Public Disclosure Copy The World Bank Implementation Status & Results Report Extractive Industries Technical Assistance Project Phase 2 (P160719) Extractive Industries Technical Assistance Project Phase 2 (P160719) AFRICA | Sierra Leone | Energy & Extractives Global Practice | IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 1 | ARCHIVED on 14-Feb-2018 | ISR31277 | Implementing Agencies: Ministry of Mines and Mineral Resources, National Minerals Agency, Ministry of Finance and Economic Development Key Dates Key Project Dates Bank Approval Date:22-Nov-2017 Effectiveness Date:-- Planned Mid Term Review Date:15-Dec-2020 Actual Mid-Term Review Date:-- Original Closing Date:31-Dec-2022 Revised Closing Date:31-Dec-2022 Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed project development objective is to strengthen governance, knowledge, and sustainability of the extractives sector in Sierra Leone. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component A—IMPROVE MINERAL SECTOR GOVERNANCE:(Cost $2.99 M) Component B—ENHANCE GEOLOGICAL KNOWLEDGE:(Cost $11.53 M) Component C—ARTISANAL MINING:(Cost $3.18 M) Component D—PROJECT MANAGEMENT:(Cost $1.96 M) Component E--CONTINGENCY FOR DISASTER RISK RESPONSE Contingency:(Cost $0.35 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  --  Satisfactory Overall Implementation Progress (IP)  --  Satisfactory Overall Risk Rating  --  Moderate 2/14/2018 Page 1 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Extractive Industries Technical Assistance Project Phase 2 (P160719) Implementation Status and Key Decisions The project is yet to become effective so there are no updates to project status and decisions. Effectiveness is expected by mid February 2018. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  High  --  High Macroeconomic  High  --  High Sector Strategies and Policies  Moderate  --  Moderate Technical Design of Project or Program  Low  --  Low Institutional Capacity for Implementation and Sustainability  Moderate  --  Moderate Fiduciary  High  --  High Environment and Social  Low  --  Low Stakeholders  Low  --  Low Other  Low  --  Low Overall  Moderate  --  Moderate Results Project Development Objective Indicators PHINDPDOTBL  Enhance overall governance of the extractives sector - Implement the Policy Actions Matrix of the Minerals Policy (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 30.00 Date 31-Aug-2017 -- -- 31-Dec-2022 PHINDPDOTBL  Enhance geological knowledge - Complete a nationwide airborne geophysical survey. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target 2/14/2018 Page 2 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Extractive Industries Technical Assistance Project Phase 2 (P160719) Value 5.00 -- -- 100.00 Date 31-Aug-2017 -- -- 30-Dec-2022 PHINDPDOTBL  Increase formalization of artisanal miners - Issue new mining licenses (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1,030.00 -- -- 1,133.00 Date 15-Aug-2017 -- -- 31-Dec-2022 Overall Comments The project is yet to become effective so there are no updates to the results framework. Effectiveness is expected by mid February 2018. Intermediate Results Indicators PHINDIRITBL  Enhance overall governance of the extractives sector - Strengthen MMMR in policy making (number of people attending policy training per year). (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 15.00 Date 31-Aug-2017 -- -- 30-Dec-2022 PHINDIRITBL  Enhance overall governance of the extractives sector - Revise licensing procedures (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 31-Aug-2017 -- -- 31-Aug-2021 2/14/2018 Page 3 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Extractive Industries Technical Assistance Project Phase 2 (P160719) PHINDIRITBL  Enhance overall governance of the extractives sector - Revise Mines and Minerals Act (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 31-Aug-2017 -- -- 30-Dec-2022 PHINDIRITBL  Enhance geological knowledge - Complete new and/or revised maps at 1:100,000 scale (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 15.00 Date 31-Aug-2017 -- -- 30-Dec-2022 PHINDIRITBL  Attract private sector investment - Issue exploration licenses (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 146.00 -- -- 175.00 Date 31-Aug-2017 -- -- 30-Dec-2022 PHINDIRITBL  Attract private sector investment - Conduct investment promotion at international conferences (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 8.00 Date 31-Aug-2017 -- -- 30-Dec-2022 2/14/2018 Page 4 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Extractive Industries Technical Assistance Project Phase 2 (P160719) PHINDIRITBL  Formalize artisanal miners - Establish cooperatives (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 5.00 Date 31-Aug-2017 -- -- 30-Dec-2022 PHINDIRITBL  Complete baseline study of artisanal mining (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 31-Aug-2017 -- -- 31-Dec-2019 PHINDIRITBL  Revise legislation on artisanal mining (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 31-Aug-2017 -- -- 30-Dec-2022 PHINDIRITBL  Implement the Green Gold Pilot - Gold miners trained on cleaner technologies (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 20.00 Date 31-Aug-2017 -- -- 30-Dec-2022 2/14/2018 Page 5 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Extractive Industries Technical Assistance Project Phase 2 (P160719) PHINDIRITBL  Implement the Green Gold Pilot - Complete study on green gold value chain (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 31-Aug-2017 -- -- 31-Dec-2018 PHINDIRITBL  Implement the Green Gold Pilot - Develop and implement the Green Gold branding campaign (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 1.00 Date 31-Aug-2017 -- -- 30-Dec-2022 PHINDIRITBL  Citizen engagement - Components A and C - Nationwide consultations on new policies (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 31-Aug-2017 -- -- 30-Dec-2022 PHINDIRITBL  Citizen engagement - Component B - Sensitization ahead of fly-overs (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- -- Y Date 31-Aug-2017 -- -- 31-Dec-2020 Overall Comments 2/14/2018 Page 6 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Extractive Industries Technical Assistance Project Phase 2 (P160719) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed Not P160719 IDA-D2680 USD 20.00 20.00 0.00 0.00 20.03 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P160719 IDA-D2680 22-Nov-2017 -- -- 31-Dec-2022 31-Dec-2022 Effective Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) 2/14/2018 Page 7 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Extractive Industries Technical Assistance Project Phase 2 (P160719) There are no related projects. 2/14/2018 Page 8 of 8 Public Disclosure Copy