The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) SOUTH ASIA | Afghanistan | Social Global Practice | IBRD/IDA | Investment Project Financing | FY 2019 | Seq No: 3 | ARCHIVED on 10-Feb-2020 | ISR40301 | Implementing Agencies: Ministry of Economy, Ministry of Finance, Aid Management Directorate Key Dates Key Project Dates Bank Approval Date: 19-Dec-2018 Effectiveness Date: 06-Feb-2019 Planned Mid Term Review Date: 31-Oct-2021 Actual Mid-Term Review Date: Original Closing Date: 31-Dec-2023 Revised Closing Date: 31-Dec-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to strengthen the enabling environment for economic opportunities in cities where there is a high influx of displaced people. This will be pursued by increasing the returnees' access to civil documents, providing short-term employment opportunities, improving market enabling infrastructure, and supporting investor friendly regulatory reforms. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Regional and National Integration of Displaced Persons:(Cost $4.50 M) Short Term Employment Opportunities, Reforms, and Market Enabling Infrastructure under IDLG:(Cost $120.50 M) Prioritized Urban Investments in Four Provincial Capital Cities:(Cost $25.00 M) Market Enabling Infrastructure and Reforms for Kabul Municipality:(Cost $40.00 M) Red Carpet and Program Coordination:(Cost $10.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating High High Implementation Status and Key Decisions The project continues to make steady implementation progress, despite experiencing some delays, and is on track to completing all the planned activities within the project implementation period. Component 1 (Regional and National Integration of Displaced Persons) and Component 3 (Prioritized Urban Investments in Four Provincial Capital Cities) continue to experience substantial delays, mostly due to the challenges faced in recruiting key staff for Project Implementation Units (PIUs). Component 3 will be fully implemented by the PIU of the Cities Investment Program 2/10/2020 Page 1 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) (CIP) and there is no additional recruitment planned under EZ-Kar, but the recruitment delays experienced under CIP has affected the rollout of Component 3. Once the staff recruitments are completed for these components, implementation is expected to pick up quickly. Component 2 (Short Term Employment Opportunities and Market Enabling Infrastructure under IDLG) implementation is generally on track, with the procurement of Facilitating Partners, who will undertake the bulk of component activities, under way (despite some delays). Component 4 (Market Enabling Infrastructure and Reforms for Kabul Municipality) implementation is also progressing, with a long list of 17 priority projects identified, and feasibility studies are under development for two of them. Component 5 (Red Carpet and Program Coordination) is making good overall progress, having completed most of key procurement and recruitment activities as well as critical path actions. The construction permits regulatory reform action plans have also been developed and cleared under Components 2, 4, and 5. Overall, the project is aiming to make substantial progress on the following key activities in the next six months: (1) Procurement and operationalization of passport issuing machines under Component 1; (2) Procurement of Facilitating Partners and commencement of social mobilization activities for Maintenance and Construction Cash Grants under Component 2; (3) Preparation and rollout of an initial set of Priority Projects under Components 3 and 4; and (4) Implementation of construction permit process streamlining and simplification, commencement of the Government to Business (G2B) regulatory baseline assessment and feasibility studies for Business Support Centers (BSCs) under Component 5. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic High High High Sector Strategies and Policies High High High Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary High High High Environment and Social Substantial Substantial Substantial Stakeholders Substantial Substantial Substantial Other Substantial Substantial Substantial Overall High High High Results PDO Indicators by Objectives / Outcomes ACCESS TO CIVIL DOCUMENTS IN00794767 ►Percentage of Afghan Passport Applications in Pakistan Processed (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 2/10/2020 Page 2 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 During the project implementation period, number of Afghan Passport Applications in Pakistan processed, divided by the number of Afghan Passport Application received in Pakistan. The Afghan missions in Pakistan has not been able to process machine readable passports yet, since Comments: required equipment has not been procurement. The procurement is delayed due to the delays in hiring the Procurement Specialist (now on board). IN00794770 Percentage of Afghan Passport Applications in Pakistan Processed (for female applicants) (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 SHORT-TERM EMPLOYMENT OPPORTUNITIES IN00794766 ►Number of vulnerable households in high IDP/returnee cities provided with short term employment support (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80,000.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of households that have participated in labor intensive public works undertaken through MCCG subprojects. Comments: Implementation of this activity has not commenced, since the procurement of the Facilitating Partners, who will implement the bulk of this activity has faced delays (expected to be hired by March 31, 2020). IN00794769 Of which IDP/Returnee households (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10,000.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 RED CARPET REFORMS AND MARKET FACILITATING INVESTMENTS IN00794685 ►Number of market enabling infrastructure built or upgraded (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,115.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of infrastructure built, upgraded, or maintained through MCCG, Gozar and Business Gozar Comments: Grants, and Priority Projects IN00794768 Of which at the community level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 900.00 2/10/2020 Page 3 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794771 Of which at the Gozar level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 180.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794772 Of which at the Business Gozar level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794773 Of which at the city level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794774 ►Number of processing steps reduced for specific Doing Business reform indicators in four cities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 13.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Comments: Number of processing steps reduced for obtaining construction permits for commercial properties IN00794775 Of which in the three cities of Jalalabad, Herat, and Kandahar (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794776 Of which in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 3.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Intermediate Results Indicators by Components Support for Afghan Refugees in Pakistan 2/10/2020 Page 4 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) IN00794777 ►Number of passports issued to Afghan refugees in Pakistan during the project implementation period (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,500,000.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of machine-readable passports issued for the applications received at the Afghan Embassy and Comments: consulates in Pakistan. IN00794782 of which women (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 600,000.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794784 ►Percentage of passport applications processed within ten (10) working days (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 The number of machine-readable passports issued within 10 working days of application received, divided by the number of complete passport applications received during the reporting period at the Afghan Comments: Embassy and consulates in Pakistan. The baseline is zero, as machine-readable passports have not been issued in Pakistan, and there is no monitoring system in place. IN00794788 of which women (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794792 ►Number of people reached through communications activities implemented through the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 750,000.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Sum of the numbers of (a) followers of the social media accounts created by the project; (b) help/support Comments: cases logged by helplines and information centers; (c) people reached by awareness campaigns. IN00794795 of which women (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 300,000.00 2/10/2020 Page 5 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Short-Term Employment Opportunities IN00794783 ►% of CDC members who are women (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 40.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of women in the CDCs established under the project, divided by the total number of members of Comments: the CDCs established under the project. Market Facilitating Investments IN00794779 ►Number of municipalities where IDLG holds EZ-Kar coordination meetings with government authorities, Gozar assemblies and Business Gozar assemblies (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 11.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of cities that have held meetings with EZ-Kar stakeholders in the cities where Gozar and Comments: Business Gozar Grants are implemented. IN00794780 ►Number of Gozars (hh and business) that have prepared their Gozar economic development plans (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 276.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Comments: Number of approved Gozar Economic Development Plans IN00794785 ►Businesses in urban areas provided with access to “Improved Water Sources” under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of businesses that are provided with access to improved water sources through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project Comments: takes on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN00794787 Of which through Priority Projects in Kabul (Number, Custom Breakdown) 2/10/2020 Page 6 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794793 Of which through Priority Projects in the four cities of Herat, Kandahar, Khost, and Jalalabad (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794796 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794798 ►Businesses in urban areas provided with access to "Improved Sanitation" under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of businesses that are provided with access to improved sanitation through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project takes Comments: on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN00794800 Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794802 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794804 ►Businesses in urban areas provided with access to all-season roads within a 500-meter range under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 2/10/2020 Page 7 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of businesses that are provided with access to all-season roads within a 500-meter range through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, Comments: since this Project takes on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN00794805 KM of roads constructed (Kilometers, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 IN00794806 KM of roads rehabilitated (Kilometers, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 IN00794807 ►Businesses in urban areas provided with access to regular solid waste collection at the markets under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of businesses that are provided with access to regular solid waste collection through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Comments: Project takes on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN00794808 Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794809 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794810 ►Businesses in urban areas provided with access to electricity under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 2/10/2020 Page 8 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of businesses that are provided with access to electricity through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project takes Comments: on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN00794811 Generation Capacity of Renewable Energy (other than hydropower) rehabilitated under the project (Megawatt, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 IN00794812 Generation Capacity of Renewable Energy (other than hydropower) constructed under the project (Megawatt, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 IN00794813 ►Businesses with improved access to ICT services under the project (number of business subscribers) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of businesses that are provided with access to ICT services through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project takes Comments: on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN00794814 Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794815 Of which through Priority Projects in the four cities of Herat, Kandahar, Khost, and Jalalabad (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794816 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 2/10/2020 Page 9 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794817 ►Number of market enabling investments under the project that address the gender gap in access to urban economic centers/ markets (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 35.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of market enabling investments under the project that close gender gaps in women’s access to markets, which can be in the form of (i) specific subprojects exclusively for women, e.g. restoration of Comments: women's markets, rehabilitation of toilet facilities for markets; or (ii) subprojects that are inclusive for (and do not exclude) women, such as extension and upgrading of pedestrian walkways, bus stops and street lighting that link to markets. IN00794818 Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794819 Of which through Priority Projects in the four cities of Herat, Jalalabad, Kandahar, and Khost (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 4.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794820 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Red Carpet Reforms IN00794778 ►Number of reform implementation plans prepared (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 5.00 5.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Comments: Number of construction permit reform implementation plans prepared IN00794781 Of which at national level (Number, Custom Breakdown) 2/10/2020 Page 10 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 1.00 1.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794786 Of which in the three cities of Herat, Jalalabad, and Kandahar (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 3.00 3.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794789 Of which in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 1.00 1.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794791 ►Reduction in time taken to obtain a construction permit for commercial properties in Jalalabad, Kandahar, Herat, and Kabul (Days, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 77.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Comments: Number of average days reduced for obtaining construction permits for commercial properties IN00794797 Of which in Jalalabad (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 14.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794799 Of which in Kandahar (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 6.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 IN00794801 Of which in Herat (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 18.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 2/10/2020 Page 11 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) IN00794803 Of which in Kabul (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 39.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Project Management IN00794790 ►Number of access to information inquiries responded to within agreed service standards (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 Number of individuals and organizations (including media and NGOs) that received project related Comments: information in accordance with agreed service standards. IN00794794 ►Percentage of complaints / grievances resolved following agreed EZ-Kar service standards (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Nov-2018 11-Feb-2019 07-Nov-2019 31-Dec-2023 The number of project related complaints or grievances resolved in accordance with EZ-Kar service Comments: standards, divided by the number of project related complaints or grievances received. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P166127 IDA-D4160 Effective USD 150.00 150.00 0.00 5.13 144.29 3.4% P166127 TF-A9092 Effective USD 50.00 50.00 0.00 1.71 48.29 3.4% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P166127 IDA-D4160 Effective 19-Dec-2018 06-Feb-2019 06-Feb-2019 31-Dec-2023 31-Dec-2023 P166127 TF-A9092 Effective 19-Dec-2018 06-Feb-2019 06-Feb-2019 31-Dec-2023 31-Dec-2023 2/10/2020 Page 12 of 13 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 2/10/2020 Page 13 of 13