The World Bank Implementation Status & Results Report Kingdom of Eswatini: Water Supply and Sanitation Access Project (P166697) Kingdom of Eswatini: Water Supply and Sanitation Access Project (P166697) AFRICA | Eswatini | Water Global Practice | IBRD/IDA | Investment Project Financing | FY 2020 | Seq No: 1 | ARCHIVED on 17-Dec-2019 | ISR39778 | Implementing Agencies: Eswatini Water Services Corporation, Ministry of Finance Key Dates Key Project Dates Bank Approval Date: 10-Oct-2019 Effectiveness Date: -- Planned Mid Term Review Date: -- Actual Mid-Term Review Date: Original Closing Date: 30-Sep-2025 Revised Closing Date: 30-Sep-2025 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To increase access to improved water supply and sanitation services in targeted areas of Eswatini. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Resilient Water Access and Management:(Cost $28.00 M) Component 2: Improved Sanitation Access:(Cost $15.00 M) Component 3: Project Management:(Cost $1.89 M) Component 4: Contingency Emergency Response Component (CERC) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Satisfactory Overall Implementation Progress (IP) -- Satisfactory Overall Risk Rating -- Substantial Implementation Status and Key Decisions The project was approved by the Board on October 10, 2019, and the agreements are expected to be signed in March 2020. The Project Implementation Unit (PIU) is in place at Eswatini Water Services Corporation. 12/17/2019 Page 1 of 6 The World Bank Implementation Status & Results Report Kingdom of Eswatini: Water Supply and Sanitation Access Project (P166697) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial -- Substantial Macroeconomic Substantial -- Substantial Sector Strategies and Policies Moderate -- Moderate Technical Design of Project or Program Moderate -- Moderate Institutional Capacity for Implementation and Sustainability Moderate -- Moderate Fiduciary Moderate -- Moderate Environment and Social Moderate -- Moderate Stakeholders Moderate -- Moderate Other Substantial -- Substantial Overall Substantial -- Substantial Results PDO Indicators by Objectives / Outcomes Increase access to improved water supply and sanitation services in targeted areas of Eswatini IN00779716 ►People provided with access to improved water sources (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 18,478.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 This indicator measures the cumulative number of people who benefited from improved water supply Comments: services that have been constructed through operations supported by the World Bank. IN00779717 People provided with access to improved water sources - Female (RMS requirement) (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 9,239.00 IN00779718 ►People provided with access to improved sanitation services (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 8,000.00 12/17/2019 Page 2 of 6 The World Bank Implementation Status & Results Report Kingdom of Eswatini: Water Supply and Sanitation Access Project (P166697) Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 The indicator measures the cumulative number of people who benefited from improved sanitation facilities Comments: that have been constructed through operations supported by the World Bank. IN00779719 People provided with access to improved sanitation services - Female (RMS requirement) (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 4,000.00 IN00779720 ►People reached through hygiene behavior awareness campaigns (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 38,233.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 The number of people in the project area that are reach through project financed hygiene behavior Comments: awareness campaigns Intermediate Results Indicators by Components Resillient Water Access and Management IN00779721 ►Schools provided with improved water access (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 32.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 Comments: Number of schools provided with improved water access through project financing IN00779723 ►Health centers provided with improved water access (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 4.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 Comments: Number of health centers provided with improved water access using project financing IN00779726 ►Length of water pipeline constructed (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 305.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 12/17/2019 Page 3 of 6 The World Bank Implementation Status & Results Report Kingdom of Eswatini: Water Supply and Sanitation Access Project (P166697) Comments: Number of km of water pipeline constructed using project financing. IN00779728 ►Develop and implement a drought monitoring and early warning system (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 Comments: A drought monitoring and early warning system is developed and implemented under the project. IN00779730 ►Women in the target area that spend 30 minutes or more to go to source of drinking water, get water and return (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 20.30 -- 20.30 10.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 Reduction in the percentage of women that spend 30 minutes or more to go to source of drinking water, Comments: get water and return. Baseline data from Multiple Indicator Cluster Survey, Central Statistics Office, 2014. Improved Sanitation Access IN00779722 ►Household containment facilities constructed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 2,000.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 Number of household containment facilities constructed using project financing or through household Comments: financing as a result of project activities. IN00779724 ►Sanitation facilities constructed in schools (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 32.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 Comments: Number of sanitation facilities constructed in schools under project financing IN00779727 ►Sanitation facilities constructed in health centers (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 4.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 Comments: Number of sanitation facilities constructed in health centers financed under the project. IN00779729 12/17/2019 Page 4 of 6 The World Bank Implementation Status & Results Report Kingdom of Eswatini: Water Supply and Sanitation Access Project (P166697) ►Reduction in open defecation (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 12.00 -- 12.00 0.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 Reduction in the percentage of people openly defecating in the project target areas. Baseline data from Comments: Multiple Indicator Cluster Survey, Central Statistics Office, 2014. IN00779731 ►Girls who benefited from having school sanitation with adequate WASH, MHM facilities and MHM education. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 2,800.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 Number of girls who benefited from having school sanitation with adequate WASH and MHM facilities constructed under the project. This specifically means: separate entrance for females, hooks, availability Comments: of MHM product disposal, availability of water and soap nearby, lockable doors and lighting. This will be complemented by MHM education campaigns. Project Management IN00779725 ►Grievances satisfactorily addressed with new grievance redress mechanism (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 100.00 Date 30-Sep-2019 -- 11-Dec-2019 30-Sep-2025 Percentage of grievances satisfactorily addressed with new grievance redress mechanism as proportion Comments: of total grievances received. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed Not P166697 IBRD-90120 USD 45.00 45.00 0.00 0.00 45.00 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P166697 IBRD-90120 10-Oct-2019 -- -- 30-Sep-2025 30-Sep-2025 Effective 12/17/2019 Page 5 of 6 The World Bank Implementation Status & Results Report Kingdom of Eswatini: Water Supply and Sanitation Access Project (P166697) Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/17/2019 Page 6 of 6