implementation Selection environmental and Social Services safeguards NG-NEWMAP-FPMU-165896- CS-CQS / Consultancy Component 2: Erosion and Consultant Services to carry out RAP Watershed Management Pending IDA / 51050 Post Qualification Limited 298,000.00 0.00 2020-06-29 2020-07-20 2020-08-10 2020-08-24 2020-11-24 Audit for the Implemented Institutions and Information Implementation Selection RAP sites in NEWMAP Services states Page 6 NG-NEWMAP-FPMU-165898- Consultant Component 4: Project Pending CS-CQS / NEWMAP Project IDA / 51050 Post Qualification Limited 115,000.00 0.00 2020-11-05 2020-11-26 2020-12-17 2021-01-07 2021-04-07 Management Implementation Compendium Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Erosion and NG-NEWMAP-FPMU-19571- Watershed Management Pending CS-CDS / Engagement of an IDA / 51050 Prior Direct Selection Direct 85,000.00 0.00 2017-07-10 2017-07-20 2017-09-23 2018-03-22 Institutions and Information Implementation Umbrella NGO -EXTENSION Services NG-NEWMAP-FPMU-19587- Component 1: Erosion and Individual Under CS-INDV / Engagement of a IDA / 51050 Watershed Management Post Consultant Open 50,000.00 0.00 2017-07-29 2018-10-23 2017-09-16 2017-10-07 2017-11-11 2018-05-10 Implementation Senior Engineering Advisor Infrastructure Investments Selection NG-NEWMAP-FPMU-19563- Component 2: Erosion and Individual CS-INDV / Engagement of Watershed Management Under IDA / 51050 Post Consultant Open 75,000.00 0.00 2017-01-09 2018-10-23 2017-02-27 2017-03-20 2017-04-24 2017-10-21 EA Expert Advisor Institutions and Information Implementation Selection (International) Services NG-NEWMAP-FPMU-19662- Individual Component 4: Project Under CS-INDV / Engagement of IDA / 51050 Post Consultant Open 40,000.00 24,608.07 2017-08-15 2017-10-09 2017-10-03 2017-10-24 2017-10-24 2017-10-25 2017-11-28 2018-05-27 Management Implementation Expert for Mid-Term Review Selection NG-NEWMAP-FPMU-19560- Individual Component 4: Project Under CS-INDV / Engagement of IDA / 51050 Post Consultant Open 45,000.00 0.00 2017-08-08 2018-03-27 2017-09-26 2017-10-17 2017-11-21 2018-05-20 Management Implementation Ombudsman Selection NG-NEWMAP-FPMU-19583- Individual CS-INDV / Re-imaging of Component 4: Project Pending IDA / 51050 Post Consultant Open 50,000.00 0.00 2017-08-17 2017-10-05 2017-10-26 2017-11-30 2018-05-29 NEWMAP interactive Management Implementation Selection Website NG-NEWMAP-FPMU-19565- CS-INDV / Consultancy Individual Component 3: Climate Services for the preparation IDA / 51050 Post Consultant Open 100,000.00 0.00 Canceled 2017-01-30 2017-03-20 2017-04-10 2017-05-15 2017-11-11 Change Response of Restructuring paper for Selection NEWMAP. NG-NEWMAP-FPMU-19525- Individual CS-INDV / Engagement of Component 4: Project IDA / 51050 Post Consultant Open 90,000.00 0.00 Canceled 2017-08-31 2017-10-19 2017-11-09 2017-12-14 2018-06-12 HR Firm International and Management Selection National. NG-NEWMAP-FPMU-19522- Component 4: Project CS-CDS / Update of IDA / 51050 Post Direct Selection Direct 30,000.00 0.00 Canceled 2017-10-24 2017-11-03 2018-01-07 2018-07-06 Management accounting system NG-NEWMAP-FPMU-83089- Individual CS-INDV / Water Component 3: Climate Pending IDA / 51050 Post Consultant Limited 16,983.00 0.00 2019-01-22 2019-01-27 2019-02-17 2019-03-24 2019-09-20 Specialist,for the Green Bond Change Response Implementation Selection Second Issuance. NG-NEWMAP-FPMU-83078- Individual CS-INDV / Oil Spills Clean- Component 3: Climate Pending IDA / 51050 Post Consultant Limited 26,406.00 0.00 2019-01-22 2019-01-27 2019-02-17 2019-03-24 2019-09-20 Up Mgt Specialist,Green Change Response Implementation Selection Bond Second Issuance. Page 7 NG-NEWMAP-FPMU-83096- CS-INDV / Recruitment of Individual Component 3: Climate Pending Economics and Financial IDA / 51050 Post Consultant Limited 46,300.00 0.00 2019-01-21 2019-01-26 2019-02-16 2019-03-23 2019-09-19 Change Response Implementation Analyst,Green Bond Second Selection Issuance. NG-NEWMAP-FPMU-83076- CS-INDV / Recruitment of Individual Component 3: Climate Pending Solar Power and OfF-Grid IDA / 51050 Post Consultant Limited 36,460.00 0.00 2019-01-23 2019-01-28 2019-02-18 2019-03-25 2019-09-21 Change Response Implementation Specialist for Green Bond Selection Second Issuance. NG-NEWMAP-FPMU-83064- CS-INDV / Communications Individual Component 3: Climate Pending and Knowledge Mgt. IDA / 51050 Post Consultant Limited 28,890.00 0.00 2019-01-24 2019-01-29 2019-02-19 2019-03-26 2019-09-22 Change Response Implementation Specialist,Green Bond Second Selection Issuance. NG-NEWMAP-FPMU-83067- Individual CS-INDV / Recruitment of Component 3: Climate Pending IDA / 51050 Post Consultant Limited 16,980.00 0.00 2019-01-24 2019-01-29 2019-02-19 2019-03-26 2019-09-22 Transport Specialist for Change Response Implementation Selection Green Bond Second Issuance. NG-NEWMAP-FPMU-83062- CS-INDV / Recruitment of Individual Component 3: Climate Pending Forest and Carbon Emission IDA / 51050 Post Consultant Limited 38,950.00 0.00 2019-01-22 2019-01-27 2019-02-17 2019-03-24 2019-09-20 Change Response Implementation Expert for Green Bond Selection Second Issuance. NG-NEWMAP-FPMU-83017- Individual Component 4: Project Pending CS-INDV / Monitoring and IDA / 51050 Post Consultant Limited 2,600.00 0.00 2019-04-02 2019-04-07 2019-04-28 2019-06-02 2019-11-29 Management Implementation Evaluation Clinic Facilitator Selection NG-NEWMAP-FPMU-78677- Component 2: Erosion and Individual CS-INDV / Engagement of a Watershed Management Under IDA / 51050 Post Consultant Limited 95,000.00 0.00 2019-03-25 2019-02-26 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Watershed/Catchment Institutions and Information Implementation Selection Planning Expert Advisor Services Component 2: Erosion and NG-NEWMAP-FPMU-78684- Individual Watershed Management Pending CS-INDV / Engagement of a IDA / 51050 Post Consultant Limited 95,000.00 0.00 2019-03-25 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Institutions and Information Implementation Geotechnical Expert Advisor Selection Services NG-NEWMAP-FPMU-78685- Individual CS-INDV / Engagement of a Component 3: Climate Under IDA / 51050 Post Consultant Limited 95,000.00 0.00 2019-03-25 2019-03-08 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Natural Resources Expert Change Response Implementation Selection Advisor NG-NEWMAP-FPMU-78532- Individual CS-INDV / Engagement of a Component 3: Climate Under IDA / 51050 Post Consultant Limited 95,000.00 0.00 2019-03-25 2019-02-26 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Climate Change Expert Change Response Implementation Selection Advisor NG-NEWMAP-FPMU-95584- Component 2: Erosion and Individual CS-INDV / Engagement of a Watershed Management Under IDA / 51050 Post Consultant Limited 95,000.00 0.00 2019-03-25 2019-02-26 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Social Livelihood Expert Institutions and Information Implementation Selection Advisor Services NG-NEWMAP-FPMU-78686- Individual Component 4: Project Under CS-INDV / Engagement of IDA / 51050 Post Consultant Limited 95,000.00 0.00 2019-03-25 2019-02-26 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Management Implementation M&E Expert Advisor Selection NG-NEWMAP-FPMU-83095- Individual Component 4: Project Under CS-INDV / NEWMAP IDA / 51050 Post Consultant Limited 45,000.00 0.00 2019-02-22 2019-03-08 2019-02-27 2019-03-20 2019-04-24 2019-10-21 Management Implementation Documentary Selection Page 8 NG-NEWMAP-FPMU-98234- CS-INDV / Engagement of a Individual Component 4: Project Pending Monitoring and Evaluation IDA / 51050 Post Consultant Limited 40,000.00 0.00 2019-02-01 2019-02-06 2019-02-27 2019-04-03 2019-09-30 Management Implementation Specialist for Green Bond Selection Second Issuance. NG-NEWMAP-FPMU-102194- CS-INDV / Engagement of a Individual National Consultant to Component 4: Project Pending IDA / 51050 Post Consultant Limited 90,000.00 0.00 2019-04-08 2019-04-13 2019-05-04 2019-06-08 2019-12-05 prepare a harmonized Policy Management Implementation Selection for Erosion Control and Watershed Management NG-NEWMAP-FPMU-32655- CS-INDV / ENGAGEMENT OF CONSULTANT FOR Individual Component 4: Project THE REVIEW OF THE IDA / 51050 Post Consultant Limited 30,000.00 0.00 Canceled 2017-10-31 2017-11-08 2017-11-05 2017-11-26 2017-12-31 2018-06-29 Management PROJECT Selection IMPLEMENTATION MANUAL FOR NEWMAP NG-NEWMAP-FPMU-19524- Individual CS-INDV / Activities towards Component 3: Climate IDA / 51050 Post Consultant Open 500,000.00 0.00 Canceled 2017-01-30 2017-03-20 2017-04-10 2017-05-15 2017-11-11 establishing and issuance of Change Response Selection Nigeria Green Bond. NG-NEWMAP-FPMU-115682- CS-INDV / Consultancy Individual Component 3: Climate Under Services for the Production IDA / 51050 Post Consultant Limited 60,000.00 0.00 2019-06-26 2019-09-07 2019-07-01 2019-07-22 2019-08-26 2019-11-12 Change Response Implementation of Guidance Manual for Selection Climate Response. NG-NEWMAP-FPMU-127255- CS-INDV / Consultancy Individual Component 4: Project Pending services for the valuation of IDA / 51050 Post Consultant Limited 20,000.00 0.00 2019-09-02 2019-09-06 2019-09-13 2019-09-17 2019-09-30 Management Implementation proposed NEWMAP House Selection to be procured NG-NEWMAP-FPMU-129812- CS-INDV / Documentary on Component 2: Erosion and NEWMAP Institutional Individual Watershed Management Pending Support to Data Collection IDA / 51050 Post Consultant Limited 45,000.00 0.00 2019-09-08 2019-09-13 2019-10-04 2019-10-10 2019-11-10 Institutions and Information Implementation and Decision Making Selection Services (AFEWs & Hyromet Equipment) NG-NEWMAP-FPMU-154960- CS-INDV / Consultancy Individual Component 3: Climate Pending services for the review of IDA / 51050 Post Consultant Limited 90,000.00 0.00 2020-01-30 2020-02-04 2020-02-11 2020-02-17 2020-03-30 Change Response Implementation Pre and Post Issuance of Selection Green Bonds. NG-NEWMAP-FPMU-165247- CS-CDS / Upgrade and Component 4: Project Pending IDA / 51050 Prior Direct Selection Direct 500,000.00 0.00 2020-03-30 2020-04-09 2020-04-30 2021-06-30 Hosting of M&E-MIS Web- Management Implementation Portal NG-NEWMAP-FPMU-165798- Individual CS-INDV / Review and Component 3: Climate Pending IDA / 51050 Post Consultant Limited 70,000.00 0.00 2020-04-03 2020-04-08 2020-04-22 2020-05-06 2020-06-30 update of Bio-Engineering Change Response Implementation Selection Manual NG-NEWMAP-FPMU-165804- CS-INDV / Engagement of a Component 1: Erosion and Individual Consultant to prepare a Pending IDA / 51050 Watershed Management Post Consultant Limited 100,000.00 0.00 2020-04-16 2020-04-21 2020-05-05 2020-05-26 2020-07-07 harmonized Policy for Implementation Infrastructure Investments Selection Erosion Control and Watershed Management Page 9 NG-NEWMAP-FPMU-165844- Component 1: Erosion and Individual Pending CS-INDV / Consultancy for IDA / 51050 Watershed Management Post Consultant Limited 100,000.00 0.00 2020-05-11 2020-05-18 2020-06-08 2020-06-22 2020-08-23 Implementation ESMP Audit Infrastructure Investments Selection Page 10