Restructuring Status: Archived Restructuring Type: Level two Last modified on date : 11/25/2013 1. Basic Information Project ID & Name P110978: LA-Rural Electrification Phase II Country Lao People's Democratic Republic Task Team Leader Veasna Bun Sector Manager/Director Julia M. Fraser Country Director Ulrich Zachau Original Board Approval Date 01/12/2010 Original Closing Date: Current Closing Date 06/30/2014 Proposed Closing Date [if applicable] 06/30/2015 EA Category B-Partial Assessment Revised EA Category B-Partial Assessment-Partial Assessment EA Completion Date 09/22/2008 Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 8.22 8.22 COMM 2.10 2.10 ESMP 0.50 0.50 IDA 0.00 20.00 IDAT 20.00 0.00 NORA 4.00 4.00 Total 34.82 34.82 3. Borrower Organization Department Location Lao People's Democratic Lao People's Democratic Republic Republic 4. Implementing Agency Organization Department Location Electricite du Laos Lao People's Democratic Republic Ministry of Energy and Mines Lao People's Democratic Republic 5. Disbursement Estimates (US$m) Actual amount disbursed as of 11/27/2013 14.11 Fiscal Year Annual Cumulative 2014 3.00 17.11 2015 3.34 20.45 Total 20.45 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select N from the checklist below and update ISDS accordingly before submitting the package. 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes a) To increase access to electricity of rural households in villages of Project provinces; and b) To further improve the financial performance of EdL. 7b. Revised Project Development Objectives/Outcomes [if applicable] ii