Procurement Plan Additional Financing for the Water Sector Capacity Building and Advisory Services Project (WCAP) I. General 1. Bank’s approval Date of the procurement Plan: January 6,2107 2. Date of General Procurement Notice: Aug 24, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year June 2016 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditure Contract Value Procurement Contracts Subject to Category (Threshold) Method Prior Review US $ US$ thousands 1. Goods Works & >600,000 ICB All Non-consulting <600,000 NCB First Contract and all subsequent contracts Services estimated to cost > 200,000 <100,000 Shopping First Contract Regardless of value Direct Contracting All 2. Consulting All TOR and Training Programs to be prior Services (Firms) reviewed by Association’s TTL regardless of value and review threshold >300,000 QCBS/QBS /FBS/LCS First contract ( remaining contracts > $ 500,000 shall be mandatorily post reviewed <300,000 CQS, First contract  25,000 Single Source Selection All First Contract only. Subsequent contracts shall have a technical sign-off of justification only on condition: (i) if it was provided in approved Procurement Plan ≤25,000 Single Source Selection and (ii) not representing a slice of an otherwise larger project and; shall be mandatorily post reviewed regardless of the sample of selected contracts Individual > 100,000 Comparison of 3 CVs First contract Consultants < 100,000 Comparison of 3 CVs First contract  10,000 Single Source Selection, Contracts All. for: procurement of Project Coordinator, Procurement/FM Specialists, Procurement Agent and Legal Expert (as applicable) All TOR to be technically reviewed by the Association July 9, 2010 First Contract only. Subsequent contracts shall have a technical sign-off of justification only on condition: (i) if it was provided in approved Procurement Plan ≤10,000 Single Source Selection and (ii) not representing a slice of an otherwise larger project and; shall be mandatorily post reviewed regardless of the sample of selected contracts ICB = International Competitive Bidding; NCB = National Competitive Bidding; QCBS=Quality- and Cost-Based Selection; CQS = Selection Based on Consultants' Qualifications. 2. Prequalification. Bidders for _Not applicable_ [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 July 9, 2010 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : Water Sector Capacity Building & Advisory Services Project (WCAP) PLAN General Information Country: Pakistan Banks Approval Date of the Original Procurement Plan: 2017-01-30 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-01-30 Project ID: P110099 GPN Date: Project Name: Water Sector Capacity Building & Advisory Services Project (WCAP) Loan / Credit No: IDA / 57600 Executing Agency(ies): WATER SECTOR CAPACITY BUILDING and ADVISORY SERVICES PROJECT WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-WCAP AF-5889-CW-RFB / Minor works for Up gradation & Component A: Capacity building Rehabilitation & for installation of of and support to the federal Single Stage - One Pending IDA / 57600 Prior Request for Bids Open - National 900,000.00 0.00 2017-03-02 2017-03-07 2017-04-18 2017-05-18 2017-06-22 2017-12-19 Soil Mechanics and Hydraulics institutions in water resources Envelope Implementation Laboratory Hyderabad (Section- planning and management. C) PK-WCAP AF-5892-CW-RFQ / Minor Work associated with Component A: Capacity building Installation & Upgradation of of and support to the federal Request for Single Stage - One Pending Existing Rooms for Survey/ IDA / 57600 Post Open - National 160,000.00 0.00 2017-03-06 2017-05-01 2017-10-28 institutions in water resources Quotations Envelope Implementation Computer and Soil Testing Labs planning and management. Irrigation Department in Balouchistan. PK-WCAP AF-5893-CW-RFQ / Component A: Capacity building Minor Work associated in of and support to the federal Request for Single Stage - One Pending IDA / 57600 Post Open - National 140,000.00 0.00 2017-03-06 2017-05-01 2017-10-28 Upgradation of Lahore Hydraulic institutions in water resources Quotations Envelope Implementation Laborite Gujranwala Punjab. planning and management. GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-WCAP AF-5866-GO-RFQ / Purchase of Lot-I hardwares ( Laptops 10 Desktop 10 ) , Component C: Project softwares ( Windows ,antivirus Request for Single Stage - One Pending IDA / 57600 management and additional Post Open - National 73,000.00 0.00 2017-01-30 2017-03-27 2017-09-23 Internet Acessories , networking Quotations Envelope Implementation studies equipment for establishment of Data Center at FFC Islamabad Component = C PK-WCAP AF-5868-GO-RFQ / Purchase of LOT-II pheripheral Goods ,Office Equipment (Scanners 2, UPS, Binding Component C: Project Machine, Paper shreders,) etc. Request for Single Stage - One Pending IDA / 57600 management and additional Post Open - National 63,000.00 0.00 2017-01-30 2017-03-27 2017-09-23 ,Furniture (Colour Printer 2, Laser Quotations Envelope Implementation studies Printer 10, Mulipurpose Colour Photocopy Machine 2) for establishment of Data Center at FFC Islamabad. PK-WCAP AF-5870-GO-RFQ / PMPIU Office IT equipment ,Installation of Audio Conference, IT Equipment, Accounting Component C: Project Request for Single Stage - One Pending Management Software (1.06 IDA / 57600 management and additional Post Open - National 83,330.00 0.00 2017-04-08 2017-06-03 2017-11-30 Quotations Envelope Implementation million ) and Accessories, and studies Installation of Security System and Equipment (Security Camras, Digital Camras, etc) PK-WCAP AF-5872-GO-RFQ / Purchase & Installation of Office Equipment (AC, LED TV, Water Component C: Project Boilers, Room Heater, White Request for Single Stage - One Pending IDA / 57600 management and additional Post Open - National 88,180.00 0.00 2017-05-10 2017-07-05 2018-01-01 Board, Refrigerators, Water Quotations Envelope Implementation studies Dispensers, Electric Geysers, Purchase of Office Furniture Sets along with Accessories. PK-WCAP AF-5877-GO-RFB / Procurement for Supply and Installation of LOT-I Modern Testing Lab Equipment Basic Component A: Capacity building Field Soil Testing Equipment of and support to the federal Single Stage - One Pending IDA / 57600 Prior Request for Bids Open - National 1,310,000.00 0.00 2017-01-25 2017-01-30 2017-03-13 2017-04-12 2017-05-17 2017-11-13 (Package-A), Lab Equipment for institutions in water resources Envelope Implementation Modern Computerized Survey planning and management. Lab Along Survey Training of Rs. 3.2 Million (Package-B) LOT-II Office Equipment PK-WCAP AF-5878-GO-RFB / Procurement for Providing & Component A: Capacity building fixing instruments for up of and support to the federal Single Stage - One Pending gradation model testing area @ IDA / 57600 Post Request for Bids Open - National 590,000.00 0.00 2017-01-25 2017-01-30 2017-03-13 2017-04-12 2017-05-17 2017-11-13 institutions in water resources Envelope Implementation Hyderabad Sindh Office / IT planning and management. Equipment LOT-I, Lab Equipment LOT-II PK-WCAP AF-5881-GO-RFQ / Purchase of Heavy Duty Boat for Component B: Improvement in Request for Single Stage - One Pending Flow measurement under flood IDA / 57600 water resources management Prior Open - National 40,816.00 0.00 2017-01-30 2017-03-27 2017-09-23 Quotations Envelope Implementation Telemetric netwok for H&R Dir. and development Component-B1 PK-WCAP AF-5883-GO-RFB / CMTL Up-gradtion of Cement, Component B: Improvement in Single Stage - One Pending Soil, Steel Sections (Lot wise: IDA / 57600 water resources management Post Request for Bids Open - International 900,000.00 0.00 2017-01-25 2017-01-30 2017-03-13 2017-04-12 2017-05-17 2017-11-13 Envelope Implementation total lots 03) and CMTL Up- and development gradtion, Component-B1 Page 1 PK-WCAP AF-5871-GO-RFQ / Purchase of Field Vehicle (4x4) Component C: Project = 02 RS 10.00 Million and Request for Single Stage - One Pending IDA / 57600 management and additional Prior Open - National 220,000.00 0.00 2017-05-09 2017-06-09 2017-12-06 Purchase of Operational Vehicle Quotations Envelope Implementation studies 1300 CC (Locally Manufactured) = 06 Rs 12.00 Million PK-WCAP AF-5876-GO-RFB / Procurement for supply and Installation of Hardware, software and Equipment fro Modern Component A: Capacity building Computerized Lab Equipment for of and support to the federal Single Stage - One Pending IDA / 57600 Post Request for Bids Open - National 1,420,000.00 0.00 2017-02-08 2017-02-13 2017-03-15 2017-03-30 2017-04-09 2017-10-06 Drawing & Numerical Modeling at institutions in water resources Envelope Implementation Hydraulic Research Station planning and management. (HRS) Nandipur Gujranwala (LOT- I) Hydraulics Engineering Instruments/Equipm PK-WCAP AF-5882-GO-RFQ / Purchase of field Vehicles : 03 Component B: Improvement in Nos. Double Cabin 2499 CC Request for Single Stage - One Pending IDA / 57600 water resources management Prior Open - National 153,000.00 0.00 2017-01-30 2017-03-04 2017-08-31 LOT-I, : 01 No. Jeep, 1299 CC , Quotations Envelope Implementation and development 01 Nos Car , 1000 CC or Eq. LOT-II for WAPDA PK-WCAP AF-5884-GO-RFQ / Purchase of Office Equipment Component A: Capacity building (Laptop, Desktop with Printer) of and support to the federal Request for Single Stage - One Pending IDA / 57600 Post Open - National 15,900.00 0.00 2017-02-12 2017-04-09 2017-10-06 Package -A Furniture & Fixture institutions in water resources Quotations Envelope Implementation (Package-B) Component = A2 planning and management. (Activity:) PK-WCAP AF-5887-GO-RFQ / Purchase of Office Equipement Component A: Capacity building (Laptop, Desktop with Printer) of and support to the federal Request for Single Stage - One Pending IDA / 57600 Post Open - National 15,900.00 0.00 2017-01-30 2017-03-27 2017-09-23 Package -A Furniture & Fixture institutions in water resources Quotations Envelope Implementation (Package-B) Component = A2 planning and management. (Activity:) IRSA PK-WCAP AF-36396-GO-RFB / Upgradation of Data Center at Component C: Project FFC Lot-1 ICT Equipment and Single Stage - One Pending IDA / 57600 management and additional Post Request for Bids Open - National 170,000.00 0.00 2017-11-13 2017-11-18 2017-12-30 2018-01-29 2018-03-05 2018-09-01 Office Equipment , Lot-II Envelope Implementation studies Equipment for Capacity Building (New Activity under Phase-II) PK-WCAP AF-36397-GO-RFB / Component C: Project Establishment of New Hydraulics Single Stage - One Pending IDA / 57600 management and additional Post Request for Bids Open - National 455,650.00 0.00 2018-01-31 2018-02-05 2018-03-19 2018-04-18 2018-05-23 2018-11-19 and Material Testing Lab , Envelope Implementation studies Peshawar, KP Component A: Capacity building PK-WCAP AF-36415-GO-RFB / of and support to the federal Single Stage - Two Pending Purchase of Telemetry System IDA / 57600 Post Request for Bids Open - International 3,500,000.00 0.00 2018-02-17 2018-02-22 2018-04-05 2018-06-18 2018-07-23 2019-01-19 institutions in water resources Envelope Implementation Equipment for IRSA planning and management. Component A: Capacity building PK-WCAP AF-36417-GO-RFQ / of and support to the federal Request for Single Stage - One Pending Purchase of Office Furniture and IDA / 57600 Post Open - National 10,000.00 0.00 2017-11-20 2018-01-15 2018-07-14 institutions in water resources Quotations Envelope Implementation Fixtures for IRSA (A2) planning and management. Component A: Capacity building PK-WCAP AF-36418-GO-RFQ / of and support to the federal Request for Single Stage - One Pending Purchase of 4x4 Field Vehicle IDA / 57600 Prior Open - National 60,000.00 0.00 2017-12-20 2018-02-14 2018-08-13 institutions in water resources Quotations Envelope Implementation Component = A2 (IRSA) planning and management. PK-WCAP AF-36419-GO-RFB / Computer Hardware & Software Component B: Improvement in for H&R Directorate, Flow Single Stage - One Pending IDA / 57600 water resources management Post Request for Bids Open - National 200,000.00 0.00 2017-11-30 2017-12-05 2018-01-16 2018-02-15 2018-03-22 2018-09-18 Forecasting Study of Kabul River, Envelope Implementation and development C&M Office and other related offices (Need basis WAPDA) PK-WCAP AF-36420-GO-RFB / Component B: Improvement in Single Stage - One Pending Strenthening of Surface Water IDA / 57600 water resources management Prior Request for Bids Open - International 1,500,000.00 0.00 2018-07-23 2018-07-28 2018-09-08 2018-10-08 2018-11-12 2019-05-11 Envelope Implementation Hydrology WAPDA (BI) and development PK-WCAP AF-5879-GO-RFB / Procurement of Supply, Installation and Commissioning Component B: Improvement in Single Stage - One Pending of Automatic Weather Station IDA / 57600 water resources management Prior Request for Bids Open - International 2,008,886.00 0.00 2017-12-19 2017-12-28 2018-02-11 2018-03-14 2018-04-03 2018-09-30 Envelope Implementation (AWS) and Integration of and development Meteorological Sensors with existing FFT Network NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-WCAP AF-5837-CS-CQS / Procurement of Consultancy Services for the Assessment /TPV on technoligical Component A: Capacity building Moderinezed Upgradation of Consultant of and support to the federal Pending Institutes (Punjab ,SINDH, IDA / 57600 Post Qualification Open - National 300,000.00 0.00 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-01-14 institutions in water resources Implementation BALUCHISTAN) relevent to their Selection planning and management. Upgradation in Nandipur Gujranwala in Punjab alongwith technical Upgradation & Strengthe Page 2 PK-WCAP AF-5859-CS-QCBS / Preparation of comprehensive Component C: Project Integrated Master Plan for the Quality And Cost- Pending IDA / 57600 management and additional Post Open - International 1,000,000.00 0.00 2017-03-20 2017-03-21 2017-04-15 2017-05-15 2017-05-30 2017-06-12 2017-06-22 2018-06-22 development and utilization of Based Selection Implementation studies power and energy resources in Upper Indus Basin. PK-WCAP AF-5861-CS-QCBS / "Automation of Flow Component A: Capacity building Measurement and Information of and support to the federal Quality And Cost- Pending System for the Indus Basin IDA / 57600 Post Open - International 1,000,000.00 0.00 2017-02-08 2017-02-22 2017-03-14 2017-04-13 2017-04-28 2017-05-06 2017-05-19 2018-05-19 institutions in water resources Based Selection Implementation Irrigation System (IBIS) using planning and management. Telemetry System and Modern Techniques" PK-WCAP AF-5862-CS-CQS / Discharge measurement at key Component A: Capacity building locations of the Indus Basin Consultant of and support to the federal Pending Irrigation System (IBIS) to IDA / 57600 Post Qualification Open - International 500,000.00 0.00 2017-02-08 2017-02-22 2017-04-11 2017-04-26 2017-05-06 2017-11-02 institutions in water resources Implementation develop standardized water flow Selection planning and management. measurement system of the IBIS (Phase-II) PK-WCAP AF-5864-CS-QCBS / Procurement of Consultancy Component B: Improvement in Services for Flow Forecasting of Quality And Cost- Pending IDA / 57600 water resources management Post Open - International 700,000.00 0.00 2017-02-08 2017-02-22 2017-03-14 2017-04-13 2017-04-28 2017-05-18 2017-05-28 2018-05-28 Chenab and Kabul River Basins Based Selection Implementation and development using RS/GIS Technique and related hydrological Models PK-WCAP AF-5833-CS-QCBS / Preparation of Comprehensive Component C: Project Quality And Cost- Pending Inventory of Water Resources of IDA / 57600 management and additional Prior Open - International 2,000,000.00 0.00 2017-03-01 2017-03-15 2017-04-09 2017-05-09 2017-05-24 2017-06-08 2017-06-16 2018-06-16 Based Selection Implementation Pakistan and Updating the Indus studies Drainage Basin Atlas PK-WCAP AF-5840-CS-QCBS / "Up-gradation of master plan of flood management of hill torrents of Pakistan and Feasibility Component C: Project Quality And Cost- Pending studies for check/recharge dams IDA / 57600 management and additional Prior Open - International 1,800,000.00 0.00 2017-03-15 2017-03-29 2017-04-18 2017-05-18 2017-06-02 2017-06-17 2017-06-25 2018-06-25 Based Selection Implementation in Sulaiman Range, and studies Feasibility study of Marri Bugti Hill Torrent " PK-WCAP AF-5863-CS-CQS / "Determination of Losses & Component A: Capacity building Gains obetween Several reaches Consultant of and support to the federal Pending in Indus & Jhelum Chenab zones IDA / 57600 Post Qualification Open - National 500,000.00 0.00 2017-02-08 2017-02-22 2017-04-08 2017-04-23 2017-05-08 2017-11-04 institutions in water resources Implementation (Phase-II) Selection planning and management. " PK-WCAP AF-36399-CS-CQS / Component C: Project Consultant Preparation of Implementation Pending IDA / 57600 management and additional Post Qualification Open - International 50,000.00 0.00 2018-06-30 2018-07-21 2018-09-03 2018-10-03 2018-11-07 2019-05-06 Framework for National Water Implementation studies Selection Policy INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-WCAP AF-5813-CS-INDV / Microsoft Consultant for Data Component C: Project Individual Consultant Pending Centre Configuration of IDA / 57600 management and additional Post Open 5,000.00 0.00 2017-01-24 2017-03-14 2017-04-04 2017-05-09 2017-11-05 Selection Implementation applications between IRSA & studies FFC PK-WCAP AF-5808-CS-INDV / Hiring of Short term Consultants Component C: Project Individual Consultant Pending for ESMP TPV on minor IDA / 57600 management and additional Post Open 5,000.00 0.00 2017-10-20 2017-11-18 2017-11-23 2017-12-08 2018-04-07 Selection Implementation associated Civil Work for studies Provinces (Sindh,Baluchistan,) Component A: Capacity building PK-WCAP AF-5829-CS-INDV / of and support to the federal Individual Consultant Pending IDA / 57600 Post Open 36,000.00 0.00 2017-05-15 2017-06-10 2017-07-01 2017-08-05 2018-02-01 Junior Engineer = 01 IRSA institutions in water resources Selection Implementation planning and management. Component A: Capacity building PK-WCAP AF-5828-CS-INDV / of and support to the federal Individual Consultant Pending IDA / 57600 Post Open 72,000.00 0.00 2017-02-16 2017-03-22 2017-03-27 2017-04-06 2017-10-03 Project Coordinator - IRSA institutions in water resources Selection Implementation planning and management. PK-WCAP AF-21116-CS-INDV / Component A: Capacity building Procurement of Services of of and support to the federal Individual Consultant Pending IDA / 57600 Post Open 48,900.00 0.00 2017-07-20 2017-08-17 2017-08-27 2017-09-18 2021-06-30 Program Officer (Information institutions in water resources Selection Implementation Technology) planning and management. PK-WCAP AF-21132-CS-INDV / Component A: Capacity building Procurement of Services of of and support to the federal Individual Consultant Pending IDA / 57600 Post Open 48,900.00 0.00 2017-07-20 2017-08-17 2017-08-27 2017-09-18 2021-06-30 Program Officer institutions in water resources Selection Implementation (Liaison/Coordination) planning and management. PK-WCAP AF-21134-CS-INDV / Component C: Project Individual Consultant Pending Procurement of Services of SAP IDA / 57600 management and additional Post Open 65,300.00 0.00 2017-07-20 2017-08-17 2017-08-27 2017-09-18 2021-06-30 Selection Implementation Analyst studies PK-WCAP AF-36403-CS-CDS / Support Services for Operation of Component C: Project Pending Flood Situation Monitoring and IDA / 57600 management and additional Prior Direct Selection Direct 140,000.00 0.00 2017-11-13 2017-11-23 2018-01-27 2018-07-26 Implementation Reporting System (FSMRS) at studies FFC Page 3 PK-WCAP AF-36408-CS-INDV / Hiring of short term consultant (water sector specialist) for preparation of ToRs relating to. 1. Component C: Project Upgradaton of Hill Torrents Individual Consultant Pending IDA / 57600 management and additional Post Open 15,000.00 0.00 2017-11-13 2018-01-01 2018-01-22 2018-02-26 2018-08-25 Manemet Study. 2 Preparation of Selection Implementation studies Impelentation Framework of National Water Policy. 3. Preparation of Water Tariff Framework PK-WCAP AF-36412-CS-INDV / Component C: Project Hiring the services of Individual Consultant Pending IDA / 57600 management and additional Post Open 5,000.00 0.00 2017-12-05 2018-01-23 2018-02-13 2018-03-20 2018-09-16 Financial/Businees Specialist Selection Implementation studies (AI) PMPIU PK-WCAP AF-5820-CS-INDV / Component B: Improvement in Hiring of Hydrologist Expert for Individual Consultant IDA / 57600 water resources management Post Open 16,020.00 0.00 Canceled 2017-05-01 2017-05-27 2017-06-17 2017-07-22 2018-01-18 WAPDA Flow Forecasting Study Selection and development WAPDA PK-WCAP AF-5824-CS-INDV / Component A: Capacity building Hiring of Expert (RS/GIS) for of and support to the federal Individual Consultant IDA / 57600 Post Open 14,700.00 0.00 Canceled 2017-05-01 2017-05-30 2017-06-04 2017-06-14 2017-12-11 WAPDA Flow Forecasting Study institutions in water resources Selection = WAPDA planning and management. PK-WCAP AF-5817-CS-INDV / Component B: Improvement in Hiring of Processing Engineer Individual Consultant IDA / 57600 water resources management Post Open 16,020.00 0.00 Canceled 2017-05-01 2017-05-21 2017-05-26 2017-06-05 2017-12-02 (RS/GIS) for WAPDA Flow Selection and development Forecasting Study = 01 Component A: Capacity building PK-WCAP AF-22484-CS-INDV / of and support to the federal Individual Consultant IDA / 57600 Prior Limited 36,000.00 0.00 Canceled 2017-07-28 2017-08-02 2017-08-07 2017-08-11 2018-08-11 Hiring of Procurement Specialist institutions in water resources Selection planning and management. Component C: Project PK-WCAP AF-46138-CS-INDV / Individual Consultant Pending IDA / 57600 management and additional Prior Open 38,000.00 0.00 2018-02-12 2018-04-02 2018-04-23 2018-05-28 2019-05-28 Procurement Specialist Selection Implementation studies Component A: Capacity building PK-WCAP AF-22480-CS-INDV / of and support to the federal Individual Consultant Pending Hiring of Director Technical for IDA / 57600 Post Limited 36,000.00 0.00 2018-01-29 2018-02-03 2018-02-08 2018-02-12 2019-02-12 institutions in water resources Selection Implementation PMPIU planning and management. Component A: Capacity building PK-WCAP AF-22488-CS-INDV / of and support to the federal Individual Consultant Pending Hiring the services of New IDA / 57600 Post Limited 36,000.00 0.00 2018-01-29 2018-02-03 2018-02-08 2018-02-20 2019-02-20 institutions in water resources Selection Implementation Principal River Engineer planning and management. Page 4