Procurement Plan Metro Colombo Urban Development Project (P122735) Sri Lanka Credit/Grant #: 8145-LK I. General 1. Bank’s approval Date of the procurement Plan: Original 8th February 2012: Revision 28th March 2017 2. Date of General Procurement Notice: 29th August 2011 3. Period covered by this procurement plan: 31st December 2017 II. Goods and Works and Non-consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB (Works) Above US$ 15,000,000 All 2. NCB (Works) Less US$ 10,000,000 First Contract only 3. Shopping (Works) Less US$ 500,000 First Contract only 4. ICB (Goods) Above US$ 4,000,000 All 5. NCB (Goods) Less US$ 1,000,000 First Contract only 6. Shopping (Goods) Less US$ 500,000 First Contract only 7. Force Account All 2. Prequalification. Bidders for identified procurements shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Procurement Guidelines. 3. Proposed Procedures for CDD Components: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Procurement Administration Manual, Metro Colombo Urban Development Project (MCUDP), December 2011 5. Any Other Special Procurement Arrangements: None III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: March 28, 2017 Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms advertised Above US$ 2,000,000 All internationally) 2. Single Source (Firms) All 3. Individual Consultants Above US$ 400,000 All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None March 28, 2017 PROCUREMENT Sri Lanka : Metro Colombo Urban Development Project PLAN General Information Country: Sri Lanka Bank’s Approval Date of the Original Procurement Plan: 2017-02-08 2019-09-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P122735 GPN Date: Project Name: Metro Colombo Urban Development Project Loan / Credit No: IBRD / 81450 Executing Agency(ies): Ministry of Megapolis and Western Development WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMWD-1762-CW-RFB / SLLRDC/W/14 - Design & Component 1: Flood and Open - Single Stage - Two IBRD / 81450 Prior Request for Bids 36,000,000.00 33,653,416.41 Signed 2016-12-16 2016-12-24 2017-01-02 2017-02-27 2017-03-30 2019-03-29 Building of new Mutwal Drainage Management International Envelope Tunnel & Torrington Tunnel LK-MOMWD-1789-CW-RFB / SLLRDC/W/12 - Design & Component 1: Flood and Open - Single Stage - Two Building of St Sebastian IBRD / 81450 Prior Request for Bids 23,650,000.00 0.00 Canceled 2016-09-20 2016-09-20 2016-09-20 2016-11-03 2017-03-24 2019-03-07 Drainage Management International Envelope Northlock gates & Pumping Station LK-MOMWD-1755-CW-RFB / SLLRDC/W/20 - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 3,816,793.00 3,419,056.09 Signed 2017-02-01 2017-02-06 2017-03-08 2017-04-07 2017-05-12 2018-09-07 Installation of Flushing Drainage Management Envelope Gates for Water Quality Improvement LK-MOMWD-1625-CW-RFB / SLLRDC/W/16/A - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 1,307,692.00 4,752,618.86 Signed 2017-05-12 2017-05-23 2017-06-20 2017-07-24 2017-11-29 2019-02-25 Kolonnawa Canal Diversion Drainage Management Envelope Scheme Stage 1 LK-MOMWD-1677-CW-RFB / SLLRDC/W/16-B - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 3,000,000.00 1,579,116.61 Signed 2017-04-08 2017-04-13 2017-05-09 2017-06-13 2017-07-17 2018-10-10 Kolonnawa Canal Diversion Drainage Management Envelope Scheme Stage II LK-MOMWD-1717-CW-RFB / SLLRDC/W/16/C - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 3,076,923.00 5,615,951.42 Signed 2017-04-17 2017-04-24 2017-05-19 2017-06-21 2017-10-27 2019-01-23 Kolonnawa Canal Diversion Drainage Management Envelope Scheme Stage III LK-MOMWD-1759-CW-RFB / SLLRDC/W/16-D - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 7,076,923.00 7,916,400.30 Signed 2017-04-25 2017-04-30 2017-05-30 2017-06-29 2017-08-25 2018-08-18 Kolonnawa Canal diversion Drainage Management Envelope stage IV LK-MOMWD-1605-CW-RFB / SLLRDC/W/05 - Madiwela Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 1,633,324.07 1,274,967.22 Signed 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-09-30 2017-09-18 East Diversion Scheme Stage- Drainage Management Envelope 1 LK-MOMWD-1607-CW-RFB / SLLRDC/W/11- Component 1: Flood and Single Stage - One Improvements to Madiwela IBRD / 81450 Post Request for Bids Open - National 736,539.95 595,805.91 Signed 2016-09-19 2016-09-19 2016-10-04 2016-11-04 2016-12-16 2017-12-11 Drainage Management Envelope East Diversion Scheme Stage 11 Page 1 LK-MOMWD-1376-CW-RFB / SLLRDC/W/19 - Component 1: Flood and Single Stage - One Improvements to Madiwela IBRD / 81450 Post Request for Bids Open - National 2,376,396.43 1,929,864.77 Signed 2016-09-05 2016-10-03 2016-11-02 2016-12-02 2017-01-06 2018-01-29 Drainage Management Envelope east Diversion Scheme Stage III LK-MOMWD-1623-CW-RFB / SLLRDC/W/9 - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 4,725,000.00 1,798,160.60 Signed 2016-10-12 2016-10-17 2016-11-16 2016-12-16 2017-04-18 2018-07-06 Construction of Bank Drainage Management Envelope Protection works of St Sebastian North Canal LK-MOMWD-1796-CW-RFB / SLLRDC/W/7/A - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 507,165.00 390,878.50 Signed 2016-09-20 2016-09-20 2016-09-20 2016-09-20 2016-10-11 2017-05-15 Conveyance Improvements to Drainage Management Envelope Wellawatta Canal at Galle Road Bridge LK-MOMWD-10623-CW-RFB / SLLRDC/W/24 Plant Component 1: Flood and Open - Single Stage - Two Design, Supply and IBRD / 81450 Post Request for Bids 14,000,000.00 12,455,020.15 Signed 2017-03-24 2017-03-31 2017-06-22 2017-08-30 2017-11-01 2019-11-07 Drainage Management International Envelope Installation of Pumping Station at Ambatale. LK-MOMWD-1375-CW-RFB / CMC/W/MD/4B - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 7,580,000.00 1,975,795.75 Signed 2017-04-30 2017-05-05 2017-06-02 2017-06-30 2017-08-31 2019-01-25 Improvements to Norris Drainage Management Envelope Canal LK-MOMWD-1839-CW-RFB / UDA/W/1-B - Development Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 2,300,000.00 2,977,944.93 Signed 2017-04-28 2017-05-09 2017-06-06 2017-07-03 2017-08-14 2018-11-15 of Bio-Diversity Park at Drainage Management Envelope Kotte Rampart LK-MOMWD-1840-CW-RFB / UDA/W/4-C - Construction of Linear Park Along Beira Lake Phase III - Western Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 2,100,000.00 791,905.90 Signed 2017-05-31 2017-06-09 2017-07-06 2017-08-03 2017-09-14 2018-10-03 Bank of West 1.25km- Drainage Management Envelope ( Along Army Head Quarter premises to Justice Akbar Mawatha ) LK-MOMWD-1836-CW-RFB / UDA/W/04-A - Construction of Linear Park AlongEastern Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 1,500,285.01 1,114,992.54 Signed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-12-30 Bank of East Beira Lake Drainage Management Envelope Phase 1 (Aitken Spence to Lotus Tower) LK-MOMWD-1834-CW-RFB / UDA/W/03-B - Construction of bank protection works of Component 1: Flood and Single Stage - One Western Bank of west Beira IBRD / 81450 Post Request for Bids Open - National 2,307,979.05 1,664,437.84 Signed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-12-30 Drainage Management Envelope Lake - 1.05 km(Along Army Head quarters premises to Justice Akbar Mawatha) LK-MOMWD-1837-CW-RFB / UDA/W/04-D - Construction of Linear Park AlongEastern Component 1: Flood and Single Stage - One Bank of East Beira Lake IBRD / 81450 Post Request for Bids Open - National 2,101,103.18 1,619,346.69 Signed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2017-09-15 Drainage Management Envelope Phase 11 Lotus Tower via Lake House Junction to Secretariat Station LK-MOMWD-1600-CW-RFB / CMC/W/MD/13 Micro Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 3,364,292.73 2,626,155.47 Signed 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2017-11-09 Drainage improvements to Drainage Management Envelope Devi Balika Junction Page 2 LK-MOMWD-1604-CW-RFB / CMC/W/MD/12 - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 1,393,986.69 1,088,141.28 Signed 2016-09-15 2016-09-15 2016-09-16 2016-09-17 2016-09-22 2017-07-19 Improvements to Kynsey Drainage Management Envelope Road drain Component 2: Urban LK-MOMWD-1827-CW-RFB development, infrastructure / KUC/W/01 - Infrastructure Single Stage - One IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 1,381,849.06 1,065,008.48 Signed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-10-12 2017-06-14 Development in Kolonnawa Envelope building for Metro Colombo Urban Council local authorities. LK-MOMWD-1813-CW-RFB / SLLRDC/W/3/A - Component 1: Flood and Single Stage - One Construction of Canal Bank IBRD / 81450 Post Request for Bids Open - National 1,982,829.89 1,430,543.30 Completed 2016-09-20 2016-09-20 2016-09-20 2016-09-20 2016-09-20 2016-09-20 Drainage Management Envelope protection of St Sebestian South Canal LK-MOMWD-1820-CW-RFB / CMC/W/MD/03 - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 2,208,990.98 1,593,710.71 Completed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 Rehabilitation of Gregory's Drainage Management Envelope Canal Component 2: Urban LK-MOMWD-1822-CW-RFB development, infrastructure Single Stage - One / CMC/W/3-A - Public IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 545,861.36 393,820.12 Completed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-11-20 Envelope Conveniences Package III building for Metro Colombo local authorities. Component 2: Urban LK-MOMWD-1832-CW-RFB development, infrastructure / CMC/W/13/A - Construction Single Stage - One IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 2,105,188.80 1,518,821.03 Completed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-11-20 of Beach Park at Crow Envelope building for Metro Colombo Island local authorities. Component 2: Urban LK-MOMWD-1824-CW-RFB development, infrastructure / SJKMC/W/03- Single Stage - One IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 584,432.97 421,648.21 Completed 2016-10-05 2016-10-05 2016-10-05 2016-10-05 2016-10-05 2016-12-26 Infrastructure Development Envelope building for Metro Colombo in SJKMC Package III local authorities. LK-MOMWD-1761-CW-FCA Component 1: Flood and / SLLRDC/W/23 - Dredging IBRD / 81450 Prior Force Account Direct 900,000.00 764,828.56 Completed 2016-09-20 2016-09-20 2016-09-20 2017-09-01 Drainage Management of Talangama Tank. LK-MOMWD-40497-CW-RFB / SLLRDC/W/12 - Design & Component 1: Flood and Open - Single Stage - Two building of St. sebastian IBRD / 81450 Prior Request for Bids 23,650,000.00 12,969,360.92 Signed 2018-01-11 2018-01-11 2018-01-11 2018-01-11 2018-01-11 2019-06-30 Drainage Management International Envelope nortlock gates & pumping station. LK-MOMWD-80060-CW-RFB / Construction of flood gate with culvert near Component 1: Flood and Single Stage - One Thalangama tank and IBRD / 81450 Post Request for Bids Open - National 875,000.00 1,465,912.35 Signed 2018-11-19 2018-11-26 2018-12-26 2019-01-25 2019-02-22 2019-10-20 Drainage Management Envelope Construction of culvert at Baudhaloka mawatha - MCUDP/PMU/W/01 LK-MOMWD-1786-CW-RFB / SLLRDC /W/18 - Supply of Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 2,000,000.00 0.00 Canceled 2017-01-12 2017-01-17 2017-02-16 2017-03-18 2017-04-22 2017-10-19 Real Time Integrated Flood Drainage Management Envelope Management system LK-MOMWD-10527-CW-RFB / UDA/W/05 Repair and Component 1: Flood and IBRD / 81450 Post Direct Selection Direct 200,000.00 0.00 Canceled 2017-05-22 2017-06-21 2017-09-10 2018-09-10 Renovation to McCallum Drainage Management Lock Gates. Page 3 LK-MOMWD-1777-CW-RFB / SLLRDC/W/13/ICB/2018- Component 1: Flood and Open - Single Stage - One Design and Building of St. IBRD / 81450 Post Request for Bids 10,770,000.00 6,884,132.82 Signed 2017-04-26 2017-05-01 2017-07-24 2017-10-01 2017-12-01 2019-12-05 Drainage Management International Envelope Sebastian South Pumping Station LK-MOMWD-1374-CW-RFB / CMC/W/MD/4A - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 3,200,000.00 0.00 Canceled 2017-06-30 2017-07-10 2017-08-07 2017-09-04 2017-10-13 2018-10-16 Improvements to Saunders Drainage Management Envelope Place Storm water system GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMWD-1670-GO-RFB / Component 1: Flood and Single Stage - One SLLRDC/G/06 - Procurement IBRD / 81450 Post Request for Bids Open - National 116,096.43 91,440.24 Signed 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-19 Drainage Management Envelope of Workshop Tools LK-MOMWD-1691-GO-RFB / PMU/LA/G/01 - Procurement Component 1: Flood and Single Stage - One of Construction, Solid Waste IBRD / 81450 Post Request for Bids Open - National 1,660,500.98 1,533,958.12 Completed 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-19 Drainage Management Envelope Management & Utility Support Vehicles LK-MOMWD-1760-GO-RFQ / SLLRDC/G/13 - Procurement of Software for Component 1: Flood and Request for Open - Single Stage - One IBRD / 81450 Post 18,000.00 23,109.31 Signed 2016-09-20 2016-09-20 2016-09-20 Geo technical Analysis, Geo Drainage Management Quotations International Envelope slope, 2D Plaxis and 3D Plaxis LK-MOMWD-1763-GO-RFQ / SLLRDC/G/14 - Component 1: Flood and Request for Open - Single Stage - One IBRD / 81450 Post 2,000.00 17,263.69 Completed 2016-09-25 2016-09-25 2016-09-25 Procurement of Microsoft Drainage Management Quotations International Envelope Office 2013 & MS Project 2013 LK-MOMWD-1766-GO-RFQ / SLLRDC/G/12 - Component 1: Flood and Request for Open - Single Stage - One Procurement of Software for IBRD / 81450 Post 26,000.00 39,892.41 Completed 2016-09-20 2016-09-20 2016-09-20 Drainage Management Quotations International Envelope Structural Design, Prokon, SAP 2000 and Etab LK-MOMWD-1769-GO-RFQ / SLLRDC/G/11 - Procurement of Auto CAD Component 1: Flood and Request for Open - Single Stage - One IBRD / 81450 Post 20,000.00 3,910.00 Signed 2016-09-20 2016-09-20 2016-09-20 2012, Auto CAD Civil 3D Drainage Management Quotations International Envelope (Geometry Design) and Google Earth Pro LK-MOMWD-1924-GO-RFQ / SLLRDC/G/17 - Component 1: Flood and Request for Open - Single Stage - One IBRD / 81450 Post 10,000.00 8,623.10 Signed 2016-09-26 2016-09-26 2016-09-26 Procurement of Upgrading Drainage Management Quotations International Envelope Arc GIS -10.3 Version LK-MOMWD-2473-GO-RFB / SLLRDC/G/4-A - Component 1: Flood and Single Stage - One Procurement of Construction IBRD / 81450 Post Request for Bids Open - National 693,790.43 582,541.06 Completed 2016-10-10 2016-10-10 2016-10-10 2016-10-10 2016-10-10 2016-10-10 Drainage Management Envelope Machinery & Equipment Package II LK-MOMWD-1923-GO-RFQ Component 1: Flood and Request for Single Stage - One / SLLRDC/G/08 - IBRD / 81450 Post Open - National 440,000.00 65,075.53 Completed 2016-10-01 2016-11-26 2017-05-25 Drainage Management Quotations Envelope Procurement of Computer Hardware Page 4 LK-MOMWD-1606-GO-RFB / Component 1: Flood and Single Stage - One SLLRDC/G/15 - Procurement IBRD / 81450 Post Request for Bids Open - National 56,428.57 54,711.68 Completed 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-12-14 Drainage Management Envelope of Generators LK-MOMWD-1754-GO-RFB / SLLRDC/G/03 - Procurement Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 420,000.00 78,654.30 Completed 2016-09-20 2016-09-20 2016-09-20 2016-09-20 2016-09-20 2016-09-20 of Testing Equipment & Drainage Management Envelope Instruments Component 2: Urban LK-MOMWD-39993-GO-RFB development, infrastructure / SLLRDC/G/03-A Single Stage - One IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 420,000.00 405,515.25 Signed 2017-12-18 2018-01-15 2018-02-14 2018-04-11 2018-10-08 Procurement of Testing Envelope building for Metro Colombo Equipment and Instruments local authorities. LK-MOMWD-14361-GO-RFQ / SLLRDC/G/18-A - Supply and installation of Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Open - National 40,000.00 28,910.24 Signed 2018-01-08 2018-05-28 2018-08-20 equipment and facilities for Drainage Management Quotations Envelope Center for Flood Control & Water Management. LK-MOMWD-40090-GO-RFQ / SLLRDC/G/18-G Supply Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 150,000.00 -55,487.45 Signed 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 2018-11-20 and installation of Rainfall Drainage Management Envelope gauges for RTC. LK-MOMWD-40334-GO-RFB / SLLRDC/G/18-K - Supply Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 150,000.00 47,223.83 Completed 2017-12-25 2017-12-30 2018-02-10 2018-03-12 2018-04-16 2018-06-15 of software with related Drainage Management Envelope training to RTC LK-MOMWD-40339-GO-RFQ / SLLRDC/G/18-L - Supply Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Open - National 37,000.00 31,110.05 Completed 2017-12-25 2018-02-19 2018-08-18 of Acoustic Doppler Current Drainage Management Quotations Envelope Profiler for RTC system LK-MOMWD-40340-GO-RFQ / SLLRDC/G/18-M - Supply of Telemetered automatic Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Open - National 23,500.00 18,039.85 Completed 2017-12-21 2018-02-09 2018-03-11 weather station & water Drainage Management Quotations Envelope level measurement system for RTC LK-MOMWD-40346-GO-RFQ / SLLRDC/G/18-N - Supply Component 1: Flood and Request for Single Stage - One of Recording & Storage type IBRD / 81450 Post Open - National 25,000.00 22,280.26 Completed 2017-12-21 2018-02-09 2018-03-11 Drainage Management Quotations Envelope weather station & water level gauges LK-MOMWD-14408-GO-RFB / SLLRDC/G/18-D - Supply Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Open - National 65,500.00 0.00 Canceled 2017-09-16 2018-02-26 2018-06-28 and installation of central Drainage Management Quotations Envelope air conditioning for RTC LK-MOMWD-2474-GO-RFB / SLLRDC/G/4-B - Component 1: Flood and Single Stage - One Procurement of Construction IBRD / 81450 Post Request for Bids Open - National 851,851.85 0.00 Canceled 2016-12-06 2016-12-11 2017-01-10 2017-02-09 2017-03-16 2017-09-12 Drainage Management Envelope Machinery & Equipment Package III LK-MOMWD-100657-GO- RFQ / MCUDP/SLLRDC/G/18- Under Component 1: Flood and Request for Single Stage - One O - Supply of Ground IBRD / 81450 Post Open - National 40,000.00 0.00 Implementati 2019-02-28 2019-04-21 2019-08-19 Drainage Management Quotations Envelope Penetrating Radar (GPR) for on SLLRDC Page 5 LK-MOMWD-14357-GO-RFQ / MCUDP/SLLRDC/G/18 - Component 1: Flood and Request for Single Stage - One Supply and installation of IBRD / 81450 Post Open - National 200,000.00 0.00 Canceled 2017-09-15 2018-02-26 2018-06-04 Drainage Management Quotations Envelope equipment & facilities for RTC centre. Component 2: Urban LK-MOMWD-1925-GO-RFB / development, infrastructure UDA/G/01 - Procurement of Single Stage - One IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2017-01-18 2017-01-23 2017-03-06 2017-04-05 2017-05-10 2017-11-06 Transport and Utility Envelope building for Metro Colombo Vehicles for UDA local authorities. LK-MOMWD-2472-GO-RFB / Component 1: Flood and Single Stage - One SLLRDC/G/05 -Procurement IBRD / 81450 Post Request for Bids Open - National 640,000.00 0.00 Canceled 2016-12-08 2016-12-15 2017-01-14 2017-02-13 2017-03-09 2017-07-06 Drainage Management Envelope of Construction Plants. LK-MOMWD-14368-GO-RFB / SLLRDC/G/18-C - Supply, installation and Pending commissioning of IT facilities Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 800,000.00 0.00 Implementati 2019-10-15 2019-10-29 2019-11-28 2019-12-28 2020-01-18 2020-04-17 including networking, Drainage Management Envelope on communication, data center facility and BMS for new RTC building. LK-MOMWD-40321-GO-RFQ / SLLRDC/G/18-J I Supply Component 1: Flood and Single Stage - One and installation of IBRD / 81450 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2019-06-03 2019-06-17 2019-07-17 2019-08-16 2019-09-20 2019-12-19 Drainage Management Envelope forecasting and control for SCADA - Phsae - I LK-MOMWD-40083-GO-RFQ / SLLRDC/G/18-E Supply, Pending Installation and Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 350,000.00 0.00 Implementati 2019-10-02 2019-10-16 2019-11-15 2019-12-15 2020-01-12 2020-04-11 Commissioning of Display Drainage Management Envelope on System for New RTC Building LK-MOMWD-40087-GO-RFQ / SLLRDC/G/18-F Supply Component 1: Flood and Single Stage - One and installation of outlet IBRD / 81450 Post Request for Bids Open - National 132,000.00 0.00 Canceled 2019-06-03 2019-06-08 2019-07-08 2019-08-07 2019-09-04 2019-12-03 Drainage Management Envelope physical model for pumping house. LK-MOMWD-40332-GO-RFB / SLLRDC/G/18-D - Supply Pending Component 1: Flood and Single Stage - One and installation of utility IBRD / 81450 Post Request for Bids Open - National 250,000.00 0.00 Implementati 2019-10-22 2019-11-21 2020-01-02 2020-02-01 2020-03-07 2020-05-06 Drainage Management Envelope and operational facilities for on RTC LK-MOMWD-117803-GO- Pending RFB / SLLRDC/G/18-F - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 50,000.00 0.00 Implementati 2019-10-09 2019-10-14 2019-11-13 2019-12-13 2020-01-03 2020-09-03 Syatem for Real Time Data Drainage Management Envelope on Management LK-MOMWD-117824-GO- RFQ / SLLRDC/G/18-K/VIII - Pending Component 1: Flood and Request for Single Stage - One Supply and Delivery of IBRD / 81450 Post Limited 960.00 0.00 Implementati 2019-09-08 2019-10-27 2019-11-10 Drainage Management Quotations Envelope Adobe Creative Cloud Suite on (All Apps) LK-MOMWD-124028-GO- DIR / SLLRDC/G/18-J I - Pending Component 1: Flood and Supply and Installation of IBRD / 81450 Post Direct Selection Direct 200,000.00 0.00 Implementati 2019-10-02 2019-10-07 2019-11-16 2020-02-14 Drainage Management Forecasting and Control for on SCADA - Phase I Page 6 LK-MOMWD-117806-GO- DIR / SLLRDC/G/18-K/III - Pending Component 1: Flood and Supply and Delivery of Flo IBRD / 81450 Post Direct Selection Direct 5,000.00 0.00 Implementati 2019-06-17 2019-06-24 2019-07-29 2019-08-28 Drainage Management 2D Model Pro Subscription 5- on Year and Perpetual License LK-MOMWD-117812-GO- Pending DIR / SLLRDC/G/18-K/V - Component 1: Flood and IBRD / 81450 Post Direct Selection Direct 7,050.00 0.00 Implementati 2019-06-17 2019-06-24 2019-07-29 2019-08-28 Supply and Delivery of Drainage Management on Mathematica Software LK-MOMWD-117790-GO- RFB / SLLRDC/G/18-J II - Pending Component 1: Flood and Supply and installation of IBRD / 81450 Post Direct Selection Direct 400,000.00 0.00 Implementati 2019-10-15 2019-10-20 2019-11-29 2020-02-27 Drainage Management forecasting and control for on SCADA - Phase II LK-MOMWD-117813-GO- DIR / SLLRDC/G/18-K/IV - Pending Component 1: Flood and Supply and Delivery of IBRD / 81450 Post Direct Selection Direct 1,050.00 0.00 Implementati 2019-06-17 2019-06-24 2019-07-29 2019-08-28 Drainage Management Highstock Developer License, on Version 6 LK-MOMWD-117816-GO- Pending DIR / SLLRDC/G/18-K/VII - Component 1: Flood and IBRD / 81450 Post Direct Selection Direct 2,990.00 0.00 Implementati 2019-06-17 2019-06-24 2019-07-29 2019-08-28 Supply and Delivery of Drainage Management on Neurosolutions Pro License LK-MOMWD-117815-GO- DIR / SLLRDC/G/18-K/VI - Pending Component 1: Flood and Supply and Delivery of IBRD / 81450 Post Direct Selection Direct 2,350.00 0.00 Implementati 2019-06-17 2019-06-24 2019-07-29 2019-08-28 Drainage Management Matlab Version R2017 with on DHIMatalab Toolbox LK-MOMWD-122409-GO- RFB / MCUDP/SLLRDC/G/18- Pending Component 1: Flood and Q - Supply, Installation and IBRD / 81450 Post Direct Selection Direct 50,000.00 0.00 Implementati 2019-10-02 2019-10-07 2019-11-16 2020-02-14 Drainage Management Operation of Communication on and Control for RTC System LK-MOMWD-117794-GO- Pending RFB / SLLRDC/G/18-P - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 600,000.00 0.00 Implementati 2019-09-09 2019-09-14 2019-10-14 2019-11-13 2019-12-04 2020-03-03 Supply and Installation of Drainage Management Envelope on Compact X Band Radar Set LK-MOMWD-108647-GO- Pending RFB / Purchasing of Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 75,000.00 0.00 Implementati 2019-10-21 2019-10-26 2019-11-16 2019-11-30 2019-12-14 2019-12-28 software with training Drainage Management Envelope on related to RTC system - Phase II LK-MOMWD-40295-GO-RFQ Pending / SLLRDC/G/18-H Supply Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 200,000.00 0.00 Implementati 2019-09-30 2019-10-05 2019-10-26 2019-11-09 2019-11-23 2020-02-21 and installation of Water Drainage Management Envelope on level gauges for RTC LK-MOMWD-14365-GO-RFB Pending / SLLRDC/G/18-B - Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Open - National 33,000.00 0.00 Implementati 2019-09-21 2019-12-02 2020-01-01 Procurement of Generator for Drainage Management Quotations Envelope on RTC NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7 LK-MOMWD-25530-NC-DIR / PMU/NC/01 Procurement Services for RTC Center Component 1: Flood and Data Integration and IBRD / 81450 Post Direct Selection Direct 623,000.00 148,652.51 Signed 2017-08-21 2017-08-21 2017-08-21 2020-06-30 Drainage Management Forecasting from Computer Engineering Department of University of Moratuwa. LK-MOMWD-99203-NC-RFP / MCUDP/PMU/NC/02 - Component 1: Flood and Single Stage - One Procurement of a Payment IBRD / 81450 Post Request for Bids Limited 51,000.00 36,000.00 Signed 2019-02-27 2019-03-02 2019-03-16 2019-03-19 2019-04-12 2020-04-11 Drainage Management Envelope Partner for Google Cloud Services CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMWD-6554-CS-QCBS / PMU/C/16-A - Consultancy Services for Design Review, Construction Supervision and Component 1: Flood and Quality And Cost- Open - IBRD / 81450 Post 1,000,000.00 1,742,015.24 Signed 2017-02-09 2017-03-02 2017-04-15 2017-05-13 2017-06-12 2017-07-17 2017-08-21 2018-08-21 Project Management for the Drainage Management Based Selection International Design and Building of St. Sebestian North Lock Gates and Pumping Station LK-MOMWD-10544-CS- QCBS / PMU/C/59 Consultancy Services for Design Review, Contract Component 1: Flood and Quality And Cost- Open - IBRD / 81450 Post 689,000.00 1,876,269.38 Signed 2017-03-27 2017-03-27 2017-05-12 2017-06-11 2017-07-11 2017-08-15 2017-09-19 2019-09-29 Management, and Drainage Management Based Selection International Construction Supervision of Plant Design Supply and Installation of Pumping Station at Ambatale. LK-MOMWD-1598-CS-QCBS / PMU/C/32 - Consultancy Services for-Construction Supervision & Project Component 1: Flood and Quality And Cost- IBRD / 81450 Post Open - National 257,196.42 200,152.73 Signed 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2019-02-02 Management in Micro Drainage Management Based Selection Drainage Component (Drains from Kynsey Road & Devi Balika Junction) LK-MOMWD-1715-CS-QCBS / PMU/C/38 - Consultancy Component 3: Quality And Cost- Services for Independent IBRD / 81450 Post Open - National 57,147.85 44,235.52 Signed 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2018-06-15 Implementation Support Based Selection Monitoring & Review of Social safeguards LK-MOMWD-1845-CS-QCBS / PMU/C/48 - Consultancy Component 1: Flood and Quality And Cost- Open - Services for Design and IBRD / 81450 Post 305,343.51 908,154.60 Signed 2016-09-22 2016-09-22 2016-09-30 2016-10-31 2016-11-30 2016-12-15 2017-01-02 2018-04-02 Drainage Management Based Selection International Construction Management for Flushing Gates LK-MOMWD-1841-CS-QCBS / PMU/C/27 - Consultancy Services for Design Review Component 1: Flood and Quality And Cost- Open - IBRD / 81450 Post 305,343.51 1,091,851.19 Signed 2016-09-26 2016-12-21 2017-02-09 2017-03-08 2017-04-14 2017-05-15 2017-06-01 2018-10-30 and Contract Management of Drainage Management Based Selection International Kolonnawa Canal Diversion Scheme Page 8 LK-MOMWD-1833-CS-QCBS / PMU/C/37 - Consultancy Services for Construction Component 1: Flood and Quality And Cost- Open - Supervision and Project IBRD / 81450 Post 380,000.00 2,119,809.94 Signed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-10-03 2016-11-01 2016-12-01 2018-08-30 Drainage Management Based Selection International Management for the Construction of St. Sebestian South New Diversion LK-MOMWD-2525-CS-QCBS / PMU/C/04 - Consultancy Component 2: Urban Services for Infrastructure development, infrastructure Quality And Cost- Under Development in Local IBRD / 81450 rehabilitation and capacity Post Open - National 178,125.00 0.00 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 Based Selection Implementation Authorities- Sri building for Metro Colombo Jayawardanepura Kotte local authorities. Municipal Council LK-MOMWD-2526-CS-QCBS Component 2: Urban / PMU/C/06 - Consultancy development, infrastructure Services for Infrastructure Quality And Cost- Under IBRD / 81450 rehabilitation and capacity Post Open - National 107,765.62 77,801.52 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2017-08-31 Development in Local Based Selection Implementation building for Metro Colombo authorities - Kolonnawa local authorities. Urban Council LK-MOMWD-23793-CS- QCBS / PMU/C/21-A - Consultancy Services for Design Review, Construction Component 1: Flood and Quality And Cost- Open - IBRD / 81450 Prior 2,223,958.00 3,023,425.48 Signed 2017-08-04 2017-08-04 2017-08-04 2017-08-04 2017-08-04 2017-08-04 2017-08-04 2020-01-21 Supervision & Project Drainage Management Based Selection International Management for the Design & Building of New Mutwal Tunnel & Torrington Tunnel LK-MOMWD-1825-CS-QCBS / PMU/C/21-A - Consultancy Services for Design Review, Construction Supervision & Component 1: Flood and Quality And Cost- Open - IBRD / 81450 Post 1,100,000.00 0.00 Canceled 2016-09-21 2016-09-21 2016-10-05 2016-10-31 2016-11-30 2016-12-15 2017-01-02 2018-04-02 Project Management for the Drainage Management Based Selection International Design & Building of New Mutwal Tunnel & Torrington Tunnel LK-MOMWD-1826-CS-QCBS / PMU/C/31 - Consultancy Services for the Construction Component 1: Flood and Quality And Cost- Supervision and Project IBRD / 81450 Post Open - National 483,000.00 286,548.19 Signed 2018-03-09 2018-04-08 2018-05-22 2018-06-21 2018-07-21 2018-08-18 2018-09-22 2019-12-21 Drainage Management Based Selection Management for the Improvements to Norris Canal - Stage I. LK-MOMWD-1838-CS-QCBS / PMU/C/07 - Consultancy Services for Project Component 1: Flood and Quality And Cost- Open - Preparation and IBRD / 81450 Post 38,000.00 0.00 Canceled 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2017-12-29 2018-06-29 Drainage Management Based Selection International Implementation Management of Metro Colombo Real Time Control System LK-MOMWD-1835-CS-QCBS / PMU/C/45 - Consultancy Services of Management Component 1: Flood and Quality And Cost- Open - IBRD / 81450 Post 1,000,000.00 0.00 Canceled 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-10-03 2019-04-01 Consultant for flood & Drainage Management Based Selection International Drainage Management Sub Projects LK-MOMWD-1823-CS-QCBS / PMU/C/16-A - Consultancy Services for Design Review, Construction Supervision and Component 1: Flood and Quality And Cost- Open - IBRD / 81450 Post 1,000,000.00 0.00 Canceled 2016-09-21 2016-09-21 2017-03-27 2017-03-27 2017-03-27 2017-05-04 2017-05-25 2019-05-15 Project Management for the Drainage Management Based Selection International Design and Building of St. Sebestian North Lock Gates and Pumping Station Page 9 LK-MOMWD-10573-CS- QCBS / PMU/C/35 Consultancy Services for Contract Management and Component 1: Flood and Quality And Cost- IBRD / 81450 Post Open - National 206,000.00 0.00 Canceled 2017-04-24 2017-07-03 2017-08-18 2017-09-15 2017-09-22 2017-10-19 2017-11-16 2018-11-20 Construction Supervision of Drainage Management Based Selection Improvements to Storm Water Drainage at Saunders Place. LK-MOMWD-86996-CS- QCBS / Consultancy services Component 3: Quality And Cost- Pending for Independent monitoring IBRD / 81450 Post Open - National 25,000.00 0.00 2019-05-02 2019-06-01 2019-06-15 2019-07-13 2019-07-27 2019-08-17 2019-08-31 2020-06-26 Implementation Support Based Selection Implementation & review of Environmental safeguards. (PMU/C/24-A) LK-MOMWD-80061-CS- QCBS / Consultancy services Component 3: Quality And Cost- for independent monitoring IBRD / 81450 Post Open - National 60,000.00 0.00 Canceled 2019-06-03 2019-07-03 2019-07-17 2019-08-14 2019-08-28 2019-09-18 2019-10-02 2020-06-28 Implementation Support Based Selection & review of social safeguards. (PMU/C/38-A) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMWD-1922-CS-INDV Component 2: Urban / PMU/C/42 - Individual development, infrastructure Individual Consultancy Services - IBRD / 81450 rehabilitation and capacity Post Consultant Open 21,428.57 16,722.42 Completed 2016-09-26 2016-09-26 2016-09-26 2016-09-26 2017-04-03 Engineering Consultant for building for Metro Colombo Selection Structural Designs. Eng. local authorities. Mrs. shyama Liyanage LK-MOMWD-1929-CS-INDV / PMU/C/52 - Procurement of Individual Component 1: Flood and Services of Individual IBRD / 81450 Post Consultant Open 49,285.71 38,461.57 Signed 2016-09-26 2016-09-26 2016-09-26 2016-09-26 2017-08-01 Drainage Management Consultant for Micro Selection Tunnelling. LK-MOMWD-2257-CS-INDV / PMU/C/44 - Individual Individual Consultancy Services - Component 3: IBRD / 81450 Post Consultant Open 21,428.57 16,722.42 Completed 2016-10-05 2016-10-05 2016-10-05 2016-10-05 2017-02-21 Engineering Consultant for Implementation Support Selection Procurement Contract & Claims. LK-MOMWD-2260-CS-INDV / PMU/C/55 - Individual Individual Consultancy Services - Component 3: Pending IBRD / 81450 Post Consultant Open 50,000.00 0.00 2016-10-05 2016-10-05 2016-10-05 2016-10-05 2017-10-05 Engineering Consultant for Implementation Support Implementation Selection Quality Control & Quality Assurance(QAQC) LK-MOMWD-2261-CS-INDV / PMU/C/41 - Individual Individual Component 3: Consultancy Services - IBRD / 81450 Post Consultant Open 12,857.14 16,722.42 Completed 2016-10-05 2016-10-05 2016-10-05 2016-10-05 2017-01-25 Implementation Support Consultant for Land Selection Acquisitions. LK-MOMWD-2379-CS-INDV / PMU/C/51 - Individual Individual Component 3: Consultancy Services - IBRD / 81450 Post Consultant Open 17,142.85 13,733.90 Completed 2016-10-07 2016-10-07 2016-10-07 2016-10-07 2017-04-28 Implementation Support Consultant for Selection communication Page 10 LK-MOMWD-2382-CS-INDV / PMU/C/56 - Individual Individual Consultancy Services - Component 1: Flood and IBRD / 81450 Post Consultant Open 73,714.28 55,852.88 Signed 2016-10-07 2016-10-07 2016-10-07 2016-10-07 2017-07-05 Engineering Consultant for Drainage Management Selection Flood Control & Water Management. LK-MOMWD-10582-CS- INDV / PMU/C/58 Individual Individual Component 1: Flood and Consultancy Services - IBRD / 81450 Post Consultant Open 50,000.00 16,722.42 Completed 2017-03-27 2017-03-27 2017-04-20 2017-05-04 2017-10-31 Drainage Management Consultant for Quantity Selection Surveying. LK-MOMWD-1919-CS-INDV / PMU/C/12 - Individual Consultancy Services - Component 2: Urban Engineering Consultant for development, infrastructure Individual Infrastructure Development IBRD / 81450 rehabilitation and capacity Post Consultant Open 70,360.00 13,377.94 Signed 2016-09-26 2016-09-26 2016-09-26 2016-09-26 2017-01-16 Component of MCUDP building for Metro Colombo Selection (Individual consultant was local authorities. selected in liaison with WB Officials through Interviews ) LK-MOMWD-39983-CS- Component 2: Urban INDV / PMU/C/42-A - development, infrastructure Individual Individual Consultancy IBRD / 81450 rehabilitation and capacity Post Consultant Open 24,000.00 10,033.45 Signed 2017-12-18 2017-12-23 2017-12-28 2018-01-02 2020-01-01 Services -Engineering building for Metro Colombo Selection Consultant for Structural local authorities. Designs. Eng. Aravinda Kalugaldeniya LK-MOMWD-39985-CS- Component 2: Urban INDV / PMU/C/57 - development, infrastructure Individual Individual Consultancy IBRD / 81450 rehabilitation and capacity Post Consultant Open 20,000.00 16,722.42 Completed 2017-12-18 2017-12-18 2017-12-18 2017-12-18 2018-06-22 Services -Engineering building for Metro Colombo Selection Consultant for Contract local authorities. Management Eng. Jayawickrama LK-MOMWD-39987-CS- INDV / PMU/C/63 Individual Individual Consultancy Services - Component 1: Flood and IBRD / 81450 Post Consultant Open 31,000.00 2,184.13 Signed 2017-12-18 2017-12-18 2017-12-18 2017-12-18 2020-06-30 Engineering Consultant for Drainage Management Selection Electro Mechanical. Eng. D.E.N. Rajapakshe LK-MOMWD-99192-CS- INDV / PMU/C/64 - Individual Component 3: Under Consultancy Services - IBRD / 81450 Post Consultant Open 21,000.00 32,540.83 2019-02-08 2019-03-01 2019-03-08 2019-03-22 2020-03-21 Implementation Support Implementation Individual Consultant for Selection Contract Management. LK-MOMWD-1928-CS-INDV / PMU/C/43 - Individual Individual Component 1: Flood and Consultancy Services - IBRD / 81450 Post Consultant Open 20,000.00 0.00 Canceled 2016-11-15 2017-01-03 2017-01-24 2017-02-28 2018-02-28 Drainage Management Engineering Consultant for Selection Geo technical; Designs LK-MOMWD-14355-CS-CDS / PMU/C/60 - Procurement of Component 1: Flood and services for RTC center data IBRD / 81450 Prior Direct Selection Direct 430,000.00 0.00 Canceled 2017-12-20 2017-12-30 2018-01-14 2020-06-30 Drainage Management integration and forecasting - Stage II LK-MOMWD-100654-CS- Individual INDV / MCUDP/PMU/C/58-A Component 1: Flood and IBRD / 81450 Post Consultant Open 20,500.00 0.00 Canceled 2019-06-03 2019-06-24 2019-07-01 2019-07-15 2020-06-09 Individual Consultant for Drainage Management Selection Quantity Surveying Page 11 LK-MOMWD-122406-CS- CDS / MCUDP/PMU/C/38-A - Procurement of Consulting Component 3: Pending IBRD / 81450 Post Direct Selection Direct 100,000.00 0.00 2019-07-15 2019-07-25 2019-08-30 2020-02-26 Services for Independent Implementation Support Implementation Monitoring and Review of Safeguards LK-MOMWD-122394-CS- INDV / MCUDP/PMU/C-65 - Component 2: Urban Procuremnt of Services of development, infrastructure Individual Pending Individual Consultant for IBRD / 81450 rehabilitation and capacity Post Consultant Direct 15,500.00 0.00 2019-07-15 2019-07-25 2019-08-08 2019-09-05 2020-03-03 Implementation Nature Interpretation and building for Metro Colombo Selection Wetland Education Services local authorities. at Kotte Rampart LK-MOMWD-14377-CS-CDS / PMU/C/62 - Procurement of Component 1: Flood and Pending services for discharge IBRD / 81450 Post Direct Selection Direct 80,000.00 0.00 2019-09-09 2019-09-21 2019-11-11 2019-12-11 Drainage Management Implementation measurement for RTC system LK-MOMWD-14371-CS-CDS / PMU/C/61 - Procurement of Component 1: Flood and Pending srevices for Install and IBRD / 81450 Post Direct Selection Direct 250,000.00 0.00 2019-09-30 2019-10-10 2019-11-14 2019-12-24 Drainage Management Implementation operation of communication for RTC system Page 12