Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: November 2013; Revision: …………….] 2. Date of General Procurement Notice: 9th July 2013 3. Period covered by this procurement plan: The procurement period of project covered from year July 2013 to April 2015. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB (Goods) Above US$ 3,000,000 All 2. NCB (Goods) Above US$ 1,000,000 First contract subject to prior review 3. ICB (Works) Above US$ 40, 000,000 All 4. NCB (Works) Above US$ 10, 000,000 First contract subject to prior review 5. Non-Consultant Services Below US$ 1,000,000 First contract subject to prior review 6 Public Private Partnership (PPP) under Below US$40, 000,000 All contracts above NCB Conditions US$10,000,000 will be prior reviewed 7 Public Private Partnership (PPP) under Above US$40, 000,000 All ICB Conditions 2. Pre-qualification [Bidders shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines]: Not Applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As per the OPCS March 2012 Guidelines for managing Procurement under CDD projects, Community Based Procurement (CBP) will implement through community Force Account/ or Shopping and Local Competitive Bidding method (LCB). LCB procedure will be limited to local advertisement using such as media as local newspaper or radio, posting notices at strategic places, circulating such notices or reading them out in community meetings or other public gatherings. 4. Reference to (if any) Project Operational/Procurement Manual: A Procurement Manual is developed for the project as per Bank’s Procurement Guidelines. The manual will be reviewed by the Bank and procurement in the project will be done as per procedures described in the Manual and agreed with the Bank. 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] The following provisions constitute additional provisions applicable for purposes of National Competitive Bidding (NCB). NCB will be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines and the following provisions: • Only the model bidding document for procurement of works through NCB agreed with the Bank (and as amended for time to time), shall be used for bidding; • Invitations to bid shall be advertised in at least one widely circulated national daily newspaper, at least 30 days prior to the deadline for the submission of bids; • No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small scale enterprises or enterprises from any given State; • Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; • Extension of bid validity shall not be allowed for prior review packages, without the prior concurrence of the World Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for prior approved packages, all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/Employer); • Re-bidding shall not be carried out without the prior concurrence of the Bank. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; • Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures. Such contracts will be acceptable however for any procurement under the Shopping procedures; • Two or three envelop system will not be used. However, two part bidding for NCB works (as described in the model bidding document) has been agreed by the Bank under this project, as followed in a similar Bank funded project “Pradhan Mantri Gram Sadak Yojana (PMGSY)”. • Domestic preferences shall not be applicable. • All procurement of works through NCB in the four participating states will be done through a standardized e-procurement system acceptable to the Bank. • As per paragraph 1.14(e) of the World Bank’s Procurement Guidelines, the Association’s right to inspect the accounts and records of bidders, suppliers and contractors will be included in the bidding documents. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ (yes/no) (Prior / million Post) Summary of Post/ the ICB None None No Prior (Works) Summary of Post/ the ICB None None No Prior (Goods) Summary of the NCB 158.93 6 No Prior All (Works) Summary of 1st contract the NCB 149.07 296 No Post for Prior (Works) Review Summary of Post/ the NCB None None No Prior (Goods) Summary of the ICB Post/ (Non- None None No Prior Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 1st contract for Prior Review 2. Single Source (Firms) All All 3. Individual Above US$ 50,000 All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of number of 44.01 17 Prior All contracts that will be let under QCBS 2 Summary of 1st contract number of 2.87 6 Post for Prior contracts that will Review be let under QCBS 3 Summary of number of 1st contract contracts that will 1.49 13 Post for Prior be let under other Review methods PROCUREMENT India : IN Rural Water Supply and Sanitation Project for Low Income States PLAN General Information Country: India Banks Approval Date of the Original Procurement Plan: 2017-03-08 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-03-08 Project ID: P132173 GPN Date: Project Name: IN Rural Water Supply and Sanitation Project for Low Income States Loan / Credit No: IDA / 53450 Executing Agency(ies): Public Health Engineering Department, Drinking Water and Sanitation Department, State Project Management Unit Lucknow, State Project Management Unit (Assam), National Project Management Unit (RWSS) WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBR - 21 GHOGHA GHAT Multi Component A: Capacity Building Village Piped / Design and build and Sector Development of all system components of Component C: Project Single Stage - One GHOGHAGHAT Multi Village IDA / 53450 Prior Request for Bids Open - National N 0.00 6,031,231.33 Signed 2015-02-24 2014-08-06 Management Support Envelope piped water supply scheme Component B: Infrastructure including billing and collection of Development tariff from customers Component A: Capacity Building WBR No. 7 [Chota and Sector Development Govindpur,Baghbera, Jh] / Rural Component C: Project Single Stage - One Pipe Water Supply Scheme - IDA / 53450 Prior Request for Bids Open - International N 0.00 37,362,992.55 Signed 2015-07-14 2015-05-25 Management Support Envelope Chhota Govindpur and Baghbera, Component B: Infrastructure Jharkhand Development W14/JH/207 / Udikel-MVS Component B: Infrastructure Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,823,333.33 0.00 2017-09-15 2017-10-15 2017-12-14 2018-02-26 2018-04-02 2025-03-31 (Khunti) Development Envelope Implementation IN-SPMU-ASSAM-22915-CW- Component C: Project Request for Single Stage - One Pending RFQ / Furnishing of DPMU office, IDA / 53450 Post Open - National 6,507.00 0.00 2018-01-09 2018-03-06 2018-05-20 Management Support Quotations Envelope Implementation Jorhat IN-SPMU-ASSAM-22921-CW- RFQ / Repair, renovation and Component A: Capacity Building Request for Single Stage - One Pending upgradation of existing building of IDA / 53450 Post Open - National 8,947.00 0.00 2017-11-20 2018-01-15 2018-03-31 and Sector Development Quotations Envelope Implementation Kamrup district level testing laboratory IN-SPMU-ASSAM-22925-CW- RFQ / Repair, renovation and Component A: Capacity Building Request for Single Stage - One Under upgradation of existing building of IDA / 53450 Post Open - National 32,536.00 0.00 2017-11-20 2018-01-15 2018-03-31 and Sector Development Quotations Envelope Implementation Jorhat district level testing laboratory IN-SPMU-ASSAM-22926-CW- RFQ / Repair, renovation and Component A: Capacity Building Request for Single Stage - One Pending upgradation of existing building of IDA / 53450 Post Open - National 14,641.00 0.00 2017-11-20 2018-01-15 2018-03-31 and Sector Development Quotations Envelope Implementation Hailakandi district level testing laboratory IN-SPMU-ASSAM-22928-CW- RFQ / Extension, Repair, Component A: Capacity Building Request for Single Stage - One Under renovation and upgradation of IDA / 53450 Post Open - National 13,014.00 0.00 2017-11-20 2018-01-15 2018-03-31 and Sector Development Quotations Envelope Implementation existing building of Bongaigaoni district level testing laboratory IN-SPMU-ASSAM-22929-CW- RFQ / Extension, Repair, Component A: Capacity Building Request for Single Stage - One Under renovation and upgradation of IDA / 53450 Post Open - National 14,641.00 0.00 2017-11-20 2018-01-15 2018-03-31 and Sector Development Quotations Envelope Implementation existing building of Morigaon district level testing laboratory IN-SPMU-ASSAM-22930-CW- RFQ / Extension, Repair, Component A: Capacity Building Request for Single Stage - One Pending renovation and upgradation of IDA / 53450 Post Open - National 24,402.00 0.00 2017-11-20 2018-01-15 2018-03-31 and Sector Development Quotations Envelope Implementation existing building of Sivasagar district level testing laboratory W17/JHDM/019 / Renovation of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 20,000.00 0.00 2017-11-19 2018-01-14 2018-07-13 Existing Laboratory (Dumka) Development Quotations Envelope Implementation W17/JHES/021 / RENOVATION Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 8,333.33 0.00 2017-11-19 2018-01-14 2018-07-13 OF EXISTING LAB Development Quotations Envelope Implementation W14/JH/236 / CONSTRUCTION Component B: Infrastructure Request for Single Stage - One Under IDA / 53450 Post Open - National 100,000.00 92,228.81 2017-10-15 2017-12-10 2018-12-10 & SUPPLY OF PWS Piskahatu Development Quotations Envelope Implementation IN-SPMU-ASSAM-21480-CW- RFB / Design, Build, Operate and Transfer Multi-village Water Supply Scheme, Greater Component B: Infrastructure Single Stage - Two Pending IDA / 53450 Prior Request for Bids Open - National 33,349,601.00 0.00 2017-12-11 2017-12-16 2018-01-27 2018-04-19 2018-05-31 2026-06-25 Jogighopa Piped Water Supply Development Envelope Implementation Scheme in Bongaigaon District with operation and maintenance period of five years. IN-SPMU-ASSAM-21436-CW- RFB / Design, Build, Operate and Transfer Multi-village Water Supply Scheme, Greater Mayang Component B: Infrastructure Single Stage - Two Pending IDA / 53450 Prior Request for Bids Open - National 22,775,338.00 0.00 2017-10-31 2017-11-05 2017-12-17 2018-03-09 2018-04-20 2026-05-15 Piped Water Supply Scheme in Development Envelope Implementation Morigaon District with operation and maintenance period of five years. IN-SPMU-ASSAM-21446-CW- RFB / Design, Build, Operate and Transfer Multi-village Water Supply Scheme, Amguri- Component B: Infrastructure Single Stage - Two Pending IDA / 53450 Prior Request for Bids Open - National 27,655,767.00 0.00 2017-11-20 2017-11-25 2018-01-06 2018-03-29 2018-05-10 2026-06-04 Gaurisagar Piped Water Supply Development Envelope Implementation Scheme in Sivasagar District with operation and maintenance period of five years. W17/JHSK/011 / Renovation of Component B: Infrastructure Request for Single Stage - One Pending Water Quality Testing IDA / 53450 Post Open - National 5,000.00 0.00 2017-11-19 2018-01-14 2018-07-13 Development Quotations Envelope Implementation Laboratory, Saraikela W14/JH/083 / CONSTRUCTION Component B: Infrastructure Single Stage - Two Pending & SUPPLY OF PWSS Lapo- IDA / 53450 Post Request for Bids Open - National 1,173,333.33 0.00 2017-09-15 2017-10-15 2017-11-26 2018-02-08 2018-03-15 2025-02-06 Development Envelope Implementation dumaria W14/JH/246 / CONSTRUCTION Component B: Infrastructure Single Stage - Two Pending & SUPPLY OF PWS Satbarwa/ IDA / 53450 Post Request for Bids Open - National 4,830,000.00 0.00 2017-09-15 2017-10-15 2017-11-26 2018-02-08 2018-03-15 2025-02-06 Development Envelope Implementation Bakoria, Palamu W14/JH/208 / Construction of Component B: Infrastructure Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 963,333.33 0.00 2017-09-15 2017-10-15 2017-11-26 2018-02-08 2018-03-15 2025-02-06 Kanti-MVS Development Envelope Implementation W14/JH/185 / Itagarh Water Component B: Infrastructure Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 776,666.67 0.00 2017-09-15 2017-10-20 2017-12-01 2018-02-13 2018-03-20 2025-02-11 Supply Scheme (MVS) Development Envelope Implementation W14/JH/184 / Dudra Kamalpur Component B: Infrastructure Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 710,000.00 0.00 2017-09-15 2017-10-20 2017-12-01 2018-02-13 2018-03-20 2025-02-11 Water Supply Scheme (MVS) Development Envelope Implementation W17/JHKH/009 / Renovation of Component B: Infrastructure Request for Single Stage - One Pending Water Quality Testing IDA / 53450 Post Open - National 50,000.00 0.00 2017-11-19 2018-01-14 2018-07-13 Development Quotations Envelope Implementation Laboratory, Khunti W14/JH/001 / Karmkitta- Tarni Component B: Infrastructure Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 2,250,000.00 0.00 2017-09-15 2017-10-15 2017-11-26 2018-02-08 2018-03-15 2025-02-06 MVS Scheme (Dumka) Development Envelope Implementation W17/JHGR/012 / Renovation of Component B: Infrastructure Request for Single Stage - One Pending Water Quality Testing IDA / 53450 Post Open - National 13,333.33 0.00 2017-11-19 2018-01-14 2018-07-13 Development Quotations Envelope Implementation Laboratory, Garhwa Component A: Capacity Building and Sector Development IN-SPMU-UP-29914-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 448,568.30 0.00 2017-11-20 2017-11-25 2018-01-06 2018-03-21 2018-04-25 2018-10-22 Batch 2 Holapur , Gonda Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-30067-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 363,261.40 0.00 2017-11-20 2017-11-25 2018-01-06 2018-03-21 2018-04-25 2018-10-22 Batch 2 Jalalpur Routiha, Gonda Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-30069-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Nahawa Parsaura, IDA / 53450 Post Request for Bids Open - National 403,596.40 0.00 2017-11-20 2017-11-25 2018-01-06 2018-03-21 2018-04-25 2018-10-22 Management Support Envelope Implementation Gonda Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-30070-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 437,812.20 0.00 2017-11-20 2017-11-25 2018-01-06 2018-03-21 2018-04-25 2018-10-22 Batch 2 Kalwari, Gonda Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-30078-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 299,392.30 0.00 2017-11-20 2017-11-25 2018-01-06 2018-03-21 2018-04-25 2018-10-22 Batch 2 Basalatpur, Gonda Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-30080-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 545,237.90 0.00 2017-11-20 2017-11-25 2018-01-06 2018-03-21 2018-04-25 2018-10-22 Batch 2 Malauna, Gonda Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-30082-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 484,011.50 0.00 2017-11-20 2017-11-25 2018-01-06 2018-03-21 2018-04-25 2018-10-22 Batch 2 Madhopur, Gonda Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-30120-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 294,353.20 0.00 2017-11-20 2017-11-25 2018-01-06 2018-03-21 2018-04-25 2018-10-22 Batch 2 Thuma Mohan, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-30153-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Bhaisa khoot, IDA / 53450 Post Request for Bids Open - National 325,831.80 0.00 2017-12-20 2017-12-25 2018-02-05 2018-04-20 2018-05-25 2018-11-21 Management Support Envelope Implementation Santkabeer Nagar, Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-30242-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Khazuri, Santkabeer IDA / 53450 Post Request for Bids Open - National 327,588.70 0.00 2017-12-20 2017-12-25 2018-02-05 2018-04-20 2018-05-25 2018-11-21 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-30247-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Tema Rahmat, IDA / 53450 Post Request for Bids Open - National 342,213.60 0.00 2017-12-20 2017-12-25 2018-02-05 2018-04-20 2018-05-25 2018-11-21 Management Support Envelope Implementation Santkabeer Nagar Component B: Infrastructure Development Page 1 Component A: Capacity Building and Sector Development IN-SPMU-UP-30257-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Molnapur, Santkabeer IDA / 53450 Post Request for Bids Open - National 278,573.20 0.00 2017-12-20 2017-12-25 2018-02-05 2018-04-20 2018-05-25 2018-11-21 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-30262-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Parjapatipur, Santkabeer IDA / 53450 Post Request for Bids Open - National 325,669.10 0.00 2017-12-20 2017-12-25 2018-02-05 2018-04-20 2018-05-25 2018-11-21 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-31763-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 280,525.40 0.00 2017-12-20 2017-12-25 2018-02-05 2018-04-20 2018-05-25 2018-11-21 Batch-2 Umaria,Santkabeernagar Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-31770-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Madhavpur, IDA / 53450 Post Request for Bids Open - National 283,567.50 0.00 2017-12-20 2017-12-25 2018-02-05 2018-04-20 2018-05-25 2018-11-21 Management Support Envelope Implementation SantkabeerNagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-31776-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Mudiyari, Santkabeer IDA / 53450 Post Request for Bids Open - National 327,946.60 0.00 2017-12-20 2017-12-25 2018-02-05 2018-04-20 2018-05-25 2018-11-21 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-32629-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 347,288.20 0.00 2018-01-08 2018-01-13 2018-02-24 2018-05-09 2018-06-13 2018-12-10 Batch 2 Khanpur, Gonda Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-32664-CW-RFB / Component C: Project Single Stage - Two Pending Bahadurpur Ta. Ibrahimpur, IDA / 53450 Post Request for Bids Open - National 347,045.20 0.00 2018-01-08 2018-01-13 2018-02-24 2018-05-09 2018-06-13 2018-12-10 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-33557-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Akbarpur Urf Gangaganj, IDA / 53450 Post Request for Bids Open - National 909,853.00 0.00 2018-01-08 2018-01-13 2018-02-24 2018-05-09 2018-06-13 2018-12-10 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-34014-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,048,050.00 0.00 2018-01-08 2018-01-13 2018-02-24 2018-05-09 2018-06-13 2018-12-10 Batch 2 Kakra, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-34044-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Patana Uparhar, IDA / 53450 Post Request for Bids Open - National 277,385.70 0.00 2018-01-08 2018-01-13 2018-02-24 2018-05-09 2018-06-13 2018-12-10 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-34066-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Badpur (Vedpur) IDA / 53450 Post Request for Bids Open - National 329,980.10 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Management Support Envelope Implementation Uparhar, Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-34322-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 367,201.30 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Tikari, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-34769-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Achhola Uparhar, IDA / 53450 Post Request for Bids Open - National 243,580.80 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-34771-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Chaukatha Narwar , IDA / 53450 Post Request for Bids Open - National 286,333.10 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-34905-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 252,121.50 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Alampur Narhi, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-34919-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 242,474.50 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Firozpur, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-34942-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 287,585.70 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Sihar, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-34944-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 240,994.20 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Tanda, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35087-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 276,474.70 0.00 2018-02-10 2018-02-15 2018-03-29 2018-06-11 2018-07-16 2019-01-12 Batch 2 Kishoi, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35089-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 316,445.10 0.00 2018-02-10 2018-02-15 2018-03-29 2018-06-11 2018-07-16 2019-01-12 Batch 2 Kudhan, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35103-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 343,287.30 0.00 2018-02-10 2018-02-15 2018-03-29 2018-06-11 2018-07-16 2019-01-12 Batch 2 Ibrahimpur, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35104-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 230,761.60 0.00 2018-02-10 2018-02-15 2018-03-29 2018-06-11 2018-07-16 2019-01-12 Batch 2 Karanpur, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35112-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 438,796.80 0.00 2018-02-10 2018-02-15 2018-03-29 2018-06-11 2018-07-16 2019-01-12 Batch 2 Hajipur Gang, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35113-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Nasirpur Belwara, IDA / 53450 Post Request for Bids Open - National 328,223.20 0.00 2018-02-10 2018-02-15 2018-03-29 2018-06-11 2018-07-16 2019-01-12 Management Support Envelope Implementation Fatehpur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35256-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,028,257.68 0.00 2018-02-10 2018-02-15 2018-03-29 2018-06-11 2018-07-16 2019-01-12 Batch 2 Husenpur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35340-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,736,430.00 0.00 2018-02-10 2018-02-15 2018-03-29 2018-06-11 2018-07-16 2019-01-12 Batch 2 Kathut, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component B: Infrastructure Development IN-SPMU-UP-35341-CW-RFB / Component A: Capacity Building Single Stage - Two Pending Batch 2 Nagwa Urf Nawapara, IDA / 53450 Post Request for Bids Open - National 530,889.90 0.00 2018-02-10 2018-02-15 2018-03-29 2018-06-11 2018-07-16 2019-01-12 and Sector Development Envelope Implementation Ghazipur Component C: Project Management Support Component A: Capacity Building and Sector Development IN-SPMU-UP-35343-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,160,104.00 0.00 2018-02-10 2018-02-15 2018-03-29 2018-06-11 2018-07-16 2019-01-12 Batch 2 Tiwaripur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35567-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,147,561.00 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch 2 Amba, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35572-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 657,071.80 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch 2 Chandpur, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35601-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,023,306.00 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch 2 Tatepur, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35609-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 452,250.40 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch 2 Gaura Purwar, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-35724-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 676,651.20 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch 2 Domari, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Page 2 Component A: Capacity Building and Sector Development IN-SPMU-UP-38689-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 221,456.30 0.00 2017-11-30 2017-12-05 2018-01-16 2018-03-31 2018-05-05 2018-11-01 Batch 2 Khatagia, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-38690-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 315,615.50 0.00 2017-11-30 2017-12-05 2018-01-16 2018-03-31 2018-05-05 2018-11-01 Batch 2 Anthaiya, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-38693-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 222,009.40 0.00 2017-11-30 2017-12-05 2018-01-16 2018-03-31 2018-05-05 2018-11-01 Nibi TA. Khaivi, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-38694-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 256,481.30 0.00 2017-11-30 2017-12-05 2018-01-16 2018-03-31 2018-05-05 2018-11-01 Batch 2 Taroila, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-38696-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,231,179.00 0.00 2017-11-30 2017-12-05 2018-01-16 2018-03-31 2018-05-05 2018-11-01 Batch 2 Gosandepur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-38698-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 354,984.00 0.00 2017-11-30 2017-12-05 2018-01-16 2018-03-31 2018-05-05 2018-11-01 Batch 2 Baramar, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42219-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 393,116.20 0.00 2018-01-03 2018-01-08 2018-02-19 2018-05-04 2018-06-08 2018-12-05 Batch 2 Rehali, Gonda Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42221-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 395,022.60 0.00 2018-01-03 2018-01-08 2018-02-19 2018-05-04 2018-06-08 2018-12-05 Batch 2 Dasrathpur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42243-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Maniya Uparhar, IDA / 53450 Post Request for Bids Open - National 273,253.60 0.00 2018-01-03 2018-01-08 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42415-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Semri Malmala, IDA / 53450 Post Request for Bids Open - National 682,465.70 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Bahraich Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42416-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Khasha Mohammadpur, IDA / 53450 Post Request for Bids Open - National 623,572.20 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Bahraich Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42417-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 450,498.70 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Batch 2 Sarai Ali, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42418-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 937,795.40 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Batch 2 Barauli, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42419-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 791,506.40 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Batch 2 Balamakan, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42420-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Rampur Kndauli, IDA / 53450 Post Request for Bids Open - National 331,055.10 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Bahraich Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42429-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 241,937.70 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Batch 2 Narauli, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42436-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 320,544.70 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Batch 2 Bharsari, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42438-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Gazipur Kkhurd, IDA / 53450 Post Request for Bids Open - National 283,567.50 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Fatehpur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42439-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Siakatai, Santkabir IDA / 53450 Post Request for Bids Open - National 323,261.40 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42440-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Pakri Apaji, Santkabir IDA / 53450 Post Request for Bids Open - National 269,007.60 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42453-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Jangal Dasahar, IDA / 53450 Post Request for Bids Open - National 512,799.90 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Santkabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42464-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Maheshwarpur, IDA / 53450 Post Request for Bids Open - National 308,913.10 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Santkabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42465-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 303,072.80 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Batch 2 Senari, SantkabirNagar Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42468-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Rampur Uparhar, IDA / 53450 Post Request for Bids Open - National 188,952.80 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42471-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 240,831.50 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Batch 2 Deorakh, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42473-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 212,167.30 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Batch 2 Semraha, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42477-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Gandaila Uparhar, IDA / 53450 Post Request for Bids Open - National 218,495.50 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42478-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Bhuipara Uparhar, IDA / 53450 Post Request for Bids Open - National 264,468.90 0.00 2018-01-04 2018-01-09 2018-02-20 2018-05-05 2018-06-09 2018-12-06 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42525-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Garhachampa Village, IDA / 53450 Post Request for Bids Open - National 406,049.30 0.00 2018-01-05 2018-01-10 2018-02-21 2018-05-06 2018-06-10 2018-12-07 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42529-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Purwa Uparhar, IDA / 53450 Post Request for Bids Open - National 246,720.50 0.00 2018-01-05 2018-01-10 2018-02-21 2018-05-06 2018-06-10 2018-12-07 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42536-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Lawayan Khurd, IDA / 53450 Post Request for Bids Open - National 297,444.10 0.00 2018-01-05 2018-01-10 2018-02-21 2018-05-06 2018-06-10 2018-12-07 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42574-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,263,357.00 0.00 2018-01-05 2018-01-10 2018-02-21 2018-05-06 2018-06-10 2018-12-07 Batch 2 Narhar Gonda, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42590-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Hatwa Uparhar, IDA / 53450 Post Request for Bids Open - National 304,634.60 0.00 2018-01-05 2018-01-10 2018-02-21 2018-05-06 2018-06-10 2018-12-07 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Page 3 Component A: Capacity Building and Sector Development IN-SPMU-UP-42591-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Mahewa Uparhar, IDA / 53450 Post Request for Bids Open - National 264,778.00 0.00 2018-01-05 2018-01-10 2018-02-21 2018-05-06 2018-06-10 2018-12-07 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42824-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 300,018.80 0.00 2018-01-08 2018-01-13 2018-02-24 2018-05-09 2018-06-13 2018-12-10 Batch 2 Padohiya, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-42829-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 349,046.20 0.00 2018-01-08 2018-01-13 2018-02-24 2018-05-09 2018-06-13 2018-12-10 Batch 2 Nasirpur, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-43211-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 827,360.30 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Lakhrampur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building IN-SPMU-UP-44755-CW-RFB / and Sector Development Upgradation of Existing District Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,530,591.00 0.00 2018-01-19 2018-01-24 2018-03-07 2018-05-20 2018-06-24 2018-12-21 Level Water Testing Laboratory in Management Support Envelope Implementation 14 Districts of Uttar Pradesh Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44756-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 455,526.20 0.00 2018-01-19 2018-01-24 2018-03-07 2018-05-20 2018-06-24 2018-12-21 Batch 2 Bibiya, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44757-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 252,821.00 0.00 2018-01-19 2018-01-24 2018-03-07 2018-05-20 2018-06-24 2018-12-21 Batch 2 Bijaura, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44760-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 481,334.10 0.00 2018-01-19 2018-01-24 2018-03-07 2018-05-20 2018-06-24 2018-12-21 Batch 2 Bahorikapur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44765-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 800,803.10 0.00 2018-01-19 2018-01-24 2018-03-07 2018-05-20 2018-06-24 2018-12-21 Batch 2 Basauna Mafi, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44767-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 813,091.90 0.00 2018-01-19 2018-01-24 2018-03-07 2018-05-20 2018-06-24 2018-12-21 Batch 2 Rampurwa, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44770-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 448,255.70 0.00 2018-01-19 2018-01-24 2018-03-07 2018-05-20 2018-06-24 2018-12-21 Batch 2 Chaukhdiya, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44771-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 924,988.70 0.00 2018-01-19 2018-01-24 2018-03-07 2018-05-20 2018-06-24 2018-12-21 Batch 2 Dellapurwa, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component B: Infrastructure Development IN-SPMU-UP-44811-CW-RFB / Component A: Capacity Building Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 410,079.00 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Devidaspur, Bahraich and Sector Development Envelope Implementation Component C: Project Management Support Component A: Capacity Building and Sector Development IN-SPMU-UP-44812-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 729,256.10 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Dokari, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44813-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 358,299.30 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Gajipur Kodari, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44814-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 545,441.80 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Gangapurwa, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44815-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 798,790.50 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Naubana, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44816-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 523,967.00 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Chulama, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44817-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 428,305.20 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Dharampur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44818-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 447,783.90 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Dhanpara, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44819-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 349,135.40 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Alahiyapur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44820-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 325,409.70 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Supani, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44821-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Tendwa Bajantpur, IDA / 53450 Post Request for Bids Open - National 552,128.40 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Management Support Envelope Implementation Bahraich Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44822-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 432,829.30 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Pure Jaita, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44823-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 429,008.20 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Bulha, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44824-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 480,334.40 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Chandela, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44825-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 341,342.00 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Chailal, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44826-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 308,942.20 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Chandradipa, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44827-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 362,472.30 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Huzoorpur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44828-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 382,995.90 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Jagta Jallalpur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44829-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 601,347.80 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Jaisinghpur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44830-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Khairisamyasa, IDA / 53450 Post Request for Bids Open - National 359,515.40 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Management Support Envelope Implementation Bahraich Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44832-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,172,538.00 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Hemariya, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Page 4 Component A: Capacity Building and Sector Development IN-SPMU-UP-44833-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 710,291.00 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Laukiha, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44834-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 484,944.70 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Materpur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44835-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 258,442.60 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Mudhapur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44836-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 530,555.90 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Murtiha, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44837-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Raigarh Baheda, IDA / 53450 Post Request for Bids Open - National 706,736.80 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Management Support Envelope Implementation Bahraich Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44838-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Sadhuwapur Gokulpur, IDA / 53450 Post Request for Bids Open - National 404,403.30 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Management Support Envelope Implementation Bahraich Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44840-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 493,286.70 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Sayyad Nagar, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44841-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Pipraon Ta. Karchana, IDA / 53450 Post Request for Bids Open - National 280,980.90 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44843-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Mawaiya Uparhar, IDA / 53450 Post Request for Bids Open - National 417,859.80 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44857-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 507,220.90 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Kharauwa, Gonda Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44858-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 315,338.90 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Devra Nar, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44859-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 671,120.10 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Mishirpura, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44860-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 405,525.20 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Batch 2 Bariya, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-44861-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Chandayar Walipur, IDA / 53450 Post Request for Bids Open - National 334,941.90 0.00 2018-01-20 2018-01-25 2018-03-08 2018-05-21 2018-06-25 2018-12-22 Management Support Envelope Implementation Ballia Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49201-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Ahmadpur Asrauli IDA / 53450 Post Request for Bids Open - National 358,888.35 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Management Support Envelope Implementation Uparhar, Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49203-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Babhani Hethar, IDA / 53450 Post Request for Bids Open - National 307,448.93 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49208-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 491,082.12 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch 2 Bahmalpur, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49213-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,001,946.12 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch 2 Bahorikapur, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49426-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 551,566.54 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Barhauli, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49428-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Bhabhaura Uparhar, IDA / 53450 Post Request for Bids Open - National 200,145.20 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49430-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 541,643.06 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Bundwan, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49432-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Chaq Sekh Ahmed Urf IDA / 53450 Post Request for Bids Open - National 293,230.70 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Kusetha, Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49435-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 626,936.18 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Chauka, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49438-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Chhatava Uparhar, IDA / 53450 Post Request for Bids Open - National 524,333.91 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component C: Project Management Support IN-SPMU-UP-49475-CW-RFB / Component B: Infrastructure Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 307,058.50 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Bharkhokha, Ballia Development Envelope Implementation Component A: Capacity Building and Sector Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49486-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 379,987.94 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Batch-2 Baghoonch, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49503-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 602,013.61 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Batch-2 Tikhampur, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49506-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 441,757.54 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Dighiya, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49509-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,212,730.60 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Batch-2 Ramna, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49512-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,039,329.98 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Batch-2 Kaithi, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49514-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 581,776.22 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Dulapur, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49515-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,089,402.89 0.00 2018-02-22 2018-02-27 2018-04-10 2018-06-23 2018-07-28 2019-01-24 Batch-2 Tikari, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49521-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 560,025.90 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Gaddopur, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Page 5 Component A: Capacity Building and Sector Development IN-SPMU-UP-49544-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Ganeshipur Uparhar, IDA / 53450 Post Request for Bids Open - National 796,562.62 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49550-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 517,517.62 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Habeliya, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49585-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Jalalpur Ghoshi, IDA / 53450 Post Request for Bids Open - National 241,612.34 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49677-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 664,059.76 0.00 2018-02-22 2018-02-27 2018-04-10 2018-06-23 2018-07-28 2019-01-24 Batch-2 Ramchandipur, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49679-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 567,102.48 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch-2 Muridpur, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49684-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Jera and Saray Kala, IDA / 53450 Post Request for Bids Open - National 521,031.50 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49688-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 239,090.80 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Kabra, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49690-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Kaneda Uparhar, IDA / 53450 Post Request for Bids Open - National 238,309.93 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49698-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 765,507.01 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Karuwa, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49705-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 739,380.60 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch-2 Lootha kala, Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49709-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 913,399.40 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Katwarupur, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49711-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,307,019.92 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch-2 Chhitauni , Varanasi Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49717-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 480,638.06 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Kosda Khurd, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49723-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Unchadeeh , IDA / 53450 Post Request for Bids Open - National 481,353.85 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Management Support Envelope Implementation SiddharthNagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49729-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Tandawa , IDA / 53450 Post Request for Bids Open - National 349,225.15 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Management Support Envelope Implementation SiddharthNagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49735-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 539,446.88 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch-2 Sohana, SiddharthNagar Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49758-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Siswa Bujurg, IDA / 53450 Post Request for Bids Open - National 214,526.24 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Management Support Envelope Implementation SiddharthNagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49764-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Sikautha, Siddharth IDA / 53450 Post Request for Bids Open - National 641,170.68 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49767-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 353,763.92 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Batch-2 Semra, SiddharthNagar Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49771-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Rasulpur, Siddharth IDA / 53450 Post Request for Bids Open - National 688,776.29 0.00 2018-02-20 2018-02-25 2018-04-08 2018-06-21 2018-07-26 2019-01-22 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49775-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 216,055.31 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Kukhuri, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49779-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 535,575.10 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Kusungur, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49781-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 442,668.55 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Lai Group, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49784-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 386,657.82 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Lakhanpur, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49785-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Lawayan Kala Uparhar, IDA / 53450 Post Request for Bids Open - National 440,407.30 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49794-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 361,507.50 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Madafa Kala, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49809-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Madara Mukundpur IDA / 53450 Post Request for Bids Open - National 418,689.52 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Uparhar, Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49817-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 371,658.73 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Mahewakala, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49821-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 829,423.98 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Malak Herher, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-49827-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 534,241.12 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Mirzapur, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50015-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Ramwapur Jagatram, IDA / 53450 Post Request for Bids Open - National 205,399.76 0.00 2018-02-21 2018-02-26 2018-04-09 2018-06-22 2018-07-27 2019-01-23 Management Support Envelope Implementation Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50045-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Pipra Pandey, IDA / 53450 Post Request for Bids Open - National 193,299.76 0.00 2018-02-21 2018-02-26 2018-04-09 2018-06-22 2018-07-27 2019-01-23 Management Support Envelope Implementation Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50051-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Pedari Mustahkam, IDA / 53450 Post Request for Bids Open - National 409,042.59 0.00 2018-02-21 2018-02-26 2018-04-09 2018-06-22 2018-07-27 2019-01-23 Management Support Envelope Implementation Siddharth Nagar Component B: Infrastructure Development Page 6 Component A: Capacity Building and Sector Development IN-SPMU-UP-50056-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Patna Bishunpur, IDA / 53450 Post Request for Bids Open - National 626,675.89 0.00 2018-02-21 2018-02-26 2018-04-09 2018-06-22 2018-07-27 2019-01-23 Management Support Envelope Implementation Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50058-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Marwatiya, Siddharth IDA / 53450 Post Request for Bids Open - National 245,955.89 0.00 2018-02-21 2018-02-26 2018-04-09 2018-06-22 2018-07-27 2019-01-23 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50063-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Manikaura, Siddharth IDA / 53450 Post Request for Bids Open - National 212,302.79 0.00 2018-02-21 2018-02-26 2018-04-09 2018-06-22 2018-07-27 2019-01-23 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50071-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 272,577.61 0.00 2018-02-21 2018-02-26 2018-04-09 2018-06-22 2018-07-27 2019-01-23 Batch-2 Malda, Siddharth Nagar Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50419-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Mubarakpur Uparhar, IDA / 53450 Post Request for Bids Open - National 520,039.16 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50423-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 682,133.51 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Nadula, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50424-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Nahawa Urf Nimikla, IDA / 53450 Post Request for Bids Open - National 448,866.66 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50428-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Maina Khas, Siddharth IDA / 53450 Post Request for Bids Open - National 497,491.71 0.00 2018-02-22 2018-02-27 2018-04-10 2018-06-23 2018-07-28 2019-01-24 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50455-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 419,779.47 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Batch 2 Nasirpatti, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50463-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Mahadeiya, Siddharth IDA / 53450 Post Request for Bids Open - National 283,401.97 0.00 2018-02-22 2018-02-27 2018-04-10 2018-06-23 2018-07-28 2019-01-24 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50468-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Onaur Uparhar, IDA / 53450 Post Request for Bids Open - National 446,426.46 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50471-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Madanpur, Siddharth IDA / 53450 Post Request for Bids Open - National 312,475.74 0.00 2018-02-22 2018-02-27 2018-04-10 2018-06-23 2018-07-28 2019-01-24 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50474-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 455,227.44 0.00 2018-02-22 2018-02-27 2018-04-10 2018-06-23 2018-07-28 2019-01-24 Batch-2 Laljot, Siddharth Nagar Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50475-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Palikaranpur Uparhar, IDA / 53450 Post Request for Bids Open - National 960,169.90 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50484-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 248,884.13 0.00 2018-02-22 2018-02-27 2018-04-10 2018-06-23 2018-07-28 2019-01-24 Batch-2 Lakda, Siddharth Nagar Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50528-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Kot Khas, Siddharth IDA / 53450 Post Request for Bids Open - National 391,375.54 0.00 2018-02-22 2018-02-27 2018-04-10 2018-06-23 2018-07-28 2019-01-24 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50536-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Kharika Pandey, IDA / 53450 Post Request for Bids Open - National 253,700.12 0.00 2018-02-22 2018-02-27 2018-04-10 2018-06-23 2018-07-28 2019-01-24 Management Support Envelope Implementation Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50543-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Panasa Uparhar, IDA / 53450 Post Request for Bids Open - National 820,216.29 0.00 2018-02-25 2018-03-02 2018-04-13 2018-06-26 2018-07-31 2019-01-27 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50542-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Khairkaura, Siddharth IDA / 53450 Post Request for Bids Open - National 273,725.36 0.00 2018-02-22 2018-02-27 2018-04-10 2018-06-23 2018-07-28 2019-01-24 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50774-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2Khairi Sheetal Prasad, IDA / 53450 Post Request for Bids Open - National 255,820.85 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50776-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Kanchanpur, Siddharth IDA / 53450 Post Request for Bids Open - National 282,965.59 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50814-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Kan Bhari PWS Scheme IDA / 53450 Post Request for Bids Open - National 219,678.80 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50822-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Pipra Scheme Distt. IDA / 53450 Post Request for Bids Open - National 292,140.74 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Ballia Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50825-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 374,717.11 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Batch-2 Sahras Pali, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50819-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Hata khas PWS IDA / 53450 Post Request for Bids Open - National 298,306.31 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Scheme Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50830-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Golhaura PWS Scheme IDA / 53450 Post Request for Bids Open - National 368,958.24 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50828-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 248,835.33 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Batch-2 Saraya, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50836-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Sarwar Kakar Ghatt, IDA / 53450 Post Request for Bids Open - National 364,321.86 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Balliai Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50835-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Gauhaniya Raj PWS IDA / 53450 Post Request for Bids Open - National 243,857.20 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Scheme Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50848-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Ganwariya PWS IDA / 53450 Post Request for Bids Open - National 225,082.45 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Scheme Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50853-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Gangwal PWS Scheme IDA / 53450 Post Request for Bids Open - National 234,860.67 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50860-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Gadakhauwa PWS IDA / 53450 Post Request for Bids Open - National 262,191.35 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Scheme Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50864-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Deipar PWS Scheme IDA / 53450 Post Request for Bids Open - National 353,227.08 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Distt. Siddharth Nagar Component B: Infrastructure Development Page 7 Component A: Capacity Building and Sector Development IN-SPMU-UP-50870-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Chaukhadha PWS IDA / 53450 Post Request for Bids Open - National 636,290.28 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Scheme Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50875-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 778,928.11 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Shivpur Diyar Numbrey, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50878-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Charthari PWS Scheme IDA / 53450 Post Request for Bids Open - National 228,207.50 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50879-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 368,600.34 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Batch-2 Sonki Bhat, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50881-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Chakai Jot PWS IDA / 53450 Post Request for Bids Open - National 317,844.18 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Scheme Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50882-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 274,457.43 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Batch-2 Sripatipur, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50884-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Biskohar PWS Scheme IDA / 53450 Post Request for Bids Open - National 601,910.37 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Management Support Envelope Implementation Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50886-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 879,383.01 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Batch-2 Udaypura, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50889-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 548,150.26 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Batch-2 Udhran, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-50893-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 694,936.42 0.00 2018-02-23 2018-02-28 2018-04-11 2018-06-24 2018-07-29 2019-01-25 Batch-2 Abhaypur, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51080-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Bhujrahi PWS Scheme IDA / 53450 Post Request for Bids Open - National 472,504.06 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51083-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Bhatijwapur PWS IDA / 53450 Post Request for Bids Open - National 436,128.81 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51086-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Bhanpur Rain PWS IDA / 53450 Post Request for Bids Open - National 469,071.52 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51087-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 309,872.86 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Adampur, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51091-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 306,358.98 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Baghauli, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51092-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Bahariya PWS Scheme IDA / 53450 Post Request for Bids Open - National 251,421.94 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51094-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 582,752.30 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Baigaon, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51095-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Baghini PWS Scheme IDA / 53450 Post Request for Bids Open - National 228,760.61 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51099-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Bagdihwa PWS IDA / 53450 Post Request for Bids Open - National 229,525.21 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Siddharth Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51106-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,030,057.22 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Pandila, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51110-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 340,066.27 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Bhaupur, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51114-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Umari Khurd PWS IDA / 53450 Post Request for Bids Open - National 410,945.95 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Sant Kabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51115-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 207,953.84 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Devmai, fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51113-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 350,168.70 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Pipari (Piyari, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51116-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Pharendiya PWS IDA / 53450 Post Request for Bids Open - National 368,128.57 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Sant Kabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51120-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 497,133.81 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Pipraon, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51122-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Neeba Horil PWS IDA / 53450 Post Request for Bids Open - National 469,331.80 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Sant Kabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51119-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 419,730.67 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Galatha Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51124-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 592,187.74 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Pure Ghasi, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51125-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Manjhariya PWS IDA / 53450 Post Request for Bids Open - National 369,348.67 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Sant Kabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51129-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Kali Lagdishpur PWS IDA / 53450 Post Request for Bids Open - National 458,497.31 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Sant kabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51133-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Jigina PWS Scheme IDA / 53450 Post Request for Bids Open - National 434,453.20 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Distt. Sant kabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51149-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Raipura Uparhar - IDA / 53450 Post Request for Bids Open - National 384,770.74 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Kanjauli Uparhar, Allahabad Component B: Infrastructure Development Page 8 Component A: Capacity Building and Sector Development IN-SPMU-UP-51150-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 714,148.93 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Guneer, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51153-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 693,618.72 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Rampur, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building IN-SPMU-UP-51148-CW-RFB / and Sector Development Batch-2 Jagdishpur Urf Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 393,832.01 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Lahuradeva PWS Scheme Distt. Management Support Envelope Implementation Sant kabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51152-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 264,224.86 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Ibrahimpur, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51154-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Rasoolpur Kashipur IDA / 53450 Post Request for Bids Open - National 353,975.41 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Uparhar, Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51157-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 322,968.60 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Rawatpur, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51160-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 950,750.72 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Samaha, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51162-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 299,005.84 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Ijaura khurd, fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51161-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Sangram Patti, IDA / 53450 Post Request for Bids Open - National 922,964.98 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51164-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 296,272.82 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Khalispur, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51163-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Dulhipar PWS Scheme IDA / 53450 Post Request for Bids Open - National 282,786.64 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Distt. Sant Kabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51167-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Sarai Dadan Uparhar, IDA / 53450 Post Request for Bids Open - National 431,411.09 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51170-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Barghat PWS Scheme IDA / 53450 Post Request for Bids Open - National 208,864.85 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Distt. Sant kabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51171-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 315,696.81 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Kotla, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51173-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Sarairah urf Korari, IDA / 53450 Post Request for Bids Open - National 338,504.54 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51174-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 478,767.24 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Lahangi, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51179-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 216,640.96 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Tarvai, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51180-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 210,133.76 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Lakhpura, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51184-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 195,525.09 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Ujihani Aima, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51185-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 227,882.14 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Mahadevpur, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51187-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Makhdumpur Kalan, IDA / 53450 Post Request for Bids Open - National 268,145.44 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Fatehpur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51181-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 493,506.05 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Teliya Tara, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51191-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Aura dand G.P PWS IDA / 53450 Post Request for Bids Open - National 445,792.00 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Sant kabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51194-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 329,280.59 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Mirmau, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51197-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Amraha PWS Scheme IDA / 53450 Post Request for Bids Open - National 278,556.96 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Distt. Sant kabir Nagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51192-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 747,482.06 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Tharwai, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51198-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Paigambarpur Rikouha IDA / 53450 Post Request for Bids Open - National 327,182.02 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation PWS Scheme Distt. Fatehpur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51193-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Tikari - Saidabad, IDA / 53450 Post Request for Bids Open - National 236,715.67 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51203-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Nizamuddeenpur, IDA / 53450 Post Request for Bids Open - National 216,478.28 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Fatehpur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51202-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Shyam Patti PWS IDA / 53450 Post Request for Bids Open - National 172,684.82 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Kushinagar Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51210-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Rasulpur Bhandra, IDA / 53450 Post Request for Bids Open - National 449,891.54 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Fatehpur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51215-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Ravatpur (Khajuwa), IDA / 53450 Post Request for Bids Open - National 240,961.62 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Fatehpur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51220-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 356,366.81 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Umapur Kala, Allahabad Management Support Envelope Implementation Component B: Infrastructure Development Page 9 Component A: Capacity Building and Sector Development IN-SPMU-UP-51221-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Upraura Uparhar, IDA / 53450 Post Request for Bids Open - National 653,762.12 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Allahabad Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51222-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 240,473.58 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Ravatpur Aung, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51224-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Ravatpur (Telyani), IDA / 53450 Post Request for Bids Open - National 270,943.54 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Fatehpur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51226-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 472,398.43 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Baidaura, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51229-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 312,020.24 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Shivrajpur, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51232-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 408,272.99 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Bhoga Jot, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51227-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 314,086.28 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Bhainsaha, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51231-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 311,873.83 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Surajipur, Fatehpur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51236-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 372,853.08 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Chakujot, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51238-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,371,782.83 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Chauksahar, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51237-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Sakadarpur PWS IDA / 53450 Post Request for Bids Open - National 144,961.98 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Gonda Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51244-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 577,576.95 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Gajadharpur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51240-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 250,429.59 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Tarapur Bhitaura Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51246-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Ranijot PWS Scheme IDA / 53450 Post Request for Bids Open - National 162,323.57 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Distt. Gonda Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51242-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 763,863.94 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Daulatpur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51249-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 418,445.50 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Haibatpur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51250-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Mijhaura PWS Scheme IDA / 53450 Post Request for Bids Open - National 304,642.70 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Distt. Gonda Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51253-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 435,467.98 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Ichachhapur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51255-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,226,021.55 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Intaha, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51257-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Dumariyadeeh Zone-II IDA / 53450 Post Request for Bids Open - National 248,965.47 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation PWS Scheme Distt. Gonda Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51256-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 401,933.48 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Jhingaha, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51245-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 383,599.44 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Aaspur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51259-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 684,443.56 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Khaira Kalan, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51264-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 750,394.04 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-1 Akberpur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51267-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,413,315.04 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Madhawapur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51265-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 543,226.58 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Kotiya, bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51269-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 344,100.74 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Babura, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51268-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Araji kasba Swad, IDA / 53450 Post Request for Bids Open - National 456,772.90 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51272-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 372,992.70 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Baghan, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51271-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 966,493.14 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Mahasi, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51273-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,056,441.23 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Mjhara, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51276-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 916,246.30 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Bavara, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51277-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 963,553.64 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Bayepur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Page 10 Component A: Capacity Building and Sector Development IN-SPMU-UP-51280-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 712,701.08 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Raja Rehua, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51279-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Sikandarpur PWS IDA / 53450 Post Request for Bids Open - National 1,058,086.99 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51274-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Tajpur Manjha PWS IDA / 53450 Post Request for Bids Open - National 1,059,339.62 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51278-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 339,359.17 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Muwafikpur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51283-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 459,766.22 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Charipur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51286-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 302,275.71 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Rajapurkalan, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51287-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 390,920.04 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Raundopur, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51282-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Sawana PWS Scheme IDA / 53450 Post Request for Bids Open - National 323,228.89 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51291-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 459,518.00 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Rewali, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51285-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Sadhopur urf Rampur IDA / 53450 Post Request for Bids Open - National 412,296.19 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation PWS Scheme Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51295-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Shahawapur Mahipal IDA / 53450 Post Request for Bids Open - National 513,418.08 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Singh, Bahraich Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51296-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,102,482.36 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Chochakpur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51298-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 359,701.75 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Dewariya, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51300-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Reotipur PWS Scheme IDA / 53450 Post Request for Bids Open - National 1,005,264.79 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51301-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 361,387.39 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Sai Gaon, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51303-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 961,129.71 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Deoria, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51307-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 426,221.60 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Sisia Chak, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51297-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Shakkarpur PWS IDA / 53450 Post Request for Bids Open - National 503,364.45 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51308-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 770,598.89 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Dubaitha, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51305-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 327,930.34 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Batch-2 Dharwar Kalan, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51314-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 890,624.20 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Urra, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51311-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Dullahpur PWS IDA / 53450 Post Request for Bids Open - National 860,870.02 0.00 2018-02-26 2018-03-03 2018-04-14 2018-06-27 2018-08-01 2019-01-28 Management Support Envelope Implementation Scheme Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51399-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Raval Zone-II PWS IDA / 53450 Post Request for Bids Open - National 381,484.60 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation Scheme Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51402-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Bara PWS Scheme IDA / 53450 Post Request for Bids Open - National 2,629,543.25 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51404-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Raval Zone-I PWS IDA / 53450 Post Request for Bids Open - National 532,126.28 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation Scheme Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51408-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 304,667.10 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch-2 Firojpur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51412-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 836,354.15 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch-2 Garoa, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51423-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,340,011.43 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Shekh Dahir, Bahraich Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51422-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Gauranm Sadkalpur, IDA / 53450 Post Request for Bids Open - National 273,774.17 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51424-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Salkhan PWS Scheme IDA / 53450 Post Request for Bids Open - National 15,576,902.82 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation Distt. Sonebhadra Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51426-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 294,271.85 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Balipur and Sarak, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51427-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Patna PWS Scheme IDA / 53450 Post Request for Bids Open - National 939,167.90 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51428-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Kundari PWS Scheme IDA / 53450 Post Request for Bids Open - National 6,936,545.05 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation Distt. Sonebhadra Component B: Infrastructure Development Page 11 Component A: Capacity Building and Sector Development IN-SPMU-UP-51430-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 371,561.12 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Bharsouta, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51431-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Pathara PWS Scheme IDA / 53450 Post Request for Bids Open - National 365,867.32 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51432-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Parmeth PWS Scheme IDA / 53450 Post Request for Bids Open - National 830,058.43 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51433-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 434,729.76 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Bhojapur, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51434-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Pallia Bujurg PWS IDA / 53450 Post Request for Bids Open - National 527,066.93 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation Scheme Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51437-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Nariyaon Urf Umarganj IDA / 53450 Post Request for Bids Open - National 1,825,123.18 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation PWS Scheme Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51438-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 269,300.47 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Bishunpura, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51441-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Narayanpur PWS IDA / 53450 Post Request for Bids Open - National 380,183.16 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation Scheme Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51442-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Chak Haji Urf Shekhpur, IDA / 53450 Post Request for Bids Open - National 224,351.99 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Ballia Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51443-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,092,575.00 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch-2 Jamuav, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51448-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Nari Pachdevra PWS IDA / 53450 Post Request for Bids Open - National 766,938.59 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Management Support Envelope Implementation Scheme Distt. Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51449-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 247,273.60 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Chandpura, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51450-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 506,731.93 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch-1 Jangipur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51457-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 262,110.02 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Diuli, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51456-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,137,783.92 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch-2 Katariya, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51455-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,129,308.29 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch-2 Jeevpur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51459-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 234,730.97 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Dopahi, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51460-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 887,484.47 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch-2 Khizirpur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51461-CW-RFB / Component C: Project Single Stage - Two Pending Batch-2 Lakhanchandpur, IDA / 53450 Post Request for Bids Open - National 950,262.68 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Ghazipur Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51463-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,165,862.49 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch-2 Matsa, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51474-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 315,713.08 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Goniya Chhapra, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51475-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 1,330,250.63 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch-2 Mednipur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51477-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 571,673.79 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Jagdeva, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51480-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 445,792.00 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch-2 Monikpur, Ghazipur Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51484-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 235,772.12 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 kachhuwa Ojha, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51491-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 769,492.67 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Madadih, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51493-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 324,497.80 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Majhoua, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51505-CW-RFB / Component C: Project Single Stage - Two Pending Batch 2 Kadiyari Patti (Saray IDA / 53450 Post Request for Bids Open - National 162,680.00 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Management Support Envelope Implementation Bharti Vill), Ballia Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51509-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 245,646.00 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch-2 Nandpur, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51514-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 254,740.61 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Narhi, Ballia Management Support Envelope Implementation Component B: Infrastructure Development Component A: Capacity Building and Sector Development IN-SPMU-UP-51517-CW-RFB / Component C: Project Single Stage - Two Pending IDA / 53450 Post Request for Bids Open - National 416,590.94 0.00 2018-02-28 2018-03-05 2018-04-16 2018-06-29 2018-08-03 2019-01-30 Batch 2 Pilue, Ballia Management Support Envelope Implementation Component B: Infrastructure Development GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SPMU-ASSAM-21354-GO- RFQ / Printing and supply of Component A: Capacity Building Request for Single Stage - One Pending leaflet, booklet on FAQ, book IDA / 53450 Post Open - National 83,602.00 0.00 2018-04-17 2018-06-12 2018-07-12 and Sector Development Quotations Envelope Implementation labels for school children, booklet on scheme Page 12 IN-SPMU-ASSAM-21422-GO- RFQ / Printing and supply of Component A: Capacity Building Request for Single Stage - One Pending IDA / 53450 Post Open - National 6,833.00 0.00 2018-05-01 2018-06-26 2018-07-26 flipchart, snakes and ladder and Sector Development Quotations Envelope Implementation game, card sorting game IN-SPMU-ASSAM-21426-GO- Component A: Capacity Building Request for Single Stage - One Pending RFQ / Printing and installation of IDA / 53450 Post Open - National 1,253.00 0.00 2018-05-13 2018-07-08 2018-08-07 and Sector Development Quotations Envelope Implementation promotional board IN-SPMU-ASSAM-21427-GO- Component A: Capacity Building Request for Single Stage - One Pending RFQ / Printing and supply of IDA / 53450 Post Open - National 8,785.00 0.00 2018-07-25 2018-09-19 2018-10-19 and Sector Development Quotations Envelope Implementation calendar 2019 IN-SPMU-ASSAM-22806-GO- RFQ / Furniture, fixtures and Component C: Project Request for Single Stage - One IDA / 53450 Post Open - National 4,880.00 7,700.73 Signed 2017-09-20 2017-11-15 2018-01-03 2017-12-15 equipment for DPMU, Management Support Quotations Envelope Bongaigaon IN-SPMU-ASSAM-22812-GO- Component C: Project Request for Single Stage - One RFQ / Furniture, fixtures and IDA / 53450 Post Open - National 4,880.00 10,218.48 Signed 2017-09-24 2017-11-19 2017-12-05 2017-12-19 Management Support Quotations Envelope equipment for DPMU, Sivasagar IN-SPMU-ASSAM-22818-GO- Component C: Project Request for Single Stage - One RFQ / Furniture, fixtures and IDA / 53450 Post Open - National 4,880.00 7,597.85 Signed 2017-09-24 2017-11-19 2018-01-03 2017-12-19 Management Support Quotations Envelope equipment for DPMU, Morigaon IN-SPMU-ASSAM-22827-GO- Component A: Capacity Building Request for Single Stage - One Pending RFQ / Provisions for chemicals IDA / 53450 Post Open - National 38,230.00 0.00 2018-01-10 2018-03-07 2018-04-21 and Sector Development Quotations Envelope Implementation for project district laboratory IN-SPMU-ASSAM-22829-GO- RFQ / Provision of computers Component A: Capacity Building Request for Single Stage - One Pending and peripherals for strengthening IDA / 53450 Post Open - National 33,698.00 0.00 2018-02-11 2018-04-08 2018-05-23 and Sector Development Quotations Envelope Implementation of MIS system for project district laboratory IN-SPMU-ASSAM-22850-GO- RFQ / Provisions of laboratory Component A: Capacity Building Request for Single Stage - One Pending IDA / 53450 Post Open - National 11,388.00 0.00 2017-12-20 2018-02-14 2018-03-31 furniture & accessories for and Sector Development Quotations Envelope Implementation project district laboratories G17/JHDM/001 / Component A: Capacity Building Request for Single Stage - One Pending Printing/Purchase/ Display of IEC IDA / 53450 Post Open - National 3,333.33 0.00 2017-12-16 2018-02-10 2018-05-11 and Sector Development Quotations Envelope Implementation Materials G17/JHDM/004 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending Furniture & Fixtures for IDA / 53450 Post Open - National 3,333.33 0.00 2017-12-26 2018-02-20 2018-05-21 Development Quotations Envelope Implementation Laboratory G17/JHDM/005 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 5,000.00 0.00 2017-12-26 2018-02-20 2018-05-21 Equipment for Laboratory Development Quotations Envelope Implementation G17/JHDM/006 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-26 2018-02-20 2018-05-21 Glassware for Laboratory Development Quotations Envelope Implementation G17/JHDM/007 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending Consumables (Chemicals) for IDA / 53450 Post Open - National 13,333.33 0.00 2018-01-30 2018-03-27 2018-06-25 Development Quotations Envelope Implementation Laboratory G17/JHDM/008 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 1,666.67 0.00 2018-01-30 2018-03-27 2018-06-25 Laptop & GPS Set for Laboratory Development Quotations Envelope Implementation G17/JHDM/009 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 8,333.33 0.00 2018-01-30 2018-03-27 2018-06-25 FTK Kit Development Quotations Envelope Implementation G17/JHES/001 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 41,666.67 0.00 2017-12-26 2018-02-20 2018-05-21 Equipment for referral lab Development Quotations Envelope Implementation G17/JHES/002 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 25,000.00 0.00 2017-12-26 2018-02-27 2018-05-28 Equipment for other lab Development Quotations Envelope Implementation G17/JHES/003 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 16,666.67 0.00 2017-12-26 2018-02-27 2018-05-28 Chemicals for water quality lab Development Quotations Envelope Implementation G17/JHES/004 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-26 2018-03-07 2018-06-05 (Glasswares) for Laboratory Development Quotations Envelope Implementation G17/JHES/005 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending Computer/Laptop, Software and IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-26 2018-02-27 2018-05-28 Development Quotations Envelope Implementation GPS set for lab G17/JHES/006 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 8,333.33 0.00 2017-12-26 2018-02-27 2018-05-28 FTK Kit Development Quotations Envelope Implementation G17/JHGR/001 / Component A: Capacity Building Request for Single Stage - One Pending Printing/Purchase/ Display of IEC IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-16 2018-02-17 2018-05-18 and Sector Development Quotations Envelope Implementation materials G17/JHGR/004 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending Furniture & Fixtures for IDA / 53450 Post Open - National 3,333.33 0.00 2017-12-26 2018-02-27 2018-05-28 Development Quotations Envelope Implementation Laboratory G17/JHGR/005 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 5,000.00 0.00 2017-12-26 2018-02-27 2018-05-28 Equipment for Laboratory Development Quotations Envelope Implementation G17/JHGR/006 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-26 2018-02-27 2018-05-28 Glassware for Laboratory Development Quotations Envelope Implementation G17/JHGR/007 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending Consumables (Chemicals) for IDA / 53450 Post Open - National 13,333.33 0.00 2017-12-26 2018-02-27 2018-05-28 Development Quotations Envelope Implementation Laboratory G17/JHGR/008 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-26 2018-02-27 2018-05-28 Laptop & GPS Set for Laboratory Development Quotations Envelope Implementation G17/JHGR/009 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 8,333.33 0.00 2017-12-26 2018-02-27 2018-05-28 FTK Kit Development Quotations Envelope Implementation G17/JHKH/001 / Component A: Capacity Building Request for Single Stage - One Pending Printing/Purchase/ Display of IEC IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-16 2018-02-17 2018-05-18 and Sector Development Quotations Envelope Implementation materials G17/JHKH/004 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending Furniture & Fixtures for IDA / 53450 Post Open - National 3,333.33 0.00 2017-12-26 2018-02-27 2018-05-28 Development Quotations Envelope Implementation Laboratory G17/JHKH/005 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 25,000.00 0.00 2017-12-26 2018-02-27 2018-05-28 Equipment for Laboratory Development Quotations Envelope Implementation G17/JHKH/006 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-26 2018-02-27 2018-05-28 Glassware for Laboratory Development Quotations Envelope Implementation G17/JHKH/007 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending Consumables (Chemicals) for IDA / 53450 Post Open - National 3,333.33 0.00 2017-12-26 2018-02-27 2018-05-28 Development Quotations Envelope Implementation Laboratory G17/JHKH/008 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-26 2018-02-27 2018-05-28 Laptop & GPS Set for Laboratory Development Quotations Envelope Implementation G17/JHKH/009 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 8,333.33 0.00 2017-12-26 2018-02-27 2018-05-28 FTK Kit Development Quotations Envelope Implementation G17/JHKH/010 / Purchase of Component C: Project Request for Single Stage - One Pending IDA / 53450 Post Open - National 833.33 0.00 2017-10-05 2017-12-07 2018-03-07 LCD Projector Management Support Quotations Envelope Implementation G17/JHKH/011 / Purchase of Component C: Project Request for Single Stage - One Pending IDA / 53450 Post Open - National 1,250.00 0.00 2017-10-05 2017-12-07 2018-03-07 Xerox Machine Management Support Quotations Envelope Implementation G17/JHSK/001 / Procurement of Component C: Project Request for Single Stage - One Pending IDA / 53450 Post Open - National 1,333.33 0.00 2017-10-25 2017-12-27 2018-03-27 Photocopier Machine Management Support Quotations Envelope Implementation G17/JHSK/003 / Procurement of Component C: Project Request for Single Stage - One Pending IDA / 53450 Post Open - National 3,000.00 0.00 2018-02-20 2018-04-24 2018-07-23 Air Conditioner Management Support Quotations Envelope Implementation G17/JHSK/004 / Procurement of Component C: Project Request for Single Stage - One Pending IDA / 53450 Post Open - National 2,000.00 0.00 2017-10-05 2017-12-07 2018-06-05 Generator Management Support Quotations Envelope Implementation G17/JHSK/005 / Procurement of Component C: Project Request for Single Stage - One Pending IDA / 53450 Post Open - National 833.33 0.00 2017-12-26 2018-02-27 2018-08-26 Furniture & Fixture Management Support Quotations Envelope Implementation G17/JHSK/006 / Procurement of Component C: Project Request for Single Stage - One Pending IDA / 53450 Post Open - National 833.33 0.00 2017-11-08 2018-01-10 2018-07-09 Coffee Vending Machine Management Support Quotations Envelope Implementation G17/JHSK/007 / Procurement of Component C: Project Request for Single Stage - One Pending IDA / 53450 Post Open - National 833.33 0.00 2017-10-24 2017-12-26 2018-06-24 Office Stationery Management Support Quotations Envelope Implementation G17/JHSK/008 / Procurement Component B: Infrastructure Request for Single Stage - One Pending of Furniture & Fixtures for IDA / 53450 Post Open - National 2,600.00 0.00 2017-12-26 2018-02-27 2018-08-26 Development Quotations Envelope Implementation Laboratory G17/JHSK/009 / Procurement of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-26 2018-02-27 2018-08-26 Equipment for Laboratory Development Quotations Envelope Implementation G17/JHSK/010 / Procurement of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-26 2018-02-27 2018-08-26 Glassware for Laboratory Development Quotations Envelope Implementation G17/JHSK/011 / Procurement of Component B: Infrastructure Request for Single Stage - One Pending Consumables (Chemicals) for IDA / 53450 Post Open - National 1,666.67 0.00 2017-12-26 2018-02-27 2018-08-26 Development Quotations Envelope Implementation Laboratory G17/JHSK/012 / Procurement Component B: Infrastructure Request for Single Stage - One Pending of Desktop & GPS Set for IDA / 53450 Post Open - National 2,333.33 0.00 2017-12-26 2018-02-27 2018-08-26 Development Quotations Envelope Implementation Laboratory G17/JHSK/013 / Purchase of Component B: Infrastructure Request for Single Stage - One Pending IDA / 53450 Post Open - National 8,333.33 0.00 2017-12-26 2018-02-27 2018-08-26 FTK Kit Development Quotations Envelope Implementation G17/JHSP/001 / Component A: Capacity Building Request for Single Stage - One Pending Printing/Purchase of IEC IDA / 53450 Post Open - National 83,333.33 0.00 2017-12-26 2018-02-27 2018-08-26 and Sector Development Quotations Envelope Implementation materials G17/JHSP/002 / Component C: Project Request for Single Stage - One Pending Hardware,Software,Furniture & IDA / 53450 Post Open - National 83,333.33 0.00 2018-01-10 2018-03-14 2018-09-10 Management Support Quotations Envelope Implementation Fixtures for SPMU IN-SPMU-ASSAM-21871-GO- RFQ / Procurement of additional Component C: Project Request for Single Stage - One IDA / 53450 Post Open - National 12,201.00 7,359.39 Completed 2017-08-09 2017-10-04 2017-08-25 2018-01-17 2017-12-08 chairs for the extension portion of Management Support Quotations Envelope the SPMU, NNP-Assam office IN-SPMU-ASSAM-21640-GO- RFQ / Power backup system for extension part of SPMU, NNP- Assam office - 1 no. 40 kVA Component C: Project Request for Single Stage - One IDA / 53450 Post Open - National 12,201.00 9,017.84 Signed 2017-09-12 2017-10-21 2017-11-07 2017-12-05 2018-02-20 salient diesel genset with Management Support Quotations Envelope automatic changing over/ switch over facility with accessories and RCC foundation. IN-SPMU-ASSAM-22902-GO- Component C: Project Request for Single Stage - One RFQ / Computers and IDA / 53450 Post Open - National 22,775.00 29,196.16 Signed 2017-09-17 2017-11-12 2017-11-21 2017-12-12 Management Support Quotations Envelope peripherals IN-SPMU-ASSAM-22804-GO- Component C: Project Request for Single Stage - One RFQ / Furniture, fixtures and IDA / 53450 Post Open - National 4,880.00 10,372.95 Signed 2017-09-20 2017-11-15 2017-12-21 2017-12-15 Management Support Quotations Envelope equipment for DPMU, Jorhat Page 13 IN-SPMU-ASSAM-22856-GO- RFQ / Equipment and Component C: Project Request for Single Stage - One IDA / 53450 Post Open - National 2,440.00 3,098.94 Completed 2017-08-22 2017-10-17 2017-10-20 2017-11-16 2017-11-14 accessories for SPMU, NNP- Management Support Quotations Envelope Assam IN-SPMU-ASSAM-22846-GO- RFB / Supply of additional equipment required in existing Component A: Capacity Building Single Stage - Two Under district level water testing IDA / 53450 Post Request for Bids Open - National 262,014.00 0.00 2017-10-25 2018-01-10 2017-10-30 2018-03-07 2017-12-11 2018-02-23 2018-04-06 2018-06-20 and Sector Development Envelope Implementation laboratories for testing as per UDWQMP of GoI (for project districts) IN-SPMU-ASSAM-33064-GO- RFQ / Computers and Component C: Project Request for Single Stage - One IDA / 53450 Post Open - National 24,402.00 19,161.54 Signed 2017-11-12 2018-01-07 2018-01-10 2018-02-06 peripherals for SPMU and Management Support Quotations Envelope DPMUs IN-SPMU-ASSAM-41001-GO- RFQ / Procurement of Office Component C: Project Request for Single Stage - One Stationery for State Project IDA / 53450 Post Open - National 5,455.38 5,230.34 Signed 2018-01-08 2018-03-08 2018-02-02 2018-04-07 Management Support Quotations Envelope Management Unit, Neer Nirmal Pariyojana-Assam Component A: Capacity Building and Sector Development IN-SPMU-UP-48544-GO-RFQ / Component C: Project Request for Single Stage - One Pending Procurement of 139 Tablets for IDA / 53450 Post Limited 27,135.19 0.00 2018-03-15 2018-05-10 2018-11-06 Management Support Quotations Envelope Implementation batch-2 SOs Component B: Infrastructure Development NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SPMU-ASSAM-21499-NC- RFQ / Security Audit of Web Component A: Capacity Building Request for Single Stage - One IDA / 53450 Post Limited 2,440.00 431.58 Completed 2017-07-23 2017-07-05 2017-09-01 2017-08-18 2017-11-15 2017-12-15 Application under Neer Nirmal and Sector Development Quotations Envelope Pariyojana, Assam IN-SPMU-ASSAM-21501-NC- RFQ / Empanelment of agencies Component C: Project Request for Single Stage - One IDA / 53450 Post Open - National 85,310.00 74,186.27 Signed 2017-07-23 2017-09-08 2017-10-24 2018-09-23 for hiring of vehicles on monthly Management Support Quotations Envelope basis IN-SPMU-ASSAM-21506-NC- RFQ / Empanelment of agencies Component C: Project Request for Single Stage - One IDA / 53450 Post Open - National 11,713.00 219.82 Signed 2017-07-23 2017-09-08 2017-10-24 2018-09-23 for hiring of vehicles for local Management Support Quotations Envelope journey on daily/half day basis IN-SPMU-ASSAM-21507-NC- RFQ / Empanelment of agencies Component C: Project Request for Single Stage - One IDA / 53450 Post Open - National 9,761.00 332.77 Signed 2017-07-23 2017-09-08 2017-10-24 2018-09-23 for hiring of vehicles for outstation Management Support Quotations Envelope journey on daily basis. IN-SPMU-ASSAM-22912-NC- Component C: Project Request for Single Stage - One IDA / 53450 Post Open - National 13,828.00 6,953.37 Signed 2017-08-10 2017-10-20 2017-10-05 2018-01-30 2018-10-20 RFQ / Hiring of security services Management Support Quotations Envelope G17/JHDM/002 / Fixing of Component A: Capacity Building Request for Single Stage - One Pending IDA / 53450 Post Open - National 6,666.67 0.00 2017-12-16 2018-02-10 2018-05-11 Signage Board and Sector Development Quotations Envelope Implementation G17/JHDM/003 / Wall writing in Component A: Capacity Building Request for Single Stage - One Pending IDA / 53450 Post Open - National 33,333.33 0.00 2017-12-16 2018-02-10 2018-05-11 Multi Colour and Sector Development Quotations Envelope Implementation G17/JHGR/002 / Fixing of Component A: Capacity Building Request for Single Stage - One Pending IDA / 53450 Post Open - National 5,000.00 0.00 2017-12-16 2018-02-17 2018-05-18 Signage Board and Sector Development Quotations Envelope Implementation G17/JHGR/003 / Wall writing in Component A: Capacity Building Request for Single Stage - One Pending IDA / 53450 Post Open - National 41,666.67 0.00 2017-12-16 2018-02-17 2018-05-18 Multi Colour and Sector Development Quotations Envelope Implementation G17/JHKH/002 / Fixing of Component A: Capacity Building Request for Single Stage - One Pending IDA / 53450 Post Open - National 3,333.33 0.00 2017-12-16 2018-02-17 2018-05-18 Signage Board and Sector Development Quotations Envelope Implementation G17/JHKH/003 / Wall writing in Component A: Capacity Building Request for Single Stage - One Pending IDA / 53450 Post Open - National 50,000.00 0.00 2017-12-16 2018-02-17 2018-05-18 Multi Colour and Sector Development Quotations Envelope Implementation G17/JHSK/002 / Wall Writing, Component A: Capacity Building Request for Single Stage - One Pending IDA / 53450 Post Open - National 36,666.67 0.00 2017-11-29 2018-01-31 2018-05-01 Sign Board & Other IEC activities and Sector Development Quotations Envelope Implementation G17/JHSP/004 / Development of Component A: Capacity Building Request for Single Stage - One Pending Documentary films on case IDA / 53450 Post Open - National 33,333.33 0.00 2018-01-03 2018-03-07 2018-09-03 and Sector Development Quotations Envelope Implementation studies IN-SPMU-ASSAM-22908-NC- RFQ / Engagement of agency for preparation of comprehensive Component A: Capacity Building Request for Single Stage - One Under GIS database for Khetri gram IDA / 53450 Post Open - National 13,014.00 0.00 2017-10-08 2017-12-03 2018-04-17 and Sector Development Quotations Envelope Implementation panchayat in Kamrup (M) district under Neer Nirmal Pariyojana on pilot basis G17/JHSP/003 / AMC for H/W & Component C: Project Request for Single Stage - One Pending IDA / 53450 Post Open - National 30,000.00 0.00 2017-12-26 2018-02-27 2018-08-26 S/W SPMU Office Management Support Quotations Envelope Implementation G17/JHES/007 / Printing of Component A: Capacity Building Request for Single Stage - One Pending Pamphlets Leaflets in Multi- IDA / 53450 Post Open - National 5,000.00 0.00 2017-12-25 2018-03-05 2018-09-01 and Sector Development Quotations Envelope Implementation colour, Registers, Jamshedpur G17/JHES/008 / Fixing of Hoardings at Entry, Exit & other Component A: Capacity Building Request for Single Stage - One Pending IDA / 53450 Post Open - National 3,333.33 0.00 2017-11-25 2018-02-03 2018-08-02 places of the District, and Sector Development Quotations Envelope Implementation Jamshedpur G17/JHES/009 / Wall writing in Component A: Capacity Building Request for Single Stage - One Pending IDA / 53450 Post Open - National 16,666.67 0.00 2018-01-25 2018-04-05 2018-10-02 Multi-colour, Jamshedpur and Sector Development Quotations Envelope Implementation G17/JHES/010 / Scheme Wise Component A: Capacity Building Request for Single Stage - One Pending Project Display Board , IDA / 53450 Post Open - National 3,333.33 0.00 2018-01-25 2018-04-05 2018-10-02 and Sector Development Quotations Envelope Implementation Jamshedpur IN-SPMU-ASSAM-41004-NC- RFQ / Preparation of Scaled Component C: Project Request for Single Stage - One Under Down 3D Animated Illustration of IDA / 53450 Post Open - National 2,440.21 0.00 2018-01-10 2018-03-10 2018-05-09 Management Support Quotations Envelope Implementation the Project under Neer Nirmal Pariyojana-Assam. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBR No. 29 / Hiring of Human Component A: Capacity Building Resource Agency for and Sector Development Recruitment and Management of Component C: Project Quality And Cost- IDA / 53450 Prior Open - International N 0.00 422,823.21 Signed 2016-01-27 2016-02-01 Professionals for 10 District Management Support Based Selection Project Management Units Component B: Infrastructure (DPMUs) - U.P. Development Consultant C17/JHSP/001 / Hiring of Component C: Project Under IDA / 53450 Post Qualification Open - National 8,333.33 0.00 2017-10-10 2017-10-31 2017-12-14 2018-01-13 2018-02-17 2019-02-17 External Auditors Management Support Implementation Selection Consultant C17/JHSP/002 / Hiring of Component C: Project Under IDA / 53450 Post Qualification Open - National 8,333.33 0.00 2017-10-10 2017-10-31 2017-12-14 2018-01-13 2018-02-17 2019-02-17 Internal Auditors Management Support Implementation Selection C17/JHSP/003 / Sector Consultant Development Studies (Hiring of Component A: Capacity Building Pending IDA / 53450 Post Qualification Open - National 83,333.33 0.00 2018-01-05 2018-01-26 2018-03-11 2018-04-10 2018-05-15 2018-11-11 Technical,Social & and Sector Development Implementation Selection Communication Institution) C17/JHSP/004 / Environment Component B: Infrastructure Quality And Cost- Pending IDA / 53450 Post Open - National 333,333.33 0.00 2017-12-18 2018-01-08 2018-02-21 2018-03-21 2018-04-20 2018-05-25 2018-06-29 2019-06-29 Audit Development Based Selection Implementation C17/JHSP/005 / Hiring of Media Component A: Capacity Building Quality And Cost- Pending IDA / 53450 Post Open - National 333,333.33 0.00 2018-01-05 2018-01-26 2018-03-11 2018-04-08 2018-05-08 2018-06-12 2018-07-17 2019-07-17 Agency and Sector Development Based Selection Implementation C17/JHSP/006 / Hiring of Component C: Project Quality And Cost- Pending outsourcing agency for IDA / 53450 Post Open - National 1,000,000.00 0.00 2017-09-10 2017-10-01 2017-11-14 2017-12-12 2018-01-11 2018-02-15 2018-03-22 2019-03-22 Management Support Based Selection Implementation recruitment and HR Management C17/JHSP/007 / Hiring of Agency for preparing a module Consultant for Grievance Redressal System Component A: Capacity Building Pending IDA / 53450 Post Qualification Open - National 8,333.33 0.00 2017-10-10 2017-10-31 2017-12-14 2018-01-13 2018-02-17 2018-08-16 for Water Supply schemes under and Sector Development Implementation Selection the existing system of the Department IN-SPMU-ASSAM-21323-CS- CQS / Hiring of Media Agency to Design, Develop and Deploy Consultant Component A: Capacity Building Audio-Visual Media for IDA / 53450 Post Qualification Open - National 243,348.00 203,497.97 Signed 2017-07-20 2017-06-27 2017-08-01 2017-09-14 2017-10-25 2017-10-14 2017-12-12 2017-11-18 2018-01-04 2018-05-20 and Sector Development Information, Education and Selection Communication under Neer Nirmal Pariyojana, Assam IN-SPMU-ASSAM-22939-CS- CDS / Third party quality Component C: Project Quality And Cost- Pending assurance consultant (TPQAC) IDA / 53450 Post Open - National 406,702.46 0.00 2017-11-17 2017-12-08 2018-01-21 2018-02-18 2018-03-20 2018-04-24 2018-06-05 2021-06-19 Management Support Based Selection Implementation for Morigaon, Sivasagar and Bongaigaon sub-projects IN-SPMU-ASSAM-41015-CS- QCBS / Preparation of a State Component A: Capacity Building Quality And Cost- Under IDA / 53450 Post Open - National 69,009.27 0.00 2018-01-08 2017-12-29 2018-01-29 2018-03-14 2018-04-11 2018-05-11 2018-06-15 2018-07-20 2019-01-31 Rural Drinking Water Supply and Sector Development Based Selection Implementation Policy for Assam IN-SPMU-ASSAM-41030-CS- QCBS / Provision of Technical Support to the Project Districts under Neer Nirmal Pariyojana in Component C: Project Quality And Cost- Under IDA / 53450 Post Open - National 569,383.44 0.00 2018-01-09 2017-12-29 2018-01-30 2018-03-15 2018-04-12 2018-05-12 2018-06-16 2018-07-21 2020-08-04 the state of Assam, in Management Support Based Selection Implementation implementation of SLWM component under SBM-G, through Technical Support Unit IN-NPMU-44751-CS-QCBS / Invitation for Expression of Interest (EoI) for engaging Project Component C: Project Quality And Cost- Under Management Consultancy in IDA / 53450 Prior Open - National 1,385,000.00 0.00 2018-01-19 2018-01-22 2018-02-09 2018-01-22 2018-04-24 2018-05-22 2018-06-21 2018-07-26 2018-08-30 2019-08-30 Management Support Based Selection Implementation Water Division of Ministry of Drinking Water & Sanitation, Government of India, New Delhi. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBR No. 27 / Independent Component A: Capacity Building Verification Agency (IVA) for and Sector Development Chhota Govindpur and Baghbera Component C: Project IDA / 53450 Prior Direct Selection Direct N 0.00 297,752.00 Signed 2016-01-22 Piped Water Supply Scheme Management Support (MVS) in East Singhbhum Component B: Infrastructure district of Jharkhand Development Component A: Capacity Building WBR No. 24 / Contract and Sector Development Agreement of Third Party Quality Component C: Project IDA / 53450 Prior Direct Selection Direct N 0.00 128,932.58 Signed 2015-07-27 Assurance Consultant (TPQAC) Management Support for Kamrup Project Component B: Infrastructure Development Page 14 Component A: Capacity Building WBR No. 28 / THIRD PARTY and Sector Development QUALITY ASSURANCE Component C: Project IDA / 53450 Prior Direct Selection Direct N 0.00 100,763.53 Signed 2016-01-11 CONSULTANT - (TPQAC) FOR Management Support HAILAKANDI PROJECT Component B: Infrastructure Development WBR No. 33 / Component A: Capacity Building TOPOGRAPHICAL SURVEY and Sector Development (PHASE-I SURVEY) OF Component C: Project IDA / 53450 Prior Direct Selection Direct N 0.00 245,547.32 Canceled SIVASAGAR, BONGAIGAON, Management Support SONITPUR & MORIGAON Component B: Infrastructure (BATCH-II PROJECT) Development Component A: Capacity Building WBR No. 25 / CONTRACT and Sector Development AGREEMENT OF THIRD PARTY Component C: Project QUALITY ASSURANCE IDA / 53450 Prior Direct Selection Direct N 0.00 136,494.70 Signed 2015-09-10 Management Support CONSULTANT (TPQAC) FOR Component B: Infrastructure JORHAT PROJECT Development IN-SPMU-ASSAM-28961-CS- Component C: Project Individual Consultant Under INDV / Construction IDA / 53450 Post Open 16,268.00 0.00 2017-09-22 2017-09-25 2017-11-10 2018-02-12 2017-12-01 2018-01-12 2019-02-06 Management Support Selection Implementation Management Engineer IN-SPMU-ASSAM-28965-CS- Component C: Project Individual Consultant Under IDA / 53450 Post Open 14,641.00 0.00 2017-09-22 2017-09-25 2017-11-10 2018-02-12 2017-12-01 2018-01-12 2019-02-06 INDV / Technical Consultant Management Support Selection Implementation IN-SPMU-ASSAM-41024-CS- Component C: Project Individual Consultant Under INDV / Engagement of Project IDA / 53450 Post Open 40,995.61 0.00 2018-01-05 2018-01-02 2018-02-23 2018-03-16 2018-04-20 2019-05-05 Management Support Selection Implementation Engineer - 3 No. IN-SPMU-ASSAM-41026-CS- Component C: Project Individual Consultant Under INDV / Engagement of Lower IDA / 53450 Post Open 4,880.43 0.00 2018-01-05 2018-01-04 2018-02-23 2018-03-16 2018-04-20 2019-05-05 Management Support Selection Implementation Division Assistant - 1 No. Page 15