Procurement Plan General 1. Bank’s approval Date of the procurement Plan October 2, 2018 2. Date of General Procurement Notice: October 15, 2018 3. Period covered by this procurement plan: October 2018 to April, 2020 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: No. Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) All ≥3,000,000 2. NCB (Goods) All <3,000,000 3. ICB (Works) ≥15,000,000 All 4. NCB (Works) <15,000,000 All 5. (Non-Consultant Services) ≥1,500,000 All 2. Prequalification. Bidders when applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project GHANA PRODUCTIVE SAFETY NETS PROJECT 02/10/2018 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Estimated Domestic Review Ref. Description Cost Packages Preference by Bank Comments No. US$ million (yes/no) (Prior / Post) Summary of the NCB 1 (Goods) 900 2 None None Summary of the ICB 2 (Non-Consultant - None None None Services) Summary of the NCB 755 3 (Non-Consultant 2 None None Services) 4 Summary of the ICS 1926.6 18 None None (services) 5 Summary of the 153 2 None None SHOPPING (Goods) 6 Summary of the 268 3 None None SHOPPING (Non- consulting services) 7 Summary of LCS 660 9 None None (services) 8 Summary of the 400 1 None None QCBS(Works) 9 Summary of the 405 2 None None CQS(Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comment 1. Competitive Methods (Firms) ≥$500 2. Single Source (Firms) ≥$100 3. Individual ≥$200 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Assignment Estimated Review No. Cost Packages by Bank Comments US$ million (Prior / Post) Summary of number of 1 contracts that will be let 400 1 under QCBS Summary of number of 2 contracts that will be let 12,617 68 under other methods PROCUREMENT Ghana : Ghana Productive Safety Net Project PLAN General Information Country: Ghana Bank’s Approval Date of the Original Procurement Plan: 2018-10-05 2020-02-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164603 GPN Date: 2019-01-25 Project Name: Ghana Productive Safety Net Project Loan / Credit No: IDA / 63370, / Executing Agency(ies): Ministry of Local Government and Rural Development WORKS Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Loan / Credit Market Procurement Prequalificatio Process Prequalification Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification / Invitation Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-SAFETY NETS-141510-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Sabiye IDA / 63370 Intensive Public Works Post Open - National 34,945.00 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Junction-Wewa Feeder Program tion Road (5.0km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141511-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 120,665.61 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Widnaba GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141512-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 54,851.25 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Popolipo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141517-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 75,667.79 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Wasipe GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141518-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 59,985.50 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Zamwengo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141519-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 72,199.69 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Zamsa GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141520-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 108,730.59 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Bachonsa GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141528-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 82,054.66 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Kenkelle GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141530-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 78,848.22 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Touri GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141531-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 163,634.70 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Pialugu GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141533-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 80,873.92 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Duuri No. 1 GH-MLGRD-SAFETY NETS-141535-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 111,418.58 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Earth Dam at Mankuri- Program tion Kontwiri GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141536-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 157,419.56 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Berwong GH-MLGRD-SAFETY NETS-141537-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 119,719.04 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Earth Dam at Eremon Program tion Yagra GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141539-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 49,966.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Dabozesi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141541-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 95,332.89 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Katagri GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141542-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 40,046.38 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Kulsalboug GH-MLGRD-SAFETY NETS-141543-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 43,399.88 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Earth Dam at Soliga Program tion (Phase 2) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141544-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 137,274.20 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Loho GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141545-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 93,202.73 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Payani GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141548-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 80,514.88 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Ketuo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141553-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 72,727.27 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Zeng GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141554-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 50,546.08 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Wulensi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141556-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 105,304.11 0.00 Implementa Rehabilition of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Lingbinsi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141557-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 87,100.13 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Singa GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141563-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 99,420.20 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Nakpala GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141565-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 34,421.20 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Nakwabi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141566-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 94,187.67 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Gbeogo Page 1 GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141567-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 29,539.78 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Tindongo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141569-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 64,982.94 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Kunyabin GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141571-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 45,942.77 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Tousal GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141572-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 96,383.27 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Bosoyiri GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141573-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 36,837.91 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Meteo GH-MLGRD-SAFETY NETS-141575-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Ujoja- IDA / 63370 Intensive Public Works Post Open - National 52,178.67 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Ochadindo Feeder Road Program tion (3.1km) GH-MLGRD-SAFETY NETS-141577-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Bulingin- IDA / 63370 Intensive Public Works Post Open - National 58,037.06 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Kangba Feeder Road Program tion (4.0Km) GH-MLGRD-SAFETY NETS-141578-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Tampiem- IDA / 63370 Intensive Public Works Post Open - National 66,192.29 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Dandafuro Feeder Road Program tion (4.8Km) GH-MLGRD-SAFETY NETS-141579-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Dupari- IDA / 63370 Intensive Public Works Post Open - National 65,206.43 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Goripie Feeder Road Program tion (4.5Km) GH-MLGRD-SAFETY NETS-141582-CW-RFB / Component 2: Labor Pending Rehabilitation of Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 26,266.79 0.00 Implementa Woramponho Junction - Quotations One Envelope 31 05 05 04 08 06 Program tion Woramponho Feeder Road (1.8Km) GH-MLGRD-SAFETY NETS-141584-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Hani - IDA / 63370 Intensive Public Works Post Open - National 39,253.92 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Storage Facility Site Program tion Feeder Road (3.5Km) GH-MLGRD-SAFETY NETS-141586-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Sawia- IDA / 63370 Intensive Public Works Post Open - National 64,370.81 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Mempekasa Feeder Road Program tion (3.7Km) GH-MLGRD-SAFETY NETS-141588-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 15,812.00 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Mpentease - Akyease Program tion Feeder Road (1.0Km) GH-MLGRD-SAFETY NETS-141589-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Jelinkon IDA / 63370 Intensive Public Works Post Open - National 90,479.20 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 -Yoliyiri Feeder Road Program tion (6.3Km) GH-MLGRD-SAFETY NETS-141590-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Saboba IDA / 63370 Intensive Public Works Post Open - National 32,333.68 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 -Boagbaln Feeder Program tion Road(2.5km) GH-MLGRD-SAFETY NETS-141591-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Ziape - IDA / 63370 Intensive Public Works Post Open - National 44,113.54 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Kikayili Feeder Road Program tion (3.5Km) GH-MLGRD-SAFETY NETS-141592-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Srenoso IDA / 63370 Intensive Public Works Post Open - National 51,784.21 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 No. 1 - Bosomponso Program tion Feeder Road (4.2Km) GH-MLGRD-SAFETY NETS-141593-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 26,903.96 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Nyankoma Junction - Program tion Sawia Feeder Road (2.1Km) GH-MLGRD-SAFETY NETS-141594-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Mama IDA / 63370 Intensive Public Works Post Open - National 56,692.16 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Kura-Hundokope Feeder Program tion Road (4.0Km) GH-MLGRD-SAFETY NETS-141595-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 43,395.27 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Nyankpani-Wumbdoja Program tion Feeder Road (3.5Km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141600-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 65,124.02 0.00 Implementa Rehabilitation of Goziiri- Quotations One Envelope 31 05 05 04 08 06 Program tion Na-Ewini Feeder Road (4.0Km) GH-MLGRD-SAFETY NETS-141601-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Kaleo- IDA / 63370 Intensive Public Works Post Open - National 28,341.37 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Buoduori Feeder Road Program tion (1.2Km) GH-MLGRD-SAFETY NETS-141603-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Bareki - IDA / 63370 Intensive Public Works Post Open - National 70,025.00 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Gundork - Zanlerigu Program tion Feeder road (4.7km) GH-MLGRD-SAFETY NETS-141604-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Kikaayiri- IDA / 63370 Intensive Public Works Post Open - National 57,025.10 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Kpatorigu Feeder Program tion Road(3.8km) GH-MLGRD-SAFETY NETS-141606-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Nalogn- IDA / 63370 Intensive Public Works Post Open - National 49,257.92 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Nanpoado Feeder Road Program tion (3.5km) GH-MLGRD-SAFETY NETS-141607-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 40,641.08 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Kunyokuong-Metorbuo Program tion Feeder Road (3.0Km) GH-MLGRD-SAFETY NETS-141609-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Nkwanta IDA / 63370 Intensive Public Works Post Open - National 71,573.62 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Farm Jnc-Hiawoanwu Program tion Feeder Road (4.2km) GH-MLGRD-SAFETY NETS-141610-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Ziseri IDA / 63370 Intensive Public Works Post Open - National 65,457.63 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Jnc-Kumasung-Zari Market Program tion Feeder Road (5.0km) Page 2 GH-MLGRD-SAFETY NETS-141611-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Kpatinga IDA / 63370 Intensive Public Works Post Open - National 24,946.23 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 - Bugnaayilii Feeder Road Program tion (1.5km) GH-MLGRD-SAFETY NETS-141612-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Ul-Kpong- IDA / 63370 Intensive Public Works Post Open - National 68,952.78 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Deriyiiri Feeder Road Program tion (5.2Km) GH-MLGRD-SAFETY NETS-141614-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Monkrate IDA / 63370 Intensive Public Works Post Open - National 65,171.07 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Jnc-Monkrate Feeder Road Program tion (3.6Km) GH-MLGRD-SAFETY NETS-141615-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 73,919.68 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Ahiamankyene-Sabaja Program tion Feeder Road (3.5Km) GH-MLGRD-SAFETY NETS-141616-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Dika- IDA / 63370 Intensive Public Works Post Open - National 53,782.99 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Ahumansu Feeder Road Program tion (4.0Km) GH-MLGRD-SAFETY NETS-141619-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Boya- IDA / 63370 Intensive Public Works Post Open - National 65,369.07 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Adonsi-Adagbira Feeder Program tion Road (4.0km) GH-MLGRD-SAFETY NETS-141621-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Dole - IDA / 63370 Intensive Public Works Post Open - National 50,925.07 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Nokoyiiri Feeder Road Program tion (3.8Km) GH-MLGRD-SAFETY NETS-141622-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Sanabiisi IDA / 63370 Intensive Public Works Post Open - National 81,019.55 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 - Kabre- Akulyor Feeder Program tion road (5.6km) GH-MLGRD-SAFETY NETS-141623-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Pintengsa- IDA / 63370 Intensive Public Works Post Open - National 57,483.53 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Bachiesa Feeder Road Program tion (4.0km) GH-MLGRD-SAFETY NETS-141624-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Kpemale- IDA / 63370 Intensive Public Works Post Open - National 54,185.28 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Bandimsugru Feeder Program tion Road(3.5km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141625-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 41,304.39 0.00 Implementa Rehabilitation of Sheri- Quotations One Envelope 31 05 05 04 08 06 Program tion Kaliito Feeder Road(3.0km) GH-MLGRD-SAFETY NETS-141627-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Takyie - IDA / 63370 Intensive Public Works Post Open - National 67,000.95 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Toyempare Feeder Road Program tion (4.8Km) GH-MLGRD-SAFETY NETS-141628-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Kukua - IDA / 63370 Intensive Public Works Post Open - National 48,664.76 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Mabung Feeder Road Program tion (3.2Km) GH-MLGRD-SAFETY Component 2: Labor Under NETS-141859-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 153,400.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Nayorku GH-MLGRD-SAFETY Component 2: Labor Under NETS-141860-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 50,500.35 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Karimenga GH-MLGRD-SAFETY NETS-141861-CW-RFB / Component 2: Labor Under Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Walewale- IDA / 63370 Intensive Public Works Post Open - National 62,297.82 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Bugya Kura Feeder Road Program tion (4.4km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141862-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 140,965.24 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Nagbo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141864-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 154,203.63 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Sakogu GH-MLGRD-SAFETY NETS-141865-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Langbinsi- IDA / 63370 Intensive Public Works Post Open - National 55,623.62 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Bumboazio Feeder Road Program tion (3.5km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-141867-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 119,719.04 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Lam-Buu GH-MLGRD-SAFETY NETS-142616-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Kpemale- IDA / 63370 Intensive Public Works Post Open - National 54,185.27 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Bandimsugru Feeder Road Program tion (3.5km) GH-MLGRD-SAFETY Component 2: Labor Under NETS-142683-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 94,057.27 0.00 Implementa Rehabilitation of Pobikwaa- Quotations One Envelope 31 05 05 04 08 06 Program tion Annan Feeder Road (4.9km) GH-MLGRD-SAFETY NETS-142686-CW-RFB / Component 2: Labor Under Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Yehuno IDA / 63370 Intensive Public Works Post Open - National 68,148.53 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Junction-Yehuno Feeder Program tion Road (4.1km)68 GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142689-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 111,954.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Wenchiki GH-MLGRD-SAFETY NETS-142698-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Sangbana IDA / 63370 Intensive Public Works Post Open - National 45,081.54 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Jnc-Sangbana Feeder Road Program tion (2.0km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142699-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 95,285.04 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Namongo GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142701-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 116,579.99 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Mangor GH-MLGRD-SAFETY NETS-142702-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Naghan- IDA / 63370 Intensive Public Works Post Open - National 54,931.55 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Sangbani Feeder Road Program tion (3.6km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142710-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 30,574.81 0.00 Implementa Rehabilitation of Dingoni Quotations One Envelope 31 05 05 04 08 06 Program tion Feeder Road (1.5Km) Page 3 GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142711-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 5,371,596.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Nakpayili GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142713-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 77,212.79 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Banda GH-MLGRD-SAFETY NETS-142716-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 51,368.34 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Abrewankor-Konkonbaline Program tion Feeder Road (3.6Km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142718-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 88,215.31 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Arizeem GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142720-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 70,119.89 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Yakin GH-MLGRD-SAFETY NETS-142722-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Mognori - IDA / 63370 Intensive Public Works Post Open - National 73,589.93 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Tampizua -Bador- Program tion Gomoluka Feeder Road (5.1km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142724-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 89,489.37 0.00 Implementa Rehabilitation of Earth Quotations One Envelope 31 05 05 04 08 06 Program tion Dams at Kumpalgunga GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142727-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 126,600.27 0.00 Implementa Rehabilitation of Earth Quotations One Envelope 31 05 05 04 08 06 Program tion Dams at Narango GH-MLGRD-SAFETY NETS-142735-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Ayumsey- IDA / 63370 Intensive Public Works Post Open - National 136,810.72 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Tabiugu Feeder Road Program tion (3.7KM) GH-MLGRD-SAFETY NETS-142738-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 136,810.72 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Earth Dam at Kadema- Program tion Kpikpaluk (Agbanlong) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142739-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 108,730.58 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Bachonsa GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142742-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 94,010.68 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Yariga GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142745-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 79,393.11 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Votukom GH-MLGRD-SAFETY NETS-142749-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 56,272.72 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Sianongo-Tesnatinga Program tion Feeder Road (3.56km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142751-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 96,587.89 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Bugpiigu GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142752-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 90,797.60 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Kugasheigu GH-MLGRD-SAFETY NETS-142757-CW-RFB / Component 2: Labor Pending Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Gagbiri IDA / 63370 Intensive Public Works Post Open - National 69,016.71 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Market -Central Mosque Program tion Feeder Road (5.0km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142758-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 85,691.72 0.00 Implementa Rehabilitation of Nabaala- Quotations One Envelope 31 05 05 04 08 06 Program tion Billaw Feeder Road (4.5Km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142760-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 150,741.49 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Nankpawie GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142762-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 76,578.39 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Nmanduanu GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142766-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 178,516.42 0.00 Implementa Rehabilitation of Small Quotations One Envelope 31 05 05 04 08 06 Program tion Earth Dam at Kunkorgu GH-MLGRD-SAFETY Component 2: Labor Pending NETS-142768-CW-RFB / Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 63370 Intensive Public Works Post Open - National 82,096.24 0.00 Implementa Rehabilitation of Gbaal- Quotations One Envelope 31 05 05 04 08 06 Program tion Kuni Feeder Road (4.8Km) GH-MLGRD-SAFETY NETS-142769-CW-RFB / Component 2: Labor Under Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Logba- IDA / 63370 Intensive Public Works Post Open - National 31,485.81 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Akusane-Horglikope Feeder Program tion Road (5.0km) GH-MLGRD-SAFETY NETS-142776-CW-RFB / Component 2: Labor Under Request for Single Stage - 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- Rehabilitation of Tsrinorni- IDA / 63370 Intensive Public Works Post Open - National 69,701.77 0.00 Implementa Quotations One Envelope 31 05 05 04 08 06 Kesenyemito Feeder Road Program tion (4.2km) GH-MLGRD-SAFETY NETS-146719-CW-FCA / Component 2: Labor Community Under Rehabilitation of 15ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 73,702.36 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Nindowala GH-MLGRD-SAFETY NETS-146726-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 60,000.00 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Nanyili GH-MLGRD-SAFETY NETS-146889-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 74,163.96 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Mamakora GH-MLGRD-SAFETY NETS-146894-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 61,456.55 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Sabare GH-MLGRD-SAFETY NETS-146895-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 77,191.82 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees including nursery at Sheini Page 4 GH-MLGRD-SAFETY NETS-146716-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 97,742.36 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Saamanpo GH-MLGRD-SAFETY NETS-146725-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees including nursery at Kaleo GH-MLGRD-SAFETY NETS-146729-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Kokoligu Gbantakuuri GH-MLGRD-SAFETY NETS-146736-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 55,951.45 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Kokoligu Bekyiinteng GH-MLGRD-SAFETY NETS-146722-CW-FCA / Component 2: Labor Community Under Rehabilitation of 15ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 77,742.36 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees including nursery at Sentu GH-MLGRD-SAFETY NETS-146750-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Wellembelle GH-MLGRD-SAFETY NETS-146754-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 50,951.45 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Sorbelle GH-MLGRD-SAFETY NETS-146783-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded community land IDA / 63370 Intensive Public Works Post Driven Direct 65,112.15 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Soe- Ayelbia GH-MLGRD-SAFETY NETS-146749-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees including nursery at Saru GH-MLGRD-SAFETY NETS-146748-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 54,878.73 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Yipala GH-MLGRD-SAFETY NETS-146759-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 65,524.18 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Nyandema GH-MLGRD-SAFETY NETS-146763-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 80,636.18 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees including nursery at Busa GH-MLGRD-SAFETY NETS-146764-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 55,951.45 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Nakore GH-MLGRD-SAFETY NETS-146765-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 80,636.18 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees including nursery at Ga GH-MLGRD-SAFETY NETS-146768-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 55,951.45 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Bankpama GH-MLGRD-SAFETY NETS-146724-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Kumasaal GH-MLGRD-SAFETY NETS-146760-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 97,742.36 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Buffiama GH-MLGRD-SAFETY NETS-146789-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 8ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 45,112.15 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Chuchuliga-Awenaguuk GH-MLGRD-SAFETY NETS-146793-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 77,164.91 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Naadema GH-MLGRD-SAFETY NETS-146810-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 86,120.18 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Nayorku GH-MLGRD-SAFETY NETS-146862-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 71,318.18 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Yishielanyili GH-MLGRD-SAFETY NETS-146799-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 5ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 52,373.45 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees including nursery at Jakpa GH-MLGRD-SAFETY NETS-146816-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 50,767.73 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Yahyayilli Page 5 GH-MLGRD-SAFETY NETS-146761-CW-FCA / Component 2: Labor Community Under Rehabilitation of 15ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 73,702.36 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Katua GH-MLGRD-SAFETY NETS-146811-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 70,969.27 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Tamaklan GH-MLGRD-SAFETY NETS-146813-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 60,969.27 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Fufulso GH-MLGRD-SAFETY NETS-146856-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 72,112.15 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Yikurugu GH-MLGRD-SAFETY NETS-146863-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 58,258.18 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Kutung GH-MLGRD-SAFETY NETS-146867-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 72,586.18 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Mango fruit trees at Ayirafie GH-MLGRD-SAFETY NETS-146869-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 72,552.00 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Monkrate GH-MLGRD-SAFETY NETS-146871-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 73,643.09 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion incluing nursery at Ahiamankyene GH-MLGRD-SAFETY NETS-146874-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 75,369.64 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Bejamse GH-MLGRD-SAFETY NETS-146875-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 55,353.27 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Beposo GH-MLGRD-SAFETY NETS-146880-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 55,353.27 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Grubi GH-MLGRD-SAFETY NETS-146885-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 77,361.73 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Nakpayili GH-MLGRD-SAFETY NETS-146886-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 55,484.09 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Tampoaya GH-MLGRD-SAFETY NETS-146887-CW-FCA / Component 2: Labor Community Under Rehabilitation of 20ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 95,597.82 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees including nursery at Pabila GH-MLGRD-SAFETY NETS-146888-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 20ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 68,278.12 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Teak woodlot trees at Damanko & Abunyanya GH-MLGRD-SAFETY NETS-146746-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Sinsina GH-MLGRD-SAFETY NETS-146751-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 97,742.36 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees including nursery at Bullu GH-MLGRD-SAFETY NETS-146769-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 70,951.45 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Kuka-Zuli GH-MLGRD-SAFETY NETS-146773-CW-FCA / Component 2: Labor Community Under Rehabilitation of 8ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 43,746.33 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Kamega GH-MLGRD-SAFETY NETS-146782-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 8ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 43,746.33 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Feo - Asebre GH-MLGRD-SAFETY NETS-146779-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 65,112.15 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Yikurugu GH-MLGRD-SAFETY NETS-146873-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 51,530.18 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Coconut fruit trees at Kadentwe & Nkatinkon GH-MLGRD-SAFETY NETS-146893-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 73,994.00 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Mogneigu Page 6 GH-MLGRD-SAFETY NETS-146792-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 65,112.15 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Sandema -Kori GH-MLGRD-SAFETY NETS-146806-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 8 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 75,112.15 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees including nursery at Gbeogo GH-MLGRD-SAFETY NETS-146794-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 55,524.18 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Nyandema GH-MLGRD-SAFETY NETS-146795-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 8ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 43,746.33 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Kpemale GH-MLGRD-SAFETY NETS-146796-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 65,112.15 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Kpentaung GH-MLGRD-SAFETY NETS-146798-CW-FCA / Rehabilitation of 5ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 52,373.45 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Nansoni GH-MLGRD-SAFETY NETS-146802-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 77,164.91 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Kubugu GH-MLGRD-SAFETY NETS-146809-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 83,940.55 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Bulbia GH-MLGRD-SAFETY NETS-146866-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 74,283.64 0.00 Implementa degraded land using 24 29 02 31 Program Development tion Mango fruit trees at Atsigode GH-MLGRD-SAFETY NETS-146882-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 85,426.91 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Ahiamansu GH-MLGRD-SAFETY NETS-146890-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 51,815.05 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Wui GH-MLGRD-SAFETY NETS-146897-CW-FCA / Component 2: Labor Community Under Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 60,850.73 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Mbowura GH-MLGRD-SAFETY NETS-146803-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 55,524.18 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Loagri GH-MLGRD-SAFETY NETS-146814-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 75,767.73 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Mbawupe GH-MLGRD-SAFETY NETS-146864-CW-FCA / Component 2: Labor Community Pending 2019-12- 2019-12- 2020-02- 2022-12- Rehabilitation of 10ha IDA / 63370 Intensive Public Works Post Driven Direct 61,318.18 0.00 Implementa 24 29 02 31 degraded land using Program Development tion Cashew fruit trees at Salaa GH-MLGRD-SAFETY NETS-146884-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 76,869.64 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Tampion GH-MLGRD-SAFETY NETS-146896-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 65,850.73 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Malando GH-MLGRD-SAFETY NETS-146704-CW-FCA / Rehabilitation of 10ha Component 2: Labor Community Pending 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 80,000.00 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Sornyo GH-MLGRD-SAFETY NETS-146711-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 60,000.00 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Kojokpere GH-MLGRD-SAFETY NETS-146717-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 97,742.36 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Balanta GH-MLGRD-SAFETY NETS-146723-CW-FCA / Component 2: Labor Community Under Rehabilitation of 15ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 73,702.36 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Billow GH-MLGRD-SAFETY NETS-146891-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 15ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 79,749.45 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees including nursery at Kunjuli GH-MLGRD-SAFETY NETS-146892-CW-FCA / Component 2: Labor Community Under Rehabilitation of 15ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 77,393.09 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Sobiba Page 7 GH-MLGRD-SAFETY NETS-146800-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 84,369.64 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Wundua GH-MLGRD-SAFETY NETS-146808-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 72,437.82 0.00 Implementa 24 29 02 31 using Mango fruit trees Program Development tion including nursery at Benwoko GH-MLGRD-SAFETY NETS-146801-CW-FCA / Rehabilitation of 15ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 81,634.36 0.00 Implementa 24 29 02 31 using Teak woodlot trees Program Development tion including nursery at Namangu GH-MLGRD-SAFETY NETS-146804-CW-FCA / Rehabilitation of 8ha Component 2: Labor Community Under 2019-12- 2019-12- 2020-02- 2022-12- degraded communal land IDA / 63370 Intensive Public Works Post Driven Direct 65,112.15 0.00 Implementa 24 29 02 31 using Cashew fruit trees Program Development tion including nursery at Dasabligo GH-MLGRD-SAFETY NETS-146805-CW-FCA / Component 2: Labor Community Under Rehabilitation of 8ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 53,746.33 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Kparikpii GH-MLGRD-SAFETY NETS-146707-CW-FCA / Component 2: Labor Community Pending Rehabilitation of 10ha 2019-12- 2019-12- 2020-02- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 60,000.00 0.00 Implementa degraded communal land 24 29 02 31 Program Development tion using Cashew fruit trees at Kakiase GH-MLGRD-SAFETY NETS-152499-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 96,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Earth Dam at Adaklu Program tion Torda GH-MLGRD-SAFETY Component 2: Labor Under NETS-152500-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 93,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Sofa GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152501-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 103,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Vakpo Korda GH-MLGRD-SAFETY Component 2: Labor Under NETS-152502-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 104,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Deve GH-MLGRD-SAFETY Component 2: Labor Under NETS-152503-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 106,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Bawakope GH-MLGRD-SAFETY Component 2: Labor Under NETS-152504-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 105,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Akorsu GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152505-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 51,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Nyantang GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152506-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 175,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Gbirigi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152507-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 64,000.00 0.00 Implementa Rehabilitation of 1No. Quotations One Envelope 10 15 14 15 19 31 Program tion Small Earth Dam at Bau GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152508-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 130,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Bambuli GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152512-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 170,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Sia-Kura GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152513-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 104,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Salankpan GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152514-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 72,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Tijo GH-MLGRD-SAFETY NETS-152515-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 120,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Earth Dam at Nanton- Program tion Kurugu GH-MLGRD-SAFETY NETS-152516-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 135,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Earth Dam at Nayili Program tion Sachedo GH-MLGRD-SAFETY NETS-152518-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of Small IDA / 63370 Intensive Public Works Post Open - National 85,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 earth dam at Nakpali Program tion Tindang GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152519-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 145,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Nahoyili GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152520-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 86,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Nakpaboari GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152521-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 58,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Kabrono GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152522-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 116,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Chokosi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152523-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 105,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Yabraso GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152524-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 120,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Degedege GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152525-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 61,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Mansin Page 8 GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152526-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 106,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 10 15 14 15 19 31 Program tion Earth Dam at Nsesreso GH-MLGRD-SAFETY NETS-152527-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 110,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Dzolopuita-Gbedome Program tion Feeder Road (6.5km) GH-MLGRD-SAFETY Component 2: Labor Under NETS-152528-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 80,000.00 0.00 Implementa Rehabilitation of Hehekpoe- Quotations One Envelope 10 15 14 15 19 31 Program tion Waya Feeder Road (4.0km) GH-MLGRD-SAFETY NETS-152529-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of Kwame IDA / 63370 Intensive Public Works Post Open - National 87,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Ntow-Apenteng Feeder Program tion Road (4.5km) GH-MLGRD-SAFETY NETS-152530-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of Dukuma IDA / 63370 Intensive Public Works Post Open - National 60,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Tsrukpe-Zanuta Feeder Program tion Road (4.6km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152531-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 80,000.00 0.00 Implementa Rehabilitation of Adwofo- Quotations One Envelope 10 15 14 15 19 31 Program tion Gyateh Feeder Road (4.1km) GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152532-CW-RFQ / Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 48,000.00 0.00 Implementa Rehabilitation of Eyisam- Quotations One Envelope 10 15 14 15 19 31 Program tion Engow Feeder Road (3.1km) GH-MLGRD-SAFETY NETS-152534-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of Mota Jnc- IDA / 63370 Intensive Public Works Post Open - National 71,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Mota Sasu Feeder Road Program tion (4.0km) GH-MLGRD-SAFETY NETS-152535-CW-RFQ / Component 2: Labor Under Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of Ayiwata- IDA / 63370 Intensive Public Works Post Open - National 75,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Ayawa-Wuxor Feeder Road Program tion (3.5km) GH-MLGRD-SAFETY NETS-152536-CW-RFQ / Component 2: Labor Under Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of Doffor IDA / 63370 Intensive Public Works Post Open - National 53,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Jnc.-Doffor & Others Program tion Feeder Road (3.5km) GH-MLGRD-SAFETY NETS-152537-CW-RFQ / Component 2: Labor Under Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of Trawa- IDA / 63370 Intensive Public Works Post Open - National 60,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Trawa Junc. Feeder Road Program tion (4.0km) GH-MLGRD-SAFETY NETS-152538-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of Nadigu- IDA / 63370 Intensive Public Works Post Open - National 64,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Digu-Zali-Dubilagbini Program tion Feeder Road (5.0Km) GH-MLGRD-SAFETY NETS-152539-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 38,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Kyeremasu-Kofibour Program tion Feeder Road (3.4Km) GH-MLGRD-SAFETY NETS-152540-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 32,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Sunurososo-Okyerekrom Program tion Feeder Road (1.9Km) GH-MLGRD-SAFETY NETS-152543-CW-RFQ / Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2022-12- Rehabilitation of IDA / 63370 Intensive Public Works Post Open - National 58,000.00 0.00 Implementa Quotations One Envelope 10 15 14 15 19 31 Asempanaye-Yawben Program tion Feeder Road (4.0km) GH-MLGRD-SAFETY NETS-156251-CW-CDD / Rehabilitation of fifteen Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- (15) ha degraded IDA / 63370 Intensive Public Works Post Driven Direct 53,000.00 0.00 Implementa 21 26 01 31 communal land using Program Development tion Cashew trees including 200,000 seedling nursery at Biema GH-MLGRD-SAFETY NETS-156252-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 30,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Boase GH-MLGRD-SAFETY NETS-156255-CW-CDD / Rehabilitation of fifteen Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- (15) ha degraded IDA / 63370 Intensive Public Works Post Driven Direct 53,000.00 0.00 Implementa 21 26 01 31 communal land using Program Development tion Grafted Mango trees including 12,000 seedling nursery at Nyire GH-MLGRD-SAFETY NETS-156256-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 33,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Grafted Mango trees at Wewa GH-MLGRD-SAFETY NETS-156257-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 28,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Kojie-Dumoli GH-MLGRD-SAFETY NETS-156259-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 45,000.00 0.00 Implementa 21 26 01 31 land using Cashew trees Program Development tion including 150,000 seedling nursery at Anyinasu GH-MLGRD-SAFETY NETS-156260-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 45,000.00 0.00 Implementa 21 26 01 31 land using Cashew trees Program Development tion including 140,000 seedling nursery at Frante GH-MLGRD-SAFETY NETS-156261-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 35,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Babaso GH-MLGRD-SAFETY NETS-156264-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 32,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Kasei GH-MLGRD-SAFETY NETS-156265-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 32,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Sekyedumasi GH-MLGRD-SAFETY NETS-156266-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 45,000.00 0.00 Implementa 21 26 01 31 land using Cashew trees Program Development tion including 200,000 seedling nursery at Afrancho Page 9 GH-MLGRD-SAFETY NETS-156267-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 32,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Akumadan GH-MLGRD-SAFETY NETS-156268-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 32,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Darso GH-MLGRD-SAFETY NETS-156272-CW-CDD / Component 2: Labor Community Pending Rehabilitation of Seven (7) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 24,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Nkenkesu GH-MLGRD-SAFETY NETS-156273-CW-CDD / Rehabilitation of five (5) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 29,000.00 0.00 Implementa 21 26 01 31 land using Cashew trees Program Development tion including 100,000 seedling nursery at Kwaman GH-MLGRD-SAFETY NETS-156275-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 16,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Birem GH-MLGRD-SAFETY NETS-156276-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 16,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Balana GH-MLGRD-SAFETY NETS-156277-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 16,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Asubuaso GH-MLGRD-SAFETY NETS-156278-CW-CDD / Rehabilitation of thirty Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- (30) ha degraded IDA / 63370 Intensive Public Works Post Driven Direct 88,000.00 0.00 Implementa 21 26 01 31 communal land using Program Development tion Cashew trees including 200,000 seedling nursery at Dagomba GH-MLGRD-SAFETY NETS-156280-CW-CDD / Component 2: Labor Community Pending Rehabilitation of twenty 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 65,000.00 0.00 Implementa five (25) ha degraded 21 26 01 31 Program Development tion communal land using Cashew trees at Anyinoffi GH-MLGRD-SAFETY NETS-156281-CW-CDD / Rehabilitation of four (4) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 19,000.00 0.00 Implementa 21 26 01 31 land using Cashew trees Program Development tion including 40,000 seedling nursery at Tainoso Badu GH-MLGRD-SAFETY NETS-156283-CW-CDD / Component 2: Labor Community Pending Rehabilitation of four (4) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 13,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Tainoso Seikwa GH-MLGRD-SAFETY NETS-156284-CW-CDD / Rehabilitation of five (5) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 21,000.00 0.00 Implementa 21 26 01 31 land using Oil Palm trees Program Development tion including 5,000 seedling nursery at Dwomo GH-MLGRD-SAFETY NETS-156285-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 18,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Oil Palm trees at Derma GH-MLGRD-SAFETY NETS-156286-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 18,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Oil Palm trees at Tweapease GH-MLGRD-SAFETY NETS-156288-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 20,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Coconut trees at Kwasu GH-MLGRD-SAFETY NETS-156289-CW-CDD / Rehabilitation of five (5) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 22,500.00 0.00 Implementa 21 26 01 31 land using Coconut trees Program Development tion including 5,000 seedling nursery at Mansin GH-MLGRD-SAFETY NETS-156290-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 40,000.00 0.00 Implementa 21 26 01 31 land using Cashew trees Program Development tion including 150,000 seedling nursery at Mewerenfiriwo GH-MLGRD-SAFETY NETS-156291-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 28,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Baahkurom GH-MLGRD-SAFETY NETS-156292-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 16,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Asuotiano GH-MLGRD-SAFETY NETS-156294-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 16,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Akontanim GH-MLGRD-SAFETY NETS-156295-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 37,000.00 0.00 Implementa 21 26 01 31 land using Oil Palm trees Program Development tion including 20,000 seedling nursery at Akrofonso GH-MLGRD-SAFETY NETS-156296-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 36,000.00 0.00 Implementa 21 26 01 31 land using Oil Palm trees Program Development tion including 20,000 seedling nursery at Nyamedom GH-MLGRD-SAFETY NETS-156298-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 33,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Oil Palm trees at Betinko Page 10 GH-MLGRD-SAFETY NETS-156299-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 33,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Oil Palm trees at Boagya GH-MLGRD-SAFETY NETS-156301-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 34,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Oil Palm trees at Okyerekrom GH-MLGRD-SAFETY NETS-156305-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 67,000.00 0.00 Implementa 21 26 01 31 land using Rubber trees Program Development tion including 30,000 seedling nursery at Anakum GH-MLGRD-SAFETY NETS-156306-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 68,000.00 0.00 Implementa 21 26 01 31 land using Rubber trees Program Development tion including 30,000 seedling nursery at Dominase GH-MLGRD-SAFETY NETS-156308-CW-CDD / Component 2: Labor Community Pending Rehabilitation of seven (7) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 44,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Rubber trees at Ayinbrem GH-MLGRD-SAFETY NETS-156309-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 34,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Rubber trees at Sompre GH-MLGRD-SAFETY NETS-156310-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 35,000.00 0.00 Implementa 21 26 01 31 land using Oil Palm trees Program Development tion including 20,000 seedling nursery at Ayiem GH-MLGRD-SAFETY NETS-156311-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 50,000.00 0.00 Implementa 21 26 01 31 land using Cocoa trees Program Development tion including 20,000 seedling nursery at Tumantu GH-MLGRD-SAFETY NETS-156312-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 18,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Oil Palm trees at Obrayebona GH-MLGRD-SAFETY NETS-156313-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 18,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Oil Palm trees at Sentiaw GH-MLGRD-SAFETY NETS-156315-CW-CDD / Rehabilitation of fifteen Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- (15) ha degraded IDA / 63370 Intensive Public Works Post Driven Direct 58,000.00 0.00 Implementa 21 26 01 31 communal land using Program Development tion Coconut trees including 20,000 seedling nursery at Krayawkrom GH-MLGRD-SAFETY NETS-156316-CW-CDD / Component 2: Labor Community Pending Rehabilitation of fifteen 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 50,000.00 0.00 Implementa (15) ha degraded 21 26 01 31 Program Development tion communal land using Coconut trees at Attaboka GH-MLGRD-SAFETY NETS-156317-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 35,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Coconut trees at Kwafuakaa GH-MLGRD-SAFETY NETS-156320-CW-CDD / Rehabilitation of fifteen Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- (15) ha degraded IDA / 63370 Intensive Public Works Post Driven Direct 55,000.00 0.00 Implementa 21 26 01 31 communal land using Program Development tion Cashew trees including 200,000 seedling nursery at Gambia GH-MLGRD-SAFETY NETS-156321-CW-CDD / Component 2: Labor Community Pending Rehabilitation of fifteen 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 40,000.00 0.00 Implementa (15) ha degraded 21 26 01 31 Program Development tion communal land using Cashew treesat Wamahinso GH-MLGRD-SAFETY NETS-156323-CW-CDD / Rehabilitation of twenty Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- (20) ha degraded IDA / 63370 Intensive Public Works Post Driven Direct 73,000.00 0.00 Implementa 21 26 01 31 communal land using Program Development tion Cashew trees including 200,000 seedling nursery at Mansie GH-MLGRD-SAFETY NETS-156324-CW-CDD / Rehabilitation of twenty Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- (20) ha degraded IDA / 63370 Intensive Public Works Post Driven Direct 71,000.00 0.00 Implementa 21 26 01 31 communal land using Program Development tion Mango trees including 20,000 seedling nursery at Mo Nkwanta GH-MLGRD-SAFETY NETS-156325-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 40,000.00 0.00 Implementa 21 26 01 31 land using Cashew trees Program Development tion including 100,000 seedling nursery at Timeabu GH-MLGRD-SAFETY NETS-156326-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 40,000.00 0.00 Implementa 21 26 01 31 land using Cashew trees Program Development tion including 100,000 seedling nursery at Yefri GH-MLGRD-SAFETY NETS-156328-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 28,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Dinkra GH-MLGRD-SAFETY NETS-156329-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 30,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Pienyina GH-MLGRD-SAFETY NETS-156330-CW-CDD / Rehabilitation of ten (10) Component 2: Labor Community Pending ha degraded communal 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 41,000.00 0.00 Implementa land using Cashew trees 21 26 01 31 Program Development tion including 200,000 seedling nursery at Damang Nkwanta Page 11 GH-MLGRD-SAFETY NETS-156332-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 16,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Kamapa GH-MLGRD-SAFETY NETS-156333-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 16,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Komfourkrom GH-MLGRD-SAFETY NETS-156334-CW-CDD / Rehabilitation of five (5) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 28,000.00 0.00 Implementa 21 26 01 31 land using Cashew trees Program Development tion including 100,000 seedling nursery at Asuoso GH-MLGRD-SAFETY NETS-156335-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 15,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Bodinka Beposo GH-MLGRD-SAFETY NETS-156337-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 28,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Chaboba GH-MLGRD-SAFETY NETS-156338-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 18,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Deiffour GH-MLGRD-SAFETY NETS-156340-CW-CDD / Rehabilitation of Ten (10) Component 2: Labor Community Pending 2020-02- 2020-02- 2020-04- 2022-12- ha degraded communal IDA / 63370 Intensive Public Works Post Driven Direct 40,000.00 0.00 Implementa 21 26 01 31 land using Cashew trees Program Development tion including 200,000 seedling nursery at Nchiraa GH-MLGRD-SAFETY NETS-156341-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 16,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Koase GH-MLGRD-SAFETY NETS-156342-CW-CDD / Component 2: Labor Community Pending Rehabilitation of five (5) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 16,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Subinso No.2 GH-MLGRD-SAFETY NETS-156343-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 28,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Tremoso GH-MLGRD-SAFETY NETS-156344-CW-CDD / Component 2: Labor Community Pending Rehabilitation of ten (10) 2020-02- 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Driven Direct 28,000.00 0.00 Implementa ha degraded communal 21 26 01 31 Program Development tion land using Cashew trees at Akrobi GH-MLGRD-SAFETY Component 2: Labor Pending NETS-156345-CW-RFQ / Request for Single Stage - 2020-02- 2020-04- 2022-12- IDA / 63370 Intensive Public Works Post Open - National 90,000.00 0.00 Implementa Rehabilitation of Small Quotations One Envelope 26 22 31 Program tion Earth Dam at Kapariyiri GOODS Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Loan / Credit Market Procurement Prequalificatio Process Prequalification Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification / Invitation Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-SAFETY Component 5: Project NETS-80531-GO-RFB / Under Management, Request for Single Stage - 2019-10- 2019-10- 2019-11- 2019-12- 2020-01- 2020-05- Procurement of 8 No. 4X4 IDA / 63370 Post Open - National 360,000.00 0.00 Implementa Coordination, and Bids One Envelope 04 09 20 20 24 23 Vehicles for LIPW and PI tion Capacity Building monitoring activities GH-MLGRD-SAFETY NETS-80528-GO-RFB / Under Supply of 170No. all- Component 1: Productive Request for Single Stage - 2019-10- 2019-10- 2019-11- 2019-12- 2020-01- 2020-04- IDA / 63370 Post Open - National 216,363.64 0.00 Implementa terrain Motorbikes for Inclusion Bids One Envelope 04 09 20 20 24 23 tion LIPW and PI Monitoring and Supervision activities GH-MLGRD-SAFETY Component 5: Project NETS-80524-GO-RFQ / Under Management, Request for Single Stage - 2019-10- 2019-12- 2020-01- Procurement of 35No. IDA / 63370 Post Open - National 26,000.00 0.00 Implementa Coordination, and Quotations One Envelope 09 04 18 Laptops and 10No. tion Capacity Building Desktops +UPS GH-MLGRD-SAFETY NETS-80525-GO-RFQ / Procurement of 5No. Component 5: Project Photocopiers, 4No. Pending Management, Request for Single Stage - 2019-12- 2020-02- 2020-03- projectors with screen, IDA / 63370 Post Limited 7,864.00 0.00 Implementa Coordination, and Quotations One Envelope 11 05 21 5No. Digital and Video tion Capacity Building Camera & LCD and 2 No. Drones for RDCU and Zonal Offices. GH-MLGRD-SAFETY NETS-80535-GO-RFB / Component 2: Labor Under Procurement of 100 Request for Single Stage - 2019-10- 2019-10- 2019-11- 2019-12- 2020-01- 2020-04- IDA / 63370 Intensive Public Works Post Open - National 25,090.91 0.00 Implementa Tablets and Biometric Bids One Envelope 04 09 20 20 24 23 Program tion Scanners for capturing LIPW Daily Work Attendance GH-MLGRD-SAFETY NETS-146899-GO-RFQ / Component 2: Labor Under Procurement of 460 Request for Single Stage - 2019-12- 2020-02- 2020-04- IDA / 63370 Intensive Public Works Post Limited 190,000.00 0.00 Implementa Tablets with Biometric Quotations One Envelope 25 19 15 Program tion Scanners for capturing LIPW Daily Work Attendance GH-MLGRD-SAFETY NETS-146900-GO-RFQ / Under Procurement of 1 No. HP Component 1: Productive Request for Single Stage - 2019-12- 2020-02- 2020-04- IDA / 63370 Post Limited 12,000.00 0.00 Implementa Server to Host GMISPro, Inclusion Quotations One Envelope 25 19 15 tion E-Dash, PI System application software and database GH-MLGRD-SAFETY Component 2: Labor Pending Request for Single Stage - 2020-02- 2020-04- 2020-07- NETS-156244-GO-RFQ / IDA / 63370 Intensive Public Works Post Limited 78,000.00 0.00 Implementa Quotations One Envelope 26 22 21 Supply of Wellington Program tion Boots GH-MLGRD-SAFETY Component 2: Labor Pending NETS-156248-GO-RFQ / Request for Single Stage - 2020-02- 2020-04- 2020-07- IDA / 63370 Intensive Public Works Post Limited 90,000.00 0.00 Implementa Supply of Viable Quotations One Envelope 26 22 21 Program tion Polyclonal Cashew Seeds GH-MLGRD-SAFETY Component 2: Labor Pending Request for Single Stage - 2020-01- 2020-03- 2020-06- NETS-152542-GO-RFQ / IDA / 63370 Intensive Public Works Post Limited 50,000.00 0.00 Implementa Quotations One Envelope 15 11 09 Supply of Poly Sheets and Program tion Shade Nets GH-MLGRD-SAFETY Component 2: Labor Pending NETS-152541-GO-RFQ / Request for Single Stage - 2020-01- 2020-03- 2020-06- IDA / 63370 Intensive Public Works Post Limited 82,000.00 0.00 Implementa Supply of Poly Pots for Quotations One Envelope 15 11 09 Program tion Cashew Seedlings Production. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Loan / Credit Market Procurement Prequalificatio Process Prequalification Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification / Invitation Award Page 12 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-SAFETY Component 5: Project NETS-80514-NC-DIR / Pending Management, 2019-10- 2019-10- 2019-11- 2020-02- Procurement of Service IDA / 63370 Post Direct Selection Direct 10,000.00 0.00 Implementa Coordination, and 15 20 24 24 Provider to migrate from tion Capacity Building ACCPAC to GIFMIS GH-MLGRD-SAFETY Pending NETS-80518-NC-DIR / Component 1: Productive 2019-10- 2019-10- 2019-11- 2020-02- IDA / 63370 Post Direct Selection Direct 30,000.00 0.00 Implementa Service Provider for Inclusion 15 20 24 22 tion Upgrading & Maintenance of GMIS-Pro GH-MLGRD-SAFETY NETS-80521-NC-DIR / Service Provider to Component 2: Labor Pending 2019-10- 2019-10- 2019-11- 2020-02- upgrade and integrate IDA / 63370 Intensive Public Works Post Direct Selection Direct 15,000.00 0.00 Implementa 15 20 24 22 Electronic Work Program tion Attendance Management System ( e-DASH) into GMIS Pro GH-MLGRD-SAFETY Component 5: Project Pending NETS-80522-NC-DIR / Management, 2019-10- 2019-10- 2019-11- 2021-05- IDA / 63370 Post Direct Selection Direct 15,000.00 0.00 Implementa Sharepoint Server Coordination, and 18 23 27 14 tion configuration Email Capacity Building hosting with NITA GH-MLGRD-SAFETY NETS-80517-NC-RFB / Component 1: Productive Request for Single Stage - 2019-10- 2019-12- 2021-05- IDA / 63370 Post Limited 72,000.00 0.00 Canceled Selection of Service Inclusion Quotations One Envelope 09 04 27 Provider for LIPW and PI E-Payment Services GH-MLGRD-SAFETY NETS-146208-NC-DIR / Component 1: Productive 2019-11- 2019-12- 2020-01- 2020-07- Selection of Service IDA / 63370 Prior Direct Selection Direct 72,000.00 0.00 Canceled Inclusion 29 04 08 06 Provider for LIPW, LEAP and PI E-Payment Services GH-MLGRD-SAFETY NETS-160575-NC-DIR / Pending Component 1: Productive 2020-02- 2020-03- 2020-04- 2022-12- Selection of Service IDA / 63370 Prior Direct Selection Direct 900,000.00 0.00 Implementa Inclusion 28 04 08 31 Provider for LIPW, LEAP tion and PI E-Payment Services CONSULTING FIRMS Activity Reference No. Actual Short List and Opening of Combined Loan / Credit Market Contract Type Estimated Process Expression of Request for Evaluation of / Description Component Review Type Method Amount Terms of Reference Draft Request for Technical Proposals Evaluation Report Signed Contract Contract Completion No. Approach Amount (US$) Status Interest Notice Proposals as Issued Technical Proposal (US$) Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Status Contract (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-SAFETY Component 5: Project Individual NETS-80479-CS-INDV / Management, 2019-01- 2019-02- 2019-03- 2020-09- IDA / 63370 Prior Consultant Open 90,000.00 48,000.00 Signed 2018-12-03 Procurement of National Coordination, and 21 11 18 08 Selection Coordinator for RDCU Capacity Building GH-MLGRD-SAFETY Component 5: Project Individual NETS-80487-CS-INDV / Management, Under 2019-01- 2019-02- 2019-03- 2020-09- / Prior Consultant Open 57,600.00 36,000.00 2018-12-03 Procurement of National Coordination, and Implementation 21 11 18 08 Selection Engineer at RDCU Capacity Building GH-MLGRD-SAFETY Component 5: Project NETS-80490-CS-INDV / Individual Management, Under 2019-01- 2019-02- 2019-03- 2020-09- Procurement of / Prior Consultant Open 57,600.00 36,000.00 2018-12-03 Coordination, and Implementation 21 11 18 08 Institutional & Capacity Selection Capacity Building Development Specialist at RDCU GH-MLGRD-SAFETY Component 5: Project NETS-80491-CS-INDV / Individual Management, Under 2019-01- 2019-02- 2019-03- 2020-09- Procurement of Productive / Prior Consultant Open 57,600.00 36,000.00 2018-12-03 Coordination, and Implementation 21 11 18 08 Inclusion Specialist for Selection Capacity Building RDCU GH-MLGRD-SAFETY Component 5: Project NETS-80494-CS-INDV / Individual Management, Under 2019-01- 2019-02- 2019-03- 2020-09- Procurement of Monitoring / Prior Consultant Open 57,600.00 30,000.00 2018-12-03 Coordination, and Implementation 21 11 18 08 and Evaluation Officer for Selection Capacity Building RDCU GH-MLGRD-SAFETY Component 5: Project Individual NETS-80504-CS-INDV / Management, Under 2019-01- 2019-02- 2019-03- 2020-09- / Prior Consultant Open 32,400.00 0.00 2018-12-10 Procurement of 1No. Coordination, and Implementation 28 18 25 15 Selection Engineer for Zonal Office Capacity Building 1 GH-MLGRD-SAFETY Component 5: Project NETS-80507-CS-INDV / Individual Management, Under 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. / Prior Consultant Open 32,400.00 0.00 2018-12-10 Coordination, and Implementation 28 18 25 15 Accountant for Zonal Selection Capacity Building Office 1 GH-MLGRD-SAFETY Component 5: Project NETS-80510-CS-INDV / Individual Management, 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. / Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 Coordination, and 28 18 25 15 Community Animator for Selection Capacity Building Zonal Office 1 GH-MLGRD-SAFETY Component 5: Project NETS-80742-CS-INDV / Individual Management, 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. / Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 Coordination, and 28 18 25 15 Community Animator for Selection Capacity Building Zonal Office 2 GH-MLGRD-SAFETY Component 5: Project NETS-80744-CS-INDV / Individual Management, 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. / Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 Coordination, and 28 18 25 15 Community Animator for Selection Capacity Building Zonal Office 3 GH-MLGRD-SAFETY Component 5: Project NETS-80746-CS-INDV / Individual Management, 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. / Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 Coordination, and 28 18 25 15 Community Animator for Selection Capacity Building Zonal Office 4 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80749-CS-INDV / Management, Under 2019-01- 2019-02- 2019-03- 2020-09- / Prior Consultant Open 32,400.00 0.00 2018-12-10 Procurement of 1No. Coordination, and Implementation 28 18 25 15 Selection Engineer for Zonal Office Capacity Building 2 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80750-CS-INDV / Management, Under 2019-01- 2019-02- 2019-03- 2020-09- / Prior Consultant Open 32,400.00 0.00 2018-12-10 Procurement of 1No. Coordination, and Implementation 28 18 25 15 Selection Engineer for Zonal Office Capacity Building 3 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80751-CS-INDV / Management, Under 2019-01- 2019-02- 2019-03- 2020-09- / Prior Consultant Open 32,400.00 0.00 2018-12-10 Procurement of 1No. Coordination, and Implementation 28 18 25 15 Selection Engineer for Zonal Office Capacity Building 4 GH-MLGRD-SAFETY Component 5: Project NETS-80754-CS-INDV / Individual Management, Under 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. / Prior Consultant Open 32,400.00 30,000.00 2018-12-10 Coordination, and Implementation 28 18 25 15 Accountant for Zonal Selection Capacity Building Office 2 GH-MLGRD-SAFETY Component 5: Project NETS-80755-CS-INDV / Individual Management, Under 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. / Prior Consultant Open 32,400.00 30,000.00 2018-12-10 Coordination, and Implementation 28 18 25 15 Accountant for Zonal Selection Capacity Building Office 3 GH-MLGRD-SAFETY Component 5: Project NETS-80756-CS-INDV / Individual Management, Under 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. / Prior Consultant Open 32,400.00 0.00 2018-12-10 Coordination, and Implementation 28 18 25 15 Accountant for Zonal Selection Capacity Building Office 4 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80758-CS-INDV / Management, Under 2019-01- 2019-02- 2019-03- 2020-09- / Prior Consultant Open 32,400.00 0.00 2018-12-10 Procurement of 1No. PI Coordination, and Implementation 28 18 25 15 Selection Officer for Zonal Office 2 Capacity Building GH-MLGRD-SAFETY Component 5: Project Individual NETS-80761-CS-INDV / Management, Under 2019-01- 2019-02- 2019-03- 2020-09- / Prior Consultant Open 32,400.00 0.00 2018-12-10 Procurement of 1No. PI Coordination, and Implementation 28 18 25 15 Selection Officer for Zonal Office 3 Capacity Building Page 13 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80763-CS-INDV / Management, Under 2019-01- 2019-02- 2019-03- 2020-09- / Prior Consultant Open 32,400.00 0.00 2018-12-10 Procurement of 1No. PI Coordination, and Implementation 28 18 25 15 Selection Officer for Zonal Office 4 Capacity Building GH-MLGRD-SAFETY Component 5: Project Individual NETS-80765-CS-INDV / Management, 2019-01- 2019-02- 2019-03- 2020-09- / Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 Procurement of 1No. PI Coordination, and 28 18 25 15 Selection Officer for RDCU Capacity Building GH-MLGRD-SAFETY Component 5: Project NETS-80499-CS-INDV / Individual Management, Under 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. Zonal IDA / 63370 Prior Consultant Open 50,400.00 0.00 2018-12-10 Coordination, and Implementation 28 18 25 15 Coordinator for Zonal Selection Capacity Building Office 1 GH-MLGRD-SAFETY NETS-87845-CS-INDV / Component 5: Project Individual Procurement of 1No. Management, 2019-01- 2019-02- 2019-03- 2020-09- IDA / 63370 Prior Consultant Open 27,000.00 30,000.00 Signed 2018-12-03 Safeguards and Case Coordination, and 21 11 18 02 Selection Management Officer at Capacity Building RDCU GH-MLGRD-SAFETY Component 5: Project Individual NETS-87846-CS-INDV / Management, 2019-01- 2019-02- 2019-03- 2020-09- IDA / 63370 Prior Consultant Open 27,000.00 36,000.00 Signed 2018-12-03 Procurement of 1No. Coordination, and 21 11 18 02 Selection Procurement Officer Capacity Building GH-MLGRD-SAFETY Component 5: Project NETS-80741-CS-INDV / Individual Management, 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. Zonal IDA / 63370 Prior Consultant Open 50,400.00 31,200.00 Signed 2018-12-10 Coordination, and 28 18 25 15 Coordinator for Zonal Selection Capacity Building Office 4 GH-MLGRD-SAFETY Component 5: Project NETS-80739-CS-INDV / Individual Management, Under 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. Zonal IDA / 63370 Prior Consultant Open 50,400.00 31,200.00 2018-12-10 Coordination, and Implementation 28 18 25 15 Coordinator for Zonal Selection Capacity Building Office 2 GH-MLGRD-SAFETY Component 5: Project NETS-80740-CS-INDV / Individual Management, 2019-01- 2019-02- 2019-03- 2020-09- Procurement of 1No. Zonal IDA / 63370 Prior Consultant Open 50,400.00 31,200.00 Signed 2018-12-10 Coordination, and 28 18 25 15 Coordinator for Zonal Selection Capacity Building Office 3 GH-MLGRD-SAFETY Component 5: Project Individual NETS-80483-CS-INDV / Management, 2019-01- 2019-02- 2019-03- 2020-09- IDA / 63370 Prior Consultant Open 57,600.00 36,000.00 Signed 2018-12-03 Procurement of Project Coordination, and 21 11 18 08 Selection Accountant at RDCU Capacity Building GH-MLGRD-SAFETY NETS-91546-CS-INDV / Component 5: Project Individual Procurement of 1No. Management, 2019-02- 2019-02- 2019-03- 2020-09- IDA / 63370 Prior Consultant Open 45,000.00 36,000.00 Signed 2018-12-14 Management Information Coordination, and 01 22 29 13 Selection Systems Specialist for Capacity Building RDCU GH-MLGRD-SAFETY Component 5: Project Individual NETS-80508-CS-INDV / Management, 2019-01- 2019-02- 2019-03- 2020-09- / Prior Consultant Open 32,400.00 0.00 Canceled 2018-12-10 Procurement of 1No. PI Coordination, and 28 18 25 15 Selection Officer for Zonal Office 1 Capacity Building Page 14