Procurement Plan I. General 1. Project Information Project Name: EDP II Country: Lebanon Project ID: P118187 Loan/Credit Numbers: 7966 2. Bank's approval date of Procurement Plan Original: November 10, 2010 Revision 3: 27 August 2013 Revision 4: 4 December 2013 Revision 5: 4 June 2014 3. Date of General Procurement Notice II. Goods, Work and Non-Consulting Services Thresholds 1. Prior Review Threshold. Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] 1a. Procurement Category Prior Review Threshold (USD) Comments and First Contract regardless the Goods (ICB) > = 3,000,000 amount Works (ICB) not applicable Goods, Works (NCB) First Contract regardless the amount Goods, Works (Shopping) First Contract Goods, Works (Direct Contracting) All maintenance and upgraded services for equipment, including IT Systems and Non-Consultant Services > = 3,000,000 hardware and software As defined by the operational School Fund manual thresholds using ESDS administrative procedures found acceptable to the Operating Costs Bank. 1b. Procurement Method Procurement Method Threshold (USD) Comments ICB and LIB (Goods) No threshlod NCB (Goods) <= USD 1,000,000 Upgraded June 4, 2014 ICB (Works) not applicable Works Bids are expected to be launched under NCB procedure due to the nature (rehabilitation works, location/disbursement/scattering of the Sites, and local context.) and timing of the Implementation (limited to almost 3 months). This will be requested for WB clearance. NCB (Works) <= 10,000,000 Upgraded June 4, 2014 Shopping (Works, Goods) <= 200,0000 Direct Contracting No threshold ICB (Non-Consultant Services) Procurement of Operation Costs (Direct) <= 2,000 Direct purchase by payment against invoice As defined by the operational School Fund manual thresholds 2. Prequalification. Bidders for _________ shall be prequlified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph 3.17 of the Guidelines): Refer to the relevant CDD project implementation document approved by the Bank 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements: [ncluding advance procurement and retroactive financing, if applicable 6. Procurement Packages with Methods and Time Schedule: See attached "Goods and Works" sheet III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 1a. Selection Category Prior Review Threshold (USD) Comments and First Contract regardless of Consulting Firms (Competitive) >= 1,000,000 contract value Consulting Firms (Single Source) All and First Contract regardless of Individual Consultants (Competitive) >= 300,000 contract value Individual Consultants (Sole Source) All As defined by the operational School Fund manual thresholds 1b. Selection Method Selection Method Threshold (USD) Comments QCBS (Firms) No Threshold CQS, FBS, LCS < 300,000 Consulting Firms (Single Source) No Threshold Individual Consultants (Competitive) No Threshold Individual Consultants (Sole Source) No Threshold Procurement of Operation Costs (Direct) <= 2,000 Direct purchase by payment against invoice As defined by the operational School Fund manual thresholds 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. (POM-3.3.2.1) Note: OPCPR list of ceilings can be found here: http://go.worldbank.org/MKXO98RY40 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule: See attached "Consulting Services" sheet The advertisement should be published in two national newspapers or in a freely accessible electronic portal for at least two days. Contracts expected to cost more than US$ 200,000 shall be advertised in UNDB online and in dgMarket. (EOI: min. 14 days from 5. UNDB posting) The Bank’s Standard Request for Proposal (SRFP) is the mandatory format for the preparation and issuance of the actual RFP for 6. contracts exceeding US$ 200,000, and is the recommended format for smaller contracts. 7. The Procurement Plan will be updated in agreement with the Project Team annually or as required to reflect the actual project implementation needs and improvements in institutional capacity. IV. Implementing Agency Capacity Building Activities with Time Schedule: See attached "Capacity Building" sheet Estimated Contract Cost (in USD) Type of Procurement High Risk Substantial Moderate Risk Low Risk Implementing Risk Implementing Implementing Agency Implementing Agency Agency Agency Works, Turnkey and S&I $ 5 million $ 10 million $ 15 million $ 20 million Goods $ 0.5 million $ 1 million $ 3 million $ 5 million IT Systems, and Non- $ 0.5 million $ 1 million $ 3 million $ 5 million Consulting Firms $ 0.2 million $ 0.5 million $ 1 million $ 2 million Services Individuals $ 0.1 million $ 0.2 million $ 0.3 million $ 0.5 million Lebanon Second Education Development Program PLANNING FOR TRAINING as of April 30, 2015 Proc. System Ref. Execution in days Selection Method Plan vs. Actual Unit Execution in Sub-Comp Costab ref (Mth/ Yr/ months Bank Rev. Completion Completion Comp SN. # Location/ Description of Study[Sty], TOR Start Training (by TTL only Date Date (last Participants Comments # Assignment Lumpsum [LS], Date Start Date ) (original) revision) Workshop [Wsh]) t1 P TR001 TR001 1 1.6 3 training program 3 trips NA PR 20-Nov-11 3-Jan-12 15 0.492 18-Jan-12 NA R 20-Sep-14 3-Nov-14 15 0.49 18-Nov-14 NA A t2 P TR002 TR002 2 2.1 Training of 30 facilitators NA PR 21-Nov-11 4-Jan-12 1464 48 7-Jan-16 NA R 21-Nov-13 4-Jan-14 1464 48 7-Jan-18 NA A P TR003 TR003 3 3.3 Workshops, Training , & NA PR 18-Jun-13 1-Aug-13 1830 60 5-Aug-18 NA Ongoing Study Tours R 27-Apr-13 10-Jun-13 1647 54.00 13-Dec-17 NA A P TR003 TR003 3 3.3 Study tours of TIMSS and NA PR 18-Jun-13 1-Aug-13 1830 60 5-Aug-18 NA Ongoing t3 PIZA R 27-Apr-13 10-Jun-13 1647 54.00 13-Dec-17 NA A 27-Apr-13 24-Oct-14 799.1 26.2 31-Dec-16 P TR003 TR003 3 3.3 Procurement Audit 27-Apr-13 10-Jun-13 4.88 0.16 14-Jun-13 NA R 27-Apr-13 10-Jun-13 4.88 0.16 14-Jun-13 NA Completed A 27-Apr-13 10-Jun-13 4.88 0.16 14-Jun-13 NA 1-Bilal P TR003 TR003 3 3.3 Procurement Works 14-Jun-13 NA Nasser: R 14-Jun-13 NA Completed A 30-Nov-15 4 4-Dec-15 NA Riwa & Maya Lebanon000Seco000procurement0plan0.xlsx Page 3 of 9 3/30/2016 Lebanon Second Education Development Program PROCUREMENT PLAN FOR GOODS AND WORKS as of April 30 , 2015 Plan vs. Actual Proc. System Execution in Execution in Sub-Comp Costab ref Bid. Completi Selection months Interval Interval Interval Interval Interval Interval Interval Interval Method Comp Bid. Doc/Specs Bid Evaluation Contract Completio Ref. # SN. # days Location/ Description of Bank Doc/Specs Invitation on Date Consultant prep. NOL Date Opening & NOL Date Signature Start Date n Date Comments Assignment Rev. prep. Date (last Name End Date Date Recomm. Date (original) Start Date revision) A B C D F G T U T U V W X Y Z AA AB A AC AD AE AF AH AI AJ AK AL AO AP G P W1 PW001 1 1.1 Rehabilitation of 72 KG schools NCB PR 19-Mar-12 30 18-Apr-12 14 18-Apr-12 1 19-Apr-12 28 17-May-12 28 14-Jun-12 14 28-Jun-12 3 1-Jul-12 14 15-Jul-12 122 4 14-Nov-12 NA R 20-Jan-16 45 5-Mar-16 14 19-Mar-16 14 2-Apr-16 30 2-May-16 30 1-Jun-16 14 15-Jun-16 14 29-Jun-16 14 13-Jul-16 122 4 12-Nov-16 NA A P W2 PW002 1 1.1 Rehabilitation of 72 KG schools NCB PR 2-Apr-13 30 2-May-13 2-May-13 1 3-May-13 28 31-May-13 28 28-Jun-13 28-Jun-13 3 1-Jul-13 14 15-Jul-13 122 4 14-Nov-13 NA R 20-Jan-16 45 5-Mar-16 14 19-Mar-16 14 2-Apr-16 30 2-May-16 30 1-Jun-16 14 15-Jun-16 14 29-Jun-16 14 13-Jul-16 122 4 12-Nov-16 NA A P W3 PW003 1 1.1 Rehabilitation of KG schools NCB PO 2-Apr-14 30 2-May-14 2-May-14 1 3-May-14 28 31-May-14 28 28-Jun-14 28-Jun-14 3 1-Jul-14 14 15-Jul-14 122 4 14-Nov-14 NA R NA A P GG1 PG001 1 1.1 Equipment for 103Schools 17 ICB PR 4-Feb-12 30 5-Mar-12 14 5-Mar-12 1 6-Mar-12 42 17-Apr-12 28 15-May-12 14 29-May-12 3 1-Jun-12 14 15-Jun-12 1464 36 18-Jun-16 NA Al Diyar Contract R additional schools KG sections 13-Nov-13 30 26-Dec-13 14 17-Jan-14 11 28-Jan-14 72 8-May-14 50 27-Jun-14 14 11-Jul-14 14 25-Jul-14 14 8-Aug-14 213.5 7 9-Mar-15 NA International Co Completed and A 13-Nov-13 43 26-Dec-13 22 17-Jan-14 11 28-Jan-14 72 8-May-14 21 29-May-14 68 5-Aug-14 29 4-Sep-14 14 4-Sep-14 122 4 4-Jan-15 4-Mar-15 SARL Paid P GG1 PG001 1 1.1 Furniture for 103Schools and 17 ICB PR 4-Feb-12 30 5-Mar-12 14 5-Mar-12 1 6-Mar-12 42 17-Apr-12 28 15-May-12 14 29-May-12 3 1-Jun-12 14 15-Jun-12 1464 36 18-Jun-16 NA Contract Fleifel IND. CO. R additional schools KG sections 13-Nov-13 30 26-Dec-13 14 17-Jan-14 11 28-Jan-14 72 8-May-14 50 27-Jun-14 14 11-Jul-14 14 25-Jul-14 14 8-Aug-14 213.5 7 9-Mar-15 NA Completed and S.A.R.L A 13-Nov-13 43 26-Dec-13 22 17-Jan-14 11 28-Jan-14 72 8-May-14 21 29-May-14 68 5-Aug-14 29 4-Sep-14 14 4-Sep-14 122 4 4-Jan-15 4-Mar-15 Paid P GG2 PG002 1 1.1 Equipment &Furniture for 153 ICB PR 4-Feb-12 30 5-Mar-12 14 5-Mar-12 1 6-Mar-12 42 17-Apr-12 28 15-May-12 14 29-May-12 3 1-Jun-12 14 15-Jun-12 1464 36 18-Jun-16 NA R Schools - KG sections- to be 2-Feb-16 31 4-Mar-16 7 11-Mar-16 12 23-Mar-16 43 5-May-16 30 4-Jun-16 14 18-Jun-16 14 2-Jul-16 7 9-Jul-16 152.5 5 8-Dec-16 NA A rehabilitated under EDP-II P GG3 PG003 1 1.1 Furniture for 110 KG schools ICB PO 4-Feb-12 30 5-Mar-12 5-Mar-12 1 6-Mar-12 28 3-Apr-12 28 1-May-12 14 15-May-12 3 18-May-12 14 1-Jun-12 1464 48 4-Jun-16 NA R 24-Mar-14 30 23-Apr-14 23-Apr-14 14 7-May-14 49 25-Jun-14 35 30-Jul-14 30-Jul-14 21 20-Aug-14 14 3-Sep-14 366 12 4-Sep-15 NA A P GG4 PG004 1 1.1 Replacement Equipment for KG NCB (SS) PR 3-May-15 30 2-Jun-15 14 2-Jun-15 1 3-Jun-15 28 1-Jul-15 28 29-Jul-15 29-Jul-15 3 1-Aug-15 14 15-Aug-15 122 5 15-Dec-15 NA R schools 24-Dec-15 7 31-Dec-15 14 14-Jan-16 3 17-Jan-16 28 14-Feb-16 7 21-Feb-16 14 6-Mar-16 14 20-Mar-16 14 3-Apr-16 152.5 5 2-Sep-16 NA A P GG5 PG005 1 1.1 Replacement Equipment for KG SS PR 3-May-15 30 2-Jun-15 2-Jun-15 1 3-Jun-15 28 1-Jul-15 28 29-Jul-15 29-Jul-15 3 1-Aug-15 14 15-Aug-15 122 4 15-Dec-15 NA R schools 24-Dec-15 7 31-Dec-15 14 14-Jan-16 3 17-Jan-16 28 14-Feb-16 7 21-Feb-16 14 6-Mar-16 14 20-Mar-16 14 3-Apr-16 152.5 5 2-Sep-16 NA A P GG6 PG006 3 3.1 Development /implementation of NCB PR 5-Apr-12 30 5-May-12 14 5-May-12 1 6-May-12 42 17-Jun-12 28 15-Jul-12 14 29-Jul-12 3 1-Aug-12 14 15-Aug-12 488 16 16-Dec-13 NA R document management system, 3-Apr-16 30 3-May-16 3-May-16 14 17-May-16 42 28-Jun-16 28 26-Jul-16 14 9-Aug-16 7 16-Aug-16 14 30-Aug-16 366 12 31-Aug-17 NA A workflow and archiving needs P GG7 PG007 3 3.2 Provision, Installation and Upgrade ICB PR 3-May-12 30 2-Jun-12 14 2-Jun-12 1 3-Jun-12 28 1-Jul-12 28 29-Jul-12 29-Jul-12 3 1-Aug-12 14 15-Aug-12 488 16 16-Dec-13 NA R of Servers (Lot 1) 1-Aug-14 417 22-Sep-15 8 30-Sep-15 21 21-Oct-15 78 7-Jan-16 40 16-Feb-16 14 1-Mar-16 7 8-Mar-16 14 22-Mar-16 91.5 3 21-Jun-16 NA A 21-Jan-15 244 22-Sep-15 8 30-Sep-15 21 21-Oct-15 78 7-Jan-16 P GG7 PG007 3 3.2 Provision and Installation of ICB PR 3-May-12 30 2-Jun-12 14 2-Jun-12 1 3-Jun-12 28 1-Jul-12 28 29-Jul-12 29-Jul-12 3 1-Aug-12 14 15-Aug-12 488 16 16-Dec-13 NA R Servers and Power Lot (Lot 2) 1-Aug-14 417 22-Sep-15 8 30-Sep-15 21 21-Oct-15 78 7-Jan-16 40 16-Feb-16 14 1-Mar-16 7 8-Mar-16 14 22-Mar-16 91.5 3 21-Jun-16 NA 1 A 21-Jan-15 244 22-Sep-15 8 30-Sep-15 21 21-Oct-15 78 7-Jan-16 P GG7 PG007 3 3.2 Provision and Installation of ICB PR 3-May-12 30 2-Jun-12 2-Jun-12 1 3-Jun-12 28 1-Jul-12 28 29-Jul-12 29-Jul-12 3 1-Aug-12 14 15-Aug-12 488 16 16-Dec-13 NA Procurement I R Storage(Lot 3) 1-Aug-14 417 22-Sep-15 8 30-Sep-15 21 21-Oct-15 78 7-Jan-16 40 16-Feb-16 14 1-Mar-16 7 8-Mar-16 14 22-Mar-16 91.5 3 21-Jun-16 NA Process Ongoing C A 21-Jan-15 244 22-Sep-15 8 30-Sep-15 21 21-Oct-15 78 7-Jan-16 B P GG7 PG007 3 3.2 Provision and Installation of ICB PR 3-May-12 30 2-Jun-12 2-Jun-12 1 3-Jun-12 28 1-Jul-12 28 29-Jul-12 29-Jul-12 3 1-Aug-12 14 15-Aug-12 488 16 16-Dec-13 NA R Network and Security (Lot 4) 1-Aug-14 417 22-Sep-15 8 30-Sep-15 21 21-Oct-15 78 7-Jan-16 40 16-Feb-16 14 1-Mar-16 7 8-Mar-16 14 22-Mar-16 152.5 5 21-Aug-16 NA A 21-Jan-15 244 22-Sep-15 8 30-Sep-15 21 21-Oct-15 78 7-Jan-16 P GG7 PG007 3 3.2 Provision and Installation of ICB PR 3-May-12 30 2-Jun-12 2-Jun-12 1 3-Jun-12 28 1-Jul-12 28 29-Jul-12 29-Jul-12 3 1-Aug-12 14 15-Aug-12 488 16 16-Dec-13 NA R Public Schools Connectivity (Lot 5) 1-Aug-14 417 22-Sep-15 8 30-Sep-15 21 21-Oct-15 78 7-Jan-16 40 16-Feb-16 14 1-Mar-16 7 8-Mar-16 14 22-Mar-16 152.5 5 21-Aug-16 NA A 21-Jan-15 244 22-Sep-15 8 30-Sep-15 21 21-Oct-15 78 7-Jan-16 Lebanon000Seco000procurement0plan0.xlsx Page 4 of 9 3/30/2016 Lebanon Second Education Development Program PROCUREMENT PLAN FOR GOODS AND WORKS (Shopping) as of April 30, 2015 Execution in months Proc. System Ref. # Execution in days Selection Method Plan vs. Actual Sub-Comp Costab ref Interval Contract Completion Completion Comp Location/ Description of Specs prep. Contract Consultant Bank Rev. Signature Date Date (last Comments Assignment Start Date Start Date Name Date (original) revision) A C D F G H T U V W X Y Z AC AD P SHG001 2 2.1 Pilot draft module for performance SH PR 1-Jan-00 1-Mar-13 14 15-Mar-13 122 4 15-Jul-13 NA R assessment program for principals 1-Jan-00 1-Mar-13 14 15-Mar-14 122 4 15-Jul-14 A P SHG002 2 2.1 Extending implementatiopn of SH PO 1-Jan-00 1-Mar-15 14 15-Mar-15 366 12 15-Mar-16 NA R module for performance 1-Jan-00 1-Mar-15 14 15-Mar-15 366 12 15-Mar-16 A assessment for programs for P SHG003 2 2.1 Pilot of draft module of school self SH PO 1-Jan-00 1-Mar-13 14 15-Mar-13 122 4 15-Jul-13 NA R assessment mechanism 1-Jan-00 1-Mar-15 14 15-Mar-15 122 4 15-Jul-15 A P SHG004 2 2.1 Extend implementation of module SH PO 1-Jan-00 1-Mar-13 14 15-Mar-13 366 12 16-Mar-14 NA R for school self assessment 1-Jan-00 1-Mar-16 14 15-Mar-16 366 12 16-Mar-17 A mechanism P SHG005 2 2.1 new school vision printing of SH PR 1-Jan-00 1-Mar-12 14 15-Mar-12 30.5 1 14-Apr-12 NA R materials 19-Jan-14 11-Feb-00 14 15-Mar-14 30.5 1 14-Apr-14 A P SHG006 2 2.1 Workshops (lunch breaks, SH PO 1-Jan-00 18-May-13 14 1-Jun-13 1586 52 4-Oct-17 NA R Coffee breaks) 7-Jul-14 11-Feb-00 14 15-Mar-14 1022 34 31-Dec-16 A P SHG007 3 3.2 Financial information System SH PO 1-Jan-00 21-Apr-12 14 5-May-12 122 4 4-Sep-12 NA Dynamesh Completed R 7-Mar-12 15-Feb-00 14 29-Feb-00 122 4 30-Jun-00 A 12-Jan-12 21-Apr-12 14 5-May-12 122 4 4-Sep-12 4-Sep-12 P SHG008 3 3.2 Data Room Infrastructure SH PO 1-Jan-00 17-Sep-13 14 1-Oct-13 122 4 31-Jan-14 NA R Construction (Works might be done A by Government-MEHE technical documents and supervision only ) P SHG009 3 3.2 Data Room Infrastructure SH PO 1-Jan-00 17-Sep-13 14 1-Oct-13 122 4 31-Jan-14 NA R Construction (Works might be done A by Government-MEHE technical documents and supervision only ) P SHG010 3 3.3 Production and distribution of SH PO 1-Jan-00 1-Jan-12 14 15-Jan-12 1464 48 18-Jan-16 NA R annual M&E report 21-Nov-13 11-Feb-00 14 15-Jan-14 1464 48 18-Jan-18 A P SHG011 3 3.3 ESDS Office Equipment SH PO 1-Jan-00 18-Oct-13 14 1-Nov-13 1464 24 4-Nov-17 NA R &Furniture 1-Sep-14 11-Feb-00 14 15-Jan-14 1082 35 31-Dec-16 A P SHG012 3 3.2 Regional Office Data Centers SH PO 1-Jan-00 18-Oct-13 14 1-Nov-13 1464 24 4-Nov-17 NA R Implementation 1-Dec-14 11-Feb-00 14 15-Jan-14 366 12 16-Jan-15 A P SHG013 3 3.3 Storage (Enclosure and tapes) SH PO 1-Jan-00 18-Oct-13 14 1-Nov-13 1464 24 4-Nov-17 NA Midware Data Completed R 7-Feb-14 12-May-14 12-May-14 60 2 11-Jul-14 Systems Sal A 7-Feb-14 12-May-14 12-May-14 60 2 11-Jul-14 MDS P SHG014 3 3.3 Operating Costs SH NA 1-Jan-00 18-Oct-13 14 1-Nov-13 1464 24 4-Nov-17 NA Ongoing R 1-Jun-13 31-Dec-17 A NA P SHG015 3 3.1 Physical Storage cabinet - SH NA 1-Jan-00 18-Oct-13 14 1-Nov-13 1464 24 4-Nov-17 NA Albert Completed and R National Exams Department 23-Oct-14 4-May-15 4-May-15 45 1.5 18-Jun-15 NA Massaad Paid A Results Registers 23-Oct-14 7-May-15 7-May-15 45 1.5 21-Jun-15 Sarl Lebanon000Seco000procurement0plan0.xlsx Page 5 of 9 3/30/2016 Lebanon Second Education Development Program PROCUREMENT PLAN FOR CONSULTANCY SERVICES - CONSULTING FIRMS as of April 30, 2015 Unit Execution in days Proc. System Ref. Selection Method Plan vs. Actual (Mth/ Yr/ Execution in Sub-Comp Costab ref Finan. Final Contract months Interval Interval Interval Interval Interval Interval Interval Interval Interval Interval Interval Interval Interval Interval Interval Interval Study[Sty], Short RFP Technical Contract Completion Completion Comp SN. # TOR end Adv. EOI Public Evaluation negotiatio Contract Consultant Location/ Description of Assignment Lumpsum Bank Rev. TOR Start Date NOL Date Listing NOL Date RFP prep. NOL Date Submission Evaluation NOL Date NOL Date signature Date Date (last Comments # Date end Date opening Report n/Award- Start Date Name [LS], Report Date Date Report Date Date (original) revision) Date Date Draft Workshop [Wsh]) A B C D E F G H I J K L M N O P Q R S T U V W X Y Z A A AB AD AE AF A AH AI AJ AK AL A AN AO AP AQ AR AU AV A C G M P FC01 FC01 1 1.2 Consultancy Services for Design and QCBS PR 18-Mar-12 14 1-Apr-12 1-Apr-12 14 15-Apr-12 7 22-Apr-12 22-Apr-12 7 29-Apr-12 29-Apr-12 28 27-May-12 7 3-Jun-12 3-Jun-12 14 17-Jun-12 5 22-Jun-12 7 29-Jun-12 29-Jun-12 2 1-Jul-12 2 3-Jul-12 793 26 4-Sep-14 NA Spectrum Contract and Contract R supervision -Rehabilitation works of 16-Jun-13 152 15-Nov-13 3 18-Nov-13 31 19-Dec-13 21 9-May-14 14-May-14 9-May-14 5 14-May-14 46 7-Jul-14 21 28-Jul-14 14 11-Aug-14 14 25-Aug-14 7 1-Sep-14 14 15-Sep-14 14 29-Sep-14 215 2-May-15 14 16-May-15 595 20 31-Dec-16 NA Amendment Signed and A 144 pre-school sections 16-Jun-13 152 15-Nov-13 3 18-Nov-13 31 19-Dec-13 43 9-May-14 5 14-May-14 9-May-14 5 14-May-14 54 7-Jul-14 54 30-Aug-14 10 9-Sep-14 7 16-Sep-14 7 23-Sep-14 20-Oct-14 4 24-Oct-14 238 19-Jun-15 14 3-Jul-15 547 18 31-Dec-16 N/A Ongoing P FC02 FC02 1 1.2 Early Childhood Education QCBS PO 18-Apr-11 14 2-May-11 2-May-11 14 16-May-11 7 23-May-11 23-May-11 7 30-May-11 30-May-11 28 27-Jun-11 7 4-Jul-11 4-Jul-11 14 18-Jul-11 5 23-Jul-11 7 30-Jul-11 30-Jul-11 2 1-Aug-11 2 3-Aug-11 91.5 3 2-Nov-11 NA R 2-Dec-14 330 28-Oct-15 3 31-Oct-15 31 1-Dec-15 14 15-Dec-15 14 29-Dec-15 7 5-Jan-16 14 19-Jan-16 42 1-Mar-16 21 22-Mar-16 14 5-Apr-16 14 19-Apr-16 7 26-Apr-16 21 17-May-16 14 31-May-16 21 21-Jun-16 3 24-Jun-16 549 18 25-Dec-17 NA A P FC03 FC03 2 2.1 Education LeadershipFirm I: QCBS PR 1-Jul-13 14 15-Jul-13 14 29-Jul-13 14 12-Aug-13 7 19-Aug-13 14 2-Sep-13 7 9-Sep-13 14 23-Sep-13 35 28-Oct-13 7 4-Nov-13 14 18-Nov-13 14 2-Dec-13 5 7-Dec-13 7 14-Dec-13 14 28-Dec-13 2 30-Dec-13 2 1-Jan-14 1098 36 3-Jan-17 NA Pearson - ERC Contract signed and Ongoing R Professional Development Program 6-Jul-13 33 8-Aug-13 26 3-Sep-13 66 8-Nov-13 50 4-Feb-14 14 18-Feb-14 7 25-Feb-14 14 11-Mar-14 63 13-May-14 14 15-Jul-14 14 29-Jul-14 14 12-Aug-14 5 12-Aug-14 14 8-Oct-14 8 16-Oct-14 35 20-Nov-14 7 27-Nov-14 765 25 31-Dec-16 NA A for School Principals &Administrators 6-Jul-13 33 8-Aug-13 26 3-Sep-13 66 8-Nov-13 88 4-Feb-14 34 10-Mar-14 4 14-Mar-14 10-Mar-14 63 12-May-14 64 15-Jul-14 6 21-Jul-14 3 24-Jul-14 8 1-Aug-14 68 8-Oct-14 8 16-Oct-14 15-Dec-14 7 15-Dec-14 747 24 31-Dec-16 P FC04 FC04 2 2.1 Education LeadershipFirm II: QCBS PR 15-Dec-13 14 29-Dec-13 29-Dec-13 14 12-Jan-14 7 19-Jan-14 19-Jan-14 7 26-Jan-14 26-Jan-14 28 23-Feb-14 7 2-Mar-14 2-Mar-14 14 16-Mar-14 5 21-Mar-14 7 28-Mar-14 28-Mar-14 2 30-Mar-14 2 1-Apr-14 732 24 2-Apr-16 NA British Council, Contract Signed and Ongoing R Consultancy Services for Design 6-Aug-13 111 25-Nov-13 3 28-Nov-13 46 13-Jan-14 116 9-May-14 5 14-May-14 9-May-14 5 14-May-14 47 30-Jun-14 58 27-Aug-14 14 3-Sep-14 23 26-Sep-14 171 16-Mar-15 16-Mar-15 4 20-Mar-15 45 4-May-15 7 11-May-15 600 20 31-Dec-16 NA LU,LAU,Intertech A &Delivery of School Improvement 6-Aug-13 111 25-Nov-13 3 28-Nov-13 46 13-Jan-14 116 9-May-14 5 14-May-14 9-May-14 5 14-May-14 47 30-Jun-14 58 27-Aug-14 3-Sep-14 23 26-Sep-14 171 16-Mar-15 16-Mar-15 4 20-Mar-15 48 7-May-15 7-May-15 604 20 31-Dec-16 Batinorm Programs P FC05 FC05 2 2.2 Teacher professional development QCBS PR 15-Dec-13 14 29-Dec-13 29-Dec-13 14 12-Jan-14 7 19-Jan-14 19-Jan-14 7 26-Jan-14 26-Jan-14 28 23-Feb-14 7 2-Mar-14 2-Mar-14 14 16-Mar-14 5 21-Mar-14 7 28-Mar-14 28-Mar-14 2 30-Mar-14 2 1-Apr-14 915 30 2-Oct-16 NA R 30-Jan-16 30 29-Feb-16 14 14-Mar-16 30 13-Apr-16 21 4-May-16 14 18-May-16 7 25-May-16 60 24-Jul-16 42 4-Sep-16 14 18-Sep-16 14 2-Oct-16 14 16-Oct-16 5 21-Oct-16 14 4-Nov-16 14 18-Nov-16 14 2-Dec-16 7 9-Dec-16 365 24 9-Dec-17 NA A P FC06 FC06 2 2.2 Training of surplus teachers on new SSS PR 4-Jun-14 14 18-Jun-14 14 2-Jul-14 2-Jul-14 2-Jul-14 2-Jul-14 2 4-Jul-14 14 18-Jul-14 28 15-Aug-14 7 22-Aug-14 14 5-Sep-14 5-Sep-14 1 6-Sep-14 7 13-Sep-14 14 27-Sep-14 2 29-Sep-14 2 1-Oct-14 366 12 2-Oct-15 NA R assigned roales 8-Feb-16 14 22-Feb-16 14 7-Mar-16 7-Mar-16 7-Mar-16 7-Mar-16 7 14-Mar-16 14 28-Mar-16 28 25-Apr-16 14 9-May-16 14 23-May-16 23-May-16 5 28-May-16 14 11-Jun-16 14 25-Jun-16 2 27-Jun-16 7 4-Jul-16 366 12 5-Jul-17 NA A P FC06 FC06 3 3.1 Firm to be named (NQF) QCBS PO 15-Dec-13 14 29-Dec-13 29-Dec-13 14 12-Jan-14 7 19-Jan-14 19-Jan-14 7 26-Jan-14 26-Jan-14 28 23-Feb-14 7 2-Mar-14 2-Mar-14 14 16-Mar-14 5 21-Mar-14 7 28-Mar-14 28-Mar-14 2 30-Mar-14 2 1-Apr-14 1098 36 3-Apr-17 NA R NA A n P FC06 A FC06 A 3 3.1 Development Regional Educational QCBS PR 28-Feb-14 33 2-Apr-14 26 28-Apr-14 66 3-Jul-14 21 24-Jul-14 14 7-Aug-14 7 14-Aug-14 60 13-Oct-14 42 24-Nov-14 14 8-Dec-14 14 22-Dec-14 14 5-Jan-15 5 10-Jan-15 14 24-Jan-15 14 7-Feb-15 14 21-Feb-15 7 28-Feb-15 1000 40 24-Nov-17 NA e R Offices, Budgeting & Accounting, 1-Mar-16 33 3-Apr-16 26 29-Apr-16 66 4-Jul-16 21 25-Jul-16 14 8-Aug-16 7 15-Aug-16 60 14-Oct-16 42 25-Nov-16 14 9-Dec-16 14 23-Dec-16 14 6-Jan-17 5 11-Jan-17 14 25-Jan-17 14 8-Feb-17 14 22-Feb-17 7 1-Mar-17 305 10 31-Dec-17 NA w A Office management and Communication Procedures n P FC06 B FC06 B 3 3.1 Development Private Education QCBS PR 28-Feb-14 33 2-Apr-14 26 28-Apr-14 66 3-Jul-14 21 24-Jul-14 14 7-Aug-14 7 14-Aug-14 60 13-Oct-14 42 24-Nov-14 14 8-Dec-14 14 22-Dec-14 14 5-Jan-15 5 10-Jan-15 14 24-Jan-15 14 7-Feb-15 14 21-Feb-15 7 28-Feb-15 1000 40 24-Nov-17 NA e R Service, Budgeting & Accounting, 1-Mar-16 33 3-Apr-16 26 29-Apr-16 66 4-Jul-16 21 25-Jul-16 14 8-Aug-16 7 15-Aug-16 60 14-Oct-16 42 25-Nov-16 14 9-Dec-16 14 23-Dec-16 14 6-Jan-17 5 11-Jan-17 14 25-Jan-17 14 8-Feb-17 14 22-Feb-17 7 1-Mar-17 305 10 31-Dec-17 NA w A Office management and Communication Procedures n P FC06 C FC06 C 3 3.1 Department d'orientation QCBS PR 28-Feb-14 33 2-Apr-14 26 28-Apr-14 66 3-Jul-14 21 24-Jul-14 14 7-Aug-14 7 14-Aug-14 60 13-Oct-14 42 24-Nov-14 14 8-Dec-14 14 22-Dec-14 14 5-Jan-15 5 10-Jan-15 14 24-Jan-15 14 7-Feb-15 14 21-Feb-15 7 28-Feb-15 1000 40 24-Nov-17 NA e R pedagogique: School Health Unit 1-Mar-16 33 3-Apr-16 26 29-Apr-16 66 4-Jul-16 21 25-Jul-16 14 8-Aug-16 7 15-Aug-16 60 14-Oct-16 42 25-Nov-16 14 9-Dec-16 14 23-Dec-16 14 6-Jan-17 5 11-Jan-17 14 25-Jan-17 14 8-Feb-17 14 22-Feb-17 7 1-Mar-17 305 10 31-Dec-17 NA w A (1300 Schools) n P FC06 D FC06 D 3 3.1 Development /implementation of QCBS PR 28-Feb-14 33 2-Apr-14 26 28-Apr-14 66 3-Jul-14 21 24-Jul-14 14 7-Aug-14 7 14-Aug-14 60 13-Oct-14 42 24-Nov-14 14 8-Dec-14 14 22-Dec-14 14 5-Jan-15 5 10-Jan-15 14 24-Jan-15 14 7-Feb-15 14 21-Feb-15 7 28-Feb-15 1000 40 24-Nov-17 NA e R document management system, 1-Mar-16 33 3-Apr-16 26 29-Apr-16 66 4-Jul-16 21 25-Jul-16 14 8-Aug-16 7 15-Aug-16 60 14-Oct-16 42 25-Nov-16 14 9-Dec-16 14 23-Dec-16 14 6-Jan-17 5 11-Jan-17 14 25-Jan-17 14 8-Feb-17 14 22-Feb-17 7 1-Mar-17 305 10 31-Dec-17 NA w A workflow and archiving needs P FC06 FC06 3 3.1 Design and Delivery of MEHE National QCBS PO 28-Feb-14 33 2-Apr-14 26 28-Apr-14 66 3-Jul-14 21 24-Jul-14 14 7-Aug-14 7 14-Aug-14 60 13-Oct-14 42 24-Nov-14 14 8-Dec-14 14 22-Dec-14 14 5-Jan-15 5 10-Jan-15 14 24-Jan-15 14 7-Feb-15 14 21-Feb-15 7 28-Feb-15 1000 40 24-Nov-17 NA On Hold R Exams Registers Archiving and 4-Jan-16 30 3-Feb-16 14 17-Feb-16 14 2-Mar-16 30 1-Apr-16 N/A 14 15-Apr-16 N/A 45 30-May-16 30 29-Jun-16 N/A 14 13-Jul-16 5 13-Jul-16 14 27-Jul-16 14 10-Aug-16 14 24-Aug-16 7 31-Aug-16 365 12 31-Aug-17 NA A Certification 26-Mar-14 33 25-Apr-14 10 5-May-14 65 9-Jul-14 56 3-Sep-14 N/A 20-Oct-14 N/A 2-Dec-14 30-Dec-14 N/A 14-May-15 P FC07 FC07 3 3.1 Operational Training Program for QCBS PO 18-Aug-11 14 1-Sep-11 1-Sep-11 14 15-Sep-11 7 22-Sep-11 22-Sep-11 7 29-Sep-11 29-Sep-11 28 27-Oct-11 7 3-Nov-11 3-Nov-11 14 17-Nov-11 5 22-Nov-11 7 29-Nov-11 29-Nov-11 2 1-Dec-11 2 3-Dec-11 366 12 3-Dec-12 NA R MEHE personnel 15-Mar-16 14 29-Mar-16 29-Mar-16 14 12-Apr-16 7 19-Apr-16 19-Apr-16 7 19-Apr-16 45 3-Jun-16 28 1-Jul-16 7 8-Jul-16 8-Jul-16 14 22-Jul-16 5 27-Jul-16 14 10-Aug-16 10-Aug-16 7 17-Aug-16 3 20-Aug-16 366 12 21-Aug-17 NA A P FC11 FC11 3 3.1 TIMSS SSS PR 6-Sep-10 14 20-Sep-10 14 4-Oct-10 4-Oct-10 4-Oct-10 4-Oct-10 2 6-Oct-10 14 20-Oct-10 28 17-Nov-10 7 24-Nov-10 14 8-Dec-10 8-Dec-10 1 9-Dec-10 7 16-Dec-10 14 30-Dec-10 2 1-Jan-11 2 3-Jan-11 1830 60 7-Jan-16 NA TIMSS Ongoing R 1-Jan-13 14 15-Jan-13 14 29-Jan-13 14 12-Feb-13 12-Feb-13 14 26-Feb-13 7 5-Mar-13 14 19-Mar-13 28 16-Apr-13 7 23-Apr-13 14 7-May-13 7-May-13 3 10-May-13 7 17-May-13 14 31-May-13 7 7-Jun-13 3 10-Jun-13 1098 36 12-Jun-16 NA A 1-Jan-13 2-May-13 2-May-13 3 14 5-May-13 7 2-May-13 1339 43.90 31-Dec-16 P FC12 FC12 3 3.1 PISA SSS PR 6-Sep-10 14 20-Sep-10 14 4-Oct-10 4-Oct-10 4-Oct-10 4-Oct-10 2 6-Oct-10 14 20-Oct-10 28 17-Nov-10 7 24-Nov-10 14 8-Dec-10 8-Dec-10 1 9-Dec-10 7 16-Dec-10 14 30-Dec-10 2 1-Jan-11 2 3-Jan-11 1830 60 7-Jan-16 NA PISA R 1-May-14 14 15-May-14 14 29-May-14 14 12-Jun-14 12-Jun-14 14 26-Jun-14 7 3-Jul-14 14 17-Jul-14 28 14-Aug-14 7 21-Aug-14 14 4-Sep-14 4-Sep-14 3 7-Sep-14 7 14-Sep-14 14 28-Sep-14 7 5-Oct-14 3 8-Oct-14 814.35 26.7 30-Dec-16 NA A 1-Jan-13 2-May-13 2-May-13 3 5-May-13 5-Sep-14 848.205 27.81 31-Dec-16 P FC14 FC14 3 3.2 Portal Software QCBS PO 19-Jul-11 14 2-Aug-11 2-Aug-11 14 16-Aug-11 7 23-Aug-11 23-Aug-11 7 30-Aug-11 30-Aug-11 28 27-Sep-11 7 4-Oct-11 4-Oct-11 14 18-Oct-11 5 23-Oct-11 7 30-Oct-11 30-Oct-11 2 1-Nov-11 2 3-Nov-11 732 24 4-Nov-13 NA R 16-Mar-16 14 30-Mar-16 30-Mar-16 14 13-Apr-16 7 20-Apr-16 20-Apr-16 7 27-Apr-16 27-Apr-16 28 25-May-16 7 1-Jun-16 1-Jun-16 14 15-Jun-16 5 20-Jun-16 7 27-Jun-16 27-Jun-16 3 30-Jun-16 3 3-Jul-16 545.95 17.9 30-Dec-17 NA A P FC15 FC15 3 3.2 Maintenance and enhancement of QCBS PR 18-Mar-11 14 1-Apr-11 1-Apr-11 14 15-Apr-11 7 22-Apr-11 22-Apr-11 7 29-Apr-11 29-Apr-11 28 27-May-11 7 3-Jun-11 3-Jun-11 14 17-Jun-11 5 22-Jun-11 7 29-Jun-11 29-Jun-11 2 1-Jul-11 2 3-Jul-11 366 12 3-Jul-12 NA R running application 15-May-16 30 14-Jun-16 14 28-Jun-16 21 19-Jul-16 14 2-Aug-16 14 16-Aug-16 7 23-Aug-16 14 6-Sep-16 42 18-Oct-16 21 8-Nov-16 14 22-Nov-16 14 6-Dec-16 7 13-Dec-16 21 3-Jan-17 14 17-Jan-17 21 7-Feb-17 14 21-Feb-17 311.1 10.2 29-Dec-17 NA A P FC17 FC17 3 3.2 Development and Consolidation of QCBS PO 19-May-12 14 2-Jun-12 2-Jun-12 14 16-Jun-12 7 23-Jun-12 23-Jun-12 7 30-Jun-12 30-Jun-12 28 28-Jul-12 7 4-Aug-12 4-Aug-12 14 18-Aug-12 5 23-Aug-12 7 30-Aug-12 30-Aug-12 2 1-Sep-12 2 3-Sep-12 549 18 6-Mar-14 NA R Applications 17-Jun-16 14 1-Jul-16 1-Jul-16 14 15-Jul-16 7 22-Jul-16 22-Jul-16 7 29-Jul-16 29-Jul-16 28 26-Aug-16 7 2-Sep-16 2-Sep-16 14 16-Sep-16 5 21-Sep-16 7 28-Sep-16 28-Sep-16 3 1-Oct-16 3 4-Oct-16 366 12 5-Oct-17 NA A P FC18 FC18 3 3.1 External Auditor LCS PR 18-Nov-12 14 2-Dec-12 14 16-Dec-12 14 30-Dec-12 7 6-Jan-13 6-Jan-13 7 13-Jan-13 14 27-Jan-13 28 24-Feb-13 7 3-Mar-13 14 17-Mar-13 14 31-Mar-13 5 5-Apr-13 7 12-Apr-13 14 26-Apr-13 2 28-Apr-13 3 1-May-13 2196 72 6-May-19 NA PriceWaterHouse Contract Signed and Ongoing R 6-Jan-14 15 21-Jan-14 3 24-Jan-14 6 30-Jan-14 7 20-Mar-14 31-Mar-14 7 20-Mar-14 11 31-Mar-14 22 22-Apr-14 24 16-May-14 14 30-May-14 14 13-Jun-14 5 18-Jun-14 7 25-Jun-14 14 9-Jul-14 3 12-Jul-14 3 15-Jul-14 1098 36 17-Jul-17 NA Coopers A 6-Jan-14 15 21-Jan-14 3 24-Jan-14 6 30-Jan-14 36 20-Mar-14 31-Mar-14 20-Mar-14 11 31-Mar-14 22 22-Apr-14 24 16-May-14 7 23-May-14 6 29-May-14 7 5-Jun-14 5-Jun-14 6 11-Jun-14 1 12-Jun-14 12-Jun-14 1145.275 37.55 31-Jul-17 P FC19 FC19 3 3.1 Internal Auditor LCS PR 14-Jan-13 14 28-Jan-13 28-Jan-13 14 11-Feb-13 7 18-Feb-13 18-Feb-13 7 25-Feb-13 25-Feb-13 28 25-Mar-13 7 1-Apr-13 1-Apr-13 14 15-Apr-13 5 20-Apr-13 7 27-Apr-13 27-Apr-13 2 29-Apr-13 2 1-May-13 2196 72 6-May-19 NA Grant Thornton Contract Signed and Ongoing R 5-Aug-13 23 28-Aug-13 8 5-Sep-13 62 6-Nov-13 21 19-Dec-13 19-Dec-13 7 19-Dec-13 14 27-Dec-13 24 20-Jan-14 22 11-Feb-14 7 18-Feb-14 14 27-Feb-14 12 11-Mar-14 11-Mar-14 3 14-Mar-14 3 10-Apr-14 10-Apr-14 1098 36 31-Dec-16 NA A 5-Aug-13 23 28-Aug-13 8 5-Sep-13 62 6-Nov-13 43 19-Dec-13 19-Dec-13 19-Dec-13 8 27-Dec-13 24 20-Jan-14 22 11-Feb-14 7 18-Feb-14 9 27-Feb-14 12 11-Mar-14 11-Mar-14 3 14-Mar-14 27 10-Apr-14 10-Apr-14 1098 36 31-Dec-16 P FC20 FC20 3 3.3 M&E Studies QCBS PO 17-Mar-13 14 31-Mar-13 31-Mar-13 14 14-Apr-13 7 21-Apr-13 21-Apr-13 7 28-Apr-13 28-Apr-13 28 26-May-13 7 2-Jun-13 2-Jun-13 14 16-Jun-13 5 21-Jun-13 7 28-Jun-13 28-Jun-13 2 30-Jun-13 2 2-Jul-13 1098 36 4-Jul-16 NA R 10-Mar-16 14 24-Mar-16 24-Mar-16 14 7-Apr-16 7 14-Apr-16 14-Apr-16 7 21-Apr-16 21-Apr-16 28 19-May-16 7 26-May-16 26-May-16 14 9-Jun-16 5 14-Jun-16 7 21-Jun-16 21-Jun-16 3 24-Jun-16 3 27-Jun-16 549 18 28-Dec-17 NA A Lebanon000Seco000procurement0plan0.xlsx Page 6 of 9 3/30/2016 Lebanon Second Education Development Program EDP II PROCUREMENT PLAN FOR CONSULTANCY SERVICES - INDIVIDUAL CONSULTANTS as of April 30, 2015 Execution in days Proc. System Ref. Selection Method Plan vs. Actual Unit Execution in Sub-Comp Costab ref (Mth/ Yr/ Short Contract months Interval Interval Interval Interval Interval Interval Interval Interval Interval Contract Completion Completion Contract Comp SN. # Location/ Description of Study[Sty], TOR Start Adv. EOI Listing negotiation/ Contract Bank Rev. TOR end Date NOL Date NOL Date NOL Date signature Date Date (last amount US$ Consultant Name Comments # Assignment Lumpsum [LS], Date end Date Report Award- Start Date Date (original) revision) (original) Workshop Date Draft [Wsh]) A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AG AH P IC020 IC020 1 1.2 Learning Difficulty Assessment IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA Re-launched R Consultant 4-Jun-14 14 18-Jun-14 25-Jun-14 14 27-Jan-16 35 2-Mar-16 N/A 9-Mar-16 16-Mar-16 7 23-Mar-16 2 25-Mar-16 40 2 4-May-16 NA NA (Early Childhood) A 4-Jun-14 14 18-Jun-14 12 30-Jun-14 27-Jan-16 N/A P IC033 IC033 2 2.1 Education Expert (Principals SSS PR 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA Contract Signed Standards and Principals Self- and Ongoing( R Assessment Model) 22-May-15 14 5-Jun-15 5 10-Jun-15 N/A N/A N/A 17-Jun-15 7 24-Jun-15 30 24-Jul-15 2 26-Jul-15 30.5 1 25-Aug-15 NA NA Rima Karami the level of effort is Akkary 35 working days A 22-May-15 14 5-Jun-15 5 10-Jun-15 N/A N/A N/A 18-Jun-15 4 22-Jun-15 35 27-Jul-15 27-Jul-15 35 1.148 31-Dec-16 $14,980.00 not consecutive) P IC035 IC035 2 2.2 Consultant in TPD - Teacher IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA the level of effort is NEW R 25-Feb-16 30 26-Mar-16 N/A 14 9-Apr-16 35 14-May-16 N/A 7 21-May-16 N/A 7 28-May-16 2 30-May-16 36 1.2 31-Dec-16 NA NA 36 working days A N/A not consecutive P IC036 IC036 2 2.2 Consultant in TPD - Technical IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA the level of effort is Platform Developer and NEW 27 working days R Administrator 25-Feb-16 30 26-Mar-16 N/A 14 9-Apr-16 35 14-May-16 N/A 7 21-May-16 N/A 7 28-May-16 2 30-May-16 27 1 31-Dec-16 NA NA not consecutive A P IC037 IC037 2 2.2 Consultant in TPD - Content IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA the level of effort is NEW Management Technician 17 working days R 25-Feb-16 30 26-Mar-16 N/A 14 9-Apr-16 35 14-May-16 N/A 7 21-May-16 N/A 7 28-May-16 2 30-May-16 17 0.6 31-Dec-16 NA NA A not consecutive P IC038 IC038 2 2.2 Consultant in TPD - Pedagogical IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA the level of effort is Counselors from DOPS NEW 45 working days R 25-Feb-16 30 26-Mar-16 N/A 14 9-Apr-16 35 14-May-16 N/A 7 21-May-16 N/A 7 28-May-16 2 30-May-16 45 1.5 31-Dec-16 NA NA not consecutive A P IC039 IC039 2 2.2 Consultant in TPD - Psychological IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA the level of effort is NEW R Counselors from CERD 25-Feb-16 30 26-Mar-16 N/A 14 9-Apr-16 35 14-May-16 N/A 7 21-May-16 N/A 7 28-May-16 2 30-May-16 47 1.6 31-Dec-16 NA NA 47 working days A N/A not consecutive P IC040 IC040 2 2.2 Consultant in TPD - Teacher IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA the level of effort is Trainers NEW 45 working days R 25-Feb-16 30 26-Mar-16 N/A 14 9-Apr-16 35 14-May-16 N/A 7 21-May-16 N/A 7 28-May-16 2 30-May-16 45 1.5 31-Dec-16 NA NA not consecutive A 1 P IC021 IC021 2 2.1 Development and delivery of IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA R training Program for WG members 6-Aug-13 14 20-Aug-13 20-Aug-13 14 3-Sep-13 7 10-Sep-13 10-Sep-13 7 17-Sep-13 17-Sep-13 7 24-Sep-13 2 1-Oct-13 30.5 1 31-Oct-13 NA NA A P IC022 IC022 2 2.1 Development and delivery of IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA R training Program for WG members 6-Aug-13 14 20-Aug-13 20-Aug-13 14 3-Sep-13 7 10-Sep-13 10-Sep-13 7 17-Sep-13 17-Sep-13 7 24-Sep-13 2 1-Oct-13 30.5 1 31-Oct-13 NA NA A P IC023 IC023 2 2.1 Development of School Princuipal IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA R Career Chart 11-Aug-16 14 25-Aug-16 25-Aug-16 14 8-Sep-16 7 15-Sep-16 15-Sep-16 7 22-Sep-16 22-Sep-16 7 29-Sep-16 2 1-Oct-16 91.5 3 31-Dec-16 NA NA A P IC024 IC024 2 2.1 Development and delivery of IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA R training Program for WG members #REF! 11-Aug-16 14 25-Aug-16 25-Aug-16 14 8-Sep-16 7 15-Sep-16 15-Sep-16 7 22-Sep-16 22-Sep-16 7 29-Sep-16 2 1-Oct-16 91.5 3 31-Dec-16 NA NA A P IC025 IC025 2 2.1 Develop Draft Standards and IC PO 13-May-11 14 27-May-11 27-May-11 14 10-Jun-11 7 17-Jun-11 17-Jun-11 7 24-Jun-11 24-Jun-11 7 1-Jul-11 2 3-Jul-11 1464 48 6-Jul-15 NA NA regulation mechanism fro private R school licensing 2-Sep-14 14 16-Sep-14 3 19-Sep-14 14 3-Oct-14 7 10-Oct-14 2 12-Oct-14 7 19-Oct-14 2 21-Oct-14 7 28-Oct-14 2 30-Oct-14 91.5 3 29-Jan-15 NA NA A P IC026 IC026 3 3.1 Manual for simplification and IC PO 13-Aug-11 14 27-Aug-11 27-Aug-11 14 10-Sep-11 7 17-Sep-11 17-Sep-11 7 24-Sep-11 24-Sep-11 7 1-Oct-11 2 3-Oct-11 61 2 3-Dec-11 NA NA streamlining of administrative R procedures 9-Apr-15 14 23-Apr-15 3 26-Apr-15 14 10-May-15 7 17-May-15 2 19-May-15 7 26-May-15 2 28-May-15 7 4-Jun-15 2 6-Jun-15 244 8 5-Feb-16 NA NA A P IC027 IC027 3 3.1 Capacity building for MTEF and IC PO 13-Aug-11 14 27-Aug-11 27-Aug-11 14 10-Sep-11 7 17-Sep-11 17-Sep-11 7 24-Sep-11 24-Sep-11 7 1-Oct-11 2 3-Oct-11 1464 48 6-Oct-15 NA NA R PBB 2-Dec-13 14 16-Dec-13 3 19-Dec-13 14 2-Jan-14 7 9-Jan-14 2 11-Jan-14 7 18-Jan-14 2 20-Jan-14 7 27-Jan-14 2 29-Jan-14 366 12 30-Jan-15 NA NA A P IC028 IC028 3 3.2 Consolidation of Application IC PO 11-Nov-13 14 25-Nov-13 25-Nov-13 14 9-Dec-13 7 16-Dec-13 16-Dec-13 7 23-Dec-13 23-Dec-13 7 30-Dec-13 2 1-Jan-14 61 2 3-Mar-14 NA NA R analysis 2-Nov-15 14 16-Nov-15 3 19-Nov-15 14 3-Dec-15 7 10-Dec-15 2 12-Dec-15 7 19-Dec-15 2 21-Dec-15 7 28-Dec-15 2 30-Dec-15 366 12 30-Dec-16 NA NA A P IC029 IC029 3 3.3 Evaluation of Student IC PO 1-Dec-14 107 18-Mar-15 N/A 1 12-May-15 180 8-Nov-15 7 N/A 14 29-Nov-15 7 N/A 7 13-Dec-15 3 16-Dec-15 746 25 31-Dec-17 NA NA Launched R Achievement Expert (Learning 1-Dec-14 115 26-Mar-15 1 27-Mar-15 46 12-May-15 NA NA Assessment) A P S13-S20 IC010 3 3.3 Staff (Long term) IC PR 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA R NA NA A P S1 IC001 3 3.3 ESDS Director SSS PR 4-Nov-10 14 18-Nov-10 14 2-Dec-10 2-Dec-10 2-Dec-10 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Completed R 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 NA NA Nada Mneimneh (Resigned) A 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 31-Dec-14 13,800.00 P S2 IC002 3 3.3 School Improvement and SSS PR 11-Nov-10 14 25-Nov-10 25-Nov-10 14 9-Dec-10 7 16-Dec-10 16-Dec-10 7 23-Dec-10 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Ongoing R Leadership Expert 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 NA NA Elham Komaty A 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 31-Dec-16 10,000.00 P S3 IC003 3 3.3 Financial Officer SSS PR 11-Nov-10 14 25-Nov-10 25-Nov-10 14 9-Dec-10 7 16-Dec-10 16-Dec-10 7 23-Dec-10 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Ongoing R 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 NA NA Bilal Nasser A 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 31-Dec-16 10,400.00 P S4 IC004 3 3.3 Monitoring & Evaluation Specialist SSS PR 11-Nov-10 14 25-Nov-10 25-Nov-10 14 9-Dec-10 7 16-Dec-10 16-Dec-10 7 23-Dec-10 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Completed R 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 NA NA Dana Shdeed (Resigned) A 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 4-Apr-14 8,000.00 P S5 IC005 3 3.3 Education Economist SSS PR 11-Nov-10 14 25-Nov-10 25-Nov-10 14 9-Dec-10 7 16-Dec-10 16-Dec-10 7 23-Dec-10 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Completed R 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 NA NA Sara Zeineddine (Resigned) A 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 31/12/2013 2,000.00 Lebanon000Seco000procurement0plan0.xlsx Page 7 of 9 3/30/2016 Lebanon Second Education Development Program EDP II Execution in days Proc. System Ref. Selection Method Plan vs. Actual Unit Execution in Sub-Comp Costab ref (Mth/ Yr/ Short Contract months Interval Interval Interval Interval Interval Interval Interval Interval Interval Contract Completion Completion Contract Comp SN. # Location/ Description of Study[Sty], TOR Start Adv. EOI Listing negotiation/ Contract Bank Rev. TOR end Date NOL Date NOL Date NOL Date signature Date Date (last amount US$ Consultant Name Comments # Assignment Lumpsum [LS], Date end Date Report Award- Start Date Date (original) revision) (original) Workshop Date Draft [Wsh]) A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AG AH P S6 IC006 3 3.3 Architect Urban Planner SSS PR 11-Nov-10 14 25-Nov-10 25-Nov-10 14 9-Dec-10 7 16-Dec-10 16-Dec-10 7 23-Dec-10 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Ongoing R 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 NA NA Maya Samaha A 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 31-Dec-16 6,800.00 P S7 IC007 3 3.3 Operations Specialist SSS PR 11-Nov-10 14 25-Nov-10 25-Nov-10 14 9-Dec-10 7 16-Dec-10 16-Dec-10 7 23-Dec-10 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Completed R 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 NA NA Leen Ataya (Resigned) A 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 15-Sep-15 2,600.00 P S8 IC008 3 3.3 Staff (Long term retroactive basis) SSS PR 11-Nov-10 14 25-Nov-10 25-Nov-10 14 9-Dec-10 7 16-Dec-10 16-Dec-10 7 23-Dec-10 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Completed Joelle H, Nadine R 18-Sep-12 14 2-Oct-12 14 16-Oct-12 16-Oct-12 16-Oct-12 16-Oct-12 7 23-Oct-12 23-Oct-12 7 30-Oct-12 2 1-Nov-12 425 14 31-Dec-13 NA NA T A 18-Nov-10 14 2-Dec-10 14 16-Dec-10 16-Dec-10 16-Dec-10 16-Dec-10 7 23-Dec-10 23-Dec-10 7 30-Dec-10 2 1-Jan-11 730 24 31-Dec-12 31/12/2012 207,150.00 P S9 IC009 3 3.3 Procurement Consultant SSS PR 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Completed R NA NA Fady Barakat A 6-Apr-13 14 20-Apr-13 14 4-May-13 14 18-May-13 7 25-May-13 14 8-Jun-13 7 15-Jun-13 7 22-Jun-13 7 29-Jun-13 2 1-Jul-13 91.5 3 1-Jul-13 11/31/2013 13,500.00 P S10 IC010 3 3.3 Education Expert (TPD) IC PO 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Signed and Being R 1-Dec-14 107 18-Mar-15 N/A 1 12-May-15 160 19-Oct-15 7 26-Oct-15 14 9-Nov-15 7 16-Nov-15 7 23-Nov-15 3 26-Nov-15 766 25.5 31-Dec-17 NA NA Basma Frangieh Implemented A 1-Dec-14 115 26-Mar-15 1 27-Mar-15 46 12-May-15 213 11-Dec-15 N/A N/A N/A 16-Jan-16 1-Jan-16 365 12 31-Dec-16 48,000.00 P S11 IC011 3 3.3 Procurement Officer -1- IC PR 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Completed R 5-Jul-13 2 7-Jul-13 3 10-Jul-13 1 11-Jul-13 80 29-Sep-13 37 5-Nov-13 5-Nov-13 5-Nov-13 5-Nov-13 5-Nov-13 1565.26 51.32 31-Dec-17 NA NA Ghada Zeaiter (Resigned in 2013) A 5-Jul-13 2 7-Jul-13 3 10-Jul-13 1 11-Jul-13 80 29-Sep-13 37 5-Nov-13 5-Nov-13 5-Nov-13 5-Nov-13 5-Nov-13 56 1.867 31-Dec-13 31-Dec-13 69,333.00 P S12 IC012 3 3.3 Education Curriculum Expert IC N/A 18-Aug-13 14 1-Sep-13 14 15-Sep-13 14 29-Sep-13 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA completed and paid (Lebanese Contribution) Antoinette R 1-Jul-13 2 3-Jul-13 3 6-Jul-13 1 7-Jul-13 76 21-Sep-13 19 10-Oct-13 14 24-Oct-13 7 31-Oct-13 14 14-Nov-13 3 17-Nov-13 1505 50.42 31-Dec-17 NA NA Sebaaly A 1-Jul-13 2 3-Jul-13 3 6-Jul-13 1 7-Jul-13 76 21-Sep-13 19 10-Oct-13 15-Dec-13 15-Dec-13 15-Dec-13 17 1-Jan-14 364.00 12.00 31-Dec-14 31-Dec-15 33,600.00 P S13 IC013 3 3.3 Procurement Assisstant (Senior) IC PR 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Frozen R 14-Sep-13 14 28-Sep-13 7 5-Oct-13 1 12-Dec-13 21 2-Jan-14 7 9-Jan-14 14 23-Jan-14 7 30-Jan-14 14 13-Feb-14 3 16-Feb-14 1414 49 31-Dec-17 NA NA A 14-Sep-13 65 18-Nov-13 3 21-Nov-13 21 12-Dec-13 P S14 IC014 3 3.3 Procurement Assisstant (Junior) IC PO 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Launched - Frozen R 1-Dec-14 107 18-Mar-15 N/A 1 12-May-15 180 8-Nov-15 7 N/A 14 29-Nov-15 7 N/A 7 13-Dec-15 3 16-Dec-15 746 25 31-Dec-17 NA NA A 1-Dec-14 115 26-Mar-15 1 27-Mar-15 46 12-May-15 P S15 IC015 3 3.3 Financial Assistant IC PO 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Signed and Being R 1-Dec-14 107 18-Mar-15 N/A 1 12-May-15 188 16-Nov-15 7 N/A 14 7-Dec-15 7 N/A 7 21-Dec-15 3 24-Dec-15 746 25 8-Jan-18 NA NA Farah Fawaz Implemented A 1-Dec-14 115 26-Mar-15 1 27-Mar-15 46 12-May-15 188 16-Nov-15 N/A N/A N/A 4-Jan-16 1-Jan-16 365 12 31-Dec-16 33,000.00 P S16 IC016 3 3.3 Expert (Lebanese Contribution) IC n/a 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Completed - LC R 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 18 48 21-Dec-13 NA NA Karma El Hassan A 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 18 21-Dec-13 21-Dec-13 6,000.00 P S17 IC017 3 3.3 Procurement Officer -2- IC PR 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Ongoing R 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 3-Dec-13 18 48 21-Dec-13 NA NA Riwa El Khoury A 5-Jul-13 2 7-Jul-13 3 10-Jul-13 1 11-Jul-13 80 29-Sep-13 37 14-Jan-14 14-Jan-14 14-Jan-14 4-Feb-14 28-Jan-14 31-Dec-14 31-Dec-14 31-Dec-16 61,233.00 P S18 IC018 3 3.3 Monitoring & Evaluation Specialist IC PO 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Launched R 1-Dec-14 107 18-Mar-15 N/A 1 12-May-15 160 19-Oct-15 7 N/A 14 9-Nov-15 7 N/A 7 23-Nov-15 3 26-Nov-15 766 25.5 31-Dec-17 NA NA A 1-Dec-14 115 26-Mar-15 1 N/A 46 12-May-15 P S19 IC019 3 3.3 Education Economist IC PO 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Launched R 1-Dec-14 115 26-Mar-15 N/A 1 12-May-15 180 8-Nov-15 7 N/A 14 29-Nov-15 7 N/A 7 13-Dec-15 3 16-Dec-15 746 25 31-Dec-17 NA NA A 1-Dec-14 115 26-Mar-15 1 N/A 46 12-May-15 P S30 IC030 3 3.3 Executive Assistant IC PO 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Launched R 1-Dec-14 115 26-Mar-15 N/A 1 12-May-15 180 8-Nov-15 7 N/A 14 29-Nov-15 7 N/A 7 13-Dec-15 3 16-Dec-15 746 25 31-Dec-17 NA NA A 1-Dec-14 115 26-Mar-15 1 N/A 46 12-May-15 P S31 IC031 3 3.3 Education Specialist IC PO 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Signed and Being R 1-Dec-14 115 26-Mar-15 N/A 1 12-May-15 180 8-Nov-15 7 N/A 14 29-Nov-15 7 N/A 7 13-Dec-15 3 16-Dec-15 746 25 31-Dec-17 NA NA Maya Fawaz Implemented A 1-Dec-14 115 26-Mar-15 1 N/A 46 12-May-15 185 13-Nov-15 N/A N/A N/A 4-Jan-16 1-Jan-16 365 12 31-Dec-16 33,600.00 P S32 IC032 3 3.3 ESDS Director IC PO 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Launched R 1-Dec-14 115 26-Mar-15 1 27-Mar-15 46 12-May-15 160 19-Oct-15 7 26-Oct-15 14 9-Nov-15 7 16-Nov-15 7 23-Nov-15 3 26-Nov-15 766 25.5 31-Dec-17 NA NA A 1-Dec-14 115 26-Mar-15 1 27-Mar-15 46 12-May-15 P S34 IC034 3 3.3 Project Assistant SSS PR 30-Sep-10 14 14-Oct-10 14 28-Oct-10 14 11-Nov-10 7 18-Nov-10 14 2-Dec-10 7 9-Dec-10 14 23-Dec-10 7 30-Dec-10 2 1-Jan-11 2555.9 83.8 31-Dec-17 NA NA Signed and Being NEW R 15-Dec-15 20 4-Jan-16 N/A N/A N/A 7 N/A 19-Jan-16 7 26-Jan-16 7 2-Feb-16 3 1-Jan-16 365 12 31-Dec-16 NA 21,600.00 Nihal Nabaa Implemented A 15-Dec-15 20 4-Jan-16 N/A N/A N/A 7 N/A 19-Jan-16 7 Lebanon000Seco000procurement0plan0.xlsx Page 8 of 9 3/30/2016 Lebanon Second Education Development Program PLANNING FOR TRAINING as of April 30, 2015 Selection Method Unit Comple Plan vs. Actual Proc. System Execution in Execution in (Mth/ Yr/ Sub-Comp Costab ref tion months Interval Interval Interval Interval Location/ Study[Sty], Completion Comp Ref. # SN. # days TOR end Training Training Date Particip Comme Description of Lumpsum Bank Rev. TOR Start Date NOL Date Date Date preparation Start Date (last ants nts Assignment [LS], (original) revision Workshop ) [Wsh]) P TR004 2 2.1 School Grants NA PR 20-Sep-11 14 4-Oct-11 14 18-Oct-11 14 1-Nov-11 2 3-Nov-11 1464 48 6-Nov-15 NA R 20-May-16 14 3-Jun-16 14 17-Jun-16 14 1-Jul-16 2 3-Jul-16 366 12 4-Jul-17 NA A The mechanism of the above amount was not defined yet