The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Central Highlands Connectivity Improvement Project (P159238) EAST ASIA AND PACIFIC | Vietnam | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 4 | ARCHIVED on 01-May-2019 | ISR36838 | Implementing Agencies: Socialist Republic of Vietnam, Projects Management Unit No. 2 Key Dates Key Project Dates Bank Approval Date: 22-Jun-2017 Effectiveness Date: 22-May-2018 Planned Mid Term Review Date: 30-Nov-2020 Actual Mid-Term Review Date: -- Original Closing Date: 30-Jun-2023 Revised Closing Date: 30-Jun-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve the connectivity, safety and climate-resilience of the National Highway 19. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Road Improvements:(Cost $145.00 M) Implementation Support:(Cost $8.70 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Unsatisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Unsatisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The Project was approved by the Board on June 22, 2017, and the FA was signed on December 27, 2017, and the effectiveness was declared on May 22, 2018. The Project activities has not started yet due to the unavailability of the Government's budget and delays in selection of detailed design and documentation consulting services. 5/1/2019 Page 1 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Low Low Low Macroeconomic Low Low Low Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Substantial Institutional Capacity for Implementation and Sustainability Moderate Moderate Substantial Fiduciary Substantial Substantial Substantial Environment and Social Moderate Substantial Moderate Stakeholders Moderate Moderate Substantial Other Low Low Low Overall Moderate Moderate Moderate Results PDO Indicators by Objectives / Outcomes To improve the connectivity, safety and climate-resilience of the National Highway 19 IN00696097 ►Annual average daily traffic (AADT) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4,950.00 4,950.00 4,950.00 6,600.00 Date 31-Mar-2017 23-Oct-2018 16-Apr-2019 30-Jun-2023 IN00696098 ►Average travel time on the NH19 Corridor (Hours, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 6.00 6.00 6.00 5.00 Date 31-Mar-2017 23-Oct-2018 16-Apr-2019 30-Jun-2023 IN00696099 ►Number of kilometers of International Road Assessment Program (iRAP) 3-star rating or above for both cars and motorcycles on the NH19 Corridor (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 75.00 75.00 75.00 228.00 Date 31-Mar-2017 23-Oct-2018 16-Apr-2019 30-Jun-2023 5/1/2019 Page 2 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) IN00696100 ►Kilometers of roads that are upgraded in compliance with climate/disaster resilient design standards (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 31-Mar-2017 23-Oct-2018 16-Apr-2019 30-Jun-2023 Intermediate Results Indicators by Components Road Improvements IN00696101 ►Roads rehabilitated, Non-rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 153.00 Date 31-Mar-2017 23-Oct-2018 16-Apr-2019 30-Jun-2023 IN00696104 ►Share of citizens from affected communes who participated in consultations (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 31-Mar-2017 23-Oct-2018 16-Apr-2019 30-Jun-2023 IN00696105 ►Share of women from affected communes who participated in consultations (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 31-Mar-2017 23-Oct-2018 16-Apr-2019 30-Jun-2023 Implementation Support IN00696102 ►Manual for motorcycle lane design and specifications (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 31-Mar-2017 23-Oct-2018 16-Apr-2019 30-Jun-2023 IN00696103 ►Guidelines for resilient road design and standards (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes 5/1/2019 Page 3 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Date 31-Mar-2017 23-Oct-2018 16-Apr-2019 30-Jun-2023 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P159238 IDA-61080 Effective USD 140.50 140.50 0.00 0.00 142.48 0% P159238 IDA-61090 Effective USD 9.50 9.50 0.00 0.00 9.59 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P159238 IDA-61080 Effective 22-Jun-2017 27-Dec-2017 22-May-2018 30-Jun-2023 30-Jun-2023 P159238 IDA-61090 Effective 22-Jun-2017 27-Dec-2017 22-May-2018 30-Jun-2023 30-Jun-2023 Cumulative Disbursements 5/1/2019 Page 4 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 5/1/2019 Page 5 of 5