PROCUREMENT PLAN (Textual Part) Project information: Afghanistan Modernizing Afghan State Owned Banks (P161348) Project Implementation agency: Ministry of Finance Date of the Procurement Plan: May 2, 2018 Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Afghanistan Procurement Law, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is applicable for those contracts identified in the Procurement Plan tables]; Other Relevant Procurement Information. NA PROCUREMENT Afghanistan : Modernizing Afghan State-Owned Banks Project PLAN General Information Country: Afghanistan Bank’s Approval Date of the Original Procurement Plan: 2018-05-05 2020-01-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161348 GPN Date: Project Name: Modernizing Afghan State-Owned Banks Project Loan / Credit No: IDA / V0820, IDA / D2830 Executing Agency(ies): Ministry of Finance WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MASOB/AF/G-10 / POS Component 2: Institutional (Machines 305 Terminals Development, Business Single Stage - One IDA / V0820 Post Request for Bids Open - National 0.00 Canceled 2018-07-22 2018-07-27 2018-09-07 2018-10-07 2018-11-11 2019-05-10 Units, Switch, Integration) Strategy, and Information Envelope for NKB BMA and BP Technology of SBs Component 2: Institutional MASOB/AF/G-13 / Under Development, Business Single Stage - One Procurement of Storage IDA / V0820 Post Request for Bids Open - National 0.00 Implementati 2018-06-26 2018-07-01 2018-08-12 2018-09-11 2018-10-16 2019-04-14 Strategy, and Information Envelope Devices for BP and BMA on Technology of SBs Component 2: Institutional MASOB/AF/G-17 / Under Development, Business Open - Single Stage - One Implementation of DR IDA / V0820 Post Request for Bids 0.00 Implementati 2018-06-18 2018-06-23 2018-08-04 2018-09-03 2018-10-08 2019-04-06 Strategy, and Information International Envelope Center for BMA and BP on Technology of SBs Component 3: Project Pending MASOB/AF/G-20 / Request for Single Stage - One IDA / V0820 Implementation and Post Limited 0.00 Implementati 2018-05-06 2018-07-01 2018-12-28 Furniture Quotations Envelope Monitoring on MASOB/AF/G-23 / Switch Component 2: Institutional Under for BP SAN switch for Development, Business Request for Single Stage - One IDA / V0820 Post Limited 0.00 Implementati 2018-06-04 2018-07-30 2019-01-26 Storage and Database Strategy, and Information Quotations Envelope on connectivity. Technology of SBs MASOB/AF/G-24 / Storage Component 2: Institutional Pending Tek tape for BP (Tape Development, Business Request for Single Stage - One IDA / V0820 Post Limited 0.00 Implementati 2018-06-25 2018-08-20 2019-02-16 Library with Tapes for Strategy, and Information Quotations Envelope on Backups) Technology of SBs MASOB/AF/G-25 / Rack with necessary network Component 2: Institutional accessories for BP (1 out of Under Development, Business Request for Single Stage - One 2 Rack will be Placed at IDA / V0820 Post Limited 0.00 Implementati 2018-05-28 2018-07-23 2019-01-19 Strategy, and Information Quotations Envelope Primary site and the other on Technology of SBs 1 will be placed at DR site).(Qty2) Page 1 MASOB/AF/G-26 / Non- Oracle Hardware for PR & Component 2: Institutional Under DR for BP (Barracuda Development, Business Request for Single Stage - One IDA / V0820 Post Limited 0.00 Implementati 2018-06-02 2018-07-28 2019-01-24 Load Balancer Appliance Strategy, and Information Quotations Envelope on with 3 Years subscription) Technology of SBs (Qty 1 ) MASOB/AF/G-30 / Network Hardware for PR&DR for Component 2: Institutional Pending BP (Network devices are Development, Business Request for Single Stage - One IDA / V0820 Post Limited 0.00 Implementati 2018-06-02 2018-07-28 2019-01-24 needed for the connectivity Strategy, and Information Quotations Envelope on and management of Primary Technology of SBs and DR sites) MASOB/AF/G-31 / 2960 24 Cisco Switch (Qty4) for BP Component 2: Institutional Under (Network devices are needed Development, Business Request for Single Stage - One IDA / V0820 Post Limited 0.00 Implementati 2018-06-02 2018-07-28 2019-01-24 for the connectivity and Strategy, and Information Quotations Envelope on management of Primary and Technology of SBs DR sites) MASOB/AF/G-32 / ISR 4331 Cisco Router (Qty2 ) for Component 2: Institutional Pending BP (Network devices are Development, Business Request for Single Stage - One IDA / V0820 Post Limited 0.00 Implementati 2018-06-02 2018-07-28 2019-01-24 needed for the connectivity Strategy, and Information Quotations Envelope on and management of Primary Technology of SBs and DR sites) MASOB/AF/G-33 / Oracle 11g R2 Real Application Cluster with 1 Year Support for BP ( Number Of Component 2: Institutional Licenses 14) This the Core Development, Business Open - Single Stage - One IDA / V0820 Prior Request for Bids 0.00 Canceled 2018-06-15 2018-06-20 2018-08-01 2018-08-31 2018-10-05 2019-04-03 Cluster software used for Strategy, and Information International Envelope Database Clustering to Technology of SBs achieve Highly available and scalable Database and Applications MASOB/AF/G-36 / Implementation of Hardware, RAC & DG configuration, all other servers configuration Component 2: Institutional i.e. domain, exchange server, Pending Development, Business Single Stage - One Antivirus and FTP server IDA / V0820 Post Request for Bids Open - National 0.00 Implementati 2018-05-28 2018-06-02 2018-07-14 2018-08-13 2018-09-17 2019-03-16 Strategy, and Information Envelope including complete DR on Technology of SBs setup.This is Oracle Database Enterprise Edition option and mandatory for Database Performance MASOB/AF/G-19 / Component 3: Project Pending Procurement of Office Request for Single Stage - One IDA / V0820 Implementation and Post Limited 0.00 Implementati 2018-06-30 2018-08-25 2019-02-21 Equipment (Copiers, Quotations Envelope Monitoring on Printers, Fax, etc) MASOB/AF/G-12 / Backup Procedure upgradeBMA, Currently BMA are using DVDs to keep the backup of CCTV footage. We are Component 2: Institutional Pending requesting to purchase Tape Development, Business Request for Single Stage - One IDA / V0820 Post Limited 0.00 Implementati 2018-06-15 2018-08-10 2019-02-06 Drives Hardware to take Strategy, and Information Quotations Envelope on and keep the backup, Technology of SBs therefor we have requested purchase of 3 LTO 7 Tape Libraries and 90 LTO 7 Carti Page 2 MASOB/AF/G-27 / Servers For Core Application Server -2 out of 3 Servers will be placed at Primary site to Component 2: Institutional host the Core Banking Development, Business Request for Single Stage - One Application in a Highly IDA / V0820 Post Limited 0.00 Canceled 2018-06-25 2018-08-20 2019-02-16 Strategy, and Information Quotations Envelope Available and Performance Technology of SBs Optimized configuration. 1 Server will be placed to host the Core Banking Application at DR s Component 2: Institutional MASOB/AF/G-9 / IT Development, Business Request for Single Stage - One IDA / V0820 Post Limited 0.00 Canceled 2018-06-26 2018-08-21 2019-02-17 Security Equipment Strategy, and Information Quotations Envelope Technology of SBs MASOB/AF/G-8 / Call Component 2: Institutional Under Center system infrastructure Development, Business Open - Single Stage - One IDA / V0820 Post Request for Bids 0.00 Implementati 2018-07-15 2018-07-20 2018-08-31 2018-09-30 2018-11-04 2019-05-03 upgradation (Hardware + Strategy, and Information International Envelope on Software) Technology of SBs Component 2: Institutional MASOB/AF/G-18 / Development, Business Open - Single Stage - One Procurement of Generators IDA / V0820 Post Request for Bids 232,136.49 Signed 2019-02-10 2019-02-15 2019-03-29 2019-04-28 2019-06-02 2019-11-29 Strategy, and Information International Envelope for NKB,BMA and BP Technology of SBs MASOB/AF/G-15 / Oracle Licensing Requirement Component 2: Institutional Oracle Database Enterprise Development, Business Single Stage - One IDA / V0820 Post Request for Bids Open - National 0.00 Canceled 2018-05-20 2018-05-25 2018-07-06 2018-08-05 2018-09-09 2019-03-08 Edition 11g R2 with 1 Strategy, and Information Envelope Year Support ( Number Of Technology of SBs Licenses 15) Component 2: Institutional MASOB/AF/G-16 / Microsoft Pending Development, Business Request for Single Stage - One Email Security Gateway for IDA / V0820 Post Limited 0.00 Implementati 2018-06-10 2018-08-05 2019-02-01 Strategy, and Information Quotations Envelope 500 Users (Qty2) on Technology of SBs Component 2: Institutional MASOB/AF/G-14 / Development, Business Request for Single Stage - One Procurement of Server Racks IDA / V0820 Post Limited 0.00 Canceled 2018-07-01 2018-08-26 2019-02-22 Strategy, and Information Quotations Envelope BMA and BP Technology of SBs Component 2: Institutional MASOB/AF/G-34 / Licenses Development, Business Request for Single Stage - One IDA / V0820 Post Limited 0.00 Canceled 2018-06-15 2018-08-10 2019-02-06 (Qty15) Strategy, and Information Quotations Envelope Technology of SBs MASOB/AF/G-35 / Licenses Qyt 15) for BP This is Component 2: Institutional Database Enterprise Edition Development, Business Request for Single Stage - One IDA / V0820 Post Limited 0.00 Canceled 2018-06-15 2018-08-10 2019-02-06 Option and mandatory for Strategy, and Information Quotations Envelope Diagnosing and resolving Technology of SBs critical database issues. Component 2: Institutional MASOB/AF/G-11 / Development, Business Open - Single Stage - One Procurement of Servers and IDA / V0820 Post Request for Bids 0.00 Canceled 2018-08-15 2018-08-20 2018-10-01 2018-10-31 2018-12-05 2019-06-03 Strategy, and Information International Envelope lenience for BMA Technology of SBs MASOB/AF/G-39 / licenses for PB plus Implementation & Warranty Oracle Database Enterprise Component 2: Institutional Edition ( #of Licenses 6)- Development, Business Open - Single Stage - One IDA / D2830 Post Request for Bids 740,463.00 Signed 2018-09-10 2018-09-15 2018-10-27 2018-11-26 2018-12-31 2019-06-29 Oracle Real Application Strategy, and Information International Envelope Cluster ( # Of Licenses 6)- Technology of SBs Oracle Diagnostic Pack -(# Licenses 6)-Oracle Tuning Pack (#Of Licenses 6) Page 3 Component 3: Project Pending MASOB/AF/G-40 / Two Request for Single Stage - One IDA / D2830 Implementation and Post Limited 0.00 Implementati 2018-11-15 2019-01-10 2019-07-09 Laptop Computers for PMT Quotations Envelope Monitoring on MASOB/AF/G-41 / NKB Component 2: Institutional FLEXCUBE Upgrading Development, Business IDA / D2830 Post Direct Selection Direct 0.00 Canceled 2018-12-22 2018-12-27 2019-01-31 2019-07-30 System Hardware and Strategy, and Information Software Technology of SBs MASOB/AF/G-28 / Blade Chassis hosting (1 out of 2 Component 2: Institutional Blade Chassis hosting 5 Development, Business Request for Single Stage - One Blade Servers will be place IDA / V0820 Post Limited 0.00 Canceled 2018-12-27 2019-02-21 2019-08-20 Strategy, and Information Quotations Envelope at Primary site and the Technology of SBs other 1 will be place at DR site) Component 2: Institutional MASOB/AF/G-21 / Core Development, Business Request for Single Stage - One Database Servers for IDA / D2830 Post Limited 0.00 Canceled 2018-12-31 2019-02-25 2019-08-24 Strategy, and Information Quotations Envelope Pashtani Bank Technology of SBs MASOB/AF/G-22 / Storage For Core Database -This Component 2: Institutional storage used in the RAC Development, Business Request for Single Stage - One configuration to host the IDA / D2830 Post Limited 0.00 Canceled 2018-12-31 2019-02-25 2019-08-24 Strategy, and Information Quotations Envelope Pashtany Bank Data, Technology of SBs Backup and other database critical files(Qty1) Component 2: Institutional MASOB/AF/G-29 / Power Development, Business Single Stage - One Edge M640 and Power Edge IDA / V0820 Post Request for Bids Open - National 0.00 Canceled 2019-01-06 2019-01-11 2019-02-22 2019-03-24 2019-04-28 2019-10-25 Strategy, and Information Envelope M 1000e Blade Chassis Technology of SBs Component 2: Institutional MASOB/AF/G-43 / Development, Business Single Stage - One Procurement of Server and IDA / D2830 Post Request for Bids Open - National 202,005.62 Signed 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 Strategy, and Information Envelope Licenses for BMA Technology of SBs Component 2: Institutional MASOB/AF/G-44 / Pending Development, Business Single Stage - One Procurement of Server Rack IDA / D2830 Post Request for Bids Open - National 0.00 Implementati 2019-03-28 2019-04-02 2019-05-14 2019-06-13 2019-07-18 2020-01-14 Strategy, and Information Envelope BMA and PB on Technology of SBs Component 2: Institutional MASOB/AF/G-45 / Core Development, Business Single Stage - One IDA / D2830 Post Request for Bids Open - National 151,936.33 Signed 2019-03-28 2019-04-02 2019-05-14 2019-06-13 2019-07-18 2020-01-14 Database for Pashtani Bank Strategy, and Information Envelope Technology of SBs MASOB/AF/G-46 / Storage For Core Database -This Component 2: Institutional storage used in the RAC Pending Development, Business Single Stage - One configuration to host the IDA / D2830 Post Request for Bids Open - National 0.00 Implementati 2019-03-28 2019-04-02 2019-05-14 2019-06-13 2019-07-18 2020-01-14 Strategy, and Information Envelope Pashtany Bank Data, on Technology of SBs Backup and other database critical files(Qty1) MASOB/AF/G-47 / Servers For Core Application Server -2 out of 3 Servers will be placed at Primary site to Component 2: Institutional host the Core Banking Pending Development, Business Single Stage - One Application in a Highly IDA / D2830 Post Request for Bids Open - National 0.00 Implementati 2019-03-28 2019-04-02 2019-05-14 2019-06-13 2019-07-18 2020-01-14 Strategy, and Information Envelope Available and Performance on Technology of SBs Optimized configuration. 1 Server will be placed to host the Core Banking Application at DR s Page 4 MASOB/AF/G-48 / Blade Chassis hosting (1 out of 2 Component 2: Institutional Blade Chassis hosting 5 Pending Development, Business Single Stage - One Blade Servers will be place IDA / D2830 Post Request for Bids Open - National 0.00 Implementati 2019-03-28 2019-04-02 2019-05-14 2019-06-13 2019-07-18 2020-01-14 Strategy, and Information Envelope at Primary site and the on Technology of SBs other 1 will be place at DR site) Component 2: Institutional Under MASOB/AF/G-49 / IT Development, Business Single Stage - One IDA / D2830 Post Request for Bids Open - National 0.00 Implementati 2019-03-28 2019-04-02 2019-05-14 2019-06-13 2019-07-18 2020-01-14 Security Equipment Strategy, and Information Envelope on Technology of SBs MASOB/AF/G-51 / NKB Component 2: Institutional FLEXCUBE Upgrading Development, Business IDA / D2830 Prior Direct Selection Direct 0.00 Canceled 2019-05-09 2019-05-14 2019-06-18 2019-12-15 System Hardware and Strategy, and Information Software Technology of SBs Component 2: Institutional MASOB/AF/G-52 / Power Under Development, Business Open - Single Stage - One Edge M640 and Power Edge IDA / D2830 Post Request for Bids 0.00 Implementati 2019-08-06 2019-08-11 2019-09-22 2019-10-22 2019-11-26 2020-05-24 Strategy, and Information International Envelope M 1000 e Blade Chassis on Technology of SBs Component 2: Institutional MASOB/AF/G- 51 / NKB Under Development, Business FLEXCUB UPgrading IDA / D2830 Prior Direct Selection Direct 0.00 Implementati 2019-11-24 2019-11-29 2020-01-03 2020-07-01 Strategy, and Information Software and Hardware on Technology of SBs MASOB/AF/G-57 / Component 2: Institutional Procurement of POS Pending Development, Business Open - Single Stage - One Machines Terminals Units, IDA / D2830 Post Request for Bids 0.00 Implementati 2020-01-30 2020-02-04 2020-03-17 2020-04-16 2020-05-21 2020-11-17 Strategy, and Information International Envelope Switches, and Integration for on Technology of SBs New Kabul Bank MASOB/AF/G-58 / Component 2: Institutional Pending Procurement of ATM Development, Business Single Stage - One IDA / D2830 Post Request for Bids Open - National 0.00 Implementati 2020-01-23 2020-01-28 2020-03-10 2020-04-09 2020-05-14 2020-11-10 Machine for New Kabul Strategy, and Information Envelope on Bank Technology of SBs NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MASOB/AF/G2 / Component 1: Improving Institutional Development MOF’s Ownership Role and Quality And Cost- Open - Pending Consultants for Corporate IDA / V0820 Prior 0.00 2019-01-15 2019-02-05 2019-03-21 2019-04-18 2019-05-18 2019-06-22 2019-07-27 2020-07-26 the Corporate Governance of Based Selection International Implementation Governance Reforms (CG, SBs Audits, Policies etc) MASOB/AF/G-3 / Component 2: Institutional Consultancy Services for Development, Business Quality And Cost- Open - Pending Strategic IT Restructuring of IDA / V0820 Prior 0.00 2019-01-20 2019-02-10 2019-03-26 2019-04-23 2019-05-23 2019-06-27 2019-08-01 2020-07-31 Strategy, and Information Based Selection International Implementation Banking Sector (MoF, DABS, Technology of SBs SB) Page 5 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Improving Individual MASOB/AF/G1 / Hiring of MOF’s Ownership Role and IDA / V0820 Post Consultant Open 0.00 Canceled 2018-05-29 2018-07-17 2018-08-07 2018-09-11 2019-03-10 Legal Advisor for MoF the Corporate Governance of Selection SBs Component 1: Improving Individual MASOB/AF/G-4 / Resident MOF’s Ownership Role and IDA / V0820 Prior Consultant Open 0.00 Under Review 2018-05-20 2018-07-08 2018-07-29 2018-09-02 2019-03-01 Banking Advisor BMA the Corporate Governance of Selection SBs Component 2: Institutional MASOB/AF/G-7 / Resident Individual Development, Business Pending advisor (Banking, LT) IDA / V0820 Prior Consultant Open 0.00 2018-05-20 2018-07-08 2018-07-29 2018-09-02 2019-03-01 Strategy, and Information Implementation International Selection Technology of SBs Component 2: Institutional Individual MASOB/AF/G-5 / Resident Development, Business IDA / V0820 Post Consultant Open 8,149.00 Signed 2018-05-25 2018-07-13 2018-08-03 2018-09-07 2019-03-06 Banking Advisor NKB Strategy, and Information Selection Technology of SBs Component 2: Institutional Individual MASOB/AFG-6 / Resident Development, Business IDA / V0820 Post Consultant Open 7,349.00 Signed 2018-06-12 2018-07-31 2018-08-21 2018-09-25 2019-03-24 Banking Advisor PB Strategy, and Information Selection Technology of SBs MASOB/AF/G-37 / Corporate Governance Component 3: Project Under Training for 3 SBs IDA / V0820 Implementation and Post Direct Selection Direct 0.00 2018-05-22 2018-06-01 2018-08-05 2019-02-01 Implementation supervisory board and MoF Monitoring project management team Component 1: Improving MASOB/AF/G-38 / Individual MOF’s Ownership Role and Corporate Governance IDA / D2830 Post Consultant Open 0.00 Canceled 2018-07-15 2018-09-02 2018-09-23 2018-10-28 2019-04-26 the Corporate Governance of Consultant Selection SBs Component 1: Improving Individual MASOB/AF/G-50 / MOF’s Ownership Role and Pending IDA / D2830 Post Consultant Open 0.00 2019-04-21 2019-06-09 2019-06-30 2019-08-04 2020-01-31 International Banking Expert the Corporate Governance of Implementation Selection SBs Component 3: Project MASOB/AF/G-53 / PACT IDA / D2830 Implementation and Post Direct Selection Direct 0.00 Canceled 2019-09-18 2019-09-28 2019-12-02 2020-05-30 Advisor Monitoring Component 3: Project MASOB/AF/G-54 / Chief IDA / D2830 Implementation and Post Direct Selection Direct 30,577.57 Signed 2019-09-22 2019-10-02 2019-12-06 2020-06-03 Technical Specialist to PACT Monitoring Component 1: Improving MASOB/AF/G-56 / Individual MOF’s Ownership Role and Under International Resident IDA / D2830 Post Consultant Open 0.00 2019-11-04 2019-12-23 2020-01-13 2020-02-17 2020-08-15 the Corporate Governance of Implementation Banking Advisor for BMA Selection SBs Page 6