HP State Roads Transform Procurement Plan for first Submitted by HPR Government of Himac HP STATE ROADS TRANSFORMATION PROGRAM PROCUREMENT PLAN FOR FIRST EIGHTEEN MONTHS 1. Procurement for the project will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers, July 2016, Revised November 2017 and August 2018 and applicable to Investment Project Financing (IPF). The project will be subject to the World Bank’s Anticorruption Guidelines, dated October 15, 2006, as revised in January 2011 and July 2016. 2. A Project Procurement Strategy for Development (PPSD) has been prepared for the project. Extensive market analysis has been carried out for different packages of procurement. Decisions on packages and lots are made to ensure adequate participation of bidders. Consultancy contracts are framed based on market research and packaging decided in terms of scope of services and period. Based on the needs assessment, the project has decided to use Government e Marketplace [GeM] for procurement of Goods up to US$ 100,000 and as mentioned under National Procurement Procedures at para 9 below. Based on risk and market analysis, the procurement plan has been prepared to set out the selection methods to be followed by the Borrower during project implementation in the procurement of Works, Goods, IT system procurement, non-consulting and consulting services financed by the World Bank. 3. The table below describes various procurement methods to be used for activities financed by the loan. The thresholds (Table 11) indicated in apply to the initial 18-months of implementation period and are based on the procurement performance of the project; these thresholds may be subsequently modified. Table 1: Procurement Thresholds Procurement Approaches and Methods Thresholds (US$ equivalent) Open international (Works) > 40 million Open national (Works) > 100,000 and up to 40 million Open international (goods, IT system, and non-consulting > 3 million services) Open national (goods, IT system, and non-consulting services) > 100,000 and up to 3 million National request for quotation (goods, IT system, works & non- Up to 100,000 consulting services) Direct selection No threshold; For Works; Goods/non-consulting services/IT system: According to paragraphs 6.8–6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Shortlist of national consultants Up to 800,000 4. Procurement prior-review thresholds. The World Bank will prior review the following contracts: October 22, 2018 1 HP STATE ROADS TRANSFORMATION PROGRAM PROCUREMENT PLAN FOR FIRST EIGHTEEN MONTHS (a) Works (including turnkey, supply and installation of plant and equipment and PPP) : All contracts more than US$ 40 million equivalent (b) Goods and IT system: All contracts more than US$2 million equivalent (c) Non-consulting services: All contracts more than US$2 million equivalent (d) Consultants: All contracts >US$1 million equivalent for firms and >US$300,000 equivalent for individuals 5. The above thresholds are for the initial 18-month implementation period; based on the procurement performance of the project, these thresholds may be subsequently modified. Even for large-value post review cases, the inputs of the World Bank on technical specifications will be obtained by the project. Irrespective of the thresholds, ToRs shall be prior reviewed by Bank. The prior review thresholds will also be indicated in the Procurement Plan. The Procurement Plan will be subsequently updated annually (or at any other time if required) and will reflect any change in the prior review thresholds. The details of National Procurement Procedures are outlined in the Procurement Plan. 6. Prior review contract. In the case of contracts subject to prior review, the Implementing Agencies will seek the World Bank’s no objection before granting/agreeing to: (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of Works, goods, IT system; non- consulting services, or consulting services and other significant changes to the terms and conditions of the contract; (c) any variation order or amendment (except in cases of extreme urgency) that, singly or combined with all variation orders or amendments previously issued, increases the original contract amount by more than 15 percent; and (d) the proposed termination of the contract. Complaints received in all prior review cases shall be sent to Bank for review and the response to the complaint in such cases, shall be cleared with the Bank. Complaints with allegations of fraud and corruption, shall be shared with Bank, irrespective of the thresholds. 7. Disclosure of procurement information. The following documents shall be disclosed on the project/state websites: (a) Procurement Plan and its updates; (b) an invitation for bids for procurement of Works, Goods, IT system procurement and non-consulting services; (c) request for expression of interest for selection/hiring of consulting services; (d) contract awards of Works, Goods, IT system procurement and non- consulting services procured following international and national procedures; (e) a list of contracts/purchase orders placed following RFQ (Request for Quotation) procedures on a quarterly basis; (f) a list of contracts following direct contracting (DC) on a quarterly basis; (g) an annual financial and physical progress report of all contracts; and (h) an action taken report on the complaints received on a quarterly basis. 8. The following details shall be sent to the World Bank for publishing on the United Nations Development Business and the World Bank external website: (a) Specific Procurement Notice (i.e. invitation for bids) for procurement of Works, Goods , IT system procurement and non-consulting services using open international procedures; (b) Requests for Expression of Interests above USD 800,000; (c) contract award details of all procurement of Works, Goods, IT system procurement and non-consulting services using open international procedure; and(d) a list of contracts/purchase orders placed following DC procedures on a quarterly basis. Further, the implementing agency will also publish on their websites any information required under the provisions of ‘suo moto’ disclosure as specified by the Right to Information Act. October 22, 2018 2 HP STATE ROADS TRANSFORMATION PROGRAM PROCUREMENT PLAN FOR FIRST EIGHTEEN MONTHS 9. National Procurement Procedures : National competition for the procurement of Works, Goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: (a) Only the model bidding documents agreed with the World Bank (and as amended from time to time) shall be used for bidding. (b) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely-used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily, among others, giving the website/electronic portal details from which the details of the invitation to bid can be downloaded) at least 30 days before the deadline for the submission of bids. (c) No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises, or enterprises from any given state. (d) Extension of bid validity shall not be allowed with reference to contracts subject to the World Bank prior review without the prior concurrence of the World Bank (i) for the first request for extension if it is longer than four weeks and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the World Bank only in cases of force majeure and circumstances beyond the control of the purchaser/employer). (e) Re-bidding shall not be carried out with reference to contracts subject to the World Bank prior review without the prior concurrence of the World Bank. (f) The system of rejecting bids outside a predetermined margin or ‘bracket’ of prices shall not be used in the project. (g) To improve efficiency and transparency of small value purchases in World Bank financed projects, the Bank has agreed to allow use of GeM as follows: Use of GeM will be allowed in lieu of RFQ as per following details: • up to INR 50,000 in catalog mode (viz. any available item could be selected by IA without further competition), provided selected Item/Supplier meeting the requisite quality, specification and delivery period. • up to INR 3 Million from the Supplier having lowest price amongst at least three Suppliers meeting the requisite quality, specification and delivery period. The tools for online bidding and online reverse auction available on GeM may be used by the Purchaser. October 22, 2018 3 HP STATE ROADS TRANSFORMATION PROGRAM PROCUREMENT PLAN FOR FIRST EIGHTEEN MONTHS • up to INR equivalent of US$ 100,000 from the Supplier having lowest price and meeting the requisite quality, specification and delivery period after mandatorily obtaining bids from at least three Suppliers, using online bidding or reverse auction tool provided on GeM. (h) No negotiations are conducted even with the lowest evaluated responsive bidders. (i) Two or three envelope system will not be used except when using e-procurement system assessed and agreed by the Bank 10. Domestic preference. The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. For details of Goods, Works, Services and Non-Consulting Services to be procured in the first year, please refer activities cleared in STEP – procurement plan. October 22, 2018 4 PROCUREMENT India : Himachal Pradesh State Roads Transformation Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2019-10-29 2020-02-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163328 GPN Date: Project Name: Himachal Pradesh State Roads Transformation Project Loan / Credit No: IBRD / P4900 Executing Agency(ies): HIMACHAL PRADESH ROAD AND OTHER INFRASTRUCTURE CORPORATION WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-HPRIDC -144245-CW- Improving select roads Under RFB / Upgradation of Baddi stimulating HP’s Single Stage - Two IBRD / P4900 Prior Request for Bids Open - National 10,500,000.00 0.00 Implementati 2019-12-02 2019-12-17 2020-01-28 2020-04-23 2020-05-28 2022-11-27 - Sai road from Km 11/600 horticultural and overall Envelope on to Km 26/400 (14.8 km) economic growth IN-HPRIDC -144270-CW- RFB / Upgradation of Improving select roads Under Raghunathpura Mandi- stimulating HP’s Single Stage - Two IBRD / P4900 Post Request for Bids Open - National 1,500,000.00 0.00 Implementati 2019-12-02 2019-12-17 2020-01-28 2020-04-23 2020-05-28 2022-05-28 Harpura- Bharari road from horticultural and overall Envelope on km 0/000 to km 2/700 (2.7 economic growth km) IN-HPRIDC -144275-CW- RFB / Upgradation of Improving select roads Pending Barrotiwal - Baddi road stimulating HP’s Single Stage - Two IBRD / P4900 Prior Request for Bids Open - National 11,500,000.00 0.00 Implementati 2019-12-12 2019-12-27 2020-02-07 2020-05-03 2020-06-07 2022-12-07 from Km 0/000 to Km horticultural and overall Envelope on 11/600 economic growth (11.6 km) IN-HPRIDC -144274-CW- Improving select roads RFB / Upgradation of Mandi Under stimulating HP’s Single Stage - Two Rewalsar Kalkhar road from IBRD / P4900 Prior Request for Bids Open - National 13,500,000.00 0.00 Implementati 2019-12-12 2019-12-27 2020-02-07 2020-05-03 2020-06-07 2022-12-07 horticultural and overall Envelope Km 12/000 to Km 29/000 on economic growth (16.7 km) IN-HPRIDC -144268-CW- Improving select roads RFB / Upgradation of Under stimulating HP’s Single Stage - Two Dadhol - Ladrour road from IBRD / P4900 Prior Request for Bids Open - National 11,000,000.00 0.00 Implementati 2019-12-02 2019-12-17 2020-01-28 2020-04-23 2020-05-28 2022-11-27 horticultural and overall Envelope km 0/00 to km 13/500 (13.5 on economic growth km ) IN-HPRIDC -144266-CW- RFB / Upgradation of Baddi Improving select roads Under - Sai - stimulating HP’s Single Stage - Two IBRD / P4900 Prior Request for Bids Open - National 13,000,000.00 0.00 Implementati 2019-12-02 2019-12-17 2020-01-28 2020-04-23 2020-05-28 2022-11-27 Ramshahar road from Km horticultural and overall Envelope on 26/400 to Km 44/700 (18.3 economic growth km) IN-HPRIDC -144272-CW- Improving select roads RFB / Upgradation of Under stimulating HP’s Single Stage - Two Mandi Rewalsar Kalkhar IBRD / P4900 Prior Request for Bids Open - National 11,500,000.00 0.00 Implementati 2019-12-12 2019-12-27 2020-02-07 2020-05-03 2020-06-07 2022-12-07 horticultural and overall Envelope road from Km 0/000 to Km on economic growth 12/000 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-HPRIDC -144358-GO- RFQ / Procurement of Axle Pending Request for Single Stage - One Weigh Pad for Road IBRD / P4900 Enhancing Road Safety Post Open - National 86,000.00 0.00 Implementati 2020-06-22 2020-08-17 2021-02-13 Quotations Envelope Maintenance/condition on Surveys under HPSRTP IN-HPRIDC -143869-CS- QCBS / Selection of a System Integrator for Design, Supply, Install, Building HP’s Transport Open - Single Stage - Two Under Integration, Commissioning, IBRD / P4900 Prior Request for Bids 5,714,300.00 0.00 2019-11-30 2019-12-15 2020-01-26 2020-05-05 2020-06-09 2025-06-08 Institutions and Resilience International Envelope Review Testing, and Maintenance of an Integrated Management Information System (IMIS) for HPPWD and HPRIDC IN-HPRIDC -144347-GO- RFB / Procurement of early Pending warning system for Road Single Stage - Two IBRD / P4900 Enhancing Road Safety Post Request for Bids Open - National 285,000.00 0.00 Implementati 2020-05-15 2020-05-30 2020-07-11 2020-10-05 2020-11-09 2023-03-09 Safety/Surveillance/climate Envelope on resilience under World Bank funded HPSRTP IN-HPRIDC -144353-GO- RFB / Procurement of Falling Weight Deflectometer Pending Single Stage - Two for Road IBRD / P4900 Enhancing Road Safety Post Request for Bids Open - National 214,300.00 0.00 Implementati 2020-06-15 2020-06-30 2020-08-11 2020-10-24 2020-11-28 2023-03-28 Envelope Maintenance/Condition on Surveys under World Bank Funded HPSRTP IN-HPRIDC -144323-GO- RFB / Procurement of CCTV Pending cameras for Road Single Stage - Two IBRD / P4900 Enhancing Road Safety Post Request for Bids Open - National 142,900.00 0.00 Implementati 2020-05-15 2020-05-30 2020-07-11 2020-10-05 2020-11-09 2023-03-09 Safety/Surveillance/climate Envelope on resilience under World Bank funded HPSRTP NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-HPRIDC -130428-CS- QCBS / Procurement of Project Management Building HP’s Transport Quality And Cost- Open - Consultant for IBRD / P4900 Prior 6,400,000.00 0.00 Canceled 2019-10-30 2019-11-27 2020-01-17 2020-02-14 2020-03-15 2020-04-19 2020-05-24 2026-05-23 Institutions and Resilience Based Selection International Implementation of World Bank funded HPSRTP in Himachal Pradesh IN-HPRIDC -143839-CS- QCBS / Construction Supervision Consultancy for upgradation of State Core Building HP’s Transport Quality And Cost- Open - Under Road network ( 90 Kms) IBRD / P4900 Prior 2,000,000.00 0.00 2019-11-30 2020-01-04 2020-02-17 2020-03-16 2020-04-15 2020-05-20 2020-06-24 2022-12-24 Institutions and Resilience Based Selection International Implementation under World Bank Funded Himachal Pradesh State Road Transformation Program (HPSRTP). Page 2 IN-HPRIDC -140127-CS- INDV / CONSULTANCY SERVICE FOR ROAD USER SATISFACTION SURVEY, SPEED SURVEY AND TRANSPORTSTION COST Building HP’s Transport Least Cost Under SURVEY(to be conducted in IBRD / P4900 Post Open - National 70,000.00 0.00 2019-12-02 2020-01-06 2020-02-19 2020-03-18 2020-04-17 2020-05-22 2020-06-26 2023-03-23 Institutions and Resilience Selection Implementation three parts – (i) at onset/ before construction; (ii) at 45- 55% completion of works; and (iii) at end term) ON TRANCHE-I HPSRTP ROADS. IN-HPRIDC -143452-CS- QCBS / Procurement of Consultancy Services for “Project Management Building HP’s Transport Quality And Cost- Open - Under IBRD / P4900 Prior 3,000,000.00 0.00 2019-11-28 2020-01-02 2020-03-12 2020-04-23 2020-05-23 2020-07-13 2020-08-31 2026-08-30 Consultant” (PMC) for Institutions and Resilience Based Selection International Implementation implementation of World Bank funded HPSRTP in Himachal Pradesh. IN-HPRIDC -150191-CS- QCBS / Procurement of Road Safety Advisory services for the State of Building HP’s Transport Quality And Cost- Open - IBRD / P4900 Prior 1,000,000.00 0.00 Under Review 2019-12-26 2020-01-30 2020-03-14 2020-04-11 2020-05-11 2020-06-22 2020-07-27 2023-01-25 Himachal Pradesh under Institutions and Resilience Based Selection International Himachal Pradesh State Roads Transformation Program IN-HPRIDC -152370-CS- INDV / Selection of Independent Verification Agent (Technical Audit Consultant-TAC) for Building HP’s Transport Quality And Cost- Under IBRD / P4900 Post Open - National 128,600.00 0.00 2020-01-18 2020-02-08 2020-03-23 2020-04-20 2020-05-20 2020-06-24 2020-07-29 2025-07-28 verification of Disbursement Institutions and Resilience Based Selection Implementation Linked Indicators (DLIs) for implementation of World Bank funded HPSRTP in Himachal Pradesh. IN-HPRIDC -152552-CS- QCBS / Procurement of logistics system and strategy development consultancy Building HP’s Transport Quality And Cost- Pending services for the State of IBRD / P4900 Post Open - National 142,000.00 0.00 2020-05-15 2020-06-05 2020-07-19 2020-08-16 2020-09-15 2020-10-20 2020-11-24 2021-11-24 Institutions and Resilience Based Selection Implementation Himachal Pradesh under Himachal Pradesh State Roads Transformation Program IN-HPRIDC -152553-CS- QCBS / Procurement of Integrated multimodal transportation plan preparation consultancy Building HP’s Transport Quality And Cost- Pending services Road Safety IBRD / P4900 Post Open - National 214,300.00 0.00 2020-04-08 2020-04-29 2020-06-12 2020-07-10 2020-08-09 2020-09-13 2020-10-18 2021-10-18 Institutions and Resilience Based Selection Implementation Advisory services for the State of Himachal Pradesh under Himachal Pradesh State Roads Transformation Program IN-HPRIDC -152557-CS- Improving select roads QCBS / Consultancy Services stimulating HP’s Quality And Cost- Pending for mapping of Geo- IBRD / P4900 Post Open - National 214,300.00 0.00 2020-03-06 2020-03-27 2020-05-10 2020-06-07 2020-07-07 2020-08-11 2020-09-15 2021-09-15 horticultural and overall Based Selection Implementation Hazards/landslides in HP economic growth and mitigation mechanism Page 3 IN-HPRIDC -157032-CS-LCS / Selection of Consultant (NGO) for support to Improving select roads implementation of stimulating HP’s Least Cost Pending IBRD / P4900 Post Open - National 70,000.00 0.00 2020-02-06 2020-02-27 2020-04-11 2020-05-09 2020-06-08 2020-07-13 2020-08-17 2021-08-17 Resettlement Action Plan horticultural and overall Selection Implementation (RAP) for Tranche-I Roads economic growth under HPSRTP (Approx. 90 km.) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-HPRIDC -143837-CS-LCS / Selection of Environmental Individual Specialist for World Bank Building HP’s Transport Under IBRD / P4900 Post Consultant Open 128,600.00 0.00 2019-11-25 2020-02-12 2020-03-11 2020-05-08 2023-05-08 Funded Himachal Pradesh Institutions and Resilience Implementation Selection State Roads Transformation Program (HPSRTP) IN-HPRIDC -143836-CS-LCS / Selection of Social Development Specialist for Individual Building HP’s Transport Under World Bank Funded IBRD / P4900 Post Consultant Open 128,600.00 0.00 2019-11-25 2020-02-12 2020-03-11 2020-05-08 2023-05-08 Institutions and Resilience Implementation Himachal Pradesh Stae Selection Roads Transformation Program (HPSRTP) IN-HPRIDC -152369-CS- INDV / Selection of Bio- engineering Solutions Individual Building HP’s Transport Pending Specialist for World Bank IBRD / P4900 Post Consultant Open 128,000.00 0.00 2020-01-23 2020-03-16 2020-04-06 2020-05-11 2023-05-11 Institutions and Resilience Implementation Funded Himachal Pradesh Selection State Roads Transformation Program (HPSRTP) IN-HPRIDC -152371-CS- INDV / Procurement of Bio engineering solutions manual preparation and Environmental and Social Individual Building HP’s Transport Pending Framework preparation IBRD / P4900 Post Consultant Open 50,000.00 0.00 2020-06-22 2020-08-10 2020-08-31 2020-10-05 2021-10-05 Institutions and Resilience Implementation consultancy services for the Selection State of Himachal Pradesh under Himachal Pradesh State Roads Transformation Program IN-HPRIDC -152482-CS- INDV / Procurement of Road Financing Mechanism study Individual consultancy services for Building HP’s Transport Pending IBRD / P4900 Post Consultant Open 40,000.00 0.00 2020-06-15 2020-08-03 2020-08-24 2020-09-28 2021-03-27 Himachal Pradesh under Institutions and Resilience Implementation Selection Himachal Pradesh State Roads Transformation Program IN-HPRIDC -152484-CS- INDV / Procurement of Direct Labor Operations Individual Advisory Services for the Building HP’s Transport Pending IBRD / P4900 Post Consultant Open 72,000.00 0.00 2020-05-15 2020-07-03 2020-07-24 2020-08-28 2021-08-28 State of Himachal Pradesh Institutions and Resilience Implementation Selection under Himachal Pradesh State Roads Transformation Program IN-HPRIDC -152555-CS- Building HP’s Transport Pending CDS / e-PMS Roll IBRD / P4900 Post Direct Selection Direct 360,000.00 0.00 2020-03-25 2020-04-08 2020-06-12 2021-06-12 Institutions and Resilience Implementation Out/Upgradation Page 4 IN-HPRIDC -152556-CS- Building HP’s Transport Pending CDS / RMS Roll IBRD / P4900 Post Direct Selection Direct 360,000.00 0.00 2020-04-15 2020-04-29 2020-07-03 2021-07-03 Institutions and Resilience Implementation Out/Upgradation IN-HPRIDC -156883-CS- INDV / Selection of Improving select roads Biodiversity/Wildlife Expert Individual stimulating HP’s Pending for World Bank Funded IBRD / P4900 Post Consultant Open 30,000.00 0.00 2020-02-05 2020-03-25 2020-04-15 2020-05-20 2020-11-16 horticultural and overall Implementation Himachal Pradesh State Selection economic growth Roads Transformation Program (HPSRTP) Page 5