Tamil Nadu Sustainable Urban Development Program (TNSUDP) PROCUREMENT PLAN I. General 1. Project information: • Project: Tamil Nadu Sustainable Urban Development Program (TNSUDP) • Country: India • Project Code: P150395 2. Bank’s approval Date of the procurement Plan Draft Procurement Plan dated February 19, 2015 Revision 0 agreed by the Bank on February 19, 2015 3. Implementing Agencies: TNUIFSL, DMA, CMWSSB, TWADB, Chennai Corporation and other ULBs 4. Period covered by this procurement plan: 18 months 5. Risk Rating for the Implementing Agency: Substantial 6. Original Procurement Risk Rating for the Project: Substantial 7. Current Procurement Risk Rating for the Project: Substantial II. Works, Non-consulting services and Goods. 1 a) Procurement Methods and Thresholds Category Method of Procurement Threshold (US$ Equivalent) Works International Competitive Bidding (ICB) > 40,000,000 National Competitive Bidding (NCB) Up to 40,000,000 (with NCB conditions) Shopping Up to 100,000 Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) for Works As per paragraph 3.14 of Guidelines Force Account As per paragraph 3.9 of Guidelines Framework Agreement (FA) As per paragraph 3.6 of Guidelines Goods and International Competitive Bidding (ICB) > 3,000,000 non- Limited International Bidding (LIB) wherever agreed by Bank consultant National Competitive Bidding (NCB) Up to 3,000,000 (with NCB conditions) services Shopping Up to 100,000 (NCS) Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) Services As per paragraph 3.14 of Guidelines Force Account (only for NCS) As per paragraph 3.9 of Guidelines Framework Agreement (FA) As per paragraph 3.6 of Guidelines Procurement from United Nations (UN) Agencies As per paragraph 3.10 of Guidelines 1 b) Prior Review Threshold Works: All contracts more than USD 10 million equivalent Goods: All contracts more than USD 2 million equivalent Non-Consultant Services and IT systems: All contracts more than USD 2 million equivalent In addition, the justifications for all contracts to be issued using LIB or direct contracting shall be subject to prior review. First framework agreement will be subject to prior review irrespective of value. For prior review contracts, the amendments for increasing the cost or extension of time beyond 15% of original value shall also be subject to Bank’s prior review. 2. Pre-qualification – Not envisaged 3. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s “Guidelines: Procurement of goods, works and non-consulting services under IBRD loans and IDA credits & grants by World Bank borrowers” dated January 2011 (as updated in July 2014). 4. Any Other Special Procurement Arrangements: NCB will be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines and the following provisions: i. Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding; ii. Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; iii. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small- scale enterprises or enterprises from any given State; iv. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; v. Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/ Employer) vi. Re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank vii. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; viii. Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures. Such contracts will be acceptable however for any procurement under the Shopping procedures; ix. Two or three envelope system will not be used (except when using e-Procurement system assessed and agreed by the Bank) Other agreed provisions are: • Any discount received from the bidders after bid submission deadline will not be considered either during the bid evaluation or the contract award. • Domestic preference will be applicable for ICB procurement of Goods as per Appendix 2 of the Procurement Guidelines. • Bids received from foreign bidders will not be rejected under NCB. • DGS&D rate contracts may be used as framework agreement (FA) provided: i. Use of DGS&D rate contracts as FA must be reflected on the procurement plan agreed by the Bank for particular goods. ii. Before issuing the purchasing order, the implementing agency will carry out a price analysis on the specific good that is intended to be purchased. If after this due diligence the implementing agency concludes (and Bank agrees) that the DGS&D rate contracts are more advantageous, DGS&D rate contracts may be used as FA. iii. To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders (in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders). On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank's right to audit and F&C clauses could be mentioned. 5. Procurement Packages with Methods and Time Schedule – As per plan in STEP III. Selection of Consultants 1 a) Selection Methods and Thresholds Method of Procurement Threshold (US$ Equivalent) Selection Based on Consultants’ Qualifications Up to 300,000 (CQS)/Least-Cost Selection (LCS) Single-Source Selection (SSS) As per paragraphs 3.9-3.11 of Guidelines Individuals As per Section V of Guidelines Particular Types of Consultants As per paragraphs 3.15-3.21 of Guidelines Quality- and Cost-Based Selection (QCBS)/ Quality- for all other cases Based Selection (QBS)/ Selection under a Fixed Budget (FBS) 1 b) Prior Review Threshold Consultancy Services: > US$ 1,000,000 for firms; and > US$ 300,000 for individuals In addition, the justifications for all contracts to be issued on the basis of single-source selection will be subject to prior review. For prior review contracts, the amendments for increasing the cost or extension of time beyond 15% of original value shall also be subject to Bank’s prior review. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None. 4. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s “Guidelines: Selection and employment of consultants under IBRD loans and IDA credits & grants by World Bank borrowers” dated January 2011 (as updated in July 2014). 5. Consultancy Assignments with Selection Methods and Time Schedule – As per plan in STEP PROCUREMENT India : Tamil Nadu Sustainable Urban Development Program PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-06-10 2019-11-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150395 GPN Date: Project Name: Tamil Nadu Sustainable Urban Development Program Loan / Credit No: IBRD / 84880 Executing Agency(ies): Tamil Nadu Urban Infrastructure Financial Services Limited WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBR 4 / Construction of A. Results Based Grants for Integrated Storm water Single Stage - One IBRD / 84880 Urban Governance Prior Request for Bids Open - National 0.00 7,116,554.07 Signed drains in Cooum watershed Envelope Component of Cooum water basin IN-TNUIFSL-3669-CW-RFB / A. Results Based Grants for Under Construction of 45 MLD Single Stage - One IBRD / 84880 Urban Governance Prior Request for Bids Open - National 41,129,033.00 0.00 Implementati 2016-11-23 2016-11-23 2016-11-24 2016-11-25 2016-12-19 2019-06-30 TTRO Plant in Kodungaiyur Envelope Component on & its allied works IN-TNUIFSL-11989-CW-RFB / Providing WSIS to A. Results Based Grants for Under Nagercoil Municipality in Single Stage - One IBRD / 84880 Urban Governance Prior Request for Bids Open - National 27,721,222.00 0.00 Implementati 2017-04-07 2017-04-19 2017-05-26 2017-06-07 2017-07-12 2018-01-08 Kanyakumari District Envelope Component on including maintenance period of 12 months IN-TNUIFSL-13575-CW-RFB A. Results Based Grants for Under / Providing Water Supply Single Stage - One IBRD / 84880 Urban Governance Prior Request for Bids Open - National 22,928,739.00 0.00 Implementati 2017-05-29 2017-06-03 2017-07-15 2017-08-14 2017-09-18 2018-03-17 Improvement Scheme in Envelope Component on Namakkal Municipality IN-TNUIFSL-13580-CW-RFB / Providing SCADA A. Results Based Grants for Under arrangements for Water Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 309,904.00 0.00 Implementati 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 Supply Improvement Scheme Envelope Component on in Theni-Allinagaram Municipality IN-TNUIFSL-16436-CW-RFB / CWSS to Sankarakoil, Puliyankudi Municipalities, Thiruvenkadam Town panchayat in Tirunelveli A. Results Based Grants for Under District and Rajapalayam, Single Stage - One IBRD / 84880 Urban Governance Prior Request for Bids Open - National 31,166,797.00 0.00 Implementati 2017-06-02 2017-06-07 2017-07-19 2017-08-18 2017-09-22 2018-03-21 Sivakasi, Thiruthangal Envelope Component on Municipalities in Virudhunagar District including maintenance for a period of 12 months under Package-1 IN-TNUIFSL-16442-CW-RFB / CWSS to Sankarakoil, Puliyankudi Municipalities, Thiruvenkadam Town panchayat in Tirunelveli A. Results Based Grants for Under District and Rajapalayam, Single Stage - One IBRD / 84880 Urban Governance Prior Request for Bids Open - National 27,515,270.00 0.00 Implementati 2017-06-02 2017-06-07 2017-07-19 2017-08-18 2017-09-22 2018-03-21 Sivakasi, Thiruthangal Envelope Component on Municipalities in Virudhunagar District including maintenance for a period of 12 months under Package-2 Page 1 IN-TNUIFSL-5574-CW-RFB / Construction of Integrated Storm Water Drain - A. Results Based Grants for Improvements in Cooum Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 4,479,651.00 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 Basin, Nolambur Watershed Envelope Component in the extended areas of Chennai Corporation - Package - 25 IN-TNUIFSL-5190-CW-RFB / Construction of Integrated Storm Water Drain - A. Results Based Grants for Improvement to Ambattur Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,210,373.00 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 sidco Canal in Cooum basin, Envelope Component Nolambur watershed in extended areas of Chennai Corporation-Package-24 IN-TNUIFSL-19179-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drain - IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,193,594.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Padikuppam Component on Canal under Package 19 A IN-TNUIFSL-19184-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drains - IBRD / 84880 Urban Governance Post Request for Bids Open - National 936,868.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Padikuppam Component on Canal under package - 19 B IN-TNUIFSL-19186-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drains - IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,090,713.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Padikuppam Component on Canal under package - 19 C IN-TNUIFSL-19187-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drains - IBRD / 84880 Urban Governance Post Request for Bids Open - National 866,500.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Padikuppam Component on Canal under package - 19 D IN-TNUIFSL-19190-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drains - IBRD / 84880 Urban Governance Post Request for Bids Open - National 739,514.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Padikuppam Component on Canal under package - 19 E IN-TNUIFSL-19191-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drains - IBRD / 84880 Urban Governance Post Request for Bids Open - National 708,332.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Padikuppam Component on Canal under package - 19 F IN-TNUIFSL-19193-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 796,523.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Ambattur Envelope Component on Sidco Canal under package - 24 A IN-TNUIFSL-19194-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,039,859.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Ambattur Envelope Component on Sidco Canal under package - 24 B Page 2 IN-TNUIFSL-19195-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drains - IBRD / 84880 Urban Governance Post Request for Bids Open - National 867,737.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur Component on Canal under package - 25 A IN-TNUIFSL-19196-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drains - IBRD / 84880 Urban Governance Post Request for Bids Open - National 852,341.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur Component on Canal under package - 25 B IN-TNUIFSL-19197-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drains - IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,157,619.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur Component on Canal under package - 25 C IN-TNUIFSL-19198-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drains - IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,073,031.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur Component on Canal under package - 25 D IN-TNUIFSL-19199-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drains - IBRD / 84880 Urban Governance Post Request for Bids Open - National 988,567.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur Component on Canal under package - 25 E IN-TNUIFSL-19200-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drains - IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,319,263.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur Component on Canal under package - 25 F IN-TNUIFSL-19202-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 871,308.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 A IN-TNUIFSL-19203-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 877,478.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 B IN-TNUIFSL-19204-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 862,083.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 C IN-TNUIFSL-19205-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,285,576.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 D IN-TNUIFSL-19206-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,285,576.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 E IN-TNUIFSL-19207-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,285,576.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 F Page 3 IN-TNUIFSL-19208-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,012,388.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 G IN-TNUIFSL-19210-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,007,032.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 H IN-TNUIFSL-19211-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,007,032.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 I IN-TNUIFSL-19212-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 921,331.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 J IN-TNUIFSL-19213-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 921,331.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 K IN-TNUIFSL-19214-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,269,491.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 L IN-TNUIFSL-19216-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,017,745.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 M IN-TNUIFSL-19217-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,017,745.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 N IN-TNUIFSL-19218-CW-RFB / Construction of Integrated A. Results Based Grants for Under Storm Water Drains - Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,017,745.00 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope Component on Nandambakkam Canal under package - 39 O IN-TNUIFSL-5192-CW-RFB / Construction of Integrated A. Results Based Grants for Single Stage - One Storm water in Cuddalore IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,964,330.00 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 Envelope Municipality under Phase-I Component Package-1 IN-TNUIFSL-5193-CW-RFB / Construction of Integrated A. Results Based Grants for Single Stage - One Storm Water Drain in IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,082,060.00 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 Envelope Cuddalore Municipality under Component Phase-1 Package-2 Page 4 IN-TNUIFSL-5194-CW-RFB / Construction of Integrated A. Results Based Grants for Single Stage - One Storm Water Drain in IBRD / 84880 Urban Governance Post Request for Bids Open - National 2,034,580.00 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 Envelope Cuddalore Municipality under Component Phase-1 Package-3 IN-TNUIFSL-5196-CW-RFB / Construction of Integrated A. Results Based Grants for Single Stage - One Storm Water Drain in IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,336,890.00 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 Envelope Cuddalore Municipality under Component Phase-1 Package-4 IN-TNUIFSL-21867-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drain in IBRD / 84880 Urban Governance Post Request for Bids Open - National 2,906,813.00 0.00 Implementati 2017-07-26 2017-07-31 2017-09-11 2017-10-11 2017-11-15 2018-05-14 Envelope Cuddalore Municipality Phase- Component on 1 Package-1 IN-TNUIFSL-21865-CW-RFB / Construction of Integrated A. Results Based Grants for Under Single Stage - One Storm Water Drain in IBRD / 84880 Urban Governance Post Request for Bids Open - National 3,121,379.00 0.00 Implementati 2017-07-26 2017-07-31 2017-09-11 2017-10-11 2017-11-15 2018-05-14 Envelope Cuddalore Municipality Phase Component on -1 Package-2 IN-TNUIFSL-47449-CW-RFB / Supply Installation and commissioning of 150 nos of A. Results Based Grants for Pending street light lamp posts with Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 92,758.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 LED fittings in the leftover Envelope Component on areas in Divsions 1,2,3,4,6,11,12, Zone1 under Package-1 IN-TNUIFSL-47451-CW-RFB / Supply, Installation and commissioning of 1377 nos of A. Results Based Grants for Pending street light lamp posts with Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 844,229.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 LED fittings in the leftover Envelope Component on areas in Divisions 15,16,17,18,19,20 Zone-2 under Package-2 IN-TNUIFSL-47454-CW-RFB / Supply, Installation, Commissioning of 747 nos of A. Results Based Grants for Pending Street Light lamp posts with Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 475,379.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 LED fittings in the leftover Envelope Component on areas in Divisions 22,23,24,25 Zone 3 under Package-3 IN-TNUIFSL-47455-CW-RFB / Supply, Installation, Commissioning of 407 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 250,790.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 33 Zone 3 under Package-4 IN-TNUIFSL-47457-CW-RFB / Supply, Installation, Commissioning of 230 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 145,769.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 26,32 Zone 3 under Package-5 IN-TNUIFSL-47459-CW-RFB / Supply, Installation, Commissioning of 196 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 114,751.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 27,30 Zone 3 under Package-6 Page 5 IN-TNUIFSL-47460-CW-RFB / Supply, Installation, Commissioning of 210nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 120,854.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 28,29 Zone 3 under Package-7 IN-TNUIFSL-47461-CW-RFB / Supply, Installation, Commissioning of 2531 nos A. Results Based Grants for Pending of Street Light lamp posts Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,460,668.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 with LED fittings in the Envelope Component on leftover areas in Divisions 79,83 Zone 7 under Package- 8 IN-TNUIFSL-47465-CW-RFB / Supply, Installation, Commissioning of 2370 nos A. Results Based Grants for Pending Single Stage - One of Street Light lamp posts IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,341,608.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope with LED fittings in the Component on leftover areas in Divisions 82 Zone 7 under Package-9 IN-TNUIFSL-47466-CW-RFB / Supply, Installation, Commissioning of 629 nos of A. Results Based Grants for Pending Street Light lamp posts with Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 420,732.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 LED fittings in the leftover Envelope Component on areas in Divisions 81,84,85,86,87,88,89,91,92 Zone 7 under Package-10 IN-TNUIFSL-47467-CW-RFB / Supply, Installation, Commissioning of 792 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 475,468.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 80,90,93 Zone 7 under Package-11 IN-TNUIFSL-47473-CW-RFB / Supply, Installation, Commissioning of 456 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 282,928.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 143 Zone 11 under Package-12 IN-TNUIFSL-47474-CW-RFB / Supply, Installation, Commissioning of 261 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 144,078.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 145 Zone 11 under Package-13 IN-TNUIFSL-47476-CW-RFB / Supply, Installation, Commissioning of 458 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 289,241.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 147 Zone 11 under Package-14 IN-TNUIFSL-47483-CW-RFB / Supply, Installation, Commissioning of 228 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 135,988.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 148, 151 Zone 11 under Package-15 Page 6 IN-TNUIFSL-47484-CW-RFB / Supply, Installation, Commissioning of 288 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 178,988.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 149 Zone 11 under Package-16 IN-TNUIFSL-47485-CW-RFB / Supply, Installation, Commissioning of 560 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 329,707.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 150 Zone 11 under Package-17 IN-TNUIFSL-47487-CW-RFB / Supply, Installation, Commissioning of 187 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 117,778.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 152 Zone 11 under Package-18 IN-TNUIFSL-47488-CW-RFB / Supply, Installation, Commissioning of 179 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 114,590.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 154 Zone 11 under Package-19 IN-TNUIFSL-47489-CW-RFB / Supply, Installation, Commissioning of 996 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 582,779.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 153,155 Zone 11 under Package-20 IN-TNUIFSL-47490-CW-RFB / Supply, Installation, Commissioning of 130 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 74,783.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 157,158 Zone 12 under Package-21 IN-TNUIFSL-47491-CW-RFB / Supply, Installation, Commissioning of 1814 nos A. Results Based Grants for Pending of Street Light lamp posts Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,109,420.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 with LED fittings in the Envelope Component on leftover areas in Divisions 188 Zone 14 under Package- 22 IN-TNUIFSL-47492-CW-RFB / Supply, Installation, Commissioning of 827 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 513,312.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 189 Zone 14 under Package-23 IN-TNUIFSL-47495-CW-RFB / Supply, Installation, Commissioning of 484 nos of A. Results Based Grants for Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Urban Governance Post Request for Bids Open - National 312,739.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover Component on areas in Divisions 190,191 Zone 14 under Package-24 Page 7 IN-TNUIFSL-47497-CW-RFB / Supply, Installation, Commissioning of 794 nos of Street Light lamp posts with A. Results Based Grants for Pending Single Stage - One LED fittings in the leftover IBRD / 84880 Urban Governance Post Request for Bids Open - National 493,215.00 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope areas in Divisions Component on 168,169,183,187 Zone-14 & Division 192-200 Zone 15 under Package-25 IN-TNUIFSL-49154-CW-RFB / Restoration of Zamin A. Results Based Grants for Pending Single Stage - One Pallavaram Periya Eri and IBRD / 84880 Urban Governance Post Request for Bids Open - National 2,346,124.00 0.00 Implementati 2018-02-16 2018-02-16 2018-02-16 2018-02-28 2018-04-04 2018-10-01 Envelope Keelkattalai Eri in Component on Pallavaram Municipality IN-TNUIFSL-62353-CW-RFB / Construction of Storm Water Drain in Tuticorin Corporation - Construction A. Results Based Grants for Pending Single Stage - One of Storm water drain at IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,772,906.00 0.00 Implementati 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 2019-03-04 Envelope Kalangarqai, Kalugupathai Component on and Kaluthaipathai odai int o S.V.Kulam under Package- II IN-TNUIFSL-62354-CW-RFB / Construction of Storm Water Drainage in Tuticorin A. Results Based Grants for Pending Corporation - Rejunvenation Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,650,745.00 0.00 Implementati 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 2019-03-04 of main S.V.Kulam, Envelope Component on Improvement of Mullikulam tank and related works under Package-III IN-TNUIFSL-62356-CW-RFB / Construction of Storm Water Drain in Tuticorin Corporation - Construction of A. Results Based Grants for Pending Single Stage - One Storm Water Drain from IBRD / 84880 Urban Governance Post Request for Bids Open - National 1,660,141.00 0.00 Implementati 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 2019-03-04 Envelope S.V.Kulam along Meelavittan Component on Road and drain towards railway side and related works under Package-IV IN-TNUIFSL-62358-CW-RFB / Construction of Storm Water Drain in Tuticorin A. Results Based Grants for Pending Single Stage - One Corporation - Construction of IBRD / 84880 Urban Governance Post Request for Bids Open - National 980,425.00 0.00 Implementati 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 2019-03-04 Envelope Main Storm Water Drain of Component on Mullakadu Odai and related work under Package-VI IN-TNUIFSL-83343-CW-RFB / Construction of Storm Water Drain in Tuticorin Corporation- Construction of A. Results Based Grants for Pending Single Stage - One Channnels for diversion of IBRD / 84880 Urban Governance Post Request for Bids Open - National 9,093,134.00 0.00 Implementati 2018-10-24 2018-10-29 2018-12-10 2019-01-09 2019-02-13 2019-08-12 Envelope kalangakari odai to Component on periapallam odai and related works along NH-45B under Package-1 IN-TNUIFSL-83344-CW-RFB / Construction of Storm Water Drain in Tuticorin Corporation-Construction of A. Results Based Grants for Pending Storm Water Drainage for Single Stage - One IBRD / 84880 Urban Governance Post Request for Bids Open - National 8,129,164.00 0.00 Implementati 2018-10-24 2018-10-29 2018-12-10 2019-01-09 2019-02-13 2019-08-12 diversion of flow of Envelope Component on Chengulam Odai to Upparu river and related works along NH-7A under Package- 5 GOODS Page 8 Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-TNUIFSL-934-NC-DIR / A. Results Based Grants for Technology workshop on IBRD / 84880 Urban Governance Post Direct Selection Direct 7,831.00 0.00 Canceled 2016-08-16 2016-08-21 2016-09-12 2016-10-31 Solid Waste Management Component (Two days) at Chennai CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBR 2 / Project Management Consultancy A. Results Based Grants for Services for Implementation Quality And Cost- Open - IBRD / 84880 Urban Governance Prior 0.00 2,294,591.76 Signed of Integrated Storm water Based Selection International Component drain in the extended areas of Chennai Corporation WBR 7 / Preparation of Base Map, Property and A. Results Based Grants for Utility Mapping and Door to Quality And Cost- Open - IBRD / 84880 Urban Governance Prior 0.00 1,099,564.93 Signed Door Survey using Geo- Based Selection International Component Spatial Techniques for Corporation of Chennai IN-TNUIFSL-915-CS-QCBS / Consultancy Services for preparation of Detailed Project Reports (DPRs) for A. Results Based Grants for Quality And Cost- providing Under Ground IBRD / 84880 Urban Governance Post Open - National 117,463.00 266,107.98 Signed 2016-08-04 2016-08-04 2016-08-04 2016-09-12 2016-09-30 2016-11-04 2016-12-09 2017-12-09 Based Selection Sewerage Schemes (UGSS) Component for eleven added areas of Greater Chennai Corporation for CMWSSB IN-TNUIFSL-928-CS-QCBS / Consultancy services for A. Results Based Grants for preparation of comprehensive Quality And Cost- Open - IBRD / 84880 Urban Governance Post 626,468.00 156,127.65 Signed 2016-08-04 2016-08-04 2016-08-04 2016-09-12 2016-09-30 2016-11-04 2016-12-09 2017-12-09 DPR for UGSS in 14 ULBs Based Selection International Component in Poonamalle cluster A in Chennai Metropolitan Area IN-TNUIFSL-932-CS-QCBS / Consultancy services for A. Results Based Grants for preparation of comprehensive Quality And Cost- Open - IBRD / 84880 Urban Governance Post 469,851.00 138,777.39 Signed 2016-08-04 2016-08-04 2016-08-04 2016-09-12 2016-09-30 2016-11-04 2016-12-09 2017-12-09 DPR for UGSS in 9 ULBs Based Selection International Component in Poonamalle cluster B in Chennai Metropolitan Area IN-TNUIFSL-2618-CS-QCBS / Consulting services for preparation of Feasibility Report, Bid Documents and A. Results Based Grants for Quality And Cost- Open - conducting Bid Process IBRD / 84880 Urban Governance Post 31,323.00 31,835.28 Completed 2016-10-17 2016-10-17 2016-10-27 2016-11-28 2016-12-13 2017-01-13 2017-02-17 2018-02-17 Based Selection International Management for Establishing Component Solar Roof Tops in Buildings maintained by Greater Chennai Corporation Page 9 IN-TNUIFSL-2619-CS-QCBS / Consulting services for Bid Process Management for A. Results Based Grants for Establishing Solar Roof Tops Quality And Cost- Open - IBRD / 84880 Urban Governance Post 62,647.00 24,016.07 Signed 2016-10-17 2016-10-17 2016-10-27 2016-11-28 2016-12-13 2017-01-13 2017-02-17 2018-02-17 in Buildings maintained by Based Selection International Component ULB's in Tamil Nadu under O/o Commissionerate of Municipal Administration IN-TNUIFSL-933-CS-QCBS / Appointment of Consultant A. Results Based Grants for for formation of Asset Quality And Cost- IBRD / 84880 Urban Governance Post Open - National 31,323.00 0.00 Canceled 2016-08-08 2016-08-08 2016-09-01 2016-10-06 2016-10-19 2016-11-23 2016-12-28 2017-12-28 Management Company for Based Selection Component Greater Chennai Corporation in PDGF under TNSUDP IN-TNUIFSL-2783-CS-QCBS / Consultancy services for Proof Checking of Engineering Designs and Costing of the DPR prepared by TWAD Board for A. Results Based Grants for Quality And Cost- Providing CWSS to IBRD / 84880 Urban Governance Post Open - National 46,986.00 37,046.57 Signed 2016-10-25 2016-10-25 2016-10-25 2016-11-29 2016-12-09 2017-01-02 2017-01-23 2017-07-22 Based Selection Nattarasankottai Town Component Panchayat and 1069 Rural Habitations with Bulk Provision to 7 Town Panchayats and 1228 Rural Habitatio IN-TNUIFSL-2831-CS-QCBS / Consulting services for preparation of Detailed Project Report for Plugging A. Results Based Grants for of outfalls, Interception & Quality And Cost- Open - IBRD / 84880 Urban Governance Post 156,617.00 0.00 Canceled 2016-11-01 2016-11-01 2016-11-01 2016-12-12 2016-12-22 2017-01-08 2017-02-08 2017-11-10 Diversion of Sewerage, Solid Based Selection International Component Waste Management, Flood carrying capacity, structural adequacy and R&R in Major drains in Cooum Basin IN-TNUIFSL-2832-CS-QCBS / Consulting services for preparation of Detailed Project Report for Plugging A. Results Based Grants for of outfalls, Interception & Quality And Cost- Open - IBRD / 84880 Urban Governance Post 195,771.00 0.00 Canceled 2016-11-01 2016-11-01 2016-11-01 2016-12-12 2016-12-22 2017-01-08 2017-02-08 2017-11-10 Diversion of Sewerage, Solid Based Selection International Component Waste Management, Flood carrying capacity, structural adequacy and R&R in Major drains in Adyar Basin IN-TNUIFSL-5533-CS-QBS / Consulting services for preparation of Feasibility Report and Detailed Project A. Results Based Grants for Report (DPR) for construction Quality And Cost- IBRD / 84880 Urban Governance Post Open - National 117,463.00 107,245.11 Completed 2017-01-12 2017-01-12 2017-01-19 2017-02-27 2017-03-15 2017-03-29 2017-04-26 2017-11-22 of bridges connecting Based Selection Component Nesapakkam to Nandampakkam over Adyar River at two locations for Greater Chennai Corporation IN-TNUIFSL-5534-CS-QCBS / Consulting services for preparation of Feasibility Report and Detailed Project Report (DPR) for construction A. Results Based Grants for Quality And Cost- of New bridge at Stephenson IBRD / 84880 Urban Governance Post Open - National 117,463.00 67,651.46 Completed 2017-01-12 2017-01-12 2017-01-19 2017-02-27 2017-03-06 2017-03-29 2017-04-26 2017-11-22 Based Selection road across Otteri Nullah Component and Widening of existing bridge across Cooum at Arunachala road for Greater Chennai Corporat Page 10 IN-TNUIFSL-5540-CS-QCBS / Consulting Services for preparation of Revised Detailed Project Report A. Results Based Grants for Quality And Cost- (DPR) for providing IBRD / 84880 Urban Governance Post Open - National 93,970.00 264,583.65 Signed 2017-01-20 2017-01-20 2017-01-30 2017-03-13 2017-03-20 2017-04-03 2017-05-08 2018-05-08 Based Selection Integrated Storm Water Component Drains (SWD) for Kosasthalaiyar basin in Greater Chennai Corporation IN-TNUIFSL-5544-CS-QCBS / Consultancy Services for Proof Checking of A. Results Based Grants for Engineering Designs and Quality And Cost- IBRD / 84880 Urban Governance Post Open - National 31,325.00 11,653.46 Signed 2017-01-30 2017-01-30 2017-02-09 2017-03-23 2017-03-30 2017-04-13 2017-05-18 2018-05-18 Costing of DPR for providing Based Selection Component Water Supply Improvement Scheme to Bodinayakkanur Municipality IN-TNUIFSL-10422-CS- QCBS / Consulting Services for preparation of Feasibility Report and Transaction A. Results Based Grants for Advisory Services for setting Quality And Cost- IBRD / 84880 Urban Governance Post Open - National 46,985.00 25,155.56 Signed 2017-03-22 2017-03-22 2017-04-03 2017-05-01 2017-05-31 2017-07-05 2017-08-09 2018-08-09 up a Multi Level Parking Based Selection Component (MLP) at Uthamar Gandhi Salai in Chennai under PPP mode for Greater Chennai Corporation IN-TNUIFSL-9650-CS-QCBS / Consulting Services for A. Results Based Grants for Quality And Cost- assessment of Industrial IBRD / 84880 Urban Governance Post Open - National 62,647.00 0.00 Canceled 2017-03-10 2017-03-27 2017-05-10 2017-06-07 2017-07-07 2017-08-11 2017-09-15 2018-03-15 Based Selection Water Supply Scenario in Component Tamil Nadu IN-TNUIFSL-11080-CS- QCBS / Consulting services for preparation of a A. Results Based Grants for Quality And Cost- Feasibility Report and IBRD / 84880 Urban Governance Post Open - National 62,647.00 20,238.14 Completed 2017-03-31 2017-03-31 2017-04-03 2017-05-05 2017-05-12 2017-06-16 2017-07-21 2018-04-30 Based Selection Detailed Project Report Component (DPR) for construction of Bus Stand for Namakkal Municipality IN-TNUIFSL-10923-CS- QCBS / Planning, Setting up and Operationalizing a Real Time Flood Forecasting & Spatial DSS for Adyar, A. Results Based Grants for Cooum, Kosasthalayar & Quality And Cost- Open - IBRD / 84880 Urban Governance Prior 4,698,512.00 0.00 Under Review 2017-03-24 2017-03-24 2017-03-24 2017-05-03 2017-06-02 2017-07-07 2017-08-11 2022-03-31 Kovalam Basins & setting Based Selection International Component up of a Hydro Modelling cum Flood Monitoring Control Room at SEOC, Chennai, setting up of Flood Monitoring Co IN-TNUIFSL-11644-CS- QCBS / Consulting Services for Preparation of Feasibility Report and conducting A. Results Based Grants for Quality And Cost- Open - Transaction Advisory Services IBRD / 84880 Urban Governance Post 156,617.20 0.00 Canceled 2017-04-05 2017-04-06 2017-05-15 2017-06-20 2017-07-05 2017-08-09 2017-09-13 2018-09-13 Based Selection International for Establishing large Solar Component Parks in various places in Tamil Nadu under Public Private Partnership mode IN-TNUIFSL-11651-CS- QCBS / Consulting Services A. Results Based Grants for Quality And Cost- Open - for Preparation of Detailed IBRD / 84880 Urban Governance Post 140,955.00 209,679.19 Signed 2017-04-05 2017-04-06 2017-05-10 2017-06-12 2017-07-03 2017-08-07 2017-09-11 2018-06-25 Based Selection International Project Report for Component Restoration of Ennore Creek Page 11 IN-TNUIFSL-11654-CS- QCBS / Consulting Services for Preparation of Detailed A. Results Based Grants for Quality And Cost- Open - Project Report for IBRD / 84880 Urban Governance Post 140,955.00 126,578.45 Signed 2017-04-05 2017-04-06 2017-05-10 2017-06-12 2017-07-03 2017-08-07 2017-09-11 2018-06-25 Based Selection International Restoration of Kovalam Component Creek (Muttukadu Back waters) IN-TNUIFSL-15977-CS- QCBS / Planning, Setting up and Operationalizing a Real Time Flood Forecasting & Spatial DSS for Adyar, A. Results Based Grants for Cooum, Kosasthalayar & Quality And Cost- Open - IBRD / 84880 Urban Governance Prior 4,698,512.00 4,216,934.12 Signed 2017-05-23 2017-05-23 2017-05-23 2017-06-30 2017-07-30 2017-09-03 2017-11-01 2022-03-31 Kovalam Basins & setting Based Selection International Component up of a Hydro Modelling cum Flood Monitoring Control Room at SEOC, GCC, Tiruvallur & Kancheepuram Collectorate IN-TNUIFSL-5543-CS-QCBS / Consulting Services for preparation of Detailed Project Report (DPR) for providing Storm Water A. Results Based Grants for Quality And Cost- Drains(SWD)for missing links IBRD / 84880 Urban Governance Post Open - National 23,493.00 0.00 Canceled 2017-01-20 2017-01-20 2017-01-27 2017-03-08 2017-03-15 2017-03-29 2017-04-26 2017-10-23 Based Selection and for draining the flooded Component water in the subways to integrate with the existing Storm Water Drains in various locations for GCC IN-TNUIFSL-9520-CS-QCBS / Consulting Services for preparation of Feasibility A. Results Based Grants for Quality And Cost- Report for assessing the IBRD / 84880 Urban Governance Post Open - National 45,865.00 0.00 Canceled 2017-03-09 2017-03-27 2017-05-10 2017-06-07 2017-07-07 2017-08-11 2017-09-15 2018-09-15 Based Selection potential of Neyveli mines as Component water storage reservoirs for CMWSSB IN-TNUIFSL-21924-CS- QCBS / Consulting Services A. Results Based Grants for Quality And Cost- for Environmental and Social IBRD / 84880 Urban Governance Post Open - National 46,875.00 14,250.50 Completed 2017-07-26 2017-07-26 2017-07-26 2017-08-28 2017-09-04 2017-09-18 2017-11-06 2018-03-31 Based Selection Audit for projects under Component TNSUDP (2017) IN-TNUIFSL-21927-CS- QCBS / Consulting Services to prepare detailed study report for providing Equitable Water Supply to A. Results Based Grants for Quality And Cost- all ULBS based on the IBRD / 84880 Urban Governance Post Open - National 93,750.00 0.00 Canceled 2017-08-21 2017-08-21 2017-08-21 2017-09-25 2017-10-16 2017-11-06 2017-12-18 2018-07-31 Based Selection study of existing Water Component Supply Schemes in Karaikudi, Thiruvannamalai, Gobichettipalayam & Chengalpattu Municipalities IN-TNUIFSL-34932-CS- QCBS / Consulting Services for preparation of a Detailed A. Results Based Grants for Project Report for Optimising Quality And Cost- IBRD / 84880 Urban Governance Post Open - National 240,000.00 134,433.01 Signed 2017-11-02 2017-11-06 2017-12-01 2017-12-29 2018-01-12 2018-02-16 2018-03-23 2019-03-23 and Revamping of the Based Selection Component existing Distribution Network and SCADA for Salem Corporation IN-TNUIFSL-37743-CS- QCBS / Consultancy Services for preparation of Feasibility A. Results Based Grants for Quality And Cost- cum Detailed Project Report IBRD / 84880 Urban Governance Post Open - National 51,564.00 0.00 Canceled 2017-11-22 2017-12-06 2017-12-16 2018-01-18 2018-01-22 2018-02-20 2018-03-27 2018-08-31 Based Selection (DPR) for reconstruction of Component VOC Market for Salem City Municipal Corporation Page 12 IN-TNUIFSL-37747-CS- QCBS / Consulting Services for preparation of Feasibility A. Results Based Grants for Report cum Detailed Project Quality And Cost- IBRD / 84880 Urban Governance Post Open - National 69,695.00 0.00 Canceled 2017-11-22 2017-12-06 2017-12-20 2018-01-22 2018-01-29 2018-02-19 2018-03-26 2018-12-20 Report for Rehabilitation of Based Selection Component Defunct Dumping site at Erumapalayam in Salem City Municipal Corporation IN-TNUIFSL-118513-CS- A. Results Based Grants for QCBS / Consulting Services Quality And Cost- Pending IBRD / 84880 Urban Governance Post Open - National 40,000.00 0.00 2019-06-30 2019-07-21 2019-09-03 2019-10-01 2019-10-31 2019-12-05 2020-01-09 2021-01-08 for Environmental and Social Based Selection Implementation Component Audit (2019) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-TNUIFSL-5191-CS-CDS / Appointment of Consultant for Preparation of common bid document for Operation and Maintenance of water A. Results Based Grants for supply improvement scheme IBRD / 84880 Urban Governance Post Direct Selection Direct 13,000.00 0.00 Canceled 2017-01-11 2017-01-21 2017-03-27 2017-09-23 and updating the common Component bid document for Operation and Maintenance of Underground Sewerage Schemes IN-TNUIFSL-5538-CS-QCBS / Consulting Services for preparation of a Technical Report for "Assessing the Level of Contamination in A. Results Based Grants for and around the solid waste IBRD / 84880 Urban Governance Post Direct Selection Direct 54,816.00 46,769.04 Signed 2017-01-19 2017-01-19 2017-02-23 2017-08-22 dumping sites at Perungudi Component in Greater Chennai Corporation and to suggest the remediation measures required" IN-TNUIFSL-5539-CS-CDS / Consulting Services for preparation of a Technical Report for "Assessing the Level of Contamination in A. Results Based Grants for and around the solid waste IBRD / 84880 Urban Governance Post Direct Selection Direct 54,816.00 46,769.04 Signed 2017-01-19 2017-01-26 2017-03-02 2017-08-29 dumping sites at Component Kodungaiyur in Greater Chennai Corporation and to suggest the remediation measures required" IN-TNUIFSL-15988-CS-CDS / Consulting Services for preparation of Feasibility A. Results Based Grants for Report for assessing the IBRD / 84880 Urban Governance Post Direct Selection Direct 39,063.00 28,797.65 Signed 2017-05-23 2017-05-23 2017-06-13 2017-08-14 potential of Neyveli mines as Component water storage reservoirs for CMWSSB IN-TNUIFSL-40766-CS-CDS / Providing Project Management Consultancy A. Results Based Grants for service for implementation of IBRD / 84880 Urban Governance Post Direct Selection Direct 100,000.00 84,593.91 Signed 2017-12-22 2017-12-26 2018-03-16 2018-09-12 Integrated Storm Water Component Drain Project under Phase-I in Cuddalore Municipality Page 13 IN-TNUIFSL-75461-CS-CDS / Supervisory Consultant Services for Planning, Setting up and Operationalizing a A. Results Based Grants for Real Time Flood Forecasting IBRD / 84880 Urban Governance Post Direct Selection Direct 299,295.00 275,851.13 Signed 2018-08-24 2018-08-24 2018-10-02 2022-03-20 and Spatial Decision Support Component System for Adyar, Cooum, Kosasthalayar and Kovalam Basins IN-TNUIFSL-102618-CS-CDS / Consulting Services as a A. Results Based Grants for Technical Quality Consultant IBRD / 84880 Urban Governance Post Direct Selection Direct 45,418.00 11,938.23 Signed 2019-02-22 2019-02-22 2019-03-07 2020-02-29 (TQC) for Consultancy Component Assignments under taken by TNUIFSL IN-TNUIFSL-143931-CS-CDS / Consulting Services for Carrying out Drone Survey using Optical Sensors in Adyar, Cooum, Kovalam, A. Results Based Grants for Kosasthalayar, Araniar, Under IBRD / 84880 Urban Governance Post Direct Selection Direct 777,602.00 0.00 2019-11-06 2019-11-11 2019-12-06 2020-12-05 Nagariyar and Nandhiyar Implementation Component Basins for Real Time Flood Forecasting and Spatial Decision Support System (RTFF & SDSS) in Chennai Basin IN-TNUIFSL-146081-CS- INDV / Providing Services as Technical Quality Consultant A. Results Based Grants for Individual Pending (GIS cum Hydro Modelling IBRD / 84880 Urban Governance Post Consultant Direct 22,713.00 0.00 2020-01-05 2020-01-15 2020-01-31 2020-02-11 2021-02-01 Implementation Expert) for the consultancy Component Selection assignments undertaken by TNUIFSL Page 14